Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0461129B2 - - Google Patents
[go: Go Back, main page]

JPH0461129B2 - - Google Patents

Info

Publication number
JPH0461129B2
JPH0461129B2 JP12523485A JP12523485A JPH0461129B2 JP H0461129 B2 JPH0461129 B2 JP H0461129B2 JP 12523485 A JP12523485 A JP 12523485A JP 12523485 A JP12523485 A JP 12523485A JP H0461129 B2 JPH0461129 B2 JP H0461129B2
Authority
JP
Japan
Prior art keywords
core material
auger rod
guide
unit
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP12523485A
Other languages
Japanese (ja)
Other versions
JPS61286414A (en
Inventor
Soichi Kitani
Toshiaki Tsucha
Shinichi Kakegawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP12523485A priority Critical patent/JPS61286414A/en
Publication of JPS61286414A publication Critical patent/JPS61286414A/en
Publication of JPH0461129B2 publication Critical patent/JPH0461129B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、ソイルセメント柱列を地下に構築
して山止め壁とする場合における多軸ソイルセメ
ント柱列構築工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application The present invention relates to a method for constructing a multi-axis soil cement column array in the case where the soil cement column array is constructed underground to serve as a retaining wall.

従来の技術 ソイルセメント柱列の山止め壁を構築するのに
能率を上げるため近時多軸のソイルオーガーマシ
ンが使用されてきた。通常使用される4軸ソイル
オーガーマシン1(第10図参照)はオーガーロ
ツド2の下部の撹拌翼3付近に4本のオーガーロ
ツド2を等間隔に軸支する連結軸受4を設けて同
一直線上で穿孔するようになつており、穿孔が終
了するとセメントミルクを注入しオーガーロツド
2の撹拌翼3で撹拌しながら引き抜いた後H形鋼
のような芯材を硬化しないソイルセメント中に挿
入する工程を4軸分を1ユニツトとして1ユニツ
ト飛びに繰返す先行ユニツト工程と、その後にそ
れらの先行ユニツト間を穿孔しソイルセメント中
に芯材を挿入する後行ユニツト工程を行つてい
る。この場合、芯材の挿入は地上においては芯材
挿入用ガイドを孔列に沿つて固定し芯材を孔の中
心位置になるように1本ずつ挿入しているが、先
端部にはガイド等はなくフリーの状態のまま重力
により垂下させて挿入していた。
BACKGROUND OF THE INVENTION Multi-axis soil auger machines have recently been used to increase efficiency in constructing soil-cement column retaining walls. A commonly used 4-shaft soil auger machine 1 (see Fig. 10) is equipped with a connecting bearing 4 that supports four auger rods 2 at equal intervals near the stirring blade 3 at the bottom of the auger rod 2, and performs drilling in the same straight line. After drilling is completed, cement milk is injected, the auger rod 2 is stirred by the stirring blades 3, and the core material is inserted into soil cement, which does not harden. There is a preceding unit process in which each unit is repeated one unit at a time, followed by a subsequent unit process in which holes are drilled between the preceding units and a core material is inserted into the soil cement. In this case, the core material is inserted on the ground by fixing a core material insertion guide along the hole row and inserting the core material one by one so that it is in the center of the hole, but there is a guide etc. at the tip. Instead, it was inserted in a free state, hanging down due to gravity.

