JPH0547710B2 - - Google Patents
Info
- Publication number
- JPH0547710B2 JPH0547710B2 JP11652090A JP11652090A JPH0547710B2 JP H0547710 B2 JPH0547710 B2 JP H0547710B2 JP 11652090 A JP11652090 A JP 11652090A JP 11652090 A JP11652090 A JP 11652090A JP H0547710 B2 JPH0547710 B2 JP H0547710B2
- Authority
- JP
- Japan
- Prior art keywords
- earth
- collapse
- existing underground
- underground structure
- collapsed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000002689 soil Substances 0.000 claims description 27
- 239000004576 sand Substances 0.000 claims description 15
- 238000000034 method Methods 0.000 claims description 14
- 238000005429 filling process Methods 0.000 claims description 4
- 238000010276 construction Methods 0.000 description 21
- 238000009412 basement excavation Methods 0.000 description 6
- 230000000694 effects Effects 0.000 description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 238000009434 installation Methods 0.000 description 3
- 238000007796 conventional method Methods 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000009931 harmful effect Effects 0.000 description 1
- 231100000989 no adverse effect Toxicity 0.000 description 1
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Earth Drilling (AREA)
- Working Measures On Existing Buildindgs (AREA)
Description
【発明の詳細な説明】
「産業上の利用分野」
本発明は、近接線(隣接する建物又は境界より
10mm〜700mmの線、以下単に近接線とする。)上の
地中壁等の既設地中構造物(以下、単に既設地中
構造物とする。)位置に、新設地中構造物又は、
地中壁、土留め壁等(以下、単に新設地中構造物
とする。)が構築できるようにした、近接線上の
既設地中構造物のはつり工法に関するものであ
る。DETAILED DESCRIPTION OF THE INVENTION "Industrial Application Field" The present invention is applicable to
Lines from 10mm to 700mm, hereinafter simply referred to as proximity lines. ), a new underground structure or
This relates to a chiseling construction method for existing underground structures in the vicinity, which enables the construction of underground walls, earth retaining walls, etc. (hereinafter simply referred to as new underground structures).
「従来の技術並びにその課題」
従来、既設地中構造物を崩壊する方法として、
通常掘削きり(掘削作業機械)を利用する工法が
採用されている。"Conventional techniques and their problems" Conventionally, as a method for collapsing existing underground structures,
A construction method that uses excavators (excavation machines) is usually adopted.
しかし、この工法は、掘削きりを近接線上に配
備することができず、結局近接線上に構築された
既設地中構造物を崩壊することができない。 However, with this construction method, it is not possible to place an excavation hole on the adjacent line, and as a result, it is not possible to collapse the existing underground structure constructed on the adjacent line.
そこで、先ず前記掘削きりで崩壊した後、残存
する既設地中構造物を、はつり機械を介して、大
変な手間及び時間、並びに労力を介して成す方法
が採用されている。 Therefore, a method has been adopted in which, after the existing underground structure has collapsed due to the excavation, the remaining underground structure is removed using a chisel machine, which requires a great deal of time, effort, and labor.
したがつて、大変であることと、前記近接線上
に新設地中構造物を構築することも、これまた大
変であり、結果的には不可能であると、考えられ
ている。 Therefore, it is difficult to construct a new underground structure on the adjacent line, and it is considered to be impossible as a result.
但し、前記の崩壊後に、本出願人が、既に権利
を取得している特許第1599399号の連続式土留め
壁を構築する接続式壁工法を、使用すれば不可能
ではない。 However, this is not impossible if the applicant uses the connected wall construction method of constructing a continuous earth retaining wall in Patent No. 1599399, to which the applicant has already obtained the rights, after the collapse.
そして、一部で施工されている矢板、切梁、腹
おこし等を利用する工法でも、前記掘削きりを利
用する工法と、ほぼ同様な課題が考えられる処で
ある。 In addition, the construction methods that utilize sheet piles, struts, sills, etc., which are currently in use in some areas, may have almost the same problems as the construction methods that utilize excavations.
以上で詳述した従来のはつり工法及び地中壁工
法では、近接線上の既設地中構造物が設けられて
いる位置には、新設地中構造物が構築できないと
いつても過言ではない。殊に、工事に伴う騒音が
大きな問題となつている。 It is no exaggeration to say that with the conventional chisel construction method and underground wall construction method detailed above, a new underground structure cannot be constructed at a location where an existing underground structure is located on the adjacent line. In particular, noise caused by construction work has become a major problem.
「課題を解決するための手段」
上記に鑑み、本発明は、近接線上であつて、か
つ既設地中構造物を確実に崩壊し得ること。また
場合により、前記既設地中構造物の崩壊後に、こ
の近接上位置に、新設地中構造物を確実、かつ簡
易に構築し、土地の有効利用が図れるようにする
為に、発明された工法であります。"Means for Solving the Problems" In view of the above, the present invention is capable of reliably collapsing an existing underground structure on a line of proximity. In some cases, after the collapse of the existing underground structure, a construction method has been invented to reliably and easily construct a new underground structure in the vicinity of the existing underground structure, thereby making it possible to utilize the land effectively. It is.
その要旨は、地中壁等の既設地中構造物内の土
砂を排除しつつ、露出された既設地中構造物間に
切梁を差し渡す、この排土及び切梁差し渡し作業
を順次繰り返して、前記既設地中構造物間に、適
宜数本の切梁を差し渡す切梁取付け工程と、
前記切梁取付け工程が終了したとき、前記既設
地中構造物の底面部を取り除く為に、この底面部
のほぼ最中部分よりその側面部の方向に向かつて
順次崩壊し、この崩壊瓦礫を、崩壊底面部の最中
部分に向かつて移送する盛替え作業を、順次繰り
返して底面部の全ての崩壊並びに盛替え作業をな
し、かつ既設地中構造物の側面部を露出し、当該
側面部の崩壊ができる隙間を形成するように盛替
えを成す底面部崩壊並びに盛替え工程と、
この底面部崩壊並びに盛替えが終了したとき、
露出された既設地中構造物の側面部を順次崩壊し
つつ、この崩壊瓦礫を前記隙間に移送し、かつ少
なくともこの崩壊された既設地中構造物部の側面
部への瓦礫、石等の混じりもののない土砂を充填
する土盛りを成すと、この一区画の側面部の崩壊
と、この崩壊側面部への土盛り作業が終了する一
区画の側面部の崩壊並びに土盛り工程と、
この一区画の側面部の崩壊並びに土盛りが終了
したとき、続いて次の一区画の土盛りと、既設地
中構造物の側面部の崩壊にかかるが、この際、先
ず切梁の撤去をし、その後、既設地中構造物の側
面部が露出する程度に、外部より搬入する土砂で
埋土を成し、一時的な底面部を構成する仮内底面
埋土作業をするとともに、続いて、前述と同様な
作業により、既設地中構造物の側面部の崩壊、崩
壊瓦礫の仮底面部への移送、並びに少なくとも崩
壊側面部への土盛りをして、当該次の一区画の崩
壊と、その土盛り作業が終了するこの一区画の側
面部の崩壊並びに土盛り工程と、
以上で詳述した各一区画単位の側面部の崩壊及
び埋土作業と、既設切梁の撤去、並びに既設地中
構造物の側面部部位になす土盛り作業を繰り返
し、かつ前記各作業を、既設地中構造物の底面部
側より上方に向かつて成すことを特徴とする近接
線上の地中壁等の既設地中構造物のはつり工法で
ある。 The gist of this is to remove earth and sand from existing underground structures such as underground walls, and then pass struts between the exposed existing underground structures.This earth removal and strut passing work is repeated in sequence. , a strut installation step in which a number of struts are appropriately passed between the existing underground structures, and when the strut installation step is completed, this step is carried out in order to remove the bottom part of the existing underground structure. The entire bottom part is completely collapsed by repeating the refilling process, in which the collapsed debris is sequentially collapsed from the middle part of the bottom part toward the side part, and the collapsed rubble is transferred towards the middle part of the collapsed bottom part. A bottom collapse and refill process that involves collapsing and refilling the existing underground structure, exposing the side surface of the existing underground structure, and performing the refilling to form a gap in which the side surface can collapse; When the collapse and replacement are completed,
While sequentially collapsing the exposed side portions of the existing underground structure, the collapsed debris is transferred to the gap, and at least debris, stones, etc. are mixed into the side portion of the collapsed existing underground structure portion. When an earth mound is filled with empty earth and sand, the side wall of this section collapses, the soil filling process for the collapsed side wall is completed, and the side wall of this section ends. When the collapse and earth embankment have been completed, the next block of earth embankment and the collapse of the side part of the existing underground structure will begin.In this case, first the struts will be removed, and then the existing underground structure will collapse. Fill the object with earth and sand brought in from outside to the extent that the sides of the object are exposed, perform temporary inner bottom filling work to form a temporary bottom part, and then perform the same work as above. Collapse of the side part of the existing underground structure, transfer of the collapsed debris to the temporary bottom part, and at least fill the collapsed side part with earth to collapse the next section and complete the earth filling work. Collapse of the side part of the plot and earth filling process, Collapse of the side part of each plot and earth filling work detailed above, removal of existing struts, and earth mounding on the side part of the existing underground structure This is a chiseling method for an existing underground structure such as an underground wall on a proximate line, which is characterized by repeating the work and performing each of the above-mentioned works upward from the bottom side of the existing underground structure.
