JPH0550437B2 - - Google Patents
Info
- Publication number
- JPH0550437B2 JPH0550437B2 JP12471285A JP12471285A JPH0550437B2 JP H0550437 B2 JPH0550437 B2 JP H0550437B2 JP 12471285 A JP12471285 A JP 12471285A JP 12471285 A JP12471285 A JP 12471285A JP H0550437 B2 JPH0550437 B2 JP H0550437B2
- Authority
- JP
- Japan
- Prior art keywords
- boom
- lateral load
- load
- limit
- value
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 230000006870 function Effects 0.000 description 9
- 230000000694 effects Effects 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000007274 generation of a signal involved in cell-cell signaling Effects 0.000 description 1
Landscapes
- Jib Cranes (AREA)
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は、移動式クレーンあるいは高所作業車
等のブームを有する作業機に用いられ、ブームの
起伏方向に直交してブームに作用する負荷すなわ
ちブーム横方向負荷が限界に達したとき、警報あ
るいは作業機の動きを止めるためのブーム横方向
負荷限界信号を出力するブームを有する作業機の
ブーム横方向負荷限界信号発生装置に関するもの
である。Detailed Description of the Invention (Industrial Application Field) The present invention is used for a working machine having a boom, such as a mobile crane or an aerial work vehicle, and is used to reduce the load that acts on the boom orthogonally to the up-and-down direction of the boom. That is, the present invention relates to a boom lateral load limit signal generating device for a working machine having a boom that outputs a boom lateral load limit signal for warning or stopping the movement of the working machine when the boom lateral load reaches its limit.
(従来の技術)
ブームを有する作業機は、基台、基台にその基
端部を起伏支点ピンを介して枢着連結され起伏支
点ピンを中心として起伏可能なブーム、および基
台とブームの適所間に介装されブームを起伏駆動
するためのブーム起伏駆動装置を備えている。そ
して、ブームの先端に荷を吊りあるいはブーム先
端に設けたバケツト上へ作業員が搭乗した上でブ
ームを起伏駆動してクレーン作業あるいは高所作
業をするものであるが、作業時にこの作業機のブ
ームには、ブームをその起伏軌跡面に沿つて曲げ
ようとする比較的大きな縦方向負荷とブームをそ
の起伏軌跡面に直交する方向に曲げようとする横
方向負荷が作用する。すなわち、前記縦方向負荷
は、ブーム自重、ブーム先端で担持する負荷の自
重成分、およびブームに作用する風の影響でブー
ム起伏軌跡面方向に生ずる力等によつて発生し、
前記横方向負荷は、ブームに作用する風の影響で
ブーム起伏軌跡面と直交する方向に生ずる力、ブ
ーム先端で担持する負荷の振れに起因してブーム
起伏軌跡面と直交する方向に生ずる力、および基
台が側方に傾斜している場合にあつてはブーム自
重およびブーム先端で担持する負荷の分力として
ブーム起伏軌跡面と直交する方向に生ずる力等に
よつて発生する。(Prior Art) A work machine having a boom includes a base, a boom whose base end is pivotally connected to the base via a hoisting fulcrum pin and can be hoisted about the hoisting fulcrum pin, and a connection between the base and the boom. It is equipped with a boom hoisting drive device that is interposed between appropriate places and drives the boom to hoist it up and down. A load is suspended from the tip of the boom, or a worker rides on a bucket installed at the tip of the boom, and then the boom is raised and lowered to perform crane work or work at high places. A relatively large longitudinal load that tends to bend the boom along its undulation trajectory plane and a lateral load that tends to bend the boom in a direction perpendicular to its undulation trajectory plane are applied to the boom. That is, the longitudinal load is generated by the boom's own weight, the dead weight component of the load carried at the tip of the boom, and the force generated in the direction of the boom's locus of the boom due to the influence of wind acting on the boom.
The lateral load is a force generated in a direction perpendicular to the boom hoisting trajectory plane due to the influence of wind acting on the boom, a force generated in a direction perpendicular to the boom hoisting trajectory plane due to swinging of the load carried at the tip of the boom, If the base is tilted laterally, this is caused by the boom's own weight and a force generated in a direction perpendicular to the boom locus plane as a component of the load carried at the tip of the boom.
そして、上記縦方向負荷および横方向負荷は、
ブームの強度あるいは作業機の安定性からその限
界値が定まつているので、作業機の作業時には常
にブームに作用する縦方向負荷並びに横方向負荷
が所定の限界値を越えないよう注意する必要があ
る。 And the above longitudinal load and lateral load are:
The limit values are determined based on the strength of the boom or the stability of the work equipment, so care must be taken to ensure that the vertical and lateral loads acting on the boom do not exceed the specified limit values at all times when working with the work equipment. be.
従来、ブームに作用する縦方向負荷がその限界
値に達したときに警報又は作業機の動きを停止さ
せるための信号を出力するブーム縦方向負荷限界
信号発生装置は、種々提案され実用化されている
が、ブームに作用する横方向負荷がその限界値に
達したときに警報又は作業機の動きを停止させる
ための信号を出力するブーム横方向負荷限界信号
発生装置は、正確なものが存在しなかつた。 Conventionally, various boom vertical load limit signal generators have been proposed and put into practical use, which output an alarm or a signal to stop the movement of the work equipment when the vertical load acting on the boom reaches its limit value. However, there is no accurate boom lateral load limit signal generator that outputs an alarm or a signal to stop the movement of the work equipment when the lateral load acting on the boom reaches its limit value. Nakatsuta.
従来のブーム横方向負荷限界信号発生装置とし
ては、特開昭58−135095に、ブームに作用する横
方向負荷が所定の限界値に達したとき警報又は作
業機を停止するための信号を出力する如きブーム
横方向負荷限界信号発生装置の基本構成は示され
ているものの、横方向負荷の上記所定の限界値を
どのようなものにするかについて何等提案されて
いない。しかしながら、特開昭58−135095に開示
された上記ブーム横方向負荷限界信号発生装置の
基本構成、並びに従来周知のブーム縦方向負荷限
界信号発生装置(これは縦方向負荷の限界値をブ
ームの起伏角に応じて変動させるようにしてい
る。)の技術をよせ集めることで、前記横方向負
荷の限界値をブームの起伏角に応じて変動するも
のとすれば良いのではないかと容易に想到でき
る。 A conventional boom lateral load limit signal generator is disclosed in Japanese Patent Application Laid-Open No. 58-135095, which outputs an alarm or a signal to stop the work equipment when the lateral load acting on the boom reaches a predetermined limit value. Although the basic structure of such a boom lateral load limit signal generating device is shown, there is no proposal as to what the predetermined limit value of the lateral load should be. However, the basic configuration of the boom lateral load limit signal generator disclosed in Japanese Patent Application Laid-Open No. 58-135095, as well as the conventionally known boom longitudinal load limit signal generator (which detects the limit value of the vertical load) It is possible to easily imagine that the limit value of the lateral load can be made to vary according to the angle of the boom. .
(従来技術の問題点)
しかしながら、これとて以下に示す理由で正確
な横方向負荷の限界値を得ることができず、その
ため正確なブーム横方向負荷限界信号発生装置を
得ることができないという欠点を有している。(Problems with the prior art) However, this has the disadvantage that it is not possible to obtain an accurate lateral load limit value for the reasons shown below, and therefore it is not possible to obtain an accurate boom lateral load limit signal generator. have.
すなわち、ブームを有する作業機のブームには
前述の如く比較的大きな縦方向負荷と横方向負荷
が作用するものであるが、ブームを破壊するため
に必要な横方向負荷は、当該ブームに作用してい
る縦方向負荷の大小によつて変動するものであ
る。このことは、ブームに縦方向負荷の限界値近
くの縦方向負荷が作用しているとき、ブームは極
めて小さな横方向負荷で破壊されることおよび、
ブームに殆んど縦方向負荷が作用していないと
き、ブームは大きな横方向負荷に耐えることから
理解できるであろう。また、ブームを有する作業
機におけるブーム横方向負荷によつて、作業機を
横方向へ転倒させようとする力は、ブームが起仰
している時ほど大きくなるので、横方向負荷の限
界値は、ブームの起伏角の大小によつても変動す
るものである。このように、ブームに作用する横
方向負荷の限界値は、単にブーム起伏角に応じて
変動するのみならず、ブームに作用する縦方向負
荷の大小によつても変動するものである。 In other words, as mentioned above, relatively large longitudinal and lateral loads act on the boom of a working machine having a boom, but the lateral load necessary to destroy the boom does not act on the boom. It varies depending on the magnitude of the longitudinal load applied. This means that when the boom is subjected to a longitudinal load close to the longitudinal load limit, the boom will be destroyed by an extremely small lateral load;
It will be appreciated that when there is little longitudinal load acting on the boom, the boom will withstand large lateral loads. In addition, the force that tends to cause the work equipment to fall laterally due to the boom lateral load on work equipment with a boom increases as the boom is raised, so the limit value of the lateral load is , which also varies depending on the magnitude of the boom's undulation angle. In this way, the limit value of the lateral load acting on the boom varies not only depending on the boom heave angle, but also depending on the magnitude of the longitudinal load acting on the boom.
したがつて、上述の如き、横方向負荷の限界値
を単にブームの起伏角の関数として変動させるよ
うにして得られるブーム横方向負荷限界信号発生
装置にあつては、ブーム横方向負荷限界信号を正
確に発することが出来ないのである。 Therefore, in the case of the boom lateral load limit signal generating device which is obtained by simply varying the lateral load limit value as a function of the boom heave angle as described above, the boom lateral load limit signal is It cannot be uttered accurately.
(本発明が解決しようとする問題点)
本発明は、従来のブーム横方向負荷限界信号発
生装置が持つていた上記欠点、すなわち不正確で
あるという欠点を改善し、正確なブーム横方向負
荷限界信号発生装置を提供しようとするものであ
る。(Problems to be Solved by the Present Invention) The present invention improves the above-mentioned drawback of the conventional boom lateral load limit signal generator, that is, it is inaccurate, and provides accurate boom lateral load limit signal generation devices. The present invention attempts to provide a signal generator.
