JPH0768858B2 - Construction method of large-section shield tunnel - Google Patents
[go: Go Back, main page]

JPH0768858B2 - Construction method of large-section shield tunnel - Google Patents

Construction method of large-section shield tunnel

Info

Publication number
JPH0768858B2
JPH0768858B2 JP4345226A JP34522692A JPH0768858B2 JP H0768858 B2 JPH0768858 B2 JP H0768858B2 JP 4345226 A JP4345226 A JP 4345226A JP 34522692 A JP34522692 A JP 34522692A JP H0768858 B2 JPH0768858 B2 JP H0768858B2
Authority
JP
Japan
Prior art keywords
section
tunnel
small
shield
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP4345226A
Other languages
Japanese (ja)
Other versions
JPH06167186A (en
Inventor
豊 加島
正巳 井上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiho Corp
Original Assignee
Daiho Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiho Corp filed Critical Daiho Corp
Priority to JP4345226A priority Critical patent/JPH0768858B2/en
Publication of JPH06167186A publication Critical patent/JPH06167186A/en
Publication of JPH0768858B2 publication Critical patent/JPH0768858B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、大断面シールドトンネ
ルの築造方法に係り、特に大断面のシールドトンネルを
安全にかつ経済的に築造するための大断面シールドトン
ネルの築造方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a large-section shield tunnel, and more particularly to a method for constructing a large-section shield tunnel for safely and economically constructing a large-section shield tunnel.

【0002】[0002]

【従来の技術】従来、例えば超大断面のシールドトンネ
ルを築造する場合、1台の超大断面密閉機械式シールド
を使って超大断面を一度に掘削し、築造する方法が採ら
れている。
2. Description of the Related Art Conventionally, when constructing a shield tunnel having a super-large cross section, for example, a method of excavating and constructing a super-large cross section at once using one super-large cross section hermetic mechanical shield has been adopted.

【0003】[0003]

【発明が解決しようとする課題】しかし、前記従来技術
では次のような問題があった。
However, the above-mentioned prior art has the following problems.

【0004】(1)シールドマシンが超大型化するた
め、マシン本体の分割数が多くなる。そのため、運搬,
組立に時間が掛かる。また、トンネルの掘削の到達時
に、超大型のシールドマシンを解体するためにも多くの
時間が掛かる。そのため、全体の工期が長くなる。 (2)シールドマシンが超大型化すると、マシン製作に
多くの日数と費用が掛かる。 (3)超大型シールドマシンに内包させるセグメントも
勿論大型化し、セグメントが高価になる。 (4)大型化したセグメントの1ピースを運搬最大重量
としても、分割数が多くなるため、運搬に時間と費用が
掛かる。 (5)超大型シールドマシンの昼,夜間作業によって発
生する掘削土砂は、非常に多量になり、土砂運搬のため
のダンプトラックが多数必要になり、交通障害を起こ
す。 (6)超大型の密閉機械式シールドの場合、掘削に大容
量の電力を必要とするため、大型の電力設備を要する。 (7)一度に大断面の切羽を掘削するため、切羽の安定
が難しくなる。
(1) Since the shield machine becomes extremely large, the number of divisions of the machine body increases. Therefore, transportation,
It takes time to assemble. Also, it takes a lot of time to dismantle the super-sized shield machine when the tunnel excavation is reached. Therefore, the whole construction period becomes long. (2) If the shield machine becomes extremely large, it will take many days and cost to manufacture the machine. (3) Of course, the segment included in the super-large shield machine also becomes large, and the segment becomes expensive. (4) Even if one piece of a large-sized segment is used as the maximum weight for transportation, the number of divisions is large, so that it takes time and money to transport. (5) The amount of excavated earth and sand generated by day and night work of the ultra-large shield machine becomes extremely large, and a large number of dump trucks are required to carry the earth and sand, which causes a traffic obstacle. (6) In the case of a super-large sealed mechanical shield, a large amount of electric power is required for excavation, and thus a large electric power facility is required. (7) Since it is necessary to excavate a large-width cutting face at once, it becomes difficult to stabilize the cutting face.

【0005】本発明は、上記の事情に鑑みてなされたも
ので、その目的とするところは、小断面シールド機を使
って施工でき、また小型の電気設備で足り、しかも安全
かつ経済的に大断面のシールドトンネルを築造し得る大
断面シールドトンネルの築造方法を提供しようとするも
のである。
The present invention has been made in view of the above circumstances, and it is an object of the present invention to carry out construction by using a small cross section shield machine, and to use a small electric equipment, which is safe and economical. An object of the present invention is to provide a method for constructing a large-section shield tunnel capable of constructing a shield tunnel having a cross section.

【0006】[0006]

【課題を解決するための手段】上記目的を達成するた
め、本発明は略矩形断面の小断面シールドトンネル1,
2,3,…を、隣接部で低強度の裏込材または場所打ち
コンクリート18を重ねるように築造して環状覆工体2
0を形成し、その後相隣接する小断面シールドトンネル
1,2,3,…の側壁部のセグメント17を順次撤去し
つつ、そのセグメント17,17間の裏込材または場所
打ちコンクリート18を徹去して相隣接する小断面シー
ルドトンネル1,2,3,…の側壁部を貫いたトンネル
23を形成し、これと並行してまたはトンネル形成後
に、トンネル23内に構造材または補強材24,25を
設置し、ついでトンネル23内にコンクリート28を打
設し、このコンクリート28の硬化後、環状覆工体20
内の土砂を掘削し排出して大断面のトンネル31を築造
するようにしたものである。
To achieve the above object, the present invention provides a small-section shield tunnel 1 having a substantially rectangular section.
The annular lining body 2 is constructed by constructing 2, 3, ... In such a manner that low-strength backing material or cast-in-place concrete 18 is overlapped in the adjacent portion.
0 is formed, and then the segments 17 of the side wall portions of the adjacent small cross-section shield tunnels 1, 2, 3, ... Are sequentially removed, and the backing material or the cast-in-place concrete 18 between the segments 17, 17 is removed. Then, the tunnels 23 are formed through the side wall portions of the small-section shield tunnels 1, 2, 3, ... Adjacent to each other, and in parallel with this or after the tunnels are formed, the structural material or the reinforcing material 24, 25 is formed in the tunnel 23. Then, concrete 28 is placed in the tunnel 23, and after hardening of the concrete 28, the annular lining body 20
The earth and sand in the inside are excavated and discharged to construct a tunnel 31 having a large cross section.

【0007】[0007]

【作用】本発明では、略矩形断面の小断面シールドトン
ネル1,2,3,…を多数築造する。このとき、小断面
シールドトンネル1,2,3,…を隣接部で裏込材また
は場所打ちコンクリート18を重ねるようにして築造し
て行き、完成断面21を内包する環状覆工体20を形成
する。
In the present invention, a large number of small-section shield tunnels 1, 2, 3, ... Of substantially rectangular section are constructed. At this time, the small-section shield tunnels 1, 2, 3, ... Are constructed by stacking backfill material or cast-in-place concrete 18 at adjacent portions to form an annular lining body 20 including a completed cross-section 21. .

【0008】その後、相隣接する小断面シールドトンネ
ル1,2,3,…の側壁部のセグメント17を順次撤去
する。また、相隣接する小断面シールドトンネル1,
2,3,…のセグメント17,17間の裏込材または場
所打ちコンクリート18を撤去し、相隣接する小断面シ
ールドトンネル1,2,3,…の側壁部を貫いたトンネ
ル23を形成する。
After that, the segments 17 on the side walls of the adjacent small cross section shield tunnels 1, 2, 3, ... Are sequentially removed. In addition, the small-section shield tunnels 1, which are adjacent to each other,
The backing material or cast-in-place concrete 18 between the segments 17, 17 of 2, 3, ... Is removed to form a tunnel 23 that penetrates the side walls of the small-section shield tunnels 1, 2, 3 ,.

【0009】前記トンネル23の形成と並行してまたは
トンネル23の形成後に、トンネル23内に構造材また
は補強材24,25を設置し、ついでトンネル23内に
コンクリート28を打設し、環状覆工体20に必要な強
度を持たせる。
In parallel with the formation of the tunnel 23 or after the formation of the tunnel 23, structural materials or reinforcing materials 24 and 25 are installed in the tunnel 23, and then concrete 28 is placed in the tunnel 23 to form an annular lining. Give the body 20 the necessary strength.

【0010】前記コンクリート28の硬化後、環状覆工
体20内の土砂(地山G)を掘削し排出して大断面のト
ンネル31を築造する。
After the concrete 28 is hardened, the earth and sand (ground material G) in the annular lining body 20 is excavated and discharged to construct a tunnel 31 having a large cross section.

【0011】このように、本発明では完成断面21を内
包する環状覆工体20を、多数の小断面シールドトンネ
ル1,2,3,…を連結して構築するようにしているの
で、小断面シールド機を使って施工でき、したがって仮
設備が少なくて済み、施工ヤードも小さくて済むし、小
型の電力設備で足りるし、切羽を容易に安定させること
もできる。
As described above, in the present invention, the annular lining body 20 including the completed cross section 21 is constructed by connecting a large number of small cross section shield tunnels 1, 2, 3, ... Construction can be done using a shield machine, therefore there is less temporary equipment, the construction yard can be smaller, a small power facility is sufficient, and the face can be easily stabilized.

【0012】また、大型のシールドマシンを使う必要が
ないので、安全に施工できる。しかも、シールドマシン
の運搬,組立を短時間で行うことができ、トンネル掘削
の到達時にシールドマシンを短時間で分解でき、マシン
製作の日数,費用も低減でき、シールドマシンに内包さ
れるセグメントの小型化,軽量化,低価格化を図ること
ができる等が相俟ち、大断面トンネルを経済的に有利に
構築することが可能となる。
Further, since it is not necessary to use a large shield machine, the construction can be carried out safely. Moreover, the shield machine can be transported and assembled in a short time, the shield machine can be disassembled in a short time when the tunnel excavation is reached, the number of days and cost for manufacturing the machine can be reduced, and the segment included in the shield machine can be small in size. In combination with cost reduction, weight reduction, and cost reduction, it becomes possible to construct a large-section tunnel economically.

【0013】[0013]

【実施例】以下、本発明の実施例を図面に基づいて説明
する。図1は完成断面を内包する環状覆工体の一例を示
す断面図、図2および図3は前記環状覆工体の構築過程
を示す図、図4および図5は環状覆工体を形成している
小断面シールドトンネルの掘削過程を示す図である。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a sectional view showing an example of an annular lining body including a completed cross section, FIGS. 2 and 3 are views showing a process of constructing the annular lining body, and FIGS. It is a figure which shows the excavation process of the small cross section shield tunnel which is doing.

【0014】まず、本発明方法では環状覆工体20を構
築する多数の小断面シールドトンネル1,2,3,…,
16を1台または複数台のシールド機によって築造する
ものであるが、図2,図3に示すこの実施例では1台の
シールド機によって築造する例を示している。
First, according to the method of the present invention, a large number of small-section shield tunnels 1, 2, 3, ...
Although 16 is built by one or a plurality of shield machines, this embodiment shown in FIGS. 2 and 3 shows an example of building by one shield machine.

【0015】そして、図2,図3から分かるように、小
断面シールドトンネル1,3,5,…というように、1
個置きに築造して行く。各小断面シールドトンネル1,
3,5,…は、セグメント17と、これを外包する裏込
材または場所打ちコンクリート18とで形成され、セグ
メント17の内部は坑内19となっている。前記セグメ
ント17は、トンネルの内部よりボルト,ナットで組
立,解体可能に締結されている。前記裏込材または場所
打ちコンクリート18は、無筋コンクリートの低強度の
もので、一軸圧縮強度は10〜50kgf/cm2 程度
とされ、厚さは通常のシールド工法によって発生するテ
ールボイドよりかなり厚くしている。その理由は、図3
に示すように、1個置きに築造された小断面シールドト
ンネル1,3,5,…間に、他の小断面シールドトンネ
ル4,6,…を築造し、隣接する小断面シールド同士を
接続し、環状覆工体20を構築して行く際に、互いに裏
込材または場所打ちコンクリート18の部分で重なり合
い、接続しやすいようにするためである。
As can be seen from FIGS. 2 and 3, small-section shield tunnels 1, 3, 5, ...
Build every other piece. Each small section shield tunnel 1,
.. are formed of a segment 17 and a backfill material or cast-in-place concrete 18 that encloses the segment 17, and the inside of the segment 17 is a pit 19. The segment 17 is fastened so that it can be assembled and disassembled from the inside of the tunnel with bolts and nuts. The backfill material or cast-in-place concrete 18 is a non-reinforced concrete having a low strength, a uniaxial compressive strength of about 10 to 50 kgf / cm 2, and a thickness considerably thicker than a tail void generated by a usual shield construction method. ing. The reason is shown in Figure 3.
As shown in, other small cross section shield tunnels 4, 6, ... are built between every other small cross section shield tunnels 1, 3, 5, ..., and adjacent small cross section shields are connected to each other. This is because, when the annular lining body 20 is constructed, the backing material or the cast-in-place concrete 18 overlap each other to facilitate connection.

【0016】前記小断面シールドトンネル1,3,5,
…は、例えば小断面シールドトンネル1について説明す
ると、図4および図5に示すように、矩形の小断面シー
ルド機100により掘削し、築造する。その小断面シー
ルド機100は、シールド外筒101と、スクリューコ
ンベヤ等の排土装置102と、推進ジャッキ103と、
加圧板105を有する覆工コンクリート加圧ジャッキ1
04と、コンクリート圧入口107を有するコンクリー
ト圧入管106と、機内裏込め注入管108と、裏込材
または場所打ちコンクリート18の厚さを決めるテール
部109とを備えている。
The small cross section shield tunnels 1, 3, 5,
For example, when the small cross section shield tunnel 1 is explained, as shown in FIGS. 4 and 5, the small cross section shield machine 100 excavates and builds. The small cross section shield machine 100 includes a shield outer cylinder 101, an earth discharging device 102 such as a screw conveyor, a propulsion jack 103,
Lining concrete pressure jack 1 having pressure plate 105
04, a concrete press-fitting pipe 106 having a concrete press-fitting port 107, an in-machine backfill injection pipe 108, and a tail portion 109 that determines the thickness of the backfill material or cast-in-place concrete 18.

【0017】そして、前記矩形の小断面シールド機10
0では、山留め用のセグメント17とシールド外筒10
1の間は、裏込材または場所打ちコンクリート18の厚
さを取るため、大きく開けられている。しかして、この
小断面シールド機100ではセグメント17に反力を取
り、推進ジャッキ103によりシールド外筒101を推
進させ、地山Gを掘削する。掘削した土砂は、排土装置
102により小断面シールド機100の後方へ運び、排
出する。また、シールド機の推進と同時にセグメント1
7とシールド外筒101間の空隙に、コンクリート圧入
管106およびコンクリート圧入口107を通じて低強
度のコンクリートを圧入し、裏込材または場所打ちコン
クリート18として打設する。その際、セグメント17
とシールド外筒101間に、前記圧入された裏込材また
は場所打コンクリート18がシールド機内に侵入しない
ように、加圧板105によりブロックする。さらに、前
記加圧板105を介して覆工コンクリート加圧ジャッキ
104により、前記セグメント17とシールド外筒10
1間の空隙に打設された裏込材または場所打ちコンクリ
ート18が硬化するまで圧力を掛け、地山Gの崩壊を防
止しながら掘進する。さらにまた、裏込材または場所打
ちコンクリート18の厚さに合わせて厚くしたテール部
109の後方に、シールド機の推進とともに機内裏込め
注入管108を用いて低強度の裏込材または場所打ちコ
ンクリート18を打設する。
Then, the rectangular small-section shield machine 10 is used.
At 0, the mountain retaining segment 17 and the shield outer cylinder 10
Between 1 is wide open to take the thickness of the backfill or cast-in-place concrete 18. Then, in this small-section shield machine 100, a reaction force is applied to the segment 17, and the shield outer cylinder 101 is propelled by the propulsion jack 103 to excavate the natural ground G. The excavated earth and sand is carried to the rear of the small cross section shield machine 100 by the earth discharging device 102 and discharged. At the same time as the promotion of the shield machine, segment 1
A low-strength concrete is press-fitted into the space between the shield tube 7 and the shield outer cylinder 101 through the concrete press-fitting pipe 106 and the concrete press-fitting port 107, and is poured as backfill material or cast-in-place concrete 18. At that time, segment 17
And the shield outer cylinder 101, the backing material or the cast-in-place concrete 18 press-fitted is blocked by a pressure plate 105 so as not to enter the shield machine. Further, the segment 17 and the shield outer cylinder 10 are provided by the lining concrete pressure jack 104 via the pressure plate 105.
Pressure is applied until the backfill material or the cast-in-place concrete 18 placed in the space between the ones is hardened to prevent the ground G from collapsing and then proceed with the excavation. Furthermore, behind the tail portion 109 thickened according to the thickness of the backfill material or cast-in-place concrete 18, the backfill material or cast-in-place concrete of low strength is used by using the in-machine backfill injection pipe 108 together with the propulsion of the shield machine. Place 18

【0018】以上の作業を繰り返し行うことによって、
1個置きに小断面シールドトンネル1,3,5,…を築
造したのち、同様の作業により前記小断面シールドトン
ネル1,3,5,…間に、他の小断面シールドトンネル
2,4,…を順次築造して行き、隣接する小断面シール
ドトンネルの裏込材または場所打ちコンクリート18の
部分を重ね合わせ、図1に示すように、小断面シールド
トンネル1,3,5,…,15と、他の小断面シールド
トンネル2,4,…,16とを連結し、この実施例では
矩形の完成断面21を内包する一体的な構造物である環
状覆工体20を構築する。
By repeating the above work,
After building small-section shield tunnels 1, 3, 5, ... Every other one, by the same work, between the small-section shield tunnels 1, 3, 5, ..., Other small-section shield tunnels 2, 4, ... Are successively built, and the backing material or the cast-in-place concrete 18 of adjacent small cross section shield tunnels are overlapped, and as shown in FIG. 1, small cross section shield tunnels 1, 3, 5, ... , 16 are connected to each other to construct an annular lining body 20 which is an integral structure including a rectangular completed cross section 21 in this embodiment.

【0019】次に、図6は環状覆工体を構成している小
断面シールドトンネルを接続する過程を示す図、図7は
図6のA−A線断面図、図8および図9は図6に続く小
断面シールドトンネルを接続する過程を示す図、図10
は完工された大断面シールドトンネルの一例を示す断面
図である。前述のごとく、小断面シールドトンネル1,
2,3,…,16を連結した環状覆工体20を構築した
のち、小断面シールドトンネル1,2,3,…,16を
一連に接続する。その際、まず図6および図7に示すよ
うに、隣接する小断面シールドトンネル同士の間22に
介在しているセグメント17を例えば1つ置きに外し、
部分的に撤去する。次に、隣接する小断面シールドトン
ネル同士の間22に打設されている低強度の裏込材また
は場所打ちコンクリート18、つまり覆工コンクリート
を人力または機械力により掘削し、相隣接する小断面シ
ールドトンネル1,2,3,…,16の側壁部を貫いた
トンネル23を形成する。
Next, FIG. 6 is a diagram showing a process of connecting the small cross section shield tunnels forming the annular lining body, FIG. 7 is a cross sectional view taken along the line AA of FIG. 6, and FIGS. FIG. 10 is a diagram showing a process of connecting a small cross section shield tunnel following FIG.
FIG. 4 is a cross-sectional view showing an example of a completed large-section shield tunnel. As mentioned above, small-section shield tunnel 1,
After constructing the annular lining body 20 in which 2, 3, ..., 16 are connected, the small-section shield tunnels 1, 2, 3, ..., 16 are connected in series. At that time, as shown in FIGS. 6 and 7, first, for example, every other segment 17 interposed between adjacent small cross-section shield tunnels 22 is removed,
Partially remove it. Next, the low-strength backfill material or cast-in-place concrete 18 that is placed between the adjacent small-section shield tunnels 22, that is, the lining concrete is excavated by manpower or mechanical force, and adjacent small-section shields A tunnel 23 penetrating the side walls of the tunnels 1, 2, 3, ..., 16 is formed.

【0020】ついで、図8に示すように、前記トンネル
23を保持するために縦,横の構造材または補強材2
4,25を設置する。この構造材または補強材24,2
5には、鉄筋,鉄骨,PC鋼線等を用いる。また、前記
構造材または補強材24,25はセグメント17を貫通
させて設置してもよく、隣接する小断面シールドトンネ
ル間に介在しているセグメント17を部分的に取り外し
て設置してもよい。
Then, as shown in FIG. 8, vertical and horizontal structural members or reinforcing members 2 for holding the tunnel 23.
Install 4,25. This structure or reinforcement 24,2
For 5, a reinforcing bar, a steel frame, a PC steel wire or the like is used. Further, the structural material or the reinforcing material 24, 25 may be installed by penetrating the segment 17, or the segment 17 interposed between adjacent small cross section shield tunnels may be partially removed and installed.

【0021】さらに、前記トンネル23内に図8に示す
ごとく、所定の間隔をおいて型枠26を設置する。
Further, as shown in FIG. 8, molds 26 are installed in the tunnel 23 at predetermined intervals.

【0022】次に、図8および図9に示すように、前記
型枠26により仕切られた区域27にコンクリート28
を打設する。なお、図面には示していないが、シールド
トンネルの発進,到達点にも、所定の間隔をおいて型枠
を設置し、その型枠により仕切られた区域内にコンクリ
ートを打設する。また、前記区域27の外側に、作業空
間27′を形成する。しかし、前記作業空間27′は、
使用後コンクリート28で埋める。さらに、前記区域2
7内にコンクリート28を打設する前に、必要により通
路形成用の型枠や、電力,通信用等の管路30(図10
参照)を設けておく。前記区域27に打設されたコンク
リート28の硬化後、型枠26を撤去する。
Next, as shown in FIGS. 8 and 9, concrete 28 is placed in an area 27 partitioned by the mold 26.
To place. Although not shown in the drawing, formwork is also installed at predetermined intervals at the starting point and reaching point of the shield tunnel, and concrete is placed in the area partitioned by the formwork. A working space 27 'is formed outside the area 27. However, the working space 27 '
After use, fill with concrete 28. Further, the area 2
Before the concrete 28 is placed in the inside of the 7, if necessary, a formwork for forming a passage, a conduit 30 for electric power, communication, etc. (see FIG. 10).
(See). After the concrete 28 cast in the area 27 is hardened, the form 26 is removed.

【0023】しかして、図10に示すように、一連の小
断面シールドトンネル1〜16により構築された環状覆
工体20を、構造材または補強材24,25およびコン
クリート28により必要な強度に仕上げ、かつ必要な個
所に作業用や排水用等の通路29、および電力,通信用
等の管路30を設けたのち、環状覆工体20の内部の土
砂、つまりこの実施例では地山Gを常法により掘削し、
その土砂を排出して行き、この実施例では矩形の完成断
面21を持った大断面のトンネル31を築造する。な
お、裏込材、あるいは場所打ちコンクリート部分は、内
空断面を確保するために、内側は撤去する事も可能であ
る。
As shown in FIG. 10, however, the annular lining body 20 constructed by a series of small-section shield tunnels 1 to 16 is finished to have a required strength by using structural materials or reinforcing materials 24 and 25 and concrete 28. After the passage 29 for work and drainage and the pipeline 30 for electric power and communication are provided at necessary places, the earth and sand inside the annular lining body 20, that is, the ground G in this embodiment, is removed. Drilled by the usual method,
The earth and sand are discharged, and in this embodiment, a large section tunnel 31 having a rectangular completed section 21 is constructed. Incidentally, the backing material or the cast-in-place concrete portion can be removed on the inside in order to secure an inner cross section.

【0024】そして、前述のごとく、小断面シールドト
ンネル1〜16を、隣接部で裏込材または場所打ちコン
クリート18を重ねるようにして形成する環状覆工体2
0の施工→隣接する小断面シールドトンネル間のセグメ
ント17の部分的な撤去→隣接する小断面シールドトン
ネル同士の間22の裏込材または場所打ちコンクリート
18を撤去し、相隣接する小断面シールドトンネルの側
壁部を貫いて形成するトンネル23の施工→構造材また
は補強材24,25の設置→前記トンネル23内への型
枠26の設置→型枠26で仕切られた区域27へのコン
クリート28の打設→環状覆工体20の内部の地山Gの
掘削および排出作業を、トンネルの到達点まで行うこと
により、大断面のトンネル31を安全にかつ経済的に築
造することが可能となる。
Then, as described above, the annular lining body 2 is formed by forming the small-section shield tunnels 1 to 16 by overlapping the backfill material or the cast-in-place concrete 18 at the adjacent portions.
Construction of 0 → Partial removal of segment 17 between adjacent small-section shield tunnels → Removal of backfill material or cast-in-place concrete 18 between adjacent small-section shield tunnels 22 and adjacent small-section shield tunnels Construction of the tunnel 23 formed through the side wall of the structure → Installation of structural materials or reinforcements 24 and 25 → Installation of the formwork 26 in the tunnel 23 → Installation of concrete 28 in the area 27 partitioned by the formwork 26 Placing → Excavation of the natural ground G inside the annular lining body 20 and discharge work to the arrival point of the tunnel makes it possible to construct the large-section tunnel 31 safely and economically.

【0025】以上、矩形の小断面シールド機によって、
矩形の大断面シールドトンネルを築造する方法について
述べたが、本発明にかかる築造方法によれば、略矩形断
面のシールドトンネルを上下方向または/および左右方
向に複数個連接した大断面シールドトンネルを築造する
こともできるし、矩形断面以外の異形断面の大断面シー
ルドトンネルを築造することもできる。
As described above, by the rectangular small cross section shield machine,
The method of constructing a rectangular large-section shield tunnel has been described. According to the constructing method of the present invention, a large-section shield tunnel is constructed by connecting a plurality of shield tunnels having a substantially rectangular cross section in the vertical direction and / or the left-right direction. It is also possible to construct a large cross section shield tunnel having a modified cross section other than a rectangular cross section.

【0026】[0026]

【発明の効果】以上のように、本発明方法では略矩形断
面の小断面シールドトンネル1,2,3,…を、隣接部
低強度の裏込材または場所打ちコンクリート18を重
ねるように築造して環状覆工体20を形成し、その後相
隣接する小断面シールドトンネル1,2,3,…の側壁
部のセグメント17を順次撤去しつつ、そのセグメント
17,17間の裏込材または場所打ちコンクリート18
を撤去して相隣接する小断面シールドトンネル1,2,
3,…の側壁部を貫いたトンネル23を形成し、これと
並行してまたはトンネル形成後に、トンネル23内に構
造材または補強材24,25を設置し、ついでトンネル
23内にコンクリート28を打設し、このコンクリート
28の硬化後、環状覆工体20内の土砂を掘削し排出し
て大断面のトンネル31を築造するようにしているの
で、小断面シールド機を使って施工でき、したがって仮
設備が少なくて済み、施工ヤードも小さくて済むし、小
型の電力設備で足りるし、切羽を容易に安定させること
もできるという効果がある。また、環状覆工体20の築
造の際の裏込材は低強度のものであるため、次工程で容
易に切削でき、掘進速度が遅くなったりすることがな
い。
As described above, according to the method of the present invention, small-section shield tunnels 1, 2, 3, ... Of substantially rectangular cross-section are constructed such that low-strength backing materials or cast-in-place concrete 18 are overlapped at adjacent portions. To form the annular lining body 20, and then sequentially remove the segments 17 of the side walls of the small-section shield tunnels 1, 2, 3, ... Adjacent to each other, and at the same time, backing material or place between the segments 17, 17. Pouring concrete 18
Of small cross section shield tunnels 1, 2
A tunnel 23 penetrating the side wall portions of 3, ... Is formed, and in parallel with this or after the tunnel is formed, structural materials or reinforcing materials 24 and 25 are installed, and then concrete 28 is poured into the tunnel 23. Since the concrete 28 is hardened and the earth and sand in the annular lining body 20 is excavated and discharged to construct the tunnel 31 having a large cross section, it can be constructed using a small cross section shield machine. There are advantages that the equipment is small, the construction yard is small, a small electric power equipment is sufficient, and the face can be easily stabilized. In addition, the construction of the annular lining body 20
Since the backing material used for manufacturing has low strength,
It can be easily cut and the excavation speed will not slow down.
Yes.

【0027】また、本発明方法では大型のシールドマシ
ンを使う必要がないので、安全に施工できるという効果
を有する外、シールドマシンの運搬,組立を短時間で行
うことができ、トンネル掘削の到達時にもシールド機を
短時間で分解でき、マシン製作の日数,費用も低減で
き、シールドマシンに内包されるセグメントの小型化,
軽量化,低価格化を図ることができる等が相俟ち、大断
面トンネルを経済的に有利に構築し得る効果がある。
Further, since the method of the present invention does not require the use of a large shield machine, it has the effect of being able to carry out the work safely, and in addition, the shield machine can be transported and assembled in a short time, and when the tunnel excavation is reached. The shield machine can be disassembled in a short time, the number of days and cost for manufacturing the machine can be reduced, and the segment included in the shield machine can be downsized.
Combined with the reduction in weight and cost, it has the effect of being able to construct a large cross-section tunnel economically.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1は完成断面を内包する環状覆工体の一例を
示す断面図である。
FIG. 1 is a cross-sectional view showing an example of an annular lining body including a completed cross section.

【図2】図1に示す環状覆工体の構築過程を示す図であ
る。
FIG. 2 is a diagram showing a process of constructing the annular lining body shown in FIG.

【図3】図2に続く環状覆工体の構築過程を示す図であ
る。
FIG. 3 is a diagram showing a process of constructing the annular lining body subsequent to FIG.

【図4】環状覆工体を構成している小断面シールドトン
ネルの掘削過程を示す図である。
FIG. 4 is a diagram showing an excavation process of a small cross section shield tunnel which constitutes an annular lining body.

【図5】図4に続く小断面シールドトンネルの掘削過程
を示す図である。
FIG. 5 is a diagram showing an excavation process of the small cross-section shield tunnel following FIG. 4;

【図6】環状覆工体を構成している小断面シールドトン
ネルを接続する過程を示す図である。
FIG. 6 is a diagram showing a process of connecting small cross-section shield tunnels forming an annular lining body.

【図7】図6のA−A線断面図である。7 is a cross-sectional view taken along the line AA of FIG.

【図8】図6に続く小断面シールドトンネルを接続する
過程を示す図である。
FIG. 8 is a diagram showing a process of connecting the small cross section shield tunnels following FIG. 6;

【図9】図8に続く小断面シールドトンネルを接続する
過程を示す図である。
FIG. 9 is a diagram showing a process of connecting the small cross-section shield tunnels following FIG. 8;

【図10】完工した大断面のトンネルの一例を示す断面
図である。
FIG. 10 is a sectional view showing an example of a completed large-section tunnel.

【符号の説明】[Explanation of symbols]

1〜16 小断面シールドトンネル 17 セグメント 18 裏込材または場所打ちコンクリート 20 環状覆工体 21 完成断面 22 隣接するシールドトンネル同士の間 23 相隣接する小断面シールドトンネル間の側壁部を
貫いて形成したトンネル 24,25 構造材または補強材 26 型枠 27 型枠で仕切られた区域 28 コンクリート 31 完成した大断面のトンネル 100 小断面シールド機 101 シールド外筒 102 排土装置 103 推進ジャッキ 104 覆工コンクリート加圧ジャッキ 105 加圧板 106 コンクリート圧入管 108 機内裏込め注入管 109 シールド外筒のテール部
1-16 Small-section shield tunnel 17 Segment 18 Backfill material or cast-in-place concrete 20 Annular lining body 21 Completed section 22 Between adjacent shield tunnels 23 Phases Formed through the side wall between adjacent small-section shield tunnels Tunnels 24, 25 Structural or reinforcing materials 26 Formwork 27 Areas partitioned by formwork 28 Concrete 31 Completed large-section tunnel 100 Small-section shield machine 101 Shield outer cylinder 102 Earth-moving device 103 Propulsion jack 104 Lining concrete addition Pressure jack 105 Pressure plate 106 Concrete press fit pipe 108 Inside backfill injection pipe 109 Tail part of shield outer cylinder

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 略矩形断面の小断面シールドトンネル
1,2,3,…を、隣接部で低強度の裏込材または場所
打ちコンクリート18を重ねるように築造して環状覆工
体20を形成し、その後相隣接する小断面シールドトン
ネル1,2,3,…の側壁部のセグメント17を順次撤
去しつつ、そのセグメント17,17間の裏込材または
場所打ちコンクリート18を撤去して相隣接する小断面
シールドトンネル1,2,3,…の側壁部を貫いたトン
ネル23を形成し、これと並行してまたはトンネル形成
後に、トンネル23内に構造材または補強材24,25
を設置し、ついでトンネル23内にコンクリート28を
打設し、このコンクリート28の硬化後、環状覆工体2
0内の土砂を掘削し排出して大断面のトンネル31を築
造することを特徴とする大断面シールドトンネルの築造
方法。
1. An annular lining body 20 is formed by constructing small-section shield tunnels 1, 2, 3, ... Of substantially rectangular cross-section so that low-strength backfill material or cast-in-place concrete 18 is overlapped at adjacent portions. Then, while sequentially removing the segments 17 of the side wall portions of the small-section shield tunnels 1, 2, 3, ... Which are adjacent to each other, the backing material or cast-in-place concrete 18 between the segments 17 and 17 is removed, and the adjacent segments are adjacent to each other. The tunnel 23 that penetrates the side walls of the small-section shield tunnels 1, 2, 3, ... Is formed, and in parallel with this or after the tunnel is formed, the structural material or the reinforcing material 24, 25 is formed in the tunnel 23.
Then, concrete 28 is placed in the tunnel 23, and after hardening of the concrete 28, the annular lining body 2
A method of constructing a large-section shield tunnel, which comprises digging and discharging earth and sand in 0 to construct a large-section tunnel 31.
JP4345226A 1992-12-01 1992-12-01 Construction method of large-section shield tunnel Expired - Fee Related JPH0768858B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4345226A JPH0768858B2 (en) 1992-12-01 1992-12-01 Construction method of large-section shield tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4345226A JPH0768858B2 (en) 1992-12-01 1992-12-01 Construction method of large-section shield tunnel

Publications (2)

Publication Number Publication Date
JPH06167186A JPH06167186A (en) 1994-06-14
JPH0768858B2 true JPH0768858B2 (en) 1995-07-26

Family

ID=18375156

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4345226A Expired - Fee Related JPH0768858B2 (en) 1992-12-01 1992-12-01 Construction method of large-section shield tunnel

Country Status (1)

Country Link
JP (1) JPH0768858B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4022681B2 (en) * 1998-08-31 2007-12-19 鹿島建設株式会社 Construction method of underground structure and shield machine
KR20010063695A (en) * 1999-12-24 2001-07-09 이관희 Method For Deviding And Constructing Underground Tunnel Having Large Cross-section
JP2006082113A (en) * 2004-09-16 2006-03-30 Taisei Corp Earth retaining member cutting apparatus and method, and tunnel forming method using them
CN113622936B (en) * 2021-08-31 2024-07-16 北京首尔工程技术有限公司 New tunneling method and tunneling device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2788953B2 (en) * 1990-06-29 1998-08-20 清水建設株式会社 Structure of tunnel structure
JPH0470499A (en) * 1990-07-10 1992-03-05 Kumagai Gumi Co Ltd Method for constructing underground space and excavator therefor

Also Published As

Publication number Publication date
JPH06167186A (en) 1994-06-14

Similar Documents

Publication Publication Date Title
JP6636773B2 (en) Construction structure and construction method of tunnel lining body
KR100890697B1 (en) Excavation Tunnel Construction Method of Open Tunnel
JP3893056B2 (en) Construction method of underground structure
JPH0768858B2 (en) Construction method of large-section shield tunnel
JP2979044B2 (en) Large-scale underground structures and their construction methods
JPH0340800B2 (en)
JPH04213695A (en) Segment for shield tunnel
JPH07331997A (en) Constructing method of rock cavern
JPH06129189A (en) Vertical shaft construction method using segments
JP2604622B2 (en) Tunnel construction method
JP2804422B2 (en) Foundation construction method
JPH08284597A (en) Shield tunnel lining construction method
JPH04309692A (en) Underground space construction method
JPH04309694A (en) Underground space construction method
JP2560483B2 (en) Construction method of annular girder in underground wall.
JP2617418B2 (en) Construction method of underground large space structure
JPH10159074A (en) Construction method of underground structure in excavation method
JP3567399B2 (en) Large section tunnel and its construction method
JP2662627B2 (en) Shield method
JP3091163B2 (en) Construction method of large section shield tunnel corresponding to section change
JPH0533584A (en) Tunnel construction method
JP2020002666A (en) Open shield method combined with propulsion method
JPH01127791A (en) Construction method of box tunnel, method of assembling reinforcing bars, and formwork equipment
JP2001115772A (en) Joining method of existing tunnel and new tunnel
JP3333770B2 (en) Construction method for underground structures

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees