Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH066807B2 - Grand anchor construction method - Google Patents
[go: Go Back, main page]

JPH066807B2 - Grand anchor construction method - Google Patents

Grand anchor construction method

Info

Publication number
JPH066807B2
JPH066807B2 JP60288106A JP28810685A JPH066807B2 JP H066807 B2 JPH066807 B2 JP H066807B2 JP 60288106 A JP60288106 A JP 60288106A JP 28810685 A JP28810685 A JP 28810685A JP H066807 B2 JPH066807 B2 JP H066807B2
Authority
JP
Japan
Prior art keywords
ground
anchor
outer tube
outer pipe
anchor body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60288106A
Other languages
Japanese (ja)
Other versions
JPS62148717A (en
Inventor
豊 桂
信夫 森
篤生 尾上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP60288106A priority Critical patent/JPH066807B2/en
Publication of JPS62148717A publication Critical patent/JPS62148717A/en
Publication of JPH066807B2 publication Critical patent/JPH066807B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、構造物と地盤とを結合させるための土木、建
築の基礎構造に係わり、特に地盤に対する引抜き抵抗を
増大させるためのグランドアンカー工法に関する。
Description: TECHNICAL FIELD The present invention relates to a civil engineering for connecting a structure to a ground and a basic structure of a building, and particularly to a ground anchor construction method for increasing pull-out resistance to the ground. Regarding

〔従来の技術〕[Conventional technology]

グランドアンカーは地盤を対象として設置する柱状の引
抜き抵抗をもった構造物であり、アンカー体、引張り部
およびアンカー頭部から構成され、当該アンカー体の力
の伝達方式によって、グラウト型アンカー工法とメカニ
カルアンカー工法に大別できる。前者はアンカー体の地
盤に対する支圧によって伝達し、後者はアンカー体周面
と地盤の摩擦によって伝達するものである。第5図は従
来のグラウトアンカー工法を示す図、第6図は従来のメ
カニカルアンカー工法を示す図である。図中、1は削孔
機、2、7は引張り材、3はグラウト注入装置、4、6
はアンカー体、5は台座、8は油圧ピストン、9は固定
装置を示す。
A ground anchor is a columnar structure with pull-out resistance that is installed on the ground.It is composed of an anchor body, a tension part, and an anchor head. Depending on the force transmission method of the anchor body, the grout type anchor construction method and mechanical Can be roughly divided into anchor construction methods. The former is transmitted by bearing pressure of the anchor body against the ground, and the latter is transmitted by friction between the peripheral surface of the anchor body and the ground. FIG. 5 is a diagram showing a conventional grout anchor construction method, and FIG. 6 is a diagram showing a conventional mechanical anchor construction method. In the figure, 1 is a boring machine, 2 and 7 are tensile members, 3 is a grout injection device, and 4 and 6
Is an anchor body, 5 is a pedestal, 8 is a hydraulic piston, and 9 is a fixing device.

グラウト型アンカー工法は第5図に示すように、(イ)
地盤を削孔機1により削孔し(ロ)その孔に引張り材2
を挿入した後、(ハ)グラウト注入装置3によりモルタ
ル、セメントペースト等のグラウトを注入し、同時にコ
ンプレッサにより加圧することにより削孔部を拡孔して
アンカー体4を形成し、最後に(ニ)引張り材2にプレ
ストレスを加え台座5に緊張、定着する方式である。こ
の方式は、引張り部(引張り材)から伝えられる力をア
ンカー体がアンカー体周面と地盤との摩擦力で支持(抵
抗)するものである。
The grout type anchor construction method is as shown in Fig. 5 (a)
Drilling the ground with the drilling machine 1 (b) Pulling material 2 into the hole
After the insertion of (c), the grout injecting device 3 injects grout such as mortar and cement paste, and at the same time, the compressor is pressed to expand the drilled portion to form the anchor body 4, and finally (ni ) It is a system in which prestress is applied to the tension member 2 and the pedestal 5 is tensioned and fixed. In this method, the anchor body supports (resists) the force transmitted from the tension portion (tensile member) by the frictional force between the peripheral surface of the anchor body and the ground.