(問題点を解決するための手段)
本発明のブームを有する作業機のブーム横方向
負荷限界信号発生装置は、ブームに作用する横方
向負荷の実際値が対比されるべき横方向負荷の限
界値を、ブーム起伏角およびブームに作用する縦
方向負荷の実際値の関数として求めるところに特
徴を有するものであり、具体的には次の如く構成
するものである。すなわち、
基台、基台にその基端部を起伏支点ピンを介し
て枢着連結され該起伏支点ピンを中心として起伏
可能なブーム、および基台とブームの適所間に介
装されブームを起伏駆動するためのブーム起伏駆
動装置を備えた移動式クレーンあるいは高所作業
車等のブームを有する作業機のブーム横方向負荷
限界信号発生装置であつて、
ブームの起伏角の実際値を検出する起伏角検出
器、
ブームに作用する負荷であつてブームの起伏方
向に作用する縦方向負荷の実際値を検出する縦方
向負荷検出器、
ブームに作用する負荷であつてブームの起伏方
向に直交して作用する横方向負荷の実際値を検出
する横方向負荷検出器、
および、前記起伏角検出器と前記縦方向負荷検
出器からの各実際値信号に基づき、実際のブーム
起伏角並びに実際の縦方向負荷での横方向負荷の
限界値を求め、この横方向負荷の限界値を前記横
方向負荷検出器からの実測値と対比し、後者の値
が前者の値に達すると警報あるいは作業機を停止
させるためのブーム横方向負荷限界信号を出力す
る演算処理部。(Means for Solving the Problems) The boom lateral load limit signal generating device for a working machine having a boom according to the present invention provides a lateral load limit signal generator with which the actual value of the lateral load acting on the boom is to be compared. is determined as a function of the actual value of the boom undulation angle and the longitudinal load acting on the boom. Specifically, it is constructed as follows. That is, a base, a boom whose base end is pivotally connected to the base via a hoisting fulcrum pin and can be hoisted about the hoisting fulcrum pin, and a boom which is interposed between the base and the boom at an appropriate position and which is able to hoist the boom. A boom lateral load limit signal generator for a working machine having a boom such as a mobile crane or an aerial work vehicle equipped with a boom hoisting drive device for driving the hoisting device for detecting the actual value of the boom hoisting angle. angle detector, a longitudinal load detector that detects the actual value of the longitudinal load acting on the boom in the direction of boom heave; a lateral load detector for detecting the actual value of the applied lateral load; and, based on the respective actual value signals from the heave angle detector and the longitudinal load detector, the actual boom heave angle and the actual longitudinal direction. The limit value of the lateral load at the load is determined, and this limit value of the lateral load is compared with the actual value measured from the lateral load detector, and when the latter value reaches the former value, an alarm is issued or the work equipment is stopped. A processing unit that outputs a boom lateral load limit signal to
とから構成したことを特徴とするものである。It is characterized by being composed of the following.
(作用)
上記構成をもつ本発明のブームを有する作業機
のブーム横方向負荷限界信号発生装置は、ブーム
に作用する横方向負荷が対比される横方向負荷の
限界値を、ブームの起伏角並びにブームに作用す
る縦方向負荷の関数として得るようにしたので、
ブーム起伏角並びに縦方向負荷の変動に伴つて変
動する横方向負荷の限界値を精度良く得ることが
でき、ひいてはブーム横方向負荷限界信号を精度
良く発生させることができるものである。(Function) The boom lateral load limit signal generating device for a working machine having a boom according to the present invention having the above-mentioned configuration determines the limit value of the lateral load to which the lateral load acting on the boom is compared, based on the boom's heave angle and the boom lateral load limit signal generator. Since it was obtained as a function of the longitudinal load acting on the boom,
It is possible to accurately obtain the limit value of the lateral load that changes with the fluctuation of the boom heave angle and the longitudinal load, and as a result, it is possible to generate the boom lateral load limit signal with high accuracy.
(実施例)
以下本発明を、トラツククレーンのブーム横方
向負荷限界信号発生装置に実施した実施例につき
図に基づいて説明する。(Example) The present invention will be described below with reference to the drawings with reference to an example in which the present invention is applied to a boom lateral load limit signal generator for a truck crane.
第1図は、ブームを有する作業機としてのトラ
ツククレーンを示す。第1図において、1は、車
輌V上へ旋回自在に搭載した基台である。2は、
基台1にその基端部を起伏支点ピン3を介して枢
着され当該起伏支点ピンを中心として起伏可能な
ブームである。4は、基台1とブーム3の適所間
に介装されブーム3を起伏駆動するためのブーム
起伏駆動装置である。5は、ブーム2の起伏角の
実際値を検出するためにブーム2の起伏支点に設
けた起伏角検出器である。6は、ブーム2に作用
する負荷のうち特にブーム2の起伏方向に作用す
る縦方向負荷の実際値を検出するための縦方向負
荷検出器である。本実施例の場合、この縦方向負
荷検出器6はブーム起伏駆動装置4たる油圧シリ
ンダのピストンロツド中へ介装したロードセルで
構成しているが、この縦方向負荷検出器6は、ブ
ーム起伏駆動装置4たる油圧シリンダのブームモ
ーメント担持側油室の油圧を電気信号に変換する
圧力−電気変換器で構成しても良いし、また、ブ
ーム2の上下壁面に貼着したストレーンゲージで
構成しても良い。更にこの縦方向負荷検出器6
は、機械式クレーンにようにブーム起伏駆動装置
がブーム先端と基台間に張設したガイロープとこ
のガイロープを操作するウインチで構成されるも
のにあつては、ガイロープの張力を測定するロー
ドセルで構成することができる。7は、ブーム2
に作用する負荷のうち特にブーム2の起伏方向に
直交して作用する横方向負荷の実際値を検出する
ための横方向負荷検出器である。この横方向負荷
検出器7は、ブーム2の左右両側に貼着されたス
トレーンゲージを含んでおり、この左右のストレ
ーンゲージの出力差を演算々出することでブーム
2に作用する横方向負荷を検出するようにしてい
る。上記起伏角検出器5、縦方向負荷検出器6お
よび横方向負荷検出器7は、第2図に基づき説明
する本発明に係るブームを有する作業機のブーム
横方向負荷限界信号発生装置の一部を構成するも
のである。 FIG. 1 shows a truck crane as a working machine having a boom. In FIG. 1, reference numeral 1 denotes a base mounted on a vehicle V so as to be rotatable. 2 is
It is a boom whose base end is pivotally connected to a base 1 via a fulcrum pin 3 and can be raised and lowered about the fulcrum pin. Reference numeral 4 denotes a boom hoisting drive device that is interposed between the base 1 and the boom 3 at a proper location and drives the boom 3 to hoist it up and down. Reference numeral 5 denotes a luffing angle detector provided at the luffing fulcrum of the boom 2 in order to detect the actual value of the luffing angle of the boom 2. 6 is a longitudinal load detector for detecting the actual value of the longitudinal load acting on the boom 2, particularly in the up-and-down direction of the boom 2. In the case of this embodiment, this longitudinal load detector 6 is constituted by a load cell inserted into the piston rod of a hydraulic cylinder that is the boom hoisting drive device 4; It may be configured with a pressure-to-electrical converter that converts the hydraulic pressure in the boom moment carrying side oil chamber of the four hydraulic cylinders into an electric signal, or it may be configured with strain gauges attached to the upper and lower walls of the boom 2. good. Furthermore, this vertical load detector 6
For mechanical cranes where the boom hoisting drive device consists of a guy rope stretched between the boom tip and the base and a winch that operates this guy rope, it consists of a load cell that measures the tension of the guy rope. can do. 7 is boom 2
This is a lateral load detector for detecting the actual value of the lateral load that acts perpendicularly to the up-and-down direction of the boom 2 among the loads that act on the boom 2. The lateral load detector 7 includes strain gauges attached to both the left and right sides of the boom 2, and calculates the lateral load acting on the boom 2 by calculating the difference in output between the left and right strain gauges. I'm trying to detect it. The heave angle detector 5, longitudinal load detector 6, and lateral load detector 7 are part of a boom lateral load limit signal generating device for a working machine having a boom according to the present invention, which will be explained based on FIG. It constitutes.