「作用」
以下本発明の作用を説明すると、先ず、既設地
中構造物内の土砂を掘削、排除し、既設地中構造
物が崩壊をしない処まで、前記掘削、排除を繰り
返して第1図の状態とする。"Operation" To explain the operation of the present invention, first, the earth and sand in the existing underground structure is excavated and removed, and the excavation and removal are repeated until the existing underground structure does not collapse. state.
そこで、既設地中構造物の崩壊を防止するとと
もに、隣接する構造物並びに地盤等への悪影響を
皆無にする為に、切梁工法により、適宜数の切梁
を装着する、いわゆる切梁取付け作業が終了し、
第2図の状態となる。 Therefore, in order to prevent the existing underground structure from collapsing and to completely eliminate any negative impact on adjacent structures and the ground, so-called strut installation work involves installing an appropriate number of struts using the strut construction method. has ended,
The state shown in Figure 2 will be reached.
続いて第3図(以下、同図とする。)の順序で
施工を成すが、先ず、原則として水抜きし、湧き
水等の水による弊害を除く。 Next, construction is carried out in the order shown in Figure 3 (hereinafter referred to as the same figure), but first, as a general rule, water is drained to remove any harmful effects caused by water such as spring water.
その後、同図イの如く、第一に既設地中構造物
の底面部を取り除くに際し、この底面部のほぼ最
中部分の鎖線で示す部位より、その側面部の方向
に向かつて順次崩壊し、この崩壊瓦礫の一部を他
の部分に取り除く。 After that, as shown in Figure A, when first removing the bottom part of the existing underground structure, the bottom part collapses sequentially from the part shown by the chain line in the middle part toward the side part. Remove some of this collapsed debris to other parts.
尚この底面部の崩壊の際に、一部の土砂が掘削
され、この掘削土砂は、前述の崩壊瓦礫とほぼ同
様に処理される。 When the bottom section collapses, some earth and sand are excavated, and this excavated earth and sand is treated in substantially the same manner as the collapse debris described above.
以上の掘削を同図イで仮想線で示すようにして
順次崩壊並びに一部の土砂の掘削し、この崩壊瓦
礫並びに掘削土砂を、空いている底面部の最中部
分に向かつて移送する。 The above excavation is carried out in sequence as shown by the imaginary line in A of the same figure, and the collapse and some of the earth and sand are excavated, and the collapse debris and the excavated earth and sand are transferred toward the middle part of the vacant bottom part.
このような作業により、容易に崩壊瓦礫並びに
掘削土砂の処理と移送ができ、究極的には、底面
部の全を崩壊していき、この崩壊瓦礫を底面部に
順次盛替え作業を成す。 Through such work, it is possible to easily process and transport the collapsed debris and excavated soil, and ultimately, the entire bottom section is collapsed and the collapsed debris is successively replaced on the bottom section.
但し、崩壊瓦礫を底面部の全部に積み上げず、
その周辺部盛替え隙間を形成する。具体的には、
後述の如く、既設地中構造物の側面部の崩壊がで
きる程度、隙間を形成する。 However, please do not pile up the collapsed debris all over the bottom.
A refill gap is formed around it. in particular,
As will be described later, a gap will be created to the extent that the sidewalls of the existing underground structure can collapse.
この底面部の崩壊並びに隙間を有する盛替え作
業を成すと、同図ロの状態となり、崩壊の対象と
なる側面部は露出されている。 When the bottom part collapses and the replacement work with a gap is completed, the state shown in FIG.
続いて、この底面部の崩壊と盛替えが終了した
ときは、同図ハの如く、露出された既設地中構造
物の側面部を順次崩壊していく、同図鎖線の部分
が崩壊され、いわゆる崩壊側面部となる。 Subsequently, when the collapse and replacement of this bottom part is completed, as shown in Figure C, the side parts of the exposed existing underground structure are sequentially collapsed, and the part indicated by the chain line in the Figure is collapsed. This becomes what is called a collapsed side part.
このようにして、崩壊された崩壊瓦礫は、同図
ニの如く、盛替え隙間に移送され、かつ前述の良
い土を充填する隙間が形成される。 In this way, the collapsed debris is transferred to the refilling gap, as shown in FIG. 2, and the gap is filled with the above-mentioned good soil.
そうして、同図ホの如く、この崩壊された既設
地中構造物の側面部部位に形成された間隙には、
順次良い土を充填する土盛りが成される。この側
面部の崩壊並びに充填作業を水平方向に順次繰り
返して、この一区画の既設地中構造物の側面部の
全ての崩壊と、この崩壊側面部への土盛りが終了
する。 Then, as shown in the figure (e), in the gap formed in the side part of this collapsed existing underground structure,
Earth mounds are gradually filled with good soil. By repeating this sidewall collapse and filling operation in the horizontal direction, all the sidewalls of the existing underground structure in this section are completely collapsed and the earth is filled on the collapsed sidewalls.
