JPH0473488B2 - - Google Patents
Info
- Publication number
- JPH0473488B2 JPH0473488B2 JP62195012A JP19501287A JPH0473488B2 JP H0473488 B2 JPH0473488 B2 JP H0473488B2 JP 62195012 A JP62195012 A JP 62195012A JP 19501287 A JP19501287 A JP 19501287A JP H0473488 B2 JPH0473488 B2 JP H0473488B2
- Authority
- JP
- Japan
- Prior art keywords
- grout
- excavation
- excavation section
- injection nozzle
- retaining wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【発明の詳細な説明】
[発明の利用分野]
本発明は地中にソイル山止め壁を形成するため
の形成方法及び装置に関する。DETAILED DESCRIPTION OF THE INVENTION [Field of Application of the Invention] The present invention relates to a method and apparatus for forming a soil pile retaining wall underground.
[背景技術]
地中の掘削孔内へグラウトを注入して掘削孔内
の土砂とともに固化させて地中壁を形成すること
により山止め壁とすることが行なわれている。[Background Art] Grout is injected into an underground excavation hole and solidified together with the earth and sand in the excavation hole to form an underground wall, thereby forming a retaining wall.
一般的にこの山止め壁の施工は、掘削ロツドを
用いて複数の平行掘削孔を形成し、これらの掘削
孔の一部を互いにオーバーラツプさせて掘削孔へ
充填するグラウトを互いに連結し連続した山止め
壁を地中へ形成するようになつている。 Generally, the construction of this retaining wall involves forming multiple parallel drilling holes using a drilling rod, overlapping some of these drilling holes, and connecting the grout to be filled into the drilling holes to form a continuous mountain. A retaining wall is formed underground.
しかし掘削孔が土質条件の変化、オーガヘツド
の回転方向等の影響で20m以上の大深度になると
正確に平行に掘削されないことがあり、隣接した
掘削孔がオーバーラツプする部分がなくなり、連
続した地中壁を形成することができず、水漏れの
原因となる。このため従来、複数の掘削ロツドを
平行に配置し、端部の掘削ロツドをすでに掘削し
た掘削孔へガイドとして挿入しながら掘削作業を
行なう方法が提案されている(特開昭60−133119
号)。この掘削方法では、既に掘削された掘削孔
と端部の掘削ロツドとが重ね合わせながら掘削さ
れるので、複数の掘削孔の平行度が維持されてオ
ーバーラツプが確保され掘削孔が正確に連通され
ることになる。 However, due to changes in soil conditions, the direction of rotation of the auger head, etc., when the drilling holes reach a deep depth of 20 m or more, they may not be drilled in parallel accurately, and there is no overlap between adjacent drilling holes, creating a continuous underground wall. cannot be formed, causing water leakage. For this reason, a conventional method has been proposed in which a plurality of drilling rods are arranged in parallel and the end drilling rod is inserted into the already drilled hole as a guide while performing the drilling work (Japanese Patent Application Laid-Open No. 133119-1982).
issue). In this drilling method, the drilled holes are overlapped with the drilled rods at the ends, so the parallelism of the multiple drilled holes is maintained, overlapping is ensured, and the drilled holes are accurately connected. It turns out.
しかしこの掘削方法では、常に端部の掘削ロツ
ドを既に掘削した掘削孔内へ挿入する必要がある
ため、長い地中壁を形成する場合には迅速な掘削
作業ができない。また掘削と同時にグラウトを掘
削部内へ注入するが、既にグラウトが充填された
掘削部をガイドとして掘削ロツドを挿入しながら
他の掘削ロツドによつて掘削作業を行なうので、
この既にグラウトが充填された掘削孔へも再びグ
ラウトを充填することになり、グラウトの使用量
が増大する原因になる。 However, with this excavation method, it is necessary to always insert the end drilling rod into an already excavated borehole, and therefore, when a long underground wall is to be formed, rapid excavation work cannot be performed. In addition, grout is injected into the excavated part at the same time as the excavation, but the excavation work is carried out using another drilling rod while inserting the drilling rod using the excavated part already filled with grout as a guide.
This excavated hole that has already been filled with grout has to be filled with grout again, which causes an increase in the amount of grout used.
本発明は上記事実を考慮し、掘削部を再度掘削
する必要がなく、掘削作業を迅速に行うことがで
き、かつ使用グラウト量の低減が可能なソイル山
止め壁の形成方法及び装置を得ることが目的であ
る。 In consideration of the above facts, the present invention provides a method and apparatus for forming a soil pile retaining wall, which eliminates the need to excavate the excavated part again, allows quick excavation work, and reduces the amount of grout used. is the purpose.
[発明の概要及び作用]
本出願の第1の発明に係るソイル山止め壁の形
成方法は、掘削後グラウトが充填された先行掘削
部と隣接して掘削した後行掘削部へ、グラウトを
充填すると同時に、前記先行掘削部と前記後行掘
削部との隣接部に限定して連続的にグラウトを噴
出して、前記先行掘削部と前記後行掘削部とを連
通することを特徴としている。[Summary and operation of the invention] A method for forming a soil heap retaining wall according to the first invention of the present application includes filling grout into a trailing excavation part excavated adjacent to a preceding excavation part filled with grout after excavation. At the same time, the method is characterized in that grout is continuously spouted only in a portion adjacent to the preceding excavation part and the following excavation part, thereby communicating the preceding excavation part and the following excavation part.
すなわち、すでに掘削してグラウトが充填され
た先行掘削部に隣接して後行掘削部を掘削してグ
ラウトを充填する際に、先行掘削部と後行掘削部
との隣接部に限定して連続的にグラウトを噴出す
るようになつている。これによつて、先行掘削部
を二度堀りする必要がなくなる。 In other words, when a trailing excavation section is excavated and filled with grout adjacent to a preceding excavation section that has already been excavated and filled with grout, continuous excavation is performed only in the adjacent section between the preceding excavation section and the following excavation section. The grout is now gushing out. This eliminates the need to excavate the preceding excavation twice.
また、先行掘削部と後行掘削部とが、平行に掘
削されていない場合、先行掘削部と後行掘削部と
がオーバーラツプせず、または、ラツプ量が少な
くなることがある。しかし、このような場合で
も、後行掘削部から噴射されるグラウトが、掘削
部間の孔壁を崩して先行掘削部と後行掘削部とを
連通させる。これによつて、水漏れのないソイル
山止め壁が構築される。また、孔壁は僅かな軸心
のずれによつて生じる薄肉部分であるため、グラ
ウト噴射によつて、崩すことができる。 Further, if the preceding excavated part and the succeeding excavated part are not excavated in parallel, the preceding excavated part and the succeeding excavated part may not overlap or the amount of overlap may be small. However, even in such a case, the grout injected from the trailing excavation part collapses the hole wall between the excavation parts and connects the preceding excavation part and the trailing excavation part. This creates a soil pile retaining wall that does not leak water. Further, since the hole wall is a thin portion caused by a slight misalignment of the axis, it can be broken down by injection of grout.
第2の発明に係るソイル山止め壁の形成装置
は、隣接して複数形成された掘削部へグラウトを
充填して連続した山止め壁を地中に形成するソイ
ル山止め壁の形成装置であつて、回転しながら地
中へ挿入され掘削部を形成する掘削ロツドと、前
記掘削ロツドの外周に配設され掘削ロツドに伴な
つて回転することなく前記掘削部内へ掘削ロツド
と伴に貫入される噴射ノズル支持部材と、前記噴
射ノズル支持部材に取付けられ先行掘削部と後行
掘削部との隣接部に限定して連続的にグラウトを
噴出する噴射ノズルと、前記噴射ノズルへグラウ
トを供給するグラウト供給手段と、を有すること
を特徴としている。 A soil pile retaining wall forming apparatus according to a second aspect of the present invention is a soil retaining wall forming apparatus that fills grout into a plurality of adjacent excavated portions to form a continuous retaining wall underground. an excavation rod that is inserted into the ground while rotating to form an excavation section; and a excavation rod that is disposed around the outer circumference of the excavation rod and that penetrates into the excavation section together with the excavation rod without rotating with the excavation rod. An injection nozzle support member, an injection nozzle that is attached to the injection nozzle support member and that continuously sprays grout only in areas adjacent to the preceding excavation section and the following excavation section, and a grout that supplies grout to the injection nozzle. It is characterized by having a supply means.
これによつて、噴射ノズルは、掘削ロツドと伴
に地中へ挿入されるので、別途、噴射ノズルを地
中へ挿入する必要はない。また、噴射ノズルは掘
削ロツドと伴に回転することがないので、先行掘
削部と後行掘削部との隣接部に限定して連続的に
グラウトを噴出することができる。 As a result, the injection nozzle is inserted into the ground together with the excavation rod, so there is no need to separately insert the injection nozzle into the ground. Further, since the injection nozzle does not rotate together with the excavation rod, grout can be continuously ejected only to the adjacent portions of the preceding excavation section and the following excavation section.
また、噴射方向変更手段で噴射ノズルの噴射方
向を変えることで、必要に応じて先行掘削部と後
行掘削部との大きなラツプ量を確保することがで
きる。さらに、この噴射方向変更手段は、掘削ロ
ツドの回転力、あるいは噴射ノズルの噴射反力の
変化によつて駆動されるので、別途駆動手段を設
ける必要がない。 Further, by changing the injection direction of the injection nozzle using the injection direction changing means, it is possible to secure a large amount of overlap between the preceding excavation section and the following excavation section as necessary. Further, since this injection direction changing means is driven by the rotational force of the excavating rod or the change in the injection reaction force of the injection nozzle, there is no need to provide a separate driving means.
[発明の実施例]
第1図には本発明が適用される掘削機10が示
されている。この掘削機10は上端部に多軸オー
ガマシン12が設けられ、この多軸オーガマシン
12から垂直下方に突出される複数本(この実施
例では4本)の掘削ロツド14が地中への挿入部
となつている。これらの掘削ロツド14は先端部
に掘削ビツト16がそれぞれ取付けられ多軸オー
ガマシン12により回転駆動されるようになつて
おり、地中の土砂を掻き崩すようになつている。
これらの掘削ビツト16は第4図に示される如く
互いに一部がオーバーラツプした掘削部20を形
成することになる。[Embodiments of the Invention] FIG. 1 shows an excavator 10 to which the present invention is applied. This excavator 10 is provided with a multi-shaft auger machine 12 at the upper end, and a plurality of (four in this embodiment) drilling rods 14 that protrude vertically downward from the multi-shaft auger machine 12 are inserted into the ground. It has become a department. Each of these excavating rods 14 has an excavating bit 16 attached to its tip and is rotatably driven by a multi-shaft auger machine 12, so as to break up earth and sand underground.
These excavation bits 16 form an excavation portion 20 that partially overlaps each other, as shown in FIG.
これらの掘削ビツト16の上方には掘削ロツド
14へ複数個の掘削翼22が固着されるととも
に、さらに上方の部分は4本の掘削ロツド14が
ロツド連結板24,26で互いに連結支持されて
いる。 A plurality of drilling blades 22 are fixed to the drilling rods 14 above these drilling bits 16, and further above, four drilling rods 14 are connected and supported to each other by rod connecting plates 24 and 26. .
第2,3図に示される如くロツド連結板24は
2枚の板材24A,24Bが重ね合わせて構成さ
れており、これらの板材24A,24B間に軸受
メタル28を介して掘削ロツド14の外周を軸支
している。 As shown in FIGS. 2 and 3, the rod connecting plate 24 is constructed by overlapping two plates 24A and 24B, and the outer periphery of the excavating rod 14 is connected between these plates 24A and 24B via a bearing metal 28. It is pivoted.
各掘削ロツド14は中空形状であり、軸心部に
はグラウト(セメントミルク)を掘削ビツト16
へと案内するためのグラウト管30が通過されて
いる。 Each drilling rod 14 has a hollow shape, and the drilling bit 16 is filled with grout (cement milk) at the shaft center.
A grouting tube 30 has been passed through for guidance.
ロツド連結板24と多軸オーガマシン12との
間には鋼管32が掘削ロツド14と平行に掛け渡
されており、内部に掘削角度調節用の傾斜計(図
示省略)が配置されている。 A steel pipe 32 is stretched between the rod connecting plate 24 and the multi-axis auger machine 12 in parallel with the excavating rod 14, and an inclinometer (not shown) for adjusting the excavating angle is disposed inside.
ロツド連結板24の長手方向(第2,3図の左
右方向)両端部には頂面に取付板34が固着され
ており、噴射ノズル36が取付けられている。こ
の噴射ノズル36は垂直な軸37廻りに回転可能
に取付板34へ取付けられており、噴射口38の
噴射方向を水平面内で変更可能となつている。こ
の噴射ノズル36は噴射口38の反対側端部へ高
圧ホース40が連結されている。この高圧ホース
40は鋼管32を通つて多軸オーガマシン12へ
導かれ、高圧グラウト材の供給装置へと連結され
ている。 Attachment plates 34 are fixed to the top surfaces of both ends of the rod connecting plate 24 in the longitudinal direction (left and right directions in FIGS. 2 and 3), and injection nozzles 36 are attached thereto. This injection nozzle 36 is rotatably attached to the mounting plate 34 about a vertical axis 37, and the injection direction of the injection port 38 can be changed within a horizontal plane. A high-pressure hose 40 is connected to the end of the injection nozzle 36 opposite to the injection port 38 . This high-pressure hose 40 is led to the multi-shaft auger machine 12 through a steel pipe 32 and connected to a high-pressure grout supply device.
またこの噴射ノズル36には取付板34との間
に引張コイルばね42が介在され、掘削ロツド1
4へ固着されるカム44の外周へ噴射ノズル36
の中間部を押圧している。このカム44は掘削ロ
ツド14の回転時に噴射ノズル36を引張コイル
ばね42の付勢力に抗して軸37回りに回転させ
るようになつている。 Further, a tension coil spring 42 is interposed between the injection nozzle 36 and the mounting plate 34, and the tension coil spring 42 is connected to the drilling rod 1.
The injection nozzle 36 is attached to the outer periphery of the cam 44 fixed to the cam 44.
The middle part of the is pressed. This cam 44 is designed to rotate the injection nozzle 36 about the shaft 37 against the biasing force of the tension coil spring 42 when the excavating rod 14 rotates.
この噴射ノズル36、引張コイルばね42、カ
ム44は噴射口38部分を除いてカバー46を取
付けて、内部へ土砂等が入り込まないようにする
ことが好ましい。 It is preferable that a cover 46 is attached to the injection nozzle 36, the tension coil spring 42, and the cam 44 except for the injection port 38 to prevent dirt and the like from entering inside.
次に本実施例の作用を説明する。 Next, the operation of this embodiment will be explained.
第4図には本実施例において山止め壁が飛び石
的に施工される順序が示されている。 FIG. 4 shows the order in which the retaining walls are constructed in a step-by-step manner in this embodiment.
すなわち第4図のAに示される如く先行掘削部
20A,20Bを掘削ピツチPの5/3倍だけ離れ
た間隔Qで形成する。これらの先行掘削部20
A,20B内にはグラウトが充填されるが、この
グラウトは掘削された土砂と混合される。 That is, as shown in FIG. 4A, the preceding excavation parts 20A and 20B are formed at an interval Q separated by 5/3 times the excavation pitch P. These advance excavation parts 20
Grout is filled in A and 20B, and this grout is mixed with the excavated earth and sand.
次に第4図Bに示される如く後行掘削部20C
をその一部が先行掘削部20A,20Bとオーバ
ーラツプ(寸法O)して形成する。この掘削及び
グラウトの充填時に噴射ノズル36からグラウト
Gを横方向に噴射させると、既に充填されている
先行掘削部20A,20Bの端部の掘削部へこの
グラウトGが噴射される。このため先行掘削部2
0A,20Bのグラウトと後行掘削部20Cのグ
ラウトとが混合される。また先行掘削部20A,
20Bと後行掘削部20Cとが軸心を正確に平行
に掘削されておらず、オーバーラツプ量(寸法
O)が少ない場合にも、これらの先行掘削部と後
行掘削部との間の土砂を噴射口38から噴射され
たグラウトが掻き落すので、先行掘削部20A,
20Bと後行掘削部20Cとの間は十分に大きな
面積で連通され、間が抜けることのない地中壁が
形成される。 Next, as shown in FIG. 4B, the trailing excavation section 20C
A portion thereof overlaps (dimension O) with the preceding excavated portions 20A and 20B. When grout G is injected laterally from the injection nozzle 36 during this excavation and grout filling, this grout G is injected into the excavated portions at the ends of the preceding excavated portions 20A and 20B that have already been filled. For this reason, the advance excavation section 2
The grouts of 0A and 20B and the grout of the trailing excavation section 20C are mixed. In addition, the advance excavation part 20A,
Even if the axes 20B and the trailing excavation section 20C are not excavated accurately in parallel with each other and the amount of overlap (dimension O) is small, it is possible to remove the earth and sand between the preceding excavation section and the trailing excavation section. Since the grout injected from the injection port 38 is scraped off, the preceding excavation part 20A,
20B and the trailing excavation part 20C are communicated over a sufficiently large area, and an underground wall with no gaps is formed.
第5図は地中壁を屈曲して形成する場合の施工
手順が示されている。すなわち先行掘削部20
A,20Bを連続して形成した後に先行掘削部2
0Bの端部へ直角に後行掘削部20Cを形成す
る。この場合、後行掘削部20Cの端部からは先
行掘削部20Bの後端部へ同様に噴射ノズルを用
いてグラウトGが充填されるので、後行掘削部2
0Cと先行掘削部20Bとは確実に連通される。
先行掘削部20Aと20Bの連結部にも同様にグ
ラウトを充填する。 FIG. 5 shows the construction procedure when forming an underground wall by bending it. That is, the advance excavation section 20
After continuously forming A and 20B, the preceding excavation part 2
A trailing excavation portion 20C is formed at right angles to the end of 0B. In this case, grout G is filled from the end of the trailing excavation section 20C to the rear end of the preceding excavation section 20B using the injection nozzle, so that the trailing excavation section 2
0C and the preceding excavation part 20B are reliably communicated.
The connecting portion between the preceding excavated portions 20A and 20B is also filled with grout.
また本発明は先行掘削部と後行掘削部との交叉
角度を直角に限らず、これ以外の角度で連結させ
る場合にも適用できる。また噴射ノズル36は複
数本の掘削ロツド14の両端部に設ける場合に限
らず、片側へのみ設けてもよい。 Further, the present invention is not limited to the intersection angle between the preceding excavation part and the following excavation part being at right angles, but can also be applied to the case where they are connected at an angle other than this. Further, the injection nozzles 36 are not limited to being provided at both ends of the plurality of excavating rods 14, but may be provided only on one side.
さらに上記実施例は噴射ノズル36がカム44
によつて噴射角度を変更される構成を示したが、
広範囲の噴射角を確保できる噴射ノズルであれば
回転させる必要はない。またカム以外の駆動力伝
達構造によつて掘削ロツド14の駆動力を噴射ノ
ズル36へ伝えてもよい。さらに噴射ノズル36
はグラウトの噴射反力で自動的に噴射角度を変更
できるようにしてもよい。 Furthermore, in the above embodiment, the injection nozzle 36 is connected to the cam 44.
Although we have shown a configuration in which the injection angle is changed by
If the injection nozzle can secure a wide range of injection angles, there is no need to rotate it. Further, the driving force of the excavating rod 14 may be transmitted to the injection nozzle 36 by a driving force transmitting structure other than the cam. Furthermore, the injection nozzle 36
Alternatively, the injection angle may be automatically changed by the injection reaction force of the grout.
[発明の効果]
以上説明した如く本発明は、ソイル山止め壁の
形成するに際して、先行掘削部を再度掘削する必
要がなく、先行掘削部と後行掘削部とがオーバー
ラツプせず、または、ラツプ量が少ない場合で
も、後行掘削部をグラウトで充填すると同時に、
先行掘削部と後行掘削部とがグラウトで確実に連
通され、水漏れのないソイル山止め壁を構築でき
る。さらに、必要な部分にのみグラウトを噴射す
るので、使用グラウト量も少なくて済む。[Effects of the Invention] As explained above, the present invention eliminates the need to excavate the preceding excavated portion again when forming the soil pile retaining wall, and prevents the preceding excavated portion and the subsequent excavated portion from overlapping or overlapping. Even if the amount is small, at the same time as filling the trailing excavation with grout,
The preceding excavation part and the following excavation part are reliably communicated with grout, and a soil pile retaining wall without water leakage can be constructed. Furthermore, since grout is injected only to the necessary areas, the amount of grout used can be reduced.
第1図は本発明が適用された掘削機を示す掘削
状態の正面図、第2図は噴射ノズルの取付部付近
を示す拡大図、第3図は第2図の平面図、第4図
及び第5図は掘削手順を示す平面図である。
10……掘削機、14……掘削ロツド、20
A,20B……先行掘削部、20C……後行掘削
部、36……噴射ノズル、38……噴射口、44
……カム。
Fig. 1 is a front view of an excavator to which the present invention is applied in an excavating state, Fig. 2 is an enlarged view showing the vicinity of the injection nozzle attachment part, Fig. 3 is a plan view of Fig. 2, Fig. 4, and FIG. 5 is a plan view showing the excavation procedure. 10...Excavator, 14...Drilling rod, 20
A, 20B... Leading excavation part, 20C... Trailing excavation part, 36... Injection nozzle, 38... Injection port, 44
……cam.
Claims (1)
接して掘削した後行掘削部へ、グラウトを充填す
ると同時に、前記先行掘削部と前記後行掘削部と
の隣接部に限定して連続的にグラウトを噴出し
て、前記先行掘削部と前記後行掘削部とを連通す
ることを特徴とするソイル山止め壁の形成方法。 2 隣接して複数形成された掘削部へグラウトを
充填して連続した山止め壁を地中に形成するソイ
ル山止め壁の形成装置であつて、回転しながら地
中へ挿入され掘削部を形成する掘削ロツドと、前
記掘削ロツドの外周に配設され掘削ロツドに伴な
つて回転することなく前記掘削部内へ掘削ロツド
と伴に貫入される噴射ノズル支持部材と、前記噴
射ノズル支持部材に取付けられ先行掘削部と後行
掘削部との隣接部に限定して連続的にグラウトを
噴出する噴射ノズルと、前記噴射ノズルへグラウ
トを供給するグラウト供給手段と、を有すること
を特徴とするソイル山止め壁の形成装置。 3 前記噴射ノズルの噴射方向を変更する噴射方
向変更手段を設けたことを特徴とする前記特許請
求の範囲第2項記載のソイル山止め壁の形成装
置。 4 前記噴射方向変更手段が掘削ロツドの回転
力、あるいは噴射ノズルの噴射反力の変化によつ
て駆動されることを特徴とする前記特許請求の範
囲第3項記載のソイル山止め壁の形成装置。[Scope of Claims] 1. Filling grout into a trailing excavation section that is excavated adjacent to a preceding excavation section filled with grout after excavation, and at the same time filling a portion adjacent to the preceding excavation section and the trailing excavation section with grout. A method for forming a soil heap retaining wall, characterized in that grout is spouted continuously in a limited manner to connect the preceding excavation section and the following excavation section. 2. A soil pile retaining wall forming device that fills grout into a plurality of adjacent excavated parts to form a continuous retaining wall underground, and is inserted into the ground while rotating to form the excavated parts. a drilling rod, an injection nozzle support member disposed on the outer periphery of the drilling rod and inserted into the excavation portion together with the drilling rod without rotating; and a jet nozzle support member attached to the injection nozzle support member. A soil heap stopper characterized by having an injection nozzle that continuously sprays grout only in an area adjacent to a preceding excavation section and a following excavation section, and a grout supply means that supplies grout to the injection nozzle. Wall forming equipment. 3. The soil pile retaining wall forming apparatus according to claim 2, further comprising a jetting direction changing means for changing the jetting direction of the jetting nozzle. 4. The soil mound retaining wall forming apparatus according to claim 3, wherein the jetting direction changing means is driven by a rotational force of an excavating rod or a change in jetting reaction force of a jetting nozzle. .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19501287A JPS6439412A (en) | 1987-08-04 | 1987-08-04 | Forming method and device of soil landslide protection wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19501287A JPS6439412A (en) | 1987-08-04 | 1987-08-04 | Forming method and device of soil landslide protection wall |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6439412A JPS6439412A (en) | 1989-02-09 |
| JPH0473488B2 true JPH0473488B2 (en) | 1992-11-20 |
Family
ID=16334064
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP19501287A Granted JPS6439412A (en) | 1987-08-04 | 1987-08-04 | Forming method and device of soil landslide protection wall |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6439412A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001241063A (en) * | 2000-02-24 | 2001-09-04 | Raito Kogyo Co Ltd | Drilling rig and method of constructing underground column continuous wall using it |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS559491B2 (en) * | 1974-01-21 | 1980-03-10 | ||
| JPS5736687U (en) * | 1980-08-09 | 1982-02-26 |
-
1987
- 1987-08-04 JP JP19501287A patent/JPS6439412A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6439412A (en) | 1989-02-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4212565A (en) | Method and apparatus for forming a continuous row of cast-in-place piles to form a wall | |
| JPH0473488B2 (en) | ||
| JP3958982B2 (en) | Horizontal drilling direction control method and drilling rod therefor | |
| JP2809559B2 (en) | Multi-axis drilling rig | |
| JPH02125016A (en) | Hollow drilling grouting method | |
| JP3450639B2 (en) | Rock bolt driving method and rock bolt driving machine | |
| WO1995011349A1 (en) | Multi-shaft excavating device | |
| JP6729902B1 (en) | Construction method of soil cement continuous wall | |
| JP4550792B2 (en) | Construction method of underground wall | |
| JP2909014B2 (en) | Method for drilling earth and sand layer and rock and apparatus for drilling earth and sand layer and rock | |
| JP3125033B2 (en) | Construction method of improved wall | |
| JP4349522B2 (en) | Ground improvement method | |
| JP3788896B2 (en) | Yamato wall construction method | |
| JP4600897B2 (en) | Chemical injection method | |
| JPH06193045A (en) | Ground improvement method by multishaft type forced stirring device | |
| JP2729940B2 (en) | Drilling rig | |
| JPS6039812B2 (en) | Steel sheet pile construction method | |
| JPS6353329B2 (en) | ||
| JPS61191721A (en) | Method of forming earth anchor | |
| JP2000290995A (en) | Construction method of underground wall by ground improvement and equipment used for it | |
| JP3232196B2 (en) | Drilling method and excavator for pile hole | |
| JPS6062333A (en) | Excavator | |
| JP4383368B2 (en) | How to install a girder member in the ground between two tunnels | |
| JPH034690B2 (en) | ||
| JPS59145821A (en) | Method and apparatus for construction of pillar-row pile |