第2図に示す如く、本発明のブームを有する作
業機のブーム横方向負荷限界信号発生装置は、前
記ブーム起伏角検出器5、前記縦方向負荷検出器
6、前記横方向負荷検出器7、および演算処理部
8とから構成されている。演算処理部8は、起伏
角検出器5と縦方向負荷検出器6からの各実際値
信号に基づき、実際のブーム起伏角並びに縦方向
負荷のもとでブーム2に許容させる横方向負荷の
限界値を演算々出する限界横方向負荷出力部9
と、この限界横方向負荷出力部9の発する横方向
負荷の限界値と前記横方向負荷検出器7の実測値
を対比し後者の値が前者の値に達すると警報ある
いはトラツククレーンの動きを停止させるための
ブーム横方向負荷限界信号を出力する比較演算部
10とを備えている。 As shown in FIG. 2, the boom lateral load limit signal generating device for a working machine having a boom according to the present invention includes the boom heave angle detector 5, the longitudinal load detector 6, the lateral load detector 7, and an arithmetic processing section 8. Based on the actual value signals from the heave angle detector 5 and the longitudinal load detector 6, the arithmetic processing unit 8 determines the limit of the lateral load allowed to the boom 2 under the actual boom heave angle and the longitudinal load. Limit lateral load output section 9 that calculates the value
Then, the limit value of the lateral load generated by the limit lateral load output section 9 is compared with the actual value measured by the lateral load detector 7, and when the latter value reaches the former value, an alarm is issued or the movement of the truck crane is stopped. and a comparison calculation unit 10 that outputs a boom lateral load limit signal for increasing the load.
前記限界横方向負荷出力部9における横方向負
荷の限界値の演算々出手法に関し、ここに数例を
あげると次のとおりである。 Some examples of methods for calculating the limit value of the lateral load in the limit lateral load output section 9 are as follows.
(1) 第3図に示す如く、限界横方向負荷出力部9
中に、各ブーム起伏角度毎の各縦方向負荷の実
際値に夫々対応する横方向負荷の限界値を記憶
するメモリー11を備えておき、起伏角検出器
5および縦方向負荷検出器6からの各実際値信
号をインデツクス信号として、メモリー11か
ら対応する横方向負荷の限界値を読み出すよう
にする。(1) As shown in Figure 3, the limit lateral load output section 9
The inside is provided with a memory 11 for storing the limit value of the lateral load corresponding to the actual value of each longitudinal load for each boom hoisting angle. Each actual value signal is used as an index signal to read out the corresponding limit value of the lateral load from the memory 11.
(2) 第4図に示すように、限界横方向負荷出力部
9中に、ブーム2に縦方向負荷が作用していな
いときの横方向負荷の限界値(以下これを縦方
向負荷を考慮しない場合における横方向負荷の
限界値という)を各ブーム起伏角度毎に記憶す
るメモリー12を備えておき、起伏角検出器5
からの実際値信号をインデツクス信号として、
メモリー12から実際のブーム起伏角に対応す
る限界値(縦方向負荷を考慮しない場合におけ
る横方向負荷の限界値)を読み出し、この読み
出した限界値を、演算回路13で以つて縦方向
負荷検出器6からの実際値信号に基づきブーム
2に作用する縦方向負荷が大きい時ほど低減さ
せ、その結果を横方向負荷の限界値とする。(2) As shown in FIG. A memory 12 is provided for storing the limit value of the lateral load in each boom lifting angle, and the lifting angle detector 5
Using the actual value signal from as the index signal,
The limit value corresponding to the actual boom heave angle (the limit value of the lateral load when the longitudinal load is not taken into consideration) is read out from the memory 12, and the read limit value is used in the arithmetic circuit 13 to detect the vertical load detector. Based on the actual value signal from 6, the larger the vertical load acting on the boom 2 is, the more it is reduced, and the result is taken as the limit value of the lateral load.
(3) 第5図に示すように、限界横方向負荷出力部
9中に、各ブーム起伏角度毎の縦方向負荷の限
界値を記憶するメモリー14を備えておき、起
伏角検出器5からの実際値信号をインデツクス
信号として、メモリー14から実際のブーム起
伏角に対応する縦方向負荷の限界値を読み出
し、この読み出した縦方向負荷の限界値とブー
ム2の縦横の強度比(これはブーム2に個有の
もので定数である。)を用いて演算回路15で
以つて、縦方向負荷を考慮しない場合における
横方向負荷の限界値を求め、ここで求めた限界
値を、演算回路16で以つて縦方向負荷検出器
6からの実際値信号に基づきブーム2に作用す
る横方向負荷が大きい時ほど低減させ、その結
果を横方向負荷の限界値とする。(3) As shown in FIG. 5, the limit lateral load output unit 9 is provided with a memory 14 for storing the limit value of the longitudinal load for each boom hoisting angle, and Using the actual value signal as an index signal, the limit value of the longitudinal load corresponding to the actual boom heave angle is read out from the memory 14. ) is used in the arithmetic circuit 15 to find the limit value of the lateral load when the longitudinal load is not taken into account, and the limit value found here is used in the arithmetic circuit 16. Based on the actual value signal from the longitudinal load detector 6, the larger the lateral load acting on the boom 2, the more it is reduced, and the result is taken as the limit value of the lateral load.
演算処理部8における限界横方向負荷出力部9
は上述の如く種々の手法のもとに、実際のブーム
起伏角並びに実際の横方向負荷での横方向負荷の
限界値を求めることができるものである。 Limit lateral load output section 9 in the calculation processing section 8
As mentioned above, it is possible to determine the limit value of the lateral load at the actual boom lifting angle and the actual lateral load based on various methods.
上記実施例においては、演算処理部8は、これ
を限界横方向負荷出力部9と比較演算部10によ
り構成していると説明し、これらが演算処理部8
中に個別に存在している如く説明したが、この演
算処理部8は、上述の限界横方向負荷出力部9の
演算処理と比較演算部10の演算処理を順次周期
的に行うマイクロコンピユータで構成しても良
く、その場合、限界横方向負荷出力部9と比較演
算部10はこのマイクロコンピユータ中に混然一
体として存在することになる。要は、演算処理部
8は、起伏角検出器5と縦方向負荷検出器6から
の各実際値信号に基づき、実際のブーム起伏角並
びに実際の縦方向負荷での横方向負荷の限界値を
求め、この横方向負荷の限界値を横方向負荷検出
器7からの実際値と対比し、後者の値が前者の値
に達すると警報あるいは作業機の動きを停止させ
るためのブーム横方向負荷限界信号出力する、演
算処理を行うものであれば良いのである。 In the above embodiment, the arithmetic processing section 8 is explained as being constituted by the limit lateral load output section 9 and the comparison arithmetic section 10, which are the arithmetic processing section 8.
Although the calculation processing section 8 has been described as being separately present in the microcomputer, it is composed of a microcomputer that sequentially and periodically performs the calculation processing of the above-mentioned limit lateral load output section 9 and the calculation processing of the comparison calculation section 10. In that case, the limit lateral load output section 9 and the comparison calculation section 10 will exist in this microcomputer as a single unit. In short, the arithmetic processing unit 8 calculates the limit value of the lateral load at the actual boom heave angle and the actual longitudinal load based on the actual value signals from the heave angle detector 5 and the longitudinal load detector 6. This lateral load limit value is compared with the actual value from the lateral load detector 7, and when the latter value reaches the former value, a boom lateral load limit is set to issue an alarm or stop the movement of the implement. Any device that outputs a signal or performs arithmetic processing is sufficient.
次に作用を説明する。演算処理部8において、
横方向負荷検出器7からの横方向負荷の実測値が
対比される限界横方向負荷(上記実施例において
限界横方向負荷出力部9の出力信号)は、起伏角
検出器5と縦方向負荷検出器6からの各実際値信
号に基づいて、すなわち実際のブーム起伏角並び
に実際のブーム縦方向負荷の関数として得られる
ものであるから、これらの関数関係を適当に設定
することで、ブーム起伏角並びにブームに作用す
る縦方向負荷の大小に伴つて変動する横方向負荷
の限界値を極めて正確に得ることができるのであ
る。それ故、このようにして得た正確な横方向負
荷と、横方向負荷検出器7からの実測値信号とを
対比し、後者の値が前者の値に達すると発生す
る、警報あるいは作業機(この場合トラツククレ
ーン)の動きを停止させるブーム横方向負荷限界
信号は、作業機(トラツククレーン)のブーム2
の横方向負荷が限界に達したときこれに正確に対
応して出力されるのである。演算処理部8から出
力される上記ブーム横方向負荷限界信号は、警報
器を作動させる信号として利用して作業機(トラ
ツククレーン)のオペレータへブームに作用する
横方向負荷が限界に達したことを知らせ、或いは
作業機(トラツククレーン)の制御装置を作動さ
せ作業機の動きを停止させる信号として利用して
ブームに作用する横方向負荷が限界に達したとき
作業機(トラツククレーン)の動きを停止させる
ものである。 Next, the effect will be explained. In the arithmetic processing section 8,
The limit lateral load (in the above embodiment, the output signal of the limit lateral load output section 9) with which the actual measured value of the lateral load from the lateral load detector 7 is compared is determined by the heave angle detector 5 and the longitudinal load detector. Based on each actual value signal from the device 6, that is, obtained as a function of the actual boom heave angle and the actual boom longitudinal load, by appropriately setting these functional relationships, the boom heave angle can be adjusted. In addition, the limit value of the lateral load, which varies with the magnitude of the longitudinal load acting on the boom, can be obtained very accurately. Therefore, the accurate lateral load obtained in this way is compared with the actual measured value signal from the lateral load detector 7, and when the latter value reaches the former value, an alarm or work equipment ( In this case, the boom lateral load limit signal that stops the movement of the truck crane is the boom 2 of the work equipment (truck crane).
When the lateral load of the vehicle reaches its limit, the output is output exactly in accordance with this. The boom lateral load limit signal output from the processing unit 8 is used as a signal to activate an alarm to notify the operator of the work equipment (truck crane) that the lateral load acting on the boom has reached its limit. When the lateral load acting on the boom reaches the limit, the movement of the work equipment (truck crane) is stopped by using it as a signal to notify or actuate the control device of the work equipment (truck crane) to stop the movement of the work equipment. It is something that makes you
次に、本発明のブームを有する作業機のブーム
横方向負荷限界信号発生装置の発展例につき説明
する。上記実施例では、作業機として説明したト
ラツククレーンのブーム2は、これを伸縮しない
ものとして説明したが、第1図に仮想線で示す如
くブーム2が伸縮式でありその長さが変動するも
のにあつては、ブーム2に作用する横方向負荷の
限界値は、ブーム起伏角、およびブームに作用す
る縦方向負荷の関数として変動する他、ブーム長
の関数としても変動する。このようなブーム長が
変動する作業機に本発明を実施する場合にあつて
は、ブーム長検出器17(第1図〜第5図に一点
鎖線で図示)を設け、これが検出したブーム長の
実際値信号を、演算処理部8に入力し、演算処理
部8において、起伏角検出器5、縦方向負荷検出
器6並びにブーム長検出器17からの各実際値信
号に基づき、実際のブーム起伏角、実際の縦方向
負荷並びに実際のブーム長での横方向負荷の限界
値を求め、この横方向負荷の限界値を横方向負荷
検出器7からの実際値と対比し、後者の値が前者
の値に達すると警報あるいは作業機(トラツクク
レーン)の動きを停止させるためのブーム横方向
負荷限界信号を出力するようにするのである。こ
の場合、上記実施例において第3図乃至第5図に
基づき説明した限界横方向負荷出力部9における
3種の横方向負荷の限界値の演算々出手法は、
夫々以下の如くなる。 Next, an example of the development of the boom lateral load limit signal generating device for a working machine having a boom according to the present invention will be described. In the above embodiment, the boom 2 of the truck crane described as a working machine was explained as being non-extendable, but as shown by the imaginary line in Fig. 1, the boom 2 is retractable and its length is variable. In this case, the limit value of the lateral load acting on the boom 2 varies as a function of the boom luffing angle and the longitudinal load acting on the boom, as well as as a function of the boom length. When implementing the present invention in such a work machine whose boom length fluctuates, a boom length detector 17 (indicated by a dashed line in FIGS. 1 to 5) is provided, and the boom length detected by the boom length detector 17 is The actual value signal is input to the arithmetic processing unit 8, and the arithmetic processing unit 8 calculates the actual boom heave based on the actual value signals from the heave angle detector 5, longitudinal load detector 6, and boom length detector 17. Find the limit value of the lateral load at the angle, the actual longitudinal load and the actual boom length, compare this lateral load limit value with the actual value from the lateral load detector 7, and compare the latter value with the former. When this value is reached, an alarm or a boom lateral load limit signal is output to stop the movement of the work equipment (truck crane). In this case, the method for calculating the limit values of the three types of lateral loads in the limit lateral load output section 9 explained based on FIGS. 3 to 5 in the above embodiment is as follows:
They are as follows.
(1) 第3図に示す如く、限界横方向負荷出力部9
中に、各ブーム起伏角度毎、各縦方向負荷毎並
びに各ブーム長毎の実際値に対応する横方向負
荷の限界値を記憶するメモリー11を備えてお
き、起伏角検出器5、縦方向負荷検出器6およ
びブーム長検出器17からの各実際値信号をイ
ンデツクス信号として、メモリー11から対応
する横方向負荷の限界値を読み出すようにす
る。(1) As shown in Figure 3, the limit lateral load output section 9
The inside is provided with a memory 11 for storing the limit value of the lateral load corresponding to the actual value for each boom hoisting angle, for each longitudinal load, and for each boom length. The respective actual value signals from the detector 6 and the boom length detector 17 are used as index signals to read out the corresponding limit value of the lateral load from the memory 11.
(2) 第4図に示すように、限界横方向負荷出力部
9中に、縦方向負荷を考慮しない場合における
横方向負荷の限界値を、各ブーム起伏角並びに
各ブーム長毎に記憶するメモリー12を備えて
おき、起伏角検出器5並びにブーム長検出器1
7からの実際値信号をインデツクス信号とし
て、メモリー12から実際のブーム起伏角並び
に実際のブーム長に対応する限界値(縦方向負
荷を考慮しない場合における横方向負荷の限界
値)を読み出し、この読み出した限界値を、演
算回路13で以つて縦方向負荷検出器6からの
実際値信号に基づき縦方向負荷が大きい時ほど
低減させ、その結果を横方向負荷の限界値とす
る。(2) As shown in Fig. 4, the limit lateral load output section 9 has a memory that stores the limit value of lateral load without considering longitudinal load for each boom heave angle and each boom length. 12, a luffing angle detector 5 and a boom length detector 1.
Using the actual value signal from 7 as an index signal, the limit value corresponding to the actual boom heave angle and the actual boom length (the limit value of the lateral load when the longitudinal load is not considered) is read out from the memory 12. The calculated limit value is reduced by the arithmetic circuit 13 based on the actual value signal from the longitudinal load detector 6 as the longitudinal load increases, and the result is taken as the limit value of the lateral load.
(3) 第5図に示すように、限界横方向負荷出力部
9中に、各ブーム起伏角度毎並びに各ブーム長
毎の縦方向負荷の限界値を記憶するメモリー1
4を備えておき、起伏角検出器5並びにブーム
長検出器17からの実際値信号をインデツクス
信号として、メモリー14から実際のブーム起
伏角並びに実際のブーム長に対応する縦方向負
荷の限界値を読み出し、この読み出した縦方向
負荷の限界値とブーム2の縦横の強度比(これ
はブーム2に固有のもので定数である)を用い
て演算回路15で以つて、縦方向負荷を考慮し
ない場合における横方向負荷の限界値を求め、
ここで求めた限界値を、演算回路16で以つて
縦方向負荷検出器6からの実際信号に基づきブ
ーム2に作用する縦方向負荷が大きい時ほど低
減させ、その結果を横方向負荷の限界値とす
る。(3) As shown in Fig. 5, in the limit lateral load output section 9, there is a memory 1 that stores the limit value of the longitudinal load for each boom hoisting angle and for each boom length.
4, and using the actual value signals from the heave angle detector 5 and the boom length detector 17 as index signals, the limit value of the longitudinal load corresponding to the actual boom heave angle and the actual boom length is stored from the memory 14. The arithmetic circuit 15 uses the read limit value of the vertical load and the vertical/horizontal strength ratio of the boom 2 (this is a constant and is unique to the boom 2) to determine the case where the vertical load is not considered. Find the limit value of the lateral load at
The limit value obtained here is reduced as the longitudinal load acting on the boom 2 is larger based on the actual signal from the longitudinal load detector 6 using the arithmetic circuit 16, and the result is used as the limit value of the lateral load. shall be.
この発展例の場合、横方向負荷検出器7の検出
する横方向負荷の実際値が対比されるべき限界横
方向負荷(限界横方向負荷出力部9の出力信号)
は、上記実施例同様起伏角検出器5と縦方向負荷
検出器6からの実際値信号に基づいて、実際のブ
ーム起伏角並びに実際の縦方向負荷の関数として
得られる他、ブーム長検出器17からの実際値信
号に基づき実際のブーム長の関数として得られる
ものである。そのため、本発展例は、伸縮ブーム
式の作業機(トラツククレーン)に用いられる高
精度のブーム横方向負荷限界信号発生装置を提供
できるのである。 In the case of this development, the limit lateral load (output signal of the limit lateral load output 9) with which the actual value of the lateral load detected by the lateral load detector 7 is to be compared
is obtained as a function of the actual boom heave angle and the actual longitudinal load based on the actual value signals from the heave angle detector 5 and the longitudinal load detector 6 as in the above embodiment. as a function of the actual boom length. Therefore, this developed example can provide a highly accurate boom lateral load limit signal generating device for use in a telescopic boom type work machine (truck crane).
上記実施例並びに発展例は、本発明をトラツク
クレーンに実施した実施例として説明したが、本
発明は、定置式クレーン、高所作業車、あるいは
定置式高所作業機等にも採用しうること勿論であ
る。 Although the above embodiments and developed examples have been explained as examples in which the present invention is applied to a truck crane, the present invention can also be adopted to a stationary crane, an aerial work vehicle, a stationary aerial work machine, etc. Of course.
尚、ブームを有する作業機にあつては、一般に
ブーム縦方向負荷限界信号発生装置、すなわち、
ブームの動作状態(ブーム起伏角、ブームが伸縮
ブームである場合にはブーム起伏角およびブーム
長)毎の縦方向負荷の限界値をメモリーに記憶し
ておき、このメモリーから、ブーム起伏角検出器
およびブーム長検出器からの実際値信号をインデ
ツクス信号として実際のブーム動作状態に対応す
る縦方向負荷の限界値を読み出し、これを縦方向
負荷検出器からの実際値信号と対比して、その対
比結果によりブーム縦方向負荷限界信号を得る如
く構成したブーム縦方向負荷限界信号発生装置が
装備されているが、この縦方向負荷限界信号発生
装置におけるブーム角検出器、縦方向負荷検出
器、ブーム長検出器および、ブーム縦方向負荷限
界信号は、本発明のブーム横方向負荷限界信号発
生装置の実施にあたりこれを援用しうること勿論
である。 In addition, in the case of a work machine having a boom, generally a boom longitudinal load limit signal generator, that is,
The vertical load limit value for each boom operating condition (boom hoisting angle, boom hoisting angle and boom length if the boom is a telescopic boom) is stored in memory, and from this memory, the boom hoisting angle detector Then, the actual value signal from the boom length detector is used as an index signal to read out the limit value of the longitudinal load corresponding to the actual boom operating state, and this is compared with the actual value signal from the longitudinal load detector, and the comparison is made. A boom longitudinal load limit signal generator configured to obtain a boom longitudinal load limit signal according to the result is equipped, and the boom angle detector, longitudinal load detector, and boom length in this longitudinal load limit signal generator are Of course, the detector and the boom longitudinal load limit signal can be used in implementing the boom lateral load limit signal generating device of the present invention.
(効果)
以上の如く構成し作用する本発明のブームを有
する作業機のブーム横方向負荷限界信号発生装置
は、ブームを有する作業機のブーム横方向負荷が
限界に達したことを精度良く検知できるものであ
り、作業機の安全作業に資する効果大なるもので
ある。(Effects) The boom lateral load limit signal generating device for a working machine having a boom according to the present invention, which is configured and operated as described above, can accurately detect that the boom lateral load of a working machine having a boom has reached its limit. This has a great effect on the safe operation of work equipment.
第1図は、ブームを有する作業機としてのトラ
ツククレーンの説明図、第2図乃至第5図は本発
明に係るブームを有する作業機のブーム横方向負
限界信号発生装置の説明図である。
基台;1、ブーム;2、起伏支点ピン;3、起
伏駆動装置;4、起伏角検出器;5、縦方向負荷
検出器;6、横方向負荷検出器;7、演算処理
部;8。
FIG. 1 is an explanatory diagram of a truck crane as a working machine having a boom, and FIGS. 2 to 5 are explanatory diagrams of a boom lateral negative limit signal generating device for a working machine having a boom according to the present invention. Base; 1. Boom; 2; Lifting fulcrum pin; 3; Lifting drive device; 4; Lifting angle detector; 5; Vertical load detector; 6; Lateral load detector; 7; Arithmetic processing unit; 8.
Claims (1)
して枢着連結され該起伏支点ピンを中心として起
伏可能なブーム、および基台とブームの適所間に
介装されブームを起伏駆動するためのブーム起伏
駆動装置を備えた移動式クレーンあるいは高所作
業車等のブームを有する作業機のブーム横方向負
荷限界信号発生装置であつて、 ブームの起伏角の実際値を検出する起伏角検出
器、 ブームに作用する負荷であつてブームの起伏方
向に作用する縦方向負荷の実際値を検出する縦方
向負荷検出器 ブームに作用する負荷であつてブームの起伏方
向に直交して作用する横方向負荷の実際値を検出
する横方向負荷検出器、 および、前記起伏角検出器と前記縦方向負荷検
出器からの各実際値信号に基づき、実際のブーム
起伏角並びに実際の縦方向負荷での横方向負荷の
限界値を求め、この横方向負荷の限界値を前記横
方向負荷検出器からの実測値と対比し、後者の値
が前者の値に達すると警報あるいは作業機を停止
させるためのブーム横方向負荷限界信号を出力す
る演算処理部。 とから構成したことを特徴とするブームを有する
作業機のブーム横方向負荷限界信号発生装置。[Scope of Claims] 1. A base, a boom whose base end is pivotally connected to the base via a hoisting fulcrum pin and can be hoisted about the hoisting fulcrum pin, and a boom interposed between the base and the boom at an appropriate position. A boom lateral load limit signal generator for a working machine having a boom, such as a mobile crane or an aerial work vehicle, which is equipped with a boom hoisting drive device for hoisting and driving the boom, and which detects the actual hoisting angle of the boom. A vertical load detector that detects the actual value of the vertical load that acts on the boom in the direction of the boom. A vertical load detector that detects the actual value of the load that acts on the boom in the direction of the boom. a lateral load detector for detecting the actual value of a lateral load acting orthogonally to the boom; The limit value of the lateral load under the actual longitudinal load is determined, and this limit value of the lateral load is compared with the actual value measured from the lateral load detector, and when the latter value reaches the former value, an alarm is issued. A calculation processing unit that outputs a boom lateral load limit signal to stop the work equipment. A boom lateral load limit signal generating device for a working machine having a boom, characterized in that it is comprised of:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12471285A JPS61282294A (en) | 1985-06-07 | 1985-06-07 | Boom lateral load limit signal generator for working machinewith boom |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12471285A JPS61282294A (en) | 1985-06-07 | 1985-06-07 | Boom lateral load limit signal generator for working machinewith boom |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS61282294A JPS61282294A (en) | 1986-12-12 |
| JPH0550437B2 true JPH0550437B2 (en) | 1993-07-29 |
Family
ID=14892238
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP12471285A Granted JPS61282294A (en) | 1985-06-07 | 1985-06-07 | Boom lateral load limit signal generator for working machinewith boom |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS61282294A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7259398B2 (en) * | 2019-02-26 | 2023-04-18 | 株式会社タダノ | BOOM ABNORMAL LOAD DETECTION DEVICE, MOBILE CRANE AND BOOM ABNORMAL LOAD DETECTION METHOD |
-
1985
- 1985-06-07 JP JP12471285A patent/JPS61282294A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS61282294A (en) | 1986-12-12 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4752012A (en) | Crane control means employing load sensing devices | |
| CN102464270B (en) | Overturning-preventing torque limiter and movable crane | |
| EP0728696A1 (en) | Lifting load and tipping moment detecting device for a mobile crane | |
| CN101348216B (en) | Crane security protection system and crane thereof | |
| CN201882830U (en) | Anti-overturning moment limiter system and traveling crane | |
| CN100546852C (en) | Mobile working device comprising a support boom | |
| CN105060122B (en) | Crane safety control system and method, moment limiter and crane | |
| JPH01256496A (en) | Load vibration preventer at time of ungrounding of slinging load of crane with boom | |
| US3913690A (en) | Crane load indicating arrangement | |
| JPH0550437B2 (en) | ||
| JPH038698A (en) | Outrigger reaction limiting signal generator of moving crane | |
| RU2271332C2 (en) | Boom load-lifting crane protection method | |
| JP2001089078A (en) | Crane overload preventive device, and its regulating method | |
| JP2664863B2 (en) | Crane overload prevention device | |
| JPH0527433Y2 (en) | ||
| JP3596931B2 (en) | Construction machine load condition detection device | |
| JPH01256497A (en) | Load vibration preventer at time of ungrounding of slinging load of crane with telescopic boom | |
| JPS6124309B2 (en) | ||
| JP3117791B2 (en) | Crane hoisting stop control device | |
| JPS6134394Y2 (en) | ||
| JPS627671Y2 (en) | ||
| JPS5948238B2 (en) | Crane safety device with adjustable boom | |
| EP1491485A1 (en) | Crane with a winch and a traction control device | |
| JPH0729110Y2 (en) | Boom-flame prediction device for mobile cranes | |
| JP3073310B2 (en) | Turn braking start signal generator for mobile cranes |