JPH0737945B2 - ICP analysis method - Google Patents
ICP analysis methodInfo
- Publication number
- JPH0737945B2 JPH0737945B2 JP63217656A JP21765688A JPH0737945B2 JP H0737945 B2 JPH0737945 B2 JP H0737945B2 JP 63217656 A JP63217656 A JP 63217656A JP 21765688 A JP21765688 A JP 21765688A JP H0737945 B2 JPH0737945 B2 JP H0737945B2
- Authority
- JP
- Japan
- Prior art keywords
- sample
- plasma
- supplied
- atomization chamber
- gas
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Investigating, Analyzing Materials By Fluorescence Or Luminescence (AREA)
Description
【発明の詳細な説明】 (イ)産業上の利用分野 本発明は試料の成分を分析するICP(高周波誘導結合プ
ラズマ)分析装置及びICP分析方法に関する。The present invention relates to an ICP (high frequency inductively coupled plasma) analyzer and an ICP analysis method for analyzing components of a sample.
(ロ)従来の技術 ICP分析装置はガス化(霧化)した試料をプラズマトー
チに導入して発光させ、この光を分光測定して試料成分
を分析する装置であり、一般に溶液状の試料は試料霧化
チェンバにより霧化し、キャリヤガス(アルゴンガス)
とともにプラズマトーチに導入する。プラズマトーチに
は誘導コイルが周回され、プラズマガス、冷却ガス(通
常は共にアルゴンガス)が供給されており、プラズマト
ーチ先端にプラズマ炎が形成される。(B) Conventional technology An ICP analyzer is a device that introduces a gasified (atomized) sample into a plasma torch to emit light, and spectroscopically measures this light to analyze the sample components. Atomized by the sample atomization chamber, and carrier gas (argon gas)
It is introduced together with the plasma torch. An induction coil is circulated around the plasma torch, and a plasma gas and a cooling gas (usually argon gas are both supplied) to form a plasma flame at the tip of the plasma torch.
ところでプラズマ炎の点灯時には大きな電力を要すると
ともにインピーダンスの整合などの複雑な操作を要する
ので、試料を断続的に分析する場合にはプラズマを点灯
したままの状態を維持する。このような場合、プラズマ
の安定性を保ち分析条件を一定にするためにプラズマト
ーチへ供給するガスの量や誘導コイルへ供給する高周波
電力を一定にしていた。By the way, when the plasma flame is turned on, a large amount of electric power is required and a complicated operation such as impedance matching is required. Therefore, when the sample is analyzed intermittently, the state where the plasma is turned on is maintained. In such a case, the amount of gas supplied to the plasma torch and the high-frequency power supplied to the induction coil are kept constant in order to maintain the stability of the plasma and keep the analysis conditions constant.
ところが1つの試料を導入して分析するのに要する時間
は10〜20秒程度であるので、大部分が待機時間となり、
高価なアルゴンガスの消費が多くなって分析コストを増
大させる問題があった。However, the time required to introduce and analyze one sample is about 10 to 20 seconds, so most of the time is waiting time,
There is a problem that the cost of the expensive argon gas increases and the analysis cost increases.
この問題を解決するため特願昭61−61555号の発明にお
いては試料霧化チェンバとプラズマトーチとの間に切換
えバルブを設け、霧化した試料を測定時のみプラズマト
ーチに導入し、それ以外の時は試料霧化チェンバを通っ
たキャリヤガスを切換えバルブから排出している。この
ようにすると測定時以外はアルゴンガスだけがプラズマ
トーチに導入されるから、最少限の口火プラズマを維持
するために必要なガス量と誘導コイルへ供給する電力と
が予測でき、ガスの量を少なくして分析コストを下げる
ことが可能となる。また分析時以外は試料霧化チェンバ
がキャリヤガスによって洗浄され、次の試料導入に備え
ることができる。In order to solve this problem, in the invention of Japanese Patent Application No. 61-61555, a switching valve is provided between the sample atomizing chamber and the plasma torch, and the atomized sample is introduced into the plasma torch only at the time of measurement. At this time, the carrier gas passing through the sample atomization chamber is discharged from the switching valve. In this way, only argon gas is introduced into the plasma torch except during measurement, so the amount of gas required to maintain the minimum ignition plasma and the power supplied to the induction coil can be predicted, and the amount of gas can be reduced. It is possible to reduce the analysis cost by reducing the amount. In addition, the sample atomization chamber is cleaned by the carrier gas except when the analysis is performed, and the sample can be prepared for the next sample introduction.
