Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0774507B2 - Construction method of underground wall - Google Patents
[go: Go Back, main page]

JPH0774507B2 - Construction method of underground wall - Google Patents

Construction method of underground wall

Info

Publication number
JPH0774507B2
JPH0774507B2 JP2037892A JP3789290A JPH0774507B2 JP H0774507 B2 JPH0774507 B2 JP H0774507B2 JP 2037892 A JP2037892 A JP 2037892A JP 3789290 A JP3789290 A JP 3789290A JP H0774507 B2 JPH0774507 B2 JP H0774507B2
Authority
JP
Japan
Prior art keywords
wall
underground
construction
steel
retaining material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2037892A
Other languages
Japanese (ja)
Other versions
JPH03241117A (en
Inventor
博光 矢野
誠一郎 木村
健治 岡田
光延 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2037892A priority Critical patent/JPH0774507B2/en
Publication of JPH03241117A publication Critical patent/JPH03241117A/en
Publication of JPH0774507B2 publication Critical patent/JPH0774507B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は建築物の地下部分の外壁の構築工法に係り、と
くに、外壁構築位置の外方に土留壁を設置するときに、
土圧の支持のための土留材の設置方法に関するものであ
る。
TECHNICAL FIELD The present invention relates to a method for constructing an outer wall of a basement part of a building, and particularly when installing a retaining wall outside the outer wall constructing position.
The present invention relates to a method of installing earth retaining material for supporting earth pressure.

[従来の技術] 建築物の地下部分を掘削し、地下外壁を構築するに際し
ては、外壁構築位置の外方にH型鋼親杭、シートパイル
等の鋼製土留材を設置して掘削用の土留壁として使用
し、建築物の地下外壁の完成後には鋼製土留材を撤去す
る。この工法の基本的な構成はよく知られており、土留
壁の撤去、とくに鋼製土留材の地上からの引き抜きを容
易にするために、外壁のコンクリートと鋼製土留材との
付着を絶縁させておくようにしている。このため、従来
では、このような山留材の絶縁材として、薄いベニヤ板
やビニールシート等を使用して、コンクリートとの接触
部分を絶縁することが知られている。
[Prior art] When excavating the underground part of a building and constructing an underground wall, a steel soil retaining material such as an H-shaped steel parent pile or sheet pile is installed outside the outer wall construction position to retain soil for excavation. It will be used as a wall and the steel retaining material will be removed after the underground wall of the building is completed. The basic structure of this construction method is well known, and in order to facilitate the removal of the soil retaining wall, especially the removal of the steel soil retaining material from the ground, the insulation between the concrete on the outer wall and the steel soil retaining material is insulated. I keep it. Therefore, it has been conventionally known to use a thin plywood board, a vinyl sheet, or the like as an insulating material for such a mountain retaining material to insulate a contact portion with concrete.

[発明が解決しようとする課題] 上記のような従来の絶縁材を用いた方法では、 絶縁材料として回収不能の高価な資材費が必要であ
り、その鋼製土留材への取付構造が確実ではなく、隙間
を生じたり、入隅部の施工が困難であったりして取付に
手間がかかり、しかも、コンクリート打設等の壁体の構
築工事中に脱落する惧れがある。
[Problems to be Solved by the Invention] In the method using the conventional insulating material as described above, an expensive material cost that cannot be recovered as the insulating material is required, and the mounting structure to the steel soil retaining material is not reliable. However, there is a risk that it will take a lot of time to install it due to the formation of gaps and the difficulty in constructing the entry corners, and it may fall off during construction work of the wall such as concrete pouring.

土留壁面に絶縁材を設けるには、土留壁面に近接して
取付けなければならないので、特別の足場を必要とし、
足場の仮設費がかかると共に、高書技能工を要する。
In order to install an insulating material on the earth retaining wall, it must be installed close to the earth retaining wall, so a special scaffold is required,
Temporary scaffolding costs are required and high-skilled craftsmen are required.

また、絶縁材料、ことに、胴縁材等の木製の支持材が
コンクリート中に異物として残留する惧れがあり、それ
自体または鉄筋の腐食の原因になるばかりでなく、設計
断面に欠損部分を生ずる惧れさえもある。
In addition, there is a risk that insulating materials, especially wooden support materials such as furring materials, may remain as foreign matter in the concrete, causing not only corrosion of the reinforcing bars themselves or of the reinforcing bars, but also defective parts in the design cross section. There is even a fear of it.

引き抜いた後の土留材に付着したコンクリートをケレ
ン等の手間をかけて清掃する必要がある。等の欠点が多
く、いずれも工期の延引や工事費に影響することが避け
られず、外壁の構築工法における課題となっていた。
It is necessary to clean the concrete adhering to the soil retaining material after pulling it out by taking some time to clean it. There are many drawbacks such as the above, and it is inevitable that the construction period will be extended and the construction cost will be affected.

[課題を解決するための手段] 本発明は、上述のような課題の解決を図ることを目的と
して創案されたものであって、鋼製土留材と地下外壁コ
ンクリートとの絶縁方法を改善することによって、地下
外壁の構築工法を合理化することを要旨としている。そ
して本発明が採用する技術的手段は、建築物の地下外壁
の構築工法において、とくに、鋼製土留材の地下外壁と
の接触内面に発泡ウレタンを吹付けて地下外壁との絶縁
層を形成する工程を包含することを特徴としている。こ
れによって、本発明の地下外壁の構築工法は、従来公知
の地下外壁の構築工法を基本にするものでありながら、
鋼製土留材の内面に吹付けた発泡ウレタンの絶縁層によ
って、鋼製土留材と壁体構築用のコンクリートとの絶縁
が確保され、しかも、鋼製土留材の引き抜きが容易かつ
確実であり、あわせて、建築物の地下工事における工
期、工費上の不利を回避することができるものである。
[Means for Solving the Problems] The present invention has been devised for the purpose of solving the problems described above, and to improve a method for insulating steel retaining material from steel and underground concrete for outer wall. The purpose is to rationalize the construction method of the underground wall. And the technical means adopted by the present invention is, in the construction method of the underground outer wall of the building, in particular, the foaming urethane is sprayed on the inner surface of the steel earth retaining material in contact with the underground outer wall to form the insulating layer with the underground outer wall. It is characterized by including steps. Thereby, the construction method of the underground outer wall of the present invention is based on the conventionally known construction method of the underground outer wall,
The insulating layer of urethane foam sprayed on the inner surface of the steel soil retaining material ensures insulation between the steel soil retaining material and the concrete for building the wall body, and furthermore, the steel soil retaining material can be easily and reliably pulled out, At the same time, it is possible to avoid disadvantages in terms of construction period and construction cost in the underground construction of the building.

[作用] 本発明を、建築物の地下外壁の構築に適用する場合の作
用は、まず、建築物の外壁位置の外周部分に、地上から
H型鋼等の親杭を所定間隔ごとに打設する。ついで、地
下室部分の掘削の進行に伴って、H型鋼の内側のフラン
ジを使用しながら、土留板として横矢板を架けわたし、
土留壁を構成する。もちろん、鋼製土留材としてシート
パイルを連設したものを使用することができる。この段
階で、掘削の根切り面に装備した移動式足場または、親
杭の頂部に架設した腹起しの切梁上の通路、足場等か
ら、現場発泡のウレタンを、直接親杭の内面全体に吹き
付け、絶縁層を形成する。ここで、地下外壁の構築に移
行し、通常は前記土留壁の内面を外側型枠として、コン
クリートを打設し、地下室部分の外壁を構築する。
[Operation] When the present invention is applied to the construction of the underground outer wall of a building, first, a parent pile of H-shaped steel or the like is driven from the ground at predetermined intervals on the outer peripheral portion of the outer wall of the building. . Then, as the excavation of the basement progressed, while using the inner flange of H-shaped steel, lay a horizontal sheet pile as a retaining plate,
Make up the retaining wall. Of course, as the soil retaining material made of steel, it is possible to use a series of sheet piles. At this stage, from the mobile scaffolding installed on the excavation surface of the excavation, or the passage, scaffolding, etc. on the upset cut beam installed on the top of the parent pile, urethane foamed on-site is directly applied to the entire inner surface of the parent pile. To form an insulating layer. Here, the process moves to the construction of the outer wall of the underground, and usually, the inner surface of the earth retaining wall is used as the outer formwork, concrete is poured, and the outer wall of the basement is constructed.

つぎに、構築工事場に別途に用意された機械を使用し
て、土留板と親杭とを順次に引き抜くと、ウレタンはH
型鋼の面で剥離し、地中内に残されたまま、地下外壁の
構築が完了する。
Next, using a machine separately prepared at the construction site, the soil retaining plate and the main pile are pulled out sequentially, and the urethane
The construction of the underground outer wall is completed while peeling off on the surface of the shape steel and leaving it in the ground.

[実施例] 本発明を採用して構築した地下外壁を図面に示す一実施
例に基づいて詳細に説明する。図面には地下外壁の一部
で示す本発明を採用した外壁の垂直断面図であって、図
中の1は地下外壁の全体を示し、2はその躯体コンクリ
ート、3は地下外壁1の内部の掘削空間、4は外部の地
盤、5は掘削空間3の根切底である。10は建築物の地下
外壁1の外方に設置される仮設の土留壁であり、11は所
定間隔に打設された鋼製土留材の一例としてのH型鋼製
の親杭、12は親杭11の内部側フランジ、13はフランジ12
間に架設された横矢板としての土留板、14は親杭11の頂
部を連結する腹起し、15は腹起し14に直角方向に設けた
切梁、16は切梁15上に設けた足場である。
[Example] An underground wall constructed by adopting the present invention will be described in detail based on an example shown in the drawings. FIG. 1 is a vertical sectional view of an outer wall adopting the present invention, which is shown as a part of the underground outer wall, in which 1 is the whole underground outer wall, 2 is its concrete concrete, 3 is the inside of the underground outer wall 1. The excavation space, 4 is the ground outside, and 5 is the root cut bottom of the excavation space 3. Reference numeral 10 is a temporary earth retaining wall installed outside the underground outer wall 1 of the building, 11 is an H-shaped steel parent pile as an example of a steel earth retaining material placed at predetermined intervals, and 12 is a parent. Inner flange of pile 11, 13 is flange 12
The earth retaining plate as a transverse sheet pile laid between them, 14 is an agitator that connects the tops of the parent piles 11, 15 is an agitated beam provided at a right angle to the agate 14, and 16 is provided on the cut beam 15. It is a scaffold.

本発明においては、親杭11の内部側フランジ12と、土留
板13の一部の面に、所定厚さの発泡ウレタン20を直接吹
き付けて絶縁層を形成してある。その施工には、根切底
5を適宜に捨てコンクリート51によって整地し、その上
に装備される移動式足場17、または切梁15上に設けた足
場16を使用して、容易に実施することができる。地下外
壁1のコンクリート2は、一部の挿入図のように、上記
の発泡ウレタン20の吹き付け後に、土留板13を外側の型
枠として発泡ウレタン20を介在させたまま打設してあ
る。
In the present invention, the urethane foam 20 having a predetermined thickness is directly sprayed on the inner side flange 12 of the parent pile 11 and a part of the surface of the earth retaining plate 13 to form an insulating layer. For the construction, the root cutting bottom 5 should be appropriately discarded, and the ground should be leveled with concrete 51, and the scaffolding 16 mounted on the scaffolding 15 or the movable scaffolding 17 mounted on the scaffolding 16 should be used for easy construction. You can As shown in a part of the inset, the concrete 2 of the underground outer wall 1 is cast while the urethane foam 20 is sprayed and the clay retaining plate 13 is used as an outer mold to interpose the urethane foam 20.

従って、地下外壁1の構築後に、土留板13とH型鋼の親
杭11を引き抜けば、内面の発泡ウレタン20とコンクリー
ト2とが付着していることから、土留板13とH型鋼の親
杭11とが発泡ウレタン20から剥離し、大きな外力を使用
することなく、発泡ウレタン20を地盤4の土中に残した
まま回収される。そしてその表面にはコンクリートが付
着していることがなく、従って、その清掃除去等の作業
も不要である。
Therefore, if the soil retaining plate 13 and the H-shaped steel parent pile 11 are pulled out after the construction of the underground outer wall 1, the urethane foam 20 and the concrete 2 on the inner surface are adhered to each other. 11 and 11 are separated from the urethane foam 20, and the urethane foam 20 is recovered while being left in the soil of the ground 4 without using a large external force. Further, concrete is not attached to the surface thereof, and therefore the work of cleaning and removing it is unnecessary.

[発明の効果] 本発明は、建築物の外壁構築位置の外方に地上から鋼製
土留材を打設し、該土留材内方の掘削を行って、地下外
壁を構築した後に、上記土留材を引き抜くようにした地
下外壁の構築工法であって、鋼製土留材の地下外壁との
接触内面に発泡ウレタンを吹付けて地下外壁との絶縁層
を形成する工程を包含することを特徴とする地下外壁の
構築工法であるから、まず、従来技術の欠点がすべて回
避され、本発明に課せられた課題が解決される。すなわ
ち、絶縁材料として使用される発泡ウレタンの材料費は
低廉であるばかりでなく、その鋼製土留材への取付は吹
付作業で行われるから、大工等の技能工を必要とせず、
隙間を生じたり入隅部の施工が困難であったりすること
がなく、施工速度も大きい。しかも、コンクリート打設
等の壁体の構築工事中に脱落することがない。また、吹
付作業はその特性上、掘削の進行に伴って切梁等から施
工することができ、土留壁面に対して特別の足場を必要
とせず仮設費がかからない。さらに、養生材料の発泡ウ
レタンが残留しても、土中側であり、腐食の惧れがない
ばかりでなく、設計断面に欠損部分を生ずることなく、
引き抜いた後の鋼製土留材にはコンクリートが付着して
いることがないから、コンクリートをケレンする等の手
間をかけて清掃することが一切不要である。
[Advantage of the Invention] The present invention is to place a steel soil retaining material from the ground outside the outer wall construction position of a building, excavate inside the soil retaining material, and construct an underground outer wall, A method for constructing an underground outer wall so as to pull out a material, characterized by including a step of spraying urethane foam on the inner surface of the steel soil retaining material in contact with the underground outer wall to form an insulating layer with the underground outer wall First, all the drawbacks of the prior art are avoided, and the problems imposed on the present invention are solved. That is, not only is the material cost of urethane foam used as an insulating material low, but since its attachment to the steel soil retaining material is done by spraying work, it does not require a skilled worker such as carpenter,
There is no gap or difficulty in the construction of the corners, and the construction speed is high. Moreover, it does not fall off during construction work of the wall such as concrete pouring. In addition, the spraying work can be performed from a cutting beam or the like as the excavation progresses due to its characteristics, and no special scaffolding is required for the earth retaining wall and temporary construction costs are not required. Furthermore, even if the urethane foam of the curing material remains, it is in the soil side, not only there is no fear of corrosion, but there is no defect in the design cross section,
Since concrete is not adhered to the steel soil retaining material after it is pulled out, it is not necessary to clean the concrete by cleaning the concrete.

要するに、本発明の地下外壁の構築工法は、従来技術の
構築工法を基本とするものでありながら、主要工程の鋼
製土留材の絶縁を改善したものあるから、従来の構築工
法に比べ、工期ならびに工費を大幅に削減することがで
きる利点を有し、地下外壁の構築工法の改善に画期的効
果をもたらす発明というべきである。
In short, the construction method of the underground outer wall of the present invention is based on the construction method of the conventional technology, but it has improved the insulation of the steel soil retention material in the main process, so the construction period is shorter than that of the conventional construction method. In addition, it should be an invention that has the advantage of being able to significantly reduce the construction cost and brings a revolutionary effect to the improvement of the construction method of the underground outer wall.

【図面の簡単な説明】[Brief description of drawings]

図面は本発明の地下外壁の構築工法を採用した地下外壁
の一部で示す垂直断面図である。 1…地下外壁、2…躯体コンクリート、3…内部の掘削
空間、4…地盤、4…根切底、10…土留壁、11…鋼製土
留材、親杭、H型鋼、12…その内部側フランジ、13…土
留板、14…腹起し、15…切梁、16…足場、17…移動式足
場、20…発泡ウレタン、51…捨てコンクリート。
The drawing is a vertical cross-sectional view showing a part of the underground outer wall adopting the construction method of the underground outer wall of the present invention. DESCRIPTION OF SYMBOLS 1 ... Underground outer wall, 2 ... Structural concrete, 3 ... Internal excavation space, 4 ... Ground, 4 ... Root cutting, 10 ... Soil retaining wall, 11 ... Steel retaining material, parent pile, H-shaped steel, 12 ... Inside Flange, 13 ... Cladding plate, 14 ... Raised, 15 ... Girder, 16 ... Scaffolding, 17 ... Mobile scaffolding, 20 ... Urethane foam, 51 ... Waste concrete.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】建築物の外壁構築位置の外方に地上から鋼
製土留材を打設し、該土留材内方の掘削を行って、地下
外壁を構築した後に、上記土留材を引き抜くようにした
地下外壁の構築工法であって、鋼製土留材の地下外壁と
の接触内面に発泡ウレタンを吹付けて地下外壁との絶縁
層を形成する工程を包含することを特徴とする地下外壁
の構築工法。
1. A steel soil retaining material is cast from the ground outside the building outer wall construction position, the inside of the soil retaining material is excavated to construct an underground outer wall, and then the soil retaining material is pulled out. The method for constructing an underground outer wall, comprising the step of spraying urethane foam on the inner surface of the steel soil retaining material in contact with the underground outer wall to form an insulating layer with the underground outer wall. Construction method.
JP2037892A 1990-02-19 1990-02-19 Construction method of underground wall Expired - Lifetime JPH0774507B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2037892A JPH0774507B2 (en) 1990-02-19 1990-02-19 Construction method of underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2037892A JPH0774507B2 (en) 1990-02-19 1990-02-19 Construction method of underground wall

Publications (2)

Publication Number Publication Date
JPH03241117A JPH03241117A (en) 1991-10-28
JPH0774507B2 true JPH0774507B2 (en) 1995-08-09

Family

ID=12510194

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2037892A Expired - Lifetime JPH0774507B2 (en) 1990-02-19 1990-02-19 Construction method of underground wall

Country Status (1)

Country Link
JP (1) JPH0774507B2 (en)

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS52113004A (en) * 1976-03-17 1977-09-21 Takenaka Komuten Co Method of extracting main sheathing pile
JPS5373818A (en) * 1976-12-14 1978-06-30 Kensetsu Kouhou Kaihatsu Kk Method of making continuous sand guard wall of pillar train
JPS5917265B2 (en) * 1981-05-27 1984-04-20 アイシン精機株式会社 exhaust gas recirculation valve
JPH0247418A (en) * 1988-08-05 1990-02-16 Nippon Petrochem Co Ltd Concrete wall body constructing method

Also Published As

Publication number Publication date
JPH03241117A (en) 1991-10-28

Similar Documents

Publication Publication Date Title
JP3728654B2 (en) Building dismantling and construction methods
US20140223851A1 (en) Prefabricated reinforced concrete wall panel and installation method
CN103132465B (en) Underground box culvert constructing method closely attached to pile foundation bearing platform
US2166632A (en) Method of constructing concrete manholes
US6220789B1 (en) Integrated excavation shoring building foundation method
JP6418683B2 (en) Temporary support method
JP3122850B2 (en) Construction method of building with basement floor with steel pipe pile foundation
JPH0774507B2 (en) Construction method of underground wall
KR101971554B1 (en) Method constructuring an underground structure using a temporary structure
JP3281554B2 (en) How to rebuild underground structures
JPH084033A (en) Construction method of the pressure barrier against the outer perimeter of the building
JPH09111776A (en) Basement and construction method thereof
JP3567387B2 (en) How to build an underground skeleton
JP2000282695A (en) Existing building seismic isolation method
JP2620035B2 (en) Construction method and structure of gas station office building
JP3020882B2 (en) Construction method of building structure with underground space
JP3062539B2 (en) Underground wall and its construction method
JP2001323485A (en) Method of constructing underground structure
CN121932040A (en) Static correction method for Shikumen
KR200400509Y1 (en) United type C-panel concrete by SSM
JPS6350491B2 (en)
JPH0681354A (en) How to build an underground structure
CN105604180A (en) Construction method of an underground structure
CN117449346A (en) A hanging board construction method for controlling the appearance of anti-sliding piles
JPH076204B2 (en) How to build an underground structure