JPH0781498B2 - How to build multiple tunnels - Google Patents
How to build multiple tunnelsInfo
- Publication number
- JPH0781498B2 JPH0781498B2 JP63213893A JP21389388A JPH0781498B2 JP H0781498 B2 JPH0781498 B2 JP H0781498B2 JP 63213893 A JP63213893 A JP 63213893A JP 21389388 A JP21389388 A JP 21389388A JP H0781498 B2 JPH0781498 B2 JP H0781498B2
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- lining
- tunnels
- sand
- secondary lining
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明は地中に構築される多連形トンネルの築造方法に
関する。Description: TECHNICAL FIELD The present invention relates to a method for constructing a multiple tunnel constructed underground.
(従来の技術) 単胴のシールドトンネルや、例えばまゆ形等の多連形の
トンネルの築造においては、掘削による土砂搬出,一次
覆工用資材の出入りと二次覆工用の型枠等の設備が必要
である。(Prior art) In the construction of a single-shield shield tunnel or a multi-layered tunnel such as an eyebrow type, when excavating earth and sand, moving in and out of materials for primary lining and formwork for secondary lining, etc. Equipment is required.
(発明が解決しようとする課題) しかしながら、単胴のシールドトンネルでは、トンネル
が一つであるため、掘削による土砂搬出,一次覆工用資
材の出入りと二次覆工用の型枠等の設備が競合し、同時
に施工を行うことができず、一次覆工完了後に二次覆工
を行っていたため、全体の工期が非常に長くなり、さら
に工事費も高くなるといった課題があった。(Problems to be solved by the invention) However, since there is only one tunnel in a single-body shield tunnel, equipment such as carrying out earth and sand by excavation, entry and exit of materials for primary lining, and formwork for secondary lining, etc. However, there was a problem that the entire construction period was extremely long and the construction cost was also high because the construction was not possible at the same time and the secondary lining was performed after the completion of the primary lining.
また、トンネル数が一以上の多連形のトンネルにおいて
も、特に一次覆工用資材の出入りと二次覆工用の型枠等
の設備をいかにするかについての配慮が全くなされて居
らず、一次覆工完了後に二次覆工を行っているという現
状にあり、作業を効率よく行うことができず、工期の短
縮化が図られていないという課題があった。In addition, even in the case of multiple tunnels with one or more tunnels, no particular consideration is given to how to put in and out the primary lining material and the equipment such as the formwork for the secondary lining, There is a problem that the secondary lining is performed after the completion of the primary lining, and the work cannot be performed efficiently, and the construction period is not shortened.
本発明はこのようなことに鑑み提案されたもので、その
目的とするところは、トンネル数が一以上の多連形シー
ルドトンネルにおいて、工期を大幅に短縮でき、その結
果、工事費を低減し得る築造方法を提供することにあ
る。The present invention has been proposed in view of the above circumstances, and an object thereof is to significantly reduce the construction period in a multi-section shield tunnel having one or more tunnels, and as a result, reduce the construction cost. It is to provide a building method to gain.
(課題を解決するための手段) 本発明では、複数のトンネルを有する多連形断面のシー
ルドトンネルの築造において、セグメント・掘削土砂の
出入り等を何れか一または一以上のトンネルを使用して
掘削、一次覆工を行い、残った一または一以上のトンネ
ル内を二次覆工し、これを一定の長さごとに交互に行っ
ていくことにより、シールドトンネルの一次覆工と二次
覆工との作業を略同時平行的に施工することにより、上
記目的を達成している。(Means for Solving the Problem) According to the present invention, in constructing a shield tunnel having a multiple cross section having a plurality of tunnels, excavation is performed using any one or more of the segments, excavation of sand, etc. The primary lining and the secondary lining of the shield tunnel are performed by performing the primary lining and secondary lining in the remaining one or more tunnels, and by alternately performing this for each fixed length. The above-mentioned object is achieved by carrying out the work with and in parallel with each other.
