JPH0718160B2 - How to build an earth anchor on a steep slope - Google Patents
How to build an earth anchor on a steep slopeInfo
- Publication number
- JPH0718160B2 JPH0718160B2 JP63246600A JP24660088A JPH0718160B2 JP H0718160 B2 JPH0718160 B2 JP H0718160B2 JP 63246600 A JP63246600 A JP 63246600A JP 24660088 A JP24660088 A JP 24660088A JP H0718160 B2 JPH0718160 B2 JP H0718160B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- anchor
- steep slope
- ground
- tube
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は急傾斜地崩壊を防止する地下水排除機能を備え
たアースアンカー構築工法に関する。DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention relates to a construction method for constructing an earth anchor having a groundwater removing function for preventing collapse of a steep slope.
急傾斜地は第8図に示すように硬い層からなる不動地盤
10とその上の透水層からなる崩壊土塊11からなっている
ので、多量の降雨があると、雨水の浸透による斜面土塊
の重量増、地盤強度の低下、浅層地下水位の上昇、集中
豪雨による多量の滞留水等が原因して崩壊が生じる。The steep slope is an immovable ground consisting of hard layers as shown in Fig. 8.
Since it consists of 10 and the collapsed mass 11 composed of the permeable layer above it, if there is a large amount of rainfall, the weight of the slope mass increases due to the infiltration of rainwater, the ground strength decreases, the shallow groundwater level rises, and heavy rainfall causes heavy rain. Collapse occurs due to a large amount of accumulated water.
図において、矢印は水の移動状態を示すもので12は降水
を、13は蒸発を、14は中間流出を、15は浸透を、16は地
下流出、17は表面流出を示す。In the figure, the arrows indicate the movement of water. 12 is precipitation, 13 is evaporation, 14 is intermediate runoff, 15 is infiltration, 16 is underground runoff, and 17 is surface runoff.
この急傾斜地崩壊を防止する為、従来から種々の方法が
あり、大別すると抑止工法としての杭工、アンカー工、
擁壁工、そして抑制工としての法面保護工、地表面水排
除工、地下水排除工があるが、急斜面地の崩壊の原因
は、降雨にあるといっても良く、従って、急傾斜地崩壊
防止方法としては、地表面水排除工、地下水排除工の抑
制工だけでも充分な効果を期待できるものである。In order to prevent this steep landslide, there have been various methods from the past, roughly classified as pile construction, anchor construction, and
There are retaining wall works, slope protection works as restraint works, surface water drainage works, and groundwater drainage works, but it can be said that the cause of collapse of steep slopes is rain, so prevention of steep slope collapse As a method, sufficient suppression of ground surface drainage and groundwater drainage can be expected.
しかしながら、大体においてこの種の工事が行われるの
は、斜面崩壊が起こった後もしくは道路幅拡張工事等で
斜面成形し邪魔になる末端土塊の除去が行われた時であ
り、まず、この斜面を安定させる為の抑止工(杭工、ア
ンカー工、擁壁工)が選択されて、次いで今後の崩壊の
原因を除くための抑制工(法面保護工、地表面水排除
工、地下水排除工)が選択されるのが通常である。However, this kind of work is generally done after the slope collapse or when the road surface expansion work etc. was performed to remove the end clods that would interfere with the slope formation. Suppression works (pile work, anchor work, retaining wall work) are selected to stabilize, and then suppression works (slope protection work, surface water drainage work, groundwater drainage work) to remove the cause of future collapse. Is usually selected.
このところ急傾斜地崩壊防止工法として、その採用が目
立つものはアースアンカーがあり、第9図に締付けアー
スアンカー20の施工図を示しており、崩壊土塊11を不動
地盤10に締付けて斜面全体にアンカー20aを配置する必
要がある。As a construction method for preventing steep landslides, the ground anchor is the most widely adopted method, and Fig. 9 shows the construction drawing of the tightening earth anchor 20. The collapsed earth mass 11 is tightened on the immovable ground 10 to anchor the entire slope. 20a need to be placed.