また、メカニカルアンカー工法は第6図に示すように、
(イ)地上でアンカー体6を作成すると共に引張り材7
を結合したうえで、アンカー体6に油圧ピストン8の先
端を係合し、該ピストン8によりアンカー体6を所定の
深さまで押し込んだ後、油圧ピストン8とアンカー体の
係合を解除し、油圧ピストン8のみを引き抜き、(ロ)
引張り材7の地上側端部を固定装置9に定着し、(ハ)
固定装置9の油圧ジャッキを伸長させることにより引張
り材7を牽引し、アンカー体6を90度回転させて所定
の状態に設置する方式である。アンカー体6は一般に鋼
材で作られ、横に直立させた形で押し込まれるので横か
らの見掛け断面が小さくなるように造られており、また
引張り材7との結合は回転自在に形成されている。この
方式に類似するもので、(ニ)に示すようにアンカー体
の支圧面が引張り材の引き抜きによって傘のように開く
方式、また(ホ)に示すように羽根を開く方式の他、ア
ンカー体がスクリュウになっているものもある。これら
のメカニカルアンカーは、引張り部(引張り材)から伝
えられる力をアンカー体がアンカー体の上面の土との支
圧力で支持(抵抗)するものである。ただし、アンカー
体がスクリュウの場合は、引張り部(引張り材)から伝
えられた力をアンカー体がアンカー体周面と地盤との摩
擦力で支持(抵抗)する。
In addition, the mechanical anchor construction method, as shown in FIG.
(B) Anchor body 6 is created on the ground and tensile member 7
, The end of the hydraulic piston 8 is engaged with the anchor body 6, and the anchor body 6 is pushed to a predetermined depth by the piston 8, and then the engagement between the hydraulic piston 8 and the anchor body is released, Pull out only the piston 8, (b)
Fix the ground side end of the tension member 7 to the fixing device 9, and (c)
This is a method in which the tension jack 7 is pulled by extending the hydraulic jack of the fixing device 9 and the anchor body 6 is rotated 90 degrees to set it in a predetermined state. The anchor body 6 is generally made of a steel material and is pushed in a state of being erected horizontally, so that the apparent cross section from the side is made small, and the connection with the tension member 7 is rotatably formed. . Similar to this method, as shown in (d), the bearing surface of the anchor body opens like an umbrella by pulling out the tension material, and as shown in (e), the blade is opened and the anchor body Some are screwed. In these mechanical anchors, the anchor body supports (resists) the force transmitted from the pulling portion (pulling material) by the bearing pressure between the anchor body and the soil on the upper surface of the anchor body. However, when the anchor body is a screw, the anchor body supports (resists) the force transmitted from the tension portion (tensile member) by the frictional force between the peripheral surface of the anchor body and the ground.

〔発明が解決しようとする問題点〕[Problems to be solved by the invention]

一般に、アンカーの極限引抜き力(破壊が生じる場合の
破壊に必要な力)は、地盤強度とアンカー材料(引張り
材及びアンカー体)の強度によって決まる。ところが、
上記従来のグランドアンカー工法はいずれも、原地盤強
度の小さな地盤では極限引抜き力が小さく、例えば浮き
基礎のロッキング防止等には使用できず、実際上は採用
することが困難であるという問題点を有している。
In general, the ultimate pull-out force of an anchor (the force necessary for breaking when breaking occurs) is determined by the ground strength and the strength of the anchor material (tensile member and anchor body). However,
All of the above-mentioned conventional ground anchor construction methods have a problem that the ultimate pull-out force is small on the ground with small original ground strength, and it cannot be used, for example, to prevent the rocking of the floating foundation and is practically difficult to adopt. Have