これにより、前記基礎の一区画の土盛りと、既
設地中構造物の側面部の崩壊が終了する。 This completes the collapse of the earth embankment of one section of the foundation and the side portion of the existing underground structure.
そこで、続いて同図ヘの如く、次の一区画の土
盛りと、既設地中構造物の側面部の崩壊にかかる
が、この際先ず既設地中構造物の側面部が露出す
る程度に、外部より搬入した土砂で埋土をなし、
仮想線で示すようになして、一時的な底面部を構
成する仮底面部の埋土を成す。 Therefore, as shown in the same figure, the next section of earth embankment and the side wall of the existing underground structure will collapse.In this case, first, the outside will be collapsed to the extent that the side wall of the existing underground structure will be exposed. The soil was filled with soil brought in from
As shown by the imaginary line, fill the temporary bottom part that will constitute the temporary bottom part.
その後同図トの如く、前述の工程と同様な、既
設地中構造物の側面部の崩壊、崩壊瓦礫の仮底面
部への移送、並びに崩壊側面部への土盛りをなす
側面部の崩壊並びに土盛り作業を成す。 After that, as shown in Fig. 3, the side part of the existing underground structure collapses, the collapsed debris is transferred to the temporary bottom part, and the side part that forms an earth mound on the collapsed side part collapses and the earth embankment is carried out in the same manner as the above-mentioned process. accomplish the work.
この工程が終了した時点で、前記反復一区画の
既設地中構造物の側面部の崩壊並びに土盛り作業
が終了する同図チの状態となる。 At the end of this process, the state shown in Figure 1C is reached, where the sidewalls of the existing underground structures in the repeated section have collapsed and the earth mounding work has been completed.
更に、既設地中構造物の側面部の立設方向の長
さに対応して、切梁の撤去並びに前記反復一区画
の既設地中構造物の側面部の崩壊並びに土盛り作
業を繰り返し、既設地中構造物の側面部の例え
ば、境界より、ほぼ10mm〜700mmに到る部位には、
良い土が土盛りされる(同図リ〜ル参照)。 Furthermore, in accordance with the length of the side part of the existing underground structure in the erection direction, the removal of the struts, the collapse of the side part of the existing underground structure in one section, and the earth-filling work are repeated, and the existing ground is removed. For example, on the side of a medium structure, approximately 10mm to 700mm from the boundary,
Good soil is mounded (see the rim of the same figure).
これにより、同図ヲで示すように、既設地中構
造物の側面部部位に良い土が充填された状態であ
り、いつでも新設地中構造物の工事が可能であ
り、また隣接構造物又は地盤への悪影響もほとん
どないものである。 As a result, as shown in the same figure, the side parts of the existing underground structures are filled with good soil, and new underground structures can be constructed at any time, and the adjacent structures or ground There is almost no negative impact on
「実施例」
図示する機材並びに装置は、本発明の実施に使
用するに最適な一例を示すものであつて、1は隣
接する建造物、2は基礎ブロツク、3は基礎杭、
4は既設地中構造物の側面部(側壁部を含む)、
5は前記既設地中構造物の底面部、6は既設構造
物の構築で形成される例えば車庫、物置、地下室
等の部屋である。``Example'' The illustrated equipment and devices represent an example best suited for use in carrying out the present invention, and include 1 an adjacent building, 2 a foundation block, 3 a foundation pile,
4 is the side part of the existing underground structure (including the side wall part),
5 is a bottom part of the existing underground structure, and 6 is a room such as a garage, a storeroom, a basement, etc. formed by constructing the existing structure.
そして、既設地中構造物の側面部4を崩壊する
に際しては、先ず、底面部5の崩壊と盛替え作業
をし、この底面部5の崩壊の作業が終了すると。 When collapsing the side part 4 of the existing underground structure, first the bottom part 5 is collapsed and replaced, and once the work of collapsing the bottom part 5 is completed.
続いて、側面部4の崩壊にかかり、この側面部
4の底面部側6a(下方)より、順次その地上側
6b(上方)に向かつて、崩壊していく。いわゆ
る、底面部側6aより上方に向かつて、崩壊さ
れ、かつ埋土、切梁の撤去等の処置が施される。 Subsequently, the side surface portion 4 begins to collapse, starting from the bottom side 6a (lower side) of the side surface portion 4 and gradually collapsing toward the ground side 6b (upper side). From the so-called bottom side 6a upwards, it is collapsed, and measures such as filling with earth and removing struts are performed.
したがつて、前記処置による崩壊側面部を4a
で示し、この崩壊側面部4aに充填される土盛り
を7で示す。 Therefore, the collapsed side part due to the above treatment is 4a
, and the earth mound filled with this collapsed side surface portion 4a is indicated by 7.