ところが、前記締付けアンカー20においては、設計アン
カー力に等しいプレストレスをかけるのであるが、プレ
ストレスが長期にわたって一定でなく時間と共に減少す
るので、再緊張の必要があり、更には軟地盤で一度に全
プレストレスを加えると周辺地盤の破壊をもたらすとい
う問題点があり、更には支圧体20bが斜面20c全体を覆う
ことになり緑化上支障がある。However, in the tightening anchor 20, a pre-stress equal to the design anchor force is applied, but since the pre-stress is not constant over a long period of time and decreases with time, it is necessary to re-tension, and further, at a time on soft ground. If all prestresses are applied, there is a problem that the surrounding ground will be destroyed, and furthermore, the bearing member 20b covers the entire slope 20c, which is an obstacle to greening.
一方、斜面に対し略水平にアースアンカーを配置する引
き止めアンカーにはこのような問題点はないが、何れの
工法を採用しても今後の崩壊を防止するため抑制工を行
う必要があり、この為、地下水排除工として横ボーリン
グによって設けた孔に40mm〜50mmの排水管を挿入し集排
水する方法が採られている。On the other hand, there are no such problems with the detent anchor that arranges the earth anchor almost horizontally to the slope, but it is necessary to carry out restraint work to prevent future collapse regardless of which construction method is adopted. Therefore, as a groundwater drainage work, a method of inserting and draining a 40 mm to 50 mm drain pipe into the hole provided by horizontal boring is used.
前記工法において、排水管の口径を大きくして集水能力
を高めるとか、集水孔の形状を改良して目詰まりし難く
するとか改善すべきことはあるのだが、横ボーリングに
よる地下水排除工は地中に施工されるので目立たないこ
と、施工しても予定通り排水があるのか無いのか分から
ないし、例え排水があってもどれほどの効果があるかは
っきりと数字で表し難く、工事費との係わりを考えた場
合に積極的に改善しようということには成り難いという
問題点があった。In the above method, there are things that should be improved, such as increasing the diameter of the drainage pipe to increase the water collection capacity, or improving the shape of the water collection hole to make it less likely to become clogged, but groundwater drainage work by horizontal boring Since it is constructed underground, it is not conspicuous.I do not know whether there is drainage as planned even if it is constructed, and it is difficult to express clearly how much effect there is even with drainage, and it is related to the construction cost There is a problem that it is difficult to proactively improve when considering.
本発明はこのような事情に鑑みてなされたもので、従来
の引き止めアンカー工法を改善し、工事費が低廉、法面
緑化も可能で、しかも効率的に降雨による急傾斜地崩壊
を防止するアースアンカー構築方法を提供することを目
的とする。The present invention has been made in view of such circumstances, and is an earth anchor that improves the conventional retaining anchor construction method, has a low construction cost, enables slope greening, and efficiently prevents collapse of steep slopes due to rainfall. The purpose is to provide a construction method.
前記目的に沿う請求項1記載の急傾斜地のアースアンカ
ー構築方法は、急傾斜地に対し略水平に施工される引き
止めアンカーの引張部に相当する部分に、外管と該外管
の内側に配置される内管とからなる排水管を配置する急
傾斜地のアースアンカー構築方法であって、前記外管及
び内管の先端部に、該外管と内管との隙間にその元部が
装着された刃先を設けると共に、前記引張部の奥側に位
置する前記外管に適当箇所に集水孔が形成された有孔管
を用い、前記引張部の手前側に位置する前記外管に無孔
管を用いて、透水層を流れる地下水を前記集水孔から外
管と内管の間に導き排除するようにして構成されてい
る。The method for constructing a ground anchor for a steep slope according to the above object is the outer pipe and the inside of the outer pipe at a portion corresponding to a tensile portion of a retaining anchor that is constructed substantially horizontally with respect to the steep slope. A method of constructing a ground anchor for a steep slope, in which a drainage pipe composed of an inner pipe and an inner pipe is arranged, the base portion of which is attached to a tip portion of the outer pipe and the inner pipe in a gap between the outer pipe and the inner pipe. A perforated tube having a water collecting hole formed at an appropriate position is provided on the outer tube located on the inner side of the tension section while providing a blade tip, and a non-perforated tube is provided on the outer tube located on the front side of the tension section. Is used to guide and remove groundwater flowing through the permeable layer from the water collection hole between the outer pipe and the inner pipe.
