Retractable crane

Info

Publication number
JPH0633154B2
JPH0633154B2 JP1745891A JP1745891A JPH0633154B2 JP H0633154 B2 JPH0633154 B2 JP H0633154B2 JP 1745891 A JP1745891 A JP 1745891A JP 1745891 A JP1745891 A JP 1745891A JP H0633154 B2 JPH0633154 B2 JP H0633154B2
Authority
JP
Japan
Prior art keywords
sheave
link
boom
top boom
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1745891A
Other languages
Japanese (ja)
Other versions
JPH04213591A (en
Inventor
清志 鈴木
清 五味
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP1745891A priority Critical patent/JPH0633154B2/en
Publication of JPH04213591A publication Critical patent/JPH04213591A/en
Publication of JPH0633154B2 publication Critical patent/JPH0633154B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Jib Cranes (AREA)

Description

【発明の詳細な説明】 【0001】 【産業上の利用分野】本発明は引込みクレーンに係り、
コンテナのような場合の4点吊り、バケットやフックの
ような2点吊りをそれぞれ可能とする多目的用の引込み
クレーンに関する。 【0002】 【従来の技術】引込みクレーンは、基台上に設けられた
マスト、このマスト下部に回動自在に取付けられたメイ
ンブーム、このメインブーム先端に回動自在に装着さ
れ、かつ吊荷を支持するトップブーム、このトップブー
ムの他端側をマット側に引張るテンションブームと、ト
ップブームの先端に設けられたシーブに巻回された巻上
ロープによって吊持される吊具、巻上ロープを巻上げる
ドラム、メインブームの押出し引込みを行なう引込み装
置などを具備している。このような引込みクレーンは、
例えば、特開昭54−67955号、特開昭54−12
2551号、特開昭55−35765号などに明らかで
ある。 【0003】吊具の種類によってロープから吊具への吊
ヶ所は変わる。 【0004】コンテナを取扱う吊具の吊点は4ヶ所あ
り、またバケットの場合は、吊点が2ヶ所、バケットの
開閉用の1ヶ所の計3ヶ所であり、またフックの場合は
2ヶ所である。 【0005】従来、バケットやフックを吊る場合には、
前記公報の如くトップブームの先端のシーブから全ての
ロープを吊下げて行っている。 【0006】コンテナを吊る場合には、実開昭53−6
7261号公報に示す如く、トップブームの先端側に向
けて水平に突出させた第1のリンクをトップブームの先
端に回動自在に設け、メインブームの先端又はテンショ
ンブームの先端をトップブームとの連結点を超えて突出
させた部分と第1のリンクの先端とを第2のリンクで接
続し、トップブームの先端のシーブ、リンクの先端のシ
ーブからコンテナ用の吊具を吊下げている。 【0007】 【発明が解決しようとする課題】上記実開昭53−67
261号公報の引込みクレーンはコンテナを吊るために
第1のリンクと第2のリンクを有するので、バケットや
フックを吊る場合にはこの二つのリンクを除くことが必
要である。 【0008】このように、吊具を変更するときには、リ
ンク等の着脱を必要としており、交換作業が面倒で、し
かも高所での作業であるので非常に危険であった。 【0009】本発明の目的は吊具の吊り方を簡単に変更
できるようにすることにある。 【0010】 【課題を解決するための手段】本発明は、トップブーム
の先端側に回動自在に設けたリンクと、該リンクの先端
側に設置されており、該リンクを前記トップブームの下
方側に回動させたとき該トップブームの先端側に設置し
た第1のシーブから吊下げられたロープの少くとも1本
を支えることが可能な第3のシーブと、前記リンクの先
端側に接続された可撓性の部材を介して該リンクを回動
させるものであり、前記マストに設置した操作装置と、
前記操作装置の操作によって全ての前記ロープを前記第
1のシーブの先端から下方に吊下げた状態のときであっ
て、前記トップブームを最小回転半径近傍にしたとき、
前記可撓性の部材が前記第1のシーブに接触しないよう
に、該可撓性の部材に接触するものであって前記トップ
ブームの下面に下方に突出して設置したストッパと、か
らなることを特徴とするものである。 【0011】 【作用】操作装置を動作させると、可撓性の部材を介し
てリンクが回動する。操作装置を用いて可撓性の部材を
引張ると、リンクが引張られ、リンクはトップブームの
下方に位置する。このとき、リンクに設置した第3のシ
ーブは少くとも1本のロープをトップブームの下方側か
ら吊下げる。操作装置を用いて可撓性の部材を戻すと、
リンクはトップブームの先端側に戻り、全てのロープが
トップブームの先端の第1のシーブから垂直方向に吊下
がる。以上のように、操作装置を操作することによっ
て、吊点を容易に変更することができる。全てのロープ
を第1のシーブから垂直方向に吊下げており、かつ、例
えば、トップブームを最小回転半径近傍にしたとき、ト
ップブームの下面のストッパが可撓性の部材に接触する
ので、該可撓性の部材が第1のシーブに接触するのを防
止する。 【0012】 【実施例】以下、本発明の詳細を図に示す一実施例によ
り説明する。 【0013】図1において、1は走行体2に載置した旋
回体であり、水平面で旋回する。旋回体1には以下の装
置が載っている。5はメインブームで、引込み装置6に
よって回動する。引込み装置6はマスト7に取付けてい
る。メインブーム5の先端にはトップブーム8が回動自
在に取付けられている。トップブーム8の後端とマスト
7との間はテンションブーム9で連結している。10は
釣合用の錘である。 【0014】図1〜図6に示すように、マスト7の側面
先端、トップブーム8の後端および先端には4本のロー
プ15a,15b,15c,15dの通るシーブ16,
17,18,19がそれぞれ設けてある。シーブ16,
17,18,19はそれぞれ4つのシーブからなる。外
側のシーブ19a,19dを通るロープ15a,15d
をドラム21に巻取るようにしている。内側のシーブ1
9b,19cを通るロープ15b,15cをドラム22
に巻取るようにしている。25はトップブーム8の先端
からリンク26で吊下げたシーブであり、ドラム27の
ロープ28で操作される。ドラム27は吊点を変更する
ための操作装置を構成する。ロープ28はメインブーム
5に沿って張られ、メインブーム5の先端のシーブ29
を通ってリンク30に連結している。リンク30はシー
ブ25と同軸で連結している。シーブ25,29は各々
2つからなり、ロープ15a,15dの鉛直下に設置し
ている。ドラム21,22,27は各々単独で運転でき
る。ドラム21と22は同期して運転できる。 【0015】トップブーム8の先端のシーブ25の周囲
の構成について、図7、図11、図12により説明す
る。以後の説明はシーブ19a,19b側について説明
するが、シーブ19c,19d側も原則として同様の構
成である。トップブーム8の先端のシーブ19と同軸状
にリンク26を回動自在に設置している。リンク26の
先端にはシーブ25、およびリンク30を回動自在に設
置している。シーブ25とリンク30は同軸である。リ
ンク30の先端にロープ28を接続している。 【0016】図11(A)のように、リンク26はシー
ブ15aを中心としてその両側において軸31に取付け
てある。リンク26の断面はH状である。 【0017】図12のように、リンク26の中心にシー
ブ25が位置し、リンク26の両側にリンク30が位置
している。板36を軸35の凹部に挿入してリンク26
にボルト37で固定し、軸35の回転および移動を防止
している。リンク30は2枚の板からなるもので、左右
2枚の板をスペーサを介してボルト41で固定して一体
にしている。 【0018】リンク26の上面側にはロープ15aを支
持可能なローラ43を設けている。ローラ43は定常時
にはロープ15aやシーブ26に接することはないが、
近接して設置している。図11(C)、図12のように
ローラ43を支持する軸44の長さLはリンク30の幅
lよりも十分に長い。またローラ43はリンク30の左
右の板の内に入ることができる。 【0019】ロープ15a,15b,15c,15dの
吊具への連結端には、例えばコッタとソケットとからな
る連結金具を設けている。図2、図3の15fはスプレ
ッダ50やバケット51の吊具のブラケットにピンを介
して連結した部分を示している。図3のバケット51の
開閉用のシーブ52や図4のフック53のシーブ54に
対しては、各々のロープ55の連結金具の間をロープ5
5で連結している。15gはこの連結部を示している。
連結部15gは両方のロープの金具にピンを通して連結
したものである。 【0020】図13〜図15はスプレッダ50への給電
ケーブル60の支持手段を示すものである。図14の如
くスプレッダ50のバスケット61はシーブ15a側の
ブーム8の側面の下方の位置に設けている。給電ケーブ
ル60は金具62でプラットフォーム63から吊下げら
れている。64はコネクタである。プラットフォーム6
3は従業員の作業場であって、ブーム8の上面に設けて
いる。68は給電ケーブル60のガイドレールであり、
凹状に溝を有し、ブーム8の側面にブラケット69,7
0で取付けている。 【0021】かかる構成における荷役作業について説明
する。 【0022】先ず、ロープ15a,15dをシーブ19
a,19dからシーブ25a,25bにかけて吊下げ
る。この場合、図11(B)の如くリンク26の穴48
から通し、ローラ43を取付ける。リンク30にロープ
28を連結する。ロープ15b,15cはシーブ19
b,19cから吊下げる。 【0023】コンテナ用のスプレッダ50を吊下げる場
合には、ロープ28をドラム27で巻上げると共にロー
プ15b,15cをドラム22で巻上げてスプレッダが
水平になる程度に引張っておく。ドラム27はその状態
で固定する。シーブ25をロープ28で引張っているの
で、ロープ15a,15dはロープ15b,15cに対
してほぼ平行に吊下がることになり、4点吊りのための
吊点間隔を保持できるものである。 【0024】そして、ドラム21,22を同期して運転
することにより、スプレッダ50の高さを調節できるも
のである。 【0025】引込み装置6の運転によってスプレッダ5
0はほぼ水平に移動させられる。トップブーム8の回動
中心にシーブ29を設けることは困難であるので、図5
の如く、トップブーム8の回動中心49とシーブ29の
取付け位置(トップブーム8に設けている)が大きく異
なる場合は、ロープ28の長さが一定であるとスプレッ
ダ50は傾斜する。スプレッダ50の傾斜量が実害のな
い程度にシーブ29の取付位置を定める。つまり、メイ
ンブーム5の長さ、トップブーム8の長さ、リンク26
の長さ、および最小回転半径、最大半径の基準に対して
スプレッダ50の傾斜量が実害のない程度にシーブ29
およびドラム27の位置を定める。又はドラム27等の
運転によってロープ28の長さを調整する。 【0026】これを若干詳細に説明すると、4点吊り時
において、スプレッダ50を水平移動させるためには、
図1,図5,図7,図8から明らかなように、メインブ
ーム5の起伏角度が変化してもリンク26の水平面に対
する傾斜角度が同一であることが必要である。つまり、
メインブーム5の起伏角度の変化に伴ってトップブーム
8に対するリンク26の傾斜角度が変化しなければなら
ない。図1と図5との比較、又、図7と図8との比較か
ら明らかなように、メインブーム5の起立角度が大きく
なると、トップブーム8の起立角度も大きくなる(図1
の想像線、図5、図8)。そして、図7と図8との比較
から明らかなように、メインブーム5(トップブーム
8)の起立角度が大きくなると、トップブーム8に対す
るリンク26の傾斜角度(ローラ43を挾んでトップブ
ーム8とリンク26とが成す角度)が大きくならなけれ
ばならない。 【0027】さて、図1から明らかなように、ロープ2