図中8は既設既設地中構造物の側面部4,4間
に設けられる切梁で、部屋6の深さ寸法により適
宜本設けられ、また既設地中構造物の側面部4の
強度又は土圧荷重に応じて増減され、隣接する構
造物等への悪影響が全く生じないように構成され
ている。更に、前記側面部4を下方より、順次上
方に崩壊していくにしたがつて、底面部側6aよ
り地上側6bに向かつて、順次取り外されてい
く。 Reference numeral 8 in the figure indicates a strut installed between the side parts 4 and 4 of the existing underground structure, which is installed as appropriate depending on the depth dimension of the room 6. The pressure is increased or decreased according to the pressure load, and is configured so that there is no adverse effect on adjacent structures. Furthermore, as the side surface portion 4 collapses sequentially from below to above, it is sequentially removed from the bottom surface side 6a toward the ground side 6b.
また9は外部より搬入した土砂で構成される埋
土であつて、底面部5より上方に向かつて、各一
区画の既設地中構造物の側面部4を崩壊していく
際に、仮底面部9aを構成する。 Reference numeral 9 denotes fill soil made up of earth and sand brought in from outside, which moves upward from the bottom surface 5 and is used as a temporary bottom surface when collapsing the side surface 4 of the existing underground structure in each section. 9a.
以上の符号とか、その符号の作業又は構成は、
反復して各一区画を順次構成していく場合も同様
である。 The above codes and the work or composition of the codes are as follows:
The same applies to the case where each section is sequentially configured by repeating the process.
そして、少なくとも崩壊された側面部4aに
は、良い土が土盛りされることにより、この土盛
り部位に、新設地中構造物が構築できるものであ
る。 By mounding at least the collapsed side surface portion 4a with good soil, a new underground structure can be constructed in this mounded area.
「発明の効果」
以上で詳述したように、本発明は、切梁を取付
けた後、先ず最初に、水抜きし、その後に先ず底
面部を取り除く、この際に、この底面部のほぼ最
中部分よりその側面部の方向に向かつて順次崩壊
し、順次繰り返して底面部の全を崩壊し、一部を
残して盛替え作業を順次なし、かつ既設地中構造
物の側面部を露出する底面部崩壊並びに盛替えを
成す。"Effects of the Invention" As described in detail above, the present invention first drains water after installing the strut, and then first removes the bottom part. The structure will collapse sequentially from the middle part to the sides, and the entire bottom part will be collapsed in sequence, leaving only a part and the work will be done to replace it, and the side parts of the existing underground structure will be exposed. The bottom part collapsed and was replaced.
そして、この底面部崩壊並びに盛替えが終了し
たとき、露出された既設地中構造物の側面部を順
次崩壊しつつ、この崩壊瓦礫を最中方向へ向かつ
て移送し、少なくともこの崩壊された既設地中構
造物の側面部部位に、順次良い土を充填する土盛
りをなす、いわゆる崩壊及び埋土並びに土盛りを
一区画全部に成すと、ここに、最初の一区画の側
面部の崩壊及び埋土、並びに土盛りが終了する。 When the collapse of the bottom part and the replacement are completed, the side parts of the exposed existing underground structure are sequentially collapsed and the collapsed debris is transported toward the center, and at least the collapsed existing underground structure is When the side part of an underground structure is filled with soil in order of good soil, so-called collapsed and filled soil and earth mound is made for an entire section, here is the collapsed and filled soil of the side part of the first section. , and the earth mounding ends.
続いて、次の一区画の土盛りと側面部の崩壊に
かかり、先ず側面部が露出する程度に、土砂で埋
土をなし、一時的な底面部を構成する仮底面部の
盛土をする。 Next, the earth mound and side wall of the next block will be collapsed. First, fill in the ground with earth and sand to the extent that the side wall is exposed, and then fill in the temporary bottom that will form the temporary bottom.
その後、前述の工程と同様な、側面部の崩壊、
崩壊瓦礫の移送並びに少なくとも崩壊側面部への
土盛りをなす、いわゆる側面部の崩壊及び埋土、
並びに土盛り作業を成すことにより、ここに、前
記反復一区画の側面部の崩壊及び埋土、並びに土
盛りが終了する。 After that, the collapse of the side part, similar to the process described above,
Transfer of collapsed debris and mounding of soil at least on the side of the collapse, so-called collapse and filling of the side of the collapse;
By completing the soil filling work, the collapse and filling of the side of the repeated section, and the soil filling are completed.
更に、側面部の立設方向の長さに対応して、切
梁の撤去並びに前記反復一区画の土盛りと側面部
の崩壊を繰り返し、少なくとも崩壊側面部には、
良い土が土盛りされる。 Furthermore, in accordance with the length of the side section in the erection direction, the removal of the struts and the collapse of the soil mound and side section of the repeated section are repeated, so that at least the collapsed side section is
Good soil is piled up.
その後、この土盛り(良い土)位置に新設地中
構造物を構築する、近接線上の側面部の崩壊及び
埋土、並びに少なくとも崩壊側面部への土盛り作
業を成すはつり工法である。 Thereafter, a new underground structure is constructed at this earth mound (good soil) location, which is a chisel construction method that involves collapsing and filling the side wall on the adjacent line, and at least filling the collapsed side wall with earth.
したがつて、近接線上に構築された既設地中構
造物の側面部を確実、かつ容易にはつることがで
きる効果と、この効果により、既設地中構造物の
側面部部位に、新設地中構造物を確実、かつ簡易
に構築することができる効果がある。 Therefore, the side part of an existing underground structure built on the adjacent line can be reliably and easily hung, and due to this effect, a new underground structure can be attached to the side part of the existing underground structure. This has the effect of allowing structures to be built reliably and easily.
また、以上の効果によつて、近接線上に、新設
地中構造物が構築でき、もつて、未活用土地が極
めて少なくなり、土地の有効利用が図れる卓効が
ある。 Furthermore, due to the above effects, a new underground structure can be constructed on the adjacent line, and as a result, the amount of unused land is extremely reduced, which is extremely effective in making effective use of land.
また本発明は、先ず既設地中構造物を切梁又は
図示しない腹おこし等を介して既設地中構造物の
崩壊を防止する一方で、崩壊側面部の部位に於い
ては、少なくともこの側面部に相当する部位に、
外部より良い土を土盛りする土盛り作業を成す工
法である。 Further, the present invention first prevents the existing underground structure from collapsing by using struts or raising the sides (not shown), and at least prevents the collapsed side surface from collapsing. In the part corresponding to
This is a construction method that involves mounding with better soil than the outside.
よつて、隣接地盤への悪影響、例えば亀裂、ゆ
るみ、崩壊等が発生することがほとんどないこ
と。また同様に、家屋、塀等の建造物の傾き、地
盤沈下等のトラブルが発生することが、極めて少
ない優れた工法である。 Therefore, there is almost no negative impact on the adjacent ground, such as cracks, loosening, collapse, etc. Similarly, it is an excellent construction method that is extremely unlikely to cause problems such as tilting of buildings such as houses and fences, and ground subsidence.
更に、本発明は、少なくとも既設地中構造物の
側面部部位に、外部より良い土を充填する工法で
ある。 Furthermore, the present invention is a method of filling at least the side portions of an existing underground structure with soil that is better than the outside.
したがつて、既設地中構造物の側面部部位に、
確実、かつ簡易に新設地中構造物を構築できる効
果がある。 Therefore, on the side part of the existing underground structure,
This has the effect of allowing new underground structures to be constructed reliably and easily.
また本発明は、先ず底面部を、その最中より崩
壊し、その後、最初の一区画に相当する既設地中
構造物の側面部の崩壊並びに土盛り等の作業を成
し、これにより、この側面部の崩壊及び埋土、並
びに土盛りが終了する。 In addition, the present invention first collapses the bottom part from the middle, and then collapses the side part of the existing underground structure corresponding to the first section and performs work such as earth mounding. The collapse and filling of the area, as well as the earth embankment, have been completed.
そして、続いて次の一区画に相当する既設地中
構造物の側面部の崩壊と土盛りにかかり、土砂で
埋土をなし、仮底面部を構成した後、前述の既設
地中構造物の側面部崩壊、瓦礫の移送並びに崩壊
側面部への土盛りを成して、反復一区画の既設地
中構造物の側面部の崩壊及び埋土、並びに土盛り
が終了する。 Then, the side of the existing underground structure corresponding to the next section collapses and is filled with earth, and after filling with earth and sand to form a temporary bottom part, the side of the existing underground structure mentioned above is collapsed. The collapse of the side of the existing underground structure, the filling of soil, and the filling of soil are completed by repeatedly collapsing the side of the existing underground structure and filling the area with earth.
その後、既設地中構造物の側面部の立設方向の
長さに対応して、切梁の撤去並びに前記反復一区
画の既設地中構造物の側面部の崩壊並びに埋土及
び盛土を繰り返し、既設地中構造物の崩壊側面部
の部位に、良い土を土盛りする作業を成す。 Thereafter, in accordance with the length of the side part of the existing underground structure in the erection direction, the removal of the struts, the collapse of the side part of the existing underground structure in one section, and the filling and embankment are repeated, This involves filling the area of the collapsed side of the existing underground structure with good soil.
その後、崩壊された既設地中構造物の部位に、
新設地中構造物を確実、かつ簡易に構築できる工
法である。 After that, in the part of the existing underground structure that collapsed,
This is a construction method that allows new underground structures to be constructed reliably and easily.
したがつて、既設地中構造物の取り壊しと、こ
の部位に新設地中構造物を構築するに際して、誠
に短期間に、かつ効率よく構築し得る効果を有す
る。 Therefore, when demolishing an existing underground structure and constructing a new underground structure in this location, it has the effect of being able to construct it efficiently in a very short period of time.
図面は本工法の一実施例を示すものであり、第
1図は既設地中構造物内の土砂を排除した状態
で、本発明の施工前の断面図、第2図は第1図に
切梁を装着した状態の断面図、第3図イ〜ヲは施
工手順の一例を示した模式図である。
1……建造物、2……基礎ブロツク、3……基
礎杭、4……既設地中構造物、4a……崩壊側面
部、5……底面部、6……部屋、6a……底面部
側、6b……地上側、7……土盛り、9……埋
土、9a……仮底面部。
The drawings show one embodiment of this construction method, and Figure 1 is a cross-sectional view of the existing underground structure with the earth and sand removed before construction, and Figure 2 is a cross-sectional view of the construction method shown in Figure 1. A cross-sectional view of the beam with the beam attached, and FIGS. 3A to 3A are schematic diagrams showing an example of the construction procedure. 1... Building, 2... Foundation block, 3... Foundation pile, 4... Existing underground structure, 4a... Collapsed side part, 5... Bottom part, 6... Room, 6a... Bottom part side, 6b...ground side, 7...mound, 9...filling soil, 9a...temporary bottom part.
Claims (1)
つつ、露出された既設地中構造物間に切梁を差し
渡す、この排土及び切梁差し渡し作業を順次繰り
返して、前記既設地中構造物間に、適宜数本の切
梁を差し渡す切梁取付け工程と、 前記切梁取付け工程が終了したとき、前記既設
地中構造物の底面部を取り除く為に、この底面部
のほぼ最中部分よりその側面部の方向に向かつて
順次崩壊し、この崩壊瓦礫を、崩壊底面部の最中
部分に向かつて移送する盛替え作業を、順次繰り
返して底面部の全ての崩壊並びに盛替え作業をな
し、かつ既設地中構造物の側面部を露出し、当該
側面部の崩壊ができる隙間を形成するように盛替
えを成す底面部崩壊並びに盛替え工程と、 この底面部崩壊並びに盛替えが終了したとき、
露出された既設地中構造物の側面部を順次崩壊し
つつ、この崩壊瓦礫を前記隙間に移送し、かつ少
なくともこの崩壊された既設地中構造物部の側面
部への瓦礫、石等の混じりもののない土砂を充填
する土盛りを成すと、この一区画の側面部の崩壊
と、この崩壊側面部への土盛り作業が終了する一
区画の側面部の崩壊並びに土盛り工程と、 この一区画の側面部の崩壊並びに土盛りが終了
したとき、続いて次の一区画の土盛りと、既設地
中構造物の側面部の崩壊にかかるが、この際、先
ず切梁の撤去をし、その後、既設地中構造物の側
面部が露出する程度に、外部より搬入する土砂で
埋土を成し、一時的な底面部を構成する仮内底面
埋土作業をするとともに、続いて、前述と同様な
作業により、既設地中構造物の側面部の崩壊、崩
壊瓦礫の仮底面部への移送、並びに少なくとも崩
壊側面部への土盛りをして、当該次の一区画の崩
壊と、その土盛り作業が終了するこの一区画の側
面部の崩壊並びに土盛り工程と、 以上で詳述した各一区画単位の側面部の崩壊及
び埋土作業と、既設切梁の撤去、並びに既設地中
構造物の側面部部位になす土盛り作業を繰り返
し、かつ前記各作業を、既設地中構造物の底面部
側より上方に向かつて成すことを特徴とする近接
線上の地中壁等の既設地中構造物のはつり工法。[Scope of Claims] 1. Earth removal and strut passing work in which earth and sand are removed from existing underground structures such as underground walls and struts are passed between exposed existing underground structures. A step of installing struts in which a number of struts are passed between the existing underground structures by repeating them in sequence, and when the step of installing the struts is completed, removing the bottom part of the existing underground structure. Then, the bottom part is successively collapsed from the middle part of the bottom part to the side part thereof, and then the collapsed rubble is transferred to the middle part of the collapsed bottom part. A bottom collapse and replacement process in which all of the collapse and replacement work is carried out, and the side part of the existing underground structure is exposed and the part is replaced so as to form a gap in which the side part can collapse; When this bottom collapse and replacement are completed,
While sequentially collapsing the exposed side portions of the existing underground structure, the collapsed debris is transferred to the gap, and at least debris, stones, etc. are mixed into the side portion of the collapsed existing underground structure portion. When an earth mound is filled with empty earth and sand, the side wall of this section collapses, the soil filling process for the collapsed side wall is completed, and the side wall of this section ends. When the collapse and earth embankment have been completed, the next block of earth embankment and the collapse of the side part of the existing underground structure will begin.In this case, first the struts will be removed, and then the existing underground structure will collapse. Fill the object with earth and sand brought in from outside to the extent that the sides of the object are exposed, perform temporary inner bottom filling work to form a temporary bottom part, and then perform the same work as above. Collapse of the side part of the existing underground structure, transfer of the collapsed debris to the temporary bottom part, and at least fill the collapsed side part with earth to collapse the next section and complete the earth filling work. Collapse of the side part of the plot and earth filling process, Collapse of the side part of each plot and earth filling work detailed above, removal of existing struts, and earth mounding on the side part of the existing underground structure A chiseling method for an existing underground structure such as an underground wall on a proximal line, characterized in that the work is repeated and each of the above-mentioned works is performed upward from the bottom side of the existing underground structure.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP11652090A JPH0414518A (en) | 1990-05-02 | 1990-05-02 | Method for constructing new retaining wall at old retaining wall position on neighboring line |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP11652090A JPH0414518A (en) | 1990-05-02 | 1990-05-02 | Method for constructing new retaining wall at old retaining wall position on neighboring line |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0414518A JPH0414518A (en) | 1992-01-20 |
| JPH0547710B2 true JPH0547710B2 (en) | 1993-07-19 |
Family
ID=14689172
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP11652090A Granted JPH0414518A (en) | 1990-05-02 | 1990-05-02 | Method for constructing new retaining wall at old retaining wall position on neighboring line |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0414518A (en) |
Families Citing this family (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101748758B (en) | 2008-12-04 | 2012-03-21 | 中国二十冶集团有限公司 | Timbering method of foundation ditches for reforming on-line equipment foundations in factory buildings |
| JP5971546B2 (en) * | 2012-01-27 | 2016-08-17 | 花田 卓蔵 | Demolition method of underground concrete structure near boundary |
| CN104164879B (en) * | 2013-05-16 | 2016-06-29 | 辛鹏 | A kind of wall base and pattern foundation pit supporting structure remove device |
| JP2019206860A (en) * | 2018-05-30 | 2019-12-05 | 花田 卓蔵 | Demolition method of underground structure |
| JP2020037777A (en) * | 2018-09-03 | 2020-03-12 | 花田 卓蔵 | Method for demolishing underground structure in contact with building |
| CN110259182B (en) * | 2019-04-26 | 2021-03-19 | 安徽省公路桥梁工程有限公司 | Construction method of ecological demolition structure of retaining wall |
| CN111139838A (en) * | 2020-01-04 | 2020-05-12 | 中亿丰建设集团股份有限公司 | Treatment method for long-standing ultra-deep foundation pit in soft soil area |
| JP7735014B1 (en) * | 2025-02-28 | 2025-09-08 | 株式会社プラント・ツリース | Construction methods and buildings |
-
1990
- 1990-05-02 JP JP11652090A patent/JPH0414518A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0414518A (en) | 1992-01-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6034121B2 (en) | Construction method of underground structure | |
| JPS62288218A (en) | Settlement caisson | |
| JPH0547710B2 (en) | ||
| KR100289256B1 (en) | Tunnel construction method in shallow toffee area | |
| JP5378066B2 (en) | Mountain fastening method | |
| KR100322844B1 (en) | tubular roof tunnel construction method | |
| KR102570649B1 (en) | Method of demolition of underground exterior walls | |
| KR100322845B1 (en) | tubular roof tunnel construction method | |
| JPH07150564A (en) | Removing engineering method for underground structure and obstacle in 1000mm proximity to boundary | |
| KR102579002B1 (en) | Method of demolition of underground exterior walls | |
| JP7295538B2 (en) | Impermeable layer construction method | |
| JP7437336B2 (en) | Temporary cofferdam method, temporary cofferdam structure | |
| KR100628511B1 (en) | External reinforcement type reverse circulation excavation | |
| JPS5936058B2 (en) | How to construct a structure using underground continuous walls | |
| KR970007379B1 (en) | Open shield method and open shield machine used therein | |
| JP3766423B2 (en) | Retaining wall construction method | |
| CN111677012A (en) | A pipe jacking working well structure for sandy soil layer and its construction method | |
| JP3794097B2 (en) | Construction method for underground structures | |
| KR970007378B1 (en) | Open shield machine | |
| KR100543284B1 (en) | Construction method of bracing walls used as columns and slabs | |
| JP5173771B2 (en) | Soil replacement method | |
| US1665797A (en) | Method of excavating and producing foundations | |
| JPH10114957A (en) | Method of sand boiling-preventive construction in excavation work of shaft, etc. | |
| KR20030051477A (en) | The method of constructing diaphragm wall making use of support wall | |
| JPH02311617A (en) | Construction of foundation pile |