また、請求項2記載の急傾斜地のアースアンカー構築方
法は、請求項1記載の構築方法において、外管は合成樹
脂管からなって、内管及び該内管の先端部に取付けられ
る刃先は鉄製であるようにして構成されている。Further, the ground anchor construction method for steep slopes according to claim 2 is the construction method according to claim 1, wherein the outer pipe is made of a synthetic resin pipe, and the inner pipe and the cutting edge attached to the tip of the inner pipe are made of iron. It is configured as follows.
請求項1、2記載の急傾斜地のアースアンカー構築方法
においては、アンカーの引張部に外管と内管からなる排
水管を使用し、更に前記引張部の奥側に位置する外管に
集水孔が形成された有孔管を用い、前記引張部の手前側
に位置する外管に無孔管を用いているので、これによっ
て崩壊土塊である透水層及び滑り面を流れる地下水を効
率的に集水して、更に挿入口付近の地盤(即ち、表面
層)の軟弱化を防ぐ。In the method of constructing a ground anchor for a steep slope according to claim 1 or 2, a drain pipe composed of an outer pipe and an inner pipe is used for a tension part of the anchor, and water is collected in an outer pipe located on the back side of the tension part. Since a perforated pipe with holes is used and a non-perforated pipe is used for the outer pipe located on the front side of the tensile part, this effectively causes the groundwater flowing through the permeable layer and sliding surface, which are collapsed soil blocks, to flow. Water is collected to prevent softening of the ground (that is, the surface layer) near the insertion port.
そして、前記外管と内管の先端部にはその隙間を閉塞す
る刃先を設けているので、排水管を打ち込むことができ
ると共に、外管と内管の先端部を該刃先が閉塞し、有孔
管によって集めた水はアンカー体及びその周囲への積極
的な浸水を生じてアンカー本来の機能を害することがな
い。Further, since the tip ends of the outer pipe and the inner pipe are provided with blade tips for closing the gap, a drainage pipe can be driven and the tip ends of the outer pipe and the inner pipe are closed by the blade tips. The water collected by the perforated tube does not impair the original function of the anchor by actively infiltrating the anchor body and its surroundings.
また、これらの工事は引き止めアンカーを施工する際に
同時に行われるので、余分のボーリングを施す必要がな
い。Further, since these works are performed at the same time when the detent anchor is installed, it is not necessary to provide extra boring.
続いて、添付した図面を参照しつつ、本発明を具体化し
た急傾斜地のアースアンカー構築方法の一実施例につい
て詳しく説明し、本発明の理解に供する。Next, an embodiment of a method for constructing a ground anchor for a steep slope embodying the present invention will be described in detail with reference to the accompanying drawings, for the understanding of the present invention.
まず、本発明の実施例に係る急傾斜地のアースアンカー
構築方法の施工手順を第2図を参照しながら説明する
と、第2図(A)に示すようにアースアンカー構築には
ケーシングパイプを2段階に分けて使用し、アンカーの
引張部22に相当するところはアンカー体23の直径より内
径が大きなケーシングパイプ24を使用してボーリングを
行なう。該引張部22のボーリングが終わってもケーシン
グパイプ24はそのまま置いて、その中を別のケーシング
パイプ25を通してアンカー体23の部分のボーリングを行
い、ケーシングパイプ25はそのままの状態で、引張材26
を挿入した後第2図(B)に示すようにケーシングパイ
プ24、25を引抜く。First, the construction procedure of the method for constructing a ground anchor on a steep slope according to the embodiment of the present invention will be described with reference to FIG. 2. As shown in FIG. Boring is performed by using a casing pipe 24 whose inner diameter is larger than the diameter of the anchor body 23 at a portion corresponding to the tension portion 22 of the anchor. Even after the boring of the pulling portion 22 is finished, the casing pipe 24 is left as it is, and the portion of the anchor body 23 is bored through another casing pipe 25, and the casing pipe 25 is left as it is and the tension member 26
After inserting, the casing pipes 24 and 25 are pulled out as shown in FIG. 2 (B).
この後、引張部22の部分に二重構造をした排水管27を第
2図(C)のように押し込む。排水管27の外径はケーシ
ングパイプ24の外径より少し小さいが、入り難い場合に
は打ち込むことができる。次に、アンカー体23の部分に
セメントかモルタル(以下、グラウト23aという)を注
入し、終われば引続き引張部22に第2図(D)のように
グラウト23aを注入して終了する。なお、ここで第3図
に示すようにアンカー体23の部分に布袋(布パッカーと
もいう)23bを配置、グラウト23aを該布袋23bに注入し
て膨らませ、しかる後に先部のアンカー体にグラウト23
aを注入することによって加圧注入が可能とすることも
自由である。After that, the drain pipe 27 having a double structure is pushed into the pulling portion 22 as shown in FIG. 2 (C). The outer diameter of the drain pipe 27 is slightly smaller than the outer diameter of the casing pipe 24, but can be driven in if it is difficult to enter. Next, cement or mortar (hereinafter referred to as grout 23a) is injected into the anchor body 23, and when finished, the grout 23a is continuously injected into the tension portion 22 as shown in FIG. Here, as shown in FIG. 3, a cloth bag (also referred to as a cloth packer) 23b is arranged on the anchor body 23, and the grout 23a is injected into the cloth bag 23b to inflate it, and then the grout 23 is attached to the anchor body at the tip.
It is also free to enable pressure injection by injecting a.
前記排水管27の先は第3図に示すように不動地盤28に1
〜2m入るようにする。そして、該排水管27の先の方、即
ち奥側に第6図に示すように外管に多数の細長状の集水
孔29が形成された有孔管30を配し、手前の方には無孔管
31を配して、該排水管27からの漏水による浸透水のため
の孔口付近の地盤の軟弱化を防ぐ。ここで、該アースア
ンカーは水平より幾分下向きに構築するが、もし水平か
上向きにした場合、アンカー体23に注入したグラウトが
流出、収縮すればアンカー体23に空洞が生じることにな
るからである。これによって水平より幾分下向きに設置
されるが地下水にはかなりの水頭差があるため充分に排
水することができる。なお、ここで集水孔29は細長状と
して集水面積を拡大しているが、本発明はこの形状に限
定されず例えば円孔、各孔、網状孔であっても良い。The end of the drain pipe 27 is attached to the immovable ground 28 as shown in FIG.
Try to enter ~ 2m. Then, a perforated pipe 30 having a large number of elongated water collecting holes 29 formed in the outer pipe as shown in FIG. 6 is arranged on the front side of the drain pipe 27, that is, on the rear side, and the front pipe is arranged on the front side. Is a non-perforated tube
31 is provided to prevent weakening of the ground near the hole for permeated water due to water leakage from the drain pipe 27. Here, the earth anchor is constructed somewhat downward from the horizontal, but if it is horizontal or upward, the grout injected into the anchor body 23 will flow out, and if it contracts, a cavity will be created in the anchor body 23. is there. As a result, it is installed slightly downward from the horizontal, but the groundwater has a considerable head difference, so it can be sufficiently drained. Here, the water collecting holes 29 are elongated so as to expand the water collecting area, but the present invention is not limited to this shape, and may be circular holes, each hole, or mesh holes, for example.
前記排水管27を二重にした理由は、仮に一重にした場合
を考えてみると水を流す部分は排水管と引張材を覆った
シース管との間ということになり、幾分傾斜することに
よって貯水される水がアンカー体周辺に浸透しアンカー
本来の機能に支障をきたすことになる。The reason why the drainage pipe 27 is doubled is that if the single drainage pipe is considered to be single, the water flowing part is between the drainage pipe and the sheath pipe covered with the tension member, and it should be slightly inclined. As a result, the water stored will permeate around the anchor body and hinder the original function of the anchor.
二重構造の排水管27について更に詳しく説明すると、第
7図に示すように、排水管27は外管32と内管33と継手34
からなり、ここでは継手34を内管33の端部に形成された
雄ネジにねじ込こんで固定し、この場合に外管32を挟む
ようにした。The drain pipe 27 having the double structure will be described in more detail. As shown in FIG. 7, the drain pipe 27 includes an outer pipe 32, an inner pipe 33, and a joint 34.
In this case, the joint 34 is fixed by screwing it into a male screw formed at the end of the inner pipe 33, and in this case, the outer pipe 32 is sandwiched.
継手34は内管33、外管32を同時に連結するためのもので
あり、第4図、第5図に示すように内側両端に雌ネジ3
6、37が刻設され、周囲には数個の通水孔38を設けられ
ている。前記外管32は合成樹脂管の一例である耐蝕性の
ある塩ビ管からなって、前述した如く集水孔29を有する
有孔管30と集水孔を有しない無孔管31とがある。内管33
は両側に雄ねじ38aが加工してあるので、前記継手34を
介して連結することができ、該排水管27は組み立てるこ
とで順次長くすることができるし、有孔管30、無孔管31
を自由に必要な所に配置できる。The joint 34 is for connecting the inner pipe 33 and the outer pipe 32 at the same time. As shown in FIG. 4 and FIG.
6 and 37 are engraved, and several water passage holes 38 are provided in the periphery. The outer pipe 32 is made of a corrosion-resistant polyvinyl chloride pipe, which is an example of a synthetic resin pipe, and includes the perforated pipe 30 having the water collecting hole 29 and the non-perforated pipe 31 having no water collecting hole as described above. Inner tube 33
Since male threads 38a are processed on both sides, they can be connected through the joint 34, the drain pipe 27 can be made longer sequentially by assembling, and the perforated pipe 30 and the non-perforated pipe 31
Can be freely placed where needed.
該排水管27の最先端には刃先35を取付け、しかも該刃先
35、継手34及び内管33は鉄製として全体を強固にして打
ち込み、捩じり、押さえ等の外力に耐えることができる
ようになっている。なお、前記刃先35は、内管33の外側
に螺合し、外管32の内側に嵌入しているので、内管33と
外管32の端部を閉塞し、アンカー体23方向の直接の水の
流れを止めている。A blade edge 35 is attached to the tip of the drain pipe 27, and the blade edge is
The 35, the joint 34, and the inner pipe 33 are made of iron so that they can be hardened as a whole and driven, and can withstand external forces such as twisting and pressing. The cutting edge 35 is screwed into the outer side of the inner tube 33 and is fitted into the inner side of the outer tube 32. Therefore, the ends of the inner tube 33 and the outer tube 32 are closed, and the direction of the anchor body 23 directly. Stops the flow of water.
急傾斜地の崩壊土層40は比較的薄く、滑動面40a(第1
図示)を境にしてその上下では地盤の堅さ、透水係数が
相当異なり、崩壊土塊40は締りがなく柔らかく透水性で
あるが、下の動かない不動地盤28はよく締まって堅く、
半透水性か不透水性の場合が多い。The collapsed soil layer 40 on a steep slope is relatively thin and has a sliding surface 40a (first
The hardness and permeability of the ground are significantly different above and below the boundary (shown in the figure), and the collapsed soil mass 40 is soft and permeable, but the immovable ground 28 below is tight and firm,
Often semi-permeable or impermeable.
そこで雨が続き水の供給が続くと土中の水位が上昇し含
水比、間隙水圧が大きくなり、崩壊土塊40は流動化し滑
動を始めるから充分に地下水排除ができるような工法が
望まれる。Therefore, if rain continues and the water supply continues, the water level in the soil rises, the water content ratio and the pore water pressure increase, and the collapsing soil mass 40 fluidizes and begins to slide, so a construction method that can sufficiently remove groundwater is desired.
第1図は前記急傾斜地のアースアンカー構築方法の施工
図で、崩壊土塊40を支圧壁41で支える形となり、該の支
圧壁41が押し倒されないように、アンカー体23及びこれ
に連接する排水管27を有する排水アンカー42で引き止め
るようにしている。該方法によれば斜面をいくつかのブ
ロックに分けて図に示すようにブロック毎に支圧壁41と
排水アンカー42とを構築する。FIG. 1 is a construction drawing of the earth anchor construction method for the steep slope, in which the collapsed mass 40 is supported by the bearing wall 41, and the anchor body 23 and the anchor body 23 are connected to the bearing wall 41 so that the bearing wall 41 is not pushed down. A drainage anchor 42 having a drainage pipe 27 is used to hold it. According to this method, the slope is divided into several blocks, and as shown in the figure, the bearing wall 41 and the drainage anchor 42 are constructed for each block.
この実施例においては、切り土成形した斜面43に直高5m
程度の間隔をめどに幅1〜2mを標準として小段44を設
け、該小段44に沿って支圧壁41と溝45とを造る。支圧壁
41は横方向に連続して造り適当な個所に収縮目地を設け
る。支圧壁41の高さは1.5m程度でコンクリート造りとし
て形は台形で、前面は鉛直背面は少し勾配を付けて、土
との接地面積を広げ、又崩壊土塊40を支えるのに都合の
良い形とする。In this example, the cut sloped slope 43 has a direct height of 5 m.
The berms 44 provided in prospect spacing degree width 1~2m as a standard, build and bearing capacity wall 41 and the groove 45 along the small step 44. Bearing wall
41 is made continuously in the lateral direction and shrink joints are provided at appropriate points. The height of the bearing wall 41 is about 1.5 m, and the shape is trapezoidal as a concrete structure, the front surface is vertical with a slight slope and the back surface is slightly inclined, it is convenient to expand the ground contact area with soil and support the collapsed mass 40 Form.
排水アンカー42は支圧壁41の略中央に水平より下向き3
度位で構築する。排水管27は滑動面43aより1〜2m不動
地盤28に嵌入させてアンカー部分と排水管部分の断面の
ズレを防ぎ、また滑動面40a上部の地下水帯46より充分
集排水でき、排水された水は側溝45によって地表面水と
共に崩壊区外に排除する。各支圧壁41の間の斜面43は緑
化を主体とした法面保護策が採れるので周囲との調和を
図ることができる。The drainage anchor 42 is located approximately in the center of the bearing wall 41 and faces downward from the horizontal 3
Build in degrees. The drainage pipe 27 is fitted to the immovable ground 28 for 1 to 2 m from the sliding surface 43a to prevent the cross section of the anchor portion and the drainage pipe portion from shifting, and the drainage water can be sufficiently collected and drained from the groundwater zone 46 above the sliding surface 40a. Is removed by the gutter 45 together with the surface water outside the collapse zone. The slopes 43 between the bearing walls 41 can be harmonized with the surroundings because the slope protection measures mainly for greening can be adopted.
請求項1、2記載の急傾斜地のアースアンカー構築方法
は、以上の説明からも明らかなように、引張部の奥側に
位置する外管に集水孔が形成された有孔管を用い、該引
張部の手前側に位置する外管に無孔管を用いているの
で、これによって崩壊土塊である透水層及び滑り面を流
れる地下水を効率的に集水でき、しかも、該アンカーの
挿入口付近の地盤の軟弱化を防ぎ、更には、表面層の崩
壊防止を図ることが可能となる。As is clear from the above description, the method of constructing a ground anchor for a steep slope according to claims 1 and 2 uses a perforated pipe in which a water collecting hole is formed in the outer pipe located on the inner side of the tensile portion, Since the non-perforated pipe is used as the outer pipe located on the front side of the tension portion, this enables efficient collection of groundwater flowing through the permeable layer and sliding surface, which are collapsed soil blocks, and the insertion port of the anchor. It is possible to prevent the softening of the surrounding ground and further prevent the surface layer from collapsing.
そして、前記排水管を構成する外管と内管の先端部には
刃先を設けているので、排水管を不動地盤に打ち込むこ
とができ、更には、外管と内管の先端部が装着された該
刃先の元部によって閉塞され、有孔管によって集めた水
はアンカー体及びその周囲への積極的な浸水防止し、こ
れによってアンカー体の緩みが防止できる。Further, since the tip ends of the outer pipe and the inner pipe constituting the drain pipe are provided with the blade edges, the drain pipe can be driven into the immovable ground, and further, the tip portions of the outer pipe and the inner pipe are mounted. Further, the water that is blocked by the base of the blade edge and collected by the perforated pipe can prevent the anchor body and its surroundings from actively inundating, thereby preventing the anchor body from loosening.
しかも、前記排水管はアースアンカーを施工する際に同
時に行えるので、余分な工事が不必要となり、工事費の
低廉及び工事期間の短縮を図ることが可能となった。Moreover, since the drainage pipe can be formed at the same time when the earth anchor is constructed, no extra construction is required, and the construction cost can be reduced and the construction period can be shortened.
また、崩壊土塊を止める支圧壁はブロック毎に配置すれ
ば良いので、法面緑化も可能となった。In addition, since the bearing wall that stops the collapsed soil blocks can be placed in each block, slope greening has become possible.
第1図は本発明の実施例に係る急傾斜地のアースアンカ
ー構築方法を施工した急傾斜地の断面図、第2図
(A),(B),(C),(D)は中間部を部分的に省
略した該急傾斜地のアースアンカー構築手順を示す断面
図、第3図は完成したアースアンカーの中間部を部分的
に省略した断面図、第4図は排水管を連結する継手の正
断面図、第5図は同側断面図、第6図は該排水管の部分
側面図、第7図は該排水管の組立状態を示す部分断面
図、第8図は急傾斜地の断面図、第9図は従来例に係る
アースアンカー工法を示す断面図である。 〔符号の説明〕 22……アンカーの引張部、23……アンカー体、24、25…
…ケーシングパイプ、26……引張材、27……排水管、28
……不動地盤、29……集水孔、30……有孔管、31……無
孔管、32……外管、33……内管、34……継手、35……刃
先、36、37……雌ネジ、38……通水孔、38a……雄ネ
ジ、40……崩壊層、40a……滑動面、41……支圧壁、42
……排水アンカー、43……斜面、44……小段、45……側
溝FIG. 1 is a cross-sectional view of a steep slope on which a method for constructing a ground anchor for a steep slope according to an embodiment of the present invention has been applied, and FIGS. 2 (A), (B), (C), and (D) show the intermediate portion. A cross-sectional view showing the procedure for constructing the ground anchor of the steep slope, which is omitted in detail, FIG. 3 is a cross-sectional view in which the intermediate portion of the completed ground anchor is partially omitted, and FIG. 5 and 5 are sectional views of the same side, FIG. 6 is a partial side view of the drainage pipe, FIG. 7 is a partial sectional view showing an assembled state of the drainage pipe, and FIG. 8 is a sectional view of a steep slope. FIG. 9 is a sectional view showing a ground anchor construction method according to a conventional example. [Explanation of reference symbols] 22 ... tension part of anchor, 23 ... anchor body, 24, 25 ...
… Casing pipe, 26 …… Tensile material, 27 …… Drain pipe, 28
...... Fixed ground, 29 ...... water collection hole, 30 ...... perforated pipe, 31 ...... non-perforated pipe, 32 …… outer pipe, 33 …… inner pipe, 34 …… joint, 35 …… cutting edge, 36, 37 …… Female thread, 38 …… Water passage hole, 38a …… Male thread, 40 …… Collapse layer, 40a …… Sliding surface, 41 …… Bearing wall, 42
…… Drainage anchor, 43 …… Slope, 44 …… Small stage, 45 …… Gutter
Claims (2)
めアンカーの引張部に相当する部分に、外管と該外管の
内側に配置される内管とからなる排水管を配置する急傾
斜地のアースアンカー構築方法であって、前記外管及び
内管の先端部に、該外管と内管との隙間にその元部が装
着された刃先を設けると共に、前記引張部の奥側に位置
する前記外管に適当箇所に集水孔が形成された有孔管を
用い、前記引張部の手前側に位置する前記外管に無孔管
を用いて、透水層を流れる地下水を前記集水孔から外管
と内管の間に導き排除することを特徴とする急傾斜地の
アースアンカー構築方法。1. A steep slope where a drainage pipe consisting of an outer pipe and an inner pipe arranged inside the outer pipe is arranged at a portion corresponding to a tension portion of a retaining anchor which is constructed substantially horizontally with respect to the steep slope. In the method of constructing an earth anchor, the tip of the outer tube and the inner tube is provided with a cutting edge whose base portion is mounted in a gap between the outer tube and the inner tube, and the position is located on the inner side of the tension section. Using a perforated pipe in which water collecting holes are formed at appropriate places in the outer pipe, and using a non-perforated pipe in the outer pipe located on the front side of the tension portion, the ground water flowing through the permeable layer is collected. A method for constructing a ground anchor on a steep slope, characterized by guiding and excluding from a hole between an outer pipe and an inner pipe.