(作用) 多連形シールドトンネルの一または複数を一次覆工用資
材の出入りに使用し、残りの他のトンネル内で一次覆工
に影響されることなく二次覆工を略平行して施工し、そ
れをある延長ごとに交互に行うことにより、一次覆工と
二次覆工とを略平行して施工することができるようにし
ている。(Operation) One or more multiple tunnel tunnels are used for the entry and exit of the primary lining material, and the secondary lining is constructed in parallel in the remaining other tunnels without being affected by the primary lining. The primary lining and the secondary lining can be constructed substantially in parallel by performing them alternately for each extension.
したがって、大幅な工期の短縮が可能となり、さらに工
事費の低減にもつながる。Therefore, the construction period can be significantly shortened and the construction cost can be reduced.
(実施例1) 第1図(a),(b)は本発明の第1実施例を示すもの
で、この実施例では上側のトンネルを一次覆工用資材の
出入りに使用し、下側のトンネルで二次覆工を行うよう
にしている。すなわち、先ず、図中1は多連形トンネル
の築造用のシールド機、2はシールド機1の前進に伴っ
てセグメント3を組込んで築造された多連形のトンネ
ル、4はトンネル内を複数のトンネル2a,2bに区画形成
するためのトンネル隔壁、5はシールド機1の隔壁6の
下部に前端が接続された切羽室7内の掘削土砂を外部に
排出する。例えばスクリューコンベアの如き排土装置で
あり、その後方部の排土口は下側のトンネル2b内に位置
され、かつベルトコンベア8,土砂圧送ポンプ9等の如き
排土装置が連設されている。(Embodiment 1) FIGS. 1 (a) and 1 (b) show a first embodiment of the present invention. In this embodiment, the upper tunnel is used for the entrance and exit of the primary lining material, and the lower tunnel is used. The secondary lining is done in the tunnel. That is, in the figure, 1 is a shield machine for constructing multiple tunnels, 2 is a multiple tunnel constructed by incorporating a segment 3 as the shield machine 1 advances, and 4 is a plurality of tunnel interiors. The tunnel bulkheads 5 for partitioning and forming the tunnels 2a, 2b of the shield machine 1 discharge the excavated earth and sand in the cutting chamber 7 whose front end is connected to the lower portion of the bulkhead 6 of the shield machine 1 to the outside. For example, it is an earth discharging device such as a screw conveyor, and the earth discharging port at the rear part thereof is located in the lower tunnel 2b, and the earth discharging device such as the belt conveyor 8 and the earth and sand pump 9 is connected in series. .
しかして、シールド機1より排土装置5を介して排出さ
れた掘削土は、下側のトンネル2bに設けられたベルトコ
ンベア8や土砂圧送ポンプ9等により上側のトンネル2a
内に設けられた土砂バケット10内に積み込まれる。そし
て、この土砂バケット10はバッテリー機関車11に引か
れ、上側トンネル2a内に設備されたレール12上を走行
し、坑外へ排出される。Then, the excavated soil discharged from the shield machine 1 through the soil discharging device 5 is transferred to the upper tunnel 2a by the belt conveyor 8 and the earth and sand pressure pump 9 provided in the lower tunnel 2b.
It is loaded in the earth and sand bucket 10 provided inside. Then, the earth and sand bucket 10 is pulled by the battery locomotive 11, travels on the rail 12 provided in the upper tunnel 2a, and is discharged to the outside of the mine.
この場合、トンネル隔壁4の適位置にはセグメント3を
取り外して上側のトンネル2aと下側のトンネル2bとの連
絡路となる開孔部4aが形成され、この開孔部4aを介して
土砂圧送ポンプ9からの排出管9aが上側のトンネル2a内
に設けられた土砂バケット10に延びている。In this case, the segment 3 is removed at an appropriate position of the tunnel partition wall 4 to form an opening 4a serving as a communication path between the upper tunnel 2a and the lower tunnel 2b, and the earth and sand pressure feeding is performed through this opening 4a. A discharge pipe 9a from the pump 9 extends to a sediment bucket 10 provided in the upper tunnel 2a.
