JPH05340102A - Assembling method for prefabricated column and beam unit reinforcing bars - Google Patents
Assembling method for prefabricated column and beam unit reinforcing barsInfo
- Publication number
- JPH05340102A JPH05340102A JP14960592A JP14960592A JPH05340102A JP H05340102 A JPH05340102 A JP H05340102A JP 14960592 A JP14960592 A JP 14960592A JP 14960592 A JP14960592 A JP 14960592A JP H05340102 A JPH05340102 A JP H05340102A
- Authority
- JP
- Japan
- Prior art keywords
- column
- unit
- divided
- units
- panel zone
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000003014 reinforcing effect Effects 0.000 title claims abstract description 23
- 238000000034 method Methods 0.000 title claims abstract description 9
- 230000002787 reinforcement Effects 0.000 claims abstract description 7
- 210000003205 muscle Anatomy 0.000 abstract description 17
- 239000000725 suspension Substances 0.000 description 3
- 238000004873 anchoring Methods 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
Landscapes
- Reinforcement Elements For Buildings (AREA)
Abstract
(57)【要約】
【目的】 超大型のH型柱梁ユニット鉄筋の先組が合理
的に行なわれる先組柱、梁のH型ユニットの組立工法を
提供する。
【構成】 パネルゾーンを介して柱鉄筋群2が対設され
た左右一対の半割柱ユニットA、及び同両ユニットAの
中間位置に梁ユニットBをスライド架台1上に平置き
し、同梁ユニットBの梁鉄筋定着部5を前記各柱ユニッ
トAのパネルゾーンに差し込み、相隣る半割柱ユニット
Aにおけるパネルゾーン以外において、外側は添え筋1
0で、内側は中子筋6でラップジョイントによって接合
し、半割柱ユニットAの各柱主筋7をテンプレート12
を介して所定間隙を保持して組立てる。
(57) [Summary] [Objective] To provide a method for assembling an H-shaped unit of pre-assembled columns and beams, in which the pre-assembly of super-large H-shaped column-beam unit reinforcing bars is rationally performed. [Structure] A pair of left and right half-divided pillar units A in which a pillar rebar group 2 is installed via a panel zone, and a beam unit B is laid flat on a slide base 1 at an intermediate position between both unit A and The beam reinforcing bar fixing portion 5 of the unit B is inserted into the panel zone of each of the pillar units A, and except for the panel zones of the adjacent half-divided pillar units A, the outside is the reinforcement bar 1
0, the inner side is joined by a lap joint with a core muscle 6, and each column main muscle 7 of the half-divided column unit A is template 12
Assemble while holding a predetermined gap.
Description
【0001】[0001]
【産業上の利用分野】本発明は先組柱、梁ユニット鉄筋
の組立て方法に係るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for assembling a pre-assembled column / beam unit reinforcing bar.
【0002】[0002]
【従来の技術】超高層ビルを鉄筋コンクリート造で設計
した場合、柱の配筋が高密度になるため、従来の現場で
の配筋では品質、能率の両面から大きな障害があった。2. Description of the Related Art When a super high-rise building is designed with a reinforced concrete structure, since the reinforcement of columns is dense, there has been a major obstacle in terms of quality and efficiency in the conventional reinforcement at the site.
【0003】[0003]
【発明が解決しようとする課題】従って鉄筋コンクリー
ト造の超高層ビルにおいては、一般には予め専用の工場
で組立てられたプレファブ鉄筋を使用することとなる
が、このような超大型の先組鉄筋の組立作業は容易でな
く、多大の労力と工費とを要し、多数の鉄筋が干渉しあ
うため合理的な作業が困難である。Therefore, in a super-high-rise building made of reinforced concrete, prefabricated reinforcing bars preassembled in a dedicated factory are generally used. However, assembling such super-sized pre-assembled reinforcing bars is required. The work is not easy, requires a large amount of labor and labor, and a large number of reinforcing bars interfere with each other, making it difficult to perform a rational work.
【0004】本発明はこのような実情に鑑みて提案され
たもので、その目的とする処は、超大型のH型柱梁ユニ
ット鉄筋の先組が合理的に行なわれる精度の高い作業性
に優れた鉄筋の組立工法を提供する点にある。The present invention has been proposed in view of the above circumstances, and an object thereof is to provide a highly accurate workability in which a super-large H-shaped column-beam unit reinforcing bar is rationally assembled. The point is to provide an excellent rebar assembly method.
【0005】[0005]
【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る先組柱、梁ユニット鉄筋の組立方法に
よれば、パネルゾーンを介して柱鉄筋群が対設された左
右1対の半割柱ユニット、及び同両柱半割りユニットの
中間位置に梁ユニットをスライド架台上に水平に載置
し、同梁ユニットの梁鉄筋定着端部を前記各半割柱ユニ
ットにおけるパネルゾーンに差し込み、相隣る柱半割ユ
ニットにおけるパネルゾーンを挟んで相対する柱鉄筋群
を、同パネルゾーン以外において外側は添え筋で、内側
は中子筋でラップジョイントによって接合するととも
に、前記柱半割りユニットの組立てに際して同ユニット
の柱鉄筋をテンプレートを介して所定間隙を保持して組
立てるものである。In order to achieve the above object, according to the method of assembling a pre-assembled column and a beam unit rebar according to the present invention, the left and right sides 1 in which a column rebar group is provided oppositely through a panel zone. A beam unit is horizontally placed on a slide frame at an intermediate position between a pair of half-divided column units and both half-divided column units, and the beam reinforcing bar fixing end of the beam unit is placed in the panel zone of each half-divided column unit. Insert the column rebar groups that face each other across the panel zone in the adjacent column half-division unit, and join the reinforced joints on the outer side and the inner core by lap joints outside the panel zone. When assembling the split unit, the pillar rebars of the split unit are assembled with a predetermined gap held therebetween via a template.
【0006】[0006]
【作用】本発明は前記したように、スライド架台上に対
設された柱半割り鉄筋ユニットを、中間にパネルゾーン
が介在された相対する柱鉄筋群より構成し、前記両半割
柱ユニットの中間に配設された梁鉄筋ユニットにおける
梁鉄筋定着部を、前記半割柱ユニットのパネルゾーンに
差し込み、同各半割柱ユニットにおけるパネルゾーンを
介して相対する柱鉄筋群を、パネルゾーン以外において
外側は添え筋で、内側は中子筋でラップジョイントによ
り接合して、柱鉄筋と梁鉄筋とによってH型の先組柱梁
ユニット鉄筋を組立てるものである。As described above, according to the present invention, the column half-divided reinforcing bar unit oppositely arranged on the slide base is constituted by the group of opposing column reinforcing bars with the panel zone interposed therebetween. The beam reinforcing bar anchoring portion in the beam reinforcing bar unit disposed in the middle is inserted into the panel zone of the half columnar unit, and the column reinforcing bar groups facing each other through the panel zones of the respective half columnar units are provided in other than the panel zone. The outer side is a reinforcing bar, and the inner side is a core bar that is joined by a lap joint, and an H-shaped pre-assembled column beam unit rebar is assembled by a column rebar and a beam rebar.
【0007】この際、前記半割柱ユニットの柱鉄筋の組
立にテンプレートを使用して鉄筋間の間隔を保持し、吊
込時の剛性を増大する。At this time, a template is used for assembling the column rebar of the half-column unit to maintain the space between the rebars and increase the rigidity during suspension.
【0008】[0008]
【実施例】以下本発明を図示の実施例について説明す
る。1は基盤上に設置されたスライド架台で、相対する
左右1対の半割柱ユニットAが水平に載置され、同両半
割柱ユニットAの中間に、梁X配筋定着端部bを有する
梁ユニットBが水平に載置されている。The present invention will be described below with reference to the illustrated embodiments. 1 is a slide mount installed on the base, and a pair of opposing left and right half-divided column units A are horizontally placed. In the middle of the both half-divided column units A, a beam X reinforcing bar fixing end b is placed. The beam unit B which it has is mounted horizontally.
【0009】前記半割柱ユニットAにおいては、パネル
ゾーンaを介して上下一双の柱鉄筋群2が対設されてい
る。3はフープ筋で、同フープ筋3はパネルゾーンaに
配筋しない。4は梁鉄筋、5はX型の梁鉄筋定着部であ
る。(図1参照) 相対する前記半割柱ユニットA,Aをスライド架台1に
沿って図2の矢印方向に移動し、梁ユニットBに配筋さ
れた梁X型梁筋の定着端部bを前記各半割柱ユニット
A,Aのパネルゾーンに差し込む。In the half-split pillar unit A, a pair of upper and lower pillar rebars 2 are provided opposite to each other via a panel zone a. 3 is a hoop muscle, and the hoop muscle 3 is not arranged in the panel zone a. Reference numeral 4 is a beam reinforcing bar, and 5 is an X-shaped beam reinforcing bar fixing portion. (See FIG. 1) The opposing half-split column units A, A are moved in the direction of the arrow in FIG. 2 along the slide base 1, and the fixing end portion b of the beam X-shaped beam bar arranged in the beam unit B is moved. Insert into the panel zone of each of the half-split column units A, A.
