Landscapes
- Barrages (AREA)
Description
【発明の詳細な説明】 産業上の利用分野 本発明は堰の仮締切工法に関する。[Detailed description of the invention] Industrial applications The present invention relates to a temporary cofferdam construction method for a weir.
従来の技術
通常、水量を調節するために堰には水門が設け
られるとともに、水門を構成する主ゲートの保
守、点検を行うために、仮締切ゲート(予備ゲー
トともいう)が設けられている。従来、この仮締
切ゲートとしては、第3図〜第5図に示すような
ものがある。第3図および第4図に示す仮締切ゲ
ート21,31は、上下において複数個に分割し
て構成され、その設置は各ピア22,32に形成
された戸溝に、径間方向に沿う長尺分割体21
a,31aを順次落とし込み、中間戸当り23,
33および堰の床版24,34管理橋25,35
に支持させるものである。第5図に示す仮締切ゲ
ート41は、浮体(フローテイングゲートともい
う)により構成され、使用時にタグボートにより
ピア42,42間に曳航固定するものである。BACKGROUND OF THE INVENTION Normally, weirs are provided with water gates to adjust the amount of water, and temporary coffer gates (also referred to as backup gates) are provided to perform maintenance and inspection of the main gates that make up the water gates. Conventionally, such temporary closing gates include those shown in FIGS. 3 to 5. The temporary coffer gates 21 and 31 shown in FIGS. 3 and 4 are constructed by being divided into a plurality of upper and lower parts, and are installed in the door grooves formed in each pier 22 and 32 along the length along the span direction. Shaku division body 21
A, 31a are dropped in order, intermediate door stop 23,
33 and weir slab 24, 34 management bridge 25, 35
It is supported by The temporary coffer gate 41 shown in FIG. 5 is constituted by a floating body (also referred to as a floating gate), and is towed and fixed between piers 42 and 42 by a tugboat when in use.
発明が解決しようとする問題点
上記第3図および第4図の仮締切ゲート21,
31によると、各ピア22,32に戸溝を設ける
とともに中間戸当り23,33を設ける必要があ
り、また長尺分割体21a,31aを順番に落と
し込む作業は手間がかかり、さらにこれら長尺分
割体21a,31aを支持するための支持金物を
堰の床版24,34および管理橋25,35に埋
設しておく必要がある等の問題点があつた。ま
た、上記第5図の仮締切ゲート41によると、堰
に特別な設備を必要としないが、浮体の格納ドツ
クあるいは引上げるためのスペースを必要とし、
また据付けにはタグボートを必要とする等の問題
点があつた。そこで、本発明は上記問題点を解消
し得る堰の仮締切工法を提供することを目的とす
る。Problems to be solved by the invention Temporary coffer gate 21 shown in FIGS. 3 and 4 above,
According to No. 31, it is necessary to provide a door groove in each pier 22, 32 and to provide an intermediate door stop 23, 33, and it is time-consuming to drop the long divided bodies 21a, 31a in order. There were problems such as the need to bury supporting hardware for supporting the bodies 21a, 31a in the weir floor slabs 24, 34 and the management bridges 25, 35. Further, according to the temporary coffer gate 41 shown in FIG. 5, no special equipment is required for the weir, but a space for storing the floating body or for pulling it up is required.
There were also other problems, such as the need for a tugboat for installation. SUMMARY OF THE INVENTION Therefore, an object of the present invention is to provide a weir temporary cofferdam construction method that can solve the above-mentioned problems.
問題点を解決するための手段
上記問題点を解決するため、本発明の堰の仮締
切工法は、上下方向所定間隔置きで複数本の索体
を堰の全幅に亘つて張架し、次にこれら索体に上
下方向の支持梁を複数個取付け、次にこれら支持
梁の上流側前面に止水用シートを取付けて堰の仮
締切を行う工法である。Means for Solving the Problems In order to solve the above problems, the weir temporary cofferdam construction method of the present invention involves stretching a plurality of cables across the entire width of the weir at predetermined intervals in the vertical direction, and then This is a construction method in which a plurality of vertical support beams are attached to these cables, and then a waterproof sheet is attached to the upstream front surfaces of these support beams to temporarily close the weir.
作 用
上記仮締切工法によると、ただ堰の上流側に索
体を張架するとともに、この索体に支持梁を介し
て止水用シートを取付けるだけで仮締切を行える
ため、従来のように、戸溝、支持金具などを設け
る必要がないとともに、その設置にタグボートな
どを使用する必要がない。Function According to the above temporary coffering method, temporary coffering can be performed by simply stretching the cable on the upstream side of the weir and attaching a water-stop sheet to the cable via the support beam, so it is not necessary to use the conventional cofferdam method. There is no need to provide door grooves, support fittings, etc., and there is no need to use tugboats or the like for installation.
実施例
以下、本発明の一実施例を第1図および第2図
に基づき説明する。1は例えば河口堰に設けられ
る水門で、複数個のピア2と、これらピア2,2
間に配置された複数個の主ゲート3とから構成さ
れている。そして、この水門1には、主ゲート3
の保守、点検のために、任意の主ゲート3の水路
を遮断する仮締切装置4が具備されている。この
仮締切装置4は、水路両側の堤体5上に設置され
た複数個のウインチ6と、これらウインチ6に巻
付けられるとともに堰の全幅すなわち両堤体5,
5間に亘つえしかも上下に複数本(例えば4本)
張架可能にされた索体7と、これら索体7の上流
側前面に取付け取外し自在にされた複数個の支持
梁8と、これら支持梁8の上流側前面に取付け取
外し自在にされた止水用シート9と、堤体5側の
両側ピア2の前面に複数個設けられた索体7の案
内用滑車10とから構成されている。Embodiment An embodiment of the present invention will be described below with reference to FIGS. 1 and 2. 1 is a water gate installed, for example, at an estuary weir, and has a plurality of piers 2 and these piers 2, 2.
It is composed of a plurality of main gates 3 arranged in between. And this water gate 1 has main gate 3.
For maintenance and inspection purposes, a temporary closing device 4 is provided to shut off the waterway of any main gate 3. This temporary coffering device 4 includes a plurality of winches 6 installed on the embankment bodies 5 on both sides of the waterway, and is wound around these winches 6 and covers the entire width of the weir, that is, both embankment bodies 5.
5 canes, and multiple canes above and below (for example, 4 canes)
A rope body 7 that can be stretched, a plurality of support beams 8 that can be attached and detached from the upstream front surfaces of these rope bodies 7, and a stop that can be attached and detached from the upstream front surfaces of these support beams 8. It is composed of a water sheet 9 and a plurality of guiding pulleys 10 for the cables 7 provided on the front surface of both piers 2 on the bank body 5 side.
次に、主ゲートの保守、点検時の仮締切工法に
ついて説明する。例えば、第1図および第2図に
おいて、左側から2番目の主ゲート3Aにおける
水路を締切る場合、両側のウインチ6を操作して
上下に複数個の索体7を堰全幅に亘つて張架す
る。次に、上記主ゲート3Aの両側のピア2,2
間位置で所定間隔置きに複数個の支持梁8を上下
方向でもつて各索体7の前面に固定金具(図示せ
ず)により取付ける。次に、これら支持梁8の前
面に止水用シート9を配置して所定ピア2,2間
の水路を遮断する。この状態で、主ゲート3を上
昇させれば、水は止水用シート9によつてせき止
められる。なお、止水用シート9にかかる水圧力
は索体7を介してピア2およびウインチに支持さ
れ、また索体7の張り具合はウインチ6にようて
調整される。このように、水圧力は索体7を介し
て支持されるので、戸溝および中間戸当りによつ
て支持する場合に比べてピアすなわち堰に及ぼす
悪影響はほとんどない。 Next, we will explain the temporary cofferdam construction method for maintenance and inspection of the main gate. For example, in FIGS. 1 and 2, when closing off the waterway at the second main gate 3A from the left, the winches 6 on both sides are operated to stretch multiple ropes 7 vertically across the entire width of the weir. do. Next, the piers 2, 2 on both sides of the main gate 3A
A plurality of support beams 8 are vertically attached at predetermined intervals to the front surface of each cable body 7 using fixing fittings (not shown). Next, a water stop sheet 9 is placed on the front surface of these support beams 8 to block the waterway between the predetermined piers 2 . If the main gate 3 is raised in this state, the water will be stopped by the water stop sheet 9. The water pressure applied to the water stop sheet 9 is supported by the pier 2 and the winch via the cable 7, and the tension of the cable 7 is adjusted by the winch 6. Since the water pressure is thus supported through the cables 7, there is little negative effect on the pier or weir compared to the case where it is supported by the doorway and intermediate doorstop.
そして、主ゲートの保守、点検が終了すれば、
主ゲート3Aを降ろした後、上記とは逆の手順に
より、止水用シート9、支持梁8、索体7を取外
せばよい。 Once the maintenance and inspection of the main gate is completed,
After lowering the main gate 3A, the water-stopping sheet 9, support beam 8, and cable body 7 may be removed by the reverse procedure to the above.
ところで、上記実施例においては、支持梁8を
所定間隔置きに複数個設けたが、例えば隣同志が
接触するように詰めて設けるようにしてもよい。 Incidentally, in the above embodiment, a plurality of support beams 8 are provided at predetermined intervals, but they may be provided close together, for example, so that adjacent ones are in contact with each other.
発明の効果
上記本発明の仮締切工法によると、堰の前面に
索体を張架し、この索体に支持梁を介して止水用
シートを取付ける方法であるため、従来のように
戸溝を形成したり、また中間戸当りを設置する必
要がないとともに長尺分割体の支持金物を埋設す
る必要がなく、さらに浮体のように、格納ドツク
およびタグボートを必要としないなどの利点があ
る。Effects of the Invention According to the above temporary cofferdam construction method of the present invention, a rope is stretched in front of a weir and a water-stop sheet is attached to this rope via a support beam. There is no need to form a bridge or install an intermediate door stop, there is no need to bury support hardware for the long divided body, and there is also no need for storage docks and tugboats unlike with floating bodies.
第1図および第2図は本発明の一実施例を示す
もので、第1図は全体正面図、第2図は同平面
図、第3図〜第5図は従来例の断面図である。
4……仮締切装置、5……堤体、6……ウイン
チ、7……索体、8……支持梁、9……止水用シ
ート。
1 and 2 show an embodiment of the present invention, FIG. 1 is an overall front view, FIG. 2 is a plan view of the same, and FIGS. 3 to 5 are sectional views of a conventional example. . 4... Temporary coffering device, 5... Embankment body, 6... Winch, 7... Cable body, 8... Support beam, 9... Water stop sheet.
Claims (1)
全幅に亘つて張架し、次にこれら索体に上下方向
の支持梁を複数個取付け、次にこれら支持梁の上
流側前面に止水用シートを取付けて堰の仮締切を
行うことを特徴とする堰の仮締切工法。1. A plurality of cables are strung across the entire width of the weir at predetermined intervals in the vertical direction, and then a plurality of vertical support beams are attached to these cables. A temporary cofferdam construction method for a weir, which is characterized by installing a water sheet and temporarily closing the weir.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19198987A JPS6436814A (en) | 1987-07-31 | 1987-07-31 | Temporary coffering work of dam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19198987A JPS6436814A (en) | 1987-07-31 | 1987-07-31 | Temporary coffering work of dam |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6436814A JPS6436814A (en) | 1989-02-07 |
| JPH0566444B2 true JPH0566444B2 (en) | 1993-09-21 |
Family
ID=16283770
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP19198987A Granted JPS6436814A (en) | 1987-07-31 | 1987-07-31 | Temporary coffering work of dam |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6436814A (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2750542B2 (en) * | 1989-08-24 | 1998-05-13 | 関西電力株式会社 | Downstream waterway of ultra-low head hydropower station |
| JP4711121B2 (en) * | 2005-01-05 | 2011-06-29 | ソニー株式会社 | LENS DEVICE AND IMAGING DEVICE HAVING LENS DEVICE |
| JP4855001B2 (en) * | 2005-07-25 | 2012-01-18 | Hoya株式会社 | Imaging module |
| JP7587223B2 (en) * | 2021-02-05 | 2024-11-20 | 豊国工業株式会社 | Membrane water stop device |
-
1987
- 1987-07-31 JP JP19198987A patent/JPS6436814A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6436814A (en) | 1989-02-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP3469145B1 (en) | Method and system for a retractable floodwall system | |
| JP4787197B2 (en) | Bridge water conveyance structure and its construction method | |
| US9267253B2 (en) | Land-mounted flap gate | |
| IE46678B1 (en) | Improvements in or relating to a port ramp for access to a roll-on roll-off ship | |
| JPH0566444B2 (en) | ||
| KR101095652B1 (en) | Hydraulic Conductive Hydro Lock | |
| JP2021063436A (en) | Settling and fixing method for box body constituting temporary cofferdam body, and fixing structure | |
| US5642963A (en) | Spillway gate system | |
| JP4550233B2 (en) | Movable waterproof device | |
| JP2003129762A (en) | Water-driven waterproof device | |
| JP7774180B1 (en) | Temporary cofferdam and its construction method | |
| JP7774179B1 (en) | Temporary cofferdam and its construction method | |
| JP3412100B2 (en) | Construction method of tide gate | |
| JPS5914499Y2 (en) | Corner removal device | |
| JP2003261921A (en) | Water gate system | |
| JPS5934595Y2 (en) | Corner drop | |
| JP2005002741A (en) | Bridge for tide gate | |
| RU2010910C1 (en) | Hydraulic-engineering gate to cover water-passing and ships-passing openings | |
| EP0029432B1 (en) | A method and means for laying a web in a submerged condition | |
| DE3001305A1 (en) | Coastal or inland water protection system - has arrayed and tiered overlapping prefab concrete platform sheaths | |
| SU1209750A1 (en) | Dam | |
| RU2262631C2 (en) | Method of building underground pipeline on tectonic fracture sections | |
| JP2003214051A (en) | Flooding preventive weir | |
| RU2000384C1 (en) | Sea protecting fence structure | |
| JPH04363407A (en) | Building work method for wide area tank |