発明が解決しようとする問題点 上記従来のソイルセメント柱列の構築工法にお
いては各ユニツト間のラツプ不足をなくすため第
11図に示すように先行ユニツトの端部の孔5
と後行ユニツトの端部の孔6とを完全に重ねて
穿孔する完全ラツプ工法も行われているが、この
場合先行ユニツトのソイルセメントが硬化し強
度を発現し特にソイルセメント柱の周辺の土質の
強度が低いようなときは、後行ユニツトのオー
ガーロツド2が固い柱部分からそれて軟かい周辺
土の方へ逃げるので穿孔の掘削精度が著しく低下
する恐れがありラツプ不足を招く原因となる。ま
た完全ラツプを行わないときでも先行ユニツト
間に後行ユニツトが穿孔を行う際、固い岩石等
に当るとオーガーロツド2が偏つて掘削する場合
があり、そうでない場合でもオーガーロツド2の
先端は連結軸受4によつてオーガーロツド2は等
間隔であるが先行ユニツトと後行ユニツトと
の間を正確にラツプさせて穿孔するためのガイド
がないため偏る場合が生じる。これらの場合に
は、いずれもラツプ部分の肉厚が薄くなり止水性
が損われる問題点があつた。
Problems to be Solved by the Invention In the above-mentioned conventional method of constructing soil cement columns, in order to eliminate the lack of overlap between each unit, holes 5 at the end of the preceding unit are
A complete lap method is also used in which the hole 6 at the end of the succeeding unit is completely overlapped with the hole 6 at the end of the succeeding unit, but in this case, the soil cement of the leading unit hardens and develops strength, especially the soil quality around the soil cement column. If the strength of the hole is low, the auger rod 2 of the trailing unit will deviate from the hard column part and escape toward the soft surrounding soil, which may significantly reduce the accuracy of drilling and cause insufficient lap. Furthermore, even when a complete lap is not performed, when the trailing unit drills a hole between the leading unit, the auger rod 2 may excavate unbalancedly if it hits hard rock, etc., and even if this is not the case, the tip of the auger rod 2 is attached to the connecting bearing 4. Although the auger rods 2 are spaced at regular intervals, they may be offset because there is no guide to accurately overlap and drill holes between the leading and trailing units. In all of these cases, there was a problem in that the wall thickness of the lap portion became thinner and water-stopping properties were impaired.

さらに、上記以外にラツプ寸法が不足する重要
な原因は、芯材の建入れに当つて地上面において
は芯材挿入用ガイドによつて芯材を案内している
が、芯材の先端部においては穿孔深さが深い程、
重力による垂下であるため先端の揺れが大きくな
り芯材の建入精度に不揃いが生じることによるも
のである。このような建入精度が保たれない場合
はソイルセメント柱列が完成後、切梁架設工事の
ためソイルセメント柱を芯材の面まで削り取るの
で、第12図に示すように芯材7が孔8の中心か
ら偏り、孔8のラツプ部分9の肉厚10が薄い肉
厚11に減少し止水柱が損われる。また、このよ
うに芯材7が孔8の中心から偏ると地下外壁のコ
ンクリート12を打設する際、正規の厚さより外
側までコンクリート13が食い込み余分にコンク
リートが必要となり、さらに切梁架設工事におい
て芯材であるH形鋼のフランジ面と腹起しとの間
に大小の間〓を生じ、間〓の大きいところには詰
めモルタルを大量に必要とし切梁架設工事を円滑
に行うことが困難であり、その上芯材を多数本ま
とめて挿入すると一度に多数本の芯材を制御でき
ず建入精度を確保することが困難であるため1本
ずつ挿入しているので能率的でない等の問題点が
あつた。
In addition to the above, another important reason for the lack of lap dimensions is that during the erection of the core material, the core material is guided by a core material insertion guide at the ground level, but at the tip of the core material The deeper the drilling depth, the
This is due to the drooping due to gravity, which increases the shaking of the tip and causes irregularities in the installation accuracy of the core material. If such construction accuracy cannot be maintained, after the soil cement column row is completed, the soil cement column will be scraped down to the surface of the core material for strut construction work, so the core material 7 will have holes as shown in Figure 12. 8, the wall thickness 10 of the lap portion 9 of the hole 8 is reduced to a thin wall thickness 11, and the water stop column is damaged. In addition, if the core material 7 is deviated from the center of the hole 8 in this way, when pouring the concrete 12 for the underground outer wall, the concrete 13 will dig in to the outside of the normal thickness, resulting in the need for extra concrete. There is a difference in size between the flange surface of the H-beam core material and the riser, and large amounts of filling mortar are required in areas with large gaps, making it difficult to perform strut erection work smoothly. Moreover, if a large number of core materials are inserted at once, it is difficult to control many core materials at once and ensure construction accuracy, so it is inefficient because they are inserted one by one. The dot was hot.