また、セグメント3は、台車13に載せられ、坑外よりバ
ッテリー機関車11と空の土砂バケット10と共に、上側ト
ンネル2a内に設備されたレール12上を走行し、開口部4a
の手前まで搬入される。In addition, the segment 3 is mounted on a bogie 13 and travels from the outside of the mine along with a battery locomotive 11 and an empty earth and sand bucket 10 on a rail 12 installed in the upper tunnel 2a, and an opening 4a.
Is delivered to the front.
しかして、セグメント3は、上側トンネル2a内の上部に
走行自在に設けられた走行クレーン14により上側用セグ
メント台車13′および下側用セグメント台車13″にそれ
ぞれ積み込まれシールド機1まで運搬され組み立てられ
る。Then, the segment 3 is loaded into the upper segment carriage 13 'and the lower segment carriage 13 "by the traveling crane 14 provided in the upper part of the upper tunnel 2a so as to travel freely, and is transported to the shield machine 1 to be assembled. .
このように掘削土砂等の搬出およびセグメント3等の資
材の搬入のほとんどを上側のトンネル2a側において行
い、一次覆工を行うため、下側トンネル2b内において
は、トンネル後方における掘削土砂の搬送、坑外からの
セグメント3の搬入等の一次覆工に影響されることなく
略平行的に二次覆工を行うことができる。In this way, most of the excavation of sand and sand and the transportation of materials such as segments 3 are carried out on the upper tunnel 2a side, and the primary lining is carried out. Therefore, in the lower tunnel 2b, the transportation of excavated earth and sand behind the tunnel, The secondary lining can be performed substantially in parallel without being affected by the primary lining such as the loading of the segment 3 from the outside of the mine.
二次覆工は通常の場合と同様に移動式型枠15を使用し、
コンクリート圧送管16により生コンクリート等を一次覆
工セグメント3′と型枠17の間に打設していくことによ
り、迅速にトンネル2内の内側に二次覆工コンクリート
18を構築することができる。The secondary lining uses the movable formwork 15 as usual,
By placing fresh concrete or the like between the primary lining segment 3 ′ and the formwork 17 by the concrete pumping pipe 16, the secondary lining concrete is quickly placed inside the tunnel 2.
18 can be built.
そして、下側トンネル2b内の二次覆工を、ある一定の延
長(例えば100m)完了後、移動式型枠15の一部または全
部を解体撤去し、その中を一次覆工用の資材の出入に使
用し、逆の上側において二次覆工を行い、この作業を順
次交互に繰り返すことにより、第1図(b)に示すよう
に、トンネル2の内側に二次覆工コンクリート18を容易
に設けることができ、工期を大幅に短縮することができ
る。Then, after the secondary lining in the lower tunnel 2b has been extended to a certain extent (for example, 100 m), part or all of the mobile formwork 15 is dismantled and removed, and the inside of the secondary lining is filled with the material for the primary lining. It is used for entrance and exit, and secondary lining is performed on the opposite upper side, and by repeating this work alternately in sequence, as shown in Fig. 1 (b), the secondary lining concrete 18 can be easily installed inside the tunnel 2. It can be installed in the, and the construction period can be significantly shortened.
なお、泥水式のように排出される掘削土砂が流動性に富
んでいるものにおいて切羽室内の土砂排出用の排出管は
トンネルの口径にもよるが差程二次覆工の邪魔にならな
いので、開口部4aを介し上側トンネル2a側に設けること
なく、下側トンネル2b内に設けることも可能である。In addition, in the case where the excavated earth and sand discharged like the mud type is highly fluid, the discharge pipe for discharging the earth and sand in the face chamber does not interfere with the secondary lining because it depends on the diameter of the tunnel. It is also possible to provide it in the lower tunnel 2b without providing it in the upper tunnel 2a side through the opening 4a.
