JPH0749680B2 - Construction method of precast steel reinforced concrete structure - Google Patents
Construction method of precast steel reinforced concrete structureInfo
- Publication number
- JPH0749680B2 JPH0749680B2 JP31945888A JP31945888A JPH0749680B2 JP H0749680 B2 JPH0749680 B2 JP H0749680B2 JP 31945888 A JP31945888 A JP 31945888A JP 31945888 A JP31945888 A JP 31945888A JP H0749680 B2 JPH0749680 B2 JP H0749680B2
- Authority
- JP
- Japan
- Prior art keywords
- column
- reinforced concrete
- steel
- sleeve
- pillar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明はプレキヤスト鉄骨鉄筋コンクリート構造物の構
築工法に係るものである。TECHNICAL FIELD The present invention relates to a construction method for a precast steel-framed reinforced concrete structure.
(従来の技術) 従来、鉄骨鉄筋コンクリート構造における躯体の施工に
際しては、1節の鉄骨柱に梁の一部を構成する接合部を
突設してなる鉄骨柱と、横架材の鉄骨梁、鉄骨小梁等を
予め工場で加工し、現場に搬入後、揚重機によって柱、
梁、小梁の順に建方を行ない、下層より柱主筋、フープ
の配筋、梁、小梁鉄筋を配筋した後、柱、梁、小梁、床
の型枠を組立て、床鉄筋の配筋後コンクリートを打設し
て順次上層の躯体を構築していく方法と、前記の工場加
工に加えて梁をPC化したり、床に各種の省力化工法を適
用した複合工法とが採用されている。(Prior Art) Conventionally, when constructing a frame in a steel-framed reinforced concrete structure, a steel-framed column formed by projecting a joint part forming a part of the beam to the steel-framed column of section 1, a steel-framed beam of a transverse member, a steel frame After processing small beams in advance at the factory and bringing them to the site, the pillars are lifted by a lifting machine.
After constructing the beams and girders in this order, and after arranging the column main bars, hoop reinforcements, beams, and girder reinforcements from the lower layer, assemble the columns, beams, girders, and floor formwork, and arrange the floor reinforcements. The method of placing concrete after reinforcement and constructing the upper-layer frame one by one, and the composite construction method in which beams are made into PC and various labor-saving construction methods are applied to the floor in addition to the above factory processing are adopted. There is.
(発明が解決しようとする課題) しかしながら前記従来工法では、前者のように鉄骨の加
工以外はすべて鉄骨建方工、鉄筋工、型枠工による現場
作業となり、また後者のように一部の部材をPC化しても
まだ現場作業が多く残っている。(Problems to be solved by the invention) However, in the above-mentioned conventional method, except for the processing of the steel frame as in the former, all work is done by steel frame erection work, rebar work, and formwork work. There is still a lot of work left to do even if the computer is turned into a PC.
このような現場作業は未だに多くの職種と労力とに頼っ
ているが、近年、慢性的に建設従事者と特殊技能量が不
足しており、所期の性能の確保、適正な工程管理、安全
管理が困難であるという問題点がある。Such field work still relies on many types of work and labor, but in recent years, there has been a chronic shortage of construction workers and special skills, ensuring the desired performance, proper process control, and safety. There is a problem that it is difficult to manage.
本発明は前記従来技術の有する問題点に鑑みて提案され
たもので、その目的とする処は、柱、梁のみならず柱梁
接合部をもPC化して、現場作業の省力化と建設従事者と
熟練工の不足を解消し、所期の性能を確保しうるプレキ
ヤスト鉄骨鉄筋コンクリート構造物の構築工法及び構築
用部材を提供する点にある。The present invention has been proposed in view of the above problems of the prior art, and the purpose thereof is to reduce the number of pillars and beams, as well as the column-beam joints to PC, to save labor in the field work and to carry out construction work. It is to provide a construction method and a construction member for a precast steel-framed reinforced concrete structure capable of solving the shortage of workers and skilled workers and ensuring the desired performance.
(課題を解決するための手段) 前記の目的を達成するため、本発明に係る構築工法は、
柱の上下端部には柱鉄骨の上下端部を囲繞する接合用ボ
ックスが、下端部には柱主筋接合用スリーブが夫々埋設
され、且つ同スリーブに接続された柱主筋の上端部が柱
上方に突出されたプレキャスト鉄骨鉄筋コンクリート柱
部材を所定位置にセットしたのち、柱鉄骨の上下突出端
部にはスタッドボルトが植立され、同柱鉄骨の中央部か
ら鉄骨梁の一部が突設されるとともに、柱主筋貫通用垂
直スリーブ及び梁上端筋貫通用水平スリーブが埋設され
た前記柱部材と同一断面のプレキャスト鉄骨鉄筋コンク
リート柱梁接合部材における前記柱鉄骨下端突出端部
を、前記柱部材の上部接合用ボックスに嵌合するととも
に、同柱部材の上端から突出した柱主筋を前記柱梁接合
部材の上端部より突出するように、同接合部材内の柱主
筋貫通用垂直スリーブに貫通し、同柱主筋貫通用垂直ス
リーブ及び前記接合用ボックスに無収縮モルタルを注入
するように構成されている。(Means for Solving the Problems) In order to achieve the above object, the construction method according to the present invention is
In the upper and lower ends of the pillar, there are joint boxes surrounding the upper and lower ends of the pillar steel frame, and in the lower end, there are embedded columns for connecting the main columns of the columns, and the upper ends of the main columns of the columns connected to the sleeves are above the columns. After setting the precast steel reinforced concrete column member protruding in the predetermined position, stud bolts are erected at the vertically protruding ends of the column steel frame, and a part of the steel beam is projected from the center of the column steel frame. Along with the column main member penetrating lower end projecting end of the precast steel-framed reinforced concrete column-beam joining member having the same cross-section as the pillar member in which the vertical main-column-penetrating penetrating vertical sleeve and the beam upper-end-piercing horizontal sleeve are embedded, A vertical three-column vertical penetration rod for penetrating the column main bar in the joint member so that the column main bar protruding from the upper end of the column member protrudes from the upper end of the column-beam joint member. Penetrate into, and is configured to inject a non-shrink mortar in the pillar main reinforcement through vertical sleeve and said junction boxes.
請求項2の発明は前記プレキャスト鉄骨鉄筋コンクリー
ト柱梁接合部材における柱鉄骨の中央部より突設された
鉄骨梁に、プレキャスト鉄骨鉄筋コンクリート梁を接合
し、同プレキャスト鉄骨鉄筋コンクリート梁の上端筋を
前記柱梁接合部材の梁上端筋貫通用水平スリーブに貫通
するとともに、同スリーブに無収縮モルタルを注入する
ように構成されている。The invention of claim 2 joins the precast steel-reinforced concrete beam to the steel beam projecting from the central portion of the column steel in the precast steel-reinforced concrete beam-column joining member, and joins the upper end bars of the precast steel-reinforced concrete beam to the beam-column joint. It is configured to penetrate a horizontal sleeve for penetrating the beam upper end of the member and to inject non-shrink mortar into the sleeve.
(作用) 本発明によれば前記したように、プレキヤスト鉄骨鉄筋
コンクリート柱部材の上下端部に埋設された柱鉄骨を囲
繞する接合用ボツクスに、プレキヤスト鉄骨鉄筋コンク
リート柱梁接合部材における上下端のスタツドボルトが
植立された柱鉄骨の突出端部が嵌合され、無収縮モルタ
ルが注入されるので、各鉄骨が負担する軸力は、鉄骨に
植立されたスタツドボルトとモルタルとの間の支圧力及
び付着力で伝達され、更に同付着力はモルタルと鉄骨へ
摩擦力として伝達される。(Operation) According to the present invention, as described above, in the joining box surrounding the pillar steel frames embedded in the upper and lower ends of the precast steel reinforced concrete column member, the stud bolts at the upper and lower ends of the precast steel reinforced concrete column beam joining member are provided. Since the projecting end of the pillared steel frame is fitted and the non-shrinking mortar is injected, the axial force borne by each steel frame depends on the supporting pressure between the stud bolt and the mortar that are planted on the steel frame. The adhesive force is transmitted, and the adhesive force is transmitted to the mortar and the steel frame as a frictional force.
また曲げモーメントは、曲げ軸に平行な鉄骨フランジと
モルタルとの付着力で、更に部材の剪断力は前記スタツ
ドボルトとモルタルとの付着力を通じて、モルタルと柱
鉄骨との摩擦力で伝達され、かくして前記プレキヤスト
鉄骨鉄筋柱部材及び柱梁接合部材が一体的に接合され
る。The bending moment is the adhesive force between the mortar and the steel frame flange parallel to the bending axis, and the shearing force of the member is transmitted by the frictional force between the mortar and the column steel frame through the adhesive force between the stud bolt and the mortar, thus The precast steel rebar column member and the beam-column joint member are integrally joined.
更に同柱梁接合部材に埋設された柱主筋貫通用垂直スリ
ーブに、前記柱部材の下端部に埋設された柱主筋接合用
スリーブの上端突出部を貫通し、前記柱主筋貫通用垂直
スリーブに無収縮モルタルを注入することによって前記
柱部材及び柱梁接合部材に亘って柱主筋が一体的に埋設
され、更に同柱主筋の前記柱梁接合部材からの上端突出
部を、上層のプレキヤスト鉄骨鉄筋コンクリート柱部材
における柱主筋接合用スリーブに装着し、同スリーブに
無収縮モルタルを注入することによって、上階層と下階
層のプレキヤスト鉄骨鉄筋コンクリート柱部材が、前記
柱梁接合部材を介して接合される。In addition, a vertical main sleeve penetrating vertical sleeve embedded in the same column-beam connecting member penetrates the upper end protruding portion of the main column connecting bar embedded in the lower end of the column member, and By injecting shrinkage mortar, the column main bar is integrally embedded over the column member and the beam-column joint member, and the upper end projecting portion of the column main bar from the column-beam joint member is an upper layer precast cast steel reinforced concrete column. The precast cast steel-framed reinforced concrete column members of the upper layer and the lower layer are joined to each other through the beam-column joining member by mounting the column main-bar joining sleeve in the member and injecting non-shrink mortar into the sleeve.
請求項2の発明によれば、前記プレキャスト鉄骨鉄筋コ
ンクリート柱梁接合部材における柱鉄骨の中央部より突
設された鉄骨梁にプレキャスト鉄骨鉄筋コンクリート梁
を接合するとともに、同プレキャスト鉄骨鉄筋コンクリ
ート梁における梁上端筋を前記プレキャスト鉄骨鉄筋コ
ンクリート柱梁接合部材に埋設された梁上端筋貫通用水
平スリーブに貫通し、同シリーブに無収縮モルタルを注
入することによって、前記プレキャスト鉄骨鉄筋コンク
リート柱梁接合部材を介して、プレキャスト鉄骨鉄筋コ
ンクリート梁がプレキャスト鉄骨鉄筋コンクリート柱に
一体的に接合されるものである。According to the invention of claim 2, the precast steel-reinforced concrete beam is joined to the steel beam projecting from the central portion of the column steel in the precast steel-reinforced concrete beam-joining member, and the beam upper end bar in the precast steel-reinforced concrete beam is connected. The precast steel-framed reinforced concrete column-beam joint member is pierced through a beam upper end piercing horizontal sleeve embedded in the beam-joint member, and by injecting non-shrinkable mortar into the sieve, the precast steel-framed reinforced concrete column-beam joint member is used to precast steel-framed reinforced concrete Beams are integrally joined to precast steel reinforced concrete columns.
(実施例) 以下本発明を図示の実施例について説明する。(Examples) The present invention will be described below with reference to illustrated examples.
(A)はプレキヤスト鉄骨鉄筋コンクリート柱で、上下
両端部に、柱鉄骨(1)の上下端部を囲繞する接合用ボ
ツクス(2)が埋設され、同ボツクス(2)は前記柱鉄
骨(1)に溶接(w)される。(第7図及び第8図参
照)更に柱主筋の下端部位置に柱主筋接合用スリーブ
(3)が埋設され、同スリーブ(3)に接合された柱主
筋(4)は柱上端面より上部階にまで突設されるととも
に、フープ筋(5)が配筋されている。(A) is a precast steel-framed reinforced concrete column, and at the upper and lower ends thereof, a bonding box (2) surrounding the upper and lower ends of the column steel frame (1) is embedded, and the box (2) is attached to the column steel frame (1). Welded (w). (See FIGS. 7 and 8) Further, a column main bar connecting sleeve (3) is embedded in the lower end position of the column main bar, and the column main bar (4) joined to the sleeve (3) is above the upper end face of the column. The hoop streak (5) is laid out while protruding up to the floor.
(B)はプレキヤスト鉄骨鉄筋コンクリート柱梁接合部
材で、柱鉄骨(6)の上下突出端部(6a)にはスタツド
ボルト(7)が植立され、前記柱鉄骨(6)の中間部か
らはX、Y両方向に突設された鉄骨梁(8)があり、更
に柱主筋貫通用垂直スリーブ(9)及び梁上端筋貫通用
水平スリーブ(10)が埋設されている。(B) is a precast steel-framed reinforced concrete beam-column joint member, in which a stud bolt (7) is erected on the vertically projecting end (6a) of the column steel frame (6), and X from the middle part of the column steel frame (6). , A steel frame beam (8) protruding in both Y directions, and a vertical sleeve (9) for penetrating the column main bar and a horizontal sleeve (10) for penetrating the beam upper end bar are embedded.
而して前記柱部材(A)の下端部の接合用ボツクス
(2)に下層階の柱梁接合部材(B)の上端部の柱鉄骨
突出端部(6a)を嵌合するとともに、柱主筋(4)の突
出端部を前記柱部材(A)の柱主筋接合用スリーブ
(3)に嵌合し、同スリーブ(3)と前記接合用ボツク
ス(2)とに無収縮モルタル(a)を充填して、前記柱
部材(A)を下層階の柱梁接合部材(B)とを一体化
し、同接合部材(B)を介して下層階の柱部材と接合す
る。Then, the pillar steel frame projecting end (6a) at the upper end of the column-beam joining member (B) on the lower floor is fitted into the joining box (2) at the lower end of the column member (A), and the pillar main bar The projecting end of (4) is fitted to the column main-bar joining sleeve (3) of the column member (A), and a non-shrink mortar (a) is placed between the sleeve (3) and the joining box (2). By filling, the pillar member (A) is integrated with the pillar-beam joining member (B) on the lower floor, and is joined to the pillar member on the lower floor through the joining member (B).
而して前記柱部材(A)の上端部の接合用ボツクス
(2)に柱梁接合部材(B)の下端部の柱鉄骨突出端部
(6a)を嵌合するとともに、前記柱部材(A)における
柱主筋(4)の突出端部を前記柱梁接合部材(B)の柱
主筋貫通用垂直スリーブ(9)に貫通し、同スリーブ
(9)及び前記接合用ボツクス(2)に無収縮モルタル
(a)を充填して、前記柱部材(A)と柱梁接合部材
(B)とを一体に接合する。Thus, the pillar steel frame projecting end portion (6a) at the lower end of the beam-column joining member (B) is fitted into the joining box (2) at the upper end portion of the column member (A), and the pillar member (A ), The projecting end of the column main bar (4) is penetrated into the column main beam penetrating vertical sleeve (9) of the beam-column joining member (B), and the sleeve (9) and the box (2) for joining do not shrink. The column member (A) and the beam-column joining member (B) are integrally joined by filling the mortar (a).