8の一端の固定位置であるドラム27の位置はメインブ
ーム5の起伏の回動点(メインブーム5とマスト7の下
部との連結点)よりも反メインブーム5側の位置にあ
る。この位置関係のため、ドラム27から軸49の近傍
のシーブ29迄の距離はメインブーム5の起伏にともな
って変化する。今、メインブーム5(トップブーム8)
の起立角度が小さい状態から大きい状態に変化すると、
前記距離は小さくなる。このため、ロープ28はマスト
7側からリンク26側に繰り出される。この繰り出し量
は一般に前記回動点に対するドラム27の位置によって
決まる。このため、図8のようにトップブーム8に対す
るリンク26の角度が大きくなり、スプレッダ50は水
平移動する。 【0028】また、シーブ29は軸49(連結点)の近
傍であって、連結点とは異なる位置のトップブーム8に
設置されているので、メインブーム5(トップブーム
8)の起立角度が小さい状態から大きい状態になると、
図1と図5との比較から明らかなように、シーブ29の
位置はトップブーム8とメインブーム5との連結点(軸
49)に対して相対的に下降する。すなわち、連結点
(軸49)とシーブ29との間の垂直距離は小さくな
る。このため、ロープ28がリンク26側に繰り出され
ることになる。この繰り出し量は一般に前記連結点(軸
49)に対するシーブ29の位置によって決まる。従っ
て、この構成からも、図8のようにトップブーム8に対
するリンク26の角度が大きくなり、スプレッダ50は
水平移動する。 【0029】給電ケーブル60を取付けるには、プラッ
トフォーム63からロープをケーブルガイド68の凹溝
に入れて垂らし、給電ケーブル60の上端側に固定した
金具62を結合してロープを引上げる。そして金具62
をプラットフォームに結合し、コネクタ64を結合させ
る。給電ケーブル60はケーブルガイド68の凹溝内に
入っている。給電ケーブル60を外す場合には逆に行
う。 【0030】これによれば、給電ケーブル60はケーブ
ルガイド68に沿って垂れ下がるので、トップブーム8
の旋回半径を最大とした図13の状態からトップブーム
8の旋回半径を最小とした図14の状態にし移動させて
も、給電ケーブル60はバスケット61内に垂れ下がる
ものである。もし、ケーブルガイド68が無い場合は、
バスケット61内に入らない場合が生ずる。例えば図1
2の状態で入るようにすれば、図15の状態で入らな
い。 【0031】次に、バケット51やフック53を吊る場
合について説明する。この場合は、図3、図4に示すよ
うにドラム27を用いてロープ28を十分に緩める。そ
して、シーブ52,54用のロープ55を結合すると共
に、吊具に連結する。ドラム21,22を適宜運転して
バケット51やフック53が水平になるようにロープ1
5の長さを調整する。吊具を吊上げるとロープ15a,
15dの張力によってシーブ25は図9、図10の如く
シーブ19よりも外側に移動し、ロープ15a,15d
は垂直に吊下がる。 【0032】トップブーム8を最小半径にした場合、図
10に示す如く、シーブ25はシーブ18,19を接続
する中心線Pよりも外側に位置するので、ロープ28を
シーブ25の軸35に直接取付けると、ロープ28がシ
ーブ19a,19dに接触したり、シーブ19a,19
dとトップブーム8との間に入り込んだりし、ロープ2
8が損傷する。 【0033】このため、リンク30を設けて、ロープ2
8がシーブ19よりも内側に位置するようにしたもので
ある。但し、リンク30はロープ28によって引張られ
てリンク26に平行になろうとする。リンク30の重量
はロープ28よりも軽く、ドラム27−シーブ29間の
方がシーブ29−シーブ25間よりも長いためである。
そこで、軸44の長さLをリンク30の幅lよりも長く
して、リンク30が軸44に当ってリンク26に平行に
ならないようにしている。これによってロープ28はシ
ーブ19よりも内側に常に位置するものである。 【0034】トップブーム8を内側から外側へ(又はそ
の逆)延して停めると、シーブ25からロープ15a,
15bが外れる可能性があり、ローラ43でこれを防止
している。このローラ43の軸44を前記リンク30の
位置決めのストッパとして兼用しているので、部材を少
くでき、軽量で安価にできるものである。 【0035】以上の如く、4点吊りするためのシーブ2
5をロープ28によって操作するようにしているので、
吊具の交換の場合の吊点の変更を極めて容易にかつ安全
に行うことができるものである。 【0036】また、4点吊り時にスプレッダ50を水平
移動させるための手段(リンク26,30,ロープ2
8,シーブ19,25等からなる)に吊点の変更のため
のドラム27を連結しているので、構成を簡単にできる
ものである。 【0037】また、ロープ28の一端側の固定端(ドラ
ム27からのロープ28の繰り出し位置)はマスト7に
あるので、水平移動させるための固定点を大きなマスト
7から選定すれば良いので、水平精度の良い固定点を容
易に選定することができるものである。また、ドラム2
7の設置位置はマスト7であるので、ドラム27の重量
による問題は他の部分(例えば、メインブーム)に比べ
て生じない。 【0038】また、シーブ25とロープ28との間にリ
ンク30を設け、かつこのリンク30の角度調整用のス
トッパ(軸44)をリンク26に設けているので、バケ
ットやフックを吊った場合にロープ28がシーブ19に
接触するのを防止できるものである。尚、リンク30は
シーブ25と同軸である必要はない。またストッパとし
ては、図10のようにブーム8のロープ28側にローラ
70を突出させて設け、ロープ28がシーブ19に接触
しないようにすることも考えられる。もちろんリンク3
0がリンク26に平行にならないようにするためのスト
ッパは必要である。また、前記ストッパをはずれ止め用
のローラ43の軸と兼用しているので、安価にできるも
のである。 【0039】フック53等の2点吊りの場合にシーブ2
5をロープ28で引張って、シーブ19,25から吊具
(フック53)までのロープを斜めに配置して使用する
こともできる。これによれば、周知のように、吊具の振
れ止めの効果がある。 【0040】シーブ25の操作装置としては、ドラム2
7の他に、ピストンシリンダ装置やスクリューロッド装
置を用いることができる。シーブ29はメインブーム5
に取付けてもよい。このシーブ25の操作装置はトップ
ブーム8とメインブーム5との結合点の近傍のトップブ
ーム8又はメインブーム5に取付けることができる。さ
らにはトップブームの先端側に寄せて取付けることもで
きる。このような場合にはロープに代えてリンクを用い
ることが可能となる。 【0041】 【発明の効果】本発明によれば、操作装置を操作するの
みで吊具の吊り方を容易に変更できると共に、その構成
を簡単にできるものである。また、トップブームの下面
に可撓性の部材(例えば、ロープ28)に接触するスト
ッパを設けているので、全てのロープをトップブームの
先端から垂直方向に吊下げているときに、トップブーム
を最小半径にした場合等において、前記可撓性の部材が
トップブームの先端のシーブに接触するのを防止できる
ものである。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a retractable crane,
The present invention relates to a multi-purpose retractable crane that enables four-point suspension in the case of containers and two-point suspension such as buckets and hooks. [0002] A retractable crane comprises a mast provided on a base, a main boom rotatably attached to a lower portion of the mast, a main boom rotatably attached to a tip of the main boom, and a suspended load. A top boom that supports the top boom, a tension boom that pulls the other end of the top boom toward the mat, and a hoisting device and a hoisting rope that are suspended by a hoisting rope that is wound around a sheave provided at the tip of the top boom It is equipped with a drum for hoisting, and a retracting device for pushing out and retracting the main boom. Such a retractable crane
For example, JP-A-54-67955 and JP-A-54-12
2551 and JP-A-55-35765. The hanging point from the rope to the hanger changes depending on the kind of the hanger. There are four hoisting points for hanging equipment for handling containers, two hoisting points for buckets and one for opening and closing buckets, and two for hooks. is there. Conventionally, when hanging a bucket or a hook,
As described in the above publication, all ropes are suspended from the sheave at the tip of the top boom. When the container is hung, the actual opening is 53-6.
As shown in Japanese Patent No. 7261, a first link horizontally projected toward the tip side of the top boom is rotatably provided at the tip of the top boom, and the tip of the main boom or the tip of the tension boom is connected to the top boom. The portion protruding beyond the connecting point and the tip of the first link are connected by the second link, and the container hanger is suspended from the sheave at the tip of the top boom and the sheave at the tip of the link. DISCLOSURE OF THE INVENTION Problems to be Solved by the Invention
