Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH047403B2 - - Google Patents
[go: Go Back, main page]

JPH047403B2 - - Google Patents

Info

Publication number
JPH047403B2
JPH047403B2 JP23319585A JP23319585A JPH047403B2 JP H047403 B2 JPH047403 B2 JP H047403B2 JP 23319585 A JP23319585 A JP 23319585A JP 23319585 A JP23319585 A JP 23319585A JP H047403 B2 JPH047403 B2 JP H047403B2
Authority
JP
Japan
Prior art keywords
steel
flange
concrete
sheath
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP23319585A
Other languages
Japanese (ja)
Other versions
JPS6294603A (en
Inventor
Masayuki Kitaoka
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YASHIRO KOGYO KOTO SENMON GATSUKOCHO
Original Assignee
YASHIRO KOGYO KOTO SENMON GATSUKOCHO
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YASHIRO KOGYO KOTO SENMON GATSUKOCHO filed Critical YASHIRO KOGYO KOTO SENMON GATSUKOCHO
Priority to JP23319585A priority Critical patent/JPS6294603A/en
Publication of JPS6294603A publication Critical patent/JPS6294603A/en
Publication of JPH047403B2 publication Critical patent/JPH047403B2/ja
Granted legal-status Critical Current

Links

Classifications

    • Y02T10/7077

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、鋼桁と床版コンクリートとを組合わ
せた鋼合成桁およびその架設工法に関し、特に、
コンクリート断面に生ずる引張応力を打消すだけ
の圧縮応力を予め導入するプレストレツシングに
伴う応力が鋼桁に残留しないようにしたものであ
る。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a steel composite girder that combines a steel girder and concrete slab, and a method for constructing the same.
This prevents stress from remaining in the steel girder due to pre-stretching, which introduces compressive stress sufficient to cancel out the tensile stress generated in the concrete cross section.

(従来の技術) 一般に、橋梁用または高速自動車道用として、
鋼桁とコンクリート床版とをずれ止めを介して組
合わせた鋼合成桁における床版コンクリートの断
面については、あらゆる設計荷重のもとで、すべ
ての部分に圧縮応力のみが生じて、圧縮応力に強
い床版コンクリートが、その断面の全面に亘つて
有効に作用することが望まれる。したがつて、何
れかの原因で床版コンクリートの断面に引張応力
が生ずることが判明した場合には、その引張応力
を打消すに必要な圧縮応力を予め導入しておく処
置、すなわち、いわゆるプレストレツシングが床
版コンクリートに施されるのが一般である。すな
わち、第2図a,bに示すように、架設を完了し
た鋼桁2の上フランジ4の上面に、適切な間隔で
多数のずれ止め3を溶接した後に、通例、鋼桁1
の長手方向に沿い、ピアノ線等の鋼材を内蔵した
シース5を適切な間隔で多数配列するとともに所
要の鉄筋構造を組立てたうえで、コンクリートを
打設して床版コンクリート1を形成する。かかる
構成の床版コンクリート1の例えば長手方向に生
ずる引張応力に対してプレストレツシングを施す
ために、シース4内のピアノ線等の両端を引張つ
て床版コンクリート1の端面7にそれぞれ固定
し、予測される引張応力に匹敵する圧縮応力を予
め床版コンクリート1に加えるようにするのが、
従来のプレストレツシング実施の態様であつた。
(Prior art) Generally, for bridges or expressways,
Regarding the cross-section of the concrete deck in a steel composite girder that combines a steel girder and a concrete deck via anti-slip devices, only compressive stress occurs in all parts under any design load, and no compressive stress occurs. It is desired that the strong slab concrete acts effectively over the entire cross section. Therefore, if it is found that tensile stress is generated in the cross section of the concrete slab for any reason, it is necessary to introduce the necessary compressive stress in advance to cancel out the tensile stress, that is, so-called pre-stressing. Lessing is generally applied to concrete floor slabs. That is, as shown in FIGS. 2a and 2b, after welding a large number of stoppers 3 at appropriate intervals to the upper surface of the upper flange 4 of the steel girder 2, which has been completely erected, the steel girder 1 is
Along the longitudinal direction, a large number of sheaths 5 containing steel materials such as piano wire are arranged at appropriate intervals, and after assembling the required reinforcing structure, concrete is poured to form the concrete floor slab 1. In order to apply pre-stressing to the concrete floor slab 1 having such a configuration, for example, against tensile stress occurring in the longitudinal direction, both ends of a piano wire or the like in the sheath 4 are pulled and fixed to the end faces 7 of the concrete floor slab 1, respectively. Applying a compressive stress comparable to the predicted tensile stress to the slab concrete 1 in advance is as follows:
This was a conventional pre-stressing implementation mode.