前記モルタル(a)の硬化後、プレキヤスト鉄骨鉄筋コ
ンクリート梁(C)の梁鉄骨(11)と前記柱梁接合部材
(B)の突設された鉄骨梁(8)とを接合板(12)及び
ボルト(13)を介して接合し、更に前記梁(C)部分に
おいてはスラブ板の設置と平行して、下端梁筋(14)
(S)を接合するとともに、梁上端筋(15)を前記柱梁
接合部材(B)の梁上端筋貫通用水平スリーブ(10)を
貫通するように配設し、同スリーブ(10)に無収縮モル
タルを注入し、型枠組立て後、梁の上部コンクリート及
び接続コンクリートを打設する。図中(16)はスタラツ
プ(8a)はボルト孔である。After hardening of the mortar (a), the beam steel frame (11) of the precast steel-framed reinforced concrete beam (C) and the projecting steel beam (8) of the beam-column joining member (B) are joined together by a joint plate (12) and bolts. (13), and at the beam (C) part, parallel to the installation of the slab plate, the lower beam beam (14)
(S) is joined, and the beam upper end streak (15) is arranged so as to penetrate the beam upper end streak penetrating horizontal sleeve (10) of the beam-column joining member (B). After injecting shrinkage mortar and assembling the form, the concrete above the beam and the connecting concrete are placed. In the figure, (16) is a tap (8a), which is a bolt hole.
以下前記同様の工程を反覆してプレキヤスト鉄骨鉄筋コ
ンクリート構造物を構築する。Thereafter, the same steps as described above are repeated to construct a precast steel-framed reinforced concrete structure.
なお第10図は本発明の他の実施例を示し、前記柱部材
(A)と柱梁接合部材(B)とを合体し、1層階のPC梁
付PC柱(A1)としたもので、同柱(A1)の下端に接合用
ボツクス(2)が埋設され、上端部は柱鉄骨(6)の突
出端部(6a)によって上層の柱部材と接合するように構
成されている。FIG. 10 shows another embodiment of the present invention, in which the column member (A) and the beam-column joining member (B) are combined to form a PC column with a PC beam (A 1 ) on the first floor. Then, a box (2) for joining is embedded in the lower end of the same column (A 1 ), and the upper end is configured to be joined to the upper column member by the projecting end (6 a) of the column steel frame (6). .
第11図は本発明の更に他の実施例を示し、柱(A2)は複
数層の柱接合部材(B)を具えた複数階の柱に構成され
ている。FIG. 11 shows still another embodiment of the present invention, in which the pillar (A 2 ) is a pillar of a plurality of floors having a plurality of layers of the column joining member (B).
(発明の効果) 本発明によれば前記したように、プレキヤスト鉄骨鉄筋
コンクリート柱部材の上下端に埋設された接合用ボツク
スに、プレキヤスト鉄骨鉄筋コンクリート柱梁接合部材
の柱鉄骨におけるスタツドボルトの植立された端部突出
部を嵌合するとともに、同接合部材に埋設された柱主筋
貫通用垂直スリーブに前記柱部材における柱主筋接合用
スリーブに接続された柱主筋突出部を貫通し、同スリー
ブ及び前記接合用ボツクスに無収縮モルタルを注入する
ことによって前記柱部材と柱梁接合部材とを一体化し、
プレキヤスト鉄骨鉄筋コンクリート柱部材のみならずそ
の柱梁接合部までプレハブ化し、プレキヤスト鉄骨鉄筋
コンクリート構造物をより合理的に施工できるように
し、現場作業の省力化、工数の低減を図り、建設従事者
と特殊技能員の不足や工程の遅延、精度の低下をなく
し、作業の安全性を向上しうるものである。(Effects of the Invention) According to the present invention, as described above, in the joining boxes embedded in the upper and lower ends of the precast steel reinforced concrete column member, the stud bolts are erected in the column steel frame of the precast steel reinforced concrete column beam joining member. While fitting the end protrusions, the column main bar penetrating protrusions connected to the column main bar connecting sleeves in the column members are passed through the column main bar penetrating vertical sleeves embedded in the joint members, and the sleeves and the joints The column member and the beam-column joining member are integrated by injecting non-shrink mortar into the box for use,
Precast steel reinforced concrete column members as well as beam-column joints are prefabricated so that precast steel reinforced concrete structures can be constructed more rationally, labor is saved on site, and man-hours are reduced. It is possible to improve work safety by eliminating the shortage of personnel, the delay of processes, and the deterioration of accuracy.
請求項2の発明は、前記プレキャスト鉄骨鉄筋コンクリ
ート柱梁接合部材における柱鉄骨の中間より突設された
鉄骨梁に、プレキャスト鉄骨鉄筋コンクリート梁を接合
し、同梁の上端筋を前記柱梁接合部材の梁上端筋貫通用
水平スリーブに貫通し、同スリーブに無収縮モルタルを
注入することによってプレキヤスト鉄骨鉄筋コンクリー
ト柱梁を確固と接合しうるものであり、現場作業の省力
化を図り施工能率を向上し、施工精度を改善しうるもの
である。In the invention of claim 2, the precast steel-reinforced concrete beam is joined to the steel beam projecting from the middle of the column steel in the precast steel-reinforced concrete beam-column joining member, and the upper end streaks of the beam are connected to the beam of the column-beam joining member. The precast steel-framed reinforced concrete columns and beams can be firmly joined by penetrating the horizontal sleeve for penetrating the upper end muscles and injecting non-shrinkable mortar into the sleeve, which saves on-site work and improves construction efficiency. The accuracy can be improved.
第1図は本発明に係るプレキヤスト鉄骨鉄筋コンクリー
ト構造物の構築工法の一実施例の実施状況を示す縦断面
図で第2図の矢視I−I図、第2図はその横断平面図で
第1図の矢視II-II図、第3図はプレキヤスト鉄骨鉄筋
コンクリート柱部材の正面図、第4図はその柱脚部を示
す縦断面図、第5図はプレキヤスト鉄骨鉄筋コンクリー
ト柱梁接合部材の正面図、第6図は前記柱部材と柱梁接
合部材との接合部を示す横断平面図で第7図の矢視VI-V
I図、第7図は第6図の矢視VII-VII図、第8図は第6図
の矢視VIII-VIII図、第9図は本発明の方法によって立
設された前記柱部材及び柱梁接合部材の正面図、第10図
及び第11図は夫々その他の各実施例を示す正面図であ
る。 (A)……プレキヤスト鉄骨鉄筋コンクリート柱部材、
(B)……プレキヤスト鉄骨鉄筋コンクリート柱梁接合
部材、(C)……プレキヤスト鉄骨鉄筋コンクリート
梁、(1)……柱鉄骨、(2)……接合用ボツクス、
(3)……柱主筋接合用スリーブ、(4)……柱主筋、
(6)……柱鉄骨、(6a)……柱鉄骨の突出端部、
(7)……スタツドボルト、(8)……突設された鉄骨
梁、(9)……柱主筋貫通用垂直スリーブ、(10)……
梁上端筋貫通用水平スリーブ、(15)……梁上端筋、
(a)……無収縮モルタル。FIG. 1 is a vertical cross-sectional view showing an implementation state of an embodiment of a construction method of a precast steel-framed reinforced concrete structure according to the present invention. FIG. 1 is a view taken along the line I--I of FIG. 2, and FIG. Fig. 1 view II-II, Fig. 3 is a front view of a precast steel reinforced concrete column member, Fig. 4 is a longitudinal sectional view showing the column base, and Fig. 5 is a front view of a precast steel reinforced concrete column beam joint member. 6 and 6 are cross-sectional plan views showing the joint portion between the column member and the beam-column joint member, and are views VI-V in FIG.
FIG. I, FIG. 7 are views VII-VII in FIG. 6, FIG. 8 is a view VIII-VIII in FIG. 6, and FIG. 9 is the pillar member erected by the method of the present invention. FIG. 10 is a front view of a beam-column joint member, and FIGS. 10 and 11 are front views showing other respective embodiments. (A) ... Precast steel-framed reinforced concrete column members,
(B) …… Precast steel-framed reinforced concrete beam-column joining member, (C) …… Precast steel-framed reinforced concrete beam, (1) …… Column steel frame, (2) …… Box for joining,
(3) …… Sleeve for connecting main pillars, (4) …… Main pillar,
(6) …… Column steel frame, (6a) …… Column steel frame protruding end,
(7) …… Stud bolt, (8) …… Studded steel beam, (9) …… Vertical sleeve for penetration of column main bar, (10) ……
Horizontal sleeve for beam upper end reinforcement, (15) …… Beam upper end reinforcement,
(A) ... Non-shrink mortar.
Claims (2)
する接合用ボックスが、下端部には柱主筋接合用スリー
ブが夫々埋設され、且つ同スリーブに接続された柱主筋
の上端部が柱上方に突出されたプレキャスト鉄骨鉄筋コ
ンクリート柱部材を所定位置にセットしたのち、柱鉄骨
の上下突出端部にはスタッドボルトが植立され、同柱鉄
骨の中央部から鉄骨梁の一部が突設されるとともに、柱
主筋貫通用垂直スリーブ及び梁上端筋貫通用水平スリー
ブが埋設された前記柱部材と同一断面のプレキャスト鉄
骨鉄筋コンクリート柱梁接合部材における前記柱鉄骨下
端突出端部を、前記柱部材の上部接合用ボックスに嵌合
するとともに、同柱部材の上端から突出した柱主筋を前
記柱梁接合部材の上端部より突出するように、同接合部
材内の柱主筋貫通用垂直スリーブに貫通し、同柱主筋貫
通用垂直スリーブ及び前記接合用ボックスに無収縮モル
タルを注入することを特徴とするプレキャスト鉄骨鉄筋
コンクリート構造物の構築工法。1. A joining box surrounding the upper and lower ends of a column steel frame is embedded in the upper and lower ends of a column, and a column main-bar joining sleeve is embedded in the lower end of the column, and the main columns of the column are connected to the sleeve. After setting the precast steel-framed reinforced concrete column member with the upper end protruding above the pillar in place, stud bolts were planted at the vertically protruding ends of the pillar steel frame, and part of the steel beam from the center of the pillar steel frame. With the projecting, the pillar main bar penetrating vertical sleeve and the beam upper end bar penetrating horizontal sleeve for embedding a horizontal sleeve for pre-cast steel frame reinforced concrete column beam joint member of the same cross section as the pillar member, the pillar steel frame lower end projecting end portion, Fits in the upper joint box of the column member, and penetrates the column main bar in the column member so that the column main bar protruding from the upper end of the column member protrudes from the upper end of the column beam connecting member. Penetrating in the vertical sleeve, construction method of precast steel reinforced concrete structures, characterized by injecting the non-shrink mortar in the pillar main reinforcement through vertical sleeve and said junction boxes.
梁接合部材における柱鉄骨の中央部より突設された鉄骨
梁に、プレキャスト鉄骨鉄筋コンクリート梁を接合し、
同プレキャスト鉄骨鉄筋コンクリート梁の上端筋を前記
柱梁接合部材の梁上端筋貫通用水平スリーブに貫通する
とともに、同スリーブに無収縮モルタルを注入する請求
項1記載のプレキャスト鉄骨鉄筋コンクリート構造物の
構築工法。2. A precast steel reinforced concrete beam is joined to a steel frame beam projecting from a central portion of a column steel frame in the precast steel frame reinforced concrete beam-column joining member,
The method for constructing a precast steel-reinforced concrete structure according to claim 1, wherein an upper end bar of the precast steel-framed reinforced concrete beam is penetrated through a horizontal sleeve for penetrating the beam upper-end bar of the beam-column joining member, and non-shrink mortar is injected into the sleeve.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP31945888A JPH0749680B2 (en) | 1988-12-20 | 1988-12-20 | Construction method of precast steel reinforced concrete structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP31945888A JPH0749680B2 (en) | 1988-12-20 | 1988-12-20 | Construction method of precast steel reinforced concrete structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH02167939A JPH02167939A (en) | 1990-06-28 |
| JPH0749680B2 true JPH0749680B2 (en) | 1995-05-31 |
Family
ID=18110426
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP31945888A Expired - Lifetime JPH0749680B2 (en) | 1988-12-20 | 1988-12-20 | Construction method of precast steel reinforced concrete structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0749680B2 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2514859B2 (en) * | 1990-11-30 | 1996-07-10 | 株式会社フジタ | Precast Steel Reinforced Concrete Concrete Column |
| JP2004190364A (en) * | 2002-12-12 | 2004-07-08 | Kajima Corp | Precast SRC column joint structure |
| CN111270763B (en) * | 2020-04-03 | 2025-01-14 | 中建海龙科技有限公司 | An assembled concrete frame structure beam column with connection nodes |
-
1988
- 1988-12-20 JP JP31945888A patent/JPH0749680B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH02167939A (en) | 1990-06-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH02136444A (en) | Construction of composite structure consisting of precast reinforced concrete column and steel structural beam | |
| JP2927402B2 (en) | Column-beam joint structure of concrete building | |
| JPH06173343A (en) | Column-beam joint structure in laminated lumber structure | |
| JPH0749680B2 (en) | Construction method of precast steel reinforced concrete structure | |
| JPH04161542A (en) | Connecting work of column and beam and its structure | |
| JP2566176B2 (en) | Building construction method | |
| JPH02300439A (en) | Prefabricating method | |
| JPS63268834A (en) | Method for constructing body of multi-storied building and reinforcing bar connected cylinder used therein | |
| JP3586121B2 (en) | Mixed structure of reinforced concrete column and steel beam and its construction method | |
| JPH0718734A (en) | Constructing method for reinforced concrete building structure | |
| JPH0781307B2 (en) | How to build a skyscraper | |
| JPH06158863A (en) | Method for constructing concrete frame | |
| JPH0732706Y2 (en) | Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams | |
| JPS62264230A (en) | Construction of body of multistairs building | |
| JPH0726440B2 (en) | Method of joining steel-reinforced bar precast concrete columns and steel beams | |
| JPH0745783B2 (en) | Construction method of precast column beam and precast earthquake resistant wall. | |
| JP2554535B2 (en) | Steel beam / reinforced concrete column composite construction method | |
| JPH01137032A (en) | Method of lap joint construction of main reinforcement in post and beam joining section | |
| JPH01287336A (en) | Steel frame reinforced concrete lamination construction | |
| JP2579944Y2 (en) | Load-bearing wall assembly structure | |
| JP2001020297A (en) | Sc-structured footing beam method for building | |
| JPS6254943B2 (en) | ||
| JPH0781315B2 (en) | Construction method of composite structure with precast reinforced concrete columns and steel beams | |
| JPH032435A (en) | Construction method for jointing column and steel frame reinforced-concrete beam to each other | |
| JPH06257166A (en) | Foundation structure for unit building |