(実施例2) 第2図は本発明の第2実施例を示すもので、この例では
一次覆工用の通路と二次覆工の施工位置とを上下逆にし
た点が第1実施例と異なっており、材料の出入り,受け
渡し方法は同様である。(Embodiment 2) FIG. 2 shows a second embodiment of the present invention. In this embodiment, the point that the passage for the primary lining and the construction position of the secondary lining are turned upside down is the first embodiment. The same as the method of moving in and out of materials.
なお、同一部材は同じ符合で示し説明は省略する。In addition, the same members are denoted by the same reference numerals and the description thereof will be omitted.
(実施例3) 第3図は本発明の第3実施例を示すもので、シールド機
1の排土装置5の後端を下側トンネル2bから上側トンネ
ル2a側にかけて立ち上がらせ、かつ各トンネル2a,2b部
分にそれぞれ第1,第2の排土口5a,5bを設け、シールド
機1の部分において必要に応じ上側トンネル2a内、また
は下側トンネル2b内に掘削土砂を出すことを可能とした
ものである。(Embodiment 3) FIG. 3 shows a third embodiment of the present invention, in which the rear end of the soil discharging device 5 of the shield machine 1 is raised from the lower tunnel 2b to the upper tunnel 2a, and each tunnel 2a The first and second earth discharge ports 5a and 5b are provided in the 2 and 2b portions, respectively, so that the excavated earth and sand can be put out in the upper tunnel 2a or the lower tunnel 2b in the shield machine 1 portion if necessary. It is a thing.
しかして、下側トンネル2b内に掘削土砂を排出して、第
1図に示した実施例のように、上側トンネル2a内側に土
砂バケット10,バッテリー機関車11等を設け、上側トン
ネル2aを一次覆工用としたり、第2図に示した実施例の
ように、下側トンネル2b側から排土作業を行い、上側ト
ンネル2a側から二次覆工作業を行うようにしても良い。Then, the excavated earth and sand are discharged into the lower tunnel 2b, and as in the embodiment shown in FIG. 1, the earth and sand bucket 10, the battery locomotive 11, etc. are provided inside the upper tunnel 2a, and the upper tunnel 2a is primarily It may be used for lining, or as in the embodiment shown in FIG. 2, the lower tunnel 2b side may perform earth removal work and the upper tunnel 2a side may perform secondary lining work.
あるいは、上側トンネル2a側から掘削土砂を排土し、第
1図とは逆に下側トンネル2b側にレール12、その上を走
行可能な土砂バケット10,バッテリー機関車11等を設
け、下側トンネル2b側から一次覆工用の材料受け渡し
を、上側トンネル2a側から二次覆工を行っていっても良
い。Alternatively, excavated earth and sand are discharged from the upper tunnel 2a side, and contrary to FIG. 1, the lower tunnel 2b side is provided with a rail 12, a sand and sand bucket 10 capable of traveling on the rail 12, a battery locomotive 11, etc. The material for the primary lining may be transferred from the tunnel 2b side, and the secondary lining may be performed from the upper tunnel 2a side.
さらには、第2図に示す実施例とは全く逆に、排土口5a
から排土し、かつ上側トンネル2a側からそのまま土砂バ
ケット10を介し排土を行い、下側トンネル2b側から二次
覆工を行っても良い。Furthermore, contrary to the embodiment shown in FIG.
The soil may be discharged from the upper tunnel 2a side, the soil may be discharged directly from the upper side tunnel 2a side via the earth and sand bucket 10, and the secondary lining may be performed from the lower side tunnel 2b side.
(実施例4) 第4図は本発明の第4実施例を示すもので、前方のシー
ルド機1部分において走行クレーン14を介しセグメント
3の上下受渡しを行うようにしている。その他について
は第1,第2,第3実施例を適宜組み合わせて作業を行えば
良い。(Embodiment 4) FIG. 4 shows a fourth embodiment of the present invention, in which the segment 3 is vertically delivered via the traveling crane 14 in the front shield machine 1 portion. Others may be performed by appropriately combining the first, second and third embodiments.
なお、トンネル形状としては、第1図(b)に示したも
ののほか、第9図に示すようなものや、その他の縦形二
連の形状以外に、例えば第10図に示すような縦形三連以
上の多連形においても同様、何れか一か一以上の複数の
トンネル側を先ず一次覆工用とし、残りを二次覆工用と
するなどして施工できることは勿論である。As the tunnel shape, in addition to the one shown in FIG. 1 (b), as shown in FIG. 9 and other vertical double shapes, for example, a vertical triple shape as shown in FIG. It is needless to say that, in the above-described multi-strip type as well, any one or more of the plurality of tunnel sides can be used first for the primary lining and the rest for the secondary lining.
(実施例5) 上記各実施例では縦形二連ないし二連以上の多連シール
ドトンネルにおける施工方法について説明したが、以
下、横形二連シールドトンネルに本発明を適用する場合
について説明する。(Embodiment 5) In each of the above-mentioned embodiments, the construction method in the vertical double or multiple double shield tunnels has been described. Hereinafter, a case where the present invention is applied to the horizontal double shield tunnel will be described.
すなわち、第5図は本発明の第5実施例を示すもので、
シールド機1の前端から見て左側トンネル2a′内を先ず
一次覆工用とし、かつ右側トンネル2b′を二次覆工用と
したもので、トンネル隔壁4の一部に設けた開口部4aを
介し横方向の移動可能なトラバーサー19を用いて左・右
のトンネル2a′,2b′相互間の材料,掘削土砂等の受け
渡しを行うようにしたことに特徴を有している。That is, FIG. 5 shows a fifth embodiment of the present invention,
When viewed from the front end of the shield machine 1, the inside of the left side tunnel 2a 'is first used for the primary lining and the right side tunnel 2b' is used for the secondary lining, and the opening 4a provided in a part of the tunnel partition wall 4 is provided. It is characterized in that the traverser 19 which can be moved in the lateral direction is used to transfer materials, excavated soil, and the like between the left and right tunnels 2a ′, 2b ′.
なお、一次覆工用の材料通路と二次覆工の施工を左右交
互に行っていくことは縦形の場合とまったく同様であ
り、同一部材は同じ符合で示し、詳細な説明は重複を避
けるために省略する。It should be noted that the material passage for the primary lining and the construction of the secondary lining are performed alternately on the left and right, which is exactly the same as in the case of the vertical type, the same members are indicated by the same reference numerals, and the detailed description is to avoid duplication. Omitted in.
(実施例6) 第6図は本発明の第6実施例を示すもので、この例では
各設備等の配置,施工を第5実施例と逆にした点が異な
っている。その他については同様である。(Embodiment 6) FIG. 6 shows a sixth embodiment of the present invention, which is different in that the arrangement and construction of each facility and the like are reversed from those of the fifth embodiment. Others are the same.
(実施例7) 第7図は本発明の第7実施例を示すもので、シールド機
1側にトラバーサー19を設け、左右の各トンネル2a′,2
b′内にそれぞれ適宜材料の受け渡しを行うようにして
いる。なお、図示例では排土装置5の排土口およびその
後方の設備の一部を左側トンネル2a′側に設けている
が、左右どちらのトンネル2a′,2b′側にするかについ
ては任意である。(Embodiment 7) FIG. 7 shows a seventh embodiment of the present invention, in which a traverser 19 is provided on the shield machine 1 side and the left and right tunnels 2a ', 2
Material is appropriately delivered in b '. In the illustrated example, the soil discharging port of the soil discharging device 5 and a part of the equipment behind the soil discharging device 5 are provided on the left side tunnel 2a ′ side, but it is optional as to which side the tunnel 2a ′, 2b ′ is located. is there.
また、上記第5図ないし第7図における実施例では横形
二連について示したが、例えば第8図に示すように、横
形三連以上の多連形についても同様に施工を行うことが
できることは勿論である。Further, in the embodiment shown in FIG. 5 to FIG. 7, the horizontal double station is shown. However, for example, as shown in FIG. Of course.
(発明の効果) 以上のように本発明によれば、複数のトンネルを有する
多連形断面のシールドトンネルの築造において、セグメ
ント・掘削土砂の出入り等を何れか一または一以上のト
ンネルを使用して掘削、一次覆工を行い、残った一また
は一以上のトンネル内を二次覆工し、これを一定の長さ
ごとに交互に行っていくことにより、シールドトンネル
の一次覆工と二次覆工との作業を略同時平行的に施工す
るようにしたから、工期を大幅に短縮でき、よって工事
費を削減し得る効果がある。(Effect of the Invention) As described above, according to the present invention, in constructing a shield tunnel having a multi-section cross-section having a plurality of tunnels, one or more tunnels are used for entry / exit of segments, excavated earth and sand, etc. Excavation and primary lining are performed, the remaining one or more tunnels are subjected to secondary lining, and the lining and secondary lining of the shield tunnel are performed by alternating this for a certain length. Since the lining work and the lining work are performed in parallel, the construction period can be greatly shortened, and the construction cost can be reduced.
第1図は本発明の第1実施例で、(a)図は縦形二連シ
ールドの一次覆工・二次覆工の同時施工例を示す説明
図、(b)図は二次覆工が完成したトンネルの正面図、
第2図は本発明の第2実施例における縦形二連シールド
の一次覆工・二次覆工の同時施工例、第3図は本発明の
第3実施例であって縦形二連シールド機内のスクリュー
コンベアに2つの排土口を設置した状態を示す説明図、
第4図は本発明の第4実施例であって縦形二連シールド
機内のエレクター部付近でのセグメント運搬図、第5
図,第6図はそれぞれ横形二連シールドの同時施工方法
における右側二次覆工時,左側二次覆工時を示す本発明
の第5,第6実施例、第7図は本発明の第7実施例の横形
二連シールド機内のエレクター部付近でのセグメント運
搬図、第8図はその他の多連横形トンネルの正面図、第
9図,第10図はその他の多連縦形トンネルの正面図を示
す。 1……シールド機、2……トンネル 2a……上側トンネル、2a′……左側トンネル 2b……下側トンネル、2b′……右側トンネル 3……セグメントFIG. 1 is a first embodiment of the present invention, FIG. 1 (a) is an explanatory view showing an example of simultaneous construction of primary and secondary linings of a vertical double shield, and FIG. Front view of the completed tunnel,
FIG. 2 shows an example of simultaneous construction of the primary and secondary linings of the vertical double shield in the second embodiment of the present invention, and FIG. 3 shows the third embodiment of the present invention in the vertical double shield machine. Explanatory diagram showing a state in which two soil discharge ports are installed on the screw conveyor,
FIG. 4 is a fourth embodiment of the present invention and is a segment transportation diagram in the vicinity of the erector in the vertical double shield machine,
Figures 6 and 6 respectively show the right side secondary lining and the left side secondary lining in the simultaneous construction method of the horizontal double shields, the fifth and sixth embodiments of the present invention, and Fig. 7 show the present invention. 7 is a segment transportation diagram near the erector in the horizontal double shield machine, FIG. 8 is a front view of other multiple horizontal tunnels, and FIGS. 9 and 10 are front views of other multiple vertical tunnels. Indicates. 1 …… Shield machine, 2 …… Tunnel 2a …… Upper tunnel, 2a ′ …… Left tunnel 2b …… Lower tunnel, 2b ′ …… Right tunnel 3 …… Segment
フロントページの続き (56)参考文献 特開 平1−116191(JP,A) 特開 昭57−178095(JP,A) 特開 昭60−141993(JP,A) 特開 昭61−57799(JP,A)Continuation of front page (56) Reference JP-A-1-116191 (JP, A) JP-A-57-178095 (JP, A) JP-A-60-141993 (JP, A) JP-A-61-57799 (JP , A)
Claims (1)
ルドトンネルの築造において、セグメント・掘削土砂の
出入り等のほとんどを何れか一または一以上のトンネル
を使用して一次覆工を行い、残った一または一以上のト
ンネル内を二次覆工し、これを一定の長さごとに交互に
行っていくことにより、シールドトンネルの一次覆工と
二次覆工との作業を略同時平行的に施工することを特徴
とした多連形トンネルの築造方法。1. In the construction of a shield tunnel having a multi-section cross section having a plurality of tunnels, most of the segments, excavation of sand and sand, etc. are subjected to a primary lining using one or more tunnels and left. In addition, the secondary lining in one or more tunnels is performed, and the secondary lining and the secondary lining of the shield tunnel are performed almost simultaneously in parallel by performing the secondary lining alternately at fixed lengths. A method of constructing multiple tunnels, characterized by being constructed in
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63213893A JPH0781498B2 (en) | 1988-08-29 | 1988-08-29 | How to build multiple tunnels |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63213893A JPH0781498B2 (en) | 1988-08-29 | 1988-08-29 | How to build multiple tunnels |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0261293A JPH0261293A (en) | 1990-03-01 |
| JPH0781498B2 true JPH0781498B2 (en) | 1995-08-30 |
Family
ID=16646760
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP63213893A Expired - Fee Related JPH0781498B2 (en) | 1988-08-29 | 1988-08-29 | How to build multiple tunnels |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0781498B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2011030657A1 (en) | 2009-09-10 | 2011-03-17 | ジャパンスーパークォーツ株式会社 | Silica glass crucible for pulling silicon single crystal and method for producing same |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS57178095A (en) * | 1981-04-24 | 1982-11-02 | Taiho Kensetsu Kk | Construction of traverse pit |
| JPS60141993A (en) * | 1983-12-28 | 1985-07-27 | 大成建設株式会社 | Vertical two-step type shield |
| JPS6157799A (en) * | 1984-08-30 | 1986-03-24 | 植村 厚一 | Drilling of face of large cylinder and blade hole apparatus |
| JPH01116191A (en) * | 1987-10-30 | 1989-05-09 | Mitsui Constr Co Ltd | Shaft excavator |
-
1988
- 1988-08-29 JP JP63213893A patent/JPH0781498B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0261293A (en) | 1990-03-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP5492342B1 (en) | Shield tunnel floor slab, shield tunnel floor slab construction method, and shield tunnel construction method | |
| JP5584813B2 (en) | Shield tunnel construction method | |
| JP2012052289A (en) | Construction method for shield tunnel | |
| US3813885A (en) | Method for constructing an underground railway | |
| CN108915714B (en) | One-hole double-TBM (tunnel boring machine) installing method | |
| US5427439A (en) | Surface mining conveyor system | |
| JPH0781498B2 (en) | How to build multiple tunnels | |
| US3590590A (en) | Tunnel building | |
| KR100351270B1 (en) | 3 dimensional multi phase tunneling mathod and apparatus corresponding same | |
| EP0989285A1 (en) | Tunneling device | |
| CN119664342A (en) | An unmanned mining and filling method for strip branch lanes based on remote control continuous mining machine | |
| CN112282773A (en) | Construction system and construction method for small-section ultra-long water delivery tunnel in hard rock stratum | |
| JP3831900B2 (en) | Tunnel construction method | |
| JP3996597B2 (en) | Open shield machine and open shield method using it | |
| CN213775379U (en) | Construction system for small-section ultra-long water delivery tunnel in hard rock stratum | |
| CN113202491B (en) | TBM dismounting construction method | |
| US1999419A (en) | Conveyer apparatus | |
| CN109488318B (en) | Construction implementation method for passing through shaft of TBM device and building device | |
| CN116906044A (en) | Support type intelligent continuous mining continuous filling coal mining equipment and method | |
| SU1011861A1 (en) | Method of working rich deposits of minerals | |
| Hulme et al. | Bored tunneling for Singapore metro | |
| CN224032605U (en) | Parallel tunneling equipment used for simultaneous construction of two or more parallel tunnels. | |
| SU842196A1 (en) | Method of mining sloping ore bodies | |
| JP7097286B2 (en) | How to carry out the face | |
| RU2140542C1 (en) | Method of process filling of sections of mine field located under objects subject to protection |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |