Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02W—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
- Y02W10/00—Technologies for wastewater treatment
- Y02W10/10—Biological treatment of water, waste water, or sewage
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Aeration Devices For Treatment Of Activated Polluted Sludge (AREA)
Description
【発明の詳細な説明】
「産業上の利用分野」
本発明は、超深層曝気槽の外管、大口径中空
杭、縦型地中自動倉庫の構造躯体等、地中深くに
埋設される地中縦型筒状構造物の施工法に関す
る。Detailed Description of the Invention "Field of Industrial Application" The present invention is applicable to materials buried deep underground, such as outer pipes of ultra-deep aeration tanks, large-diameter hollow piles, and structural frames of vertical underground automated warehouses. Concerning construction methods for medium vertical cylindrical structures.
「従来の技術と発明が解決しようとする問題点」
近年、有機系廃水の処理に、第3図に示す超深
層曝気法が採用されている。図において、イは、
超深層曝気槽を構成する地中深く埋設した外管、
ロは、該外管に内装されている小径の内管、ハ
は、汚水入口、ニは、処理水出口、ホは、返送汚
水入口、ヘは、内管へ処理用空気を、外管へ循環
開始用空気を供給するコンプレツサである。"Problems to be Solved by the Prior Art and the Invention" In recent years, the ultra-deep aeration method shown in Figure 3 has been adopted for the treatment of organic wastewater. In the figure, A is
Outer pipes buried deep underground that make up the ultra-deep aeration tank,
B is a small-diameter inner pipe built into the outer pipe, C is sewage inlet, D is treated water outlet, E is return sewage inlet, F is air for processing to the inner pipe and to the outer pipe. This is a compressor that supplies air for starting circulation.
この超深層曝気法は、生物学的処理方法であ
り、従来の活性汚泥法に比較して、
(1) 敷地面積が少ない。 This ultra-deep aeration method is a biological treatment method, and compared to the conventional activated sludge method, (1) it requires less site area;
(2) 酸素利用効率が高い。(2) High oxygen utilization efficiency.
(3) 高濃度有機排水の処理が可能。(3) Possible to treat highly concentrated organic wastewater.
(4) 汚泥発生量が少ない。(4) Less sludge generation.
(5) 臭気の発生が少ない。(5) Low odor generation.
などの特長を有しており、適用分野も、下水処
理、団地等の生活廃水処理、一般産業廃水、屎尿
処理、中水施設などと幅広く、今後の需要増が見
込まれている。また、この場合、超深層曝気槽
は、直径3〜6m、深さ50〜150mの外管を地下
に建造する必要から、品質、経済性等の面で優れ
た施工法が望まれている。It has the following characteristics, and its application fields are wide-ranging, including sewage treatment, domestic wastewater treatment in housing complexes, general industrial wastewater, human waste treatment, gray water facilities, etc., and demand is expected to increase in the future. Further, in this case, since the ultra-deep aeration tank requires an outer pipe with a diameter of 3 to 6 m and a depth of 50 to 150 m to be constructed underground, a construction method that is excellent in terms of quality, economy, etc. is desired.
従来、上記外管を地下に建造する場合、第4図
に示すように、地下掘削後、その掘削孔aへ所定
長さの鋼管b…を地上で接続しながら挿入して、
構築するか、又は、第5図に示すように、地下掘
削後、その掘削孔aへ円筒状のPCaユニツトc…
を次々に落し込み、底部から積み上げて、構築す
る方法がとられている。 Conventionally, when constructing the above-mentioned outer pipe underground, as shown in Fig. 4, after underground excavation, a predetermined length of steel pipe b is inserted into the excavated hole a while being connected above ground.
Or, as shown in Figure 5, after underground excavation, a cylindrical PCa unit c...
The method used is to drop them one after another and build them up from the bottom.
しかし、前者は、 鋼製のため不経済である。 However, the former It is uneconomical because it is made of steel.
腐蝕の進行など耐久性が低い。 Durability is low due to progress of corrosion.
などの欠点があり、後者の場合、
地下で接続するため接合部の品質確保が難し
い(水密性、強度)。In the latter case, it is difficult to ensure the quality of the joint (watertightness, strength) because it is connected underground.
大口径の場合、大型揚重機を必要とする。 Large diameters require large lifting equipment.
PCaユニツトと掘削土砂との隙間が残り、不
安定である。 A gap remains between the PCa unit and the excavated soil, making it unstable.
などの欠点がある。また、両者いずれも大口径に
適し難い欠点がある。There are drawbacks such as. Furthermore, both have the disadvantage that they are difficult to apply to large diameters.
そこで、大口径に適するものを敢えて従来技術
で施工するとすれば、第6図に示すものになるで
あろうと思われる。すなわち、所定の掘削孔aを
削孔した後()、型枠dと鉄筋籠eとを組み合
わせた状態で掘削孔a内へ挿入して設置し、(、
)、型枠dと掘削孔aの孔壁との間に泥水中で
コンクリートfを打設し()、コンクリートf
の硬化後、内部の水を抜いて型枠dを解体除去し
()、構築する。 Therefore, if we were to construct a structure suitable for large diameters using conventional technology, it would probably be as shown in FIG. 6. That is, after drilling a predetermined excavation hole a (), the formwork d and reinforcing bar cage e are inserted and installed in the excavation hole a in a combined state (,
), concrete f is poured in muddy water between formwork d and the hole wall of excavation hole a (), concrete f
After curing, the water inside is drained, the formwork d is dismantled and removed (), and the mold is constructed.
しかし、この場合にも、
型枠及び鉄筋籠を設置するときに、掘削孔の
中心からずれる可能性がある。この結果、躯体
に厚い部分と薄い部分ができて、強度的に問題
を生じる。 However, even in this case, there is a possibility that the formwork and reinforcing bar cages may be shifted from the center of the excavation hole when installing them. As a result, the structure has thick and thin sections, which poses problems in terms of strength.
コンクリートを泥水中で打設するため、コン
クリート強度に対する安全率を大きく取る必要
があり、地上(空気中)で打設する場合に比べ
て不経済である。 Since concrete is placed in muddy water, it is necessary to have a large safety factor for concrete strength, which is uneconomical compared to placing concrete on the ground (in the air).
コンクリートの打設中に孔壁がわずかでも崩
壊すると、躯体部分に土砂が混入し、強度的に
欠陥を生じると共に、止水性が失われ、所期の
機能を果たさなくなる。 If the hole wall collapses even slightly during concrete pouring, earth and sand will enter the structure, causing defects in strength, as well as loss of water-tightness and the structure not functioning as intended.
上記の場合やコンクリートにジヤンカがで
きた場合等に、補修することがほとんど不可能
である。 It is almost impossible to repair in the above cases or when jitters are formed on the concrete.
コンクリート打設後、所定の強度が発生する
までの間、水中に型枠を存置させておく必要が
あることから、型枠等の材質に特別の工夫をし
なければならない。 Since it is necessary to leave the formwork underwater until the specified strength is achieved after concrete is poured, special measures must be taken for the material of the formwork, etc.
型枠を脱型する際、足場が必要となるが、地
中深く埋設される筒状の構造物という特殊性か
ら、その足場の形式、架け方及び外し方等に特
別の配慮が必要となる。 Scaffolding is required when removing the formwork, but due to the unique nature of the cylindrical structure being buried deep underground, special consideration must be given to the type of scaffolding, how to erect it, how to remove it, etc. .
取り外した型枠資材を搬出する際、足場と躯
体との間隙が狭いため、クレーンによる吊り上
げが困難であるばかりでなく、その吊り荷のほ
ぼ真下に作業員がいることになり、危険な作業
となる。 When transporting removed formwork materials, the narrow gap between the scaffolding and the structure not only makes it difficult to lift with a crane, but also requires workers to be located almost directly below the hoisted material, making the work dangerous. Become.
などの欠点がある。There are drawbacks such as.
本発明は、これらのことを考慮し、施工精度、
品質、作業性、安全性、工期、コスト、その他あ
らゆる面で優れた工法を提供しようとするもので
ある。 The present invention takes these things into account and improves construction accuracy,
The aim is to provide construction methods that are superior in quality, workability, safety, construction period, cost, and all other aspects.
「問題点を解決するための手段」
本発明は、地下掘削後、地上に筒状の型枠を装
備させた架台を設けて、その型枠によりコンクリ
ート躯体を順次に打継ぎ成形し硬化させては掘削
孔内へ繰り込み、この際、掘削孔内の泥水による
浮力を利用してコンクリート躯体の重量を適宜に
支え、躯体全長を孔内に設置した後、コンクリー
ト躯体と掘削孔孔壁との間にグラウトを注入し硬
化させることを特徴とする。"Means for Solving the Problems" The present invention involves, after underground excavation, installing a pedestal equipped with a cylindrical form on the ground, and using the form to successively pour-form and harden the concrete frame. is carried into the borehole, and at this time, the weight of the concrete frame is appropriately supported using the buoyancy of the muddy water in the borehole, and after the entire length of the frame is installed in the hole, the gap between the concrete frame and the borehole wall is It is characterized by injecting grout into and hardening it.
「作用」
如上の施工により、現場における鉄筋コンクリ
ート躯体の迅速な構築が可能となる。``Operation'' The construction described above makes it possible to quickly construct a reinforced concrete frame on site.
「実施例」
その1
第1図は、本発明の一実施例であり、施工の手
順を示すものである。これをその順序に従つて説
明すると、次の通りである。 "Example" Part 1 FIG. 1 shows an example of the present invention and shows the construction procedure. This is explained in order as follows.
所定の深さまで掘削を行つて、掘削孔1を形
成し、孔壁保護のため掘削孔上部にケーシング
2を設置し、かつ、掘削孔周辺に仮設の土間コ
ンクリート3を打設する。 Excavation is performed to a predetermined depth to form an excavated hole 1, a casing 2 is installed on the upper part of the excavated hole to protect the hole wall, and a temporary earthen floor concrete 3 is placed around the excavated hole.
掘削孔1の上部に作業用の架台4を設置す
る。この架台は、配筋、型枠建込み、コンクリ
ート打設、型枠解体及びその他の作業を行うた
めの足場として使用すると同時に、鉄筋コンク
リートの躯体を施工中に上下移動させたり、仮
固定する装置を備える架台としても使用するも
のである。 A work platform 4 is installed above the excavation hole 1. This frame is used as a scaffold for reinforcing reinforcement, erecting formwork, pouring concrete, dismantling formwork, and other tasks, and at the same time is used as a device to move the reinforced concrete frame up and down during construction, and to temporarily fix it. It can also be used as a pedestal.
次に、掘削孔1の周囲に3本以上のグラウト
用パイプ5…を設置する。このグラウト用パイ
プは、所定の鉄筋コンクリートの躯体ができ上
つた後に、躯体と孔壁の間をモルタル又はセメ
ントミルクでグラウトするためのパイプである
が、躯体を順次沈めていくときのガイドレール
を役目を果たすものである。 Next, three or more grouting pipes 5 are installed around the excavated hole 1. This grouting pipe is a pipe for grouting the space between the frame and the hole wall with mortar or cement milk after the specified reinforced concrete frame is completed, but it also serves as a guide rail when the frame is sunk one by one. It fulfills the following.
予め別の場所で製作された鉄筋コンクリート
の躯体6の底部を掘削孔1の上部に挿入し、孔
内の泥水7に浮かせる。その躯体6の底部の下
面には浮力調整用エアバツグ8を付設してお
き、その躯体底部の重量に比べて浮力が小さい
場合、エアバツグに空気を送つて浮力を調整
し、支持させる架台4への負担を小さくする。 The bottom part of a reinforced concrete frame 6 previously manufactured at another location is inserted into the upper part of the excavated hole 1 and floated on muddy water 7 in the hole. A buoyancy adjustment air bag 8 is attached to the lower surface of the bottom of the frame 6, and when the buoyancy is small compared to the weight of the bottom of the frame, air is sent to the air bag to adjust the buoyancy, and the buoyancy is adjusted to the pedestal 4 for support. Reduce the burden.
躯体6の底部が架台4に仮固定された状態
で、該底部の上に引き続き配筋9を施し、型枠
10を建込んで、コンクリート打設(打継ぎ)
を行う。この段階で、重量の増加に伴いエアバ
ツグ8に更に空気を送り込むことによつて浮力
を増大させて、全体の重量のバランスを保つよ
うにする。なお、図中、4′は、作業用吊り足
場である。 With the bottom of the frame 6 temporarily fixed to the frame 4, reinforcing bars 9 are placed on top of the bottom, formwork 10 is erected, and concrete is poured (concrete pouring).
I do. At this stage, as the weight increases, more air is fed into the air bag 8 to increase the buoyancy and maintain the overall weight balance. In addition, in the figure, 4' is a suspended scaffold for work.
所定の型枠存置期間を経た後に、型枠を解体
する。このときコンクリートの仕上り状態を確
認し、ジヤンカ等がある場合、この時点で十分
な補修を行う。また、コンクリートの打継ぎ面
の処理等もこの段階で行う。 After a predetermined retention period of the formwork, the formwork is dismantled. At this time, check the finished condition of the concrete, and if there are any jitters, etc., make sufficient repairs at this point. In addition, treatment of the concrete pouring surface will also be done at this stage.
次に、所定の位置まで躯体6を沈める。この
ときエアバツグ8の空気を抜いて浮力を減じ、
エアバツグの空気を全て抜いても浮力が大きい
場合は躯体6の内部に注水11することによつ
て、重量のバランスを保つようにする。所定の
位置まで沈めたら再び躯体6を架台4に仮固定
する。 Next, the frame 6 is lowered to a predetermined position. At this time, let the air out of the air bag 8 to reduce the buoyancy.
If the buoyancy is large even after all the air is removed from the airbag, water is injected 11 into the body 6 to maintain the weight balance. After sinking to a predetermined position, the frame 6 is temporarily fixed to the frame 4 again.
以下同様の作業を繰り返し、所定長さの躯体
6を掘削孔1内に設置する。 Thereafter, similar operations are repeated to install the frame 6 of a predetermined length into the excavated hole 1.
最後に、ケーシング2を引き抜き、グラウト
用パイプ5…を通して躯体6の掘削孔1の孔壁
との間にグラウト12を注入(裏込め)しつつ
そのグラウト用パイプ5…を逐次引き抜き、掘
削孔1の上部まで注入し、硬化させて、完成す
る。 Finally, the casing 2 is pulled out, and the grout 12 is injected (backfilled) between the hole wall of the excavated hole 1 of the frame 6 through the grout pipes 5... and the grout pipes 5... are successively pulled out. Inject to the top and harden to complete.
その2
第2図は、本発明の他の実施例である。この場
合は、前例において、乃至の工程が異なるこ
と及び鉄筋コンクリートの躯体6に適数の躯体支
持用PC鋼線14…を用いることを除き、前例と
ほぼ同一である。そこで、前例の乃至の工程
に相当する図示の′乃至′の工程につき説明す
る。 Part 2 FIG. 2 shows another embodiment of the present invention. This case is almost the same as the previous example, except that the steps are different and that an appropriate number of PC steel wires 14 for supporting the frame are used for the reinforced concrete frame 6. Therefore, the illustrated steps ``to'', which correspond to the steps ``to'' in the previous example, will be explained.