(発明が解決しようとする問題点) しかしながら、かかる態様の従来のプレストレ
ツシング実施に際しては、床版コンクリート1の
コンクリートが、鋼桁2の上フランジ4に溶接し
たずれ止め3と一体になつて、すでに硬化してい
るので、予め加えた圧縮応力、すなわち、プレス
トレスは、床版コンクリート1と鋼桁2との合成
断面に加わることになる。したがつて、上述の実
施態様による従来のプレストレツシングに要する
加力の一部、例えば、本発明者の試算によれば25
%程度が鋼桁2を変形させることに消費され、鋼
桁2には「プレストレツシングに伴う応力」が止
むを得ず残留するという好ましからぬ結果となる
のみならず、余分の加力を行なうために、余分の
シースを配設して余分の加工作業を実施する必要
があり、甚だ不経済である、という問題点があつ
た。
(Problems to be Solved by the Invention) However, when performing conventional pre-stressing in this manner, the concrete of the deck slab 1 is integrated with the slip stopper 3 welded to the upper flange 4 of the steel girder 2. , has already hardened, so the compressive stress applied in advance, that is, the prestress, will be applied to the composite cross section of the concrete deck 1 and the steel girder 2. Therefore, a portion of the applied force required for the conventional pre-stressing according to the embodiment described above, for example, 25
% is consumed in deforming the steel girder 2, which not only results in the undesirable result that "stress due to pre-stressing" inevitably remains in the steel girder 2, but also causes excessive force to be applied. Therefore, it is necessary to provide an extra sheath and perform extra processing operations, which is extremely uneconomical.

本発明の目的は、上述した従来の問題点を解決
し、プレストレツシングの実施に際して、従来は
鋼桁の上フランジ上にずれ止めを直接溶接し、そ
の上フランジ上に床版コンクリートを形成してい
たのに対し、鋼桁の上フランジに高力ボルトによ
つて締結した別のフランジ上にずれ止めを溶接し
てその上に床版コンクリートを形成することによ
り、鋼桁と床版コンクリートとの間の結合を絶
ち、本来プレストレスを必要とするコンクリート
断面のみにプレストレスを与えて、鋼桁には無用
の応力を残留させず、必要最小限度の加力で足り
るようにした鋼合成桁およびその架設工法を提供
することにある。
An object of the present invention is to solve the above-mentioned conventional problems, and when performing pre-stressing, conventionally, a shear stopper was welded directly onto the upper flange of a steel girder, and slab concrete was then formed on the flange. In contrast, by welding a shear stop onto another flange fastened to the upper flange of the steel girder with high-strength bolts and forming deck concrete on top of it, the steel girder and deck concrete can be easily connected. A steel composite girder that eliminates the bond between the steel girders and applies prestress only to the concrete cross section that originally requires prestress, leaving unnecessary stress on the steel girder and requiring only the minimum amount of force necessary. and its construction method.

(問題点を解決するための手段) 上述した目的を達成するために、本発明鋼合成
桁は、ずれ止めを溶接したフランジ上に鋼材を内
蔵したシースおよび鉄筋を組立ててコンクリート
を打設するとともに前記鋼材に引張力を加えて形
成したプレストレス床版コンクリートの当該フラ
ンジを鋼桁の上フランジ上に油脂層を介して配設
し、当該上フランジに前記フランジを高力ボルト
により締結したことを特徴とするものである。
(Means for Solving the Problems) In order to achieve the above-mentioned object, the steel composite girder of the present invention is constructed by assembling a sheath containing a steel material and reinforcing bars on a flange to which anti-slip is welded, and pouring concrete. The flange of the prestressed concrete slab formed by applying tensile force to the steel material is placed on the upper flange of the steel girder via an oil layer, and the flange is fastened to the upper flange with high-strength bolts. This is a characteristic feature.

また、本発明による鋼合成桁の架設工法は、架
設を完了した鋼桁の上フランジ上に、油脂層を介
し、ずれ止めを溶接したフランジを配設して高力
ボルトにより前記上フランジに仮締めする工程
と、 前記フランジ上に鋼材を内蔵したシースおよび
鉄筋を組立ててコンクリートを打設し、床版コン
クリートを完成する工程と、 前記シースに内蔵した前記鋼材の両端を前記床
版コンクリートの端面に固定する工程と、 前記高力ボルトを本締めした後に前記シース内
にモルタルを注入する工程と を順次に施すことを特徴とするものである。
In addition, in the method of constructing a steel composite girder according to the present invention, a flange to which a slip stopper is welded is placed on the completed steel girder upper flange through an oil layer, and is temporarily attached to the upper flange using high-strength bolts. a step of assembling a sheath with a built-in steel material and reinforcing bars on the flange and pouring concrete to complete the concrete floor slab; and a step of attaching both ends of the steel material built into the sheath to the end face of the concrete floor slab. and a step of injecting mortar into the sheath after fully tightening the high-strength bolts.

(作用) 上述の特徴を有する本発明鋼合成桁およびその
架設工法においては、床版コンクリートの断面に
必要最小限度の引張力を加えて、鋼桁には無用の
応力を残留させることなく、適切にプレストレツ
シングを施すことができる。
(Function) In the steel composite girder of the present invention having the above-mentioned features and its construction method, the minimum necessary tensile force is applied to the cross section of the concrete slab, and the steel girder is properly constructed without residual unnecessary stress. can be pre-stressed.

(実施例) 以下に図面を参照して実施例につき本発明を詳
細に説明する。
(Example) The present invention will be described in detail below with reference to the drawings.

第2図に示した従来の鋼合成桁と同様に支間が
比較的長い鋼桁を用いた場合における本発明鋼合
成桁の要部の詳細な構成の例を、各部の断面につ
いて、第1図a〜cにそれぞれ示す。
Figure 1 shows an example of the detailed structure of the main parts of the steel composite girder of the present invention when a steel girder with a relatively long span is used like the conventional steel composite girder shown in Figure 2, and the cross section of each part is shown in Figure 1. They are shown in a to c, respectively.

図示の構成例においては、まず、架設を完了し
た鋼桁2における上フランジ14の板厚の変化を
ならして、上フランジ14の上面を平坦かつ平滑
にするとともに、上フランジ14の現場継手は現
場溶接し、上側の余盛を平滑に仕上げておく。さ
らに、上フランジ14における長手方向の縁辺部
には、図示のように、鋼板からなるタブプレート
13を溶接しておく。かかる加工を施した鋼桁2
における上フランジ14の平滑面上に、潤滑材と
して油脂類を一面に塗布したうえで、厚さ10mm以
上の軟鋼板よりなる第2フランジ11を、上フラ
ンジ14と長手方向の端縁を揃えた状態で重ねて
配設する。この軟鋼板よりなる第2フランジ11
は、後述するように、コンクリートを打設して形
成した床版コンクリート1の合成断面の一部材と
して一体に作用する。また、この第2フランジ1
1は、上述した床版コンクリート1を鋼桁2に結
合させるために、図示のように、軟鋼材よりなる
フイラ9を介し、上フランジ14に溶接したタブ
プレート13に例えばトルシア型の高力ボルト6
により締結して固定する。なお、その際に第2フ
ランジ11およびタブプレート13に設けるボル
ト穴は、鋼桁2の長手方向のスロツト状に形成し
て、第2フランジ11を上フランジ14に固定す
る位置を相対的にずらし得るようにしておく。ま
た、締結に使用する高力ボルト6は、ボルト頭が
後にコンクリート中に埋設されるのであるから、
リベツト状のボルト頭を有し、ねじの先端部でナ
ツトに対し固定し得るとともに、所定値を超えた
締付けトルクに対して剪断されるトルシア型とす
るのが好適である。
In the illustrated configuration example, first, changes in the plate thickness of the upper flange 14 in the steel girder 2 that has been completely erected are smoothed out to make the upper surface of the upper flange 14 flat and smooth, and the field joints of the upper flange 14 are Weld on-site and finish the upper layer smoothly. Furthermore, a tab plate 13 made of a steel plate is welded to the longitudinal edge of the upper flange 14 as shown in the figure. Steel girder 2 subjected to such processing
After applying an oil or fat as a lubricant to the smooth surface of the upper flange 14, the second flange 11 made of a mild steel plate with a thickness of 10 mm or more is aligned with the longitudinal edges of the upper flange 14. Lay them out one on top of the other. The second flange 11 made of this mild steel plate
As will be described later, it acts integrally as a part of the composite cross section of the concrete floor slab 1 formed by pouring concrete. Also, this second flange 1
1, in order to connect the above-mentioned concrete slab 1 to the steel girder 2, high-strength bolts of, for example, Torcia type are attached to the tab plate 13 welded to the upper flange 14 via a filler 9 made of mild steel, as shown in the figure. 6
Fasten and secure. In this case, the bolt holes provided in the second flange 11 and the tab plate 13 are formed in the shape of slots in the longitudinal direction of the steel girder 2, so that the position where the second flange 11 is fixed to the upper flange 14 is relatively shifted. Make sure you get it. In addition, since the head of the high-strength bolt 6 used for fastening is buried in concrete later,
It is preferable that the bolt be of the Torcia type, which has a rivet-like bolt head, can be fixed to a nut at the tip of the screw, and can be sheared when a tightening torque exceeds a predetermined value.

上述のように構成する第2フランジ11の上面
には、適切に分散させて、コンクリートずれ止め
3を例えば図示のように溶接する。なお、ずれ止
め3は、その種類や型式の如何を問わない。かか
る第2フランジ11上に、コンクリート打設のた
めの鉄筋および第2図につき前述したと同様のプ
レストレツシングのための鋼材を内蔵したシース
5を適切に配設して組立てたうえでコンクリート
を打設し、所要の床版コンクリート1を形成す
る。なお、シース5に内蔵する鋼材5は、例えば
いわゆるピアノ線など、鋼線、撚り鋼線、鋼棒等
を適切に選択して使用する。
On the upper surface of the second flange 11 configured as described above, concrete shear stops 3 are welded, for example, as shown in the drawings, with appropriate distribution. Note that the anti-slip 3 may be of any type or type. On the second flange 11, a sheath 5 containing reinforcing bars for concrete pouring and a steel material for pre-stressing similar to that described above in FIG. 2 is appropriately disposed and assembled, and then concrete is poured. The required concrete floor slab 1 is formed by pouring. The steel material 5 contained in the sheath 5 is appropriately selected from, for example, a so-called piano wire, a steel wire, a twisted steel wire, a steel rod, or the like.

上述のように構成する本発明鋼合成桁は、つぎ
に述べるような手順の工法によつて順次に架設す
るのが好適である。
The steel composite girder of the present invention constructed as described above is preferably erected in sequence by the construction method described below.

(1) 鋼桁2の架設を完了した後に、その上フラン
ジ14の上面4に、潤滑材として例えばグリー
スなどの油脂類を一面に塗布する。
(1) After completing the erection of the steel girder 2, the upper surface 4 of the upper flange 14 is coated with oil such as grease as a lubricant.

(2) 鋼桁2における上フランジ14の上面4上
に、ずれ止め3を適切に分散させて溶接した第
2フランジ11を重ねて配置し、その第2フラ
ンジ11の縁辺部と上フランジ14に溶接して
あるタグプレート13とを、フイラ9を介し、
高力ボルト6により仮締めして、仮に固定す
る。
(2) On the upper surface 4 of the upper flange 14 of the steel girder 2, the second flange 11 welded with the anti-slip 3 appropriately distributed is placed overlappingly, and the edge of the second flange 11 and the upper flange 14 are Welded tag plate 13 via filler 9,
Temporarily tighten with high-strength bolts 6 to temporarily fix.

(3) 第2フランジ11上に、床版コンクリート1
用の鉄筋とプレストレツシング用のピアノ線等
の鋼材を内蔵したシース5とを適切に組立てた
うえで、コンクリートを打設して養生し、床版
コンクリート1を完成する。
(3) Floor slab concrete 1 on the second flange 11
After appropriately assembling the reinforcing bars for use in the concrete and the sheath 5 containing steel materials such as piano wire for pre-stretching, concrete is poured and cured to complete the concrete floor slab 1.

(4) 鋼桁2の支間中点以外に位置する高力ボルト
6をすべて完全に緩め、鋼桁2の上フランジ1
4に対し、その支間中点以外においては、プレ
ストレスを加えたときに第2フランジ11がそ
のプレストレスに応じて摺動し得るようにす
る。
(4) Completely loosen all the high-strength bolts 6 located other than the midpoint of the span of the steel girder 2, and tighten the upper flange 1 of the steel girder 2.
4, the second flange 11 is made to be able to slide in accordance with the prestress when prestress is applied except at the midpoint of the span.

(5) 各シース5内のコンクリート・プレストレツ
シング(PC)用のピアノ線等の鋼材の両端に
所定の引張力に達するまで加力し、その鋼材の
両端に結合させたボルト・ナツトにより、その
両端を床版コンクリート1の端面に固定する。
(5) Apply force to both ends of a steel material such as piano wire for concrete pre-stretching (PC) in each sheath 5 until a predetermined tensile force is reached, and use bolts and nuts connected to both ends of the steel material. Its both ends are fixed to the end face of the concrete floor slab 1.

(6) 必要に応じ、床版コンクリート1上に、振動
機8を用いて、桁端から支間中点に向けて、繰
返し移動させながら振動を与え、プレストレツ
シングに際して鋼桁2の上フランジ14の上面
4と第2フランジ11との間に生ずる摩擦を減
少させ、プレストレスに応じて第2フランジ1
1が相対的に摺動し易くなるようにする。
(6) If necessary, use a vibrator 8 to vibrate the concrete slab 1 while repeatedly moving it from the end of the girder toward the midpoint of the span, to loosen the upper flange 14 of the steel girder 2 during pre-stressing. The friction generated between the upper surface 4 and the second flange 11 is reduced, and the second flange 1 is
1 so that it can slide relatively easily.

(7) 上述した振動の作用効果によつてPC鋼材の
引張力が減少して緩みが生ずる度毎に、再度加
力して所定の引張力を維持する。
(7) Every time the tensile force of the prestressing steel material decreases due to the effect of the vibration described above and loosens, apply force again to maintain the predetermined tensile force.

(8) PC鋼材に導入するプレストレスが予想の引
張力を打消すに必要な所定の値に達して安定し
たときには、必要なプレストレツシングが完了
したのであるから、すべての高力ボルトを本締
めして完全に固定した後に、すべてのシース5
内にモルタルを注入して、床版コンクリート1
全体を隙間なく硬化させる。
(8) When the prestressing introduced into the prestressing steel reaches the predetermined value required to cancel the expected tensile force and becomes stable, the necessary prestressing has been completed, and all high-strength bolts should be After tightening and fully securing all sheaths 5
Inject mortar into the floor slab concrete 1
Harden the whole thing without any gaps.

(発明の効果) 以上の説明から明らかなように、本発明の鋼合
成桁は、引張力を加えた後のプレストレス床版コ
ンクリートのフランジと鋼桁の上フランジとを高
力ボルトによつて締結してあるので、床版コンク
リートに生ずる引張応力を打消すために施すプレ
ストレツシングの加力の一部が従来のように鋼桁
の上フランジに加わることがない。
(Effects of the Invention) As is clear from the above description, the steel composite girder of the present invention connects the flange of the prestressed deck concrete after applying tensile force and the upper flange of the steel girder with high-strength bolts. Because they are fastened, a portion of the pre-stretching force applied to cancel the tensile stress generated in the concrete slab is not applied to the upper flange of the steel girder, unlike in the conventional case.

したがつて、本発明の鋼合成桁の架設工法に関
しては、床版コンクリートに施すプレストレツシ
ングを必要最小限の加力により経済的に施工する
ことができる。
Therefore, with the method of constructing a steel composite girder of the present invention, pre-stressing of concrete slabs can be carried out economically by applying the minimum necessary force.

【図面の簡単な説明】[Brief explanation of drawings]

第1図a,b,cは本発明鋼合成桁の要部の構
成例を各部についてそれぞれ示す断面図、第2図
aおよびbは従来の鋼合成桁の概略構成の例をそ
れぞれ示す側面図および各部断面図である。 1…床版コンクリート、2…鋼桁、3…ずれ止
め、4…フランジ上面、5…シース、6…高力ボ
ルト、7…コンクリート端面、8…振動機、9…
フイラ、11…第2フランジ、13…タブプレー
ト、14…上フランジ。
Figures 1a, b, and c are cross-sectional views showing examples of the main parts of the steel composite girder of the present invention, respectively, and Figures 2a and b are side views showing examples of the schematic configuration of a conventional steel composite girder, respectively. and sectional views of various parts. 1... Slab concrete, 2... Steel girder, 3... Slip prevention, 4... Flange top surface, 5... Sheath, 6... High strength bolt, 7... Concrete end face, 8... Vibrator, 9...
Filler, 11...Second flange, 13...Tab plate, 14...Upper flange.

Claims (1)

【特許請求の範囲】 1 ずれ止めを溶接したフランジ上に鋼材を内蔵
したシースおよび鉄筋を組立ててコンクリートを
打設するとともに前記鋼材に引張力を加えて形成
したプレストレス床版コンクリートの当該フラン
ジを鋼桁の上フランジ上に油脂層を介して配設
し、当該上フランジに前記フランジを高力ボルト
により締結したことを特徴とする鋼合成桁。 2 特許請求の範囲第1項記載の鋼合成桁におい
て、前記高力ボルトをトルシア型高力ボルトとし
たことを特徴とする鋼合成桁。 3 架設を完了した鋼桁の上フランジ上に、油脂
層を介し、ずれ止めを溶接したフランジを配設し
て高力ボルトにより前記上フランジに仮締めする
工程と、 前記フランジ上に鋼材を内蔵したシースおよび
鉄筋を組立ててコンクリートを打設し、床版コン
クリートを完成する工程と、 前記シースに内蔵した前記鋼材の両端を前記床
版コンクリートの端面に固定する工程と、 前記高力ボルトを本締めした後に前記シース内
にモルタルを注入する工程と を順次に施すことを特徴とする鋼合成桁の架設工
法。 4 特許請求の範囲第3項記載の架設工法におい
て、前記床版コンクリートの端面に前記シースに
内蔵した前記鋼材の両端をプレストレツシングの
後に固定するにあたり、前記鋼桁の所定の不動点
以外に位置する前記高力ボルトをすべて予め緩め
るとともに、前記床版コンクリートに振動機によ
り振動を与えながら前記シースに内蔵した前記鋼
材の両端に所定の引張力を加えることを特徴とす
る鋼合成桁の架設工法。 5 特許請求の範囲第3項または第4項記載の架
設工法において、前記高力ボルトをトルシア型高
力ボルトとしたことを特徴とする鋼合成桁の架設
工法。
[Scope of Claims] 1. A sheath with a built-in steel material and reinforcing bars are assembled on the flange to which the anti-slip is welded, and concrete is poured, and a tensile force is applied to the steel material to form the flange of prestressed slab concrete. A steel composite girder, characterized in that it is disposed on an upper flange of a steel girder via an oil layer, and the flange is fastened to the upper flange with high-strength bolts. 2. A steel composite girder according to claim 1, wherein the high strength bolt is a Torsia type high strength bolt. 3 A process of installing a flange with a slip stopper welded to it through an oil layer on the upper flange of the steel girder that has been completed and temporarily fastening it to the upper flange with high-strength bolts, and incorporating steel material on the flange. a step of assembling the sheath and reinforcing bars and pouring concrete to complete the concrete floor slab; a step of fixing both ends of the steel built in the sheath to an end face of the concrete floor slab; 1. A method for constructing a steel composite girder, comprising sequentially performing a step of injecting mortar into the sheath after tightening the sheath. 4. In the construction method as set forth in claim 3, when fixing both ends of the steel material built into the sheath to the end face of the concrete deck after pre-stretching, a fixed point other than a predetermined fixed point of the steel girder is fixed. Erection of a steel composite girder characterized by loosening all the high-strength bolts located in advance, and applying a predetermined tensile force to both ends of the steel material built in the sheath while applying vibration to the concrete floor slab with a vibrator. Construction method. 5. A construction method for a steel composite girder according to claim 3 or 4, characterized in that the high-strength bolt is a Torsia type high-strength bolt.
JP23319585A 1985-10-21 1985-10-21 Steel synthetic beam and temporary construction thereof Granted JPS6294603A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23319585A JPS6294603A (en) 1985-10-21 1985-10-21 Steel synthetic beam and temporary construction thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23319585A JPS6294603A (en) 1985-10-21 1985-10-21 Steel synthetic beam and temporary construction thereof

Publications (2)

Publication Number Publication Date
JPS6294603A JPS6294603A (en) 1987-05-01
JPH047403B2 true JPH047403B2 (en) 1992-02-10

Family

ID=16951234

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23319585A Granted JPS6294603A (en) 1985-10-21 1985-10-21 Steel synthetic beam and temporary construction thereof

Country Status (1)

Country Link
JP (1) JPS6294603A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016044679A1 (en) 2014-09-19 2016-03-24 Realityworks, Inc. Welding speed sensor

Also Published As

Publication number Publication date
JPS6294603A (en) 1987-05-01

Similar Documents

Publication Publication Date Title
US20220220734A1 (en) Panelized serrated beam assembly
JPH0932313A (en) Reinforcement method for concrete beams
JP2928475B2 (en) Precast concrete girder for composite floor slab
JPH047403B2 (en)
JP3322637B2 (en) Construction method of cast-in-place concrete slab of bridge
JPS5853286Y2 (en) Composite girder with PC precast concrete blocks in the tension section
JPH0520817Y2 (en)
JPH0426483Y2 (en)
JP2928474B2 (en) Prestressed concrete girder
JP2762906B2 (en) RC frame
JP2528435B2 (en) Prestressing reinforcement structure for structures with girders installed in parallel
JP2000038797A (en) Semi-precast floor slab
JP3276800B2 (en) Joint and connection structure of lattice reinforcement
JPH0642039A (en) Joining method of end of precast concrete beam to precast concrete girder, and joining construction thereof
JPS6133762Y2 (en)
JPS648147B2 (en)
JPS6022083Y2 (en) Connection structure of precast concrete slab
JPS5927819B2 (en) Unbonded prestressed concrete method
JP2982023B2 (en) Beam for precast assembly method
JPH0151619B2 (en)
JPH0621929Y2 (en) Reinforcement structure of bridge reinforced concrete floor slab
JP3144077B2 (en) How to join columns and beams
JPH073101B2 (en) Concrete slab composite member with shear prestress and its manufacturing method
JPH1193119A (en) Connection of precast concrete slab
JPH04141B2 (en)

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term