Since the retractable crane of Japanese Patent No. 261 has a first link and a second link for suspending a container, it is necessary to remove these two links when suspending a bucket or a hook. [0008] As described above, when changing the suspension, it is necessary to attach and detach the links and the like, and the replacement work is troublesome and it is a work at a high place, which is very dangerous. An object of the present invention is to make it possible to easily change the suspension method of the suspension. According to the present invention, there is provided a link rotatably provided on the tip side of the top boom, and the link is installed on the tip side of the link, and the link is provided below the top boom. Connected to the tip side of the link, and a third sheave capable of supporting at least one rope suspended from the first sheave installed on the tip side of the top boom when rotated to the side The link is rotated through a flexible member that is provided, and an operating device installed on the mast,
When all the ropes are suspended from the tip of the first sheave by the operation of the operation device, and when the top boom is in the vicinity of the minimum turning radius,
A stopper that comes into contact with the flexible member so as not to come into contact with the first sheave and that is installed on the lower surface of the top boom so as to project downward. It is a feature. When the operating device is operated, the link rotates via the flexible member. When the flexible member is pulled using the operating device, the link is pulled, and the link is located below the top boom. At this time, the third sheave installed on the link suspends at least one rope from the lower side of the top boom. When the flexible member is returned using the operating device,
The links return to the tip side of the top boom and all ropes hang vertically from the first sheave at the tip of the top boom. As described above, the hanging point can be easily changed by operating the operating device. When all the ropes are suspended from the first sheave in the vertical direction, and the stopper on the lower surface of the top boom comes into contact with the flexible member, for example, when the top boom is near the minimum turning radius, Preventing the flexible member from contacting the first sheave. The details of the present invention will be described below with reference to an embodiment shown in the drawings. In FIG. 1, reference numeral 1 is a revolving structure mounted on a traveling structure 2 and revolving in a horizontal plane. The following device is mounted on the revolving structure 1. A main boom 5 is rotated by the retracting device 6. The retracting device 6 is attached to the mast 7. A top boom 8 is rotatably attached to the tip of the main boom 5. A tension boom 9 connects the rear end of the top boom 8 and the mast 7. Reference numeral 10 is a counterweight. As shown in FIGS. 1 to 6, a sheave 16, through which four ropes 15a, 15b, 15c and 15d pass, is provided at the side end of the mast 7, the rear end and the end of the top boom 8.
17, 18 and 19 are provided respectively. Sheave 16,
Each of 17, 18, and 19 consists of four sheaves. Rope 15a, 15d passing through the outer sheave 19a, 19d
Is wound around the drum 21. Inner sheave 1
The ropes 15b and 15c passing through 9b and 19c on the drum 22
I'm trying to wind it up. Reference numeral 25 is a sheave suspended from the tip of the top boom 8 by a link 26, and is operated by a rope 28 of a drum 27. The drum 27 constitutes an operating device for changing the hanging point. The rope 28 is stretched along the main boom 5 and has a sheave 29 at the tip of the main boom 5.
It is connected to the link 30 through. The link 30 is coaxially connected to the sheave 25. Each of the sheaves 25 and 29 includes two sheaves and is installed vertically below the ropes 15a and 15d. Each of the drums 21, 22, 27 can be operated independently. The drums 21 and 22 can be operated in synchronization. The structure around the sheave 25 at the tip of the top boom 8 will be described with reference to FIGS. 7, 11 and 12. In the following description, the sheaves 19a and 19b will be described, but the sheaves 19c and 19d have the same configuration in principle. A link 26 is rotatably installed coaxially with the sheave 19 at the tip of the top boom 8. A sheave 25 and a link 30 are rotatably installed at the tip of the link 26. The sheave 25 and the link 30 are coaxial. The rope 28 is connected to the tip of the link 30. As shown in FIG. 11A, the link 26 is attached to the shaft 31 on both sides of the sheave 15a with the sheave 15a as the center. The cross section of the link 26 is H-shaped. As shown in FIG. 12, the sheave 25 is located at the center of the link 26, and the links 30 are located on both sides of the link 26. The plate 36 is inserted into the recess of the shaft 35 so that the link 26
It is fixed to the shaft with a bolt 37 to prevent the shaft 35 from rotating and moving. The link 30 is composed of two plates, and the left and right two plates are fixed by bolts 41 via spacers to be integrated. A roller 43 capable of supporting the rope 15a is provided on the upper surface side of the link 26. The roller 43 does not come into contact with the rope 15a or the sheave 26 in a steady state,
Installed in close proximity. As shown in FIGS. 11C and 12, the length L of the shaft 44 supporting the roller 43 is sufficiently longer than the width 1 of the link 30. Further, the rollers 43 can enter the left and right plates of the link 30. At the connecting ends of the ropes 15a, 15b, 15c, 15d to the hanging tool, connecting fittings including, for example, a cotter and a socket are provided. 15f of FIG. 2 and FIG. 3 has shown the part connected with the bracket of the suspension tool of the spreader 50 or the bucket 51 via the pin. For the sheave 52 for opening and closing the bucket 51 of FIG. 3 and the sheave 54 of the hook 53 of FIG.
Connected with 5. 15g has shown this connection part.