(ハ)解決すべき課題 以上のような特願昭61−61555号の発明では、試料霧化
チェンバとプラズマトーチとの間に設けた切換えバルブ
がスタンド内雰囲気により錆びてその作動精度が悪化
し、分析に支障を来たすという問題があった。また切換
えバルブの気密性が悪化するとプラズマが不安定になっ
たり消えたりする問題が発生した。(切換えバルブは正
確な動作を要し複雑な構成となり加工性などの理由で金
属部材も使用されていた。) (ニ)課題を解決するための手段 本発明においては、上記の従来技術の問題点と課題を解
決するために次のような方法をとった。(C) Problems to be solved In the invention of Japanese Patent Application No. 61-61555 as described above, the switching valve provided between the sample atomizing chamber and the plasma torch is rusted by the atmosphere in the stand and its operating accuracy deteriorates. , There was a problem that it interfered with the analysis. Further, when the airtightness of the switching valve is deteriorated, the plasma becomes unstable or disappears. (The switching valve requires a precise operation and has a complicated structure, and a metal member is also used for the reason of workability.) (D) Means for Solving the Problems In the present invention, the problems of the above-mentioned conventional technology The following methods were taken to solve the problems and issues.
試料霧化チェンバとプラズマトーチとの間に設けた切り
換えバルブをなくし、キャリアガスを試料霧化チェンバ
に供給する前の経路上でオン/オフするようにした。そ
してキャリアガスの流す量を次のように制御する。The switching valve provided between the sample atomization chamber and the plasma torch is eliminated, and the carrier gas is turned on / off on the path before being supplied to the sample atomization chamber. Then, the flow rate of the carrier gas is controlled as follows.
分析の待機時にはプラズマトーチへ供給するガスの量及
び誘導コイルへ供給する高周波電力を制御して口火プラ
ズマを維持するとともに試料霧化チェンバに供給するキ
ャリヤガスを遮断しておく。分析に際してはプラズマト
ーチへ供給するガスの量及び誘導コイルへ供給する高周
波電力を増加させてプラズマ出力を上昇させるととも
に、試料霧化チェンバにキャリヤガスを供給して試料を
霧化しプラズマトーチに導入して測定を行なう。測定の
終了後は、しばらくの間、プラズマ出力を上昇させた状
態に保つとともに試料霧化チェンバにキャリヤガスを供
給して試料霧化チェンバの洗浄を行なう。そして試料霧
化チェンバの洗浄終了後には前記待機時の状態に戻るよ
うにする。During the analysis standby, the amount of gas supplied to the plasma torch and the high frequency power supplied to the induction coil are controlled to maintain the spark plasma and the carrier gas supplied to the sample atomization chamber is shut off. During analysis, increase the amount of gas supplied to the plasma torch and the high frequency power supplied to the induction coil to increase the plasma output, and also supply the carrier gas to the sample atomization chamber to atomize the sample and introduce it into the plasma torch. Measure. After the measurement is completed, the plasma output is kept raised for a while and the carrier gas is supplied to the sample atomizing chamber to clean the sample atomizing chamber. After the cleaning of the sample atomizing chamber is completed, the standby state is restored.
(ホ)作用 試料霧化チェンバに供給する前のキャリヤガス経路を通
るのは不活性のアルゴンガスたけとなり、また腐蝕性の
雰囲気外に置いた簡単な構造のバルブでキャリヤガスを
オン/オフできるので、腐蝕による劣化がない。(E) Action Inert argon gas only passes through the carrier gas path before it is supplied to the sample atomization chamber, and the carrier gas can be turned on / off by a valve with a simple structure placed outside the corrosive atmosphere. Therefore, there is no deterioration due to corrosion.
試料霧化チェンバとプラズマトーチとの間に設けた切換
えバルブをなくしたため、待機時間中の試料導入系のク
リーニング作用がなくなるため、キャリヤガスが試料霧
化チェンバからプラズマトーチを介して流れる時間を延
長し、これによって試料導入系のクリーニング作用を行
なわせる。(このクリーニング時間中、ガス流量やプラ
ズマ出力を下げるとキャリヤガスに混入した残留試料ガ
スによってプラズマが消える恐れがあるので、出力は上
昇した状態を保持する。) (ヘ)実施例 第1図は本発明の一実施例を示すICP分析装置の要部構
成図である。本図において、1はアルゴンガスを供給す
るボンベ、2はプラズマトーチ、6,8は夫々プラズマト
ーチ2へ供給する冷却ガス,プラズマガスの供給管、10
は誘導コイル、12は高周波電源14と誘導コイルとのイン
ピーダンスマッチングをとるためのマッチングボック
ス、16は冷却ガス,プラズマガスの供給量を制御するた
めのガスコントローラ(プラズマトーチへ供給するガス
の量を制御する手段)、18は試料霧化チェンバ、20は溶
液試料、22はキャリヤガス供給管、26は試料霧化チェン
バに供給するキャリヤガスをオン/オフするバルブ、32
はガスコントローラ16及び高周波電源(高周波電力供給
手段)14及びバルブ26の動作をコントロールする制御装
置(シーケンスコントローラ)である。(分光、測定部
は省略する) 次に第1図の装置を用いたICP分析方法(分析動作のシ
ーケンス)を説明する。第2図は誘導コイルに供給する
高周波電力とプラズマトーチへ供給するガス(冷却ガ
ス,プラズマガス,キャリヤガス)の量を分析における
シーケンスに対応して表したグラフであり、第2図は第
1図の装置の場合、第3図は特願昭61−61555号の発明
の場合を表わす。Since the switching valve provided between the sample atomization chamber and the plasma torch is eliminated, the cleaning action of the sample introduction system during the standby time is lost, so the time for the carrier gas to flow from the sample atomization chamber through the plasma torch is extended. In this way, the cleaning action of the sample introduction system is performed. (During this cleaning time, if the gas flow rate or the plasma output is reduced, the plasma may be extinguished by the residual sample gas mixed in the carrier gas, so the output is kept in the increased state.) (F) Example 1 FIG. It is a principal part block diagram of the ICP analyzer which shows one Example of this invention. In the figure, 1 is a cylinder for supplying argon gas, 2 is a plasma torch, 6 and 8 are cooling gas and plasma gas supply pipes supplied to the plasma torch 2, 10 respectively.
Is an induction coil, 12 is a matching box for impedance matching between the high frequency power supply 14 and the induction coil, 16 is a gas controller for controlling the supply amounts of the cooling gas and the plasma gas (the amount of gas supplied to the plasma torch is Control means), 18 is a sample atomization chamber, 20 is a solution sample, 22 is a carrier gas supply pipe, 26 is a valve for turning on / off the carrier gas supplied to the sample atomization chamber, 32
Is a control device (sequence controller) for controlling the operations of the gas controller 16, the high frequency power supply (high frequency power supply means) 14 and the valve 26. (Spectral and measurement units are omitted.) Next, an ICP analysis method (analysis operation sequence) using the apparatus of FIG. 1 will be described. FIG. 2 is a graph showing the amounts of high-frequency power supplied to the induction coil and the gases (cooling gas, plasma gas, carrier gas) supplied to the plasma torch corresponding to the sequence in the analysis, and FIG. In the case of the apparatus shown in FIG. 3, FIG. 3 shows the case of the invention of Japanese Patent Application No. 61-61555.
第1図の装置を用いたICP分析方法(分析動作のシーケ
ンス)を第2図によって説明すると、 (1)待機時にはプラズマトーチへ供給する冷却ガス及
びプラズマガスの総量を毎分6リットルに制御し、試料
霧化チェンバ18に供給するキャリヤガスの流量は零にす
る。(オン/オフバルブ26はオフの状態) この時誘導コイルへ供給する高周波電力(プラズマ出
力)は約0.2kWに制御して口火プラズマを維持する。The ICP analysis method (analysis operation sequence) using the apparatus of FIG. 1 will be described with reference to FIG. 2. (1) During standby, the total amount of cooling gas and plasma gas supplied to the plasma torch is controlled to 6 liters per minute. The flow rate of the carrier gas supplied to the sample atomization chamber 18 is set to zero. (On / off valve 26 is off) At this time, the high frequency power (plasma output) supplied to the induction coil is controlled to about 0.2 kW to maintain the spark plasma.
(2)分析に際しては溶液試料20を導入(設定)し、プ
ラズマトーチへ供給する冷却ガス及びプラズマガスの総
量を毎分13リットルに、誘導コイルへ供給する高周波電
力を約1.2kWに増加させてプラズマ出力を上昇させると
ともに、バルブ26をオンにして試料霧化チェンバにキャ
リヤガスを供給(毎分1リットル)し、試料を霧化して
プラズマトーチ2に導入して測定を行ない、 (3)測定終了後プラズマ出力を上昇させた状態に保つ
とともに試料霧化チェンバ18にキャリヤガスを供給して
約10秒間試料霧化チェンバの洗浄を行ない、 (4)試料霧化チェンバの洗浄終了後前記待機時の状態
(1)に戻る。(2) For analysis, introduce (set) the solution sample 20, increase the total amount of cooling gas and plasma gas supplied to the plasma torch to 13 liters per minute, and increase the high-frequency power supplied to the induction coil to about 1.2 kW. While increasing the plasma output, turn on the valve 26 to supply the carrier gas to the sample atomization chamber (1 liter / min), atomize the sample and introduce it into the plasma torch 2 for measurement (3) Measurement After the end, keep the plasma output in a rising state and supply the carrier gas to the sample atomization chamber 18 to clean the sample atomization chamber for about 10 seconds. (4) After cleaning the sample atomization chamber Return to the state (1).
これに対して従来の特願昭61−61555号の発明の場合
は、第3図のように試料霧化チェンバに常にキャリヤガ
スを供給しており、プラズマトーチへ供給するガスの量
及び誘導コイルへ供給する高周波電力は測定時のみ増加
させている。On the other hand, in the case of the invention of Japanese Patent Application No. 61-61555, the carrier gas is always supplied to the sample atomizing chamber as shown in FIG. 3, the amount of gas supplied to the plasma torch and the induction coil. The high frequency power supplied to is only increased during measurement.
(ト)効果 本発明によると高価なアルゴンガスの消費が少なくなっ
て分析コストを減少させることができるとともに、特願
昭61−61555号の発明のように試料霧化チェンバとプラ
ズマトーチとの間に設けた切換えバルブがスタンド内雰
囲気により錆びて動作の精度が悪化し分析に支障を来た
すという問題が解消され、分析の信頼度が向上するとい
う優れた効果を奏する。(G) Effect According to the present invention, the consumption of expensive argon gas can be reduced, and the analysis cost can be reduced, and, as in the invention of Japanese Patent Application No. 61-61555, a sample atomization chamber and a plasma torch can be provided. It is possible to solve the problem that the switching valve provided at the position rusts due to the atmosphere in the stand and deteriorates the operation accuracy and hinders the analysis, and the reliability of the analysis is improved.
第1図は本発明のICP分析装置の一実施例を示す要部構
成図であり、第2図は本発明の分析方法を説明する図、
第3図は従来の分析方法を説明する図である。 1……アルゴンガスボンベ、10……誘導コイル 2……プラズマトーチ、18……試料霧化チェンバ 6,8……ガス供給管、14……高周波電源 16……ガスコントローラ、20……試料 22……キャリヤガス供給管 26……オン/オフバルブ 32……制御装置(シーケンスコントローラ)FIG. 1 is a block diagram of the essential parts showing an embodiment of the ICP analysis device of the present invention, and FIG. 2 is a diagram for explaining the analysis method of the present invention,
FIG. 3 is a diagram for explaining a conventional analysis method. 1 …… Argon gas cylinder, 10 …… Induction coil 2 …… Plasma torch, 18 …… Sample atomization chamber 6,8 …… Gas supply pipe, 14 …… High frequency power supply 16 …… Gas controller, 20 …… Sample 22… … Carrier gas supply pipe 26 …… ON / OFF valve 32 …… Control device (sequence controller)
Claims (1)
ラズマトーチに導入して発光させ、この光を分光測定し
て試料成分を分析する方法において、 待機時にはプラズマトーチへ供給するガスの量及び誘導
コイルへ供給する高周波電力を制御して口火プラズマを
維持するとともに試料霧化チェンバに供給するキャリヤ
ガスを遮断しておき、 分析に際してはプラズマトーチへ供給するガスの量及び
誘導コイルへ供給する高周波電力を増加させてプラズマ
出力を上昇させるとともに、試料霧化チェンバにキャリ
ヤガスを供給して試料を霧化しプラズマトーチに導入し
て測定を行ない、 プラズマ出力を上昇させた状態に保つとともに試料霧化
チェンバにキャリヤガスを供給して試料霧化チェンバの
洗浄を行ない、 試料霧化チェンバの洗浄終了後前記待機時の状態に戻る
ことを特徴とするICP分析方法。1. A method of introducing a sample atomized by a sample atomization chamber into a plasma torch to cause it to emit light, and spectroscopically measuring this light to analyze sample components, in the standby state, the amount of gas supplied to the plasma torch and The high-frequency power supplied to the induction coil is controlled to maintain the ignition plasma and the carrier gas supplied to the sample atomization chamber is shut off. During analysis, the amount of gas supplied to the plasma torch and the high-frequency supplied to the induction coil While increasing the electric power to increase the plasma output, a carrier gas is supplied to the sample atomization chamber to atomize the sample and introduce it into the plasma torch for measurement to maintain the increased plasma output and atomize the sample. After supplying the carrier gas to the chamber to clean the sample atomization chamber, after cleaning the sample atomization chamber An ICP analysis method characterized by returning to a standby state.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63217656A JPH0737945B2 (en) | 1988-08-30 | 1988-08-30 | ICP analysis method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63217656A JPH0737945B2 (en) | 1988-08-30 | 1988-08-30 | ICP analysis method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0264438A JPH0264438A (en) | 1990-03-05 |
| JPH0737945B2 true JPH0737945B2 (en) | 1995-04-26 |
Family
ID=16707667
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP63217656A Expired - Lifetime JPH0737945B2 (en) | 1988-08-30 | 1988-08-30 | ICP analysis method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0737945B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5355214A (en) * | 1990-08-31 | 1994-10-11 | Varian Associates, Inc. | Flow control device |
| US6222186B1 (en) | 1998-06-25 | 2001-04-24 | Agilent Technologies, Inc. | Power-modulated inductively coupled plasma spectrometry |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6275334A (en) * | 1985-09-30 | 1987-04-07 | Yokogawa Electric Corp | High frecquency induction bond plasma emission spectrosope |
| JPS63196841A (en) * | 1987-02-12 | 1988-08-15 | Shimadzu Corp | ICP emission spectrometer |
-
1988
- 1988-08-30 JP JP63217656A patent/JPH0737945B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0264438A (en) | 1990-03-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0211272A (en) | Load voltage detection system and pulse arc welding equipment, pulse laser beam machine and surface treating device using said detection system | |
| JP3800621B2 (en) | ICP analyzer | |
| EP0475636A2 (en) | Method and apparatus for analysis of gases using plasma | |
| JPH0737945B2 (en) | ICP analysis method | |
| JPH0640074B2 (en) | ICP analysis method | |
| JPH0368469A (en) | Method and device for plasma wire spraying | |
| JP3686198B2 (en) | Inductively coupled plasma mass spectrometer | |
| US5130537A (en) | Plasma analyzer for trace element analysis | |
| JPH09159610A (en) | Plasma analyzer equipped with sample introduction stabilization mechanism | |
| JPH06287739A (en) | Thermally spraying equipment | |
| JPWO2019012906A1 (en) | Plasma generator, emission spectrometer and mass spectrometer equipped with the same, and apparatus state determination method | |
| JPH0151939B2 (en) | ||
| JP2006153762A (en) | Sample analyzing method and sample analyzer | |
| JP3039231B2 (en) | Method and apparatus for rapid analysis of steel components | |
| JPH0886755A (en) | Method for using plasma gas | |
| DK1131181T3 (en) | Improved welding device and method of welding | |
| JPH0669629B2 (en) | Plasma torch pilot arc generation method | |
| EP0193821A2 (en) | In-situ analysis of a liquid conductive material | |
| US20250283828A1 (en) | Spark stand for optical emission spectrometry with improved dust removal | |
| JPS6317001Y2 (en) | ||
| JPH11153542A (en) | Cleaning method for plasma torch in ICP emission spectroscopy | |
| JP2677106B2 (en) | Emission spectroscopy method | |
| JPH052846Y2 (en) | ||
| JPS62175650A (en) | ICP emission spectroscopy method | |
| JPH10321182A (en) | Induction coupling plasma mass and spectral analysis device |