JPH0523992B2 - - Google Patents
[go: Go Back, main page]

JPH0523992B2 - - Google Patents

Info

Publication number
JPH0523992B2
JPH0523992B2 JP59032044A JP3204484A JPH0523992B2 JP H0523992 B2 JPH0523992 B2 JP H0523992B2 JP 59032044 A JP59032044 A JP 59032044A JP 3204484 A JP3204484 A JP 3204484A JP H0523992 B2 JPH0523992 B2 JP H0523992B2
Authority
JP
Japan
Prior art keywords
deck
platform
section
barge
dock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP59032044A
Other languages
Japanese (ja)
Other versions
JPS60176883A (en
Inventor
Isao Uchida
Yoshio Matsumoto
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
Ishikawajima Harima Heavy Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ishikawajima Harima Heavy Industries Co Ltd filed Critical Ishikawajima Harima Heavy Industries Co Ltd
Priority to JP59032044A priority Critical patent/JPS60176883A/en
Publication of JPS60176883A publication Critical patent/JPS60176883A/en
Publication of JPH0523992B2 publication Critical patent/JPH0523992B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)
  • Ship Loading And Unloading (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は大型双胴型のクレーン船、その他の海
上構造物の建造方法に関するもので、特に、ドツ
ク幅を超える大きさの双胴型構造物をドツク内と
海上で建造する方法に関するものである。尚、双
胴型構造物とは、2つの浮体を甲板部あるいはプ
ラツトホーム部で連結した構造物のことである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method for constructing a large twin-hulled crane ship and other offshore structures, and particularly relates to a method for constructing a large twin-hulled crane ship and other offshore structures. It's about how things are built in docks and at sea. Incidentally, a twin-hulled structure is a structure in which two floating bodies are connected by a deck section or a platform section.

[従来技術] ドツク幅を超える大きさの双胴型構造物を建造
しようとする場合、従来、次のような方法があつ
た。すなわち、 大型の構造物を数ブロツクに分割し、海上で
フローテイングクレーンを使用してブロツクを
組み立てて行き構造物を建造する方法、 隣接する2つのドツクを使用し、両ドツクを
跨ぐようにして建造する方法、 双胴部を沈降させてその上方位置に甲板部又
はプラツトホームを浮かせた後、再び双胴部を
浮上させて組み立て建造する方法 等である。
[Prior Art] When attempting to construct a twin-hulled structure with a size exceeding the width of a dock, the following methods have conventionally been used. In other words, the structure is constructed by dividing a large structure into several blocks and assembling the blocks using a floating crane at sea, or by using two adjacent docks and straddling both docks. There are two methods of construction: the twin hull is lowered, the deck or platform is floated above it, and then the twin hull is floated again to be assembled and constructed.

しかし、上記の方法は、フローテイングクレ
ーンを使用するものであり、このフローテイング
クレーンで各ブロツクを組み立てるときの位置決
めが困難であり、又、各ブロツクを溶接するため
溶接個所が増え、それだけ危険業も多くなり、全
体的にコスト高となる欠点がある。
However, the above method uses a floating crane, and it is difficult to position each block when assembling it with this floating crane. Also, since each block is welded, the number of welding points increases, which makes the work more dangerous. This has the drawback of increasing the overall cost.

の方法は、2つのドツクが隣接していること
が必要で設備上に問題がある。
This method requires that the two docks be adjacent to each other, which poses a problem in terms of equipment.

の方法は、双胴部を沈めたり浮かせたりする
ため、推進の浅いところでは実施できない。
This method requires the twin fuselage to sink or float, so it cannot be carried out in shallow areas.

[発明の目的] 本発明は、ドツク幅を超える双胴型構造物をド
ツク内で大部建造して海上で別の浮体を使用して
最終的に建造することによつて従来のフローテイ
ングクレーンを不要にし、且つ海上における溶接
等の作業を最少にし、容易の建造することを目的
とする。
[Object of the Invention] The present invention improves the construction of a conventional floating crane by constructing a twin-hulled structure that exceeds the width of the dock, mostly within the dock, and finally constructing it at sea using a separate floating structure. The purpose is to eliminate the need for welding, minimize work such as welding at sea, and simplify construction.

[発明の構成] 本発明の双胴型構造物の建造方法は、構成物の
浮力を有する双胴部を、ドツク幅に合わせて対峙
間隔を狭めてドツク内に位置させ、上記並置され
た2つの胴部上に甲板部あるいはプラツトホーム
部を載置させるに際し、片方の胴部と甲板部ある
いはプラツトホーム部とは正規の位置で組み立
て、他方の胴部は甲板部あるいはプラツトホーム
部に対し正規位置より内側にずらした状態で仮付
してドツク内で建造し、しかる後、ドツク内でそ
のまま浮上させて出渠させ、海上にてバージ等を
使用して甲板部あるいはプラツトホーム部を支持
させた後、上記正規位置より内側にずらして仮付
けした他方の胴部を正規位置へ移動して本付け
し、双胴型構造物を建造する。
[Structure of the Invention] The method for constructing a twin-hulled structure of the present invention involves positioning the buoyant twin-hulled portions of the structure in a dock with a narrowing distance between them in accordance with the width of the dock, and When placing a deck or platform on two bodies, one body and the deck or platform should be assembled in their normal position, and the other body should be assembled inside the normal position with respect to the deck or platform. The ship is constructed in a dock by temporarily attaching it in a shifted position, and then floated in the dock as it is and docked. After supporting the deck part or platform part at sea using a barge etc., the above-mentioned The other body, which has been temporarily attached by shifting it inward from the normal position, is moved to the normal position and permanently attached to construct the twin-body structure.

以下、本発明の実施例を図面を参照して説明す
る。
Embodiments of the present invention will be described below with reference to the drawings.

[実施例] 実施例 1 第1図乃至第3図は本発明の一実施例を示すも
ので、ドツク内でドツク幅を超える大きさの双胴
型構造物を建造するに際し、先ず、第1図に示す
如く、浮力を有する双胴部1a,1bのうち、片
側の胴部1bを正規取付位置よりも内側にずらし
てドツク2の幅に合わせた対峙間隔とし、ドツク
2内に据え付けた架台3上に、上記対峙間隔を狭
めた胴部1aと1bを載置させる。次に、上記胴
部1aと1bを、途中に仮棧5を組み入れた梁4
で連結して強度を高めるようにすると共に、上記
胴部1aと1b上に亘りドツク幅よりも広い幅の
甲板部あるいはプラツトホーム部6を載せ、該甲
板部あるいはプラツトホーム部6と胴部1aとは
正規の位置で固定し、甲板部あるいはプラツトホ
ーム部6と胴部1bとは正規位置より内側にずれ
た位置で仮付けする。
[Example] Example 1 Figures 1 to 3 show an example of the present invention. When constructing a twin-hulled structure larger than the width of the dock, first, the first As shown in the figure, one of the twin body parts 1a and 1b having buoyancy is shifted inward from the normal mounting position to create a facing interval that matches the width of the dock 2, and a frame is installed inside the dock 2. 3, the body parts 1a and 1b with the above-mentioned facing interval narrowed are placed. Next, the body parts 1a and 1b are connected to a beam 4 with a temporary frame 5 incorporated therein.
In addition, a deck section or platform section 6 having a width wider than the dock width is placed over the body sections 1a and 1b, and the deck section or platform section 6 and the body section 1a are It is fixed at the normal position, and the deck section or platform section 6 and the body section 1b are temporarily attached at a position shifted inward from the normal position.

次に、ドツク2に水を張つて双胴部1a,1b
の浮力により出渠させ、海上にて別のバージ7を
双胴間に入れ、該バージ7にて甲板部あるいはプ
ラツトホーム部6を支持させ、次いで、第2図に
示す如く、バージ7を作業足場として仮棧5を取
り外し、胴部1aと1bとの連結を断ち切る。
Next, fill water in the dock 2 and
Another barge 7 is inserted between the twin hulls at sea, and the deck section or platform section 6 is supported by the barge 7. Then, as shown in Fig. 2, the barge 7 is placed on a working scaffold. As a result, the temporary frame 5 is removed and the connection between the body parts 1a and 1b is cut off.

次に、胴部1bと甲板部あるいはプラツトホー
ム部6との仮付けを外して該胴部1bを浮力の調
整で僅かに沈めるか、あるいはバージ7にて甲板
部6を持ち上げることにより甲板部6と胴部1b
との間に隙間δを作つて胴部1bが自由に動ける
状態にし、この胴部1bを図示しないウインチ等
で正規の取付位置まで移動させた後、該胴部1b
の上端と甲板部6とを再び当接させ本付けを行
う。しかる後、両側の胴部1aと1bの梁4間よ
り取り外した仮棧部に正規の梁8を挿入し取り付
けて建造を終了する。9はパージ7の上端に取り
付けたコロである。なお、甲板部を持ち上げるの
みの場合はコロは不要である。
Next, either remove the temporary attachment between the trunk 1b and the deck or platform 6 and lower the trunk 1b slightly by adjusting the buoyancy, or lift the deck 6 with the barge 7. Torso 1b
A gap δ is created between the body part 1b so that the body part 1b can move freely, and after moving this body part 1b to the normal mounting position using a winch or the like (not shown), the body part 1b is
The upper end of the deck portion 6 is brought into contact with the deck portion 6 again to perform the final attachment. Thereafter, the regular beams 8 are inserted and attached to the temporary beams removed from between the beams 4 of the body parts 1a and 1b on both sides, and the construction is completed. 9 is a roller attached to the upper end of the purge 7. Note that rollers are not required if only the deck part is to be lifted.

実施例 2 第4図は本発明の他の実施例を示すもので、ド
ツク内での作業が終了して出渠した後、海上にて
移動側の胴部1bの外側にコロ9付きのバージ1
0を位置させて該バージ10のコロ部で甲板部6
を支持させ、該バージ10にて甲板部6を浮かせ
た状態でパージ10とともに胴部1bを正規の取
付位置まで移動させ、しかる後、胴部1bと甲板
部6とを本付けして建造するようにする。この
際、バージ10は胴部1bに固定してもよいし、
離しておいてもよい。
Embodiment 2 FIG. 4 shows another embodiment of the present invention, in which a barge with rollers 9 is attached to the outside of the body 1b on the moving side at sea after the work in the dock is completed and the barge is docked. 1
0, and the deck part 6 with the roller part of the barge 10.
is supported, and with the deck part 6 floating on the barge 10, the body part 1b is moved together with the purge 10 to the regular installation position, and then the body part 1b and the deck part 6 are permanently attached and constructed. do it like this. At this time, the barge 10 may be fixed to the body 1b, or
You can leave them apart.

実施例 3 第5図は本発明の他の実施例を示すもので、第
4図の場合と同様に海上にて胴部1bを移動させ
る方法を更に変えたものであり、移動側の胴部1
b上に、ジヤツキ12及びコロ13を備えた架台
11を備えた支持装置を載せ、ジヤツキ12にて
甲板部6を胴部1bの上端より少し持ち上げ、こ
の状態でコロ13を転動させながら胴部1bを正
規の取付位置まで移動させ、次いでジヤツキ12
を短縮させて甲板部6を胴部1b上端に載せた
後、本付けして建造する。この実施例における架
台11の形状は図示以外のものでもよい。
Embodiment 3 FIG. 5 shows another embodiment of the present invention, in which the method of moving the trunk 1b on the sea is further changed as in the case of FIG. 1
A support device including a frame 11 equipped with jacks 12 and rollers 13 is placed on top b, and the deck section 6 is slightly lifted from the upper end of the body section 1b using the jacks 12. In this state, while rolling the rollers 13, the body is Move the part 1b to the proper mounting position, then tighten the jack 12.
After shortening the deck part 6 and placing it on the upper end of the body part 1b, the main body part 1b is attached and constructed. The shape of the pedestal 11 in this embodiment may be other than that shown.

