Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH07116844B2 - External wall member mounting system - Google Patents
[go: Go Back, main page]

JPH07116844B2 - External wall member mounting system - Google Patents

External wall member mounting system

Info

Publication number
JPH07116844B2
JPH07116844B2 JP14066889A JP14066889A JPH07116844B2 JP H07116844 B2 JPH07116844 B2 JP H07116844B2 JP 14066889 A JP14066889 A JP 14066889A JP 14066889 A JP14066889 A JP 14066889A JP H07116844 B2 JPH07116844 B2 JP H07116844B2
Authority
JP
Japan
Prior art keywords
wall
wall member
board
lifting
mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP14066889A
Other languages
Japanese (ja)
Other versions
JPH035573A (en
Inventor
幸男 長谷川
俊男 中村
俊和 宮嶋
祐輔 松下
伸二 山下
信博 奥山
正宏 西村
春夫 星野
徹 篠崎
亮二 吉武
寛 浅野
雅之 寺尾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Kajima Corp
Shimizu Construction Co Ltd
Komatsu Ltd
Takenaka Komuten Co Ltd
Kumagai Gumi Co Ltd
Sato Kogyo Co Ltd
Toda Corp
Original Assignee
Taisei Corp
Kajima Corp
Shimizu Construction Co Ltd
Komatsu Ltd
Takenaka Komuten Co Ltd
Kumagai Gumi Co Ltd
Sato Kogyo Co Ltd
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, Kajima Corp, Shimizu Construction Co Ltd, Komatsu Ltd, Takenaka Komuten Co Ltd, Kumagai Gumi Co Ltd, Sato Kogyo Co Ltd, Toda Corp filed Critical Taisei Corp
Priority to JP14066889A priority Critical patent/JPH07116844B2/en
Publication of JPH035573A publication Critical patent/JPH035573A/en
Publication of JPH07116844B2 publication Critical patent/JPH07116844B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は外壁揚重装置等の省力機械装置を使用して外壁
部材を無人で取りつけられるようにした外壁部材取付け
システムに関するものである。
Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an outer wall member mounting system capable of unmanned mounting of an outer wall member using a labor-saving mechanical device such as an outer wall lifting device.

〔従来の技術〕[Conventional technology]

一般に、建築構造物の外壁を構築する工法として、PCカ
ーテンウォールやアルミカーテンウォールが採用されて
いる。この方法では、タワークレーンなどにより揚重さ
れた外壁部材を作業者が建物内部から身をのり出してつ
かみ、これを取りつけ位置まで引き込むようにして取付
け作業を行っている。
Generally, a PC curtain wall or an aluminum curtain wall is adopted as a construction method for constructing an outer wall of a building structure. According to this method, a worker lifts the outer wall member lifted by a tower crane or the like from the inside of the building, grabs it, and pulls it to the mounting position to perform the mounting work.

〔発明が解決しようとする課題〕 この外壁半PC板は現場での工期短縮、省力化、作業員不
足など最近の社会的背景から多く使われてきている。し
かし、現在使われている外壁半PC板取付け作業は基本的
に人手によるものであり、安全性を向上させるととも
に、作業能率を向上させるには限界があった。そこで外
壁揚重装置等の省力機械装置を導入して外壁の取付けを
しようとしても、従来の外壁半PC板では対応することが
できず、省力機械装置で行うことができる取付け工法に
適したように外壁半PC板の接合部、接合方法などトータ
ルシステムを改善する必要がある。
[Problems to be solved by the invention] This half-wall PC board has been widely used from the recent social background such as shortening the construction period at the site, labor saving, and lack of workers. However, the outer wall half-PC board mounting work currently used is basically manual work, and there is a limit to improving the work efficiency while improving the safety. Therefore, even if you try to install an outer wall by introducing a labor-saving mechanical device such as an outer-wall lifting device, the conventional half-PC board for the outer wall cannot handle it, and it seems that it is suitable for a mounting method that can be performed with a labor-saving mechanical device. In addition, it is necessary to improve the total system such as the joint part of the outer wall half PC board and the joining method.

本発明は上記課題を解決するためのもので、省力機械装
置により無人で簡便、迅速に取付けを行い、省力化、安
全性の向上、作業能率の向上を図ることができる外壁部
材取付けシステムを提供することを目的とする。
The present invention is to solve the above problems, and provides an outer wall member mounting system capable of unmanned, simple, and quick mounting by a labor-saving mechanical device, which can save labor, improve safety, and improve work efficiency. The purpose is to do.

〔課題を解決するための手段〕[Means for Solving the Problems]

