JPH0674595B2 - Steel plate concrete ship foundation method for soft ground - Google Patents
Steel plate concrete ship foundation method for soft groundInfo
- Publication number
- JPH0674595B2 JPH0674595B2 JP17584590A JP17584590A JPH0674595B2 JP H0674595 B2 JPH0674595 B2 JP H0674595B2 JP 17584590 A JP17584590 A JP 17584590A JP 17584590 A JP17584590 A JP 17584590A JP H0674595 B2 JPH0674595 B2 JP H0674595B2
- Authority
- JP
- Japan
- Prior art keywords
- steel plate
- concrete
- foundation
- ship foundation
- ship
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Foundations (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、土木分野では鉄道橋梁もしくは各種プラント
その他の構造物の基礎、建築分野では高層ビル、原子力
関係もしくは塔体等の基礎の施工法に関するものであ
る。DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention relates to a method for constructing a foundation of a railway bridge or various plants and other structures in the field of civil engineering, and a foundation of a high-rise building, nuclear power-related or tower in the field of construction It is about.
このような基礎を軟弱地盤に施工する場合は、支持層ま
で掘削を行い、そのレベルでコンクリート造の構造物を
作る必要がある。When constructing such a foundation on soft ground, it is necessary to excavate to the support layer and make a concrete structure at that level.
そして従来工法では、掘削を行うために止水用の山留を
必要とし、また構造物底部の地盤は支持力及び止水性を
確保するために地盤改良を行うことが多い。Further, in the conventional method, a retaining pile for stopping water is required for excavation, and the ground at the bottom of the structure is often improved to secure bearing capacity and water stopping.
また、掘削後に地下水面以下の深さでコンクリート造の
構造物を作る方法としては、ポンプ法で水を抜いた状態
でコンクリートを打設する方法と水中コンクリートを打
設する方法がある。Further, as a method for making a concrete structure at a depth below the water table after excavation, there are a method of placing concrete in a state of draining water by a pump method and a method of placing underwater concrete.
なお、山留をせずに構造物を掘削と同時に製作する方法
として、ニューマチックケーソン工法もある。There is also a pneumatic caisson method as a method of manufacturing a structure at the same time as excavating a structure without retaining a mountain.
前記止水用の山留を施工する山留工法では、山留壁を不
透水層に達する深さまで構築する必要があり、この不透
水層が深く壁が不透水層まで達しない場合には代わりに
底面地盤の止水性を改良することになるが、かかる地盤
改良工事は大掛かりな付帯工事であり、その分の費用と
工期は膨大なものである。In the mountain retaining method for constructing the retaining mountain for water stopping, it is necessary to construct the mountain retaining wall to a depth that reaches the impermeable layer, and if this impermeable layer is deep and the wall does not reach the impermeable layer, substitute it. Although it will improve the water resistance of the bottom ground, such ground improvement work is a large-scale incidental work, and the cost and construction period are enormous.
また、止水を目的とした山留壁の施工法として、多軸オ
ーガを使用してモルタユやソイルコンクリート等の柱列
壁を順次ラップさせながら連続させていく工法がある
が、この工法では施工が比較的簡単であるが、深度が大
きい場合にオーガの鉛直掘削精度に問題があり、柱列壁
相互の重合わせが不完全になるおそれがあり、境界部の
止水性確保が難しい。In addition, as a construction method of a mountain retaining wall for the purpose of stopping water, there is a construction method that uses a multi-axis auger to continuously wrap pillar wall walls such as Mortayu or soil concrete while successively wrapping them. Is relatively simple, but there is a problem in vertical excavation accuracy of the auger when the depth is large, and there is a risk that the mutual alignment of the column walls may be incomplete, and it is difficult to secure water shutoff at the boundary.
ニューマチックケーソン工法では、ケーソン内の掘削作
業を主として人力で行なわなければならず、施工能率が
悪い。In the pneumatic caisson method, excavation work inside the caisson must be performed mainly by manpower, and the construction efficiency is poor.
本発明の目的は前記従来例の不都合を解消し、不透水層
に達するまでの山留壁などは必要なく、また底面地盤の
改良も不要で、さらに止水効果も充分なものである軟弱
地盤における鋼板コンクリート船基礎工法を提供するこ
とにある。The object of the present invention is to eliminate the disadvantages of the conventional example, no need for mountain retaining walls, etc. until reaching the impermeable layer, no need for improvement of the bottom ground, and a soft ground with sufficient water stopping effect. To provide a steel plate concrete ship foundation method in Japan.
本発明は前記目的を達成するため、構造物の建設地点に
鋼管杭を適宜間隔で打設し、該鋼管杭頂部に設置した仮
設構台を利用して地盤の掘削を行い、この仮設構台を撤
去後にその位置で鋼板コンクリート船基礎の鋼板部を組
立て、かつそれを鋼管杭の先端に設けた降下装置で吊支
承し、次いで該降下装置により鋼板コンクリート船基礎
の鋼板部を吊降ろして進水させ、水に浮かせた船基礎の
鋼板部内にコンクリートを打設して該船基礎を完成さ
せ、この鋼板コンクリート船基礎内側に配筋しまた基礎
コンクリートを打設して鋼板コンクリート船基礎を自重
で沈設させ、沈設した船基礎の下部領域や周囲にコンク
リートを打設し、かつ周辺を埋戻して構造物基礎を構築
することを要旨とするものである。In order to achieve the above-mentioned object, the present invention places steel pipe piles at appropriate intervals at the construction point of a structure, excavates the ground using a temporary gantry installed at the top of the steel pipe pile, and removes this temporary gantry. After that, the steel plate part of the steel plate concrete ship foundation is assembled at that position, and it is suspended and supported by the descending device provided at the tip of the steel pipe pile, and then the steel plate part of the steel plate concrete ship foundation is suspended by the descending device to be launched. , Concrete is placed in the steel plate part of the ship foundation that is floated in water to complete the ship foundation, and the steel plate concrete ship foundation is reinforced and the concrete is placed and the steel plate concrete ship foundation is sunk by its own weight. The purpose is to construct concrete by placing concrete in the lower area and surrounding area of the sunk ship foundation and backfilling the surrounding area.
本発明によれば、鋼板コンクリート船基礎の鋼板部を組
立て、かつそれを進水させ、鋼板コンクリート船基礎を
完成させてから沈設させて構造物基礎とするものである
から、不透水層に達するまでの止水用の山留壁などは不
要である。According to the present invention, the steel plate portion of the steel plate concrete ship foundation is assembled and launched, and the steel plate concrete ship base is completed and then laid down to form the structure foundation, thus reaching the impermeable layer. There is no need for a retaining wall to stop the water.
また、船基礎をなす鋼板コンクリート構造、及び下部領
域のコンクリート自体が支持地盤に置き換わるので、底
面地盤の改良が不要となり、鋼板コンクリート構造を構
成する周囲の鉄板により止水効果も高い。Further, since the steel plate concrete structure that forms the ship foundation and the concrete itself in the lower region are replaced by the supporting ground, it is not necessary to improve the bottom ground, and the water blocking effect is high due to the surrounding iron plates that form the steel plate concrete structure.
しかも、掘削は地上より大型機械を用いた掘削も可能で
ある。Moreover, the excavation can be performed using a large machine from the ground.
以下、図面について本発明の実施例を詳細に説明する。 Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
第1図〜第13図は、本発明の軟弱地盤における鋼板コン
クリート船基礎工法の1実施例を示す各工程の縦断側面
図である。1 to 13 are longitudinal side views of respective steps showing one embodiment of a steel plate concrete ship foundation method for soft ground according to the present invention.
先ず、第1図に示すように構造物の建設地点に鋼管杭
(φ≒1.0m)lを適宜間隔(10.0m×10.0m程度)で、か
つその杭長が掘削深さよりも長くなるように打設する。First, as shown in FIG. 1, steel pipe piles (φ≈1.0 m) 1 should be appropriately spaced (about 10.0 m × 10.0 m) at the construction point of the structure, and the pile length should be longer than the excavation depth. To set.
次いで、第2図に示すように鋼管杭1の頂部に仮設構台
2を設置し、第3図に示すようにこの構台2を利用し
て、及び周辺の地上から大型機械を用いて地盤の掘削を
行う。この際、掘削する地盤は常水位が高いので、水中
掘削となる。Next, as shown in FIG. 2, a temporary gantry 2 is installed on the top of the steel pipe pile 1, and as shown in FIG. 3, the gantry 2 is used and the ground is excavated from the surrounding ground using a large machine. I do. At this time, since the ground to be excavated has a high normal water level, the excavation will be underwater.
また、掘削に先立ち必要に応じて周辺に仮設山止め3を
施すが、これは簡易なものでよく、止水効果は期待しな
くてよい。In addition, a temporary mountain stopper 3 is provided around the periphery as needed prior to excavation, but this may be a simple one and the water-stop effect need not be expected.
掘削終了後、第4図に示すように法面及び底面に水中コ
ンクリートを厚さ200mm程度に打設して保護層4を形成
し、また仮設構台2を撤去する。After excavation, as shown in FIG. 4, underwater concrete is cast on the slope and bottom to a thickness of about 200 mm to form a protective layer 4, and the temporary gantry 2 is removed.
そして、第5図に示すようにこの仮設構台2があった位
置で、鋼板コンクリート(SC)船基礎5の鋼板部5aのみ
を組立てる。Then, as shown in FIG. 5, only the steel plate portion 5a of the steel plate concrete (SC) ship foundation 5 is assembled at the position where the temporary gantry 2 was.
第14図、第15図に示すように、鋼板コンクリート船基礎
5は、鋼管杭1の先端部が内部を貫通突出するように外
側管6を底面から立上げており、この鋼管杭1の先端に
設けた降下装置7で該外側管6の先端を係止すること
で、鋼板コンクリート船基礎5の鋼板部5aの全体を鋼管
杭1で吊支承する。As shown in FIGS. 14 and 15, in the steel plate concrete ship foundation 5, the outer pipe 6 is raised from the bottom surface so that the tip of the steel pipe pile 1 projects through the inside. By locking the tip of the outer pipe 6 with the descending device 7 provided in the above, the entire steel plate portion 5a of the steel plate concrete ship foundation 5 is suspended and supported by the steel pipe pile 1.
この降下装置7としては種々の構成のものが考えられる
が、主に吊下げワイヤー7bとこれを調整するジャッキ7a
とからなるもので、第14図に示したように鋼管杭1の先
端にガイドローラ用の滑車8を設けてもよい。Although various structures are conceivable as the lowering device 7, the hanging wire 7b and the jack 7a for adjusting the hanging wire 7b are mainly used.
As shown in FIG. 14, a pulley 8 for a guide roller may be provided at the tip of the steel pipe pile 1 as shown in FIG.
また、ジャッキ7aとしてセンターホール式のジャッキを
使用し、吊下げワイヤー7bをこのジャッキに係脱する定
着具で着脱自在に係止するようにすることもできる。It is also possible to use a center-hole type jack as the jack 7a and detachably lock the hanging wire 7b with a fixing tool that engages with and disengages from the jack.
第6図に示すように、前記降下装置7によりすでに組立
てた鋼板コンクリート船基礎5の鋼板部5aを吊降ろして
進水させ、第7図に示すようにこの水に浮かせた船基礎
5の鋼板部5a内にコンクリート10を打設して該船基礎5
を完成させる。As shown in FIG. 6, the steel plate portion 5a of the steel plate concrete ship foundation 5 already assembled by the descending device 7 is hung and launched, and as shown in FIG. 7, the steel plate of the ship base 5 floated on this water. Concrete 10 is placed in the part 5a and the ship foundation 5
To complete.
なお、鋼板コンクリート船基礎5の降下に先立ち、外側
管6は上部に継ぎ足しを行い、その先端が常に常水位よ
りも上にでるようにする。Before the descent of the steel plate concrete ship foundation 5, the outer pipe 6 is added to the upper part so that the tip of the outer pipe 6 is always above the normal water level.
第8図に示すように、船基礎5の内側に構造物の基礎を
製作するために配筋9を行い、同時に鋼板コンクリート
船基礎5の沈設レベルを決定する定規コン17を打設す
る。As shown in FIG. 8, the bar arrangement 9 is performed inside the ship foundation 5 in order to manufacture the foundation of the structure, and at the same time, the ruler control 17 which determines the sinking level of the steel plate concrete ship foundation 5 is placed.
また、鋼管杭1の先端で常水位よりも上にでる部分は切
断撤去する。Further, the portion of the tip of the steel pipe pile 1 that is above the normal water level is cut and removed.
第9図に示すように、トレミー管11等で鋼板コンクリー
ト船基礎5内部に基礎コンクリート12を打設すると、こ
の鋼板コンクリート船基礎5は自重で定規コン17で支承
される位置まで沈設する。As shown in FIG. 9, when the concrete concrete 12 is placed inside the steel plate concrete ship foundation 5 with the tremie pipe 11 or the like, the steel plate concrete ship foundation 5 is sunk to the position supported by the ruler con 17 under its own weight.
そして、第10図、第16図、第17図に示すように鋼管杭1
を底部付近で水中切断し、底部支持地盤の強度確認を行
う。Then, as shown in FIGS. 10, 16 and 17, the steel pipe pile 1
Underwater is cut near the bottom to check the strength of the bottom support ground.
さらに、船基礎5の周囲にコンクリート13を打設して船
基礎5の下部領域を外気に対して密閉し、外側管6内か
ら船基礎5の下部領域の水を抜きながら空気を圧入して
作業空間を作る。Further, concrete 13 is cast around the ship foundation 5 to seal the lower area of the ship foundation 5 against the outside air, and air is injected while draining the water of the lower area of the ship foundation 5 from the outside pipe 6. Create a working space.
第11図に示すように、船基礎5の下部領域にコンクリー
ト13′を打設し、第12図に示すように該コンクリート1
3′と船基礎5の隙間や外側管6内にモルタル14をグラ
ウトし、周辺の前記コンクリート13上に埋戻し15を施
す。As shown in FIG. 11, concrete 13 'is placed in the lower region of the ship foundation 5, and as shown in FIG.
The mortar 14 is grouted in the gap between the 3'and the ship foundation 5 or in the outer pipe 6, and the backfill 15 is applied on the concrete 13 in the periphery.
その後第13図に示すように、外側管6の基礎コンクリー
ト12から突出する部分を切断撤去し、止水蓋16を端部に
溶接して基礎工事を完了する。After that, as shown in FIG. 13, the portion of the outer pipe 6 projecting from the basic concrete 12 is cut and removed, and the water blocking lid 16 is welded to the end to complete the basic work.
図示は省略するが、この基礎の上には筒体壁工事を行う
などして上部構造物を施工する。Although illustration is omitted, an upper structure is constructed on this foundation by performing a cylindrical wall construction or the like.
以上述べたように本発明の軟弱地盤における鋼板コンク
リート船基礎工法は、軟弱地盤を掘削して支持層レベル
に構造物基礎を施工するのに、不透水層に達するまでの
山留壁などは必要なく、また底面地盤の改良も不要で、
簡単かつ迅速に施工でき、しかも止水効果も高く、信頼
性が高い基礎が得られるものである。As described above, the steel plate concrete ship foundation method for soft ground according to the present invention requires a retaining wall or the like to reach the impermeable layer in order to excavate the soft ground and construct the structure foundation at the support layer level. There is also no need to improve the bottom ground,
It is easy and quick to construct, has a high water blocking effect, and provides a highly reliable foundation.
第1図〜第13図は、本発明の軟弱地盤における鋼板コン
クリート船基礎工法の1実施例を示す各工程の縦断側面
図、第14図は鋼板コンクリート船基礎の降下状態の詳細
を示す要部の縦断側面図、第15図は同上平面図、第16図
は鋼板コンクリート船基礎の沈設状態を示す要部の縦断
側面図、第17図は要部の平面図である。 1……鋼管杭、2……仮設構台 3……仮設山止め、4……保護層 5……鋼板コンクリート船基礎 5a……鋼板部、6……外側管 7……降下装置、7a……ジャッキ 7b……吊下げワイヤー 8……滑車、9……配筋 10……コンクリート、11……トレミー管 12……基礎コンクリート、13,13′……コンクリート 14……モルタル、15……埋戻し 16……止水蓋、17……定規コン1 to 13 are vertical sectional side views of each step showing one embodiment of the steel plate concrete ship foundation method for soft ground of the present invention, and FIG. 14 is a main part showing details of the descending state of the steel plate concrete ship foundation. Fig. 15 is a vertical side view of Fig. 15, Fig. 15 is a plan view of the same as above, Fig. 16 is a vertical side view of a main part showing the submerged state of a steel plate concrete ship foundation, and Fig. 17 is a plan view of the main part. 1 …… Steel pipe pile, 2 …… Temporary gantry 3 …… Temporary mountain stopper, 4 …… Protective layer 5 …… Steel plate concrete ship foundation 5a …… Steel plate part, 6 …… Outside pipe 7 …… Descent device, 7a …… Jack 7b …… Suspending wire 8 …… Pulley, 9 …… Rebar arrangement 10 …… Concrete, 11 …… Tremy pipe 12 …… Basic concrete, 13,13 ′ …… Concrete 14 …… Mortar, 15 …… Backfilling 16: Water stop lid, 17: Ruler control
Claims (1)
設し、該鋼管杭頂部に設置した仮設構台を利用して地盤
の掘削を行い、この仮設構台を撤去後にその位置で鋼板
コンクリート船基礎の鋼板部を組立て、かつそれを鋼管
杭の先端に設けた降下装置で吊支承し、次いで該降下装
置により鋼板コンクリート船基礎の鋼板部を吊降ろして
進水させ、水に浮かせた船基礎の鋼板部内にコンクリー
トを打設して該船基礎を完成させ、この鋼板コンクリー
ト船基礎内側に配筋しまた基礎コンクリートを打設して
鋼板コンクリート船基礎を自重で沈設させ、沈設した船
基礎の下部領域や周囲にコンクリートを打設し、かつ周
辺を埋戻して構造物基礎を構築することを特徴とした軟
弱地盤における鋼板コンクリート船基礎工法。1. A steel pipe pile is driven at appropriate intervals at a construction point of a structure, the ground is excavated by using a temporary gantry installed at the top of the steel pipe pile, and a steel plate is removed at that position after the temporary gantry is removed. The steel plate part of the concrete ship foundation was assembled, and it was suspended and supported by the descending device provided at the tip of the steel pipe pile, and then the steel plate part of the steel plate concrete ship foundation was suspended by the descending device to be launched and floated in water. The concrete is placed in the steel plate portion of the ship foundation to complete the ship foundation, the steel plate concrete is placed inside the ship foundation, and the concrete is placed so that the steel plate concrete ship foundation is sunk by its own weight. A steel plate concrete ship foundation construction method for soft ground, characterized by constructing a concrete foundation by placing concrete in the lower area of the foundation and its surroundings and then backfilling the surrounding area.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17584590A JPH0674595B2 (en) | 1990-07-02 | 1990-07-02 | Steel plate concrete ship foundation method for soft ground |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17584590A JPH0674595B2 (en) | 1990-07-02 | 1990-07-02 | Steel plate concrete ship foundation method for soft ground |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0464622A JPH0464622A (en) | 1992-02-28 |
| JPH0674595B2 true JPH0674595B2 (en) | 1994-09-21 |
Family
ID=16003221
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP17584590A Expired - Lifetime JPH0674595B2 (en) | 1990-07-02 | 1990-07-02 | Steel plate concrete ship foundation method for soft ground |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0674595B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4904578B2 (en) * | 2006-06-08 | 2012-03-28 | 清水建設株式会社 | Structure fixing method, pier foundation construction method and pile fixing structure |
| JP7702897B2 (en) * | 2022-02-08 | 2025-07-04 | 大成建設株式会社 | Anti-fouling materials that inhibit the adhesion of marine organisms |
-
1990
- 1990-07-02 JP JP17584590A patent/JPH0674595B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0464622A (en) | 1992-02-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108914931B (en) | An assembled vertical shield ring foundation pile and construction method | |
| CN104264688B (en) | Manually digging hole non-uniform pile support construction process | |
| CN101672041B (en) | Top-down construction method of large underground structure outer wall | |
| CN204491626U (en) | The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine | |
| CN203475440U (en) | SMW stiffened wall inclined-supporting combined space enclosing structure for foundation pit | |
| CN102828520A (en) | Ring-shaped inner supporting structure used in deep peat soil deep foundation pit | |
| CN114541439B (en) | Construction method of double-wall steel cofferdam structure without bottom sealing | |
| CN108277818A (en) | Basement top-down method Combined tower crane foundation structure and construction method | |
| CN105951711A (en) | Enclosing construction method of underground continuous wall of seashore power station | |
| CN103938634B (en) | A kind of deep foundation pit supporting structure and construction method | |
| CN108457282A (en) | Deep water hard rock is without back cover steel sheet pile cofferdam construction method | |
| CN104264683B (en) | Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition | |
| CN109610473A (en) | A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration | |
| CN119412105A (en) | A construction method for protecting intersecting shield sections | |
| CN110820756A (en) | Shield well and vertical shaft deep foundation pit excavation safety construction method | |
| CN108035360A (en) | A kind of method for pattern foundation pit supporting structure | |
| CN108571010B (en) | Method for integrating open cut method engineering prefabricated main structure and supporting structure | |
| CN211421139U (en) | A shield shaft crown beam support structure | |
| CN106400814A (en) | Foundation pit supporting method | |
| CN108005086A (en) | A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure | |
| JPH0674595B2 (en) | Steel plate concrete ship foundation method for soft ground | |
| CN115217114B (en) | Construction method of foundation pit rescue back pressure platform | |
| CN116291499A (en) | Construction process of tunneling-before-well of water-rich sand layer in river | |
| JPH09316894A (en) | Bridge pier foundation structure, and construction method thereof | |
| CN109137944B (en) | Construction method of water-stop wall in deep-water bottom-sealing-free steel cofferdam |