JPH0751777B2 - Cast-in-place - Google Patents
Cast-in-placeInfo
- Publication number
- JPH0751777B2 JPH0751777B2 JP15776690A JP15776690A JPH0751777B2 JP H0751777 B2 JPH0751777 B2 JP H0751777B2 JP 15776690 A JP15776690 A JP 15776690A JP 15776690 A JP15776690 A JP 15776690A JP H0751777 B2 JPH0751777 B2 JP H0751777B2
- Authority
- JP
- Japan
- Prior art keywords
- pile
- piles
- tip
- arc
- force
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 229910000831 Steel Inorganic materials 0.000 description 11
- 239000004567 concrete Substances 0.000 description 11
- 239000010959 steel Substances 0.000 description 11
- 230000002093 peripheral effect Effects 0.000 description 10
- 238000010276 construction Methods 0.000 description 6
- 238000009412 basement excavation Methods 0.000 description 4
- 238000000034 method Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 230000035515 penetration Effects 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000010802 sludge Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Description
【発明の詳細な説明】 [産業上の利用分野] この発明は場所打ち杭、特に杭本数の低減化に関するも
のである。The present invention relates to cast-in-place piles, and more particularly to reduction of the number of piles.
[従来の技術] 建築物,土木構造物等の荷重に対する地盤耐力を十分に
確保するために杭基礎が使用されている。この杭は、大
きく分けると既製杭と場所打ち杭に分けられる。[Prior Art] Pile foundations are used to ensure sufficient ground strength against loads such as buildings and civil engineering structures. The piles can be roughly divided into ready-made piles and cast-in-place piles.
既製杭は現場あるいは工場で作られるもので、コンクリ
ート杭や鋼杭等からなる。また、場所打ち杭は掘削後コ
ンクリートを打設する掘削方式と、貫入後コンクリート
を打設する貫入方式とがある。この場所打ち杭は既製杭
の打撃工法に比べて騒音や振動が少なく、かつ打ち込む
ことがないので振動による近接構造物への影響が少な
く、都市部の工事に広く採用されている。このように杭
は製造と設置方法により分類されるが、いずれの杭も直
線状の杭が使用されている。Ready-made piles are made on site or in factories and consist of concrete piles or steel piles. As for the cast-in-place pile, there are an excavation method of placing concrete after excavation and a penetration method of placing concrete after penetration. This cast-in-place pile has less noise and vibration than the hammering method for ready-made piles, and since it does not drive in, it has little effect on neighboring structures due to vibration and is widely used for construction in urban areas. As described above, the piles are classified according to the manufacturing method and the installation method, but all the piles are linear piles.
[発明が解決しようとする課題] 通常、杭の支持力は杭先端支持力と杭の周面摩擦による
支持力の和と考えられる。この杭先端支持力は杭先端の
面積に比例し、周面摩擦による支持力は杭の周長に比例
する。すなわち、従来のように直杭を使用した場合、杭
の支持力は杭の外径に比例する。場所打ち杭は杭の外径
を既製杭と比べて大きくすることができるが、外径を大
きくするにも限度がある。このため、構造物等の荷重に
対する地盤耐力を十分に確保するのに多数の杭を使用し
なければならないという短所があった。[Problems to be Solved by the Invention] Usually, the supporting force of a pile is considered to be the sum of the supporting force at the tip of the pile and the supporting force due to friction of the peripheral surface of the pile. The pile tip supporting force is proportional to the area of the pile tip, and the supporting force due to friction on the peripheral surface is proportional to the pile perimeter. That is, when a straight pile is used as in the conventional case, the bearing capacity of the pile is proportional to the outer diameter of the pile. The cast-in-place pile can have a larger outer diameter than the ready-made pile, but there is a limit to increasing the outer diameter. Therefore, there is a disadvantage in that a large number of piles must be used in order to ensure sufficient ground resistance against the load of the structure or the like.
また、従来の場所打ち杭コンクリート杭は、例えばコン
クリートの常用許容圧縮強度を60Kg/cm2、支持層のN値
を50とすると、先端の地盤耐力は25Kg/cm2となり、コン
クリート強度を全部活用するために、杭先端部を拡底す
ることがしばしば行なわれる。このように杭先端部を拡
底すると、杭が支持する常時鉛直荷重が増大する。耐震
設計に用いる杭頭への水平力は、ほぼ常時鉛直荷重と水
平震度の積で表わされるので、常時鉛直荷重が増大する
と水平力も増大する。杭頭部がこの水平力による曲げモ
ーメントに耐え得るためには、杭頭部も拡径しなければ
ならない場合が生じ、施工費用が増大するという短所が
あった。In the conventional cast-in-place concrete pile, for example, assuming that the normal allowable compressive strength of concrete is 60 kg / cm 2 and the N value of the support layer is 50, the ground bearing capacity of the tip is 25 kg / cm 2 , and the concrete strength is fully utilized. In order to do so, it is often the case that the bottom of the pile is expanded. By expanding the bottom of the pile tip in this way, the vertical load constantly supported by the pile increases. Since the horizontal force on the pile head used for seismic design is almost always represented by the product of vertical load and horizontal seismic intensity, the horizontal force also increases as the vertical load increases. In order for the pile head to withstand the bending moment due to this horizontal force, the pile head may have to be expanded in diameter, which increases the construction cost.
この発明はかかる短所を解決するためになされたもので
あり、杭先端部を拡底せずに支持力を増大することがで
きる場所打ち杭を得ることを目的とするものである。The present invention has been made to solve such disadvantages, and an object of the present invention is to obtain a cast-in-place pile that can increase the supporting force without expanding the bottom of the pile.
[課題を解決するための手段] この発明に係る場所打ち杭は、杭先端までの鉛直方向長
さとほぼ同じ長さの半径を有する円弧状に形成したこと
を特徴とする。[Means for Solving the Problem] The cast-in-place pile according to the present invention is characterized in that it is formed in an arc shape having a radius of a length substantially the same as the vertical length up to the tip of the pile.
[作用] この発明においては、杭を円弧状にすることにより、支
持層における鉛直方向の地盤反力を受ける部分の面積を
大きくして地盤反力を増大すると共に、杭全体の長さを
長くして周面摩擦力を増大させる。[Operation] In the present invention, by making the pile arc-shaped, the area of the portion of the support layer that receives the ground reaction force in the vertical direction is increased to increase the ground reaction force, and at the same time, increase the length of the entire pile. To increase the frictional force on the peripheral surface.
[実施例] 第1図はこの発明の一実施例を示す縦断面図である。図
に示すように、N=10,深さL1(m)のシルト層1の下
にN=50の支持層2がある地盤に、軸径D(mm),先端
までの鉛直方向の長さLとほぼ同じ長さの半径R(m)
の円弧状をした場所打ち杭(以下、円弧杭という)3を
支持層2にL2(m)根入れした場合を示す。[Embodiment] FIG. 1 is a longitudinal sectional view showing an embodiment of the present invention. As shown in the figure, the ground with the support layer 2 with N = 50 under the silt layer 1 with N = 10 and depth L 1 (m) has a shaft diameter D (mm) and a vertical length to the tip. Radius R (m) of almost the same length as length L
The case where an arc-shaped cast-in-place pile (hereinafter referred to as an arc pile) 3 is embedded in the support layer 2 by L 2 (m) is shown.
以下、円弧杭3を使用する有利性を直杭の場合と比べて
説明する。Hereinafter, the advantages of using the arc pile 3 will be described in comparison with the case of the straight pile.
円弧杭3の極限支持力RU(tf)は杭先端抵抗と周面摩擦
力及び上向きの地盤反力の和で定まり下記(1)式で表
わされる。The ultimate bearing capacity R U (tf) of the circular arc pile 3 is determined by the sum of the pile tip resistance, the peripheral frictional force, and the upward ground reaction force, and is expressed by the following equation (1).
RU=qd・A+UΣLi・fi+Qz ……(1) 但し、 A :杭先端面積(m2) qd:杭先端の極限支持力度(tf/m2) U :杭の周長(m) Li:周面摩擦力が作用する杭の長さ(m) fi:周面摩擦力が作用する層の最大周面摩擦力力度(tf
/m2) Qz:上向きの地盤反力(tf) 例えば、シルト層1の深さL1=27(m).根入れ深さL2
=3(m)とし、軸径D=609.6(mm),厚さ9.5(mm)
の鋼管4の内部にコンクリート5を充填し、円弧の半径
R=30(m)の円弧杭3を造成した場合の杭先端抵抗qd
・Aは、支持層2におけるqdの推定値を300とすると、 qd・A=300×(π/4)×0.60962 =87.51(tf)になる。R U = q d · A + UΣL i · f i + Q z (1) where A: pile tip area (m 2 ) q d : ultimate bearing capacity of pile tip (tf / m 2 ) U: pile circumference (M) L i : Length of pile on which peripheral frictional force acts (m) f i : Maximum peripheral frictional force of a layer on which peripheral frictional force acts (tf
/ m 2 ) Q z : Upward ground reaction force (tf) For example, the depth of the silt layer 1 L 1 = 27 (m). Rooting depth L 2
= 3 (m), shaft diameter D = 609.6 (mm), thickness 9.5 (mm)
Pile tip resistance q d when the inside of the steel tube 4 concrete 5 was filled, was constructed an arc pile 3 of arc having a radius R = 30 (m)
・ A is q d · A = 300 × (π / 4) × 0.6096 2 = 87.51 (tf), where the estimated value of q d in the support layer 2 is 300.
また、円弧杭3のシルト層1における長さL1Rは33.6
(m)、支持層2における長さL2Rは13.5(m)になる
から、周面摩擦力は、 UΣLi・fi =0.609π{(33.6×0.1×10) +(13.5×0.1×50)} =193.5(tf) になる。The length L 1R of the circular arc pile 3 in the silt layer 1 is 33.6.
(M), the length L 2R of the supporting layer 2 is 13.5 (m), so the peripheral frictional force is UΣL i · f i = 0.609π {(33.6 × 0.1 × 10) + (13.5 × 0.1 × 50 )} = 193.5 (tf).
また、上向きの地盤反力Qzは円弧杭3全体にわたり作用
するが、鉛直方向分力の大きいN値が50以上の支持層2
に埋め込まれている部分のみを考慮し、かつ地盤反力を
少なめに見込むと、支持層2における上向きの地盤反力
Qz2は次式で表わせる。Further, the upward ground reaction force Q z acts on the entire arc pile 3, but the supporting layer 2 having a large vertical component force and an N value of 50 or more is used.
Considering only the part embedded in the ground, and considering the ground reaction force to be small, upward ground reaction force in the support layer 2
Q z2 can be expressed by the following equation.
Qz2=L2R・KU・δ・D ……(2) 但し、 L2R:鉛直方向地盤反力を受ける長さ(cm) KU : 地盤反力係数(Kg/cm3) δ :沈下量(cm) D :杭外径(cm) ここで、地盤反力係数KU=1(Kg/cm3),沈下量δ=1
(cm)とすると、Qz2=82.2(tf)になる。Q z2 = L 2R · K U · δ · D (2) However, L 2R : Length to receive vertical ground reaction force (cm) K U : Ground reaction force coefficient (Kg / cm 3 ) δ: Settlement Amount (cm) D: Pile outside diameter (cm) where ground reaction force coefficient K U = 1 (Kg / cm 3 ), subsidence amount δ = 1
(Cm), Q z2 = 82.2 (tf).
したがって、円弧杭3の極限支持力RUはこれらの和にな
り、RU=363.2(tf)になる。Therefore, the ultimate bearing capacity R U of the circular pile 3 becomes the sum of these, and R U = 363.2 (tf).
一方、第2図に示すように、同じ地盤に直杭6を造成し
た場合を考えると、直杭6の極限支持力RUは、 RU=qd・A+UΣLi・fi =167.9(tf) になる。On the other hand, as shown in Fig. 2, considering the case where the straight pile 6 is constructed on the same ground, the ultimate bearing capacity R U of the straight pile 6 is R U = q d · A + UΣL i · f i = 167.9 (tf ) become.
すなわち、円弧杭3の極限支持力RUは直杭6の約2倍に
なる。したがって、同一の極限支持力RUを得るために
は、円弧杭3にすると杭本数を半分に減らすことができ
る。That is, the ultimate bearing capacity R U of the circular pile 3 is about twice that of the straight pile 6. Therefore, in order to obtain the same ultimate bearing capacity R U , the number of piles can be reduced to half by using the circular arc piles 3.
また、円弧杭3と直杭6の許容引抜き力PUを比較する
と、許容引抜き力PUは周面摩擦力UΣLi・fiで定まり、
直杭4の場合は80.39(tf/本)であるのに対して、円弧
杭3の場合には193.5(tf/本)になり、許容引抜き力PU
を考慮しても、円弧杭3は直杭6の場合より本数を半分
以下に減らすことができる。In addition, comparing the allowable pull-out force P U of the circular pile 3 and the straight pile 6, the allowable pull-out force P U is determined by the peripheral frictional force UΣL i · f i ,
In the case of straight pile 4, it is 80.39 (tf / piece), whereas in the case of circular pile 3, it is 193.5 (tf / piece), and the allowable pull-out force P U is
In consideration of the above, the number of circular arc piles 3 can be reduced to less than half that of the straight piles 6.
なお、円弧杭3の場合には、杭の抜け出しに対してより
地盤が抵抗するため引抜き力をより大きくすることがで
きる。In the case of the circular arc pile 3, the ground further resists the pulling-out of the pile, and thus the pulling-out force can be increased.
この円弧杭3の座屈を考えると、座屈荷重Ncrは次式で
表わされる。Considering the buckling of the circular arc pile 3, the buckling load N cr is expressed by the following equation.
Ncr=mcE1y/(Rθ)2 ……(3) 但し、 mc :杭の支持条件で定まる値 E :杭材のヤング係数 Iy :杭の断面2次モーメント Rθ:座屈長さ ここで、mc=32,E=2.1×106(Kg/cm2),Iy=π(D4−
Din 4)/64(Din:円弧杭3の鋼管4内径),座屈長さR
θとして杭頭部から杭底部までの長さをとると、上記円
弧杭3の座屈荷重Ncr=244(tf)になる。N cr = m c E1 y / (Rθ) 2 (3) where m c is a value determined by the support conditions of the pile E: Young's modulus of the pile material I y : Moment of inertia of the pile Rθ: Buckling length Here, m c = 32, E = 2.1 × 10 6 (Kg / cm 2 ), I y = π (D 4 −
D in 4 ) / 64 (D in : Steel pipe 4 inner diameter of arc pile 3), Buckling length R
When the length from the pile head to the pile bottom is taken as θ, the buckling load of the circular arc pile 3 becomes N cr = 244 (tf).
一方、円弧杭3の許容支持力Raは安全率を3と考える
と、極限支持力RUから Ra=RU/3=121(tf) になり、座屈荷重Ncr=244(tf)の1/2程度であり、面
外座屈のおそれはない。なお、実際の場合には円弧杭3
の全方向が拘束されているため、座屈荷重Ncrは上記モ
デルで求めた場合よりはるかに大きくなる。On the other hand, considering the allowable bearing capacity R a safety factor of the arc pile 3 3 consists ultimate bearing capacity R U in R a = R U / 3 = 121 (tf), the buckling load N cr = 244 (tf It is about 1/2 of that of () and there is no risk of out-of-plane buckling. In the actual case, the circular arc pile 3
The buckling load N cr is much larger than that obtained by the above model because all directions are constrained.
次に、上記円弧杭3の施工法の一例を説明する。Next, an example of a construction method of the circular arc pile 3 will be described.
円弧杭3の施工には、例えば第3図に示すように長手方
向に湾曲した内管11の先端に取付けた先端駆動型ドリル
12を使用する。For the construction of the circular arc pile 3, for example, as shown in FIG. 3, a tip drive type drill attached to the tip of the inner pipe 11 curved in the longitudinal direction.
Use 12
先端駆動型ドリル12はカイド部13と、カイド部13の先端
部に取付けられた回転部14とからなり、回転部14は先端
にパイロットビット15を有し、周方向の側面の複数個所
に起倒可能なリトラクトビット16を有する。The tip drive type drill 12 comprises a guide portion 13 and a rotating portion 14 attached to the tip portion of the guide portion 13. The rotating portion 14 has a pilot bit 15 at the tip and is raised at a plurality of positions on the circumferential side surface. It has a retractable retract bit 16.
そして、円弧杭3の半径Rの円弧状に湾曲した鋼管4の
内面で先端駆動型ドリル12のガイド部13を案内しなが
ら、鋼管4の先端から回転部14を突出させ、パイロット
ビット15とリトラクトビット16で地中を掘削しながら内
管11と鋼管4を推進させる。この掘削に用いる掘削水は
内管11を通じてパイロットビット15の前面に供給し、排
土を含む排泥水はくむ内管11と鋼管4の間を通つて排出
する。Then, while guiding the guide portion 13 of the tip drive type drill 12 on the inner surface of the steel pipe 4 which is curved in an arc shape having the radius R of the arc pile 3, the rotating portion 14 is projected from the tip of the steel pipe 4, and the pilot bit 15 and the retract. The inner pipe 11 and the steel pipe 4 are propelled while excavating the underground with the bit 16. Excavation water used for this excavation is supplied to the front surface of the pilot bit 15 through the inner pipe 11, and is discharged through the space between the inner pipe 11 and the steel pipe 4, which contains the waste sludge.
このように地中を掘削し、所定位置に鋼管4を設置した
後、内管11と先端駆動型ドリル12を引き抜き、鋼管4内
にコンクリートを打設し、円弧杭3を完成する。After excavating the ground in this way and installing the steel pipe 4 at a predetermined position, the inner pipe 11 and the tip drive type drill 12 are pulled out, concrete is placed in the steel pipe 4, and the arc pile 3 is completed.
なお、上記実施例においては、円弧杭3を鋼管コンクリ
ート杭で形成した場合について説明したが、コンクリー
ト杭や鉄筋コンクリート杭により円弧杭3を形成して
も、上記実施例と同様な作用を奏することができる。In addition, in the said Example, although the case where the circular arc pile 3 was formed with the steel pipe concrete pile was demonstrated, even if the circular arc pile 3 is formed with a concrete pile or a reinforced concrete pile, the same effect as the said Example is produced. it can.
[発明の効果] この発明は以上説明したように、杭を円弧状にすること
により、支持層における鉛直方向の地盤反力を受ける部
分の面積を大きくして地盤反力を増大すると共に、杭全
体の長さを長くして周面摩擦力を増大させて支持力を大
きくしたから、設置する杭の本数を低減することができ
る。[Effect of the Invention] As described above, the present invention increases the ground reaction force by increasing the area of the portion of the support layer that receives the ground reaction force in the vertical direction by increasing the ground reaction force by forming the pile in an arc shape. Since the whole length is increased to increase the frictional force on the peripheral surface and increase the supporting force, the number of piles to be installed can be reduced.
また、杭の本数を低減することにより、施工工期を短縮
することができると共に、施工費用の低減を図ることが
できる。Further, by reducing the number of piles, the construction period can be shortened and the construction cost can be reduced.
第1図はこの発明の実施例を示し、(a)は円弧杭の縦
断面図、(b)はN値の分布図、第2図(a)は直杭の
縦断面図、(b)はN値の分布図、第3図は円弧杭を設
置するときの状態を示す説明図である。 1……シルト層、2……支持層、3……円弧杭、4……
鋼管、5……コンクリート。FIG. 1 shows an embodiment of the present invention, (a) is a vertical sectional view of an arc pile, (b) is a distribution diagram of N values, and FIG. 2 (a) is a vertical sectional view of a straight pile, (b). Is a distribution chart of N values, and FIG. 3 is an explanatory view showing a state when installing an arc pile. 1 ... silt layer, 2 ... support layer, 3 ... arc pile, 4 ...
Steel pipe, 5 ... Concrete.
Claims (1)
の半径を有する円弧状に形成したことを特徴とする場所
打ち杭。1. A cast-in-place pile, which is formed in an arc shape having a radius substantially the same as the vertical length to the tip of the pile.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15776690A JPH0751777B2 (en) | 1990-06-18 | 1990-06-18 | Cast-in-place |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15776690A JPH0751777B2 (en) | 1990-06-18 | 1990-06-18 | Cast-in-place |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0449318A JPH0449318A (en) | 1992-02-18 |
| JPH0751777B2 true JPH0751777B2 (en) | 1995-06-05 |
Family
ID=15656846
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP15776690A Expired - Lifetime JPH0751777B2 (en) | 1990-06-18 | 1990-06-18 | Cast-in-place |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0751777B2 (en) |
-
1990
- 1990-06-18 JP JP15776690A patent/JPH0751777B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0449318A (en) | 1992-02-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR100289256B1 (en) | Tunnel construction method in shallow toffee area | |
| JP5769104B2 (en) | Foundation structure of buildings in soft ground | |
| KR20170046362A (en) | Helix steel pipe pile for reinforcement of buckling and construction method of the same | |
| JP3516391B2 (en) | Ground excavation method | |
| JPH08184037A (en) | Double pipe type steel pipe pile | |
| JP4017593B2 (en) | Steel pipe pile | |
| JPH07119549B2 (en) | Twin tunnel | |
| JP2871458B2 (en) | Steel pipe pile and construction method of steel pipe pile | |
| JPH0751777B2 (en) | Cast-in-place | |
| US4543015A (en) | Pile having wedge former | |
| US4349298A (en) | Wedge-forming pile | |
| RU2091540C1 (en) | Pile | |
| JP3488454B1 (en) | H-shaped steel pile for temporary work | |
| JPH0751778B2 (en) | Expanding method of expanding circular pile and circular arc pile | |
| KR102252011B1 (en) | Composite Pile Using Angled Channel With Different Strength Steels | |
| KR102337545B1 (en) | Underground retaining wall using concrete pile and soil retaining plate | |
| KR20230030596A (en) | Temporary earth retaining facility using guide bracket and ground anchor and its construction method | |
| JP4502442B2 (en) | Seismic foundation, seismic building, and pile reinforcement method | |
| JPS5842328B2 (en) | steel pipe sheet piles | |
| KR102289576B1 (en) | Top-down type underground structure construction method using earth support plate | |
| CN114808929A (en) | Method for connecting pile-column integrated cast-in-place pile and horizontal structure and connecting node | |
| JP4440799B2 (en) | Ground excavation method | |
| JP2589073Y2 (en) | Concrete cast-in-place pile | |
| JPS6343275Y2 (en) | ||
| JP2016188510A (en) | Design method for ground improvement method |