そのために本発明の外壁部材取付けシステムは、1階小
梁下に設けられたレールに沿って走行し、上側及び下側
接合治具が設けられた外壁部材を水平状態で把持してス
トックヤードから水平搬送する搬送用装置と、搬送され
た外壁部材が載置され、外壁部材を所定角度まで起こす
位置決め昇降装置と、建物最上階の外周部に敷設された
レール上を走行し、所定角度まで起こされた外壁部材を
把持して垂直状態でワイヤにより揚重する外壁揚重装置
とを備え、外壁揚重装置は外壁部材を外壁の取りつけ位
置まで揚重し、外壁部材を壁側に引き込んで落とし込む
ことにより、外壁部材の上側、下側接合治具をそれぞれ
上階大梁の取付けブラケット、下階外壁部材の上側接合
治具に嵌合させ、固定することを特徴とする。
Therefore, the outer wall member mounting system of the present invention travels along a rail provided below the first-order beam, and horizontally holds the outer wall member provided with the upper and lower joining jigs from the stockyard. A device for horizontal transportation, a positioning elevating device for mounting the transported outer wall member and raising the outer wall member to a predetermined angle, and traveling on a rail laid on the outer periphery of the top floor of the building, and raising it to a predetermined angle. And an outer wall lifting device for lifting the outer wall member by a wire in a vertical state, and the outer wall lifting device lifts the outer wall member to a mounting position of the outer wall, pulls the outer wall member toward the wall side, and drops it. Thus, the upper and lower joining jigs of the outer wall member are fitted and fixed to the mounting bracket of the upper girder and the upper joining jig of the lower floor outer wall member, respectively.

〔作用〕[Action]

本発明は、外壁部材にホイスト用、揚重用の被把持部
と、上側及び下側接合治具を予め設けておき、現場に外
壁部材を搬入後、搬送装置、揚重装置により所定の取付
け位置まで搬送・揚重し、外壁部材の上側接合治具、下
側接合治具をそれぞれ上階大梁の取付けブラケット、下
階外壁部材の上側接合治具に合わせる形で嵌め込み、固
定するようにしたので、無人で簡便、迅速に外壁部材の
取付けを行うことができ、省力化を達成し、安全性、作
業能率の向上を図ることができる。
According to the present invention, the outer wall member is provided with gripping parts for hoisting and hoisting and upper and lower joining jigs in advance, and after the outer wall member is carried into the site, a predetermined mounting position is set by the carrying device and the lifting device. Since it was transported and lifted up, the upper joint jig and the lower joint jig of the outer wall member were fitted and fixed in a manner to match the upper floor girder mounting bracket and the upper joint jig of the lower floor outer wall member, respectively. Thus, the outer wall member can be mounted easily and quickly unattended, labor saving can be achieved, and safety and work efficiency can be improved.

〔実施例〕〔Example〕

以下、実施例を図面を参照して説明する。 Hereinafter, embodiments will be described with reference to the drawings.

第1図は本発明の外壁部材取付けシステムの概要を説明
するための図である。図中、101は外壁揚重ロボット、1
03はレール、105はワイヤ、107は把持装置、109はホイ
ストロボット、111は走行レール、113は位置決め昇降装
置である。
FIG. 1 is a diagram for explaining the outline of the outer wall member mounting system of the present invention. In the figure, 101 is an outer wall lifting robot, 1
Reference numeral 03 is a rail, 105 is a wire, 107 is a gripping device, 109 is a hoist robot, 111 is a traveling rail, and 113 is a positioning lifting device.

本発明の外壁部材取付けシステムにおいては、鉄骨、大
梁、小梁等を組み立てた建物の最上階の周囲にレール10
3を敷設し、外壁揚重ロボット101が自由に走行できるよ
うにする。搬入されてきた外壁半PC板はストックヤード
に積み重ねられてあり、ホイストロボット109(詳細は
後述する)で水平にしたままの状態で持ち上げて水平搬
送し、位置決め昇降装置113に載せる。ここで外壁半PC
板に異常な力が作用して傷めることがないように位置決
め昇降装置113で所定角度まで起こし、外壁揚重ロボッ
ト101の把持装置107で外壁半PC板に設けられた吊りピー
スを掴んで垂直状態で吊り下げて所定位置へ揚重し、後
述するように壁側へ引き込み、落とし込むことにより嵌
合固定する。
In the outer wall member mounting system of the present invention, the rail 10 is provided around the top floor of a building in which steel frames, girders, girders, etc. are assembled.
3 is laid so that the outer wall lifting robot 101 can travel freely. The outer half-PC boards that have been carried in are stacked in a stock yard, and are hoisted by a hoist robot 109 (details will be described later) in a state where they are leveled and conveyed horizontally, and placed on a positioning lifting device 113. Outer wall half PC here
The positioning lifting device 113 raises it up to a predetermined angle so that it will not be damaged by an abnormal force acting on the plate, and the gripping device 107 of the outer wall lifting robot 101 grips the hanging piece provided on the outer half PC plate and holds it vertically. It is hung up and lifted to a predetermined position, and it is fitted and fixed by pulling it toward the wall and dropping it, as will be described later.

第2図は本発明のシステムにおいて使用される外壁半PC
板のファスナー部を示す図、第3図は本発明の外壁半PC
板のジョイント部を示す図である。図中、121は半PC
板、123、125は鉄筋、127は上側取りつけファスナー、1
27aはボルト、127bは固定ナット、127cはミゾ、129はレ
ベル調整ボルト、131は下側取りつけファスナー、131a
はミゾ、133は外周大梁、135は取りつけブラケット、13
5aはブラケット端部、135bはボルト、135cは固定ナット
である。
FIG. 2 shows an outer wall half PC used in the system of the present invention.
The figure which shows the fastener part of a board, FIG. 3 is the outer wall half PC of this invention.
It is a figure which shows the joint part of a board. In the figure, 121 is a half PC
Plates, 123 and 125 are reinforcing bars, 127 is an upper mounting fastener, 1
27a is a bolt, 127b is a fixing nut, 127c is a groove, 129 is a level adjustment bolt, 131 is a lower mounting fastener, 131a
Is a groove, 133 is a perimeter girder, 135 is a mounting bracket, 13
5a is a bracket end, 135b is a bolt, and 135c is a fixing nut.

