JPH0741525B2 - Production line management system - Google Patents
Production line management systemInfo
- Publication number
- JPH0741525B2 JPH0741525B2 JP10267187A JP10267187A JPH0741525B2 JP H0741525 B2 JPH0741525 B2 JP H0741525B2 JP 10267187 A JP10267187 A JP 10267187A JP 10267187 A JP10267187 A JP 10267187A JP H0741525 B2 JPH0741525 B2 JP H0741525B2
- Authority
- JP
- Japan
- Prior art keywords
- work
- worker
- time
- skill level
- data
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000004519 manufacturing process Methods 0.000 title claims description 10
- 238000000034 method Methods 0.000 claims description 36
- 230000015654 memory Effects 0.000 description 15
- 238000009958 sewing Methods 0.000 description 12
- 238000012545 processing Methods 0.000 description 7
- 230000003936 working memory Effects 0.000 description 3
- 230000002411 adverse Effects 0.000 description 2
- 238000012937 correction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000006870 function Effects 0.000 description 2
- 238000012549 training Methods 0.000 description 2
- 238000013459 approach Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 239000013256 coordination polymer Substances 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 239000004973 liquid crystal related substance Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G07—CHECKING-DEVICES
- G07C—TIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
- G07C3/00—Registering or indicating the condition or the working of machines or other apparatus, other than vehicles
- G07C3/08—Registering or indicating the production of the machine either with or without registering working or idle time
- G07C3/10—Registering or indicating the production of the machine either with or without registering working or idle time using counting means
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Sewing Machines And Sewing (AREA)
- Multi-Process Working Machines And Systems (AREA)
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
【発明の詳細な説明】 発明の目的 (産業上の利用分野) この発明は複数の作業工程を経て製品を分業生産するた
め、作業者に端末器を介して作業工程を順次指示する生
産管理システムに関するものである。DETAILED DESCRIPTION OF THE INVENTION (Industrial field of application) The present invention is a production control system for sequentially instructing a worker through a terminal device to sequentially perform a work process in order to separately manufacture a product through a plurality of work processes. It is about.
(従来の技術) 多種類のミシンを設置し、生産品目別に分業生産を行な
う縫製工場においては、品目別分業過程の各工程毎に一
定量の加工品の処理に必要な単位作業時間を予め設定
し、各分業過程に設けた制御装置が前記単位作業時間の
終了をもって作業者に対し次作業の開始を指示する。(Prior art) In a sewing factory where multiple types of sewing machines are installed and the division of labor is performed for each production item, the unit work time required to process a certain amount of processed products is preset for each process of the division of labor for each item. Then, the control device provided in each division of labor instructs the worker to start the next work at the end of the unit work time.
(発明が解決しようとする問題点) ところが、上記のシステムは単に時間的管理によって単
位作業の終了を決定するものであり、作業者個人の処理
能力は配慮しものではない。このため、養成中の作業者
等、熟練度の低い物が担当する部署において、作業に遅
延が生じ、所定時間内に単位作業が終了しない時、制御
装置の指示に基づく作業が行われず、当該工程のみなら
ず他工程の作業進行にも悪影響を与え、分業作業全体が
円滑に行われない虞れがある。(Problems to be Solved by the Invention) However, the above system merely determines the end of the unit work by time management, and does not consider the processing capability of each individual worker. For this reason, in a department such as a worker under training who is in charge of low skill, when the work is delayed and the unit work is not completed within the predetermined time, the work based on the instruction of the control device is not performed, Not only the process but also the progress of other processes may be adversely affected, and the entire division of labor may not be performed smoothly.
発明の構成 (問題点を解決するための手段) この発明は上記した問題点を解決するために、作業者に
指示された作業工程の技術度と、その作業工程を遂行す
る作業者の作業熟練度とを比較し、当該作業熟練度が前
記技術度の領域にあるか否かを判断する第1の判断手段
と、判断手段による判断の結果、前記作業者の作業熟練
度が技術度の領域にある場合には、前記作業工程に対し
予め設定された基準時間及び作業者の作業熟練度に基づ
いて熟練者用の必要作業時間を演算する第1の演算手段
と、判断手段による判断の結果、前記作業者の作業熟練
度が技術度の領域にない場合には、前記作業工程に対し
予め設定された基準時間及び作業者の作業熟練度に基づ
いて養成者用の必要作業時間を演算する第2の演算手段
と、第1又は第2の演算手段により演算された熟練者用
又は養成者用の必要作業時間を記憶する記憶手段と、そ
の記憶手段に記憶された必要作業時間を読み出し、その
必要作業時間と作業者が指示された作業工程を開始して
からの経過時間とに基づいて、作業者に作業工程が指示
されてから前記必要作業時間が経過したか否かを判断す
る第2の判断手段と、第2の判断手段により作業者に作
業工程が指示されてから前記必要作業時間が経過したこ
とが判断された時、新たな作業工程を指示する作業指示
手段とを備えたものである。Structure of the Invention (Means for Solving Problems) In order to solve the above-mentioned problems, the present invention relates to the technical level of the work process instructed by the worker and the work skill of the worker performing the work process. The degree of work skill of the worker is in the technical level area as a result of the determination by the first determination means for determining whether the work skill level is in the area of the technical level by comparing In the case of, the first calculation means for calculating the necessary work time for the expert based on the preset reference time for the work process and the work skill of the worker, and the result of the judgment by the judging means. If the work skill level of the worker is not within the technical skill range, the necessary work time for the trainer is calculated based on the reference time preset for the work process and the work skill level of the worker. Second computing means and first or second computing means The storage means for storing the required work time for the expert or trainer calculated by the above, and the required work time stored in the storage means are read out, and the work step instructed by the required work time and the operator is started. Second judging means for judging whether or not the required working time has elapsed after the worker is instructed of the work process based on the elapsed time after When it is determined that the required work time has elapsed since the work process was instructed, a work instruction means for instructing a new work process is provided.
(作用及び効果) この発明は上記した手段を採用したことにより、作業者
の熟練度に従って一作業工程の必要作業時間が熟練者用
又は養成者用の2種類の必要作業時間のいずれかに設定
され、この必要作業時間に従って次の作業工程が作業者
に指示される。よって、作業者の処理能力に適合する必
要作業時間内に所定量の作業が行なわれ、作業の遅延は
極めて少なくなり、分業作業全体が円滑に行われ得る。(Operation and effect) By adopting the above-described means, the present invention sets the required work time of one work process to either of two types of work time for the expert or the trainer according to the skill level of the operator. Then, the next work process is instructed to the worker according to the required work time. Therefore, a predetermined amount of work is performed within the required work time that matches the processing capacity of the worker, the work delay is extremely reduced, and the entire division of labor work can be smoothly performed.
(実施例) 以下、この発明の一実施例を図面に従って詳述する。Embodiment An embodiment of the present invention will be described in detail below with reference to the drawings.
縫製工場内には多種多用のミシン(図示しない)が設置
されており、生産品目毎に1つの分業生産用グループを
構成している。そして、第1図に示すように、各ミシン
に設置した端末器2が通信コントローラ3を介してホス
ト側の制御装置4に接続されている。Various sewing machines (not shown) are installed in the sewing factory, and one divisional production group is formed for each production item. Then, as shown in FIG. 1, the terminal device 2 installed in each sewing machine is connected to the control device 4 on the host side via the communication controller 3.
前記制御装置4は中央処理装置(CPU)と読出し専用メ
モリ(ROM)と読出し及び書込み専用メモリ(RAM)とか
ら構成され、ROMにはミシン別機能データ、ミシン番号
データ、作業優先順位データ、作業名データ、各作業の
技術度を表す技術度データ、作業者コードデータのリス
ト、各工程における1枚の加工布を縫製するに必要な時
間を秒単位で示す標準時間データ、生産品目毎のロット
ナンバーを示すデータが記憶されている。The control device 4 comprises a central processing unit (CPU), a read-only memory (ROM), and a read-write memory (RAM). The ROM has function data for each sewing machine, sewing machine number data, work priority data, and work data. Name data, skill level data showing the skill level of each work, list of worker code data, standard time data showing the time required to sew one work cloth in each process in seconds, lot for each production item Data indicating the number is stored.
そして、CPUはミシン別機能データに従って選択したミ
シン番号データに該当するミシンの端末器2に対し、作
業名データ、技術名データ、ロットナンバーデータ、作
業者コードデータリスト等の作業遂行に必要なデータ群
を出力するようになっている。Then, the CPU sends data such as work name data, technical name data, lot number data, worker code data list, etc. necessary for performing work to the terminal device 2 of the sewing machine corresponding to the sewing machine number data selected according to the function data for each sewing machine. It is designed to output a group.
第2図に示すように、前記端末器2には端末器用の中央
処理装置(以下CPUという)5が設けられ、同CPU5には
開始スイッチ6、終了スイッチ7、作業用メモリ8、プ
ログラムメモリ8a、磁気カードリーダー9、クロックカ
ウンタ10、液晶表示器11がそれぞれ接続されている。前
記CPU5により本発明の第1及び第2の演算手段並びに第
1及び第2の判断手段が構成され、作業用メモリ8によ
り本発明の記憶手段が構成されている。前記磁気カード
リーダー9は磁気カード12より入力される各種データを
読み取ってCPU5に出力するものであり、この磁気カード
12には作業者のコードデータ、作業者の保有技能デー
タ、各保有技能データ毎の技術的熟練度データ、さらに
はこの熟練度データに基づく熟練者用及び養成者用補正
率データが記録されている。As shown in FIG. 2, the terminal unit 2 is provided with a central processing unit (hereinafter referred to as CPU) 5 for the terminal unit, and the CPU 5 has a start switch 6, an end switch 7, a work memory 8 and a program memory 8a. , A magnetic card reader 9, a clock counter 10, and a liquid crystal display 11 are respectively connected. The CPU 5 constitutes the first and second calculating means and the first and second judging means of the present invention, and the working memory 8 constitutes the storage means of the present invention. The magnetic card reader 9 reads various data input from the magnetic card 12 and outputs the data to the CPU 5.
The code data of the worker, the skill data of the worker, the technical skill level data for each skill level data, and the correction rate data for the skilled worker and the trainer based on this skill level data are recorded in 12. There is.
前記作業用メモリ8は読出し及び書込み可能なメモリで
あり、制御装置4から入力された当該ミシンの操作能力
を備えた作業者のコードデータのリスト、技術度デー
タ、標準時間データが記憶されるようになっている。ま
た、プログラムメモリ8aは読出し専用メモリが使用さ
れ、CPU5が制御装置4に対し作業指示要求信号を出力す
る時間を表す作業指示要求時間データ及びCPU5の動作プ
ログラムが記憶されている。さらに、クロックカウンタ
10は分単位での時間計測を行い、この計測値をCPU5に出
力する。The work memory 8 is a readable and writable memory, and stores a list of code data of a worker having the operating ability of the sewing machine, the technical level data, and the standard time data input from the control device 4. It has become. A read-only memory is used as the program memory 8a, and the work instruction request time data representing the time at which the CPU 5 outputs the work instruction request signal to the control device 4 and the operation program of the CPU 5 are stored. In addition, the clock counter
10 measures the time in minutes, and outputs the measured value to the CPU 5.
そして、磁気カード12からCPU5に作業者名データ13が入
力されると、CPU5は作業用メモリ8から作業者コードデ
ータリストを読出し、同リストにコードデータがある場
合には磁気カード12を保持する作業者が当該工程に必要
な技能を備えていることを確認する。When the worker name data 13 is input from the magnetic card 12 to the CPU 5, the CPU 5 reads the worker code data list from the work memory 8 and holds the magnetic card 12 when the list contains code data. Make sure that the workers have the necessary skills for the process.
また、磁気カード12のデータ群が磁気カードリーダー9
にて読込まれ、作業用メモリ8に格納される。また、CP
U5は作業用メモリ8から標準時間データ及びロッドナン
バーデータに基づく数量データを読出し、標準時間と数
量とを乗ずる計算にて当該作業工程に必要な基準時間を
予め求め、さらにこの基準時間に熟練者用又は養成者用
補正率を乗じて、基準時間を作業者の熟練度に適合する
ように調整したのち、この値を60で割ることにより必要
時間を分単位に変換して必要作業時間を演算する。そし
て、クロックカウンタ10の分単位の計測値を前記必要作
業時間から減じ、この値を常に作業名、ロットナンバー
とともに表示器11に表示させて、作業者に必要作業時間
の減少を認識させる。The data group of the magnetic card 12 is the magnetic card reader 9
Read in and stored in the work memory 8. Also, CP
U5 reads the standard time data and the quantity data based on the rod number data from the working memory 8, finds the reference time required for the work process in advance by the calculation of multiplying the standard time and the quantity, and further the expert time at this reference time. After adjusting the reference time to match the skill level of the worker by multiplying the correction rate for training or trainers, divide this value by 60 to convert the required time into minutes and calculate the required working time To do. Then, the minute-measured value of the clock counter 10 is subtracted from the required work time, and this value is constantly displayed on the display unit 11 together with the work name and lot number so that the worker recognizes the decrease in the necessary work time.
一方、プログラムメモリ8aに記憶された作業指示要求時
間データはCPU5にて作業用メモリ8に格納され、CPU5が
前記クロックカウンタ10の減算動作に基づいて、必要作
業時間の終了直前の作業指示要求時間に達したことを認
識すると、CPU5は制御装置4に作業指示要求信号を出力
する。すると、制御装置4は前記作業指示要求信号に基
づいて、ROM内の各種データに従い作業者が次になすべ
き作業名及び作業場所を検索し、この結果に基づいて作
業指示信号を端末器2に出力し、これが表示器11に表示
される。On the other hand, the work instruction request time data stored in the program memory 8a is stored in the work memory 8 by the CPU 5, and the CPU 5 determines the work instruction request time immediately before the end of the required work time based on the subtraction operation of the clock counter 10. When the CPU 5 recognizes that it has reached, the CPU 5 outputs a work instruction request signal to the control device 4. Then, the control device 4 searches for the work name and work place to be performed next by the worker based on the various data in the ROM based on the work instruction request signal, and based on the result, sends the work instruction signal to the terminal device 2. It is output, and this is displayed on the display unit 11.
さて、上記のように構成した生産ライン管理システムの
作用を第3図のフローチャートに従って以下に述べる。Now, the operation of the production line management system configured as described above will be described below with reference to the flowchart of FIG.
作業者が磁気カード12を磁気カードリーダ9にて読込ま
せると、その磁気カード12のデータがCPU5に入力され、
ステップS1(以下ステップを単にSという)において、
作業者コードデータが作業用メモリ8に記憶された作業
者コードデータリスト内にあることを確認する。作業者
コードデータがデータリスト内に存在しない場合、適切
な磁気カード12のデータが磁気カードリーダー9にて読
込まれるまで待機する。作業者コードデータをデータリ
ストにて確認した場合、S2で作業者が開始スイッチ6を
操作すると、S3でCPU5は当該工程の技術度を作業用メモ
リ8から読み込む。すると、S4において、この技術度と
磁気カード12から入力された作業者の技術的熟練度とを
比較し、当該作業工程における作業者の処理能力が熟練
領域にあるか否かを判断する。作業者の処理能力が熟練
領域にある時にはS5において、熟練者用の必要作業時間
が演算され、熟練領域に達していない時にはS9にスキッ
プして養成者用の必要作業時間が演算される。When the operator reads the magnetic card 12 with the magnetic card reader 9, the data of the magnetic card 12 is input to the CPU 5,
In step S1 (hereinafter step is simply referred to as S),
It is confirmed that the worker code data is in the worker code data list stored in the work memory 8. If the operator code data does not exist in the data list, the magnetic card reader 9 waits until the appropriate data on the magnetic card 12 is read. When the worker code data is confirmed in the data list, when the worker operates the start switch 6 in S2, the CPU 5 reads the skill level of the process from the work memory 8 in S3. Then, in S4, this technical level is compared with the technical level of skill of the operator input from the magnetic card 12, and it is determined whether or not the processing capacity of the worker in the work step is in the skilled area. When the processing capacity of the worker is in the skill area, the necessary work time for the expert is calculated in S5, and when it does not reach the skill area, the process is skipped to S9 and the necessary work time for the trainer is calculated.
このあと、S6において必要作業時間が作業用メモリ8に
記憶され、次いでクロックカウンタ10の計測動作に基づ
いて、S7にて必要作業時間の終了より所定時間前の作業
指示要求時間に達したか否かが判断される。そして、こ
の判断結果がNOの時にはS10で必要作業時間からクロッ
クカウンタ10の計算値が減じられた後にS7に復帰し、作
業指示要求時間に到達したことを確認するまで同一の動
作が繰り返される。そして、S7における判断結果がYES
の場合にはS8において、制御装置4に対し作業指示要求
信号が出力される。なお、S10における減算値は表示器1
1に分単位で逐一表示されるため、作業者は当該工程遂
行に必要な残余時間を黙視確認することができる。After that, the required work time is stored in the work memory 8 in S6, and then, based on the measurement operation of the clock counter 10, it is determined in S7 whether or not the work instruction request time, which is a predetermined time before the end of the required work time, is reached. Is determined. Then, when the result of this determination is NO, the process returns to S7 after the calculated value of the clock counter 10 is subtracted from the required work time in S10, and the same operation is repeated until it is confirmed that the work instruction request time has been reached. Then, the determination result in S7 is YES
In this case, in S8, a work instruction request signal is output to the control device 4. The subtracted value in S10 is
Since it is displayed in 1 minute by minute, the operator can visually check the remaining time required to perform the process.
端末器2の上記した動作が終了に近づくと、制御装置4
は端末器2から送られ作業指示要求信号に基づいて、作
業者の次になすべき作業を検索し、これに関する情報を
表示器11に表示して作業者に知らせるとともに、次作業
に使用されるミシンの端末器2に工程遂行のための各種
データを出力する。この動作は必要作業時間の終了前に
行われるため、作業者は当該工程の終了に先立って、次
工程に関する情報を得ることができ、次工程への移行は
時間的な無駄を省き、円滑な状態で行われる。When the above-described operation of the terminal 2 approaches the end, the control device 4
Is used for the next work while searching the work to be performed next by the worker based on the work instruction request signal sent from the terminal device 2 and displaying the information on this on the display 11 to inform the worker. Various data for performing the process are output to the terminal device 2 of the sewing machine. Since this operation is performed before the end of the required work time, the worker can obtain information about the next process prior to the end of the process, and the transition to the next process saves time waste and is smooth. Done in the state.
上記したように、この実施例においては当該工程におけ
る作業者の処理能力を考慮して、熟練度の低い作業者に
も無理のない作業指示要求時間のタイミングが調整され
る。従って、当該工程における作業の遅延が回避され、
他工程に悪影響を与えることはない。As described above, in this embodiment, the timing of the work instruction request time is adjusted in consideration of the processing ability of the worker in the process so that even a worker with a low degree of skill is not unreasonable. Therefore, work delay in the process is avoided,
It does not adversely affect other processes.
第1図はこの発明におけるホスト側制御装置と端末器と
の接続を示す説明図、第2図は電気的構成を示すブロッ
グ図、第3図はCPUの動作を示すフローチャートであ
る。 図において、2は端末器、5は第1及び第2の演算手段
並びに第1及び第2の判断手段を構成するCPU、8は記
憶手段を構成する作業用メモリである。FIG. 1 is an explanatory diagram showing the connection between the host-side control device and the terminal device in the present invention, FIG. 2 is a blog diagram showing the electrical configuration, and FIG. 3 is a flowchart showing the operation of the CPU. In the figure, 2 is a terminal device, 5 is a CPU constituting the first and second calculating means and the first and second judging means, and 8 is a working memory constituting a storing means.
Claims (1)
ため、作業者に端末器を介して作業工程を順次指示する
生産管理システムにおいて、 作業者に指示された作業工程の技術度と、その作業工程
を遂行する作業者の作業熟練度とを比較し、当該作業熟
練度が前記技術度の領域にあるか否かを判断する第1の
判断手段と、 判断手段による判断の結果、前記作業者の作業熟練度が
技術度の領域にある場合には、前記作業工程に対し予め
設定された基準時間及び作業者の作業熟練度に基づいて
熟練者用に必要作業時間を演算する第1の演算手段と、 判断手段による判断の結果、前記作業者の作業熟練度が
技術度の領域にない場合には、前記作業工程に対し予め
設定された基準時間及び作業者の作業熟練度に基づいて
養成者用の必要作業時間を演算する第2の演算手段と、 第1又は第2の演算手段により演算された熟練者用又は
養成者用の必要作業時間を記憶する記憶手段と、 その記憶手段に記憶された必要作業時間を読み出し、そ
の必要作業時間と作業者が指示された作業工程を開始し
てからの経過時間とに基づいて、作業者に作業工程が指
示されてから前記必要作業時間が経過したか否かを判断
する第2の判断手段と、 第2の判断手段により作業者に作業工程が指示されてか
ら前記必要作業時間が経過したことが判断された時、新
たな作業工程を指示する作業指示手段と、 を備えたことを特徴とする生産ライン管理システム。1. A production management system for sequentially instructing a worker through a terminal device in order to separately produce a product through a plurality of work processes, wherein the technical level of the work process instructed by the worker, A first judging means for judging whether or not the working skill level of the worker performing the work process is in the range of the skill level, and the result of the judgment by the judging means, When the work skill level of the worker is in the range of the skill level, the necessary work time is calculated for the expert based on the reference time preset for the work process and the work skill level of the worker. When the work skill level of the worker is not in the technical skill range as a result of the judgment by the calculating means and the judging means, the work time is based on the reference time preset for the work process and the work skill level of the worker. Performance time required for trainers And a storage means for storing the required work time for the expert or trainer calculated by the first or second calculation means, and the required work time stored in the storage means , Determining whether or not the required work time has passed since the worker was instructed to perform the work process, based on the required work time and the elapsed time after the worker started the instructed work process. A second determining means, and a work instructing means for instructing a new work step when it is determined that the required work time has elapsed after the worker has instructed the work step by the second determining means. A production line management system characterized by being equipped.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10267187A JPH0741525B2 (en) | 1987-04-24 | 1987-04-24 | Production line management system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10267187A JPH0741525B2 (en) | 1987-04-24 | 1987-04-24 | Production line management system |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS63267149A JPS63267149A (en) | 1988-11-04 |
| JPH0741525B2 true JPH0741525B2 (en) | 1995-05-10 |
Family
ID=14333696
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP10267187A Expired - Lifetime JPH0741525B2 (en) | 1987-04-24 | 1987-04-24 | Production line management system |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0741525B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2024048053A1 (en) * | 2022-08-29 | 2024-03-07 | 株式会社神戸製鋼所 | Work procedure creation system, work procedure creation method, and recording medium for maintenance of production property machinery |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5212635A (en) * | 1989-10-23 | 1993-05-18 | International Business Machines Corporation | Method and apparatus for measurement of manufacturing technician efficiency |
| CN103455013A (en) * | 2013-09-12 | 2013-12-18 | 苏州瑞光电子有限公司 | Intelligent electronic control system of garment production line and operation method thereof |
| JP2017182131A (en) * | 2016-03-28 | 2017-10-05 | ブラザー工業株式会社 | Server device and terminal device specification method |
| JP7119687B2 (en) * | 2018-07-18 | 2022-08-17 | コニカミノルタ株式会社 | Work process control system, work process control method, and work process control program |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6063613A (en) * | 1983-09-16 | 1985-04-12 | Mitsubishi Electric Corp | Production grating system |
-
1987
- 1987-04-24 JP JP10267187A patent/JPH0741525B2/en not_active Expired - Lifetime
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2024048053A1 (en) * | 2022-08-29 | 2024-03-07 | 株式会社神戸製鋼所 | Work procedure creation system, work procedure creation method, and recording medium for maintenance of production property machinery |
| JP2024032260A (en) * | 2022-08-29 | 2024-03-12 | 株式会社神戸製鋼所 | Work procedure creation system, work procedure creation method, and program for maintenance of production goods machinery |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS63267149A (en) | 1988-11-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0449020A (en) | Molding monitor device | |
| JPH0741525B2 (en) | Production line management system | |
| JP2544960B2 (en) | Programmable controller | |
| JPH0685121B2 (en) | Control device | |
| JP2623566B2 (en) | Sorting instruction device for production system | |
| JP2676512B2 (en) | Program restart method | |
| JP2663540B2 (en) | Programmable controller | |
| JPS63267394A (en) | production line management system | |
| JPH067396Y2 (en) | Production management information processing equipment in a sewing factory | |
| JPS63194921A (en) | Injection molder changing color of alarm display in response to kind of alarm | |
| JPH083725B2 (en) | Abnormality diagnostic device for sequence controller | |
| JP3032319B2 (en) | Vending machine control device | |
| JPH0751659Y2 (en) | Vending machine controller | |
| JP2550580B2 (en) | Programmable controller failure diagnosis device | |
| JPH056216A (en) | Robot controller | |
| JPH04305740A (en) | Method for displaying processing status | |
| JPH067395Y2 (en) | Scheduled work completion time display | |
| JPH0584374A (en) | Allocation time calculating system for each process in sewing factory and device therefor | |
| JP2000207003A (en) | Programmable controller | |
| JPS61184609A (en) | Method for displaying situation of working progress | |
| JP2737489B2 (en) | Numerical control unit | |
| JPS59188702A (en) | Programmable controller | |
| JP3132591B2 (en) | Work volume accumulator | |