JPH0680249B2 - Reinforced embankment construction method - Google Patents
Reinforced embankment construction methodInfo
- Publication number
- JPH0680249B2 JPH0680249B2 JP3285396A JP28539691A JPH0680249B2 JP H0680249 B2 JPH0680249 B2 JP H0680249B2 JP 3285396 A JP3285396 A JP 3285396A JP 28539691 A JP28539691 A JP 28539691A JP H0680249 B2 JPH0680249 B2 JP H0680249B2
- Authority
- JP
- Japan
- Prior art keywords
- embankment
- pile
- anchor material
- reinforced
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は補強盛土の施工方法に
関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a reinforced embankment.
【0002】[0002]
【従来の技術】盛土法面をできるだけ急な勾配に形成し
て安定させるために、最近は盛土内に複数層に引張強度
の大きいシート状のアンカー材を埋設し、盛土とアンカ
ー材との間に働く摩擦力によってアンカー材を盛土内に
固定し、その引張力で斜面の滑り破壊力に対杭して、斜
面の滑り破壊を防ぐ方法が用いられている。2. Description of the Related Art Recently, in order to form a steep slope as steep as possible and to stabilize it, recently, a sheet-like anchor material having a large tensile strength is embedded in a plurality of layers in the embankment and the space between the embankment and the anchor material is increased. A method is used in which the anchor material is fixed in the embankment by the frictional force that acts on the pile, and the tensile force of the anchor material counters the sliding failure force of the slope to prevent the sliding failure of the slope surface.
【0003】[0003]
【発明が解決しようとする課題】上記の従来技術には、
次ぎのような問題点が存在する。即ち、上記のように引
張強度の大きいアンカー材を埋設して盛土法面を安定さ
せる工法の場合には、勾配を従来の盛土よりも急にする
ことが可能となる。しかし、勾配を急にすると法面の際
が崩れ易いので、盛土端部に土嚢袋を土留として積み上
げ、その上をシート状のアンカー材で覆い、更に、上方
で盛土の中に巻き込んで土嚢袋を安定させてから、盛土
工事を行っているこのため、土嚢詰め・アンカー材の巻
き込み等の作業に人手が掛り、省力化が進まなず、思う
ようにコスト引き下げができないことが問題となってい
る。DISCLOSURE OF THE INVENTION Problems to be Solved by the Invention
There are the following problems. That is, in the case of the method of embedding the anchor material having high tensile strength to stabilize the embankment slope as described above, the slope can be made steeper than that of the conventional embankment. However, if the slope is steep, the slope tends to collapse, so sandbags are piled up at the end of the embankment as clods, covered with sheet-shaped anchor material, and then rolled up into the embankment to wrap up the sandbag. Since the embankment work is carried out after stabilizing the work, labor is required for work such as packing sandbags and winding anchor material, and labor saving does not progress, and it is not possible to reduce costs as expected. There is.
【0004】[0004]
【課題を解決するための手段】本発明は、上記のような
問題点を解決するためになされたもので、急な勾配にお
いても盛土作業を容易にし、ひいてはコストを安くする
盛土の施工方法を提供することを目的としている即ち、
本発明は、盛土内に引張強度の大きいアンカー材を略水
平に埋設し、盛土の法肩より少し内側の個所に杭を立設
し、この杭を前記アンカー材と連結するとともに、杭を
多数設けたり、杭の間に堰板を設けてから、次層の盛土
工事を行うものである。The present invention has been made to solve the above-mentioned problems, and provides a method of embankment that facilitates embankment work even at a steep slope and thus reduces costs. The purpose is to provide:
The present invention is to embed an anchor material having a large tensile strength substantially horizontally in the embankment, to erect a pile at a position slightly inside the shoulder of the embankment, and to connect this pile with the anchor material and to make a large number of piles. After installing or installing a dam plate between the piles, the embankment work for the next layer is performed.
【0005】[0005]
【実施例1】以下、この発明の実施例を図面について詳
しく説明する。 アンカー材 アンカー材1は、盛土内に水平方向に埋設することによ
り、盛土の円弧滑りなどに対抗して盛土を安定させるた
めのものである。アンカー材1は盛土内に水平に埋設す
るものであり、面状、帯状、線状等の形状のものが用い
られる。 面状アンカー材 面状アンカー材11としては、プラスチックネット、不
織布、透水マット、鋼板など、引張強度の大きいものな
ら特に材料を規定するものではない。この面状アンカー
材11の盛土法面側の端辺は、図2に示すように、巻付
管21に巻きつけて、ピン22等によって取り付ける。 帯状アンカー材 帯状アンカー材12は、面状アンカー材11を帯状に複
数に分断したものである。これらの帯状アンカー材12
は、図3に示すように、所定間隔をおいて、巻付管21
に盛土法面側の端辺を巻きつけて、ピン22等によって
取り付ける。Embodiment 1 An embodiment of the present invention will be described in detail below with reference to the drawings. Anchor material The anchor material 1 is embedded in the embankment in the horizontal direction to stabilize the embankment against the arc slide of the embankment. The anchor material 1 is embedded horizontally in the embankment and has a planar shape, a strip shape, a linear shape, or the like. Planar anchor material The planar anchor material 11 is not particularly limited as long as it has a large tensile strength, such as a plastic net, a nonwoven fabric, a water-permeable mat, a steel plate. As shown in FIG. 2, the edge of the surface anchor material 11 on the embankment slope side is wound around a winding tube 21 and attached by a pin 22 or the like. Band-shaped anchor material The band-shaped anchor material 12 is obtained by dividing the planar anchor material 11 into a plurality of bands. These strip anchor materials 12
As shown in FIG. 3, the winding tube 21 is
Wind the edge of the embankment slope side and attach it with pins 22 or the like.
【0006】線状アンカー材 図4に示すように、線状アンカー材13は、異形鉄筋の
様に表面に凹凸を設けて摩擦抵抗を大きくした捧状体等
を用いる。線状アンカー材13には、周面に凹凸を設け
る代わりに、抵抗板等を取り付けた棒状体や鋼索等を用
いることができる。このように形成した線状アンカー材
13を多数用いて、盛土内に埋設することも考えられる
が、線状アンカー材13は比較的摩擦抵抗が小さいた
め、上記の面状アンカー材あるいは帯状アンカー材と併
用すると効果的である。また、面状アンカー材と帯状ア
ンカー材との併用も考えられる。Linear Anchor Material As shown in FIG. 4, the linear anchor material 13 is a sacrificial body or the like having irregularities on the surface such as deformed reinforcing bars to increase frictional resistance. As the linear anchor material 13, a rod-shaped body to which a resistance plate or the like is attached, a steel rope, or the like can be used instead of providing irregularities on the peripheral surface. It is conceivable that a large number of the linear anchor materials 13 formed in this way are used and embedded in the embankment. However, since the linear anchor material 13 has a relatively small frictional resistance, the above-mentioned planar anchor material or strip anchor material is used. It is effective when used together with. It is also possible to use a planar anchor material and a strip anchor material together.
【0007】杭 杭3は、アンカー材1に直接ないし間接的に取付けられ
て盛土の法肩から所定の間隔をおいて盛土上に立設さ
れ、場合によっては、後述する堰板を取付けるものであ
る。杭3は、盛土巻き出しの際に盛土をせき止めるの
で、断面二次モーメントの大きいことが要求される。そ
の意味では鋼管パイプ、H形鋼、C形鋼などを用いるの
が望ましい。このまま法面の表面にでる場合もあり、そ
の場合には美観に優れたものが望ましく、図5に示すよ
うなコンクリート製の擬木杭31などが適している。図
6に示すように、上半分が擬木杭31、打ち込み部の下
半分が鋼管パイプ32で構成されている合成杭33でも
よい。The pile 3 is directly or indirectly attached to the anchor material 1 and is erected on the embankment with a predetermined distance from the shoulder of the embankment. In some cases, a weir plate described later is attached. is there. Since the pile 3 blocks the embankment when unwinding the embankment, it is required to have a large second moment of area. In that sense, it is desirable to use a steel pipe, H-section steel, C-section steel or the like. In some cases, the surface of the slope is left as it is, and in this case, it is desirable that it has an excellent aesthetic appearance, and a pseudo wooden pile 31 made of concrete as shown in FIG. 5 is suitable. As shown in FIG. 6, the upper half may be a synthetic wood pile 31 and the lower half may be a composite pile 33 having a steel pipe 32.
【0008】堰板 堰板4は、アンカー材の上に盛土作業を行う前に、杭に
取付けて盛土を堰止めて、土の落ちこぼれを防ぐもので
ある。軽量で強度があり、通水性のある波型の帯状体、
ネット状堰板などが適している。 (1)波型帯状体 図7に示すように、厚さ1.6mmの亜鉛メッキ鋼板を
素材とし、プレノッチロールフォーミング成形により、
巾10cmで高さ3cmの二連の波形断面を持つ、長さ
1mの帯状体41からなり、波形の各斜面に多数の通水
孔42を付設してある。 (2)ネット状堰板 ネット状堰板43は、簡易に土をせき止める目的であ
り、盛土の完成の後、法面を植生する場合などに適して
いる。金網、プラスチックネット、編網等が広く使用で
きるが、図8に示したのは比較的強度が大きく、目の粗
い亜鉛メッキ金網44の内面に、土の落ちこぼれを防ぐ
ため不織布等の透水性シート45を貼り合わせしたもの
である。Barrier plate The barrier plate 4 is attached to a pile to block the embankment before the embankment work is performed on the anchor material to prevent the soil from falling off. Lightweight, strong, water-permeable corrugated strip,
A net barrier is suitable. (1) Corrugated strip As shown in FIG. 7, using a zinc-plated steel sheet having a thickness of 1.6 mm as a material, by pre-notch roll forming,
It is composed of a band-shaped body 41 having a width of 10 cm and a height of 3 cm and having two corrugated cross-sections and having a length of 1 m, and a large number of water passage holes 42 are attached to each slope of the corrugation. (2) Net-shaped dam plate The net-shaped dam plate 43 is for the purpose of easily damming the soil, and is suitable for vegetation on the slope after the completion of the embankment. Although wire nets, plastic nets, knitted nets, etc. can be widely used, the one shown in FIG. 8 has a relatively large strength, and a water-permeable sheet of non-woven fabric or the like is formed on the inner surface of the zinc-plated metal net 44 having a coarse mesh to prevent the falling of soil. 45 is pasted together.
【0009】第一次盛土の構築 盛土基盤は盛土施工のスタートであり、盛土の基礎を確
固にするためのものである。図9に示すように、盛土体
を形成する地盤をローラー等を用いて充分に締め固めて
平坦にし、盛土基盤50を形成した後、アンカー材1を
その上に水平に敷設する。敷設する際には、アンカー材
1の端部には巻付管21を取付けたうえ、巻付管21を
盛土の法尻計画線に沿うように配置する。法尻計画線に
そって1m間隔で杭3を鉛直に打ち込む。杭と杭の間に
は横断方向に堰板4を設置する。杭3と巻付管21とを
ターンバックル23を用いて確りと接合し、アンカー材
1を反対方向に引っ張ってフックピン24を用いて盛土
基盤50に固定する。杭3が盛土巻き出し時の土圧によ
って外側に傾かないようにするには、図に示すように、
杭3を外側から筋交い25を用いて支持するのが有効で
ある。盛土が完成してから取り外すことが可能である。
このような準備がでれば、盛土基盤50上に盛土作業を
行い、転圧ローラー52を用いて確りと締め固めて第一
次盛土51を完成する。Construction of the first embankment The embankment foundation is the start of embankment construction and is intended to solidify the foundation of the embankment. As shown in FIG. 9, the ground forming the embankment is sufficiently compacted and flattened by using a roller or the like to form the embankment base 50, and then the anchor material 1 is laid horizontally on the embankment base 50. At the time of laying, the winding pipe 21 is attached to the end portion of the anchor material 1, and the winding pipe 21 is arranged along the sloped planned line of the embankment. Drive piles 3 vertically at 1m intervals along the Hojiri planning line. A weir plate 4 is installed in the transverse direction between the piles. The pile 3 and the winding pipe 21 are firmly joined together using the turnbuckle 23, and the anchor material 1 is pulled in the opposite direction and fixed to the embankment base 50 using the hook pin 24. To prevent the piles 3 from tilting outward due to earth pressure when unwinding the embankment, as shown in the figure,
It is effective to support the pile 3 from the outside by using the braces 25. It can be removed after the embankment is completed.
After such preparation, the embankment work is performed on the embankment base 50, and the compaction roller 52 is used to firmly compact it to complete the primary embankment 51.
【0010】盛土の完成 図1に示すように、第一次盛土51の上にアンカー材1
を敷設する。敷設する際には、アンカー材1の端部には
巻付管21を取付けたうえ、巻付管21を第一次盛土5
1の法肩53、これは杭3の上端の位置にも当たるが、
から30cm奥に入った地点を杭計画線とし、この計画
線に沿って1m間隔で杭3を鉛直に打ち込む。杭は確り
と深く打ち込む。杭と杭の間には横断方向に堰板4を設
置する。杭3と巻付管21とをターンバックル23を用
いて確りと接合し、アンカー材1を反対方向に引っ張っ
てフックピン24を用いて第一次盛土51に固定する。
第一次盛土の場合と同様に、筋交い25を用いて杭の傾
きを防止してもよい。このような準備が完了すれば、第
一次盛土の上の盛土5を行う。以下、このような作業を
繰り返し、多層状のアンカー材で補強された盛土体を完
成する。各層の盛土の法肩53と杭3との間には小段5
4が形成される。Completion of the embankment As shown in FIG. 1, the anchor material 1 is placed on the primary embankment 51.
To lay. When laying, the winding tube 21 is attached to the end of the anchor material 1, and the winding tube 21 is attached to the primary embankment 5
No. 1 shoulder 53, which also hits the upper end of the pile 3,
A point 30 cm deep from is used as a pile planning line, and piles 3 are vertically driven at 1 m intervals along this planning line. Drive the pile firmly and deeply. A weir plate 4 is installed in the transverse direction between the piles. The pile 3 and the winding pipe 21 are firmly joined using the turnbuckle 23, the anchor material 1 is pulled in the opposite direction, and fixed to the primary embankment 51 using the hook pin 24.
As in the case of the first embankment, the braces 25 may be used to prevent the pile from tilting. When such preparation is completed, the embankment 5 on the first embankment is performed. Hereinafter, such work is repeated to complete the embankment body reinforced by the multilayer anchor material. A small step 5 is placed between the upper shoulder 53 of the embankment of each layer and the pile 3.
4 is formed.
【0011】杭3とアンカー材1との連結は、杭が盛土
の土圧で外側に押し出されるのを、カンカー材の引張力
を用いて移動するのを防ぐのが最大の目的である。従っ
て、両者の連結は水平方向の移動を抑制すればよい。長
期的な観点から、上層に敷設するアンカー材は、その層
の上に立設する杭の下端部に連結するのみならず、直
接、ないしは、引張力の大きいスペーサーなどを介する
とか、下層のアンカー材を盛土の先端を巻き戻して上層
のアンカー材と連結するなどの方法で間接的に、一段下
の杭の上端にも連結しておいて、盛土の完成後も杭が外
側に倒れることを防止するのが望ましい。The greatest purpose of the connection between the pile 3 and the anchor material 1 is to prevent the pile from being pushed out by the earth pressure of the embankment and moving by the tensile force of the canker material. Therefore, the connection between the two may be suppressed in the horizontal movement. From a long-term perspective, the anchor material laid in the upper layer is not only connected to the lower end of the pile erected on the layer, but also directly or through a spacer with a large tensile force, or the anchor in the lower layer. Indirectly connect the material to the upper end of the pile one step lower by unwinding the tip of the embankment and connecting it with the anchor material of the upper layer, so that the pile will not fall outside even after the embankment is completed. It is desirable to prevent it.
【0012】杭とアンカー材との連結方法を例示すると
次のとおりである。図10に示すように、亜鉛メッキを
施した鋼板からなるL字型の長尺材からなる連結具6を
形成する。短辺61には5cm間隔でボルト孔62を設
け、長辺63には縁に沿って多数の連結突起64を設け
る。この連結突起64を面状アンカー材11の端部の網
の目に差込んで面状アンカー材11と連結する。短辺6
1の外側にはU字ボルト26を用いて杭3と連結する。
連結具6を介して杭3と面状アンカー材は連結される。An example of the method of connecting the pile and the anchor material is as follows. As shown in FIG. 10, the connector 6 made of an L-shaped long member made of a galvanized steel plate is formed. The short side 61 is provided with bolt holes 62 at 5 cm intervals, and the long side 63 is provided with a large number of connecting protrusions 64 along the edge. The connecting protrusions 64 are inserted into the meshes at the end portions of the planar anchor material 11 to connect to the planar anchor material 11. Short side 6
A U-shaped bolt 26 is used to connect the pile 3 to the outside of the pile 1.
The pile 3 and the planar anchor material are connected to each other via the connecting tool 6.
【0013】又、図11に示すように、面状アンカー材
11に杭用の十文字の切れ目14を設ける。切れ目を設
けることによる面状アンカー材の引張強度の低下を補う
ために、亜鉛メッキ鋼板に杭3の大きさに合致する貫通
孔65を設けた補強板66を準備し、上記切れ目14の
周囲に接合すればよい。杭3をこの貫進孔65に打ち込
むことにより杭3の水平方向、即ち、引張力の移動を抑
制することが可能となる。Further, as shown in FIG. 11, cross-shaped cuts 14 for piles are provided on the planar anchor material 11. In order to compensate for the decrease in tensile strength of the planar anchor material due to the provision of the cut, a reinforcing plate 66 having a through hole 65 matching the size of the pile 3 is prepared in the galvanized steel plate, and the reinforcing plate 66 is provided around the cut 14. Just join them. By driving the pile 3 into the penetration hole 65, it is possible to suppress the movement of the pile 3 in the horizontal direction, that is, the tensile force.
【0014】[0014]
【実施例2】筒状体を用いた施工方法を説明する。筒状
体7は杭3を正確に打つための補助材で、杭3が余裕を
もって挿入できる内径を持つものである。通常は内径1
0cm程度の鋼管を用いる。図12に示すように、盛土
基盤50の上の法尻計画線に沿って、1m間隔で筒状体
7を上端が盛土基盤50に埋まる程度に深く、鉛直に打
ち込む。この筒状体7の中に杭3を差込み、その周囲に
は早強モルタル71を注入して杭3の鉛直度を調節しな
がら固定する。杭3は次層の盛土の高さ分だけ突出させ
る。杭3の裏面には堰板4を取付ける。盛土基盤50の
上には面状アンカー材11を水平に敷設する。[Embodiment 2] A construction method using a tubular body will be described. The tubular body 7 is an auxiliary material for accurately driving the pile 3, and has an inner diameter that allows the pile 3 to be inserted with a margin. Usually 1 inner diameter
A steel pipe of about 0 cm is used. As shown in FIG. 12, the cylindrical bodies 7 are vertically driven at 1 m intervals along the Fushiri planning line on the embankment base 50 deep enough to fill the upper end of the embankment base 50. The pile 3 is inserted into the tubular body 7, and early strong mortar 71 is injected around the pile 3 to fix it while adjusting the verticality of the pile 3. The pile 3 is made to protrude by the height of the embankment of the next layer. A weir plate 4 is attached to the back surface of the pile 3. The planar anchor material 11 is laid horizontally on the embankment base 50.
【0015】上記作業に引続き、杭3から30cmの間
隔をおいた個所に、次層の筒状体7を立設する。筒状体
7と杭3とは上下二個所でスペーサー27を介して固定
する。筒状体7の高さは計画盛土高よりもやや低くし、
土が入らないように上面にカバー72を被せておく。こ
のように準備した後、第一次盛土51を施工する。盛土
は充分に転圧して固める。次層の盛土を施工する場合に
は、筒状体7のカバー72を破いて杭3を挿入し、モル
タルを用いて固定するという、上記の操作を繰り返し、
全体の盛土を施工する。Subsequent to the above work, the cylindrical body 7 of the next layer is erected at a position spaced from the pile 3 by 30 cm. The tubular body 7 and the pile 3 are fixed to each other at two upper and lower positions via spacers 27. The height of the tubular body 7 should be slightly lower than the planned embankment height,
The upper surface is covered with a cover 72 to prevent dirt from entering. After preparing in this way, the first embankment 51 is constructed. The embankment should be compacted by sufficient compaction. When constructing the embankment of the next layer, the cover 72 of the tubular body 7 is ruptured, the pile 3 is inserted, and the mortar is used to fix the same.
Build the entire embankment.
【0016】図13に示すように、盛土基盤50に低い
杭3を立設し、これに対応する低い筒状体7を立設し、
この高さ迄盛土5を行う。次いで、筒状体7に杭を挿入
・立設し、筒状体を平行に立てる、という操作を繰り返
すことにより、アンカー材1とアンカー材1との層を複
数の盛土5層に分割することも可能である。各盛土5層
毎に小段54が形成される。このような場合、杭3と筒
状体7は図14に示すように、スペーサー27を用いて
予め平行に接合しておくことができ、施工能率が良くな
る。As shown in FIG. 13, a low pile 3 is erected on the embankment base 50, and a corresponding low tubular body 7 is erected on it.
Fill 5 up to this height. Then, the pile of the anchor material 1 and the anchor material 1 is divided into a plurality of embankments 5 layers by repeating the operation of inserting and standing the pile in the tubular body 7 and standing the tubular body in parallel. Is also possible. A small step 54 is formed for each 5 layers of embankment. In such a case, the pile 3 and the tubular body 7 can be preliminarily joined in parallel with each other by using a spacer 27 as shown in FIG. 14, which improves the construction efficiency.
【0017】[0017]
【実施例3】枠体を用いた施工方法を説明する。枠体8
は、杭を地盤に打ち込めないような場合に用いる。図1
5に示すように、リップミゾ形鋼34からなる杭3を二
本1.2mの間隔をおいてミゾ部35を向かい合わせて
一対とする。下端には直交方向に基礎枠材81を接合す
る。直角を確保するために内角には筋交い25で補強す
る。基礎枠材81同志の間は二枚の連結枠板82で連結
し枠体8を完成する。[Embodiment 3] A construction method using a frame will be described. Frame 8
Is used when piles cannot be driven into the ground. Figure 1
As shown in FIG. 5, two piles 3 made of lip-grooved steel 34 are arranged at intervals of 1.2 m so that the groove portions 35 face each other to form a pair. A base frame member 81 is joined to the lower end in the orthogonal direction. The inner corners are reinforced with braces 25 to ensure a right angle. The base frame members 81 are connected by two connecting frame plates 82 to complete the frame body 8.
【0018】図16に示すように、盛土基盤51の上の
法尻計画線に合わせて、基礎枠材を内側にして枠体8を
設置する。隣接する枠体同志は基礎枠材、並びに杭同志
をボルトナットなどで連結する。対峙するミゾ部35に
は波型帯状体41を落とし込んで、全面に堰板4を構成
する。盛土基盤51には面状アンカー材11を敷設し、
アンカー材には余裕のある長いものを用い、堰板4の下
端部と連結した上、余り分は堰板4の裏面に巻き上げて
置く。第一次盛土51を行った後、アンカー材の余裕部
分は盛土の上に巻き戻す。このアンカー材の端部は、次
層のアンカー材と共通のフックピン24でもって連結さ
れる。第一次盛土51の上には、法肩53から少し内側
に枠体8を設置し、上記と同様な施工を行い、盛土を完
成する。このように施工すると、枠体8はアンカー材に
より引っ張られているので外側に押し出されることもな
く、同時に、基礎枠材81と連結枠板82の上の盛土重
量で抑えられるので、外側に倒れることがない。又、面
状アンカー材11が盛土を包み込むので堰板に掛かる土
圧を軽減することができる。As shown in FIG. 16, the frame body 8 is installed so that the foundation frame material is on the inside in accordance with the sloping plan line on the embankment base 51. Adjacent frame members connect the foundation frame material and the pile members with bolts and nuts. The corrugated belt-like body 41 is dropped into the facing groove portion 35 to form the dam plate 4 on the entire surface. Laying the planar anchor material 11 on the embankment base 51,
A long anchor material is used, which is connected to the lower end of the dam plate 4, and the surplus portion is wound up on the back surface of the dam plate 4. After performing the primary embankment 51, the surplus portion of the anchor material is rewound onto the embankment. The ends of the anchor material are connected by hook pins 24 that are common to the anchor material of the next layer. On the primary embankment 51, the frame body 8 is installed slightly inward from the shoulder 53, and the same construction as above is performed to complete the embankment. When constructed in this way, the frame body 8 is pulled by the anchor material so that it is not pushed out to the outside, and at the same time, it is suppressed by the embankment weight on the foundation frame material 81 and the connecting frame plate 82, so it falls down to the outside. Never. Further, since the planar anchor material 11 wraps the embankment, the earth pressure applied to the dam plate can be reduced.
【0019】その他の場合 実施例では、杭を間隔をおいて立設し、杭と杭の間には
堰板を設置して盛土を行ったが、図17に示すように、
擬木杭31を並列して立設することもできる。この場
合、杭は裏面で横方向の連結板で連結しておくのが望ま
しい。盛土法面を緑化したい場合には、堰板としてネッ
ト状堰板43を用いて盛土を行い、堰板の裏面に植生種
子紙を貼り付けておくなどの方法が可能である。又、杭
と杭の隙間を開けておくとか、孔空きの堰板を用いるな
どにより実現が可能である。各層の法肩と杭との間の小
段54は水平でもあるので、植生・植栽に最適である。
枠体8としては、図18に示すように、エキスパンドメ
タル83を直角に折り曲げて形成してもよい。折り曲げ
た2辺をターンバックル23を用いて連結しておけば、
設置する盛土面に不陸があったり、盛土の圧で表面が傾
いたりした場合に修正するのに都合がよい。Other Cases In the examples, piles were erected at intervals, and a weir plate was installed between the piles to perform embankment. However, as shown in FIG.
The artificial wood piles 31 can be installed upright in parallel. In this case, it is desirable that the piles be connected to each other on the rear surface by a horizontal connecting plate. When it is desired to green the embankment slope, a method is possible in which the net-shaped dam plate 43 is used as a dam plate for embankment and vegetation seed paper is attached to the back surface of the dam plate. Further, it can be realized by making a gap between the piles or using a dam plate having holes. Since the step 54 between the shoulder and the pile of each layer is also horizontal, it is suitable for vegetation and planting.
The frame body 8 may be formed by bending an expanded metal 83 at a right angle as shown in FIG. If you connect the two bent sides using the turnbuckle 23,
It is convenient to correct when the embankment surface to be installed is uneven or the surface is inclined due to the pressure of the embankment.
【0020】[0020]
【本発明の作用】盛土作業の際に土圧が内側から強く押
しつけることが考えられるが、本発明のように構成する
と、杭は盛土内に深く埋設された引張力大なアンカー材
と連結されているため、アンカー材と盛土との間に働く
摩擦力によって、外側に押し出されることがない。Operation of the present invention It is considered that the earth pressure is strongly pressed from the inside during the embankment work. However, with the construction of the present invention, the pile is connected to the anchor material deeply buried in the embankment and having a large tensile force. Therefore, it is not pushed out by the frictional force acting between the anchor material and the embankment.
【0021】[0021]
【本発明の効果】本発明は次のような効果を得ることが
できる。 (1)通常、盛土法面を形成する場合は、勾配を2割な
いし1割8分とするが、本発明は引張強度の大きいアン
カー材で補強されているので、確実に盛土の崩壊を防ぐ
ので、この勾配を1割ないし3分程度にすることがで
き、有効利用できる土地を拡張できる上、運搬する土量
も少なく経済効果が大きい。 (2)杭ないし堰板をアンカー材に取付けることによっ
て、堰板が安定でき、土嚢袋で盛土法面を形成しないで
も盛土表面の土の落ちこぼれを防ぎ、盛土作業を容易に
することができる。 (3)土嚢積み作業・アンカー材の巻き込み作業を省略
することにより、作業を早めるとともに、人員を削減し
コスト低減を計ることができる。 (4)小段の高さと奥行きにより全体としての法勾配が
決定できるので、正確な勾配の盛土作業ができる。 (5)従来の垂直盛土工法とは違い任意の勾配の盛土が
可能である。 (6)従来の垂直盛土工法のように、盛土表面に大規模
な基礎の上に立つ擁壁を必要とせず、簡便に施工ができ
るのでコストが安くできる。 (7)従来の垂直盛土工法のように、表面壁が剛性板体
に限定されることなく、任意に選択できる。 (8)面状アンカー材は合成樹脂・合成繊維のものがお
おく、盛土法面の表面に使用する場合、燃焼性が間題に
されることがあった。この発明の杭ならびに堰板に不燃
林料を用いると、盛土法面の表面が不燃となり、都合が
よい。 (9)小段は勿論のこと、表面全体を緑化することが可
能である。The present invention can obtain the following effects. (1) Normally, when forming a fill slope, the gradient is set to 20 to 10 minutes, but since the present invention is reinforced with an anchor material having high tensile strength, it is possible to reliably prevent collapse of the fill. Therefore, this gradient can be set to about 10% to 3 minutes, the land that can be effectively used can be expanded, and the amount of soil to be transported is small, which has a large economic effect. (2) By attaching the piles or the dam plate to the anchor material, the dam plate can be stabilized, and even if the embankment slope is not formed by the sandbag, it is possible to prevent the soil from spilling on the embankment surface and facilitate the embankment work. (3) By omitting the sandbag stacking work and the anchor material winding work, the work can be speeded up, the number of personnel can be reduced, and the cost can be reduced. (4) Since the normal gradient as a whole can be determined by the height and depth of the small steps, the embankment work with an accurate gradient can be performed. (5) Unlike the conventional vertical embankment method, embankment with an arbitrary slope is possible. (6) Unlike the conventional vertical embankment method, it does not require a retaining wall standing on a large-scale foundation on the surface of the embankment, and the construction can be performed easily, so the cost can be reduced. (7) The surface wall is not limited to the rigid plate as in the conventional vertical embankment method, and can be arbitrarily selected. (8) Most of the planar anchor materials are synthetic resins and synthetic fibers, and when used on the surface of the embankment slope, flammability was sometimes a problem. It is convenient to use a non-combustible forest material for the pile and the dam plate of the present invention because the surface of the embankment slope becomes non-combustible. (9) It is possible to green the entire surface as well as the small steps.
【図1】 盛土の施工方法を示す説明図である。FIG. 1 is an explanatory view showing a method of constructing an embankment.
【図2】 面状アンカー材の説明図である。FIG. 2 is an explanatory diagram of a planar anchor material.
【図3】 帯状アンカー材の説明図である。FIG. 3 is an explanatory diagram of a band-shaped anchor material.
【図4】 線状アンカー材の説明図である。FIG. 4 is an explanatory diagram of a linear anchor material.
【図5】 擬木杭の斜視図である。FIG. 5 is a perspective view of a pseudo wood pile.
【図6】 合成杭の斜視図である。FIG. 6 is a perspective view of a composite pile.
【図7】 波型帯状体の堰板の斜視図である。FIG. 7 is a perspective view of a dam plate having a corrugated band.
【図8】 ネット状堰板の斜視図である。FIG. 8 is a perspective view of a net-like dam plate.
【図9】 第一次盛土の施工方法を示す説明図であ
る。FIG. 9 is an explanatory diagram showing a method of constructing the first embankment.
【図10】 杭とアンカー材の連結方法を示す説明図で
ある。FIG. 10 is an explanatory diagram showing a method of connecting a pile and an anchor material.
【図11】 杭とアンカー材の他の連結方法を示す説明
図である。FIG. 11 is an explanatory view showing another method of connecting the pile and the anchor material.
【図12】 盛土の施工方法の他の例を示す説明図であ
る。FIG. 12 is an explanatory diagram showing another example of a method of constructing an embankment.
【図13】 小段の形成方法を示す説明図である。FIG. 13 is an explanatory diagram showing a method of forming small steps.
【図14】 筒状体を予め接合した杭の斜視図である。FIG. 14 is a perspective view of a pile in which tubular bodies are joined in advance.
【図15】 枠体の形成状況を示す説明図である。FIG. 15 is an explanatory diagram showing a formation state of a frame body.
【図16】 盛土の施工方法の他の例を示す説明図であ
る。FIG. 16 is an explanatory diagram showing another example of a method of constructing an embankment.
【図17】 杭の設置状況を示す説明図である。FIG. 17 is an explanatory diagram showing a situation of installing piles.
【図18】 枠体の他の例の斜視図である。FIG. 18 is a perspective view of another example of the frame body.
Claims (8)
る補強盛土工法において、既設盛土上に引張強度の大き
いアンカー材を略水平に敷設し、既設盛土の法肩から所
定の間隔内測の盛土に杭を連続的に立設し、上記杭と上
記アンカー材とを連結してから、次層の盛土工事を行
う、補強盛土の施工方法。1. A reinforced embankment method for laying a plurality of layers of anchor material in a horizontal direction, in which an anchor material having a high tensile strength is laid substantially horizontally on an existing embankment and is measured at a predetermined distance from the shoulder of the existing embankment. A method of constructing a reinforced embankment, in which piles are continuously erected on the embankment, the pile and the anchor material are connected, and then the embankment work for the next layer is performed.
る補強盛土工法において、既設盛土上に引張強度の大き
いアンカー材を略水平に敷設し、既設盛土の法肩から所
定の間隔内側の盛土に、複数本の杭を所定間隔をおいて
立設し、上記杭と上記アンカー材とを連結すると共に、
上記杭に堰板を取付けてから、次層の盛土工事を行う、
補強盛土の施工方法。2. A reinforced embankment method for laying a plurality of layers of anchor material in a horizontal direction, in which an anchor material having high tensile strength is laid substantially horizontally on an existing embankment, and the embankment is located at a predetermined distance from the shoulder of the existing embankment. In, a plurality of piles are erected at a predetermined interval, while connecting the pile and the anchor material,
After installing the weir plate on the pile, perform embankment work on the next layer,
Construction method of reinforced embankment.
されたアンカー材にも連結されたことを特徴とした、請
求項1ないし請求項2記載の、補強盛土の施工方法。3. The method of constructing a reinforced embankment according to claim 1, wherein the pile is also connected to an anchor material embedded under the uppermost embankment of the existing embankment.
側の個所に、筒状体を立設し、上記筒状体を盛土上に敷
設されたアンカー材に連結した後に盛土工事を行い、次
層の盛土工事を行う際には、杭を上記筒状体に挿入して
所定の位置で固定して杭を立設することを特徴とした、
請求項1ないし請求項3記載の、補強盛土の施工方法。4. When embedding a pile, a tubular body is erected at a position inside a predetermined distance from the pile, and the tubular body is connected to an anchor material laid on the embankment before embankment work. When performing the embankment work of the next layer, the pile is inserted into the tubular body and fixed at a predetermined position to stand the pile.
The method for constructing a reinforced embankment according to claim 1.
平行に接合されたものである、請求項4記載の補強盛土
の施工方法。5. The method for constructing a reinforced embankment according to claim 4, wherein the pile and the tubular body are preliminarily joined in parallel at a predetermined interval.
杭の根入れ際の個所で杭と連結され、その延長部が杭並
びに堰板の内面に沿って巻き上げられ、盛土の上端で内
側に巻き戻されて次層の盛土上に敷設されたことを特徴
とする、補強盛土の施工方法。6. The anchor material is a planar anchor material,
It was connected to the pile at the point of rooting the pile, and its extension was rolled up along the inner surface of the pile and the weir plate, rewound inward at the upper edge of the embankment and laid on the next layer of embankment. The characteristic method of constructing a reinforced embankment.
は、堰板面には空隙が設けられ、この空隙を通して植生
が行われることを特徴とした、請求項1ないし請求項6
記載の、補強盛土の施工方法。7. The method according to claim 1, wherein a gap is provided between the piles forming the embankment surface or between the piles or on the surface of the dam plate, and vegetation is performed through the gaps.
The method of construction of the reinforced embankment described.
小段には、植生ないし植栽が行われることを特徴とし
た、請求項1ないし請求項7記載の、補強盛土の施工方
法。8. The construction of a reinforced embankment according to claim 1, wherein vegetation or planting is performed on the step formed between the shoulder of the embankment and the pile of the next layer. Method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3285396A JPH0680249B2 (en) | 1991-08-07 | 1991-08-07 | Reinforced embankment construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3285396A JPH0680249B2 (en) | 1991-08-07 | 1991-08-07 | Reinforced embankment construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0539613A JPH0539613A (en) | 1993-02-19 |
| JPH0680249B2 true JPH0680249B2 (en) | 1994-10-12 |
Family
ID=17690993
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP3285396A Expired - Lifetime JPH0680249B2 (en) | 1991-08-07 | 1991-08-07 | Reinforced embankment construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0680249B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5945167B2 (en) * | 2012-06-08 | 2016-07-05 | 宏明 石原 | Basic construction method, photovoltaic panel construction method and building construction method |
| JP6444241B2 (en) * | 2015-03-30 | 2018-12-26 | 日鐵住金建材株式会社 | Earth retaining fence |
-
1991
- 1991-08-07 JP JP3285396A patent/JPH0680249B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0539613A (en) | 1993-02-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4343571A (en) | Reinforced earth structures | |
| US7377725B2 (en) | Arched soil nail wall | |
| US20070286688A1 (en) | Retaining wall having modular panels | |
| CN110656652B (en) | A three-dimensional ecological bag slope protection structure | |
| US20080267718A1 (en) | Reinforced Soil Retaining Wall System and Method of Construction | |
| EP0574233A1 (en) | Method for forming vegetated slopes in strengthened ground and a product obtained by such method | |
| CN209703527U (en) | A three-dimensional ecological bag slope protection structure | |
| JP2597116B2 (en) | Embankment foundation and its construction method | |
| JPH0680249B2 (en) | Reinforced embankment construction method | |
| JP3472708B2 (en) | Slope and seawall retaining wall structures and their construction methods | |
| JPS6245801A (en) | Construction of structure by foamed resin block | |
| JP3580410B2 (en) | Wall material reinforced earth construction method | |
| JP4330504B2 (en) | Construction method of the stable soil structure on the slope of the impervious sheet | |
| JP2023127771A (en) | Embankment reinforcement wall and construction method for embankment reinforcement wall | |
| JP2750364B2 (en) | Steep embankment | |
| JPH0841880A (en) | Vegetation method of embankment slope | |
| Douglas | Design and construction of fabric-reinforced retaining walls by New York State | |
| JPH06128961A (en) | Embankment construction method | |
| JP2631056B2 (en) | Embankment structure reinforced with concrete underground beams | |
| JP2000328577A (en) | Soil retaining cage frame and method of building steep grade banking using the cage frame | |
| JPH0790863A (en) | Retaining wall for embankment | |
| JPH0351426A (en) | Lightweight banking structure | |
| JPS6351527A (en) | Slope stabilization work | |
| JPH0359220A (en) | Steep slope embankment and earth retaining members used for it | |
| JP2000273867A (en) | Method for constructing steep banking |