第2図に示すように、本発明における外壁半PC板121に
は、上側取りつけファスナー(接合治具)127、下側取
りつけファスナー(接合治具)131が設けられ、上側取
りつけファスナー127にはボルト127a、固定ナット127
b、ミゾ127cが、また下側取りつけファスナー131にはミ
ゾ131aが設けられている。一方、第3図に示すように、
外壁半PC板121が取りつけられる外周大梁133からは取り
つけブラケット135が外側に張り出しており、その端部1
35aが垂直に立ち上がっていてその部分にボルト135b、
固定ナット135cが設けられ、ボルト135bに上側取りつけ
ファスナー127のミゾ127cが嵌合し、固定ナット135cで
外壁半PC板121が取りつけられる。さらに上階の外壁半P
C板の下側ファスナー131のミゾ131aを、下階の外壁半PC
板の上側取りつけファスナー127のボルト127aに嵌合さ
せ、固定ナット127bを締めることにより上下の外壁半PC
板を固定している。このとき、下階の外壁半PC板の頂部
に設けられたレベル調整ボルト129により上階の外壁半P
C板の位置調節を行うようにする。
As shown in FIG. 2, the outer wall half PC board 121 of the present invention is provided with an upper mounting fastener (joining jig) 127 and a lower mounting fastener (joining jig) 131, and the upper mounting fastener 127 is bolted. 127a, fixing nut 127
b, the groove 127c, and the lower mounting fastener 131 is provided with the groove 131a. On the other hand, as shown in FIG.
A mounting bracket 135 projects outward from the outer girder 133 to which the outer wall half PC plate 121 is mounted, and its end portion 1
35a is standing upright and bolt 135b on that part,
A fixing nut 135c is provided, the groove 127c of the upper attachment fastener 127 is fitted to the bolt 135b, and the outer wall half PC board 121 is attached by the fixing nut 135c. Outer wall half P on the upper floor
The bottom wall of the C plate, the fastener 131a, and the PC 131
Fit the bolt 127a of the fastener 127 on the upper side of the plate and tighten the fixing nut 127b to fix the upper and lower outer wall half PC
The board is fixed. At this time, the outer wall half P of the upper floor by the level adjustment bolt 129 provided on the top of the outer wall half PC board of the lower floor.
Adjust the position of the C plate.

次に本発明のシステムに用いられるホイストロボット、
位置決め装置について説明する。
Next, a hoist robot used in the system of the present invention,
The positioning device will be described.

第4図はホイストロボットを示す図、第5図は位置決め
装置を示す図、第6図は外壁半PC板の吊りピースを示す
図である。図中、109aは走行部、109bはホイスト部、10
9cは部材把持部、113aはベース部、113bは傾斜昇降部、
115は油圧ユニット、117はコントローラ、121aは開口
部、121bは外壁揚重ロボット用吊りピース、121cはホイ
ストロボット用吊りピース、121dはピン穴である。
FIG. 4 is a diagram showing a hoist robot, FIG. 5 is a diagram showing a positioning device, and FIG. 6 is a diagram showing a hanging piece of an outer wall half PC plate. In the figure, 109a is a traveling section, 109b is a hoist section, and 10
9c is a member gripping part, 113a is a base part, 113b is a tilting elevating part,
Reference numeral 115 is a hydraulic unit, 117 is a controller, 121a is an opening, 121b is an outer wall lifting robot suspension piece, 121c is a hoist robot suspension piece, and 121d is a pin hole.

ホイストロボット109は第4図に示すように、走行部109
a、ホイスト部109b、部材把持部109cからなり、一階小
梁下に敷設した走行レール111に沿ってモノレール方式
で走行する。そこで外壁半PC板121には第6図(a)に
示すように窓となる開口部121aの周囲に3つのホイスト
ロボット用吊りピース121c、端部に2つの外壁揚重ロボ
ット用吊りピース121bが設けられており、この吊りピー
スは第6図(b)に示すようにピン穴121dを有してい
る。そして、ホイストロボット109の部材把持部109cに
はこの3つの吊りピース121cに対応して3つのクランプ
部が設けられており、ピン穴にピンを通すことにより外
壁半PC板を水平な状態で把持するようになっている。
The hoist robot 109, as shown in FIG.
a, a hoist portion 109b, and a member gripping portion 109c, and travels in a monorail system along a traveling rail 111 laid under the first-girder beam. Therefore, as shown in FIG. 6 (a), the outer wall half-PC board 121 has three hoisting robot hanging pieces 121c around the opening 121a, which is a window, and two outer wall lifting robot hanging pieces 121b at the ends. This hanging piece has a pin hole 121d as shown in FIG. 6 (b). The member holding portion 109c of the hoist robot 109 is provided with three clamp portions corresponding to the three hanging pieces 121c, and the outer wall half PC plate is held in a horizontal state by inserting a pin into the pin hole. It is supposed to do.

このホイストロボット109で水平搬送された外壁半PC板
は一旦位置決め装置113上に載せられる。位置決め装置1
13は、第5図に示すようにベース部113a、傾斜昇降部11
3bからなり、油圧ユニット115、コントローラ117によっ
て傾斜昇降部113bの角度が調節できるようになってい
る。この装置は平らな状態で外壁半PC板を保持して揚重
したのでは外壁半PC板に異常な力が作用して傷める可能
性があるので、一旦半PC板を起こしておいてから吊り上
げるためのものである。こうして、外壁半PC板121を立
てた状態で外壁揚重ロボット101の把持装置107で吊りピ
ース121bを把持して所定位置まで揚重する。
The half-PC plate on the outer wall horizontally conveyed by the hoist robot 109 is once placed on the positioning device 113. Positioning device 1
As shown in FIG. 5, reference numeral 13 denotes a base portion 113a and an inclined lifting portion 11
3b, and the angle of the inclined elevating part 113b can be adjusted by the hydraulic unit 115 and the controller 117. If this equipment is held flat and lifted while holding the outer half PC board, abnormal force may act on the outer half PC board and damage it, so raise the half PC board and then lift it up. It is for. In this way, the lifting piece 121b is gripped by the gripping device 107 of the outer wall lifting robot 101 in a state where the outer wall half PC board 121 is erected and lifted to a predetermined position.

次に外壁揚重ロボットによる外壁の取付けについて詳細
に説明する。
Next, the mounting of the outer wall by the outer wall lifting robot will be described in detail.

第7図はロボットによる外壁半PC板取付概要を説明する
ための図、第8図は外壁揚重ロボットの概観を示す図で
ある。図中、101は外壁揚重ロボット、103はレール、10
5はワイヤ、107は部材把持装置、121は外壁半PC板、153
はドラム、155はシリンダ、157は走行モータ、159はタ
イミングベルト、161は走行用車輪、165は反力受け用車
輪、173、177は固定用ナット、175は上階大梁、179は下
階大梁を示す。
FIG. 7 is a diagram for explaining the outline of mounting the outer wall half-PC board by the robot, and FIG. 8 is a diagram showing an overview of the outer wall lifting robot. In the figure, 101 is an outer wall lifting robot, 103 is a rail, and 10
5 is a wire, 107 is a member gripping device, 121 is an outer wall half-PC board, 153
Is a drum, 155 is a cylinder, 157 is a running motor, 159 is a timing belt, 161 is a running wheel, 165 is a reaction force receiving wheel, 173 and 177 are fixing nuts, 175 is an upper girder, and 179 is a lower girder. Indicates.

第7図において、レール103は建物の最上階に敷設され
るものであり、外壁揚重ロボット101は、このレール103
上を走行用車輪161、反力受け用車輪165を使って走行す
るようにしたものである、走行モータ157はタイミング
ベルト159を介して走行用車輪161を駆動するものであ
る。ワイヤ105の先端には部材把持装置107が取付けら
れ、ドラム153でこのワイヤ105の巻き取り量を調節する
ことによって部材把持装置107による吊り下げ高さが調
節される。従って、外壁揚重ロボット101には、図示し
ないが走行モータ157の他ドラム153を回転させるための
モータも搭載されている。この外壁揚重ロボット101の
概観図を示したものが第8図である。
In FIG. 7, the rail 103 is laid on the top floor of the building, and the outer wall lifting robot 101 is
The traveling wheel 161 and the reaction force receiving wheel 165 are used to travel above. The traveling motor 157 drives the traveling wheel 161 via a timing belt 159. The member gripping device 107 is attached to the tip of the wire 105, and the hanging height of the member gripping device 107 is adjusted by adjusting the winding amount of the wire 105 by the drum 153. Therefore, the outer wall lifting robot 101 is also equipped with a motor (not shown) for rotating the drum 153 in addition to the traveling motor 157. FIG. 8 shows a schematic view of the outer wall lifting robot 101.

上記外壁揚重ロボット101による外壁半PC板の取付けを
行う場合には、まず第7図(a)に示すようにシリンダ
155を伸ばした状態でドラム153によりワイヤ105を巻き
取って外壁半PC板121を所定の高さまで揚重する。しか
る後、シリンダ155を縮小させて外壁半PC板121を建物側
面方向に引き込む。そして、ワイヤ105を伸ばして外壁
半PC板121を落とし込み、外壁半PC板121の上側ファスナ
ーのミゾ、下側ファスナーのミゾをそれぞれ上階大梁の
取付けブラケットのボルト、下階外壁半PC板上側ファス
ナーのボルトに合わせる形で嵌け込んで同図(b)に示
すように上階大梁175、下階大梁179の固定ナット173、1
77で締め付け固定する。
When mounting the outer wall half PC board by the outer wall lifting robot 101, first, as shown in FIG.
The wire 105 is wound up by the drum 153 with the unrolled 155, and the outer wall half PC board 121 is lifted to a predetermined height. After that, the cylinder 155 is contracted and the outer half PC board 121 is pulled in the lateral direction of the building. Then, the wire 105 is extended and the outer wall half PC board 121 is dropped, and the groove of the upper fastener of the outer wall half PC board 121 and the groove of the lower fastener are respectively the bolts of the mounting bracket of the upper girder, the lower wall outer half PC board of the upper floor. As shown in Fig. 2 (b), the fixing nuts 173, 1 for the upper girder 175 and the lower girder 179 are fitted to fit the bolts of
Tighten and fix with 77.

第9図は本システムに用いる部材の水平引き込み装置の
他の例を説明するための図であり、103はレール、105は
ワイヤ、181はガイドレール、183はドラム、185はシリ
ンダ、161は走行用車輪、193はベルト、165は反力受け
用車輪、197はベース、201はコントローラ、203はエン
コーダ、205、211、213はモータ、207はガイド、209は
垂直距離測定用ワイヤを示す。
FIG. 9 is a diagram for explaining another example of the horizontal retracting device for the members used in the present system. 103 is a rail, 105 is a wire, 181 is a guide rail, 183 is a drum, 185 is a cylinder, and 161 is a traveling line. Wheels, 193 is a belt, 165 is a reaction force receiving wheel, 197 is a base, 201 is a controller, 203 is an encoder, 205, 211, 213 are motors, 207 is a guide, and 209 is a vertical distance measuring wire.

第9図において、ガイドレール181はシリンダ185の先端
をガイドし、シリンダ185を縮めた場合に揚重部材の高
さが変動しない軌跡を描くようにしたものである。その
ためには、シリンダ185を縮めたとき、その先端がドラ
ム183からベース197のレベルまでのワイヤ105の長さが
一定になるように軌跡を描かせることである。この軌跡
は、同図(b)に示すようにドラム183の位置における
座標を(0,0)、シリンダ185の先端の座標を(x,y)、
シリンダが水平になった時のワイヤ長さをa、シリンダ
が水平になった時のワイヤとシリンダとのなす過度をθ
とすると、ワイヤ105の長さを植えずに部材を水平移動
するシリンダ185の先端のx,y軌跡は、 となる。上記の式で得られる軌跡上をシリンダ先端が移
動するようにガイドレールを設置すると、シリンダ185
およびガイドを上下方向に回転可能に支持することによ
り、シリンダを引き込むだけでワイヤを巻取らずに部材
を水平に移動させ、引き込むことができる。
In FIG. 9, the guide rail 181 guides the tip of the cylinder 185 so that the height of the lifting member does not change when the cylinder 185 is contracted. For that purpose, when the cylinder 185 is contracted, the tip of the cylinder 185 is traced so that the length of the wire 105 from the drum 183 to the level of the base 197 becomes constant. This locus has coordinates (0,0) at the position of the drum 183, coordinates (x, y) at the tip of the cylinder 185, as shown in FIG.
The wire length when the cylinder is horizontal is a, and the excess between the wire and the cylinder when the cylinder is horizontal is θ.
Then, the x, y locus of the tip of the cylinder 185 that horizontally moves the member without planting the length of the wire 105 is Becomes If the guide rail is installed so that the cylinder tip moves along the locus obtained by the above formula, the cylinder 185
By supporting the guide so as to be rotatable in the vertical direction, the member can be horizontally moved and retracted only by retracting the cylinder without winding the wire.

このガイドレール181の取り付け位置の例を平面図で示
したのが第9図(c)である。図において、走行用モー
タ213はタイミングベルト193を介して走行用車輪189を
駆動するものであり、エンコーダ203は走行用車輪189の
回転速度、すなわち部材水平引き込み装置の走行速度を
検出するものである。荷吊り用ワイヤ105は2本あっ
て、荷吊り用ワイヤ巻き取りドラム183によって巻き取
られ、その巻き取りを制御するのがモータ211である。
垂直距離測定用ワイヤ209は荷吊り用ワイヤ105の巻き取
り制御に追従してモータ205により巻き取り制御される
ものであり、この繰出し長さから部材の高さを測定す
る。シリンダ185は部材を吊り上げる時は伸長し、引き
込む時に縮小する。ガイド207はこの伸縮の際に2本の
荷吊り用ワイヤ105に対して一方の引き込み距離が大き
くなったりすることなく、等しく作用させるものであ
り、このガイド207と垂直距離測定用ワイヤ209との間に
ガイドレール181を設けている。
FIG. 9C shows an example of the mounting position of the guide rail 181 in a plan view. In the figure, a traveling motor 213 drives a traveling wheel 189 via a timing belt 193, and an encoder 203 detects a rotational speed of the traveling wheel 189, that is, a traveling speed of a member horizontal retracting device. . There are two load-hanging wires 105, which are wound up by the load-hanging wire winding drum 183, and the motor 211 controls the winding.
The vertical distance measuring wire 209 is controlled by the motor 205 in accordance with the winding control of the load hanging wire 105, and the height of the member is measured from this feeding length. The cylinder 185 extends when the member is lifted and contracts when the member is retracted. The guide 207 acts equally on the two wire-hanging wires 105 at the time of this expansion and contraction without increasing the pull-in distance of one of them, and the guide 207 and the vertical distance measuring wire 209. A guide rail 181 is provided between them.

そして、部材を揚重し引き込む場合には、まずシリンダ
185を図示左方点線の位置まで伸長させ水平状態で荷吊
り用ワイヤ105の先端に取付けられた把持装置で部材を
把持し、モータ211を回転させ部材を所定の高さになる
まで吊り揚げる。垂直距離測定用ワイヤ209によって所
定の高さまで揚重されたと確認されると、モータ211を
停止させ、次にシリンダ185を縮小させる。シリンダ185
が縮小すると、先の説明したようにシリンダ185の先端
が上の方の所定の軌跡を描き、シリンダ185の縮小長さ
に対応して先端が上がるので、部材の高さが一定に保た
れたまま引き込まれる。
Then, when lifting and retracting the member, first
185 is extended to the position of the dotted line on the left side in the drawing, and in a horizontal state, the member is gripped by a gripping device attached to the tip of the wire for wire lifting 105, and the motor 211 is rotated to lift the member to a predetermined height. When it is confirmed that the wire has been lifted to a predetermined height by the vertical distance measuring wire 209, the motor 211 is stopped and then the cylinder 185 is contracted. Cylinder 185
As described above, the tip of the cylinder 185 draws a predetermined upward trajectory as described above, and the tip rises according to the reduced length of the cylinder 185, so that the height of the member was kept constant. I am drawn in.

第10図は外壁半PC板の搬送、揚重を説明するための図
で、同図(a)は平面図、同図(b)は側面図である。
図中、第1図と同一番号は同一内容を示す。なお、113a
〜dは位置決め昇降装置、241はストックヤードであ
る。
FIG. 10 is a view for explaining the transportation and lifting of the outer wall half-PC board, FIG. 10 (a) is a plan view, and FIG. 10 (b) is a side view.
In the figure, the same numbers as in FIG. 1 indicate the same contents. Note that 113a
˜d is a positioning lifting device, and 241 is a stockyard.

図において、1階小梁下に敷設された走行レール111に
沿ってホイストロボット109が走行し、ストックヤード2
41に積み重ねられた外壁半PC板を水平状態のまま把持し
て位置決め昇降装置113a〜dのいずれかまで搬送する。
搬送された外壁半PC板は位置決め昇降装置に載せられて
前述したように所定角度まで起こされる。次に外壁揚重
ロボット101の部材把持装置107で外壁半PC板を把持して
垂直状態で吊って揚重する。外壁揚重ロボット101は
梁、小梁等を組みたてた建物の最上階の外周に敷設され
たレールに沿って自由に走行でき、所定取付け位置へ外
壁半PC板を揚重し、前述したように外壁半PC板を壁側へ
引き込み、落とし込むことにより外壁半PC板の接合治具
を大梁、下階の外壁半PC板の接合治具に嵌合固定する。
In the figure, the hoist robot 109 travels along the traveling rail 111 laid under the beam on the first floor,
The outer half PC boards stacked on 41 are held in a horizontal state and conveyed to any of the positioning elevating devices 113a to 113d.
The conveyed outer wall half PC plate is placed on the positioning elevating device and raised up to a predetermined angle as described above. Next, the outer wall half-PC board is gripped by the member gripping device 107 of the outer wall lifting robot 101, and is hung in a vertical state and lifted. The outer wall lifting robot 101 can freely travel along a rail laid on the outer periphery of the top floor of a building with beams, beamlets, etc., and lifts the outer wall half PC plate to a predetermined mounting position, as described above. In this way, the outer wall half-PC board is pulled toward the wall side and dropped to fit and fix the joining jig for the outer-wall half-PC board to the girder and the joining jig for the outer-wall half-PC board on the lower floor.

〔発明の効果〕 以上のように本発明によれば、外壁部材にホイスト用の
揚重用の被把持部と、上側及び下側接合治具を予め設け
ておき、搬送装置、揚重装置を用いて搬送・揚重し、外
壁部材の上側接合治具、下側接合治具により上階大梁、
下階外壁部材の上側接合治具に嵌合固定するようにした
ので、無人で簡便、迅速に外壁部材の取付けを行うこと
ができ、省力化を達成し、安全性、作業能率の向上を図
ることができる。
[Advantages of the Invention] As described above, according to the present invention, the gripping portion for hoisting for hoisting and the upper and lower joining jigs are provided in advance on the outer wall member, and the carrying device and the hoisting device are used. Transporting and hoisting, and using the upper joint jig and the lower joint jig for the outer wall members,
Since the outer wall member on the lower floor is fitted and fixed to the upper joining jig, the outer wall member can be easily and quickly installed unattended, which saves labor and improves safety and work efficiency. be able to.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明の外壁部材取付けシステムの概要を説明
するための図、第2図は本発明のシステムにおいて使用
される外壁半PC板のファスナー部を示す図、第3図は本
発明の外壁半PC板のジョイント部を示す図、第4図はホ
イストロボットを示す図、第5図は位置決め装置を示す
図、第6図は外壁半PC板の吊りピースを示す図、第7図
はロボットによる外壁半PC板取付概要を説明するための
図、第8図は外壁揚重ロボットの概観を示す図、第9図
は本システムに用いる部材の水平引き込み装置の他の例
を説明するための図、第10図は外壁半PC板の搬送、揚重
を説明するための図である。 101……外壁揚重ロボット、103……レール、105……ワ
イヤ、107……把持装置、109……ホイストロボット、11
1……走行レール、113……位置決め昇降装置、121……
外壁半PC板、127……上側取りつけファスナー、131……
下側取りつけファスナー、133……外周大梁、135……取
りつけブラケット。
FIG. 1 is a diagram for explaining an outline of an outer wall member mounting system of the present invention, FIG. 2 is a diagram showing a fastener portion of an outer wall half-PC board used in the system of the present invention, and FIG. 3 is a diagram of the present invention. The figure which shows the joint part of outer wall half PC board, FIG. 4 is a figure which shows a hoist robot, FIG. 5 is a figure which shows a positioning device, FIG. 6 is a figure which shows the hanging piece of outer wall half PC board, FIG. 7 is Fig. 8 is a diagram for explaining the outline of mounting the outer wall half-PC board by the robot, Fig. 8 is a diagram showing an overview of the outer wall lifting robot, and Fig. 9 is another example of the horizontal retracting device for the members used in this system. FIG. 10 and FIG. 10 are views for explaining the transportation and lifting of the outer wall half-PC board. 101 …… Outer wall lifting robot, 103 …… Rail, 105 …… Wire, 107 …… Gripping device, 109 …… Hoist robot, 11
1 …… Traffic rail, 113 …… Positioning and lifting device, 121 ……
Outer wall half PC board, 127 …… Upper side mounting fastener, 131 ……
Lower mounting fastener, 133 …… Outer beam, 135 …… Mounting bracket.

───────────────────────────────────────────────────── フロントページの続き (71)出願人 999999999 佐藤工業株式会社 富山県富山市桜木町1番11号 (71)出願人 999999999 清水建設株式会社 東京都中央区京橋2丁目16番1号 (71)出願人 999999999 大成建設株式会社 東京都新宿区西新宿1丁目25番1号 (71)出願人 999999999 株式会社竹中工務店 大阪府大阪市中央区本町4丁目1番13号 (71)出願人 999999999 戸田建設株式会社 東京都中央区京橋1丁目7番1号 (71)出願人 999999999 株式会社フジタ 東京都渋谷区千駄ヶ谷4丁目6番15号 (71)出願人 999999999 株式会社小松製作所 東京都港区赤坂2丁目3番6号 (71)出願人 999999999 日立造船株式会社 大阪府大阪市西区江戸堀1丁目6番14号 (72)発明者 長谷川 幸男 東京都新宿区大久保3―4―1 早稲田大 学システム科学研究所内 (72)発明者 中村 俊男 東京都千代田区内神田1―15―11 久保田 ビル6F (72)発明者 宮嶋 俊和 東京都調布市飛田給2―19―1 (72)発明者 松下 祐輔 東京都新宿区築地町16 ライオンズマンシ ョン102号 (72)発明者 山下 伸二 神奈川県厚木市三田47―3 (72)発明者 奥山 信博 東京都港区芝浦4―15―33 芝浦清水ビル 4F (72)発明者 西村 正宏 東京都新宿区西新宿1―25―1 (72)発明者 星野 春夫 東京都江東区南砂2―5―14 株式会社竹 中工務店技術研究所内 (72)発明者 篠崎 徹 東京都中央区京橋1―3―3 柏原ビル5 階 (72)発明者 吉武 亮二 東京都渋谷区千駄ケ谷4―6―15 (72)発明者 浅野 寛 神奈川県平塚市万田1200 (72)発明者 寺尾 雅之 大阪府大阪市西区江戸堀1丁目6番14号 日立造船株式会社内 (56)参考文献 特開 平1−105870(JP,A) 特開 昭64−17970(JP,A) 実公 昭52−17957(JP,Y2) ─────────────────────────────────────────────────── ─── Continuation of the front page (71) Applicant 999999999 Sato Industry Co., Ltd. 1-11 Sakuragicho, Toyama City, Toyama Prefecture (71) Applicant 999999999 Shimizu Corporation 2-16-1 Kyobashi, Chuo-ku, Tokyo (71) ) Applicant 999999999 1-25-1, Nishishinjuku, Shinjuku-ku, Tokyo (71) Applicant 999999999 Takenaka Corporation 4-1-1-13, Honmachi, Chuo-ku, Osaka-shi, Osaka (71) Applicant 999999999 Toda Construction Co., Ltd. 1-7-1, Kyobashi, Chuo-ku, Tokyo (71) Applicant 999999999 Fujita Co., Ltd. 4-6-1, Sendagaya, Shibuya-ku, Tokyo (71) Applicant 999999999 Komatsu Ltd. Akasaka, Minato-ku, Tokyo 2-3-6 (71) Applicant 999999999 Hitachi Zosen Corporation 1-6-14 Edobori, Nishi-ku, Osaka-shi, Osaka (72) Inventor Yukio Hasegawa 3-4-1 Okubo, Shinjuku-ku, Kyoto, within Waseda University Institute of Systems Science (72) Inventor Toshio Nakamura 1-15-11, Kanda, Chiyoda-ku, Tokyo 6F Kubota Building (72) Inventor Toshikazu Miyajima Tobita, Chofu-shi, Tokyo 2 ―19― (72) Inventor Yusuke Matsushita No. 102 Lions Mansion, 16 Tsukiji-cho, Shinjuku-ku, Tokyo (72) Inventor Shinji Yamashita 47-3 Mita, Atsugi, Kanagawa Prefecture (72) Nobuhiro Okuyama Minato-ku, Tokyo 4-15-33 Shibaura Shibaura Shimizu Building 4F (72) Inventor Masahiro Nishimura 1-25-1, Nishishinjuku, Shinjuku-ku, Tokyo (72) Inventor Haruo Hoshino 2-5-14 Minamisuna, Koto-ku, Tokyo Takenaka Corporation (72) Inventor Toru Shinozaki Toru Shinozaki 1-3-3 Kyobashi, Chuo-ku, Tokyo Kashihara Building 5th floor (72) Inventor Ryoji Yoshitake 4-6-15 Sendagaya, Shibuya-ku, Tokyo (72) Inventor Hiroshi Asano Kanagawa 1200 Manda, Hiratsuka-shi, Japan (72) Inventor Masayuki Terao 1-6-14 Edobori, Nishi-ku, Osaka City, Osaka Prefecture Hitachi Zosen Corporation Within the company (56) Reference Patent flat 1-105870 (JP, A) JP Akira 64-17970 (JP, A) the actual public Akira 52-17957 (JP, Y2)

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】1階小梁下に設けられたレールに沿って走
行し、上側及び下側接合治具が設けられた外壁部材を水
平状態で把持してストックヤードから水平搬送する搬送
用装置と、搬送された外壁部材が載置され、外壁部材を
所定角度まで起こす位置決め昇降装置と、建物最上階の
外周部に敷設されたレール上を走行し、所定角度まで起
こされた外壁部材を把持して垂直状態でワイヤにより揚
重する外壁揚重装置とを備え、外壁揚重装置は外壁部材
を外壁の取りつけ位置まで揚重し、外壁部材を壁側に引
き込んで落とし込むことにより、外壁部材の上側、下側
接合治具をそれぞれ上階大梁の取付けブラケット、下階
外壁部材の上側接合治具に嵌合させ、固定することを特
徴とする外壁部材取付けシステム。
1. A transfer device that travels along a rail provided under a beam on the first floor and horizontally holds an outer wall member provided with upper and lower joining jigs and horizontally transfers the stock member from a stockyard. The transported outer wall member is placed on the rail, and the positioning and elevating device that raises the outer wall member to a predetermined angle and the rail that is laid on the outer periphery of the top floor of the building are run to grip the outer wall member raised to the predetermined angle. And an outer wall lifting device that vertically lifts with a wire, and the outer wall lifting device lifts the outer wall member to a mounting position of the outer wall, pulls the outer wall member toward the wall side, and drops the outer wall member. An outer wall member mounting system, characterized in that the upper and lower joining jigs are fitted and fixed to a mounting bracket for an upper girder and an upper joining jig for a lower floor outer wall member, respectively.
【請求項2】外壁部材は半PC板であり、水平搬送用の複
数の吊りピースと、揚重用の複数の吊りピースとを有し
ている請求項1記載の外壁部材取付けシステム。
2. The outer wall member mounting system according to claim 1, wherein the outer wall member is a half-PC board, and has a plurality of hanging pieces for horizontal conveyance and a plurality of hanging pieces for lifting.
JP14066889A 1989-06-02 1989-06-02 External wall member mounting system Expired - Fee Related JPH07116844B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14066889A JPH07116844B2 (en) 1989-06-02 1989-06-02 External wall member mounting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14066889A JPH07116844B2 (en) 1989-06-02 1989-06-02 External wall member mounting system

Publications (2)

Publication Number Publication Date
JPH035573A JPH035573A (en) 1991-01-11
JPH07116844B2 true JPH07116844B2 (en) 1995-12-18

Family

ID=15273985

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14066889A Expired - Fee Related JPH07116844B2 (en) 1989-06-02 1989-06-02 External wall member mounting system

Country Status (1)

Country Link
JP (1) JPH07116844B2 (en)

Also Published As

Publication number Publication date
JPH035573A (en) 1991-01-11

Similar Documents

Publication Publication Date Title
CN112239116B (en) Method and device for elevator guide rail installation
JP2587684B2 (en) Construction wall construction equipment
JP3034960B2 (en) Equipment installed in hoistway
JP2753203B2 (en) Long material lifting equipment
JPH07116844B2 (en) External wall member mounting system
JPH08245116A (en) Elevator installation method
CN112031370A (en) Ceiling installation equipment and construction method thereof
JPH05113026A (en) Temporary scaffold structure
CN117185155A (en) Steel structure roof truss hoisting device and use method
JPH0812262A (en) Installation method and equipment for overhead crane
JP3037759B2 (en) Method and apparatus for working in elevator shaft
CN110002345A (en) Based on the assembled architecture automation hoisting platform from jacking steel platform
JPH05330758A (en) Elevator guide rail installation work support device and guide rail installation work method
JPH07113244B2 (en) Outer wall half PC board and its mounting method
JPH0734069Y2 (en) Lifting device for car or counterweight in elevator
CN223705005U (en) Tower crane wall-attached avoiding assembly
JPH09100629A (en) Beam member attachment device and beam member attachment method
JP3029500B2 (en) All-weather building automatic construction method
RU2759162C1 (en) Method for automated installation of external fence for gravitational energy storage and system for its implementation
CN219297040U (en) Portable semi-automatic device for installing and transporting pier hanging fence
JP2761518B2 (en) Construction method of building
JPH0826664B2 (en) Pillar assembly method using a robot
JPH10238123A (en) Apparatus and method for transporting and mounting a building outer wall
JPH05270764A (en) Elevator rail lifting device
CN119860100A (en) Intelligent construction platform and construction method for assembled residential engineering construction

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees