Balcony Slab Construction EquipmentInfo
- Publication number
- JPH0730626B2 JPH0730626B2 JP19224587A JP19224587A JPH0730626B2 JP H0730626 B2 JPH0730626 B2 JP H0730626B2 JP 19224587 A JP19224587 A JP 19224587A JP 19224587 A JP19224587 A JP 19224587A JP H0730626 B2 JPH0730626 B2 JP H0730626B2
- Authority
- JP
- Japan
- Prior art keywords
- balcony slab
- slab construction
- construction equipment
- present
- joist
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 title claims description 14
- 238000009415 formwork Methods 0.000 description 9
- 238000000034 method Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明は、バルコニースラブを施工性良く形成するため
の施工装置に関する。The present invention relates to a construction device for forming a balcony slab with good workability.
(従来の技術) 第2図は従来のバルコニースラブの施工手段を示すもの
であり、型枠組付け時の施工手順としては、まず、下階
に形成されたバルコニースラブ1上にパイプサポート2
を立設し、その上部に大引3及び根太4をこの順序で組
付け、最後に型枠パネル5を設置してからパイプサポー
ト2により型枠パネル5のレベルを位置決め設定するよ
うになっている。(Prior Art) FIG. 2 shows a conventional means for constructing a balcony slab. As a construction procedure when assembling a form, first, a pipe support 2 is placed on a balcony slab 1 formed on the lower floor.
Is installed upright, the Daihiki 3 and joist 4 are assembled in this order in the order, and finally the formwork panel 5 is installed, and then the level of the formwork panel 5 is positioned and set by the pipe support 2. There is.
また、型枠パネル上にバルコニースラブ1を打設して、
所定期間の養生後には、上記したのと逆の手順により型
枠及び支保工の脱型、撤去作業を行うものである。Also, place the balcony slab 1 on the formwork panel,
After curing for a predetermined period of time, the mold and the supporting work are demolded and removed by the procedure reverse to the above.
(発明が解決しようとする問題点) 従来は上記した如き施工工程によるため、工程が複雑で
施工作業に長時間を要し、また、コンクリート打設等の
際には、外部足場を必要とする問題を有していた。(Problems to be solved by the invention) Conventionally, because of the construction process as described above, the process is complicated and the construction work requires a long time, and an external scaffold is required for concrete pouring. Had a problem.
本発明は、かかる従来の問題点を解決し、施工性良くバ
ルコニースラブを形成することが可能なバルコニースラ
ブ施工装置を提供することを目的とするものである。SUMMARY OF THE INVENTION It is an object of the present invention to provide a balcony slab construction device that solves the conventional problems and can form a balcony slab with good workability.
(問題点を解決するための手段) 上記目的を達成するため本発明に係るバルコニースラブ
施工装置においては、バルコニースラブ打設用の型枠パ
ネルと、根太と、大引と、パイプサポートとを一体に組
付け、かつ前記型枠パネル及び根太の張り出し部分に手
摺を一体に設けてなることを特徴とするものである。(Means for Solving Problems) In the balcony slab construction apparatus according to the present invention for achieving the above object, a form panel for placing a balcony slab, a joist, a large pull, and a pipe support are integrated. And a handrail is integrally provided on the projecting portion of the form panel and joist.
(実施例) 以下、本発明の好適な実施例を図面により説明する。(Examples) Hereinafter, preferred examples of the present invention will be described with reference to the drawings.
第1図は本発明の一実施例を示すものであり、本実施例
に係るバルコニースラブ施工装置10は、バルコニースラ
ブ打設用の型枠パネル11と、根太12と、大引13と、パイ
プサポート14とを一体に組付け、かつ前記型枠パネル11
と根太12の外方への張り出し部分11a、12aに手摺15を一
体に設けてなり、全体として移動、据付が可能なもので
ある。FIG. 1 shows an embodiment of the present invention. A balcony slab construction apparatus 10 according to the present embodiment includes a form panel 11 for placing a balcony slab, joists 12, a haul 13, and a pipe. The support 14 and the formwork panel 11 are assembled together.
The handrails 15 are integrally provided on the outwardly projecting portions 11a, 12a of the joists 12 and can be moved and installed as a whole.
よって、施工にあたっては、まず、バルコニースラブ施
工装置10全体をクレーン等の揚重手段により所定位置ま
で揚重、移動し、第1図に示すように下階のバルコニー
スラブ1上に設置するとともに、パイプサポート14の調
節ネジ14aの操作により、型枠パネル11が所定高さにな
るように位置決めを行ない、しかる後にコンクリートを
打設すればよい。Therefore, in the construction, first, the entire balcony slab construction device 10 is lifted and moved to a predetermined position by a lifting means such as a crane and installed on the balcony slab 1 on the lower floor as shown in FIG. By operating the adjusting screw 14a of the pipe support 14, the form panel 11 is positioned so as to have a predetermined height, and then concrete is poured.
打設作業にあたっては、型枠パネル11及び根太12の張り
出し部分11a,12aと手摺15により足場が確保されるの
で、別個に外部足場を設置する必要がなくなる。Since the scaffolding is secured by the projecting portions 11a and 12a of the formwork panel 11 and joist 12 and the handrail 15 in the placing work, it is not necessary to separately install an external scaffolding.
また、コンクリートの養生後の脱型にあたっては、パイ
プサポート14の調節ネジ14aにより型枠全体を所定寸法
分下げた後、上記揚重手段により施工装置10全体を引出
し、次の施工位置に移動させればよいものである。Further, in demolding after curing the concrete, after lowering the entire formwork by a predetermined dimension by the adjusting screw 14a of the pipe support 14, the whole lifting device 10 is pulled out by the lifting means and moved to the next working position. It's good.
このように、本実施例においては型枠、支保工及び手摺
が一体化されているため、従来のような現場での組付作
業が一切必要でなく、レベル調整を行なうだけでよくな
る。As described above, in this embodiment, since the formwork, the supporting work and the handrail are integrated, there is no need for the conventional on-site assembly work, and only the level adjustment is required.
さらに、型枠脱型時にもパイプサポート14の操作だけで
よく、組付、脱型作業が格段に省力化されうるものであ
る。Further, even when the mold is removed from the mold, only the operation of the pipe support 14 is required, and the assembling and demolding work can be significantly labor-saving.
また、移動の際も装置全体として移動可能であるため、
短時間で作業が可能であり、手摺15を有する足場が確保
されているため、外部足場が不要でコスト的にも低減化
しうる。Also, since it can be moved as a whole when moving,
Since the work can be performed in a short time and the scaffold having the handrail 15 is secured, an external scaffold is not necessary and cost can be reduced.
なお、本発明は上記実施例に限定されるものではなく、
本発明の要旨を逸脱しない範囲内で種々の変形例が可能
なことは言うまでもない。The present invention is not limited to the above embodiment,
It goes without saying that various modifications can be made without departing from the scope of the present invention.
(発明の効果) 本発明は上述した如く構成されており、バルコニースラ
ブ打設用の型枠パネルと、根太と、大引と、パイプサポ
ートとを一体に組付け、かつ前記型枠パネル及び根太の
張り出し部分に手摺を一体に設けて、装置全体としての
移動、設置、撤去が可能なものとしたため、施工作業を
簡易、かつ迅速に行なうことができ、外部足場を別個に
設けることも不要となるものである。(Effects of the Invention) The present invention is configured as described above, and integrally assembles a formwork panel for placing balcony slabs, joists, large hauls, and pipe supports, and forms the formwork panel and joists. Since the handrail is integrally provided on the overhanging part of the device, and the entire device can be moved, installed, and removed, construction work can be performed easily and quickly, and it is not necessary to separately provide an external scaffold. It will be.
第1図は本発明に係るバルコニースラブ施工装置の一実
施例を示す概念図、第2図は従来の型枠支保工を示す概
念図である。 1……バルコニースラブ、10……バルコニースラブ施工
装置、11……型枠パネル、12……根太、13……大引、14
……パイプサポート、15……手摺。FIG. 1 is a conceptual diagram showing an embodiment of a balcony slab construction apparatus according to the present invention, and FIG. 2 is a conceptual diagram showing a conventional form supporting work. 1 …… Balcony slab, 10 …… Balcony slab construction equipment, 11 …… Form panel, 12 …… Joist, 13 …… Daiki, 14
…… Pipe support, 15 …… Handrail.
Claims (1)
根太と、大引と、パイプサポートとを一体に組付け、か
つ前記型枠パネル及び根太の張り出し部分に手摺を一体
に設けてなることを特徴とするバルコニースラブ施工装
置。1. A form panel for placing a balcony slab,
A balcony slab construction device characterized in that a joist, a Daihiki, and a pipe support are integrally assembled, and a handrail is integrally provided on the projecting portion of the form panel and joist.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19224587A JPH0730626B2 (en) | 1987-07-31 | 1987-07-31 | Balcony Slab Construction Equipment |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19224587A JPH0730626B2 (en) | 1987-07-31 | 1987-07-31 | Balcony Slab Construction Equipment |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6436865A JPS6436865A (en) | 1989-02-07 |
| JPH0730626B2 true JPH0730626B2 (en) | 1995-04-10 |
Family
ID=16288078
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP19224587A Expired - Lifetime JPH0730626B2 (en) | 1987-07-31 | 1987-07-31 | Balcony Slab Construction Equipment |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0730626B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP1088883A4 (en) * | 1999-04-15 | 2003-06-18 | Japan Energy Corp | LUBRICANT FOR REFRIGERATING MACHINE USING AMMONIA-BASED REFRIGERANT |
| KR100833306B1 (en) * | 2006-09-05 | 2008-05-28 | 삼성물산 주식회사 | Edge table system formwork and its installation method |
| CN110185284A (en) * | 2019-06-12 | 2019-08-30 | 北京矿建建设集团有限公司 | A kind of assembled side roof support means |
| GB2614922A (en) * | 2022-01-25 | 2023-07-26 | Sapphire Balconies Ltd | A method and apparatus for installing a series of balconies on a building |
| CN117722007A (en) * | 2024-01-29 | 2024-03-19 | 中建八局第二建设有限公司 | A support system and construction method for integral pouring formwork for super high-rise cantilevered balconies |
-
1987
- 1987-07-31 JP JP19224587A patent/JPH0730626B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6436865A (en) | 1989-02-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3196043B2 (en) | Construction method of stairs and staircase, construction method of stairs, and stair members | |
| JPH0730626B2 (en) | Balcony Slab Construction Equipment | |
| KR101948294B1 (en) | gang form assembly and construction method for falling prevention | |
| KR100361047B1 (en) | Construction mold | |
| JP2884440B2 (en) | Formwork for construction of concrete prism and construction method of column using it | |
| KR20040087359A (en) | Foldable gang form and construction method using the same | |
| CN112223496A (en) | Simple mould for assembling building unit | |
| JPH0642184A (en) | Method of constructing a skeleton using half-PC floorboard | |
| JP2962121B2 (en) | Sliding form method | |
| JP2002194892A (en) | Construction method of building | |
| JPH0518106A (en) | Constructing device for concrete building | |
| JP2724891B2 (en) | Construction method of pillar half PCa formwork | |
| JP3087196B2 (en) | How to build stairs | |
| JPS637654Y2 (en) | ||
| JPH1024407A (en) | Apparatus and method for manufacturing semi-PCa balcony | |
| JPS5898571A (en) | Method and apparatus for constructing epanded part | |
| JP2002364139A (en) | Steel stair mounting hardware, mounting device and mounting method | |
| JP2745238B2 (en) | Temporary support for slab half PCa board erection | |
| JPS61191763A (en) | Construction of pc panel for balcony using large beam floor mold frame | |
| JP2722121B2 (en) | Construction method of reinforced concrete building | |
| JPH0681476A (en) | Building method for concrete structure | |
| JPH10115090A (en) | Climb form construction method | |
| JPS6378964A (en) | Mold frame construction method | |
| JP3021512B2 (en) | PC handrail for cantilever slab | |
| JPS6152304B2 (en) |