Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0689525B2 - Elevated railway bridge and its construction method - Google Patents
[go: Go Back, main page]

JPH0689525B2 - Elevated railway bridge and its construction method - Google Patents

Elevated railway bridge and its construction method

Info

Publication number
JPH0689525B2
JPH0689525B2 JP32965190A JP32965190A JPH0689525B2 JP H0689525 B2 JPH0689525 B2 JP H0689525B2 JP 32965190 A JP32965190 A JP 32965190A JP 32965190 A JP32965190 A JP 32965190A JP H0689525 B2 JPH0689525 B2 JP H0689525B2
Authority
JP
Japan
Prior art keywords
slab
railway bridge
main beam
installation
elevated railway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP32965190A
Other languages
Japanese (ja)
Other versions
JPH04202905A (en
Inventor
俊夫 梅原
武雄 宮崎
五八男 鶴田
好弘 村山
建次 斉藤
達夫 若井
Original Assignee
日本鉄道建設公団
スパンクリート製造株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日本鉄道建設公団, スパンクリート製造株式会社 filed Critical 日本鉄道建設公団
Priority to JP32965190A priority Critical patent/JPH0689525B2/en
Publication of JPH04202905A publication Critical patent/JPH04202905A/en
Publication of JPH0689525B2 publication Critical patent/JPH0689525B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は高架鉄道橋及びその構築工法に関するものであ
る。
TECHNICAL FIELD The present invention relates to an elevated railway bridge and a construction method thereof.

(従来の技術) 現在、鉄道に用いられている高架鉄道橋は、第5図に示
すように主梁40、スラブ50、横梁20及び防音壁30が夫々
一体に構築されている。
(Prior Art) In an elevated railway bridge currently used for railways, a main beam 40, a slab 50, a lateral beam 20, and a soundproof wall 30 are integrally constructed as shown in FIG.

これは、現場において柱脚10の上端まで型枠を建ち上
げ、該型枠に現場打ちコンクリートを打設して構築する
ものである。
This is a construction in which a formwork is built up to the upper end of the column base 10 at the site and the cast-in-place concrete is placed on the formwork.

しかし、この構築方法はわざわざ柱脚10の上端まで型枠
を建ち上げ、この型枠を柱脚10と同等或はそれ以上の長
さの支保工で支えなければならないため、工費が蒿むと
共に工期も長期化するという問題があった。
However, in this construction method, the formwork must be purposefully built up to the upper end of the column base 10, and this formwork must be supported by a support work of a length equal to or longer than that of the column base 10. There was a problem that the construction period would be prolonged.

さらに高架鉄道橋は多雪地帯において、線路上の雪をど
のように処理するかが大きな課題であり、従来はこの線
路上の雪の処理対策として、散水消雪、ラッセル車又は
ロータリ車等による強制排雪が行われていたが、これら
はいずれも多大の経費を必要とするという問題があっ
た。
Furthermore, how to handle snow on railway tracks is a major issue in elevated snow bridges in heavy snowfall areas. Conventionally, as measures against snow on these railway tracks, sprinkling snow removal, Russell cars or rotary cars have been used. Although forced snow removal was performed, all of them had a problem that they required a great deal of expense.

そこで、これらの問題を解決するために、主梁の脇に線
路上等の雪を収容するための貯雪部を備えた高架鉄道橋
が考えられた。
Therefore, in order to solve these problems, an elevated railway bridge having a snow storage section for accommodating snow on the tracks and the like beside the main beam was considered.

これは、現場打ちコンクリートで主梁、スラブ、横梁、
ダクトを夫々一体的に構築するものや、前記スラブを除
くこれらの三部材に鋼材を取り付けてこの四部材とプレ
キャストコンクリート版とを組合わせて構成するものと
がある。
This is cast-in-place concrete with main beams, slabs, cross beams,
There are those in which the ducts are integrally constructed, and those in which a steel material is attached to these three members excluding the slab and the four members are combined with a precast concrete slab.

