JPH076243B2 - Concrete construction method, construction runner and construction structure - Google Patents
Concrete construction method, construction runner and construction structureInfo
- Publication number
- JPH076243B2 JPH076243B2 JP26450191A JP26450191A JPH076243B2 JP H076243 B2 JPH076243 B2 JP H076243B2 JP 26450191 A JP26450191 A JP 26450191A JP 26450191 A JP26450191 A JP 26450191A JP H076243 B2 JPH076243 B2 JP H076243B2
- Authority
- JP
- Japan
- Prior art keywords
- runner
- concrete
- lath
- plate
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 title claims description 20
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 18
- 230000003014 reinforcing effect Effects 0.000 claims description 13
- 229910052742 iron Inorganic materials 0.000 claims description 9
- 239000002184 metal Substances 0.000 claims description 4
- 229910052751 metal Inorganic materials 0.000 claims description 4
- 230000002787 reinforcement Effects 0.000 claims description 4
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 4
- 238000009415 formwork Methods 0.000 description 4
- 125000006850 spacer group Chemical group 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 238000005452 bending Methods 0.000 description 1
- 210000000078 claw Anatomy 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、ラス板或は鉄板によっ
て型枠を形成し、それら板を構築物の補強として残すコ
ンクリート構築法、該構築法に使用するランナー及びコ
ンクリート構築構造に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a concrete construction method in which a form is formed by lath plates or iron plates, and the plates are left as reinforcement for the construction, a runner used in the construction method, and a concrete construction structure. .
【0002】[0002]
【従来の技術】鉄板に多数の切込みを施し、これを一方
向に引張って網状に形成した周知のラス板をコンクリー
ト用型枠に用いたラス型枠工法が実施されている。2. Description of the Related Art A lath formwork method has been practiced in which a well-known lath plate formed by making a large number of cuts in an iron plate and pulling the cut in one direction to form a net is used as a concrete formwork.
【0003】従来のラス型枠工法は、図7に示す如く、
コンクリート基礎面(1)の上に、構築すべき梁の幅に対
応して墨線(11)を施し、墨線(11)内に補強鉄筋枠(9)を
組込み、墨線(11)に沿って帯鉄製ランナー(27)を敷設す
る。The conventional lath formwork method is as shown in FIG.
A black wire (11) is applied on the concrete foundation surface (1) according to the width of the beam to be constructed, and a reinforcing reinforcing bar frame (9) is incorporated into the black wire (11). Install the iron runner (27).
【0004】補強鉄筋枠(9)上に上向きにネジ軸(8)
(8)を突設し、該ネジ軸にナット(82)(82)を螺合し、両
ネジ軸に跨がって幅決め金具(83)を嵌め込み、ナット(8
2)で支える。Screw shaft (8) upwards on the reinforcing bar frame (9)
(8) is protruded, nuts (82) and (82) are screwed onto the screw shaft, the width determining metal fitting (83) is fitted over both screw shafts, and the nut (8
Support with 2).
【0005】幅決め金具(83)の両端のU溝(84)に棒状ラ
ンナー(85)を嵌め、該上ランナー(85)にラス板(31)を番
線(88)等によって括り付けて吊り下げ支持する。The rod-shaped runners (85) are fitted in the U-grooves (84) at both ends of the width determining metal fitting (83), and the lath plate (31) is bundled with the upper runners (85) by the numbered wires (88) or the like and suspended. To support.
【0006】ラス板(31)の外側にて、パイプ(86)を縦向
きにし、略等間隔に下ランナー(2)上に配備し、下ラン
ナー(2)に設けた切り起し爪片(28)にパイプ下端を嵌め
て位置決めし、左右のパイプを番線(87)にて引張り合
う。On the outside of the lath plate (31), the pipe (86) is oriented vertically, and the pipes (86) are arranged on the lower runner (2) at substantially equal intervals, and the cut-and-raised claw pieces (provided on the lower runner (2) ( Fit the lower end of the pipe to 28), position it, and pull the left and right pipes together with the numbered wire (87).
【0007】ラス板(31)(31)間にコンクリート打設し、
コンクリート固化後、パイプ(86)を外す。Concrete is placed between the lath plates (31) (31),
After solidifying the concrete, remove the pipe (86).
【0008】[0008]
【発明が解決しようとする課題】上ランナー(85)にラス
板(31)を吊り下げ支持するための、番線(88)による括り
付け箇所が多くなり、作業性が悪い。[Problems to be Solved by the Invention] Since the lath plate (31) is suspended from and supported by the upper runner (85), the number of binding points by the numbered wires (88) increases, resulting in poor workability.
【0009】又、パイプ(86)(86)間に於て、ラス板(31)
の下端縁は単に垂れ下がっているだけであり、コンクリ
ートを打設した際、内圧によってラス板(31)の下端が膨
らんで湾曲し、梁の側面が波を打った状態となる。本発
明は上記問題を解決できるコンクリート構築法、該構築
法に用いる構築用ランナー及び構築構造を明らかにする
ものである。Further, the lath plate (31) is provided between the pipes (86) (86).
The lower end edge of is simply hanging down, and when concrete is poured, the lower end of the lath plate (31) swells and bends due to internal pressure, and the side surface of the beam becomes wavy. The present invention clarifies a concrete construction method capable of solving the above problems, a construction runner and a construction structure used in the construction method.
【0010】[0010]
【課題を解決する手段】本発明のコンクリート構築法
は、基礎面(1)上に構築すべき壁厚に対応して墨出しを
行なう第1工程、墨出し幅内にてコンクリート補強用の
鉄筋枠(9)を組込む工程、或は墨線(11)に沿って断面略
コ字状の長尺ランナー(2)を開口を上向きにして固定配
備する工程を、前後を問わず行なう第2、第3工程、ラ
ンナー(2)の溝(20)内に高さ調節部材(7)を挿入し、リ
ブ(32)を縦向にしたラス板(31)或は鉄板の下端縁を該溝
(20)に嵌めて枠壁(3)を形成する第4工程、両枠壁(3)
(3)の上端に断面略コ字状の長尺ランナー(2a)(2a)を開
口を下向きにして被せ、左右の上ランナー(2a)(2a)間を
セパレータ(4)にて所定の間隔を保って連結する第5工
程、枠壁(3)(3)間にコンクリートを打設する第6工程
を含む。又、本発明のコンクリート構築用ランナーは、
断面略コ字状を成し、一方の側板(22)を略等間隔に切り
起こして底板(21)の延長上に突片(23)を形成し、該突片
に釘孔(24)を開設している。又、本発明のコンクリート
構築構造は、両側面がラス板(31)或は金属板で形成され
た枠壁(3)(3)にて補強され、枠壁(3)の上端に断面コ
字状のランナー(2a)(2a)が被さって、ランナーの角部が
梁の稜となっている。According to the concrete construction method of the present invention, the first step of marking out according to the wall thickness to be built on the foundation surface (1), the reinforcing steel for concrete reinforcement within the marking width. The step of assembling the frame (9) or the step of fixedly deploying the long runner (2) having a substantially U-shaped cross section along the black line (11) with the opening facing upward 3 steps, inserting the height adjusting member (7) into the groove (20) of the runner (2), and the lower end edge of the lath plate (31) or iron plate with the rib (32) oriented vertically
Fourth step of fitting to (20) to form frame wall (3), both frame walls (3)
Cover the upper end of (3) with a long runner (2a) (2a) with a substantially U-shaped cross section with the opening facing downward, and place a predetermined gap between the left and right upper runners (2a) (2a) with a separator (4). A fifth step of connecting while maintaining the above, and a sixth step of placing concrete between the frame walls (3) and (3) are included. Further, the concrete construction runner of the present invention,
It has a substantially U-shaped cross section, one side plate (22) is cut and raised at substantially equal intervals to form a protrusion (23) on the extension of the bottom plate (21), and a nail hole (24) is formed in the protrusion. It is open. In addition, the concrete construction structure of the present invention is reinforced by frame walls (3) and (3) formed on both sides by lath plates (31) or metal plates, and has a U-shaped cross section at the upper end of the frame wall (3). The runners (2a) (2a) are covered, and the corners of the runners are the ridges of the beam.
【0011】[0011]
【作用及び効果】コンクリート構築法の発明にあって
は、枠壁(3)はリブ(32)を縦向きにしたラス板(31)或は
鉄板を、その下端を下ランナー(2)の溝(20)に嵌めて自
立させるため、従来の様に、リブ(32)を横向きにしたラ
ス板を上ランナーに吊り下げ支持する場合の様に、ラス
板(31)と上ランナー(2a)とを番線(88)によって幾箇所も
締結する面倒な作業は不要となり、作業性が大幅に向上
する。[Operation and effect] In the invention of the concrete construction method, the frame wall (3) is a lath plate (31) or an iron plate in which the ribs (32) are oriented vertically, and the lower end thereof is a groove of the lower runner (2). In order to fit it on (20) and make it self-sustaining, as in the case of suspending and supporting the lath plate with the ribs (32) in the horizontal direction, the lath plate (31) and the upper runner (2a) are The troublesome work of fastening multiple points with the number line (88) is unnecessary, and workability is greatly improved.
【0012】枠壁(3)の下端縁は下ランナー(2)の溝(2
0)に嵌まって膨らみは防止されるため、コンクリート梁
の側面が波打つことをなくすことができる。The lower end edge of the frame wall (3) has a groove (2
Since the bulge is prevented by fitting in (0), it is possible to prevent the side surface of the concrete beam from waviness.
【0013】下ランナー(2)の溝(20)に高さ調節部材
(7)を挿入するため、ラス板(31)或は鉄板を溝(20)に嵌
めるだけでその上端縁は設定高さに揃い、従来の様に、
補強鉄筋枠(9)上のネジ軸(82)に嵌めたナット(82)によ
って、ラス板(31)の吊り下げ高さを調節することに比べ
て、作業性が良い。Height adjusting member in the groove (20) of the lower runner (2)
To insert (7), just insert the lath plate (31) or iron plate into the groove (20) and the upper edge will be aligned with the set height.
The workability is better than adjusting the hanging height of the lath plate (31) by the nut (82) fitted to the screw shaft (82) on the reinforcing steel frame (9).
【0014】ランナー(2)の発明にあっては、上記の如
く、側板(22)(22)間の溝(20)に枠壁(3)の下端を嵌め
て、枠壁(3)の下部縁の湾曲を防止できる。又、ランナ
ー(2)を基礎面(1)に固定するための突片(23)は、ラン
ナー(2)の一方の側板(22)を切り起こして簡単に形成で
きる。In the invention of the runner (2), as described above, the lower end of the frame wall (3) is fitted into the groove (20) between the side plates (22) and (22), and the lower part of the frame wall (3) is fitted. Curvature of the edge can be prevented. Further, the protruding piece (23) for fixing the runner (2) to the base surface (1) can be easily formed by cutting and raising one side plate (22) of the runner (2).
【0015】コンクリート構築構造の発明にあっては、
上ランナー(2a)の底板(21)と側板(22)とが成す隅部がコ
ンクリート梁の稜となるため、上ランナーが稜の補強の
役割をなし、欠け、割れ等の稜の損傷を防止できる。In the invention of the concrete construction structure,
Since the corners formed by the bottom plate (21) and side plates (22) of the upper runner (2a) form the ridge of the concrete beam, the upper runner plays a role of reinforcing the ridge and prevents damage to the ridge such as chipping or cracking. it can.
【0016】[0016]
【実施例】図面は、ラス板(31)を縦使い、即ちラス板(3
1)に等間隔に形成された平行補強リブ(32)を縦向きにし
て使用する実施例を示している。ラス板(31)は規格寸法
のものを、構築すべき梁の高さに対応して切断し、或は
縦方向に繋ぎ合わせる。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The drawing shows that a lath plate (31) is used vertically,
1) shows an embodiment in which the parallel reinforcing ribs (32) formed at equal intervals are used in the vertical direction. The lath plate (31) having a standard size is cut according to the height of the beam to be constructed or joined in the longitudinal direction.
【0017】上記ラス板(31)の下端縁を受けるランナー
(2)は、図2、図5に示す如く、断面コ字状の長尺杆を
規格寸法、実施例では1800mmに切断して形成され
る。ランナー(2)の溝幅約12mm、溝深さは約50mmで
ある。ランナー(2)の溝幅は、2枚のラス板(31)(31)を
互いのリブ(31)を重ねてた状態で丁度嵌まる程度であ
る。A runner for receiving the lower edge of the lath plate (31)
As shown in FIGS. 2 and 5, (2) is formed by cutting a long rod having a U-shaped cross section into a standard dimension, 1800 mm in the embodiment. The runner (2) has a groove width of about 12 mm and a groove depth of about 50 mm. The groove width of the runner (2) is such that two lath plates (31), (31) are fitted with each other with the ribs (31) overlapped with each other.
【0018】ランナー(2)は、一方の側板(22)を約30
0mmピッチで部分的に切り起こして、底板(21)の延長上
に複数の矩形の突片(23)を形成している。The runner (2) has one side plate (22) with about 30
A plurality of rectangular protrusions (23) are formed on the extension of the bottom plate (21) by partially cutting and raising it at a pitch of 0 mm.
【0019】突片(23)は幅約50mmの矩形をなし、固定
用の釘孔(24)(24)及び幅方向の中央にて溝寄りに後記す
るセパレータ(4)が嵌まる連結孔(25)を開設している。The projecting piece (23) has a rectangular shape with a width of about 50 mm, and has nail holes (24) (24) for fixing and a connecting hole (in the center of the width direction) to which a separator (4) described later is fitted near the groove. 25) has been established.
【0020】次に、上記ランナー(2)及びラス板(31)を
用いた型枠工法を説明する。図1に示す如く、基礎コン
クリート面(1)上に、構築すべき梁の幅に合わせて、墨
出し、即ち、平行墨線(11)を印す。Next, the formwork method using the runner (2) and the lath plate (31) will be described. As shown in FIG. 1, a black line, that is, a parallel black line (11) is marked on the basic concrete surface (1) according to the width of the beam to be constructed.
【0021】墨線(11)(11)間にコンクリート補強用鉄筋
枠(9)を組込む(図2、図3、図4では補強鉄筋枠は省
略し、図示していない)。A concrete reinforcing steel frame (9) is incorporated between the black wire (11) and (11) (the reinforcing steel frame is omitted in FIGS. 2, 3 and 4 and is not shown).
【0022】図2の如く、墨線(11)に沿ってランナー
(2)敷設する。ランナー(2)は溝開口を上に向け、突片
(23)を外に向け、内側縁を墨線(11)に一致させ、突片(2
3)にコンクリート釘(29)を打ち込んで基礎面(1)に固定
する。尚、作業段取りによっては、ランナー(2)を基礎
面(1)に固定した後に、前記補強用鉄筋枠(9)を組込ん
でも可い。As shown in FIG. 2, the runner runs along the black line (11).
(2) Laying. The runner (2) has the groove opening facing upwards
(23) facing outward, align the inner edge with the black line (11), and
Drive concrete nails (29) into 3) and fix to the foundation surface (1). Depending on the work setup, the reinforcing bar frame (9) may be incorporated after the runner (2) is fixed to the foundation surface (1).
【0023】定規板(6)をランナー(2)の溝(20)に嵌
め、トランシット(図示せず)を見ながら定規板(6)の上
端を構築すべき梁の高さに合わせ、定規板(6)の下端位
置に合わせてランナー(2)に印(61)を施す。The ruler plate (6) is fitted into the groove (20) of the runner (2), the upper end of the ruler plate (6) is aligned with the height of the beam to be constructed while watching the transit (not shown), and the ruler plate Mark (61) the runner (2) according to the lower end position of (6).
【0024】図5の如く、ランナー(2)の溝(20)に上記
印(61)の位置までスペーサ(71)を嵌め、ラス板(31)の高
さ調節部材(7)と成す。As shown in FIG. 5, the spacer (71) is fitted into the groove (20) of the runner (2) up to the position of the mark (61) to form the height adjusting member (7) of the lath plate (31).
【0025】図4の如く、ラス板(31)を縦使いにしてそ
の下端をランナー(2)の溝(20)に嵌め、枠壁(3)を形成
する。As shown in FIG. 4, the lath plate (31) is used vertically and its lower end is fitted into the groove (20) of the runner (2) to form the frame wall (3).
【0026】ラス板(31)は必要に応じて横に繋ぎ、この
とき隣り合うラス板(31)(31)は互いの端部リブ(32)を重
ねて溝(20)に嵌める。ランナー(2)の溝(20)にはスペー
サ(71)が挿入されており、枠壁(3)の上端は全長に亘っ
て設定高さに揃う。The lath plates (31) are laterally connected as necessary, and at this time, the adjacent lath plates (31) (31) are fitted in the groove (20) by overlapping the end ribs (32) of each other. A spacer (71) is inserted in the groove (20) of the runner (2), and the upper end of the frame wall (3) is aligned at the set height over the entire length.
【0027】上記ランナー(2)と同様のランナー(2a)を
溝開口を下向きにし、突片(23)を外向きにして枠壁(3)
の上端に被せる。A runner (2a) similar to the above runner (2) has a groove opening downward and a projecting piece (23) facing outward, and a frame wall (3).
Cover the top of.
【0028】セパレータ(4)の両端屈曲片(41)(41)を、
左右の上ランナー(2a)(2a)の突片(23)に開設した連結孔
(25)に嵌めて、枠壁(3)(3)の上端間を所定幅に保持し
て枠壁(3)(3)を連結する。The bent pieces (41) (41) at both ends of the separator (4) are
Connecting holes formed on the protrusions (23) of the left and right upper runners (2a) (2a)
Fitting in (25), the frame walls (3), (3) are held at a predetermined width between their upper ends to connect the frame walls (3), (3).
【0029】上記セパレータ(4)は丸棒の両端を同方向
に直角に屈曲して形成されている。枠壁(3)の外側に角
パイプ製の補強杆(5)を横向きにして、ラス板(31)(31)
を貫通させた番線(51)によって左右の補強杆(5)を結束
する。The separator (4) is formed by bending both ends of a round bar at right angles in the same direction. Outside the frame wall (3), the reinforcing rods (5) made of square pipes are placed sideways and the lath plates (31) (31)
The left and right reinforcing rods (5) are bound by the numbered wire (51) penetrating through.
【0030】枠壁(3)(3)間にコンクリートを打設す
る。コンクリートが固化すれば、 補強杆(5)を外す。Concrete is poured between the frame walls (3) and (3). Once the concrete has solidified, remove the reinforcing rod (5).
【0031】図6に示す如く、両側面がラス板(31)(31)
にてにて補強され、枠壁(3)の上端に断面コ字状のラン
ナー(2a)(2a)が被さって、ランナーの角部が梁の稜とな
っているコンクリート構築構造が完成する。As shown in FIG. 6, both sides are lath plates (31) (31).
The runners (2a) and (2a) having a U-shaped cross section are covered on the upper end of the frame wall (3) to complete the concrete construction structure in which the corners of the runners are the ridges of the beam.
【0032】上記の如く、リブ(32)を縦向きにしたラス
板(31)をその下端を下ランナー(2)の溝(20)に嵌めて自
立させるため、従来の様に、リブ(32)を横向きにしたラ
ス板を上ランナーに吊り下げ支持した場合の様に、ラス
板(31)と上ランナーの番線よる面倒な締結作業は必要と
せず、作業性が大幅に向上する。As described above, since the lower end of the lath plate (31) having the ribs (32) oriented vertically is fitted into the groove (20) of the lower runner (2) to be self-supporting, the ribs (32) are formed as in the conventional case. Unlike the case of suspending and supporting a lath plate with the () sideways on the upper runner, troublesome fastening work between the lath plate (31) and the upper runner is not required, and workability is significantly improved.
【0033】ラス板(31)の下端縁は下ランナー(2)の溝
(20)に嵌まって膨らみは防止されるため、コンクリート
梁の側面が波打つことをなくすことができる。The lower edge of the lath plate (31) is the groove of the lower runner (2).
Since the bulge is prevented by fitting into (20), it is possible to prevent the side surface of the concrete beam from waviness.
【0034】下ランナー(2)の溝(20)にスペーサ(71)を
挿入することによって、ラス板(31)を溝(20)に嵌めるだ
けでその上端縁は設定高さに揃い、従来の様に、補強鉄
筋枠(9)上のネジ軸(82)に嵌めたナット(82)によって、
ラス板(31)の吊り下げ高さを調節することに比べて、作
業性が良い。By inserting the spacer (71) into the groove (20) of the lower runner (2), the top edge of the lath plate (31) is aligned with the set height only by fitting the lath plate (31) into the groove (20). Similarly, by the nut (82) fitted to the screw shaft (82) on the reinforcing bar frame (9),
Workability is better than adjusting the hanging height of the lath plate (31).
【0035】本発明の実施において、ラス板(31)に代え
て鉄板を用いることができ、この場合、下ランナー(2)
は、図5の仮想線で示す如く、両側板(22)(22)に複数の
高さ調節孔(26)を縦方向に等間隔に穿設し、前記スペー
サ(71)に代えて、左右の高さ調節孔(26)に跨がってピン
(72)を挿入し、該ピン(72)を鉄板の下端を受ける高さ調
節部材(7)となすこともできる。本発明は上記実施例の
構成に限定されることはなく、特許請求の範囲に記載の
範囲で種々の変形が可能である。In the practice of the present invention, an iron plate may be used in place of the lath plate (31), in which case the lower runner (2) is used.
As shown by the phantom line in FIG. 5, a plurality of height adjusting holes (26) are formed in the both side plates (22) (22) at equal intervals in the vertical direction, and instead of the spacer (71), left and right Pin across the height adjustment hole (26)
It is also possible to insert (72) and use the pin (72) as a height adjusting member (7) for receiving the lower end of the iron plate. The present invention is not limited to the configuration of the above embodiment, and various modifications can be made within the scope of the claims.
【図1】基礎面上に墨線を施した状態の斜面図である。FIG. 1 is a perspective view showing a state where black lines are drawn on a base surface.
【図2】基礎面上にランナーを敷設した状態の斜面図で
ある。FIG. 2 is a perspective view of a runner laid on a foundation surface.
【図3】基礎面上にラス板を立設した状態の斜面図であ
る。FIG. 3 is a perspective view showing a state in which a lath plate is erected on a foundation surface.
【図4】ラス板の上端に上ランナーを被せてセパレータ
にて連結し、補強杆を取付けた状態の斜面図である。FIG. 4 is a perspective view showing a state in which an upper runner is covered on the upper end of a lath plate and connected by a separator, and a reinforcing rod is attached.
【図5】ランナーの要部拡大図である。FIG. 5 is an enlarged view of a main part of a runner.
【図6】コンクリート梁の断面図である。FIG. 6 is a cross-sectional view of a concrete beam.
【図7】従来工法の説明図である。FIG. 7 is an explanatory diagram of a conventional method.
(1) 基礎面 (2) ランナー (20) 溝 (3) 枠壁 (32) リブ (4) セパレータ (7) 高さ調節部材 (9) コンクリート補強用鉄筋枠 (1) Foundation surface (2) Runner (20) Groove (3) Frame wall (32) Rib (4) Separator (7) Height adjusting member (9) Reinforcing frame for concrete reinforcement
Claims (3)
て墨出しを行なう第1工程、 墨出し幅内にてコンクリート補強用の鉄筋枠(9)を組込
む工程、或は墨線(11)に沿って断面略コ字状の長尺ラン
ナー(2)を開口を上向きにして固定配備する工程を、前
後を問わず行なう第2、第3工程、 ランナー(2)の溝(20)内に高さ調節部材(7)を挿入し、
リブ(32)を縦向にしたラス板(31)或は鉄板の下端縁を該
溝(20)に嵌めて枠壁(3)を形成する第4工程、 両枠壁(3)(3)の上端に断面略コ字状の長尺ランナー(2
a)(2a)を開口を下向きにして被せ、左右の上ランナー(2
a)(2a)間をセパレータ(4)にて所定の間隔を保って連結
する第5工程、 枠壁(3)(3)間にコンクリートを打設する第6工程を含
むコンクリート構築法。1. A first step of marking out according to a wall thickness to be built on a foundation surface (1), a step of incorporating a reinforcing bar frame (9) for concrete reinforcement within the marking width, or The second and third steps of performing the step of fixedly deploying the long runner (2) having a substantially U-shaped cross section along the black line (11) with the opening facing upward, the groove ( Insert the height adjustment member (7) into 20),
The fourth step of fitting the lower end edge of the lath plate (31) or iron plate with the ribs (32) in the vertical direction into the groove (20) to form the frame wall (3), both frame walls (3) (3) At the upper end of the long runner (2
a) (2a) with the opening facing downwards, and put the left and right upper runners (2
A concrete construction method including a fifth step of connecting a) and (2a) with a separator (4) at a predetermined interval, and a sixth step of placing concrete between the frame walls (3) and (3).
略等間隔に切り起こして底板(21)の延長上に突片(23)を
形成し、該突片に釘孔(24)を開設したコンクリート構築
用ランナー。2. A projecting piece (23) is formed on the extension of the bottom plate (21) by cutting and raising one side plate (22) at substantially equal intervals and having a substantially U-shaped cross section. A concrete construction runner with holes (24).
た枠壁(3)(3)にて補強され、枠壁(3)の上端に断面コ
字状のランナー(2a)(2a)が被さって、ランナーの角部が
梁の稜となっているコンクリート構築構造。3. Both sides are reinforced by frame walls (3) and (3) formed of lath plates (31) or metal plates, and runners (2a) having a U-shaped cross section are provided at the upper ends of the frame walls (3). ) (2a) is covered, the concrete construction structure in which the corner of the runner is the ridge of the beam.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP26450191A JPH076243B2 (en) | 1991-10-14 | 1991-10-14 | Concrete construction method, construction runner and construction structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP26450191A JPH076243B2 (en) | 1991-10-14 | 1991-10-14 | Concrete construction method, construction runner and construction structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH05340013A JPH05340013A (en) | 1993-12-21 |
| JPH076243B2 true JPH076243B2 (en) | 1995-01-30 |
Family
ID=17404115
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP26450191A Expired - Lifetime JPH076243B2 (en) | 1991-10-14 | 1991-10-14 | Concrete construction method, construction runner and construction structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH076243B2 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001146751A (en) * | 1999-11-22 | 2001-05-29 | Alinco Inc | Runner for throwaway formwork |
| JP2002309775A (en) * | 2001-04-13 | 2002-10-23 | Ishiyama:Kk | Form using liner |
| KR102198165B1 (en) * | 2018-09-04 | 2021-01-04 | 백두산업 주식회사 | Aseismicity wall permanent form unit and Wall construction method using the same |
-
1991
- 1991-10-14 JP JP26450191A patent/JPH076243B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH05340013A (en) | 1993-12-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US6003278A (en) | Monolithic stud form for concrete wall production | |
| US5174083A (en) | Concrete slab forming system | |
| US5839249A (en) | Foam block wall and fabrication method | |
| US6023902A (en) | Frame structure and method of construction by using the same | |
| US5501057A (en) | Unit masonry fence and method for erecting | |
| US5803669A (en) | Thermal-insulated concrete forming system | |
| US4700523A (en) | Reinforcing frame work for constructing reinforced concrete structure | |
| CN102791936A (en) | Building unit for concrete structure and method of executing construction using said building unit | |
| JP3735781B2 (en) | Double bar spacer | |
| JPH076243B2 (en) | Concrete construction method, construction runner and construction structure | |
| JPH0756172B2 (en) | Mold panel | |
| US4505088A (en) | Method of constructing arcuate structures | |
| KR102065623B1 (en) | the improved yoke truss and the wall form structure using the same | |
| RU2107789C1 (en) | Shuttering for walls | |
| JPH0637160Y2 (en) | Sleeve fixed hardware | |
| CN219498851U (en) | Pre-buried line box with installation fixed knot constructs | |
| JPH07286332A (en) | Execution method of precast concrete foundation and installation spacer used therefor | |
| JP2577145Y2 (en) | Width stop member for base formwork construction for housing foundation | |
| JP2627574B2 (en) | Building structure and construction method for tiled roof | |
| JPH0227062Y2 (en) | ||
| WO1983001975A1 (en) | A method of erecting a building construction and a reinforcing element for use in the method | |
| JP2000257078A (en) | Construction method of mat foundation to use pc foundation beam member and pc support frame for pc foundation beam member | |
| JP2700096B2 (en) | Concrete formwork | |
| GB2076868A (en) | Frame member | |
| JPH0821088A (en) | Fixing structure of sheathing board wire netting plate requiring no removal in concrete form |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19950725 |