内管の先端部に取付けられる刃先は鉄製である請求項1
記載の急傾斜地のアースアンカー構築方法。2. The outer tube is made of a synthetic resin tube, and the inner tube and the cutting edge attached to the tip of the inner tube are made of iron.
Construction method for earth anchor on steep slope.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63246600A JPH0718160B2 (en) | 1988-09-29 | 1988-09-29 | How to build an earth anchor on a steep slope |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63246600A JPH0718160B2 (en) | 1988-09-29 | 1988-09-29 | How to build an earth anchor on a steep slope |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0291316A JPH0291316A (en) | 1990-03-30 |
| JPH0718160B2 true JPH0718160B2 (en) | 1995-03-01 |
Family
ID=17150825
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP63246600A Expired - Lifetime JPH0718160B2 (en) | 1988-09-29 | 1988-09-29 | How to build an earth anchor on a steep slope |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0718160B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105672313A (en) * | 2016-01-25 | 2016-06-15 | 兰州理工大学 | Convection-accelerating ventilating and cooling anchor pipe and construction method |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4951254B2 (en) * | 2005-03-07 | 2012-06-13 | 株式会社大林組 | Leg frame structure and method for constructing the frame structure |
| JP6262814B1 (en) * | 2016-08-04 | 2018-01-17 | 株式会社サムシング | Protection method for embankment slope |
| CN115627782B (en) * | 2022-10-19 | 2024-06-04 | 中南大学 | Nail-stitch type reinforcing structure for slope construction of slope land topography filling embankment and construction method |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6040427A (en) * | 1983-08-15 | 1985-03-02 | Kazuo Hasegawa | Earth-and-lock anchor with strainer |
-
1988
- 1988-09-29 JP JP63246600A patent/JPH0718160B2/en not_active Expired - Lifetime
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105672313A (en) * | 2016-01-25 | 2016-06-15 | 兰州理工大学 | Convection-accelerating ventilating and cooling anchor pipe and construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0291316A (en) | 1990-03-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP4296660B2 (en) | Slope stabilization method | |
| JP4727718B2 (en) | Retaining method for retaining wall | |
| KR20150047172A (en) | The water permeable block with rain water storage and comstruction method using it | |
| JP4900972B2 (en) | Ground drainage structure and its construction method | |
| JPH09158223A (en) | Filling and cutting drainage structure | |
| JPH0718160B2 (en) | How to build an earth anchor on a steep slope | |
| JP4953384B2 (en) | Ground drainage structure and its construction method | |
| JP2004278287A (en) | Permeable steel pipe mountain retaining type retaining wall structure | |
| JP2851816B2 (en) | Slope stable structure | |
| KR20140020548A (en) | System for preventing erosion and the concreting method therefor | |
| JPH04194226A (en) | Drain pipe for reinforcing slope | |
| JP2006194044A (en) | Installation method for water drain pipe in toe of slope on back of levee body, water draining method for seepage water on back of levee body, and water drain structure for seepage water | |
| JPH03206211A (en) | Drain material, soft ground improving structure using drain material and foundation pillar using the same structure | |
| JPH10168985A (en) | Structure for promoting infiltration of surface water | |
| KR101809978B1 (en) | Strike type one body drain structure body for ground and construction method thereof | |
| JP3247324B2 (en) | Slope reinforced earth method | |
| JP2512469Y2 (en) | Concrete U type drainage | |
| JPH022771Y2 (en) | ||
| JP4056522B2 (en) | Levee reinforced drain structure and levee reinforced drain construction method | |
| JPH0447247Y2 (en) | ||
| JPH1018294A (en) | Stable structure of slope | |
| JPS60123615A (en) | Method of draining underground water | |
| JPH086337B2 (en) | Foundation construction method and foundation pile | |
| JP3552925B2 (en) | Opening method of groundwater holes in steel pipe column retaining wall | |
| JP2005240507A (en) | Rain water storage tank and its construction method |