JPH0768875B2 - Buried pipe propulsion method - Google Patents
Buried pipe propulsion methodInfo
- Publication number
- JPH0768875B2 JPH0768875B2 JP2289901A JP28990190A JPH0768875B2 JP H0768875 B2 JPH0768875 B2 JP H0768875B2 JP 2289901 A JP2289901 A JP 2289901A JP 28990190 A JP28990190 A JP 28990190A JP H0768875 B2 JPH0768875 B2 JP H0768875B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- excavator
- propulsion
- buried
- propulsion shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 この発明は埋設管の推進工法に関し、詳しくは、下水道
等の地下埋設管を施工する際に、地盤を開削することな
く、地中に埋設孔を形成しながら、形成された埋設孔に
埋設管を順次推進させて埋設していく、いわゆる推進工
法に関するものである。Description: [Industrial field of application] The present invention relates to a propulsion method for a buried pipe, and more specifically, when constructing an underground buried pipe such as a sewer, it is buried in the ground without excavating the ground. The present invention relates to a so-called propulsion method in which a buried pipe is sequentially propelled and buried in the formed buried hole while forming the hole.
地下埋設管の推進工法としては、先端にオーガー等の掘
削機構を備えた掘進機で、地中に埋設孔を掘削しなが
ら、掘削機の掘削推進につづいて埋設管を推進埋設して
いく方法があり、この工法はオーガー工法等と呼ばれて
いる。また、近年、このような推進工法に用いる埋設管
の材料として、軽量で腐食せずコストの安価な塩ビ管や
強化プラスチック管の採用が検討されている。As a method for provoking underground buried pipes, a machine with an excavating mechanism such as an auger at the tip is used to excavate a buried hole in the ground, and then to bury the buried pipe following the excavation of the excavator. This method is called the auger method. Further, in recent years, as a material for a buried pipe used in such a propulsion method, adoption of a lightweight polyvinyl chloride pipe or a reinforced plastic pipe which does not corrode and is inexpensive has been considered.
従来のオーガー工法では、掘進機の後方に順次埋設管を
連結し、推進を開始する立坑、すなわち出発坑内で、埋
設管の最後尾を元押しジャッキ等で押して、埋設管およ
びその先端の掘進機を推進させるようにしていた。しか
し、この方法では、推進時に地盤から埋設管に加えられ
る摩擦抵抗力や掘進機で地盤を掘削する際の掘削抵抗力
が全て、埋設管同士の継目を介して後方に伝達され、埋
設管の最後端に集中して、元押しジャッキから加えられ
る推進力と対抗することになるので、埋設管の端面、特
に埋設管の最後尾には極めて大きな圧力もしくは応力が
発生することになる。そのため、埋設管として、塩ビ管
のように、あまり耐力のない材料を用いると、埋設管の
変形や破損が生じるため、塩ビ管等を使用することが出
来ないという問題があった。特に、1工程で連続施工す
る推進距離が長くなるほど、前記地盤からの摩擦抵抗力
が増え、埋設管の端面や最後尾に生じる圧力や応力も大
きくなるので、推進距離を延ばして施工能率を高め施工
コストを削減しようとするほど、前記した埋設管の変形
や破損が問題となる。In the conventional auger method, the buried pipe is connected to the rear of the excavator in order, and in the vertical shaft where the propulsion is started, that is, in the starting pit, the tail end of the buried pipe is pushed by the push jack etc. Was being promoted. However, in this method, all the frictional resistance force applied from the ground to the buried pipe at the time of propulsion and the excavation resistance force when excavating the ground with the excavator are transmitted to the rear through the joint between the buried pipes, and Since it concentrates on the rearmost end and opposes the propulsive force applied from the original pushing jack, extremely large pressure or stress is generated on the end face of the buried pipe, particularly on the rearmost end of the buried pipe. Therefore, if a material having a low proof stress, such as a PVC pipe, is used as the buried pipe, the buried pipe may be deformed or damaged, so that the PVC pipe or the like cannot be used. In particular, the longer the propulsion distance for continuous construction in one step, the greater the frictional resistance from the ground and the greater the pressure and stress generated at the end face and the tail end of the buried pipe. Therefore, the propulsion distance can be extended to improve construction efficiency. As the construction cost is reduced, the above-mentioned deformation or breakage of the buried pipe becomes a problem.
そこで、本願発明者らは、埋設管の最後尾等に局部的に
過大な圧力や応力が生じないような推進工法を研究した
結果、以下に述べる方法を発明し、先に、特願平1-1832
71号等として特許出願を行っている。Therefore, as a result of researching a propulsion method that does not locally cause excessive pressure or stress at the tail end of the buried pipe, the inventors of the present invention invented the method described below, and previously proposed Japanese Patent Application No. -1832
Patent application has been filed as No. 71 etc.
この方法は、掘進機の後方に、鋼管等からなる駆動軸体
を順次継ぎ足していき、この駆動軸体の最後尾を元押し
ジャッキで押して、掘進機を推進させる。また、埋設管
は、前記駆動軸体の外周に挿通された形で掘進機の後方
に継ぎ足されていくとともに、埋設管をその内側の駆動
軸体に保持固定させる。埋設管は、前記駆動軸体の推進
により駆動軸体とともに推進していくことになる。駆動
軸体に埋設管を保持固定させる手段としては、例えば、
圧力空気の供給によって膨張する膨張体を駆動軸体の外
面に設置しておき、この膨張体を膨張させて埋設管の内
面に押し付けて、埋設管を駆動軸体に保持固定させる構
造等が採用される。In this method, a drive shaft body made of a steel pipe or the like is sequentially added to the rear of the excavator, and the rear end of the drive shaft body is pushed by a push jack to propel the excavator. Further, the embedded pipe is extended to the rear of the excavator while being inserted into the outer periphery of the drive shaft, and the embedded pipe is held and fixed to the drive shaft inside thereof. The buried pipe will be propelled together with the drive shaft body by propelling the drive shaft body. As means for holding and fixing the embedded pipe on the drive shaft, for example,
An expansion body that expands by the supply of pressurized air is installed on the outer surface of the drive shaft body, and this expansion body is expanded and pressed against the inner surface of the embedded pipe to hold and fix the embedded pipe to the drive shaft body. To be done.
上記方法では、掘進機に加わる掘削抵抗力は、埋設管に
は全く伝わらず、駆動軸体を経て元押しジャッキからの
推進力と対抗する。また、個々の埋設管に加わる地盤の
摩擦抵抗力も、その内側の駆動軸体に伝えられるので、
埋設管同士の継目や埋設管列の最後尾に、他の埋設管の
摩擦抵抗力が全て集中して伝わるようなことはなく、埋
設管に局部的に過大な圧力や応力が発生することがなく
なる。その結果、塩ビ管等の耐力に劣る埋設管を推進工
法に利用することも可能になり、また、1工程の推進距
離を大幅に延長することも可能になった。In the above method, the excavating resistance force applied to the excavator is not transmitted to the buried pipe at all, and opposes the propulsive force from the original push jack via the drive shaft. In addition, the ground frictional resistance applied to each buried pipe is also transmitted to the drive shaft inside, so
All of the friction resistance of other buried pipes will not be concentrated and transmitted to the joints between buried pipes or the last part of the buried pipe row, and excessive pressure or stress may be locally generated in the buried pipes. Disappear. As a result, it is possible to use a buried pipe such as a PVC pipe having a poor yield strength in the propulsion method, and it is also possible to significantly extend the propulsion distance in one step.
ところが、従来行われている推進工法には、前記したオ
ーガー工法のほかに、泥水加圧工法と呼ばれる方法があ
るが、この泥水加圧工法では、前記した駆動軸体に埋設
管を保持固定させる方法が採用し難いという問題があ
る。However, in the conventional propulsion method, there is a method called a mud pressure method in addition to the auger method mentioned above. In this mud pressure method, the embedded pipe is held and fixed on the drive shaft body. There is a problem that the method is difficult to adopt.
泥水加圧工法は、掘進機の掘削個所に水または泥水を送
り込み、地盤面を加圧しながら掘削を行うことにより、
地盤の掘削を容易にするとともに地盤の崩壊や地下水の
噴出を防ぐことができ、掘削された土砂は泥水ととも排
出されるので、排土作業も簡単になる等の利点を備えて
いる。この泥水加圧工法では、立坑から掘進機の先端ま
で水や泥水を供給するための送泥配管と、掘削された土
砂および泥水を排出するための排泥配管の2本の配管
を、埋設孔内に通しておく必要がある。The muddy water pressure construction method sends water or muddy water to the excavation point of the excavator, and excavates while pressurizing the ground surface,
It has the advantages of facilitating the excavation of the ground, preventing the collapse of the ground and the spouting of groundwater, and excavating the earth and sand discharged together with the mud, which simplifies the earth removal work. In this mud pressure method, two pipes, a mud pipe for supplying water and mud from the vertical shaft to the tip of the excavator and a drain pipe for discharging excavated earth and sand and mud, It is necessary to pass it inside.
ところが、前記したように、駆動軸体に埋設管を保持固
定させておく構造を採用すると、駆動軸体と埋設管の間
の空間には、埋設管の保持固定手段が設置されることな
り、前記した泥水加圧工法に必要な送泥配管や排泥配管
を通することができ難くなる。一般に、送泥配管は、液
体状の水または泥水のみを流すので、それほど太い管径
は必要ないが、排泥配管は、泥水とともに礫石等の塊状
の土砂を流すので、充分に太い管径を有していなければ
ならない。そのため、駆動軸体と埋設管の間に、埋設管
の保持固定手段と同時に送泥配管および排泥配管の両方
をも設置することは極めて困難である。However, as described above, when the structure in which the embedded pipe is held and fixed to the drive shaft is adopted, the holding and fixing means of the embedded pipe is installed in the space between the drive shaft and the embedded pipe. It becomes difficult to pass through the mud sending pipe and the mud discharging pipe required for the above-mentioned mud pressure application method. Generally, the mud sending pipe does not need to have a large diameter because it flows only liquid water or muddy water, but the mud discharging pipe does not need to have a sufficiently thick pipe diameter because it flows lumps of sand such as pebbles along with mud water. Must have. Therefore, it is extremely difficult to install both the mud sending pipe and the mud discharging pipe between the drive shaft and the buried pipe together with the holding and fixing means of the buried pipe.
特に、埋設管の保持固定手段として、前記したような、
圧力空気等で膨張させる膨張体を用いた場合、埋設管の
内面に押し付けたときに充分な摩擦保持力を発揮させる
ためには、埋設管の広い面積にわたって膨張体が接触す
る必要があり、膨張体の占める容積が非常に大きくな
り、前記した送泥配管および排泥配管を設置する余裕が
なくなる。さらに、埋設管の保持固定を確実にするため
には、埋設管の内周全方向を駆動軸体に保持固定してお
く必要があるが、そうすると、送泥配管および排泥配管
を設置する隙間が全く無くなってしまう。In particular, as a means for holding and fixing the buried pipe, as described above,
When using an expander that expands with pressurized air, etc., the expander must contact over a large area of the buried pipe in order to exert sufficient friction holding force when pressed against the inner surface of the buried pipe. The volume occupied by the body becomes very large, and there is no room to install the above-mentioned mud sending pipe and mud discharging pipe. Further, in order to securely hold and fix the buried pipe, it is necessary to hold and fix the inner circumference of the buried pipe in all directions on the drive shaft body. It will be completely lost.
そこで、この発明の課題は、泥水加圧工法においても、
前記したような、駆動軸体に埋設管を保持固定させて、
推進時に埋設管に対して過大な圧力や応力の発生を防ぐ
構造を適用できるようにする方法を提供することにあ
る。Therefore, an object of the present invention is to apply the mud pressure method,
As described above, by holding and fixing the embedded pipe on the drive shaft,
(EN) It is intended to provide a method for applying a structure for preventing generation of excessive pressure or stress to a buried pipe during propulsion.
上記課題を解決する、この発明にかかる埋設管の推進工
法は、掘進機の後方に、推進軸体、および、この推進軸
体の外側に保持固定された埋設管をそれぞれ順次継ぎ足
しながら、推進軸体に推進力を加えて掘進機および埋設
管を埋設孔に推進させていく埋設管の推進工法におい
て、掘進機の先端に回転可能に設置された掘削面板を掘
進機内に配置された駆動源で回転駆動し、先端側が掘進
機に固定された後端側に推進力が加えられる推進軸体を
二重管で構成し、二重管の内外管路のうち、一方の管路
を通して、掘進機に水または泥水を供給して地盤を加圧
しながら、他方の管路を通して、掘進機で掘削された土
砂を泥水とともに後方に排出する。In order to solve the above-mentioned problems, a propulsion method for a buried pipe according to the present invention includes a propulsion shaft, which is sequentially connected to a rear side of a machine and a propulsion shaft and a buried pipe held and fixed outside the propulsion shaft. In the buried pipe propulsion method in which the propulsion force is applied to the body to propel the excavator and the buried pipe into the buried hole, the excavation face plate rotatably installed at the tip of the excavator is driven by the drive source arranged in the excavator. The propulsion shaft is driven by rotation and the propulsive force is applied to the rear end side that is fixed to the excavator at the tip side.The propulsion shaft is composed of a double pipe, and one of the inner and outer ducts of the double pipe is passed through the excavator. While supplying water or muddy water to the ground and pressurizing the ground, the earth and sand excavated by the excavator is discharged backward together with the muddy water through the other pipeline.
掘進機は、基本的には、通常の泥水加圧工法に採用され
ている掘進機と同様のものが用いられる。具体的に説明
すると、掘進機の前面には、地盤を掘削するカッターヘ
ッド、カッターディスクあるいは面板等と呼ばれる掘削
面板を備えている。The excavator is basically the same as the excavator employed in the normal mud pressure method. More specifically, the excavator is provided on the front surface with an excavation face plate called a cutter head for excavating the ground, a cutter disk, or a face plate.
掘削面板は、モータ等で回転駆動され、掘削面板の回転
に伴って地盤が掘削される。従来の掘進機では、掘削面
板を回転駆動させるモータ等の駆動源が、立坑や地表な
どに設置され、駆動源の回転を埋設孔の中央を貫通する
駆動軸を経て掘進機内の掘削面板に伝達する構造のもの
もあるが、この発明では、駆動源を、掘削面板の直後な
ど、掘進機の内部に配備しておくのが好ましい。これ
は、この発明の場合、推進軸体を送泥配管および排泥配
管として利用するので、前記駆動軸を推進軸体に内蔵し
ておくと、管路スペースが少なくなるためである。ま
た、掘削面板の近くに駆動源があれば、駆動軸も短くて
済む。但し、モータを作動させるための、電源ケーブル
や油圧ケーブル等は、推進軸体と埋設管の間の空間等を
通して、後方の立坑や地表までつながっていてもよい。The excavation face plate is rotationally driven by a motor or the like, and the ground is excavated as the excavation face plate rotates. In a conventional excavator, a drive source such as a motor that rotationally drives the excavation face plate is installed on a shaft or the surface of the earth, and the rotation of the drive source is transmitted to the excavation face plate inside the excavator via a drive shaft that penetrates the center of the buried hole. However, in the present invention, it is preferable to arrange the drive source inside the excavator, such as immediately after the excavation face plate. This is because, in the case of the present invention, since the propulsion shaft is used as the mud sending pipe and the mud discharging pipe, if the drive shaft is built in the propulsion shaft, the space for the pipe line is reduced. Further, if the drive source is near the excavation face plate, the drive shaft can be short. However, a power cable, a hydraulic cable, or the like for operating the motor may be connected to a shaft or a surface in the rear through a space between the propulsion shaft and the buried pipe.
掘削面板には、土砂を背部に送り込むためにスリット等
と呼ばれる排土口が設けられており、この排土口は隔壁
等で密閉された圧力室、泥水室などとも呼ばれる空間、
いわゆる取込室につながっている。この取込室に、水や
泥水を供給する送泥配管、および、土砂と泥水を排出す
る排泥配管がつながっている。取込室への、水や泥水の
送泥量もしくは圧力と、土砂および泥水の排泥量もしく
は圧力を適当に設定することにより、掘削面板の前方お
よび周囲の地盤に加える圧力を調整することができる。The excavation face plate is provided with a soil discharge port called a slit or the like for sending earth and sand to the back, and this soil discharge port is a space that is also called a pressure chamber, a mud chamber, etc. that is sealed by a partition wall,
It is connected to a so-called intake room. A mud pipe for supplying water and muddy water and a mud pipe for discharging earth and sand and muddy water are connected to the intake chamber. By appropriately setting the amount or pressure of water or muddy water sent to the intake chamber and the amount or pressure of muddy sand or muddy water discharge, it is possible to adjust the pressure applied to the ground in front of and around the excavation face plate. it can.
掘進機には、上記構造のほか、掘進機の掘削方向を変え
る方向修正ジャッキや、位置測量のためのレーザ測量用
ターゲット等、通常の掘進機と同様の各種機構や構造を
備えることができる。In addition to the above structure, the excavator can be provided with various mechanisms and structures similar to those of a normal excavator, such as a direction correction jack for changing the excavation direction of the excavator, a laser surveying target for position measurement, and the like.
推進軸体は、元押しジャッキからの推進力に耐える程度
の剛性を有する鋼等の金属で形成された二重管からな
り、同心状に内外2層の管路が構成されている。推進軸
体は、先端を掘進機の後部に、フランジやボルトで連結
固定可能であるとともに、推進軸体同士を軸方向に連結
可能になっている。推進軸体の連結固定手段は、通常の
推進工法における駆動軸体あるいは推進軸の連結固定手
段と同様の機構が採用できる。但し、推進軸体の二重の
管路を、水または泥水と、土砂を含む泥水とが流れるの
で、連結部分に各管路の水封手段を設けておくのが好ま
しい。水封手段は、通常の配管と同様に、シールゴムや
Oリング、パッキンその他の機構が採用できる。The propulsion shaft body is composed of a double pipe made of metal such as steel having a rigidity that can withstand the propulsion force from the original push jack, and two inner and outer layers of pipe lines are concentrically formed. The propulsion shaft can be connected and fixed to the rear part of the excavator with a flange or bolts, and the propulsion shafts can be connected to each other in the axial direction. As the connecting and fixing means of the propulsion shaft body, the same mechanism as the connecting and fixing means of the drive shaft body or the propulsion shaft in the usual propulsion method can be adopted. However, since water or muddy water and muddy water containing earth and sand flow through the double conduits of the propulsion shaft, it is preferable to provide a water sealing means for each conduit at the connecting portion. As the water sealing means, a sealing rubber, an O-ring, a packing, or other mechanism can be adopted as in the case of normal piping.
推進軸体の最先端は、掘進機に固定され、推進軸体の二
重の管路が、それぞれ前記取込室の隔壁まで配管連結さ
れていて、取込室に開口している。推進軸体の最後端
は、立坑内等で、二重管路の一方の管路が、水または泥
水の供給装置と配管連結され、また、他方の管路が、土
砂を含む泥水から土砂と水を分離したり、土砂を回収し
たり、分離した水を再循環させたりする装置に連結され
る。土砂と水の分離装置で分離された水または泥水は、
前記供給装置に戻して、循環利用できる。The tip of the propulsion shaft is fixed to the excavator, and the double pipe lines of the propulsion shaft are connected to the partition wall of the intake chamber by piping to open into the intake chamber. At the rear end of the propulsion shaft, one of the double pipes is pipe-connected to a water or muddy water supply device in the vertical shaft, etc., and the other pipe is changed from muddy water containing sediment to sediment. It is connected to a device that separates water, collects soil and recycles the separated water. The water or muddy water separated by the sediment and water separator is
It can be recycled by returning to the supply device.
推進軸体の内外二重の管路のうち、何れを、排泥配管ま
たは排泥配管に用いてもよい。一般には、塊状の土砂等
も流すために比較的大きな口径を要する排泥配管を、内
側管路に設定し、狭い隙間でも流れる水または泥水を流
す送泥配管を外側管路に設定するのが好ましい。二重管
の内外管路の口径比、あるいは、断面積の配分は、上記
のような排泥配管と送泥配管の目的の違いや、掘進機の
性能、施工条件等を考慮して、任意に設定することがで
きる。Either of the inner and outer double pipe lines of the propulsion shaft may be used as the sludge pipe or the sludge pipe. Generally, it is recommended to set the sludge drainage pipe, which requires a relatively large diameter in order to flow even lumpy sediment, as the inner pipe line, and set the mud transmission pipe for flowing water or muddy water in a narrow gap as the outer pipe line. preferable. The diameter ratio of the inner and outer pipelines of the double pipe, or the distribution of the cross-sectional area can be arbitrarily determined in consideration of the above-mentioned purpose of the sludge pipe and the sludge pipe, the performance of the excavator, and the construction conditions. Can be set to.
推進軸体には、埋設管を保持固定する手段を備えてお
く。埋設管の保持固定手段としては、埋設管の内面側に
当接して埋設管が軸方向に移動しないように固定してお
けば、通常の各種機械装置における管材の固定手段が適
用できる。例えば、ゴム等で形成された袋状の膨張体を
推進軸体の外面に設けておき、この膨張体に圧力空気や
油、水等の圧力媒体を送り込んで、膨張体を外周に向か
って膨張させ、膨張体を埋設管の内面に押し当てれば、
埋設管を推進軸体に保持固定できる。また、機械的に作
動する押圧板を埋設管の内面に押し当てたり、埋設管の
内面に係合して軸方向に固定する係合機構を推進軸体に
設けておいてもよい。埋設管の保持固定手段の詳しい構
造については、前記した特願平1-183271号や特願平1-24
0408号、特願昭63-298619号等に開示された構造等が採
用できる。The propulsion shaft is provided with means for holding and fixing the embedded pipe. As the means for holding and fixing the embedded pipe, if the embedded pipe is fixed so as not to move in the axial direction by making contact with the inner surface side of the embedded pipe, the fixing means for the pipe material in various ordinary mechanical devices can be applied. For example, a bag-shaped expander made of rubber or the like is provided on the outer surface of the propulsion shaft, and a pressure medium such as pressure air, oil, or water is fed into the expander to expand the expander toward the outer periphery. And press the expander against the inner surface of the buried pipe,
The embedded pipe can be held and fixed to the propulsion shaft. Further, a mechanically operated pressing plate may be pressed against the inner surface of the embedded pipe, or an engagement mechanism that engages with the inner surface of the embedded pipe and fixes in the axial direction may be provided in the propulsion shaft body. Regarding the detailed structure of the holding and fixing means of the buried pipe, the above-mentioned Japanese Patent Application No. 1-183271 and Japanese Patent Application No. 1-24
The structures disclosed in No. 0408 and Japanese Patent Application No. 63-298619 can be used.
埋設管の保持固定手段は、二重管からなる推進軸体の外
周に設けられるので、推進軸体と埋設管の間の空間を自
由に利用して設置しておけるが、推進軸体と埋設管の間
に、測量用のレーザ光路を設けたり、掘進機へ電源や油
圧等を供給するケーブルや配管の設置個所をあけておく
のが好ましい。Since the means for holding and fixing the embedded pipe is provided on the outer periphery of the propulsion shaft made of the double pipe, the space between the propulsion shaft and the embedded pipe can be freely used for installation, but the propulsion shaft and the embedded pipe can be installed. A laser beam path for surveying is preferably provided between the pipes, and a cable or a pipe for supplying power, hydraulic pressure or the like to the excavator is preferably opened.
推進工法の具体的手順や工程は、前記先願特許に開示さ
れた推進工法と基本的には同じでよい。すなわち、外周
に埋設管を被せて保持固定手段で固定した推進軸体を、
掘進機の後方に順次連結して継ぎ足していきながら、推
進軸体の後端に元押しジャッキで推進力を加え、掘進機
および推進軸体、埋設管を推進させていく。The specific procedure and steps of the propulsion method may be basically the same as those of the propulsion method disclosed in the prior patent. That is, the propulsion shaft body covered with a buried pipe on the outer periphery and fixed by the holding and fixing means,
The excavator, the propulsion shaft, and the buried pipe are propelled by applying a propulsive force to the rear end of the propulsion shaft with a push jack while sequentially connecting and connecting the rear part of the excavator.
そして、推進軸体の後端側では、二重管の一方の管路
に、水または泥水を供給する送泥配管が連結され、推進
軸体を通して掘進機に水または泥水を供給する。掘進機
では、掘削面板を回転駆動させて地盤を掘削するととも
に、取込室に供給された水または泥水で地盤に圧力を加
えておく。掘削された土砂は、泥水とともに推進軸体の
他方の管路を通して、後方に送られ、推進軸体の後端に
連結された排泥配管を経て、外部に排出される。Then, on the rear end side of the propulsion shaft, a mud sending pipe for supplying water or muddy water is connected to one pipeline of the double pipe, and water or muddy water is supplied to the excavator through the propulsion shaft. In the excavator, the excavation face plate is rotationally driven to excavate the ground, and pressure is applied to the ground with water or muddy water supplied to the intake chamber. The excavated earth and sand is sent to the rear along with the muddy water through the other pipeline of the propulsion shaft, and is discharged to the outside through the mud pipe connected to the rear end of the propulsion shaft.
上記のような工程を繰り返して、掘進機で埋設孔が掘削
形成され、掘進機の後方で埋設孔に埋設管が順次推進埋
設されていくことになる。目的の立坑まで埋設管が埋設
されれば、掘進機と推進軸体を分解撤去する。推進軸体
は、保持固定手段による埋設管の保持固定を解除すれ
ば、埋設管を埋設孔に残したままで推進軸体のみを撤去
することができる。その後、埋設管の継目や立坑の露出
部分等を適当に処理する等、通常の推進工法と同様の後
処理作業が行われて、埋設管の埋設施工が完了する。By repeating the above-described steps, the buried hole is excavated and formed by the excavator, and the buried pipes are sequentially propelled and buried in the buried hole behind the excavator. When the buried pipe is buried up to the target shaft, the excavator and propulsion shaft are disassembled and removed. With respect to the propulsion shaft, if the holding and fixing of the buried pipe by the holding and fixing means is released, only the propulsion shaft can be removed with the buried pipe left in the buried hole. After that, the post-processing work similar to the ordinary propulsion method is performed, such as appropriately treating the joints of the buried pipe and the exposed portion of the vertical shaft, and the burying work of the buried pipe is completed.
この発明にかかる埋設管の推進工法は、前記した下水道
のほか、ガス配管や地中電線配管その他の、比較的小口
径の埋設管施工に好ましく適用されるが、その他、任意
の目的および口径を有する地下埋設管の施工に利用する
ことができる。また、埋設管の材料は、前記したような
塩ビ管や強化プラスチック管が好ましく用いられるが、
同様の問題を有するその他の管材料を用いることも可能
である。The buried pipe propulsion method according to the present invention, in addition to the above-mentioned sewer, is preferably applied to the construction of a relatively small-diameter buried pipe such as gas pipes and underground electric wire pipes. It can be used for the construction of underground pipes that it has. The material of the buried pipe is preferably a vinyl chloride pipe or a reinforced plastic pipe as described above,
It is also possible to use other tubing materials that have similar problems.
掘進機に推進力を伝える推進軸体に埋設管を保持固定さ
せておく場合、埋設管と推進軸体の間の空間には、泥水
加圧工法で用いる送泥配管や排泥配管を通すことができ
ない。When the embedded pipe is held and fixed to the propulsion shaft that transmits the propulsion force to the excavator, pass the mud sending pipe or drainage pipe used in the mud pressure construction method in the space between the buried pipe and the propulsion shaft. I can't.
しかし、推進軸体を二重管で構成して、この二重管の内
外2層の管路を、送泥配管と排泥配管に利用すれば、埋
設管の保持固定手段の設置構造に全く影響を与えること
なく、送泥配管および排泥配管の設置が可能である。However, if the propelling shaft is constructed of a double pipe and the two inner and outer layers of the double pipe are used for the mud sending pipe and the mud carrying pipe, the structure for holding and fixing the buried pipe is completely eliminated. It is possible to install the mud sending pipe and the mud discharging pipe without affecting.
しかも、送泥配管および排泥配管が推進軸体と共通であ
れば、特別な配管部品や配管接続作業が不要であり、施
工装置の簡略化および施工作業の能率化が図れる。Moreover, if the mud sending pipe and the mud discharging pipe are common to the propulsion shaft, no special piping parts or pipe connecting work is required, and the construction device can be simplified and the construction work can be streamlined.
ついで、この発明の実施例を、図面を参照しながら以下
に説明する。An embodiment of the present invention will be described below with reference to the drawings.
第1図は、この発明の推進工法に用いる施工装置のう
ち、先端の掘進機付近の構造を示している。掘進機10
は、埋設孔の口径に合わせた筒状の外形を有し、前面に
掘削面板20を備えている。FIG. 1 shows the structure near the excavator at the tip of the construction apparatus used in the propulsion method of the present invention. Excavator 10
Has a cylindrical outer shape that matches the diameter of the buried hole, and is provided with the excavation face plate 20 on the front surface.
掘削面板20は、前面にカッタービット21等の掘削機構を
備えるとともに、掘削された土砂を後方に送るスリット
状の排土口22が設けられている。掘削面板20は、背面中
心に設けられた駆動軸24を経て駆動モータ26に連結され
ている。駆動軸24は、掘進機10の内部を仕切る隔壁12に
支持されている。駆動モータ26の回転駆動により、掘削
面板20が回転し、カッタービット21で地盤を掘削して、
掘削された土砂が排土口22から後方に取り込まれる。掘
削面板20と隔壁12の間の空間は取込室14となる。The excavation face plate 20 is provided with an excavation mechanism such as a cutter bit 21 on the front surface, and a slit-shaped soil discharge port 22 for sending the excavated earth and sand backward. The excavation face plate 20 is connected to a drive motor 26 via a drive shaft 24 provided at the center of the back surface. The drive shaft 24 is supported by a partition wall 12 that partitions the interior of the excavator 10. By the rotational drive of the drive motor 26, the excavation face plate 20 rotates, the cutter bit 21 excavates the ground,
The excavated earth and sand is taken in rearward from the soil discharge port 22. A space between the excavation face plate 20 and the partition wall 12 serves as an intake chamber 14.
掘進機10は、掘削面板20および隔壁12が取り付けられた
前筒部11と、後述する推進軸体を固定する後筒部16が、
端部を一部重ねた状態で組み合わせられ、周方向の複数
個所に設けられた伸縮自在な方向修正ジャッキ15で連結
されている。方向修正ジャッキ15の伸縮量を変えること
により、後筒部16の中心軸に対して、前筒部11の中心軸
を任意の方向に傾けることができ、これにより、掘進機
10の掘削方向を修正できるようになっている。前筒部11
と後筒部16の重なり部分には、シール材等の密封手段17
が設けられている。The excavator 10 includes a front cylinder part 11 to which the excavation face plate 20 and the partition wall 12 are attached, and a rear cylinder part 16 for fixing a propulsion shaft body described later,
The end portions are combined in a partially overlapped state, and are connected by expandable direction correction jacks 15 provided at a plurality of positions in the circumferential direction. By changing the amount of expansion and contraction of the direction correction jack 15, the central axis of the front cylinder part 11 can be tilted in any direction with respect to the central axis of the rear cylinder part 16.
It is possible to correct 10 drilling directions. Front cylinder part 11
A sealing means 17 such as a sealing material is provided on the overlapping portion of the rear cylindrical portion 16 and
Is provided.
掘進機10の後筒部16には、フランジ接続機構19を介し
て、推進軸体30が固定されている。推進軸体30は、鋼管
等から形成された二重管で構成され、外側管路34が水ま
たは泥水を流す送泥配管となり、内側管路32が掘削され
た土砂および泥水を流す排泥配管となる。推進軸体30の
先端で、外側管路34の外面には、フレキシブルホース等
からなる延長配管84が接続され、延長配管84は、隔壁12
に接続されて取込室14に開口している。また、内側管路
32の端面にも延長配管82が接続され、隔壁12を経て取込
室14に開口している。A propulsion shaft body 30 is fixed to a rear cylinder portion 16 of the excavator 10 via a flange connection mechanism 19. The propulsion shaft body 30 is composed of a double pipe formed of a steel pipe or the like, the outer pipe line 34 serves as a mud transport pipe for flowing water or muddy water, and the inner pipe line 32 serves as a mud pipe for flowing excavated earth and sand and muddy water. Becomes An extension pipe 84 made of a flexible hose or the like is connected to the outer surface of the outer pipe line 34 at the tip of the propulsion shaft body 30.
Is open to the intake chamber 14. Also, the inner pipeline
An extension pipe 82 is also connected to the end face of 32 and opens into the intake chamber 14 through the partition wall 12.
推進軸体30の後端には、別の推進軸体30が接続され、順
次後方に推進軸体30が継ぎ足される。第3図は、推進軸
体30同士の接続部分の構造を示している。二重管の外管
33、33の突き合わせ部分で、一方の外管33には、断面略
S字状のフランジ35が取り付けられ、これと対向する外
管33には、平面状のフランジ36が取り付けられており、
両方のフランジ35、36を対面させて、ボルト37で締め付
け固定する。断面S字状のフランジ35と他方の外管33の
外周面との対向個所にはシールゴム100が装着され、外
管33、33の継目個所の水封性能を高めている。また、二
重管の内管31、31の突き合わせ部分では、一方の内管31
に断面L字形のフランジ38が取り付けられている。この
フランジ38と他方の内管31の外周面との対向個所にもシ
ールゴム100が装着されていて、内側管路32と外側管路3
4との水封遮断を図っている。Another propulsion shaft body 30 is connected to the rear end of the propulsion shaft body 30, and the propulsion shaft body 30 is sequentially added rearward. FIG. 3 shows the structure of the connecting portion between the propulsion shafts 30. Double tube outer tube
At the abutting portion of 33, 33, a flange 35 having a substantially S-shaped cross section is attached to one outer pipe 33, and a flat flange 36 is attached to the outer pipe 33 facing the outer pipe 33.
Face both flanges 35, 36 and tighten with bolts 37. A seal rubber 100 is attached to a portion where the flange 35 having an S-shaped cross section and the outer peripheral surface of the other outer tube 33 are opposed to each other, thereby enhancing the water sealing performance at the joint portion of the outer tubes 33, 33. Also, at the abutting portion of the inner pipes 31, 31 of the double pipe, one inner pipe 31
A flange 38 having an L-shaped cross section is attached to the. A seal rubber 100 is also attached at a position where the flange 38 and the outer peripheral surface of the other inner pipe 31 face each other, and the inner pipe line 32 and the outer pipe line 3 are attached.
We are trying to cut off the water seal with 4.
推進軸体30の外周には、埋設管の保持固定手段40が取り
付けられている。第4図にも示すように、保持固定手段
40は、ゴム等の弾性材料からなり、断面が偏平な長円形
をなす円環チューブ状の膨張体42と、この膨張体42を支
持して推進軸体30に固定する支持部材44で構成されてい
る。膨張体42には、圧力空気を送り込む供給配管46が接
続されている。膨張体42に圧力空気を充填すると、膨張
体42が外周側に膨張して、膨張体42の外面が、塩ビ管等
からなる埋設管70の内面に押し付けられる。膨張体42が
埋設管70に押し付けられていると、埋設管70と膨張体42
の間に作用する摩擦支持力によって、埋設管70が膨張体
42すなわち推進軸体30に保持固定されることになる。膨
張体42は、埋設管70に弾力的に当接するので、埋設管70
が傷付いたり局部的に変形する心配はない。膨張体42に
充填された圧力空気を抜けば、膨張体42は内周側に収縮
するので、埋設管70に対する保持固定が解除される。On the outer periphery of the propulsion shaft body 30, a holding and fixing means 40 for the buried pipe is attached. As shown in FIG. 4, holding and fixing means
40 is made of an elastic material such as rubber and is composed of an annular tube-shaped expander 42 having a flat oval cross section and a support member 44 that supports the expander 42 and fixes it to the propulsion shaft 30. ing. A supply pipe 46 for sending pressurized air is connected to the expander 42. When the expander 42 is filled with pressurized air, the expander 42 expands to the outer peripheral side, and the outer surface of the expander 42 is pressed against the inner surface of the embedded pipe 70 made of a vinyl chloride pipe or the like. When the expander 42 is pressed against the buried pipe 70, the buried pipe 70 and the expander 42
Due to the frictional support force acting between the
That is, 42 is held and fixed to the propulsion shaft body 30. Since the expander 42 elastically abuts the embedded pipe 70, the embedded pipe 70
There is no need to worry about scratching or local deformation. When the compressed air filled in the expansion body 42 is released, the expansion body 42 contracts toward the inner peripheral side, so that the holding and fixing to the embedded pipe 70 is released.
第4図に示すように、保持固定手段40の支持部材44は、
膨張体42を取り付けた筒面板43と筒綿板43を推進軸体30
に支持する端面板48とからなり、端面板48には、レーザ
測量用のターゲット空間45やケーブル配管の挿通用空間
47が貫通形成されている。レーザ測量とは、埋設管70の
最後尾で立坑内等に設置されたレーザ測量装置から掘進
機10に向けてレーザ光を照射し、掘進機10に設けられた
ターゲット(図示せず)で反射したレーザ光を再びレー
ザ測量装置で検知して、掘進機10の位置、すなわち埋設
孔の曲がりや傾きを測量するものである。前記、ターゲ
ット空間45は、レーザ光路を確保するものである。ケー
ブル配管の挿通用空間47には、掘進機10の駆動モータ26
や方向修正ジャッキ15その他の機構部分に電源や油圧を
供給するための電源ケーブルや油圧配管等が通される。As shown in FIG. 4, the support member 44 of the holding and fixing means 40 is
Cylinder face plate 43 with expander 42 attached and cotton swab 43 are propelled shaft 30
The end plate 48 supports the target space 45 for laser surveying and the space for inserting the cable piping.
47 is formed through. Laser survey means that a laser surveying device installed at the end of the buried pipe 70 in a shaft or the like emits laser light toward the excavator 10 and is reflected by a target (not shown) provided in the excavator 10. The generated laser light is again detected by the laser surveying device to measure the position of the excavator 10, that is, the bending and inclination of the buried hole. The target space 45 secures a laser optical path. In the space 47 for inserting the cable pipe, the drive motor 26 of the excavator 10
A power cable for supplying power and hydraulic pressure, hydraulic piping, and the like are passed through the direction adjusting jack 15 and other mechanical parts.
保持固定手段40は、前後に継ぎ足される推進軸体30の全
てに設けておいてもよいし、推進軸体30の複数本置きに
保持固定手段40を設けておいてもよい。最前方の推進軸
体30に保持固定された埋設管70は、先端の一部が掘進機
10の後筒部16の内側に挿入される。複数の推進軸体30に
配備される保持固定手段40は、圧力空気の供給配管46を
共通にするなどして、複数の保持固定手段40を同時に作
動もしくは作動解除できるようにしておけば、施工後の
埋設管70の保持固定解除や推進軸体30の分解撤去が行い
易い。The holding and fixing means 40 may be provided on all of the propulsion shafts 30 that are added to the front and the rear, or the holding and fixing means 40 may be provided on a plurality of propulsion shafts 30. A part of the tip of the buried pipe 70, which is held and fixed to the foremost propulsion shaft body 30, is an excavator.
It is inserted inside the rear tube portion 16 of the casing 10. The holding and fixing means 40 arranged on the plurality of propulsion shafts 30 can be constructed by making the plurality of holding and fixing means 40 actuate or deactivate at the same time by making the supply pipe 46 for the compressed air common. It is easy to release and hold the embedded pipe 70 later and disassemble and remove the propulsion shaft body 30.
上記のようにして、掘進機10の後方に推進軸体30および
埋設管70が順次継ぎ足されていく。そして、第2図に示
すように、最後尾の推進軸体30aにおいて、外側管路34
の外面に、水または泥水の供給装置につながる送泥配管
94が接続される。内側管路32は、外側管路34を貫通し
て、推進軸体30の外部まで延長され、土砂と泥水との分
離装置等につながる排泥配管92が接続される。推進軸体
30aの後端には、当輪52を介して元押しジャッキ50が配
備されている。元押しジャッキ50は、立坑の固定壁60に
支持されて前方に伸縮作動し、推進軸体30aに推進力を
与える。As described above, the propulsion shaft body 30 and the buried pipe 70 are sequentially added to the rear of the excavator 10. Then, as shown in FIG. 2, in the rearmost propulsion shaft body 30a, the outer pipe line 34
On the outer surface of the pipe, mud pipes connected to the water or mud supply device
94 is connected. The inner pipe line 32 penetrates the outer pipe line 34, extends to the outside of the propulsion shaft body 30, and is connected with a sludge discharge pipe 92 connected to a device for separating soil and muddy water or the like. Propulsion shaft
At the rear end of 30a, a source push jack 50 is provided via a wheel 52. The source push jack 50 is supported by the fixed wall 60 of the vertical shaft and expands and contracts forward to apply a propulsive force to the propulsion shaft body 30a.
推進軸体30aが推進移動すると、送泥配管94および排泥
配管92も移動する必要があるので、両配管92、94をフレ
シキブルホース等で形成して伸縮変形可能に構成してお
くのが好ましい。最後尾の推進軸体30aは、一定距離推
進させた後、元押しジャッキ50を縮めて推進軸体30aを
元の位置まで戻し、最後尾の推進軸体30aとその前方の
推進軸体30の間に生じる隙間に、別の新たな推進軸体30
を挿入して、次々と推進軸体30を継ぎ足していくように
する。このようにすれば、送泥配管94および排泥配管92
を最後尾の推進軸体30aに取り付けたままで、推進軸体3
0の推進および継ぎ足し連結作業を行うことができる。When the propulsion shaft body 30a is propulsively moved, the mud sending pipe 94 and the mud discharging pipe 92 also need to be moved. Therefore, it is preferable that both pipes 92, 94 are formed of flexible hoses or the like so that they can be expanded and contracted. . The rearmost propulsion shaft 30a is propelled by a certain distance, then the original push jack 50 is contracted to return the propulsion shaft 30a to the original position, and the rearmost propulsion shaft 30a and the propulsion shaft 30 in front of it. Another new propulsion shaft 30
Are inserted, and the propulsion shafts 30 are added one after another. By doing this, the mud sending pipe 94 and the mud sending pipe 92
Is attached to the rearmost propulsion shaft 30a,
Zero propulsion and replenishment connection work can be performed.
上記のような装置を用いて、埋設管70の推進埋設を行う
方法を説明する。まず、出発坑となる立坑内の側壁か
ら、地盤を掘削しながら掘進機10を水平方向に推進させ
ていく。埋設管70は、単独で推進軸体30に被せて保持固
定手段40で推進軸体30に固定しておく。埋設管70が保持
固定された推進軸体30を、掘進機10の後部に連結し、推
進軸体30の内外管路32、34は、掘進機10および最後尾の
推進軸体30aに接続し、掘進機10に水または泥水を供給
したり、掘削された土砂を泥水とともに後方に排出でき
るようにしておく。A method of performing propulsive embedding of the embedding pipe 70 using the above-described device will be described. First, the excavator 10 is horizontally propelled while excavating the ground from the side wall in the vertical shaft that is the starting shaft. The embedded pipe 70 is individually covered on the propulsion shaft 30 and fixed to the propulsion shaft 30 by the holding and fixing means 40. The propulsion shaft body 30 in which the buried pipe 70 is held and fixed is connected to the rear portion of the excavator 10, and the inner and outer conduits 32 and 34 of the propulsion shaft body 30 are connected to the excavator 10 and the rearmost propulsion shaft body 30a. It is possible to supply water or muddy water to the machine 10 and to discharge the excavated earth and sand together with the muddy water to the rear.
掘進機10で地盤を掘削して埋設孔を形成し、最後尾の推
進軸体30aに元押しジャッキ50で推進力を加えることに
よって、掘進機10および推進軸体30ならびに埋設管70が
一体となって埋設孔内に推進される。地盤を掘削する際
には、掘進機10の取込室14に水または泥水が充填されて
前方の地盤に一定の圧力を加えるので、地盤が崩壊した
り、地下水が噴出したりすることがない。掘削された土
砂は泥水とともに順次後方に排出される。The ground is excavated by the excavator 10 to form a buried hole, and a propulsion force is applied to the rearmost propulsion shaft 30a by the original pushing jack 50, whereby the excavator 10 and the propulsion shaft 30 and the buried pipe 70 are integrated. And is propelled into the buried hole. When excavating the ground, the intake chamber 14 of the excavator 10 is filled with water or muddy water and applies a certain pressure to the ground in front, so the ground will not collapse or groundwater will not spout. . The excavated earth and sand are discharged to the rear along with mud.
1組の推進軸体30および埋設管70が地盤内に推進されれ
ば、別の新たな推進軸体30および埋設管70を継ぎ足し
て、前記同様の工程を繰り返す。掘進機10が、目的の立
坑まで到達すれば、掘進機10を後方の推進軸体30から分
解撤去する。埋設孔の全長に埋設管70が埋設されれば、
推進軸体30による埋設管70の保持固定を解除し、埋設管
70を埋設孔内に残したままで、推進軸体30のみを分解撤
去する。こうして、埋設管の推進埋設施工は完了する。When one set of the propulsion shaft 30 and the buried pipe 70 is propelled into the ground, another new propulsion shaft 30 and the buried pipe 70 are added, and the same process as above is repeated. When the excavator 10 reaches the intended vertical shaft, the excavator 10 is disassembled and removed from the rear propulsion shaft 30. If the buried pipe 70 is buried in the entire length of the buried hole,
The holding and fixing of the embedded pipe 70 by the propulsion shaft 30 is released, and the embedded pipe 70 is released.
Only the propulsion shaft body 30 is disassembled and removed while leaving 70 in the buried hole. In this way, the propulsion burial construction of the buried pipe is completed.
以上に述べた、この発明にかかる埋設管の推進工法によ
れば、埋設管を推進軸体に保持固定して、埋設管に局部
的に過大な圧力や応力が生じないようにできると同時
に、掘進機に水または泥水を供給して地盤に一定の圧力
を負荷した状態で掘削を行う、いわゆる泥水加圧式の推
進工法を適用できることになる。According to the propulsion method for the buried pipe according to the present invention described above, the buried pipe can be held and fixed to the propulsion shaft so that excessive pressure or stress is not locally generated in the buried pipe, at the same time, It is possible to apply a so-called muddy water pressure type propulsion method, in which water or muddy water is supplied to the excavator and the excavation is performed with a certain pressure being applied to the ground.
すなわち、推進軸体を二重管で構成し、この二重管の内
外2層の管路を、送泥配管および排泥配管として利用す
るので、埋設管を推進軸体に保持固定する保持固定手段
の構造や配置に全く影響を与えず、送泥配管および排泥
配管の機能を発揮させることができるのである。しか
も、送泥配管および排泥配管を別に設置する必要がない
ので、配管施工の手間が省け、別に配管部品を用意する
必要もないので、設備コストおよび施工コストが削減で
きることになる。That is, since the propulsion shaft is composed of a double pipe, and the inner and outer two layers of the double pipe are used as the mud sending pipe and the mud discharging pipe, the embedded pipe is held and fixed to the propulsion shaft. The functions of the mud sending pipe and the mud discharging pipe can be exerted without affecting the structure and arrangement of the means at all. Moreover, since it is not necessary to separately install the mud sending pipe and the mud discharging pipe, it is possible to save the labor of the piping work and to prepare the piping parts separately, so that the equipment cost and the construction cost can be reduced.
その結果、泥水加圧工法の利点である、地盤の崩壊や地
下水の噴出を良好に防止できる点、掘削能率が向上する
点、掘削された土砂の排出が能率的に行える点等と、埋
設管を推進軸体に保持固定させる方法の利点である、埋
設管に過大な圧力や応力が加わらない点の何れをも良好
に発揮することが可能になる。As a result, the advantage of the mud pressure method is that it can prevent ground collapse and groundwater spouting well, that excavation efficiency is improved, and that excavated earth and sand can be discharged efficiently. It is possible to satisfactorily exert any of the advantages of the method of holding and fixing the above-mentioned to the propulsion shaft body, that is, the point that excessive pressure or stress is not applied to the buried pipe.
したがって、従来の泥水加圧工法では極めて困難であっ
た、塩ビ管等の耐力に劣る管材料を用いたり、従来の工
法では不可能な長距離の連続推進を行ったりすることが
可能になり、推進工法の施工能率向上や埋設管の耐食性
向上あるいは施工コストの大幅な低減を図ることができ
る。Therefore, it was possible to use a pipe material with poor yield strength such as a PVC pipe, which was extremely difficult in the conventional mud pressure method, or to perform long-distance continuous propulsion, which is not possible in the conventional method. It is possible to improve the construction efficiency of the propulsion method, improve the corrosion resistance of the buried pipe, or significantly reduce the construction cost.
第1図はこの発明の推進工法を実施する施工装置の先端
部分を示す断面図、第2図は後端部分を示す断面図、第
3図は推進軸体の連結部分を示す要部拡大断面図、第4
図は第1図と直交する方向の拡大断面図である。 10……掘進機、30……推進軸体、32……内側管路、34…
…外側管路、40……保持固定手段、50……元押しジャッ
キ、70……埋設管FIG. 1 is a sectional view showing a tip portion of a construction device for carrying out the propulsion method of the present invention, FIG. 2 is a sectional view showing a rear end portion, and FIG. 3 is an enlarged sectional view showing an essential portion showing a connecting portion of a propulsion shaft. Figure, 4th
The drawing is an enlarged cross-sectional view in a direction orthogonal to FIG. 10 …… excavator, 30 …… propulsion shaft, 32 …… inner conduit, 34…
… Outside pipe, 40 …… Holding and fixing means, 50 …… Original jack, 70 …… Buried pipe
Claims (1)
推進軸体の外側に保持固定された埋設管をそれぞれ順次
継ぎ足しながら、推進軸体に推進力を加えて掘進機およ
び埋設管を埋設孔に推進させていく埋設管の推進工法に
おいて、掘進機の先端に回転可能に設けられた掘削面板
を掘進機に配置された駆動源で回転駆動し、先端側が掘
進機に固定され後端側に推進力が加えられる推進軸体を
二重管で構成し、二重管の内外管路のうち、一方の管路
を通して、掘進機に水または泥水を供給して地盤を加圧
しながら、他方の管路を通して、掘進機で掘削された土
砂を泥水とともに後方に排出することを特徴とする埋設
管の推進工法。1. An excavator and a buried pipe by applying a propulsive force to the propulsion shaft while successively adding a propulsion shaft and a buried pipe held and fixed on the outside of the propulsion shaft to the rear of the excavator. In the propulsion method of the buried pipe that propels the digging hole into the burial hole, the excavation face plate rotatably provided at the tip of the excavator is rotationally driven by the drive source arranged in the excavator, and the tip side is fixed to the excavator. The propulsion shaft to which the propulsive force is applied is composed of a double pipe, and water or muddy water is supplied to the excavator through one of the inner and outer pipe lines of the double pipe while pressurizing the ground. , A propulsion method for buried pipes, characterized in that the earth and sand excavated by an excavator is discharged backward together with mud through the other pipeline.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2289901A JPH0768875B2 (en) | 1990-10-26 | 1990-10-26 | Buried pipe propulsion method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2289901A JPH0768875B2 (en) | 1990-10-26 | 1990-10-26 | Buried pipe propulsion method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH04161695A JPH04161695A (en) | 1992-06-05 |
| JPH0768875B2 true JPH0768875B2 (en) | 1995-07-26 |
Family
ID=17749241
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2289901A Expired - Lifetime JPH0768875B2 (en) | 1990-10-26 | 1990-10-26 | Buried pipe propulsion method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0768875B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107576238B (en) * | 2017-10-12 | 2023-05-12 | 贵州大学 | Mining blasting is with buried pipe device |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS63114800A (en) * | 1986-07-21 | 1988-05-19 | 株式会社機動技術研究所 | Muddy water type shield excavator for small bore pipe |
| JPH0696945B2 (en) * | 1988-11-26 | 1994-11-30 | 機動建設工業株式会社 | Method and device for burial of buried pipe |
-
1990
- 1990-10-26 JP JP2289901A patent/JPH0768875B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH04161695A (en) | 1992-06-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO1994020730A1 (en) | Double wall pipe for propulsion technique and construction of pipe end of leading pipe | |
| JPH0768875B2 (en) | Buried pipe propulsion method | |
| JP4214082B2 (en) | Propulsion method excavation equipment and propulsion method | |
| JPH03290590A (en) | Jacking method of underground pipe | |
| JP3830918B2 (en) | Tunnel excavator for pipe formation | |
| JP4156582B2 (en) | Underground excavation equipment | |
| JP2001227300A (en) | Tunnel back filling device and method of construction | |
| JP2005282196A (en) | Water cut-off device | |
| JPH11107675A (en) | Underwater shield method and shield machine used for it | |
| JPH1068290A (en) | Gas pipe burial method | |
| JPH1193562A (en) | Branch shield excavation method and shield excavator capable of branch excavation | |
| JPH02178496A (en) | Re-laying method for existing pipeline and underground excavating device | |
| JPH1163299A (en) | Execution method of multi-conduit pipe and multi-conduit pipe | |
| JP3323178B2 (en) | Underground joining type shield machine and underground joining method | |
| JP3347312B2 (en) | Underground joining type shield machine and underground joining method | |
| JP3145345B2 (en) | Method of laying vacuum sewer pipe and composite pipe for vacuum sewer pipe | |
| JP2863492B2 (en) | Propulsion method, excavation device and propulsion device | |
| JP4015110B2 (en) | Pipe construction method and pipe construction device having large diameter part | |
| JP3773842B2 (en) | Muddy water propulsion method, feed / drain mud pipe and muddy water propulsion method equipment | |
| JP2952105B2 (en) | Piping materials used in mud pressurized propulsion method | |
| JP5463049B2 (en) | Synthetic pipe bending equipment | |
| JP3585446B2 (en) | Underground pipeline construction method | |
| JP6230284B2 (en) | Existing pipe renewal method | |
| JP3487645B2 (en) | Underground joining structure and underground joining method of different diameter shield machine | |
| JPS6280384A (en) | Method of replacement construction of residual pipe |