The connecting portion 15g is connected to the metal fittings of both ropes through pins. FIGS. 13 to 15 show the supporting means of the power feeding cable 60 to the spreader 50. As shown in FIG. 14, the basket 61 of the spreader 50 is provided below the side surface of the boom 8 on the sheave 15a side. The power supply cable 60 is suspended from the platform 63 by a metal fitting 62. 64 is a connector. Platform 6
3 is an employee's workplace, which is provided on the upper surface of the boom 8. 68 is a guide rail of the power supply cable 60,
It has a groove in a concave shape and the brackets 69,
It is attached with 0. The cargo handling work in such a configuration will be described. First, the ropes 15a and 15d are attached to the sheave 19
Suspend from a, 19d to sheaves 25a, 25b. In this case, the hole 48 of the link 26 as shown in FIG.
Then, the roller 43 is attached. The rope 28 is connected to the link 30. Rope 15b, 15c is sheave 19
Suspend from b, 19c. When the spreader 50 for a container is suspended, the rope 28 is wound up on the drum 27 and the ropes 15b and 15c are wound up on the drum 22 and pulled so that the spreader becomes horizontal. The drum 27 is fixed in that state. Since the sheave 25 is pulled by the rope 28, the ropes 15a and 15d are suspended substantially parallel to the ropes 15b and 15c, and the suspension point intervals for four-point suspension can be maintained. The height of the spreader 50 can be adjusted by operating the drums 21 and 22 in synchronization. The spreader 5 is operated by operating the retractor 6.
0 is moved almost horizontally. Since it is difficult to provide the sheave 29 at the center of rotation of the top boom 8, FIG.
As described above, when the rotation center 49 of the top boom 8 and the mounting position of the sheave 29 (provided on the top boom 8) are significantly different, the spreader 50 tilts if the length of the rope 28 is constant. The mounting position of the sheave 29 is determined so that the spread amount of the spreader 50 is not harmful. That is, the length of the main boom 5, the length of the top boom 8, the link 26
Of the sheave 29 to the extent that the inclination of the spreader 50 is not harmful to the reference of the length and the minimum turning radius and the maximum radius.
And the position of the drum 27 is determined. Alternatively, the length of the rope 28 is adjusted by operating the drum 27 or the like. Explaining this in a little more detail, in order to move the spreader 50 horizontally during four-point suspension,
As is clear from FIG. 1, FIG. 5, FIG. 7, and FIG. 8, it is necessary that the inclination angle of the link 26 with respect to the horizontal plane be the same even if the hoisting angle of the main boom 5 changes. That is,
The inclination angle of the link 26 with respect to the top boom 8 must change in accordance with the change in the up-and-down angle of the main boom 5. As is clear from the comparison between FIG. 1 and FIG. 5 and the comparison between FIG. 7 and FIG. 8, as the rising angle of the main boom 5 increases, the rising angle of the top boom 8 also increases (FIG. 1).
Imaginary line of FIG. 5, FIG. 8). Then, as is clear from the comparison between FIG. 7 and FIG. 8, when the standing angle of the main boom 5 (top boom 8) becomes large, the inclination angle of the link 26 with respect to the top boom 8 (the top boom 8 with the roller 43 sandwiched between The angle formed by the link 26 must be increased. Now, as is clear from FIG. 1, the rope 2
The position of the drum 27, which is a fixed position at one end of 8, is located on the side opposite to the main boom 5 side from the pivoting point of the ups and downs of the main boom 5 (the connection point between the main boom 5 and the lower part of the mast 7). Due to this positional relationship, the distance from the drum 27 to the sheave 29 near the shaft 49 changes as the main boom 5 rises and falls. Now, main boom 5 (top boom 8)
When the standing angle of changes from a small state to a large state,
The distance becomes smaller. Therefore, the rope 28 is paid out from the mast 7 side to the link 26 side. This feeding amount is generally determined by the position of the drum 27 with respect to the turning point. Therefore, the angle of the link 26 with respect to the top boom 8 becomes large as shown in FIG. 8, and the spreader 50 moves horizontally. Further, since the sheave 29 is installed in the top boom 8 near the shaft 49 (connection point) and at a position different from the connection point, the standing angle of the main boom 5 (top boom 8) is small. From the state to the big state,
As is clear from the comparison between FIG. 1 and FIG. 5, the position of the sheave 29 is relatively lowered with respect to the connection point (the shaft 49) between the top boom 8 and the main boom 5. That is, the vertical distance between the connecting point (axis 49) and the sheave 29 becomes smaller. Therefore, the rope 28 is paid out to the link 26 side. This amount of extension is generally determined by the position of the sheave 29 with respect to the connecting point (axis 49). Therefore, also from this configuration, the angle of the link 26 with respect to the top boom 8 becomes large as shown in FIG. 8, and the spreader 50 moves horizontally. In order to mount the power supply cable 60, the rope is inserted from the platform 63 into the groove of the cable guide 68 and hung down, and the metal fitting 62 fixed to the upper end side of the power supply cable 60 is connected and the rope is pulled up. And metal fittings 62
To the platform and connector 64. The power supply cable 60 is placed in the groove of the cable guide 68. When removing the power supply cable 60, the procedure is reversed. According to this, since the power feeding cable 60 hangs down along the cable guide 68, the top boom 8
Even when the top boom 8 is moved from the state of FIG. 13 where the turning radius is maximum to the state of FIG. 14 where the turning radius of the top boom 8 is minimum, the power feeding cable 60 hangs down in the basket 61. If there is no cable guide 68,
In some cases, it may not fit in the basket 61. Figure 1
If it enters in the state of 2, it will not enter in the state of FIG. Next, the case of suspending the bucket 51 and the hook 53 will be described. In this case, as shown in FIGS. 3 and 4, the drum 28 is used to loosen the rope 28 sufficiently. Then, the ropes 55 for the sheaves 52, 54 are joined together, and also connected to the hanger. Operate the drums 21 and 22 appropriately so that the bucket 51 and the hook 53 become horizontal.
Adjust the length of 5. If you lift the hanger, rope 15a,
The sheave 25 is moved to the outside of the sheave 19 by the tension of 15d as shown in FIGS.
Hangs vertically. When the top boom 8 has a minimum radius, as shown in FIG. 10, the sheave 25 is located outside the center line P connecting the sheaves 18 and 19, so that the rope 28 is directly attached to the shaft 35 of the sheave 25. When attached, the rope 28 comes into contact with the sheaves 19a, 19d, and the sheaves 19a, 19d.
d between the d and the top boom 8 and the rope 2
8 is damaged. For this reason, the link 30 is provided and the rope 2
8 is located inside the sheave 19. However, the link 30 is pulled by the rope 28 and tends to be parallel to the link 26. This is because the weight of the link 30 is lighter than the rope 28, and the distance between the drum 27 and the sheave 29 is longer than that between the sheave 29 and the sheave 25.
Therefore, the length L of the shaft 44 is made longer than the width 1 of the link 30 so that the link 30 does not hit the shaft 44 and become parallel to the link 26. As a result, the rope 28 is always located inside the sheave 19. When the top boom 8 is extended from the inner side to the outer side (or vice versa) and then stopped, the sheave 25 pulls the rope 15a,
15b may come off, and the roller 43 prevents this. Since the shaft 44 of the roller 43 is also used as a stopper for positioning the link 30, the number of members can be reduced, and the weight and cost can be reduced. As described above, the sheave 2 for suspending four points
Since 5 is operated by the rope 28,
This makes it possible to extremely easily and safely change the suspension point when replacing the suspension. Also, means for horizontally moving the spreader 50 when suspending at four points (links 26, 30, rope 2)
The drum 27 for changing the suspension point is connected to (8, sheaves 19, 25, etc.), so that the structure can be simplified. Since the fixed end on one end side of the rope 28 (the position where the rope 28 is paid out from the drum 27) is on the mast 7, the fixed point for horizontal movement may be selected from the large mast 7. It is possible to easily select an accurate fixed point. Also, drum 2
Since the installation position of 7 is the mast 7, the problem due to the weight of the drum 27 does not occur compared to other parts (for example, the main boom). Further, since the link 30 is provided between the sheave 25 and the rope 28 and the stopper (shaft 44) for adjusting the angle of the link 30 is provided on the link 26, when a bucket or a hook is hung, The rope 28 can be prevented from coming into contact with the sheave 19. The link 30 need not be coaxial with the sheave 25. As a stopper, it is also possible to provide a roller 70 protruding toward the rope 28 side of the boom 8 so as to prevent the rope 28 from coming into contact with the sheave 19, as shown in FIG. Link 3 of course
A stop is needed to prevent the zero from being parallel to the link 26. Further, since the stopper also serves as the shaft of the roller 43 for preventing the disengagement, the cost can be reduced. The sheave 2 when the hook 53 or the like is suspended at two points.
It is also possible to use 5 by pulling 5 with the rope 28 and diagonally arranging the rope from the sheaves 19 and 25 to the hanger (hook 53). According to this, as is well known, there is an effect of steadying the hanging device. The operating device for the sheave 25 is the drum 2
Besides 7, a piston cylinder device and a screw rod device can be used. Sheave 29 is the main boom 5
May be attached to. The operating device for the sheave 25 can be attached to the top boom 8 or the main boom 5 near the connection point between the top boom 8 and the main boom 5. Furthermore, it can be attached to the tip side of the top boom. In such a case, a link can be used instead of the rope. According to the present invention, it is possible to easily change the suspension method of the suspending tool and to simplify the configuration thereof only by operating the operating device. Further, since a stopper that comes into contact with a flexible member (for example, the rope 28) is provided on the lower surface of the top boom, the top boom can be lifted when all the ropes are suspended vertically from the tip of the top boom. It is possible to prevent the flexible member from coming into contact with the sheave at the tip of the top boom when the radius is set to the minimum.

【図面の簡単な説明】 【図1】本発明の一実施例の引込みクレーンの全体正面
図である。 【図2】図1の引込みクレーンにおいてスプレッダを吊
る場合のロープの配置を示す斜視図である。 【図3】図1の引込みクレーンにおいてバケットを吊る
場合のロープの配置を示す斜視図である。 【図4】図1の引込みクレーンにおいてフックを吊る場
合のロープの配置を示す斜視図である。 【図5】図1の引込みクレーンのトップブームの周辺の
正面図である。 【図6】図1の引込みクレーンのトップブームのシーブ
の配置を示す図である。 【図7】図1の引込みクレーンにおいてスプレッダを吊
った場合でトップブームを最大半径にした場合のトップ
ブームの先端の正面図である。 【図8】図1の引込みクレーンにおいてスプレッダを吊
った場合でトップブームを最小半径にした場合のトップ
ブームの先端の正面図である。 【図9】図1の引込クレーンにおいてフックを吊った場
合でトップブームを最大半径にした場合のトップブーム
の先端の正面図である。 【図10】図1の引込みクレーンにおいてフックを吊っ
た場合でトップブームを最小半径にした場合のトップブ
ームの先端の正面図である。 【図11】図7のA−A線に沿う断面図である。 【図12】図7のC−C線に沿う断面図である。 【図13】図1の引込みクレーンにおいて給電ケーブル
の支持手段を示すトップブームの先端の正面図である。 【図14】図1の引込みクレーンにおいて給電ケーブル
の支持手段を示すトップブームの先端の正面図である。 【図15】図12の中央縦断面図である。 【符号の説明】 2…旋回体、5…メインブーム、6…引込み装置、7…
マスト、8…トップブーム、9…テンションブーム、1
5,15a,15b,15c,15d…ロープ、16,
17,18,19,19a,19b,19c,19d,
25,29…シーブ、21,22,27…ドラム、2
6,30…リンク、28…ロープ、43…ガイドロー
ラ、44…軸、50…スプレッダ、51…バケット、5
3…フック、60…給電ケーブル、61…バスケット、
62…金具、63…プラットフォーム、64…コネク
タ、68…ケーブルガイド。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is an overall front view of a retractable crane according to an embodiment of the present invention. FIG. 2 is a perspective view showing the arrangement of ropes when suspending a spreader in the retractable crane of FIG. 3 is a perspective view showing an arrangement of ropes when suspending a bucket in the retractable crane of FIG. 1. FIG. FIG. 4 is a perspective view showing an arrangement of ropes when suspending a hook in the retractable crane of FIG. 1. 5 is a front view around the top boom of the retractable crane of FIG. 1. FIG. 6 is a view showing the arrangement of sheaves of the top boom of the retractable crane of FIG. 1. FIG. FIG. 7 is a front view of the tip of the top boom when the spreader is hung in the retractable crane of FIG. 1 and the top boom has the maximum radius. 8 is a front view of the tip of the top boom when the spreader is hung in the retractable crane of FIG. 1 and the top boom has a minimum radius. 9 is a front view of the tip of the top boom when the hook is hung in the retractable crane of FIG. 1 and the top boom has the maximum radius. FIG. 10 is a front view of the tip of the top boom when the hook is hung in the retractable crane of FIG. 1 and the top boom has a minimum radius. 11 is a cross-sectional view taken along the line AA of FIG. 12 is a cross-sectional view taken along the line CC of FIG. 13 is a front view of the tip of the top boom showing the support means of the power feeding cable in the retractable crane of FIG. 1. FIG. FIG. 14 is a front view of the tip of the top boom showing the support means of the power feeding cable in the retractable crane of FIG. 15 is a central vertical cross-sectional view of FIG. [Explanation of reference numerals] 2 ... Revolving structure, 5 ... Main boom, 6 ... Retracting device, 7 ...
Mast, 8 ... Top boom, 9 ... Tension boom, 1
5, 15a, 15b, 15c, 15d ... Rope, 16,
17, 18, 19, 19a, 19b, 19c, 19d,
25, 29 ... Sheaves 21, 22, 27 ... Drums, 2
6, 30 ... Link, 28 ... Rope, 43 ... Guide roller, 44 ... Shaft, 50 ... Spreader, 51 ... Bucket, 5
3 ... Hook, 60 ... Power supply cable, 61 ... Basket,
62 ... Metal fittings, 63 ... Platform, 64 ... Connector, 68 ... Cable guide.

Claims (1)

【特許請求の範囲】 1.マストと、該マストに回動自在に取付けたメインブ
ームと、該メインブームに回動自在に取付けたトップブ
ームと、該トップブームの後端側と該マストとの間に回
動自在に取付けたテンションブームと、吊具を吊る複数
本のロープと、該ロープを前記トップブームの先端側の
第1のシーブ、同後端の第2のシーブを介して巻取るド
ラムと、前記メインブームを回動させる引込装置と、を
備えた引込みクレーンにおいて、前記トップブームの先
端側に回動自在に設けたリンクと、該リンクの先端側に
設置されており、該リンクを前記トップブームの下方側
に回動させたとき前記第1のシーブから吊下げられた前
記ロープの少くとも1本を支えることが可能な第3のシ
ーブと、前記リンクの先端側に接続された可撓性の部材
を介して該リンクを回動させるものであり、前記マスト
に設置した操作装置と、前記操作装置の操作によって全
ての前記ロープを前記第1のシーブの先端から下方に吊
下げた状態のときであって、前記トップブームを最小回
転半径近傍にしたとき、前記可撓性の部材が前記第1の
シーブに接触しないように、該可撓性の部材に接触する
ものであって前記トップブームの下面に下方に突出して
設置したストッパと、からなる引込クレーン。
[Claims] 1. Mast, main boom rotatably attached to the mast, top boom rotatably attached to the main boom, and rotatably attached between the rear end side of the top boom and the mast A tension boom, a plurality of ropes for suspending a hanging tool, a drum for winding the ropes through a first sheave on the front end side of the top boom and a second sheave on the rear end thereof, and a main boom. In a retracting crane equipped with a retracting device for moving, a link rotatably provided on the tip side of the top boom and a tip installed on the tip side of the link, and the link is provided on the lower side of the top boom. Via a third sheave capable of supporting at least one of the ropes suspended from the first sheave when rotated, and a flexible member connected to the tip side of the link. Turn the link When the operating device installed on the mast and all the ropes are suspended downward from the tip of the first sheave by the operation of the operating device, the top boom is minimized. The flexible member comes into contact with the first sheave so that the flexible member does not come into contact with the first sheave when it is near the radius of rotation, and is installed so as to project downward on the lower surface of the top boom. A retractable crane consisting of a stopper.
JP1745891A 1991-02-08 1991-02-08 Retractable crane Expired - Lifetime JPH0633154B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1745891A JPH0633154B2 (en) 1991-02-08 1991-02-08 Retractable crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1745891A JPH0633154B2 (en) 1991-02-08 1991-02-08 Retractable crane

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP59201616A Division JPS6181390A (en) 1984-09-28 1984-09-28 retraction crane

Publications (2)

Publication Number Publication Date
JPH04213591A JPH04213591A (en) 1992-08-04
JPH0633154B2 true JPH0633154B2 (en) 1994-05-02

Family

ID=11944579

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1745891A Expired - Lifetime JPH0633154B2 (en) 1991-02-08 1991-02-08 Retractable crane

Country Status (1)

Country Link
JP (1) JPH0633154B2 (en)

Also Published As

Publication number Publication date
JPH04213591A (en) 1992-08-04

Similar Documents

Publication Publication Date Title
US3897097A (en) Flying fork-type lifting member
CN207046706U (en) Subtract and shake hoisting system and crane
US4505397A (en) Apparatus for hoisting materials and placing concrete
JP2001233586A (en) Mounting method for counterweight and frame support means
JPH0633154B2 (en) Retractable crane
JPH0780673B2 (en) Retractable crane
CN113148863A (en) Crane and control method thereof
JPH0633153B2 (en) Retractable crane
JPH04213592A (en) retractable crane
JP2749157B2 (en) Retractable crane
JPS5851877B2 (en) Container tilting method and device
CN218145325U (en) Hoisting rigging
JPH027873B2 (en)
JPH0536354B2 (en)
JPS6181389A (en) Power supply device for pulling crane
JPH027874B2 (en)
CN217350485U (en) Lifting machine
JPH0111670Y2 (en)
CN223495966U (en) Crane sling with automatic unhooking function
JP2562475Y2 (en) Counterweight attachment / detachment device for construction machinery
CN219792310U (en) Hoisting hoist
CN215364628U (en) Detachable rotatory gallows
JP2004256240A6 (en) crane
JPH07108759B2 (en) Retractable crane
JPS6019683A (en) Method of carrying in and installing long-sized article