【0010】而して前記各半割柱ユニットAはパネルゾ
ーン以外において相隣る上半部柱ユニット筋A1 と下半
部柱ユニット筋A2 に、夫々端部がフック加工された中
子筋6を柱主筋7に沿って端部が柱ユニット筋の端部よ
り外部に跳ね出すように配筋しておく。図中8は幅止め
筋である。而して前記したように半割柱ユニットAのパ
ネルゾーンに梁ユニットBの両端梁鉄筋定着部5を差し
込んだのち、パネルゾーン以外において、外側は前記半
割ユニット筋A1 またはA2 の中子筋6を反対側の半割
ユニット筋A2 またはA1に押込んで、先端のフック部
に剪断補強筋9を配筋するとともにラップジョイント方
式によって互いに接合し、内側は添え筋10でラップジ
ョイント方式を介して接合する。図中11は補助筋であ
る。In each of the half-divided pillar units A, the cores in which the end portions are hooked to the upper half-pillar unit ribs A 1 and the lower half-pillar pillar ribs A 2 which are adjacent to each other except in the panel zone. The muscles 6 are arranged along the main pillar muscles 7 so that the ends of the muscles 6 project outward from the ends of the pillar unit muscles. Reference numeral 8 in the figure denotes a width stop bar. As described above, after inserting the both-end beam reinforcing bar fixing portion 5 of the beam unit B into the panel zone of the half-divided column unit A, the outside is the inside of the half-divided unit reinforcement A 1 or A 2 except the panel zone. The child muscle 6 is pushed into the half-divided unit muscle A 2 or A 1 on the opposite side, and the shear reinforcement muscle 9 is laid in the hook portion at the tip and joined to each other by the lap joint method. Join through the method. In the figure, 11 is an auxiliary muscle.
【0011】前記柱鉄筋群2の端部にはテンプレート1
2が配設され、同テンプレート12の透孔12aに柱鉄
筋群2の各鉄筋を挿入し柱鉄筋群2の間隔を保持し、且
つ吊込時の鉄筋群の剛性を保持し、また先行筋と結合干
渉する鉄筋2′は予め吊り上げる。かくして半割柱ユニ
ットAと梁ユニットBとをH型に組立てたのち、パネル
ゾーンに割りフープ筋等によりフープ筋を配筋する。The template 1 is provided at the end of the column rebar group 2.
2 are arranged, each rebar of the column rebar group 2 is inserted into the through hole 12a of the template 12 to maintain the interval between the column rebar groups 2, and to maintain the rigidity of the rebar group at the time of suspension, and the preceding bar. Reinforcing bar 2'that interferes with the coupling is lifted in advance. Thus, after the half-split column unit A and the beam unit B are assembled into an H-shape, the hoop muscles are arranged in the panel zone by split hoop muscles or the like.
【0012】しかるのち吊り治具Cを介してH型柱、梁
ユニット鉄筋を所定位置に吊り揚げ、セットする。図中
13は固定ナット、14は吊りフック付きカプラーであ
る。After that, the H-shaped column and the beam unit rebar are hung at a predetermined position through the hanging jig C and set. In the figure, 13 is a fixing nut, and 14 is a coupler with a hanging hook.
【0013】[0013]
【発明の効果】このように本発明によれば先組鉄筋柱、
梁を簡単にH型柱、梁ユニットに組立て、同ユニットを
所定位置に容易に吊込み、組立てることができる。また
柱ユニットの組立てにテンプレートを使用して柱鉄筋の
間隙を正確に保持し、吊込み時の剛性を保持し、また干
渉鉄筋の吊上げにも使用することができる。As described above, according to the present invention, the pre-assembled rebar columns,
The beam can be easily assembled into the H-shaped column and the beam unit, and the unit can be easily suspended at a predetermined position and assembled. Further, the template can be used for assembling the pillar unit to accurately hold the gap between the pillar rebars, to maintain the rigidity during hanging, and also to be used for hoisting the interfering reinforcing bars.
【図1】本発明に係る先組柱、梁ユニットの吊込み状態
を示す立面図である。FIG. 1 is an elevational view showing a suspended state of a post-assembled column and a beam unit according to the present invention.
【図2】前記先組柱、梁ユニットの組立状態を示す説明
図である。FIG. 2 is an explanatory view showing an assembled state of the front-assembled column and beam unit.
【図3】(イ)(ロ)は柱ユニットの組立工程を示す平
面図である。3A and 3B are plan views showing a process of assembling the pillar unit.
【図4】柱ユニットの地組状態を示す斜視図である。FIG. 4 is a perspective view showing an assembled state of a pillar unit.
【図5】先組柱、梁の吊上げ状態を示す斜視図である。FIG. 5 is a perspective view showing a lifted state of a front-assembled column and a beam.
A 半割柱ユニット B 梁ユニット C 吊り治具 1 スライド架台 2 柱鉄筋群 2′ 先行筋と結合干渉する鉄筋 3 フープ筋 4 梁鉄筋 5 梁鉄筋定着部 6 中子筋 7 柱主筋 8 幅止筋 9 剪断補強筋 10 添え筋 11 補助筋 12 テンプレート 13 固定ナット 14 吊りフック付きカプラー A Half-column unit B Beam unit C Hanging jig 1 Slide stand 2 Column rebar group 2 ′ Reinforcing bar that connects and interferes with preceding bar 3 Hoop bar 4 Beam rebar 5 Beam rebar anchoring section 6 Core bar 7 Column main bar 8 Width stop bar 9 Shear reinforcement muscles 10 Brace muscles 11 Auxiliary muscles 12 Templates 13 Fixing nuts 14 Couplers with suspension hooks
Claims (1)
れた左右1対の半割柱ユニット、及び同両柱半割りユニ
ットの中間位置に梁ユニットをスライド架台上に水平に
載置し、同梁ユニットの梁鉄筋定着端部を前記各半割柱
ユニットにおけるパネルゾーンに差し込み、相隣る柱半
割ユニットにおけるパネルゾーンを挟んで相対する柱鉄
筋群を、同パネルゾーン以外において外側は添え筋で、
内側は中子筋でラップジョイントによって接合するとと
もに、前記柱半割りユニットの組立てに際して同ユニッ
トの柱鉄筋をテンプレートを介して所定間隙を保持して
組立てることを特徴とする先組柱、梁ユニット鉄筋の組
立方法。1. A pair of left and right half-divided column units in which a group of column rebars are provided opposite to each other via a panel zone, and a beam unit is horizontally placed on a slide frame at an intermediate position between the two column half-divided units. , The beam reinforcing bar anchor end of the beam unit is inserted into the panel zone in each of the above-mentioned half-divided column units, and the column rebar groups that face each other across the panel zones in the adjacent column half-divided units are placed outside the panel zone. With the braces
The inner side is joined by a lap joint by a core reinforcement, and at the time of assembling the column half-divided unit, the column rebars of the unit are assembled with a predetermined gap maintained through a template. Assembly method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP04149605A JP3075835B2 (en) | 1992-06-09 | 1992-06-09 | Assembling method of pre-assembled column and beam unit rebar |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP04149605A JP3075835B2 (en) | 1992-06-09 | 1992-06-09 | Assembling method of pre-assembled column and beam unit rebar |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH05340102A true JPH05340102A (en) | 1993-12-21 |
| JP3075835B2 JP3075835B2 (en) | 2000-08-14 |
Family
ID=15478866
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP04149605A Expired - Lifetime JP3075835B2 (en) | 1992-06-09 | 1992-06-09 | Assembling method of pre-assembled column and beam unit rebar |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3075835B2 (en) |
-
1992
- 1992-06-09 JP JP04149605A patent/JP3075835B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP3075835B2 (en) | 2000-08-14 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN114592696A (en) | Beam-column joint stirrup binding method | |
| JPH0726624A (en) | Joining method for steel reinforced concrete structural columns in precast method | |
| JPH05340102A (en) | Assembling method for prefabricated column and beam unit reinforcing bars | |
| JPH03132532A (en) | Construction method of precast reinforced concrete column and beam | |
| JPH0517996A (en) | Building constructing method | |
| JPH02252830A (en) | Pre-assembled cross beam construction method | |
| JP2002332691A (en) | Column and beam connection structure | |
| JPH02236325A (en) | Construction method for super-highrise building | |
| JPH0732706Y2 (en) | Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams | |
| JPH0726440B2 (en) | Method of joining steel-reinforced bar precast concrete columns and steel beams | |
| JP2620118B2 (en) | Net formwork method for walls and floors | |
| JP2972955B2 (en) | Column and beam joining method and its structure | |
| JPH01203537A (en) | Src precast beam and junction structure of column and beam | |
| JPH10196027A (en) | Deck panel for concrete form | |
| JPH01137032A (en) | Method of lap joint construction of main reinforcement in post and beam joining section | |
| JPH03275839A (en) | Connection construction of reinforced concrete column and steel beam | |
| JPS6043547A (en) | Mold frame and reinforcement iron integral assembling and constructing method | |
| JPH0135886Y2 (en) | ||
| JPH05311748A (en) | Connecting execution method of pole and beam | |
| JPH0518114A (en) | Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure building | |
| JP2984626B2 (en) | PC pillar construction method and its PC pillar | |
| JPH02236328A (en) | Construction method for super-highrice building | |
| JPH0460183B2 (en) | ||
| JPS6366970B2 (en) | ||
| JPS6044473B2 (en) | Connection method of main beam reinforcement for extension |