JPH0619144B2 - Sloping ground structure - Google Patents
Sloping ground structureInfo
- Publication number
- JPH0619144B2 JPH0619144B2 JP10554989A JP10554989A JPH0619144B2 JP H0619144 B2 JPH0619144 B2 JP H0619144B2 JP 10554989 A JP10554989 A JP 10554989A JP 10554989 A JP10554989 A JP 10554989A JP H0619144 B2 JPH0619144 B2 JP H0619144B2
- Authority
- JP
- Japan
- Prior art keywords
- ground
- sloping
- underground
- sloped
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 この発明は傾斜地にその地形を可能な限り残したままで
建設される傾斜地盤上構造物に関するものである。Description: TECHNICAL FIELD The present invention relates to a sloping ground structure constructed on a sloping land with the topography left as much as possible.
傾斜地では、その上に建設される建物の計画に合わせて
切土、盛土、斜面の整地等大規模な造成工事を行う必要
があるが、傾斜地に於ける造成工事は平地よりコスト高
となるだけでなく、地形の形質変更を伴うことにより地
滑り、地盤の崩壊を招く恐れがある。On a sloping land, it is necessary to carry out large-scale construction work such as cutting, embankment and leveling of slopes according to the plan of the building to be built on it, but the construction work on a sloping land will only cost more than flat land. In addition, landslides and ground collapse may occur due to changes in the terrain characteristics.
又、自然破壊の問題もある。There is also the problem of natural destruction.
更に、傾斜地に地形により構造物の形態も大きく左右さ
れることが多く、設計がしにくい。Further, the shape of the structure is often greatly influenced by the terrain on the sloping land, which makes it difficult to design.
この発明はこのような前記従来の問題点を解消する為に
提案されたもので、傾斜地に建物を建設する際に、造成
工事を可能な限り少なくすることができると共に、可能
な限り自然環境を残したままで地上構造物を建設するこ
とができ、しかも地上構造物を建設する上でのプラニン
グの自由度を著しく高めることができる傾斜地盤構造物
を提供することを目的とするものである。The present invention has been proposed in order to eliminate the above-mentioned conventional problems, and when constructing a building on a sloping land, it is possible to reduce the construction work as much as possible, and to keep the natural environment as much as possible. It is an object of the present invention to provide a sloping ground structure capable of constructing a ground structure while leaving it as it is, and further significantly increasing the degree of freedom of planning in constructing the ground structure.
この発明は傾斜地に、その地形及び自然環境を可能な限
り残したままで、地上構造物を建設することができる傾
斜地盤構造物に関するもので、傾斜地盤上に当該傾斜地
盤の傾斜方向に添って階段状をなす地中梁を傾斜地盤の
幅方向に添つて一定間隔置きに設置するか、若しくは傾
斜地盤中に当該傾斜地盤の傾斜方向に連続し、且つ上端
が階段状をなす地中連続壁を傾斜地盤の幅方向に一定間
隔置きに構成すると共に、当該地中連続壁上端の水平部
分間に人工地盤を、垂直部分間に擁壁をそれぞれ設けた
構成とすることにより前記目的を達成するものである。The present invention relates to a sloping ground structure capable of constructing a ground structure on a sloping land while keeping its topography and natural environment as much as possible. The present invention relates to a sloping ground, and stairs along the inclination direction of the sloping ground. -Shaped underground beams are installed along the width direction of the sloping ground at regular intervals, or in the sloping ground, a continuous underground wall that is continuous in the sloping direction of the sloping ground and has an upper end that is stepped Achieving the above-mentioned object by constructing the artificial ground between the horizontal portions of the upper end of the underground continuous wall and the retaining wall between the vertical portions, respectively, at a constant interval in the width direction of the sloping ground Is.
以下、この発明を図示する一実施例によって説明する。 Hereinafter, the present invention will be described with reference to an illustrated embodiment.
傾斜地盤1の上に複数の地中梁2が傾斜地盤1の傾斜方
向に添って段階状に連続して構成され、且つ傾斜地盤1
の幅方向に一定間隔置きに構成されている。On the sloping ground 1, a plurality of underground beams 2 are continuously formed in stages along the inclination direction of the sloping ground 1, and the sloping ground 1
Are arranged at regular intervals in the width direction.
地中梁2は鉄骨、鉄筋コンクリート若しくは鉄骨鉄筋コ
ンクリートより構成されている。The underground beam 2 is made of steel, reinforced concrete or steel reinforced concrete.
地中梁2の施工方法としては、完全な現場施工とする場
合と予め複数部分に工場生産し、これを現場に於いて組
み立てるプレハブ工法がある。As a method of constructing the underground beam 2, there are a case of complete on-site construction and a prefabricated construction method in which a plurality of parts are factory-produced in advance and then assembled on site.
尚、地中梁2の構造形式及び断面の大きさは傾斜地盤1
の地質及びその上に構築される地上構造物の種類、規模
によって適宜決められるものである。In addition, the structure type and the size of the cross section of the underground beam 2 are the sloped ground 1
It is decided as appropriate according to the geology of the above and the type and scale of the above-ground structure constructed on it.
地中梁2,2の水平部分2a,2a間には人工地盤3
が、垂直部分2b,2b間には擁壁4がそれぞれ水平部
分2a及び垂直部分2bとそれぞれ一体的に構成されて
いる。An artificial ground 3 is provided between the horizontal portions 2a, 2a of the underground beams 2, 2.
However, the retaining wall 4 is integrally formed with the horizontal portion 2a and the vertical portion 2b between the vertical portions 2b and 2b.
人工地盤3及び擁壁4は鉄筋コンクリート若しくは鉄骨
鉄筋コンクリートより構成され、その断面は地中梁2と
同様に地上構造物の種類、規模等によって決められる。The artificial ground 3 and the retaining wall 4 are made of reinforced concrete or steel-framed reinforced concrete, and the cross section thereof is determined by the type and scale of the above-ground structure like the underground beam 2.
人工地盤3及び擁壁4の施工方法としては、地中梁2と
同様に完全な現場施工とする場合と予め複数部分に工場
生産し、これを現場に於いて組み立てるプレハブ工法が
ある。As a construction method of the artificial ground 3 and the retaining wall 4, there are a case where the construction is completed on-site like the case of the underground beam 2 and a prefabricated construction method in which a plurality of parts are factory-produced in advance and assembled on site.
そして、人工地盤3の上に当初計画の地上構造物5が建
設される。Then, the initially planned ground structure 5 is constructed on the artificial ground 3.
尚、人工地盤3を設けないで傾斜地盤1上の植え込み6
をそのまま残し、自然の景観を可能な限り残すこともあ
る。In addition, the planting 6 on the sloping ground 1 without providing the artificial ground 3
May be left as is, leaving as much of the natural landscape as possible.
第2図はこの発明の第2実施例を示したもので、地中梁
2を傾斜地盤1の傾斜方向に添って略直線状に構成する
と共に、当該地中梁2の上端を階段状とし、更に地中梁
2を複数本のアースアンカー7,…によって傾斜地盤1
に強固にアンカーしたもので、その他の構成は第一の実
施例と略同じである。FIG. 2 shows a second embodiment of the present invention, in which the underground beam 2 is formed in a substantially linear shape along the inclination direction of the sloping ground 1, and the upper end of the underground beam 2 is made into a stepped shape. , The ground beam 2 and a plurality of earth anchors 7, ...
It is firmly anchored to, and the other structure is almost the same as that of the first embodiment.
第3図はこの発明の第3実施例を示したもので、傾斜地
盤1に地中梁2を造成する代わりに傾斜地盤1の傾斜方
向に連続する地中連続壁8を構成すると共に、当該地中
連続壁8の上端を階段状に形成し、且つ当該地中連続壁
8の水平部分8a,8a間に人工地盤3を、垂直部分8
b,8b間に擁壁4を構成したもので、その他の構成は
第1図及び第2図の実施例と略同じである。FIG. 3 shows a third embodiment of the present invention. Instead of constructing the subterranean beam 2 on the sloping ground 1, a continuous underground wall 8 which is continuous in the sloping direction of the sloping ground 1 is formed. The upper end of the underground continuous wall 8 is formed stepwise, and the artificial ground 3 is provided between the horizontal portions 8a of the underground continuous wall 8 and the vertical portion 8a.
The retaining wall 4 is formed between b and 8b, and other configurations are substantially the same as those of the embodiment shown in FIGS. 1 and 2.
尚、地中連続壁8は傾斜地盤1中に鉄筋コンクリート
杭、鉄骨鉄筋コンクリート杭若しくはPC杭を連続的に
打ち込むか若しくは現場打ちコンクリート杭を構築する
ことによって構成されている。The underground continuous wall 8 is constructed by continuously driving a reinforced concrete pile, a steel frame reinforced concrete pile, or a PC pile in the sloping ground 1, or constructing a cast-in-place concrete pile.
この発明は以上の構成からなるので、以下の効果を有す
る。Since the present invention is configured as described above, it has the following effects.
傾斜地盤の勾配、位置に関係なく自然環境を可能な限り
残したままで傾斜地盤の上に人工地盤を構築できる為、
構造工事の簡略化、造成工事費の化減化が図れると共
に、地上構造物を構築する上でのプラニングの自由度を
著しく高めることができる。Regardless of the slope and position of the sloping ground, you can build an artificial ground on the sloping ground while leaving the natural environment as much as possible,
The structural work can be simplified, the construction cost can be reduced, and the degree of freedom of the planning in constructing the above-ground structure can be significantly increased.
第1図、第2図及び第3図はこの発明の一実施例を示し
たもので、何も傾斜地盤構造物の斜視図である。 1……傾斜地盤、2……地中梁、2a……水平部分 2b……垂直部分、3……人工地盤、4……擁壁、 5……地上構造物、6……植え込み、 7……アースアンカー、8……地中連続壁、 8a……水平部分、8b……垂直部分。FIG. 1, FIG. 2 and FIG. 3 show an embodiment of the present invention, which is a perspective view of an inclined ground structure. 1 ... sloping ground, 2 ... underground beam, 2a ... horizontal part, 2b ... vertical part, 3 ... artificial ground, 4 ... retaining wall, 5 ... ground structure, 6 ... planting, 7 ... ... Earth anchor, 8 ... Underground continuous wall, 8a ... Horizontal part, 8b ... Vertical part.
Claims (4)
段状をなす地中梁を傾斜地盤の横方向に一定間隔置きに
構成し、当該地中梁の水平部分間に人工地盤を、垂直部
分間に擁壁をそれぞれ構成してなることを特徴とする傾
斜地盤構造物。Claims: 1. On the sloped ground, underground beams having a step shape in the inclination direction of the sloped ground are arranged at regular intervals in the lateral direction of the sloped ground, and artificial ground is provided between horizontal portions of the grounded beam. A sloping ground structure characterized by comprising retaining walls between vertical portions.
続する地中梁を傾斜地盤の幅方向に一定間隔置きに構成
すると共に、当該地中梁の上端を階段状に形成し、且つ
前記地中梁の水平部分間に人工地盤を、垂直部分間に擁
壁をそれぞれ構成してなることを特徴とする傾斜地盤構
造物。2. An underground beam, which is continuous in the direction of inclination of the sloped ground, is arranged on the sloped ground at regular intervals in the width direction of the sloped ground, and the upper end of the grounded beam is formed in a step shape, and An inclined ground structure characterized in that an artificial ground is formed between horizontal portions of the underground beam and a retaining wall is formed between vertical portions thereof.
続する地中連続壁を傾斜地盤の横方向に一定間隔おきに
設けると共に、当該地中連続壁上端の水平部分間に人工
地盤を、垂直部分間に擁壁をそれぞれ構成してなること
を特徴とする傾斜地盤構造物。3. An underground ground wall which is continuous in the slope direction of the slope ground is provided in the slope ground at regular intervals in the lateral direction of the slope ground, and artificial ground is provided between the horizontal portions of the upper end of the ground ground wall. , A sloping ground structure characterized by comprising retaining walls between vertical portions.
筋コンクリート杭、PC杭より構成してあることを特徴
とする請求項第3項記載の傾斜地盤構造物。4. The sloping ground structure according to claim 3, wherein the underground continuous wall is composed of a reinforced concrete pile, a steel frame reinforced concrete pile, and a PC pile.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10554989A JPH0619144B2 (en) | 1989-04-25 | 1989-04-25 | Sloping ground structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10554989A JPH0619144B2 (en) | 1989-04-25 | 1989-04-25 | Sloping ground structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH02282519A JPH02282519A (en) | 1990-11-20 |
| JPH0619144B2 true JPH0619144B2 (en) | 1994-03-16 |
Family
ID=14410655
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP10554989A Expired - Lifetime JPH0619144B2 (en) | 1989-04-25 | 1989-04-25 | Sloping ground structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0619144B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001234634A (en) * | 2000-02-24 | 2001-08-31 | Ingu:Kk | Hierarchical building built using sloping land |
| JP2010255309A (en) * | 2009-04-24 | 2010-11-11 | Takenaka Komuten Co Ltd | Foundation structure for structure |
-
1989
- 1989-04-25 JP JP10554989A patent/JPH0619144B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH02282519A (en) | 1990-11-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4653962A (en) | Retaining wall construction and method of manufacture | |
| JP2007154413A (en) | Soldier pile type earth retaining anchor type retaining wall and its construction method | |
| US5870789A (en) | Precast bridges | |
| CN111304988A (en) | Light embankment structure built on high and steep hillside and construction method | |
| JPH0619144B2 (en) | Sloping ground structure | |
| JP2868651B2 (en) | Earth retaining method above existing underground structure | |
| JPH07119549B2 (en) | Twin tunnel | |
| JP3244324B2 (en) | Mountain retaining method | |
| JPH0533346A (en) | Greening reinforcing earthwork construction and greening block | |
| JP2003119787A (en) | Greening structure of construction | |
| JP2000257088A (en) | Earth retaining wall and its construction method | |
| JPH07158085A (en) | Simple underground construction method | |
| JP2554507B2 (en) | Underground space construction method | |
| KR0180072B1 (en) | Slope construction | |
| JPS6011168Y2 (en) | Earth retaining wall structure for slopes | |
| KR100346947B1 (en) | The SEN Retaining Wall | |
| JP2523234B2 (en) | Anchor retaining wall | |
| JP4423390B2 (en) | Construction method of slope protection retaining wall | |
| JP2785828B2 (en) | Steep slope construction method for existing embankment slope | |
| JP2003055959A (en) | Soil cement column line earth retaining wall and earth retaining method | |
| JPH0790863A (en) | Retaining wall for embankment | |
| JPH04115016A (en) | Earth retaining wall in weak foundation and method of retaining earth | |
| JP2842146B2 (en) | Underground foundation structure | |
| JP3012215B2 (en) | Building structures using piles as pillars | |
| JPH08134913A (en) | Soil retaining method |