′ スライデイングフオーム用の型枠15を架
台4に設置し、既にでき上つている鉄筋コンク
リート躯体6の底部の立上り部分に型枠15を
合わせる。また、架台4に躯体支持用PC鋼線
14…を挿通させ保持する躯体上下移動用セン
ターホールジヤツキ16…を設ける。' A formwork 15 for the sliding form is installed on the pedestal 4, and the formwork 15 is aligned with the rising part of the bottom of the already completed reinforced concrete frame 6. Further, center hole jacks 16 for vertically moving the frame are provided in the frame 4 for inserting and holding PC steel wires 14 for supporting the frame.
′ その型枠15内に鉄筋9を配筋し、コンク
リートを打設し、打継ぐ。この際、前例と同様
に、重量の増加に伴いエアバツグ8に更に空気
を供給し、重量のバランスをとる。' Reinforcement bars 9 are arranged within the formwork 15, concrete is poured, and concrete is poured. At this time, as in the previous example, as the weight increases, more air is supplied to the air bag 8 to balance the weight.
′ 次いで、型枠15のスライデイングを行う。
ただし、一般的なスライデイングフオーム工法
では、型枠を順次に上昇させて行くが、この場
合は、躯体6を順次下降させるものとする。こ
の下降は、エアバツグ8の空気の排出とセンタ
ーホールジヤツキ16…の作動とで行い、必要
なときは、前例と同様に、躯体6に注水を行
う。' Next, the formwork 15 is slid.
However, in the general sliding form construction method, the formwork is raised one after another, but in this case, the frame 6 is lowered one after another. This lowering is performed by discharging the air from the air bag 8 and operating the center hole jack 16, and when necessary, water is injected into the frame 6 as in the previous example.
他の工程については前例による。 For other processes, precedents apply.
「発明の効果」
本発明によれば、
(i) 構造躯体をコンクリートで造り、鋼管を用い
ないので、経済的であり、腐蝕の心配がない。"Effects of the Invention" According to the present invention, (i) The structural frame is made of concrete and no steel pipes are used, so it is economical and there is no fear of corrosion.
(ii) 全ての作業を地上で行うので、精度の良い施
工ができる。(ii) Since all work is done on the ground, construction can be carried out with high precision.
(iii) コンクリートの成形を地上で行うので、仕上
り状態を確認でき、場合によつては補修等も行
うことができる。(iii) Since the concrete is formed on the ground, the finished condition can be checked and repairs can be made in some cases.
(iv) 地上の空気中でコンクリート打設を行うの
で、泥水中で打設する場合に比べて、構造設計
上、より大きな許容圧縮応力度を採用すること
ができ、経済的である。(iv) Since concrete is placed in the air above the ground, it is possible to adopt a larger allowable compressive stress level in the structural design, compared to when concrete is placed in muddy water, which is economical.
(v) コンクリート打設に当たり型枠を水中に長期
間存置しないので、一般的な木製型枠とするこ
とができ、また、何回も転用することが可能で
経済的である。(v) Since the formwork is not left underwater for a long period of time when concrete is poured, it is possible to use a general wooden formwork, and it is economical because it can be reused many times.
(vi) 型枠をスライデイングフオームタイプとする
こともでき、その場合には、型枠の建込み、解
体作業がないので、作業工程を短縮することが
できる。(vi) The formwork can be of the sliding form type, in which case there is no need to erect and dismantle the formwork, so the work process can be shortened.
(vii) 打設したコンクリートは一体となつて構造躯
体を構成するので、止水性の高い躯体を造るこ
とができ、特に、縦型地中自動倉庫などの内部
空間を水のない状態で利用する場合に適してい
る。(vii) Since the poured concrete is integrated to form a structural frame, it is possible to construct a frame with high water-stop properties, which is especially useful for using the internal space of vertical underground automated warehouses without water. suitable for the case.
(viii) コンクリート躯体を造りながら、でき上つた
部分を順次掘削孔内に沈めて行き、その際、泥
水による浮力を利用するので、大きな揚重機な
どが不要であり、上下移動用の装置や仮固定す
るための装置が軽微なものですみ、経済的であ
る。(viii) While constructing the concrete frame, the completed parts are sunk into the excavation hole one by one, using the buoyancy of muddy water, so there is no need for large lifting machines, and there is no need for vertical movement equipment or temporary It is economical because only a small fixing device is required.
(ix) 浮力の利用に当たり、躯体内部へ注水とエア
バツクとを採用すれば、躯体の自重と浮力との
バランスを逐次調整できる。(ix) When using buoyancy, if water injection and air bags are used inside the structure, the balance between the weight of the structure and buoyancy can be adjusted sequentially.
(x) グラウト注入用のパイプをコンクリート躯体
の沈め込みのためのガイドレールとして利用す
ることにより、躯体が掘削孔の孔壁に接触して
孔壁を破壊することを防止でき、躯体の立て入
れ精度の確保に役立たせることができる。(x) By using the grouting pipe as a guide rail for sinking the concrete structure, it is possible to prevent the structure from coming into contact with the hole wall of the excavation hole and destroying the hole wall. This can help ensure accuracy.
(xi) 掘削孔内に設置した躯体と孔壁との隙間に
グラウトを注入し硬化させるので、全体として
一体化し、地中に定着した安定で、強固で、高
品質で、耐久性の高い躯体を造ることができ
る。(xi) Grout is injected into the gap between the framework installed in the borehole and the hole wall and hardened, resulting in a stable, strong, high-quality, and durable framework that is integrated as a whole and is anchored in the ground. can be built.
(xii) 従来の欠点を一掃できる。(xii) Traditional drawbacks can be wiped out.
などの効果を奏し、所期の目的を達成できる。It has the following effects and achieves the intended purpose.
第1図、第2図は、本発明の実施例を示し、第
1図は、一例の工程説明図、第2図は、他の例の
工程説明図、第3図は、超深層曝気法の説明図、
第4図、第5図、第6図は、それぞれ従来の施工
法を示す説明図である。
1……掘削孔、2……ケーシング、3……土間
コンクリート、4……架台、5……グラウト用パ
イプ、6……躯体、7……泥水、8……浮力調整
用エアバツグ、9……配筋、10……型枠、11
……注水、12……グラウト、14……PC鋼線、
15……スライデイングフオーム用型枠、16…
…センターホールジヤツキ。
Fig. 1 and Fig. 2 show examples of the present invention, Fig. 1 is a process explanatory diagram of one example, Fig. 2 is a process explanatory diagram of another example, and Fig. 3 is an ultra-deep aeration method. An explanatory diagram of
FIG. 4, FIG. 5, and FIG. 6 are explanatory views showing conventional construction methods, respectively. 1... Excavation hole, 2... Casing, 3... Concrete floor, 4... Frame, 5... Grout pipe, 6... Frame, 7... Mud water, 8... Air bag for buoyancy adjustment, 9... Reinforcement, 10...Formwork, 11
... Water injection, 12 ... Grout, 14 ... PC steel wire,
15...Formwork for sliding form, 16...
...Center hole jack.
Claims (1)
架台を設けて、その型枠によりコンクリート躯体
を順次に打継ぎ成形し硬化させては掘削孔内へ繰
り込み、この際、掘削孔内の泥水による浮力を利
用してコンクリート躯体の重量を適宜に支え、躯
体全長を孔内に設置した後、コンクリート躯体と
掘削孔孔壁との間にグラウトを注入し硬化させる
ことを特徴とする地下縦型筒状構造物の施工法。1 After underground excavation, a pedestal equipped with a cylindrical formwork is installed on the ground, and the concrete frame is sequentially poured and formed using the formwork, hardened, and rolled into the excavation hole. After the entire length of the concrete structure is installed in the hole, the weight of the concrete structure is appropriately supported using the buoyancy of muddy water, and grout is injected between the concrete structure and the wall of the borehole and hardened. Construction method for vertical cylindrical structures.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP60280520A JPS62242022A (en) | 1985-12-12 | 1985-12-12 | Method for constructing underground vertical-type cylindrical structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP60280520A JPS62242022A (en) | 1985-12-12 | 1985-12-12 | Method for constructing underground vertical-type cylindrical structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS62242022A JPS62242022A (en) | 1987-10-22 |
| JPH0510448B2 true JPH0510448B2 (en) | 1993-02-09 |
Family
ID=17626247
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP60280520A Granted JPS62242022A (en) | 1985-12-12 | 1985-12-12 | Method for constructing underground vertical-type cylindrical structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS62242022A (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS63147070A (en) * | 1986-12-09 | 1988-06-20 | 石川島播磨重工業株式会社 | How to build an underground tank |
| DE102009020517B3 (en) * | 2009-05-08 | 2010-10-21 | Herrenknecht Ag | Method of constructing an underground structure |
| CN111550268A (en) * | 2020-05-27 | 2020-08-18 | 李军 | Self-propelled bridge main body for inverted arch trestle trolley |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5413604A (en) * | 1977-07-01 | 1979-02-01 | Kajima Corp | Method of construction of closely building casing |
| JPS56105020A (en) * | 1980-01-24 | 1981-08-21 | Kajima Corp | Method of construction of concrete columnar body utilizing buoyancy |
-
1985
- 1985-12-12 JP JP60280520A patent/JPS62242022A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS62242022A (en) | 1987-10-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111005387A (en) | Deep foundation pit prestress support replacement support construction method | |
| CN116446434A (en) | Construction method of open caisson with water-rich sand layer | |
| CN109518711B (en) | A catheter rack foundation with bifurcated catheter legs and a construction method thereof | |
| CN107503355B (en) | Externally-arranged rear-inserted steel type double-row pile foundation pit supporting system and construction method thereof | |
| CN109056808A (en) | Stake and steel pipe column construction method in a kind of subway station | |
| JPH0510448B2 (en) | ||
| CN111042173B (en) | Quicksand layer open caisson construction method | |
| JP2001241287A (en) | Construction method of shaft, assembly method of structural body used for construction method, and assembly device used for assembly method | |
| AU2019101512B4 (en) | A method of constructing a column, a subterranean structure, and a structure made from the method. | |
| CN114000514A (en) | Construction method of deep foundation pit angle support pile column component | |
| JPS62153488A (en) | Construction of underground vertical cylindrical structure | |
| JP2006194031A (en) | Pillar construction method | |
| JP2996113B2 (en) | How to build a shaft | |
| JP6792239B2 (en) | Scuttling prevention device for steel pipe piles and scuttling prevention method | |
| CN219410886U (en) | Light combined upright post structure for water area foundation pit engineering | |
| JP7655871B2 (en) | Method for backfilling boreholes, method for treating underground structures, and method for removing existing piles | |
| JP7790936B2 (en) | How to build underground structures | |
| JP2025022475A (en) | How to construct a structural column | |
| JPH059945A (en) | Underground structure construction method | |
| JPH10152853A (en) | Construction method of underground structure and structural member used therefor | |
| JP3815258B2 (en) | How to build a true pillar | |
| CN120042216A (en) | Construction method for detecting and repairing well in top pipe well | |
| IT9020759A1 (en) | UNDERWALL PROCESS | |
| JP2565457B2 (en) | Structure pillar construction method | |
| JPH0511170B2 (en) |