(発明が解決しようとする課題) しかしながら、上記の主梁、スラブ、横梁、ダクトが一
体となったものは、貯雪部のスラブが薄いためひび割れ
が発生する恐れがあり、また主梁とスラブとが一体にな
っているため列車走行時に、主梁の振動がスラブに直接
伝達してスラブも振動させる二次騒音の原因となってい
た。
(Problems to be solved by the invention) However, the above-mentioned main beam, slab, lateral beam, and duct are integrated, and the slab of the snow storage part is thin, so cracks may occur, and the main beam and slab Because of the integrated structure, the vibration of the main beam was directly transmitted to the slab when the train was running, causing secondary noise that also vibrates the slab.

また、主梁、横梁、ダクトの三部材に鋼材を取り付ける
ものは、鋼材を使用するために材料費が高価になるばか
りでなく、防水工や施工も複雑となるため非経済的であ
った。
Further, the one in which the steel member is attached to the three members of the main beam, the lateral beam, and the duct is uneconomical because not only the material cost becomes expensive because the steel member is used but also the waterproofing work and the construction become complicated.

本発明は上記のような問題に鑑みてなされたものであ
り、その目的は、短期間でかつ容易に構築することがで
き、しかも建設費や排雪費等の維持管理費が安価な高架
鉄道橋及びその構築工法を提供することである。
The present invention has been made in view of the above problems, and an object thereof is an elevated railway that can be easily constructed in a short period of time and that maintenance costs such as construction costs and snow removal costs are low. It is to provide a bridge and its construction method.

(課題を達成するための手段) 以上のような課題を達成するための本発明の高架鉄道橋
は、高架鉄道橋用柱脚の上端に横幅方向に掛け渡した横
梁と、該横梁間に線路の敷設方向へ架け渡したプレキャ
ストコンクリート製の設置スラブと、該設置スラブ上で
前記各高架鉄道橋用柱脚間にわたって形成した主梁と、
該主梁と設置スラブの両側に立設した防音壁との間に形
成した貯雪部とによりなることを特徴とする構成にする
ことであり、 また、高架鉄道橋の構築工法は、適宜間隔をもって連続
的に立設した高架鉄道橋用柱脚の上端に横梁を掛け渡
し、該横梁間にプレキャストコンクリート版を敷設して
線路の敷設方向へ伸びる設置スラブを形成し、該設置ス
ラブの上面に設置スラブを基盤として支保工を建てて型
枠を設置した後、該型枠内にコンクリートを打設して前
記横梁間に主梁を架設し、設置スラブの両側に防音壁を
立設して該防音壁と前記主梁との間に貯雪部を形成する
ことを特徴とする構成にすることである。
(Means for Achieving the Object) The elevated railway bridge of the present invention for achieving the above-mentioned object is a cross beam crossed over the upper end of a pillar pier for an elevated railway bridge in the lateral width direction, and a line between the cross beams. An installation slab made of precast concrete that has been bridged in the laying direction of, and a main beam formed over the installation slab between each of the elevated railroad bridge column bases,
The construction method is characterized by comprising a snow-storing part formed between the main beam and soundproof walls standing upright on both sides of the installation slab. A horizontal beam is laid on the upper end of the column base for an elevated railway bridge that is continuously erected, a precast concrete plate is laid between the horizontal beams to form an installation slab that extends in the laying direction of the track, and it is installed on the upper surface of the installation slab. After constructing a supporting structure based on a slab and installing a formwork, concrete is placed in the formwork and a main beam is installed between the horizontal beams, and soundproof walls are erected on both sides of the installation slab. A snow storage part is formed between the soundproof wall and the main beam.

(作用) 而して、上記のような構成の高架鉄道橋によれば、主梁
の下側における防音壁との間に貯雪部が形成されること
により、該貯雪部のスペースを大きくとることができる
ので、排雪が容易となって排雪費等の維持管理費を低減
することができると共に、設置スラブ面の上に主梁を架
設するので設置スラブのスペースも大きくとることがで
きる。
(Operation) According to the elevated railway bridge having the above-described structure, the snow storage portion is formed between the soundproof wall below the main beam, so that the space of the snow storage portion is increased. Since the snow can be easily removed, maintenance costs such as snow removal costs can be reduced, and since the main beam is installed on the surface of the installation slab, a large space for the installation slab can be secured.

また、上記のような高架鉄道橋の構築工法によれば、設
置スラブをプレキャストコンクリート版で形成したこと
により、短期間で構築することができ、しかも長大な支
保工を必要としないため、建設費の低減することができ
る。
Further, according to the construction method of the elevated railway bridge as described above, since the installation slab is formed of the precast concrete slab, it can be constructed in a short period of time and, in addition, a long support work is not required. Can be reduced.

(実施例) 以下、本発明の一実施例を図面に基づいて詳細に説明す
る。
(Example) Hereinafter, one example of the present invention will be described in detail with reference to the drawings.

第1図は高架鉄道橋の横断面図、第2図は同側面図を夫
々示す。
FIG. 1 is a cross-sectional view of the elevated railway bridge, and FIG. 2 is a side view of the same.

高架鉄道橋Aは高架鉄道橋用柱脚1の上端に横梁2を形
成し、該横梁2の上面にプレキャストコンクリート版3a
を敷設して線路4aを敷設方向に伸びる設置スラブ3を形
成し、該設置スラブ3上の前記横梁2間に渡って主梁4
を形成することにより、該主梁4と設置スラブ3両側の
防音壁3bとの間に貯雪部5を形成して構成されている。
The elevated railway bridge A has a horizontal beam 2 formed on the upper end of a column base 1 for an elevated railway bridge, and a precast concrete slab 3a is formed on the upper surface of the horizontal beam 2.
Is installed to form the installation slab 3 extending in the laying direction of the line 4a, and the main beam 4 is extended across the installation slab 3 between the horizontal beams 2.
By forming the above, the snow storage part 5 is formed between the main beam 4 and the soundproof walls 3b on both sides of the installation slab 3.

前記主梁4は設置スラブ3上に形成した型枠に現場打ち
コンクリートを打設することにより、横梁2で支持され
るように形成される。そして、この主梁4の形成により
隣接する横梁2が強固に結合されて耐震的に優れた構造
となる。
The main beam 4 is formed so as to be supported by the horizontal beam 2 by pouring cast-in-place concrete into a form formed on the installation slab 3. Then, by the formation of the main beam 4, the adjacent horizontal beams 2 are firmly connected to each other, and a structure excellent in earthquake resistance is obtained.

また、主梁4はその荷重を高架鉄道橋用柱脚1で支持す
るように、高架鉄道橋用柱脚1上に形成され、その上面
に線路4aが敷設される。
Further, the main beam 4 is formed on the pedestal 1 for the elevated railway bridge so that the load is supported by the pedestal 1 for the elevated railway bridge, and a track 4a is laid on the upper surface thereof.

このように主梁4が横梁2と設置スラブ3上に設置され
たので、該主梁4の脇の下側に貯雪部5が形成され、該
貯雪部5へ線路4a上に積もった雪を排雪することができ
る。
Since the main beam 4 is installed on the horizontal beam 2 and the installation slab 3 in this way, a snow storage part 5 is formed under the side of the main beam 4 and the snow accumulated on the track 4a is discharged to the snow storage part 5. can do.

次に、この高架鉄道橋Aの構築工法について説明する。Next, the construction method of this elevated railway bridge A will be described.

第3図及び第4図は高架鉄道橋Aの構築工法を示した横
断面図及び側面図である。
3 and 4 are a cross-sectional view and a side view showing the construction method of the elevated railway bridge A.

[横梁の形成] 先ず初めに、線路4aの敷設方向にそって適宜間隔をもっ
て立設された、各高架鉄道橋用柱脚1の上端に横梁2を
形成する。これは高架鉄道橋用柱脚1の上端に型枠を形
成し、該型枠に鉄筋を配筋して、現場打ちコンクリート
を打設することにより形成するものである。
[Formation of Cross Beam] First, a cross beam 2 is formed at the upper end of each elevated railroad bridge column base 1, which is erected at appropriate intervals along the laying direction of the line 4a. This is formed by forming a formwork at the upper end of the column base 1 for an elevated railway bridge, arranging reinforcing bars in the formwork, and pouring cast-in-place concrete.

[設置スラブの敷設] 次に、前記横梁2間にわたってプレキャストコンクリー
ト版3aを夫々掛け渡して、線路4aの敷設方向に設置スラ
ブ3を形成する。
[Laying Installation Slab] Next, the precast concrete slabs 3a are laid across the transverse beams 2 to form the installation slab 3 in the laying direction of the line 4a.

[主梁の形成] 上記のように横梁2と設置スラブ3を形成した後、該設
置スラブ3を基盤としてその上面に支保工を立設して主
梁4用の型枠を形成する。
[Formation of Main Beam] After forming the horizontal beam 2 and the installation slab 3 as described above, a supporting structure is erected on the upper surface of the installation slab 3 as a base to form a formwork for the main beam 4.

この際、主梁4のコンクリートの自重による支保工の沈
下量を予め計算し、所要の量だけ上げ越しをしておく。
At this time, the subsidence amount of the supporting work due to the weight of the concrete of the main beam 4 is calculated in advance, and the required amount is raised.

そして、型枠内に鉄筋を配筋して現場打ちコンクリート
を打設すると、主梁4と横梁2とが接続される。
Then, when reinforcing bars are arranged in the formwork and cast-in-place concrete is placed, the main beam 4 and the horizontal beam 2 are connected.

[貯雪部の形成] 次に、前記型枠に打設したコンクリートが硬化した後に
型枠を解体する。そして、設置スラブ3の両側に防音壁
3b用の支持柱3cを横梁2の間隔ごとに立設すると共に、
防音壁3bをクレーンで吊り上げて支持柱3cに取り付ける
ことにより、主梁4の脇の下側と防音壁3bとの間に貯雪
部5が形成される。
[Formation of Snow Storage] Next, the mold is disassembled after the concrete cast into the mold is hardened. And soundproof walls on both sides of the installation slab 3
Support pillars 3c for 3b are erected at intervals of the horizontal beams 2, and
By lifting the soundproof wall 3b with a crane and attaching it to the support pillar 3c, a snow storage part 5 is formed between the soundproof wall 3b and the underside of the main beam 4.

(発明の効果) 本発明は以上のような構成にしたことにより下記の効果
を有する。
(Effects of the Invention) The present invention has the following effects due to the above configuration.

設置スラブをプレキャストコンクリート版で形成する
と共に、主梁を設置スラブの上面に設けたので、該主梁
の下側における防音壁との間に、貯雪スペースを大きく
とることができる。
Since the installation slab is formed of a precast concrete slab and the main beam is provided on the upper surface of the installation slab, a large snow storage space can be secured between the installation beam and the soundproof wall below the main beam.

スラブ面が広く使用できるので、該スラブ面での作業
性及び安全性が向上すると共に、ケーブル用ダクトの設
置場所を任意の箇所に選択することができる。
Since the slab surface can be widely used, the workability and safety on the slab surface are improved, and the installation location of the cable duct can be selected at an arbitrary position.

主梁と設置スラブとが一体に形成されていないので、
列車通過時における主梁の振動が直接スラブに伝わるこ
とがなく、二次騒音が大幅に軽減される。
Since the main beam and the installation slab are not integrally formed,
The vibration of the main beam when passing the train is not directly transmitted to the slab, and the secondary noise is greatly reduced.

プレキャストコンクリート版の力学的性状がはっきり
しているため、支保工の上げ越し計算予測値の確度が高
い。
Since the mechanical properties of the precast concrete slabs are clear, the accuracy of the predicted uplift calculation for shoring work is high.

高架鉄道橋において大きな割合を占めるスラブがプレ
キャストコンクリート版で形成されることにより、型枠
設置、鉄筋組立、コンクリート養生等の工程がなくなる
ので、短期間に高架鉄道橋を構築することができる。
Since the slabs that make up a large proportion of the elevated railway bridge are made of precast concrete slabs, the steps of formwork, rebar assembly, concrete curing, etc. are eliminated, so that the elevated railway bridge can be constructed in a short period of time.

主梁を形成する際に、該主梁の型枠を支持する支保工
を設置スラブ面から建てることができるので、支保工の
空立積が大幅に減少し、経済的でかつ短期間に高架鉄道
橋を構築することができる。
When the main beam is formed, the supporting work that supports the formwork of the main beam can be built from the installation slab surface, so the empty space of the supporting work is greatly reduced, and it is economical and can be elevated in a short time. You can build a railroad bridge.

【図面の簡単な説明】[Brief description of drawings]

第1図は高架鉄道橋の横断面図、第2図は同側面図、第
3図は高架鉄道橋の構築方法を示す横断面図、第4図は
同側面図、第5図は従来の高架鉄道橋の横断面図、第6
図は同縦断面図である。 図中、 A:高架鉄道橋 1:高架鉄道橋用柱脚、2:横梁 3:プレキャストコンクリート版で構築した設置スラブ 3a:プレキャストコンクリート版 3b:防音壁、3c……防音壁用支柱 4:主梁、5:貯雪部 である。
Fig. 1 is a cross-sectional view of an elevated railroad bridge, Fig. 2 is a side view of the same, Fig. 3 is a cross-sectional view showing how to construct an elevated railroad bridge, Fig. 4 is the same side view, and Fig. 5 is a conventional side view. Cross section of elevated railway bridge, No. 6
The figure is a vertical sectional view of the same. In the figure, A: Elevated railway bridge 1: Elevated railway bridge column base, 2: Horizontal beam 3: Installation slab constructed with precast concrete slab 3a: Precast concrete slab 3b: Soundproof wall, 3c ...... Soundproof wall stanchion 4: Main Liang, 5: Snow storage section.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 村山 好弘 東京都文京区本郷1―27―8 本郷ハウス 1105 (72)発明者 斉藤 建次 埼玉県久喜市西582―2 (72)発明者 若井 達夫 千葉県松戸市松戸113―608 (56)参考文献 特公 昭60−59362(JP,B2) 実公 昭54−39761(JP,Y2) ─────────────────────────────────────────────────── ─── Continued Front Page (72) Inventor Yoshihiro Murayama 1-25-8 Hongo Hongo House, Bunkyo-ku, Tokyo 1105 (72) Inventor Kenji Saito 582-2 Nishi, Kuki-shi, Saitama (72) Inventor Tatsuo Wakai 113-608 Matsudo, Matsudo City, Chiba Prefecture (56) References JP 60-59362 (JP, B2) JP 54-39761 (JP, Y2)

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】高架鉄道橋用柱脚の上端に横幅方向に掛け
渡した横梁と、該横梁間に線路の敷設方向へ架け渡した
プレキャストコンクリート製の設置スラブと、該設置ス
ラブ上で前記各高架鉄道橋用柱脚間にわたって形成した
主梁と、該主梁と設置スラブの両側に立設した防音壁と
の間に形成した貯雪部とによりなることを特徴とする高
架鉄道橋。
1. A horizontal beam laid across the widthwise direction on the upper end of a column base for an elevated railway bridge, an installation slab made of precast concrete laid across the horizontal beams in the direction of laying a track, and each of the above-mentioned installation slabs. An elevated railway bridge comprising: a main beam formed between pillar columns for an elevated railway bridge; and a snow storage part formed between the main beam and soundproof walls standing on both sides of the installation slab.
【請求項2】適宜間隔をもって連続的に立設した高架鉄
道橋用柱脚の上端に横梁を掛け渡し、該横梁間にプレキ
ャストコンクリート版を敷設して線路の敷設方向へ伸び
る設置スラブを形成し、該設置スラブの上面に設置スラ
ブを基盤として支保工を建てて型枠を設置した後、該型
枠内にコンクリートを打設して前記横梁間に主梁を架設
し、設置スラブの両側に防音壁を立設して該防音壁と前
記主梁との間に貯雪部を形成することを特徴とする高架
鉄道橋の構築工法。
2. An installation slab that extends in the laying direction of a track is formed by straddling a horizontal beam on the upper end of a column base for an elevated railway bridge that is continuously erected at appropriate intervals and laying a precast concrete slab between the horizontal beams. After installing a supporting structure on the upper surface of the installation slab based on the installation slab and installing a formwork, concrete is placed in the formwork and a main beam is installed between the horizontal beams, and both sides of the installation slab are installed. A construction method for an elevated railway bridge, characterized in that a soundproof wall is erected and a snow storage part is formed between the soundproof wall and the main beam.
JP32965190A 1990-11-30 1990-11-30 Elevated railway bridge and its construction method Expired - Lifetime JPH0689525B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32965190A JPH0689525B2 (en) 1990-11-30 1990-11-30 Elevated railway bridge and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32965190A JPH0689525B2 (en) 1990-11-30 1990-11-30 Elevated railway bridge and its construction method

Publications (2)

Publication Number Publication Date
JPH04202905A JPH04202905A (en) 1992-07-23
JPH0689525B2 true JPH0689525B2 (en) 1994-11-09

Family

ID=18223729

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32965190A Expired - Lifetime JPH0689525B2 (en) 1990-11-30 1990-11-30 Elevated railway bridge and its construction method

Country Status (1)

Country Link
JP (1) JPH0689525B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100601100B1 (en) * 2004-12-21 2006-07-19 재단법인 포항산업과학연구원 Steel pipe PRT bridge
JP5405337B2 (en) * 2010-02-01 2014-02-05 株式会社フジタ Construction method of railway RC ramen structure viaduct

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6059362B2 (en) 2013-11-11 2017-01-11 Ykk株式会社 Suspension material

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6059362B2 (en) 2013-11-11 2017-01-11 Ykk株式会社 Suspension material

Also Published As

Publication number Publication date
JPH04202905A (en) 1992-07-23

Similar Documents

Publication Publication Date Title
US7461427B2 (en) Bridge construction system and method
KR100454405B1 (en) Method for changing steel bridge of supporting rail into concreat bridge
CN202194317U (en) Guide rail structure for cast-in-site concrete slope surface
KR20130068158A (en) Reinforced concrete arch bridge of girder type uniting with superstructure and substructure and its automatic construction method
JP5405337B2 (en) Construction method of railway RC ramen structure viaduct
KR100742206B1 (en) Steel composite ramen bridge with long span and low profile by moment redistribution and construction method
CN105803924A (en) Simply supported T beam sidewalk combination structure and combination method of mixed passenger and freight railway
KR20040086653A (en) bridge and construction process with integral pier-type mixed abutment
JP2002194704A (en) How to build digits
JP4162291B2 (en) Railway work girder cradle and rail work girder cradle construction method
KR100603901B1 (en) Structure and construction method of plate girder bridge using part of existing girder
JPH0689525B2 (en) Elevated railway bridge and its construction method
KR101194866B1 (en) Rahmen bridge construction method using longitudinal and lateral steel member
JP2006112086A (en) Bridge structure and its replacement method
JP3701078B2 (en) Road slab construction method
JP4901178B2 (en) Steel / concrete composite rigid frame bridge construction method
JP3621291B2 (en) Expansion joint structure of bridge
JP2536376B2 (en) Foundation structure of shed for road protection
JP3028157B2 (en) Railroad viaduct structure
JP4233025B2 (en) How to construct a three-dimensional intersection
KR100928166B1 (en) Plain formwork installed prefabricated on the lower flange of type I concrete beam, and construction method of upper slab bridge and disassembly form of formless formwork using the same
JPH046450Y2 (en)
JP3824242B2 (en) Viaduct-free support construction method
CN215160354U (en) Concrete crane beam structure
JPH049901B2 (en)