問題点を解決するための手段 上記の問題点を解決するため、この発明は(1)多
軸オーガーロツドで先行ユニツト柱列の柱孔を穿
孔し、各柱孔にセメントミルクを注入して撹拌し
た後オーガーロツドを引抜き、つぎに後行ユニツ
トの多軸オーガーロツドを案内するガイド付き芯
材の下端部に各柱孔内面をガイドとする案内片を
取付けて各芯材を挿入する先行ユニツト工程と、
前記ガイドによつて案内された多軸オーガーロツ
ドで後行ユニツト柱列を穿孔し、各柱孔にセメン
トミルクを注入して撹拌した後オーガーロツドを
引抜き、つぎに下端部に各柱孔内面をガイドとす
る案内片を取付けた芯材を挿入する後行ユニツト
工程とからなる多軸ソイルセメント柱列構築工
法、(2)多軸オーガーロツドで先行ユニツト柱列の
柱孔を穿孔し、各柱孔にセメントミルクを注入し
て撹拌した後オーガーロツドを引抜き、つぎに後
行ユニツトの多軸オーガーロツドおよび芯材を案
内するガイド付き芯材の下端部に各柱孔内面をガ
イドとする案内片を取付けて各芯材を挿入する先
行ユニツト工程と、前記ガイドによつて案内され
た多軸オーガーロツドで後行ユニツト柱列を穿孔
し、各柱孔にセメントミルクを注入して撹拌した
後オーガーロツドを引抜き、つぎに前記ガイドに
よつて一連の芯材の下部を連結した連結板を案内
して一連の芯材を同時に挿入する後行ユニツト工
程とからなる多軸ソイルセメント柱列構築工法の
手段を講じるものである。
Means for Solving the Problems In order to solve the above problems, the present invention consists of (1) drilling the post holes in the column row of the preceding unit with a multi-axis auger rod, injecting cement milk into each post hole and stirring it; A preceding unit step in which the rear auger rod is pulled out, and then a guide piece is attached to the lower end of the core member with a guide that guides the multi-axis auger rod of the trailing unit, and each core member is inserted by attaching a guide piece that uses the inner surface of each post hole as a guide;
A multi-axis auger rod guided by the guide is used to perforate the columns of the trailing unit, and after injecting and stirring cement milk into each column hole, the auger rod is pulled out, and then the inner surface of each column hole is inserted into the lower end of the column as a guide. (2) A multi-axis auger rod is used to drill the column holes of the preceding unit column, and cement is inserted into each column hole. After injecting and stirring the milk, pull out the auger rod, and then attach a guide piece using the inner surface of each post hole as a guide to the lower end of the guided core material that guides the multi-shaft auger rod and core material of the trailing unit. The preceding unit step involves inserting the material, and the subsequent unit column rows are perforated with a multi-axis auger rod guided by the guide. After pouring cement milk into each column hole and stirring, the auger rod is pulled out. This is a multi-axis soil cement column construction method consisting of a trailing unit step in which a series of core materials are simultaneously inserted by guiding a connecting plate connecting the lower parts of a series of core materials by a guide.

作 用 この発明は、多軸オーガーロツドで先行ユニツ
ト柱列の柱孔を穿孔しセメントミルクを注入し撹
拌してオーガーロツドを引抜いてから芯材を挿入
する先行ユニツト工程を行うが、先行ユニツトが
精度よく穿孔されれば芯材は案内片により柱孔の
中心部に精度よく挿入される。そして正確な位置
に挿入された芯材に取付けたガイドにより後行ユ
ニツトの多軸オーガーロツドを案内させて精度の
よい穿孔を行いセメントミルクを注入し撹拌して
オーガーロツドを引抜いた後は芯材は案内片で柱
孔の中心部に精度よく挿入するか、または芯材を
連結した連結片を前記ガイドを案内として精度よ
く挿入することができる。
Function This invention performs the preceding unit process of drilling the column holes in the column row of the preceding unit with a multi-axis auger rod, injecting cement milk, stirring, pulling out the auger rod, and inserting the core material. Once the hole is drilled, the core material is accurately inserted into the center of the post hole by the guide piece. Then, the multi-shaft auger rod of the trailing unit is guided by the guide attached to the core material inserted in the correct position to perform precise drilling. After cement milk is injected and stirred and the auger rod is pulled out, the core material is guided. A single piece can be inserted into the center of the post hole with high precision, or a connecting piece connecting the core material can be inserted with high precision using the guide as a guide.

実施例 まず、第1の発明の第1実施例について図面を
参照して説明する。
Embodiment First, a first embodiment of the first invention will be described with reference to the drawings.

第10図に示す4軸ソイルオーガマシン1のオ
ーガーロツド2で第1図に示す先行ユニツトの
柱列を穿孔し、各柱孔20にセメントミルクを注
入し、オーガーロツド2の下方の撹拌翼3で撹拌
した後オーガーロツド2を引抜き、つぎに第1図
〜第3図に示すように先行ユニツトの最外側の
柱孔20に芯材21を挿入する。この時芯材21
であるH形鋼のウエブ22に、後行ユニツトの
オーガーロツド2の連結軸受4の外端に設けた軸
23を案内するアングル形のガイド24を取付
け、かつ芯材21の下端部に第8図に示す案内片
25を取付けて各芯材21を挿入し先行ユニツト
工程を終了する。この場合前記案内片25は第8
図および第9図に示すように、柱孔20の内周面
と一致する4分円弧面26を有し、その両端縁2
7を弦方向に折り曲げて脚部28とし、その端面
29に芯材21を挾持する凹溝30を設けた合成
樹脂製薄肉偏平体31で構成されている。
The auger rod 2 of the four-shaft soil auger machine 1 shown in FIG. 10 perforates the columns of the preceding unit shown in FIG. After that, the auger rod 2 is pulled out, and the core material 21 is then inserted into the outermost post hole 20 of the preceding unit as shown in FIGS. 1 to 3. At this time, the core material 21
An angle-shaped guide 24 for guiding the shaft 23 provided at the outer end of the connecting bearing 4 of the auger rod 2 of the trailing unit is attached to the web 22 of H-shaped steel, and attached to the lower end of the core member 21 as shown in FIG. The guide piece 25 shown in FIG. 1 is attached, each core material 21 is inserted, and the preceding unit process is completed. In this case, the guide piece 25 is the eighth
As shown in FIG. 9 and FIG.
7 is bent in the chord direction to form a leg portion 28, and the thin flat body 31 made of synthetic resin is provided with a concave groove 30 for holding the core material 21 in the end surface 29 of the leg portion 28.

つぎに、前記ガイド24によつて連結軸受4の
軸23を案内された多軸オーガーロツド2で後行
ユニツトの柱孔20を穿孔し、各柱孔20にセ
メントミルクを注入しオーガーロツド2の撹拌翼
3で撹拌した後オーガーロツド2を引抜き、つぎ
に下端部に第8図および第9図に示す案内片25
を取付けた芯材21を挿入して後行ユニツト工程
を終了し多軸ソイルセメント柱列の構築を完了す
る。
Next, the post holes 20 of the trailing unit are bored with the multi-shaft auger rod 2 guided by the shaft 23 of the connecting bearing 4 by the guide 24, cement milk is injected into each post hole 20, and the stirring blade of the auger rod 2 is drilled. After stirring in step 3, pull out the auger rod 2, and then attach the guide piece 25 shown in FIGS. 8 and 9 to the lower end.
The core material 21 with the attached core material 21 is inserted to complete the subsequent unit process and complete the construction of the multi-axial soil cement column row.

以下に、第2の発明の第2実施例について図面
を参照して説明する。
A second embodiment of the second invention will be described below with reference to the drawings.

先行ユニツト工程までは第1実施例と同一であ
り、後行ユニツト工程はつぎのとおりである。
The preceding unit process is the same as the first embodiment, and the subsequent unit process is as follows.

先行ユニツトの芯材21に取付けたガイド2
4によつて連結軸受4の軸23を案内された多軸
オーガーロツド2で後行ユニツトの柱列を穿孔
し、各柱孔20にセメントミルク2を注入しオー
ガーロツド2の撹拌翼3で撹拌した後オーガーロ
ツド2を引抜き、つぎに第4図〜第7図に示すよ
うにH形鋼からなる芯材21の下端32に、芯材
21のウエブ33を嵌合する切込み34をくし形
に切欠いた連結板35を溶着し、その上端36は
横長のH形鋼37との間を芯材21のウエブ33
に柱孔20と等間隔に設けたワイヤー38で吊
り、H形鋼37をワイヤー40で吊り下げ、芯材
21はその下端32部を連結板35の端部39で
前記ガイド24に案内されながら柱孔20中に挿
入され、後行ユニツト工程を終了し、このように
して多軸ソイルセメント柱列の構築を完了する。
Guide 2 attached to the core material 21 of the preceding unit
After drilling the column rows of the trailing unit with the multi-shaft auger rod 2 guided by the shaft 23 of the connecting bearing 4 by 4, cement milk 2 is injected into each column hole 20 and stirred with the stirring blade 3 of the auger rod 2. The auger rod 2 is pulled out, and as shown in FIGS. 4 to 7, the lower end 32 of the core material 21 made of H-beam steel is connected with a notch 34 into which the web 33 of the core material 21 is fitted. A plate 35 is welded, and its upper end 36 is connected to the web 33 of the core material 21 between it and a horizontally long H-beam 37.
The H-shaped steel 37 is suspended by wires 38 provided at equal intervals to the post holes 20, and the core material 21 is guided by the guide 24 with its lower end 32 at the end 39 of the connecting plate 35. It is inserted into the post hole 20 to complete the trailing unit process, thus completing the construction of the multi-axial soil cement post array.

発明の効果 第1の発明は、先行ユニツトの穿孔を正確に行
えば後行ユニツトのオーガーロツドが先行ユニツ
トの芯材のガイドに案内され掘削精度が確保され
ラツプ不足を招くことがなく、したがつて止水性
が損われることがない。完全ラツプ工法でも後行
ユニツトが正確に行われるので止水性を確保でき
る。
Effects of the Invention The first invention is that if the drilling of the leading unit is performed accurately, the auger rod of the trailing unit is guided by the guide of the core material of the leading unit, ensuring drilling accuracy and preventing insufficient lap. Water-stopping properties are not impaired. Even with the complete wrap construction method, the trailing unit is placed accurately, ensuring watertightness.

また、芯材の挿入はその先端部に取付けた案内
片により柱孔の中心から偏ることがないため地下
外壁のコンクリートを打設する際、正規の壁厚よ
り食い込むことがなく、したがつて余分なコンク
リートを必要とせず、また切梁架設工事において
芯材と腹起しの間に大きな間隙を生じないので多
量の詰めモルタルを必要とするようなことがなく
工事を円滑に行うことができる。
In addition, the guide piece attached to the tip of the core material prevents it from being deviated from the center of the post hole, so when pouring concrete for the underground exterior wall, it does not dig deeper than the normal wall thickness, and therefore no excess material is inserted. This method does not require concrete, and since no large gap is created between the core material and the rib during strut erection work, the work can be carried out smoothly without the need for a large amount of mortar.

第2の発明は、上記のほかに多数本の芯材をま
とめて一度に挿入しても芯材の連結片をガイドで
案内するので各芯材とも一様に正確に挿入され建
入精度を確保できるため芯材のユニツト化が可能
で工期の短縮に寄与することができる。
In addition to the above, the second invention is that even if a large number of core materials are inserted at once, the connecting pieces of the core materials are guided by a guide, so each core material is inserted uniformly and accurately, improving construction accuracy. Since it can be secured, the core material can be made into a unit, which can contribute to shortening the construction period.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第9図は、この発明の第1実施例およ
び第2実施例を示すもので、、第1図は穿孔時の
横断平面図、第2図はオーガーロツドの下方を示
す1部の正面図、第3図は連結軸受の1部を示す
斜視図、第4図は芯材挿入時の横断平面図、第5
図は芯材の下部を示す1部の正面図、第6図は連
結板を示す正面図、第7図は芯材の上部を示す1
部の正面図、第8図は芯材に案内片を取付けた状
態を示す拡大横断面図、第9図は同じく側面図、
第10図はソイルオーガーマシンの正面図、第1
1図および第12図は従来例を示すもので第11
図は完全ラツプ工法を示す横断平面図、第12図
は芯材挿入不良時を示す横断平面図である。 2…オーガーロツド、20…柱孔、21…芯
材、24…ガイド、25…案内片、35…連結
板、…先行ユニツト、…後行ユニツト。
1 to 9 show a first embodiment and a second embodiment of the present invention, FIG. 1 is a cross-sectional plan view during drilling, and FIG. 2 is a partial view showing the lower part of the auger rod. Figure 3 is a front view, Figure 3 is a perspective view showing a part of the coupling bearing, Figure 4 is a cross-sectional plan view when the core material is inserted, Figure 5
The figure is a front view of part 1 showing the lower part of the core material, Figure 6 is a front view showing the connecting plate, and Figure 7 is a front view of part 1 showing the upper part of the core material.
8 is an enlarged cross-sectional view showing a state in which the guide piece is attached to the core material, and FIG. 9 is a side view of the same.
Figure 10 is a front view of the soil auger machine,
Figures 1 and 12 show conventional examples.
The figure is a cross-sectional plan view showing the complete wrap construction method, and FIG. 12 is a cross-sectional plan view showing a case where the core material is inserted incorrectly. 2... Auger rod, 20... Post hole, 21... Core material, 24... Guide, 25... Guide piece, 35... Connecting plate,... Leading unit,... Trailing unit.

Claims (1)

【特許請求の範囲】 1 多軸オーガーロツド2で先行ユニツト柱列
の柱孔20を穿孔し、各柱孔20にセメントミル
クを注入して撹拌した後オーガーロツド2を引抜
き、つぎに後行ユニツトの多軸オーガーロツド
2を案内するガイド24付き芯材21の下端部に
各柱孔20内面をガイドとする案内片25を取付
けて各芯材21を挿入する先行ユニツト工程と、
前記ガイド24によつて案内された多軸オーガー
ロツド2で後行ユニツト柱列を穿孔し、各柱孔
20にセメントミルクを注入して撹拌した後オー
ガーロツド2を引抜き、つぎに下端部に各柱孔2
0内面をガイドとする案内片25を取付けた芯材
21を挿入する後行ユニツト工程とからなる多軸
ソイルセメント柱列構築工法。 2 多軸オーガーロツド2で先行ユニツト柱列
の柱孔20を穿孔し、各柱孔20にセメントミル
クを注入して撹拌した後オーガーロツド2を引抜
き、つぎに後行ユニツトの多軸オーガーロツド
2および芯材21を案内するガイド24付き芯材
21の下端部に各柱孔20内面をガイドとする案
内片25を取付けて各芯材21を挿入する先行ユ
ニツト工程と、前記ガイド24によつて案内され
た多軸オーガーロツド2で後行ユニツト柱列を
穿孔し、各柱孔20にセメントミルクを注入して
撹拌した後オーガーロツド2を引抜き、つぎに前
記ガイド24によつて一連の芯材21の下部を連
結した連結板35を案内して一連の芯材21を同
時に挿入する後行ユニツト工程とからなる多軸ソ
イルセメント柱列構築工法。
[Scope of Claims] 1 The multi-axis auger rod 2 is used to drill the post holes 20 of the leading unit column row, and after pouring cement milk into each post hole 20 and stirring, the auger rod 2 is pulled out, and then the multi-axis auger rod 2 is drilled. A preceding unit step in which a guide piece 25 that uses the inner surface of each post hole 20 as a guide is attached to the lower end of the core material 21 with a guide 24 that guides the shaft auger rod 2, and each core material 21 is inserted;
The multi-axis auger rod 2 guided by the guide 24 perforates the columns of the trailing unit, and after injecting cement milk into each column hole 20 and stirring, the auger rod 2 is pulled out, and then each column hole is drilled in the lower end. 2
A method for constructing a row of multi-axis soil cement columns, which includes a subsequent unit step of inserting a core material 21 with a guide piece 25 attached to the inner surface as a guide. 2 The multi-shaft auger rod 2 is used to drill the post holes 20 in the column row of the leading unit, and after pouring cement milk into each post hole 20 and stirring, the auger rod 2 is pulled out, and then the multi-shaft auger rod 2 and the core material of the following unit are A preceding unit step in which a guide piece 25 that guides the inner surface of each post hole 20 is attached to the lower end of the core material 21 with a guide 24 for guiding the core material 21 and each core material 21 is inserted; A multi-axis auger rod 2 is used to drill holes in the trailing unit column rows, and after pouring cement milk into each column hole 20 and stirring, the auger rod 2 is pulled out, and then the guide 24 connects the lower part of the series of core materials 21. A construction method for constructing a row of multi-axial soil cement columns, which comprises a subsequent unit step in which a series of core materials 21 are simultaneously inserted by guiding a connected connecting plate 35.
JP12523485A 1985-06-11 1985-06-11 Constructing method for multispindle soil cement column line Granted JPS61286414A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12523485A JPS61286414A (en) 1985-06-11 1985-06-11 Constructing method for multispindle soil cement column line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12523485A JPS61286414A (en) 1985-06-11 1985-06-11 Constructing method for multispindle soil cement column line

Publications (2)

Publication Number Publication Date
JPS61286414A JPS61286414A (en) 1986-12-17
JPH0461129B2 true JPH0461129B2 (en) 1992-09-30

Family

ID=14905125

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12523485A Granted JPS61286414A (en) 1985-06-11 1985-06-11 Constructing method for multispindle soil cement column line

Country Status (1)

Country Link
JP (1) JPS61286414A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05311641A (en) * 1992-01-16 1993-11-22 Fusao Sakano Construction method for earth retaining wall on bank, small mountain, cliff and link type or bond type earth retaining wall
JPH09119131A (en) * 1996-08-02 1997-05-06 Kengi Kaihatsu Kk Construction method of column row type underground continuous wall and guide plate structure of multishaft auger machine used therefor

Also Published As

Publication number Publication date
JPS61286414A (en) 1986-12-17

Similar Documents

Publication Publication Date Title
JPH0461129B2 (en)
JP2002275922A (en) Reverse construction method
JPS59228529A (en) Formation of sheathing continuous wall and rotary excavator and sheathing member therefor
JPS59126821A (en) Erection work of foundation pile
JP2832508B2 (en) Retaining wall structure and retaining method
JPH07109096B2 (en) Impermeable method for underground wall
JP4314681B2 (en) Reverse strut construction method
JP7082594B2 (en) How to build excavation jigs and earth retaining structures
JPS63181813A (en) Construction of steel tubular sheet pile
JP2659612B2 (en) Column type continuous underground wall construction method
JPH03228914A (en) Driving method for steel-pipe pile
JPS5820825A (en) Pile formation work and device therefor
JP2004238818A (en) Work execution method for soil cement column-row wall with tip foot protection pile structure
JPS59145821A (en) Method and apparatus for construction of pillar-row pile
JP2991736B2 (en) Basement wall installation method
JP2594724B2 (en) Construction method of trussed pillar
JPS6033151Y2 (en) Stirring device for continuous earth retaining pile wall
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPS59145822A (en) Construction work of underground continuous wall
JPH0333783Y2 (en)
JP3232196B2 (en) Drilling method and excavator for pile hole
JPS6033152Y2 (en) Stirring device for continuous earth retaining pile wall
JPS5985022A (en) Underground continuous wall constructing work
JPH0641956A (en) Execution method for high proof stress cast-in-place concrete pile, etc.
JPH03290588A (en) Rock-bed grooving method and guide bar for main down-the-haul drill therewith