実施例 4 第6図は本発明の更に他の実施例を示すもの
で、海上にて甲板部6を支持するバージとして中
空型バージ14を使用し、該バージ14の中空部
に移動側の胴部1bを位置させてバージ14上端
のコロ9を介して甲板部6を支持させるように
し、バージ14にて甲板部6を持ち上げてバージ
14とともに胴部1bを正規位置まで移動させ、
胴部1bを甲板部6に本付けして建造するもので
ある。なお、中空型バージ14は2分割して2台
のバージとして使用してもよく、コロ9に代えて
滑り易いものを使用してスライドさせるようにし
てもよい。
Embodiment 4 FIG. 6 shows still another embodiment of the present invention, in which a hollow barge 14 is used as a barge to support the deck section 6 at sea, and a moving side trunk is installed in the hollow part of the barge 14. The part 1b is positioned so that the deck part 6 is supported via the rollers 9 at the upper end of the barge 14, the deck part 6 is lifted by the barge 14, and the body part 1b is moved together with the barge 14 to the normal position,
It is constructed by attaching the trunk section 1b to the deck section 6. Note that the hollow barge 14 may be divided into two parts and used as two barges, and instead of the rollers 9, a slippery material may be used to make it slide.

実施例 5 第7図は本発明の更に他の実施例を示すもの
で、海上にて最初に第7図Aに示す如くバージ7
を移動側胴部1bの外側に配備し、甲板部6を持
ち上げて胴部1bを正規位置の方へ移動させ、バ
ージ7上のコロ9が甲板部6から外れる位置に来
ると、バージ7を胴部1bの内側へ移して再び甲
板部6を持ち上げて胴部1bを正規位置へ移動さ
せ、該胴部1bと甲板部6とを本付けして建造す
る。
Embodiment 5 FIG. 7 shows yet another embodiment of the present invention, in which a barge 7 is first installed at sea as shown in FIG. 7A.
is placed on the outside of the movable body part 1b, the deck part 6 is lifted and the body part 1b is moved to the normal position, and when the rollers 9 on the barge 7 come to a position where they are removed from the deck part 6, the barge 7 is moved. The body part 1b is moved to the inside of the body part 1b, the deck part 6 is lifted again, the body part 1b is moved to the normal position, and the body part 1b and the deck part 6 are permanently attached to construct the body.

[発明の効果] 以上述べた如く、本発明の建造方法によれば次
のような優れた効果を奏し得る。
[Effects of the Invention] As described above, according to the construction method of the present invention, the following excellent effects can be achieved.

(i) 所有ドツク設備を超える大型の双胴型構造物
の建造が容易に可能となる。
(i) It becomes possible to easily construct a large twin-hulled structure that exceeds the existing dock equipment.

(ii) 海上における溶接等の作業を最小にできて安
全性が向上すると共に品質も向上する。
(ii) Work such as welding at sea can be minimized, improving safety and quality.

(iii) フローテイングクレーン等が不要になつて設
備費を低減できる。
(iii) Floating cranes, etc. are no longer required, reducing equipment costs.

(iv) 水深にあまり影響されることなく実施でき
る。
(iv) It can be carried out without much influence from water depth.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第3図は本発明の建造方法の一実施
例を示す建造工程を示す正面図、第4図乃至第7
図A,Bはいずれも本発明の建造方法の他の実施
例を示す正面図である。 1a,1bは胴部、2はドツク、6は甲板部あ
るいはプラツトホーム部、7はバージ、8は梁、
10はバージ、11は架台、14は中空型バージ
を示す。
1 to 3 are front views showing the construction process showing an embodiment of the construction method of the present invention, and FIGS. 4 to 7
Figures A and B are front views showing other embodiments of the construction method of the present invention. 1a and 1b are the trunk, 2 is the dock, 6 is the deck or platform, 7 is the barge, 8 is the beam,
10 is a barge, 11 is a pedestal, and 14 is a hollow barge.

Claims (1)

【特許請求の範囲】[Claims] 1 2つの浮体を甲板部あるいはプラツトホーム
部で連結して成る双胴型構造物の建造方法におい
て、浮体としての2つの胴部のうち、片側の胴部
を甲板部あるいはプラツトホーム部への正規の取
付位置よりも内側にずらしてドツク幅に合わせて
ドツク内に設置し、次いで、ドツクにて甲板部あ
るいはプラツトホーム部と一方の胴部とを正規位
置で固定すると共に他方の胴部と甲板部あるいは
プラツトホーム部とを仮付けした後、海上へ移し
て海上に浮かべたバージや他方の胴部に取付けた
支持装置で甲板部あるいはプラツトホーム部を支
持し、次に、仮付けした胴部を正規位置へ移動し
て甲板部あるいはプラツトホーム部へ本付けして
建造することを特徴とする双胴型構造物の建造方
法。
1. In the construction method of a twin-hulled structure consisting of two floating bodies connected by a deck or platform, one of the two bodies as a floating body is properly attached to the deck or platform. Shift it inward from the position and install it in the dock according to the width of the dock, then fix the deck section or platform section and one body section in the correct position with the dock, and connect the other body section and the deck section or platform section. After temporarily attaching the parts, move it to the sea and support the deck part or platform part with a support device attached to the barge floating on the sea or the other body part, and then move the temporarily attached part to the normal position. A method for constructing a twin-hulled structure, characterized in that the structure is constructed by attaching the structure to the deck or platform.
JP59032044A 1984-02-22 1984-02-22 Construction method of catamaran type structure Granted JPS60176883A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP59032044A JPS60176883A (en) 1984-02-22 1984-02-22 Construction method of catamaran type structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP59032044A JPS60176883A (en) 1984-02-22 1984-02-22 Construction method of catamaran type structure

Publications (2)

Publication Number Publication Date
JPS60176883A JPS60176883A (en) 1985-09-10
JPH0523992B2 true JPH0523992B2 (en) 1993-04-06

Family

ID=12347863

Family Applications (1)

Application Number Title Priority Date Filing Date
JP59032044A Granted JPS60176883A (en) 1984-02-22 1984-02-22 Construction method of catamaran type structure

Country Status (1)

Country Link
JP (1) JPS60176883A (en)

Also Published As

Publication number Publication date
JPS60176883A (en) 1985-09-10

Similar Documents

Publication Publication Date Title
US4729695A (en) Process for the installation of the enbloc superstructure of an offshore platform, and equipment for carrying it practically
US4648751A (en) Method and apparatus for erecting offshore platforms
US6276875B1 (en) Method and transporter for installation or removal of a jacket for an offshore platform
EP1248885B1 (en) Removal of decks from offshore structures
US6209474B1 (en) Transporter for heavy objects at sea
GB1565884A (en) Method of loading and unloading heavy objects from a vessel and an equipment for carrying said method into effect
US4181452A (en) Oil-production platform and method of assembling and installing the same on a sea bed
JPH0523992B2 (en)
EP1492699B1 (en) Submersible watercraft
SU1555424A1 (en) Method and apparatus for mounting upper structure of stationary drilling platform onto supporting foundation
WO1997045597A1 (en) Method and apparatus for erecting a marine structure
JP7197118B2 (en) Work barge equipped with a crane and its crane operation method
JPH06193391A (en) How to launch a submerged box
SU1068333A1 (en) Method of constructing and launching a semisubmersible floating offshore drilling rig
JPS61162617A (en) Method of building off-shore structure
JPH0833010B2 (en) Caisson installation method and device
JP2589629B2 (en) Installation method of caisson by work boat
JPH0811775A (en) Connection method for hull module
JPS6354600B2 (en)
JPS62152996A (en) Building method for heavy marine structure
SU1058828A1 (en) Method of centering blocks prior to their delivery into assembly zone when constructing the top hull of semi-submerged offshore platform
JPS6343280B2 (en)
JPS5847068Y2 (en) Oil fence mooring device
JPS6137588A (en) Building method of marine structure of ship with beam beyond dock width
JPS6095017A (en) Jack-up type working ship