特にグラウト型アンカー工法においては、削孔を伴うた
め原地盤の応力開放をもたらし、原地盤強度を弱めると
いう問題点を有している。また、引張り材がアンカー体
の中心に位置していれば引張り材とアンカー体は強く結
合されるが、地下水や地盤内応力の影響等により削孔部
が変形したり崩壊したりした場合、引張り材がアンカー
体の周辺部に偏って位置してしまい、引張り材とアンカ
ー体の結合が弱まり、かつ、この状態すなわちアンカー
支持部の形状を確認できないため信頼性に欠けるという
問題点を有している。さらに、施工速度が一本あたり1
時間程度を要するという欠点も有している。
In particular, the grout type anchor construction method has a problem that it causes stress relief of the original ground and weakens the original ground strength because it involves drilling. If the tension material is located in the center of the anchor body, the tension material and the anchor body will be strongly connected, but if the drill hole is deformed or collapsed due to the influence of groundwater or stress in the ground, the tension material Since the material is located unevenly in the peripheral part of the anchor body, the connection between the tension material and the anchor body is weakened, and in this state, that is, the shape of the anchor support part cannot be confirmed, there is a problem that it lacks reliability. There is. Furthermore, the construction speed is 1 per
It also has a drawback that it takes time.

また、メカニカルアンカー工法においては、油圧ピスト
ンを地盤中に押し込むため地盤が乱され、最良に設置し
た場合でも原地盤強度(アンカー設置前の強度)しか期
待できないという問題点を有している。また、アンカー
材料の強度については、引張り材とアンカー体の結合部
分が引張り材、アンカー体の強度よりも小さくなりやす
く、結合部の強度によってアンカーの支持力が決まるた
め、アンカーは結合部の強度分の小さな支持力しか期待
できないという問題点を有している。さらに、アンカー
体の加工及びアンカー体と引張り材の結合部の構造が複
雑になると共に、アンカー体は押し込み容易でかつ引き
抜きが困難な形状が要求されるため、引張り材とアンカ
ー体の形状及び強度は極く限られた特殊なものとなって
しまう。従って、メカニカルアンカーの使用頻度は極め
て少ないのが現状である。
In addition, the mechanical anchor construction method has a problem that since the hydraulic piston is pushed into the ground, the ground is disturbed and only the original ground strength (strength before anchor installation) can be expected even in the best installation. As for the strength of the anchor material, the strength of the joint is determined by the strength of the joint, because the strength of the strength of the joint between the tension member and the anchor body tends to be smaller than the strength of the tension member and the anchor body. It has the problem that only a small supporting capacity can be expected. Furthermore, since the processing of the anchor body and the structure of the joint part between the anchor body and the tension member become complicated, and the anchor body is required to have a shape that is easy to push in and difficult to pull out, the shape and strength of the tension member and the anchor body are required. Will be very limited and special. Therefore, at present, the frequency of use of mechanical anchors is extremely low.

本発明は、上記問題点を解消するものであって、アンカ
ーの定着層として適切でなかった沖積砂質地盤でも十分
な強度をもたせることができるアンカーを提供すること
を目的とする。
The present invention solves the above-mentioned problems, and an object of the present invention is to provide an anchor that can have sufficient strength even in alluvial sandy ground that was not suitable as an anchoring layer for the anchor.

〔問題点を解決するための手段〕[Means for solving problems]

そのために本発明においては、地盤改良工法の一種であ
るサンドコンパクション工法において使用される外管貫
入装置に着目している。これは第4図に示すように、台
車にクローラクレーン10及びガイドマスト11が設置
されていて、ガイドマスト11の上端から吊り治具12
を介して加振機13及び外管14が吊り下げられると共
に、外管14の先端には開閉可能な先端シュー15が取
付けられている。この外管貫入装置を使用した地盤改良
の施工法は、加振機13により外管14を振動させなが
ら地中に挿入してゆく過程で、砂を外管14内に投入
し、外管14を振動させながら上下させた後、先端シュ
ー15を開閉して砂を地中に放出させ、再び、振動させ
ながら外管14を上下して砂を地中に圧入してゆき、最
後に外管14を引き抜き、締め固めた砂柱を作るもので
ある。
Therefore, in the present invention, attention is paid to the outer pipe penetration device used in the sand compaction method, which is one of the ground improvement methods. As shown in FIG. 4, a trolley has a crawler crane 10 and a guide mast 11, and a lifting jig 12 is provided from the upper end of the guide mast 11.
The vibrator 13 and the outer pipe 14 are suspended via the, and a tip shoe 15 that can be opened and closed is attached to the tip of the outer pipe 14. The construction method of soil improvement using this outer pipe penetration device is to insert sand into the outer pipe 14 while inserting the outer pipe 14 into the ground while vibrating the outer pipe 14 by the vibration exciter 13. After raising and lowering while vibrating, the tip shoe 15 is opened and closed to discharge the sand into the ground, and again while vibrating, the outer pipe 14 is moved up and down to press the sand into the ground and finally the outer pipe. 14 is pulled out to make a compacted sand column.

本発明によるグランドアンカー工法は、上記外管貫入装
置を採用することにより、従来の問題点を解消するもの
であって、外管の先端を閉塞した状態で、外管を振動さ
せながら地盤中に挿入した後、引張り材及び充填材を外
管内に入れ、再び、外管を振動させながら所定の位置ま
で貫入させた後、外管の先端を開放させ外管を振動させ
ながら引き抜くことにより、外管周辺部の地盤及び充填
材を締め固めた後、前記引張り材にプレストレスを加え
て定着させることを特徴とするものである。
The ground anchor construction method according to the present invention eliminates the conventional problems by adopting the above-mentioned outer pipe penetrating device. In the state where the tip of the outer pipe is closed, the outer pipe is vibrated in the ground. After inserting it, put the tension material and the filling material into the outer tube, re-penetrate it to the specified position while vibrating the outer tube again, and then open the tip of the outer tube and pull out while vibrating the outer tube. The present invention is characterized in that after the ground and the filler in the peripheral portion of the pipe are compacted, a prestress is applied to the tensile member to fix it.

〔作用〕[Action]

先端を閉塞した状態で、外管を振動させながら地盤中に
挿入することにより、外管周辺部の地盤密度を上昇させ
強度を増大させる。また、充填材を外管内に投入した
後、外管を振動させながら引き抜き作業を行うことによ
り、外管周辺部の地盤及び充填材を締め固める。
By inserting the outer pipe into the ground while vibrating the outer pipe with the tip closed, the ground density around the outer pipe is increased and the strength is increased. In addition, after the filler is put into the outer pipe, the ground and the filler around the outer pipe are compacted by performing an extracting work while vibrating the outer pipe.

〔実施例〕〔Example〕

以下、図面を参照しつつ実施例を説明する。第1図は本
発明のグランドアンカー工法の1実施例を示す図、第2
図はアンカー材料の各実施例を示す図、第3図はアンカ
ー設置後の地盤改良効果を示す図である。図中、14は
外管、15は先端シュー、16は引張り材、17は充填
材を示す。
Hereinafter, embodiments will be described with reference to the drawings. FIG. 1 is a diagram showing an embodiment of the ground anchor construction method of the present invention, and FIG.
The figure shows each embodiment of the anchor material, and FIG. 3 shows the ground improvement effect after the anchor is installed. In the figure, 14 is an outer tube, 15 is a tip shoe, 16 is a tension material, and 17 is a filler.

第1図により施工方法を説明すると、先ず(イ)前述し
た第4図に示した外管貫入装置により、先端シュー15
を閉塞した状態で、外管14を振動させながら砂質地盤
中に挿入してゆく。この時、外管14周辺部の原地盤
(砂質地盤)の密度が上がり強度が増大する。次に
(ロ)一定の位置まで外管を挿入した後、引張り材16
及び充填材17を外管14内に入れ、さらに外管14を
振動させながら充填材を締め固め、所定の位置まで貫入
させる。この際、外管内の充填材17はミキシング効果
により、品質においてバラツキの少ないものとなる。充
填材17としては原地発生地(砂)または貧配合のモル
タル(原地発生土とセメントを混合したもの)が使用さ
れるが、所定の強度が得られればそれ以外でもよい。ま
た、引張り材は鋼棒、鋼より線、FRP等の新素材など
種々のものが考えられる。次に(ハ)所定の位置まで外
管14を貫入させた後、先端シュー15を開放させ外管
14を振動させながら引き抜くことにより、外管14周
辺部の地盤および充填材17を締め固め、最後に引張り
材にプレストレスを加えて定着しアンカーの施工が終了
する。
The construction method will be described with reference to FIG. 1. First, (a) by the outer pipe penetrating device shown in FIG.
In the closed state, the outer pipe 14 is inserted into the sandy ground while vibrating. At this time, the density of the raw ground (sandy ground) around the outer pipe 14 increases and the strength increases. Next, (b) after inserting the outer tube to a certain position, the tension member 16
Then, the filling material 17 is put into the outer pipe 14, and the filling material is compacted while vibrating the outer pipe 14 and penetrated to a predetermined position. At this time, the filling material 17 in the outer tube has little variation in quality due to the mixing effect. As the filler 17, an origin generation site (sand) or a poorly mixed mortar (mixture of origin generation soil and cement) is used, but other materials may be used as long as a predetermined strength can be obtained. Various materials such as steel rods, stranded steel wires, and new materials such as FRP can be considered as the tensile material. (C) After the outer pipe 14 is penetrated to a predetermined position, the tip shoe 15 is opened and the outer pipe 14 is pulled out while vibrating to compact the ground and the filling material 17 around the outer pipe 14, Finally, prestressing is applied to the tension material to fix it and the anchor construction is completed.

上記アンカーの設置による原地盤の改良効果について説
明する。第3図は、アンカー周辺部の幾つかの測定点ご
とに、アンカー設置前後における深度とN値(標準貫入
試験における打撃回数)との関係を示したものである。
これによれば、外管の周辺部および内部ともに、原地盤
におけるN値が平均5程度のものを本発明によるアンカ
ーを設置することにより、N値を平均20以上に締め固
めることができ、結果としてアンカーの引き抜き抵抗を
砂地盤で1.8kg/cm2以上に増大させることができ十
分な強度をもたせることができる。
The improvement effect of the ground by installing the anchor will be described. FIG. 3 shows the relationship between the depth and the N value (the number of hits in the standard penetration test) before and after the anchor is installed for each of several measurement points around the anchor.
According to this, the N value can be compacted to an average of 20 or more by installing the anchor according to the present invention in which the N value in the original ground is about 5 on both the peripheral portion and the inside of the outer pipe. As a result, the pullout resistance of the anchor can be increased to 1.8 kg / cm 2 or more on the sand ground, and sufficient strength can be provided.

なお、本発明は上記の実施例に限定されるものでなく、
種々の変形が可能であることは勿論のことである。。例
えば、上記実施例においては、アンカー材料として引張
り材をそのまま挿入しているが、第2図に示すように
(イ)引張り材16の先端にモルタルからなるアンカー
体18を固定してもよいし、(ロ)引張り材16に多数
のリブ19を取付けるか、(ハ)草の根型のリブ20を
取付けてもよい。これらの場合には引き抜き抵抗をさら
に増大させることができる。
The present invention is not limited to the above embodiment,
Of course, various modifications are possible. . For example, in the above embodiment, the tension member is inserted as it is as the anchor material, but as shown in FIG. 2, the anchor body 18 made of mortar may be fixed to the tip of the tension member 16 (a). (B) A large number of ribs 19 may be attached to the tension member 16 or (c) grass-root type ribs 20 may be attached. In these cases, the pullout resistance can be further increased.

また、上記実施例においては、外管の先端を閉塞した状
態で、外管を振動させながら地盤中に挿入しているが、
挿入の途中で外管内に砂を投入した後先端シューを開
き、次いで外管を上方に移動させてから先端シューを閉
じ、再び外管を振動させながら地盤中に挿入することに
より、外管外に放出された砂を締め固める方式を採用し
てもよい。
In the above embodiment, the outer tube is inserted into the ground while vibrating the outer tube in a state where the tip of the outer tube is closed.
After inserting sand into the outer tube during the insertion, open the tip shoe, then move the outer tube upward, close the tip shoe, and insert it into the ground while oscillating the outer tube again. You may employ the method of compacting the sand discharged | emitted.

〔発明の効果〕〔The invention's effect〕

以上の説明から明らかなように、本発明によれば、下記
の効果が奏されるものである。
As is apparent from the above description, the present invention has the following effects.

原地盤のN値が5程度の地盤でも、アンカーを設置す
ることにより、外管周辺部の地盤および外管内の充填材
のN値を20以上に高めることができ、これまでアンカ
ーの定着層として適切でなかった沖積砂質地盤でも十分
な強度をもたせることができる。
By installing anchors, the N value of the ground around the outer pipe and the filling material inside the outer pipe can be increased to 20 or more even on the ground where the N value of the original ground is about 5, and it has been used as a anchor anchoring layer up to now. Sufficient strength can be given to alluvial sandy soil that was not suitable.

充填材として特にモルタル等の混合材を採用した場合
には、振動により十分なミキシングが行え、アンカー体
の品質のバラツキを少なくさせることができる。
Particularly when a mixed material such as mortar is used as the filler, it is possible to perform sufficient mixing by vibration and reduce variations in the quality of the anchor body.

アンカー材料は地上で組み立てられるため、アンカー
定着部の形状、品質については設計者の意図を十分に反
映させることができる。
Since the anchor material is assembled on the ground, the designer's intention can be sufficiently reflected in the shape and quality of the anchor fixing portion.

充填材は原地発生土を利用できるため、充填材に要す
る費用を低減できる。
Since the filler can use the soil generated in the original area, the cost required for the filler can be reduced.

振動装置および砂投入装置として従来よりサンドコン
パクション工法に使用されている外管貫入装置をそのま
ま使用できる。
The outer pipe penetrating device that has been conventionally used in the sand compaction method can be used as it is as a vibrating device and a sand feeding device.

施工時間はサンドコンパクション工法並の時間(1サ
イクル15分程度)であり、従来のグラウト型アンカー
工法の約1/4であるため、施工費の低廉化、工期の短
縮化に極めて効果的である。
The construction time is about the same as the sand compaction construction method (about 15 minutes per cycle) and about 1/4 of the conventional grout type anchor construction method, so it is extremely effective in reducing construction costs and shortening the construction period. .

施工時の振動、騒音もサンドコンパクション工法程度
である。
Vibration and noise during construction are also about the sand compaction method.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明のグランドアンカー工法の1実施例を示
す図、第2図はアンカー材料の各実施例を示す図、第3
図はアンカー設置後の地盤改良効果を示す図、第4図は
外管貫入装置を示す図、第5図は従来のグラウトアンカ
ー工法を示す図、第6図は従来のメカニカルアンカー工
法を示す図である。 14…外管、15…先端シュー、16…引張り材、17
…充填材、18…アンカー体、19、20…リブ。
FIG. 1 is a diagram showing one embodiment of the ground anchor construction method of the present invention, FIG. 2 is a diagram showing each embodiment of anchor material, and FIG.
Figure shows the ground improvement effect after anchor installation, Figure 4 shows the outer pipe penetration device, Figure 5 shows the conventional grout anchor method, and Figure 6 shows the conventional mechanical anchor method. Is. 14 ... Outer tube, 15 ... Tip shoe, 16 ... Tensile material, 17
... filling material, 18 ... anchor body, 19, 20 ... rib.

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 昭53−73810(JP,A) 特開 昭53−73809(JP,A) 特開 昭51−148916(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (56) Reference JP-A-53-73810 (JP, A) JP-A-53-73809 (JP, A) JP-A-51-148916 (JP, A)

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】外管の先端を閉塞した状態で、外管を振動
させながら地盤中に挿入した後、引張り材及び充填材を
外管内に入れ、さらに外管を振動させながら所定の位置
まで貫入させた後、外管の先端を開放させ外管を振動さ
せながら引き抜くことにより、外管辺部の地盤及び充填
材を締め固めた後、前記引張り材にプレストレスを加え
て定着させることを特徴とするグランドアンカー工法。
1. An outer tube is inserted into the ground while vibrating the outer tube in a state where the tip of the outer tube is closed. Then, a tension material and a filling material are put into the outer tube, and the outer tube is vibrated to a predetermined position. After the penetration, the tip of the outer tube is opened and the outer tube is pulled out while vibrating to compact the ground and the filling material around the outer tube, and then prestressing the tension material to fix it. The characteristic ground anchor construction method.
JP60288106A 1985-12-21 1985-12-21 Grand anchor construction method Expired - Lifetime JPH066807B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60288106A JPH066807B2 (en) 1985-12-21 1985-12-21 Grand anchor construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60288106A JPH066807B2 (en) 1985-12-21 1985-12-21 Grand anchor construction method

Publications (2)

Publication Number Publication Date
JPS62148717A JPS62148717A (en) 1987-07-02
JPH066807B2 true JPH066807B2 (en) 1994-01-26

Family

ID=17725874

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60288106A Expired - Lifetime JPH066807B2 (en) 1985-12-21 1985-12-21 Grand anchor construction method

Country Status (1)

Country Link
JP (1) JPH066807B2 (en)

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS51148916A (en) * 1975-06-16 1976-12-21 Nippon Dev Consult Tippopen type bagged sand drain method and hollow pipe used for same
JPS6044450B2 (en) * 1976-12-11 1985-10-03 株式会社武智工務所 Deep compaction method
JPS5373810A (en) * 1976-12-11 1978-06-30 Takechi Komusho Kk Method and device for tape convection
JPS57116824A (en) * 1981-01-08 1982-07-21 Fudo Constr Co Ltd Sand drain and its formation

Also Published As

Publication number Publication date
JPS62148717A (en) 1987-07-02

Similar Documents

Publication Publication Date Title
JP5265500B2 (en) Pile digging method, foundation pile structure
US20140056651A1 (en) Method of providing a support column
SE460674B (en) PROCEDURE AND DEVICE FOR PREPARING A COMPRESSIVE DEVELOPMENT CONSTRUCTION
JP2003268767A (en) Construction method for double tube digging small diameter pile using hole excavating rod
JP3448629B2 (en) Seismic retrofitting method for existing structure foundation
JP2885077B2 (en) Connection pile method of ready-made concrete pile
JPH066807B2 (en) Grand anchor construction method
JP2559394Y2 (en) Rock anchored octopus foot anchor foundation
KR101158512B1 (en) Compressing steel bar ground anchor and method for constructing thereof
JPS6327618A (en) Setting work of concrete pile by preboring
JP2546733B2 (en) Anchor construction method for consolidation ground
JP2936353B2 (en) Construction method of high strength embedded pile
JPH04115024A (en) Sheathing method
JP2884273B2 (en) Construction method for high strength cast-in-place concrete piles
JPH0355612B2 (en)
JP2002146784A (en) Ground anchoring method using existing pile
JP2002356847A (en) Support structure of foundation pile and construction method of foundation pile
JPH11256572A (en) Composite ground reinforcing method
JP7826234B2 (en) Ground improvement method
KR100396393B1 (en) Pile driving-in method using screw type pile with conical end
JPH07166544A (en) Ready-made concrete pile method
JPH11247203A (en) Reinforcing method of existing building foundation by inclined shaft
JP2927612B2 (en) Foundation method
JPH04336116A (en) Executing method for cast-in-place concrete pile
JP3345605B2 (en) Construction method for high strength cast-in-place concrete piles