Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH083183B2 - Retaining wall construction method using artificial lightweight soil - Google Patents
[go: Go Back, main page]

JPH083183B2 - Retaining wall construction method using artificial lightweight soil - Google Patents

Retaining wall construction method using artificial lightweight soil

Info

Publication number
JPH083183B2
JPH083183B2 JP63254827A JP25482788A JPH083183B2 JP H083183 B2 JPH083183 B2 JP H083183B2 JP 63254827 A JP63254827 A JP 63254827A JP 25482788 A JP25482788 A JP 25482788A JP H083183 B2 JPH083183 B2 JP H083183B2
Authority
JP
Japan
Prior art keywords
retaining wall
formwork
slope
lightweight soil
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP63254827A
Other languages
Japanese (ja)
Other versions
JPH02104823A (en
Inventor
孝成 芳賀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP63254827A priority Critical patent/JPH083183B2/en
Publication of JPH02104823A publication Critical patent/JPH02104823A/en
Publication of JPH083183B2 publication Critical patent/JPH083183B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Retaining Walls (AREA)

Description

【発明の詳細な説明】 《産業上の利用分野》 この発明は、人工軽量土を用いた擁壁の施工方法に関
する。
TECHNICAL FIELD The present invention relates to a method for constructing a retaining wall using artificial lightweight soil.

《従来の技術》 既存の土構造物の法面に擁壁を築造する工法は、例え
ば石積み擁壁であれば、法面の前面側に石積みを行な
い、その後裏込め土、裏込め砂利などを背面側に充填
し、このとき排出用パイプ等の施工も同時に行われてい
た。
<Conventional technology> For example, in the case of a masonry retaining wall, masonry is performed on the front side of the slope, and then backfilling soil, backfilling gravel, etc. It was filled on the back side, and at this time, construction of a discharge pipe and the like was also performed.

《発明が解決しようとする課題》 しかしながら、この石積みによる擁壁工法では前記法
面の前面に石積みと裏込めとを交互に繰り返しながら順
次構築するため、機械化施工が出来ず、施工の手間がか
かるほか、石積み技能者不足のおり、工期が長期化する
欠点があった。
<Problems to be solved by the invention> However, in this retaining wall construction method using masonry, masonry and backfilling are alternately repeated on the front surface of the slope to construct sequentially, so mechanized construction cannot be performed, and construction work is troublesome. In addition, there was a shortage of masonry engineers, which had the drawback of lengthening the construction period.

また、機械化施工ができないため、石積み擁壁の施工
とその背面の裏込め作業の時期がずれることから、擁壁
背面の裏込め土の圧縮によってその表面に不同沈下が生
じやすかった。
Moreover, since mechanized construction is not possible, the timing of construction of the masonry retaining wall and the backfilling work on the back side of the retaining wall is different, so that the settlement of the backfilling soil on the backside of the retaining wall tends to cause uneven settlement on the surface.

さらには、擁壁の勾配が急であると、前記盛土や裏込
めによる土圧によって地滑りなどが起こり易く、したが
って、前記擁壁の安定化を保つために勾配を緩くとって
施工する必要がある。しかし、このように緩勾配にする
と、その分だけ擁壁の上部または下部の用地面積を縮小
させることになり、用地の有効利用ができなかった。
Furthermore, if the retaining wall has a steep slope, landslides are likely to occur due to the earth pressure due to the embankment and backfilling. Therefore, it is necessary to construct the retaining wall with a gentle slope in order to keep the retaining wall stable. . However, such a gentle slope would reduce the site area above or below the retaining wall by that amount, and could not effectively use the site.

この発明は以上の欠点を解決するものであって、機械
化施工ができ、圧縮による不同沈下がなく、擁壁の勾配
を急にしても地滑りなどを生ずることがなく、そのため
擁壁上下の用地面積を広くとることのできるようにした
人工軽量土を用いた擁壁の施工方法を提供することを目
的とする。
This invention solves the above-mentioned drawbacks, can be mechanized, has no differential settlement due to compression, and does not cause landslides even if the slope of the retaining wall is steep. Therefore, the land area above and below the retaining wall is reduced. It is an object of the present invention to provide a method for constructing a retaining wall using an artificial lightweight soil that can be widely used.

《課題を解決するための手段》 前記目的を達成するため、この発明は、擁壁を構成す
る土砂として、砂質土や粘性土等の自然土やフライアッ
シュ、高炉スラグなどの産業副産物の単独もしくはこれ
らの混合物と、気泡を発生させる発泡剤もしくは起泡剤
を発泡させた気泡および固結剤とを混合撹拌した混合物
を用い、該混合物を既存用地の法面と型枠との間に順次
所定の高さで打設し固結させることを繰り返すことによ
って既存用地の法面に所定勾配の軽量土構造物を積層状
に構築するようにした。
<Means for Solving the Problems> In order to achieve the above-mentioned object, the present invention uses, as earth and sand constituting a retaining wall, natural soil such as sandy soil and cohesive soil, fly ash, and industrial by-products such as blast furnace slag. Alternatively, a mixture obtained by mixing and agitating a mixture of these mixtures with a foaming agent or a foaming agent for generating bubbles and a solidifying agent is used, and the mixture is sequentially placed between the slope of the existing site and the formwork. By repeatedly placing and solidifying at a predetermined height, a lightweight soil structure having a predetermined slope was constructed in a laminated manner on the slope of the existing site.

また、この発明では前記型枠はコンクリートなどで構
成された板状の本体と、この本体の背面側に設けられた
アンカー材とを備え、この型枠の背面に前記軽量土構造
物を積層状に構築し、前記アンカー材をこの軽量土構造
物中に埋設することで前記型枠を埋め殺し状態に一体化
することができる。
Further, in the present invention, the formwork includes a plate-shaped main body made of concrete or the like and an anchor material provided on the back side of the main body, and the lightweight earth structure is laminated on the backside of the formwork. Then, by embedding the anchor material in the lightweight earth structure, the form can be buried and integrated.

更にこの発明では、既存用地の法面を削りとって新た
な急勾配の擁壁を築造するようにもできる。
Further, in the present invention, the slope of the existing site can be shaved to construct a new steep retaining wall.

《作 用》 以上の構成によれば、既存用地と型枠の間に打設され
た軽量土混合物は固結し、人工軽量土構造物となる。ま
た、固結後はその上部に同様にして順次軽量土混合物が
打設され、これを繰返えすことにより擁壁が完成する。
<< Working >> According to the above configuration, the lightweight soil mixture placed between the existing site and the formwork is solidified into an artificial lightweight soil structure. In addition, after consolidation, the lightweight soil mixture is sequentially placed on the upper part in the same manner, and the retaining wall is completed by repeating this.

したがって、型枠に土圧などの負荷をかけず、また地
盤沈下などを生じない。
Therefore, no load such as earth pressure is applied to the formwork, and ground subsidence does not occur.

型枠としてコンクリート製のものを用いた場合には、
軽量土構造物は裏込め土砂としての機能と、擁壁の補強
としての機能を兼用する。
If you use concrete as the formwork,
The lightweight soil structure has both the function of backfilling sand and the function of reinforcing the retaining wall.

得られる擁壁は、軽量土混合物が軽量なので急勾配に
することができ、既存用地の法面の勾配との差に応じ
て、上部側用地面積、または下部側用地面積を拡幅でき
る。
The obtained retaining wall can be made steep because the lightweight soil mixture is lightweight, and the upper side land area or the lower side land area can be widened according to the difference from the slope of the slope of the existing land.

《実 施 例》 以下、この発明の一実施例を図面を用いて詳細に説明
する。
<< Example >> An example of the present invention will be described below in detail with reference to the drawings.

第1図、第2図はこの発明を既存盛土の高速道路の法
面に構築される擁壁の施工方法に適用した場合を示すも
のである。
1 and 2 show a case where the present invention is applied to a method of constructing a retaining wall constructed on the slope of an existing embankment expressway.

図において、上部が高速道路用地1aである既存盛土1
の下部地盤面Eには、既存盛土1の法面W1の勾配より急
勾配の型枠2が構築される。
In the figure, the existing embankment 1 whose upper part is the expressway site 1a
On the lower ground surface E of, the formwork 2 having a steeper slope than the slope of the slope W1 of the existing embankment 1 is constructed.

なお、第1図に示す法面W2は、型枠2を設置するため
に若干既存法面W1を掘削している。
As for the slope W2 shown in FIG. 1, the existing slope W1 is slightly excavated in order to install the mold 2.

型枠2は第2図(a),(b)に示すように、コンク
リートタイル状をなす所定寸法のユニットに形成され、
得ようとする擁壁3の表面を構成する平板状の型枠本体
2aを備えている。
As shown in FIGS. 2 (a) and 2 (b), the formwork 2 is formed into a concrete tile-shaped unit of a predetermined size,
A plate-shaped mold body that constitutes the surface of the retaining wall 3 to be obtained
It has 2a.

そして、この型枠本体2aの裏面側には、縦横に配置さ
れたアンカー材2bが設けられ、型枠2は、本体2aが所定
角度になるようにアンカー材2bによって立て掛け状態に
法面W2から所定の間隔を置いて設置される。
Anchor materials 2b arranged vertically and horizontally are provided on the back side of the mold body 2a, and the formwork 2 is leaned by the anchor material 2b from the slope W2 so that the body 2a is at a predetermined angle. It is installed at a predetermined interval.

次いで、型枠2の構築状態ではその下部地盤面Eに排
水用のフィルタFが敷設される。
Next, in the construction state of the formwork 2, a drainage filter F is laid on the lower ground surface E thereof.

以上の準備完了後、軽量土混合物Aを型枠2と既存盛
土1との隙間に打設し、固結させることによって人工軽
量土構造物6が両者間を一体に結合した状態で積層状に
構築される。
After the above preparation is completed, the lightweight soil mixture A is cast in the gap between the formwork 2 and the existing embankment 1 and solidified to form the artificial lightweight soil structure 6 in a laminated state in which both are integrally connected. Be built.

この場合、型枠2を定着させるために、その全高に相
当する軽量土混合物Aを一度に打設せず、適当な量を打
設した状態で一旦停止し、混合物Aがある程度固結した
後に残量を打設してもよい。
In this case, in order to fix the formwork 2, the lightweight soil mixture A corresponding to the entire height of the formwork 2 is not cast at one time, but is stopped once with an appropriate amount placed, and after the mixture A has solidified to some extent. The remaining amount may be set.

前記軽量土混合物Aは、第1図に示すように、既存盛
土1の上部用地1aの面に設置された製造プラントによっ
て製造され、順次打設される。
As shown in FIG. 1, the lightweight soil mixture A is manufactured by a manufacturing plant installed on the surface of the upper land 1a of the existing embankment 1 and sequentially placed.

この軽量土混合物Aは、土砂Bと、これに起泡剤、例
えば界面活性剤、動物性加水分解蛋白質を水に溶解した
水溶液Cを圧縮空気とともに発泡器7に供給して前記起
泡剤を発泡させた起泡Dと、固結剤E、例えばセメント
スラリーとを連続式のミキサー8に投入し、ミキサー8
でこれらを混合撹拌することで作製される。
This lightweight soil mixture A is prepared by supplying earth and sand B and a foaming agent, for example, an aqueous solution C in which a surfactant and an animal hydrolyzed protein are dissolved in water together with compressed air to a foaming machine 7 to generate the foaming agent. The foamed foam D and the solidifying agent E, such as cement slurry, are charged into a continuous mixer 8 and the mixer 8
It is prepared by mixing and stirring these.

作製された軽量土混合物Aは、ベルトコンベア9によ
って前記既存盛土1の法面W2と型枠2との間に打設さ
れ、その打設量がほぼ型枠2の天端に至った状態で打設
作業を停止する。打設された軽量土混合物Aは、固結剤
Eを含有しているので気泡Dを含んだ状態で固結し、固
結によって軽量土構造物6が型枠2の裏面に一体化した
状態で構築される。
The produced lightweight soil mixture A is placed between the slope W2 of the existing embankment 1 and the formwork 2 by the belt conveyor 9, and the amount of placement is almost at the top of the formwork 2. Stop the placing work. Since the poured lightweight soil mixture A contains the solidifying agent E, it is consolidated in a state of containing the bubbles D, and the lightweight soil structure 6 is integrated on the back surface of the form 2 by the consolidation. Built in.

この作業完了後に次の型枠2の構築作業が行われる。 After this work is completed, the next work of constructing the form 2 is performed.

この作業は、この実施例では次の段の型枠2を最下段
の型枠2上に連続かつ同一勾配となるように設置する方
法によって行なわれているが、上段側のものを下側より
も急傾斜にすることもできる。
In this embodiment, this work is carried out by a method of installing the formwork 2 of the next stage on the formwork 2 of the lowermost stage so as to be continuous and at the same gradient. Can also be steep.

この場合にあっても、軽量土構造物6の表面にフィル
タFを設置し、前記と同様に軽量土混合物Aを既存盛土
1と型枠2の間に打設し、固結することを繰り返す。
Even in this case, the filter F is installed on the surface of the lightweight soil structure 6, and the lightweight soil mixture A is placed between the existing embankment 1 and the form 2 and solidified as described above. .

最終段階では、最上部の型枠2の天端を、既存盛土1
の上部用地面1aと同一水平面となるように設け、フィル
タFを設置後、この型枠2と既存盛土1との隙間に軽量
土混合物Aを打設し、これを固結させることによって、
擁壁3の築造が完成する。
At the final stage, the top of the top formwork 2 is replaced with the existing embankment 1.
It is provided so as to be on the same horizontal plane as the upper ground 1a, and after the filter F is installed, the lightweight soil mixture A is placed in the gap between the formwork 2 and the existing embankment 1 and is solidified,
Construction of the retaining wall 3 is completed.

完成状態において、前記型枠本体2aは擁壁3の表面を
構成し、その背部のアンカー材2aは軽量土混合物A中に
埋設され、これにより型枠2は埋め殺し状態で前記軽量
土構造物6と一体化される。
In the completed state, the formwork main body 2a constitutes the surface of the retaining wall 3, and the anchor material 2a on the back side thereof is embedded in the lightweight soil mixture A, whereby the formwork 2 is buried and the lightweight soil structure is formed. It is integrated with 6.

そして、この実施例では擁壁3の完成状態では既存盛
土1と型枠2との勾配の差に応じた上部の高速道路用地
1aの拡幅Lを得られることになる。
Then, in this embodiment, in the completed state of the retaining wall 3, the upper expressway site corresponding to the difference in slope between the existing embankment 1 and the formwork 2
A widening width L of 1a can be obtained.

なお、図においては、型枠2を3段に積み重ねている
が、これは型枠2の大きさや重量、法面W2の高さ、およ
び軽量土混合物Aの固結までに型枠2に加わる側圧等に
よって定まる。
In the figure, the formwork 2 is stacked in three stages, but this is added to the formwork 2 by the size and weight of the formwork 2, the height of the slope W2, and the consolidation of the lightweight soil mixture A. Determined by lateral pressure etc.

また型枠2を一般に用いられる耐水合板等で構成して
もよく、この場合には施工完了後型枠2を撤去すれば、
軽量土構造物6の露出表面を擁壁3の表面とすることが
できる。
Further, the form 2 may be composed of a commonly used waterproof plywood or the like. In this case, if the form 2 is removed after the completion of construction,
The exposed surface of the lightweight earth structure 6 can be the surface of the retaining wall 3.

さらに、以上の軽量土混合物Aに使用できるのは、土
砂Bとして、現場で掘削された土砂のほか、他の場所か
ら運搬された砂質土や、粘性土等の自然土、或いはフラ
イアッシュ、高炉スラグなどの産業副産物を単独ないし
は混合して用いることができる。
Furthermore, the above lightweight soil mixture A can be used as the soil B, in addition to the soil excavated at the site, sandy soil transported from other places, natural soil such as cohesive soil, or fly ash, Industrial by-products such as blast furnace slag can be used alone or as a mixture.

さらにまた、気泡Dに替えて、無機質系の発泡剤、例
えばアルミニウム粉末や過酸化水素系の発泡剤も使用で
き、これらを用いる場合には発泡器7は必要とせず、発
泡剤を土砂Bと固結剤Eとに混合し撹拌するだけで軽量
土混合物Aを得るとこができる。
Furthermore, in place of the air bubbles D, an inorganic foaming agent such as aluminum powder or hydrogen peroxide foaming agent can be used. When these are used, the foaming device 7 is not required, and the foaming agent is earth and sand B. The lightweight soil mixture A can be obtained simply by mixing with the solidifying agent E and stirring.

更に、軽量化の促進と、コストダウンとを考えると人
工軽量土Aに多孔質の高炉急冷スラグ,高炉膨脹スラグ
等の軽量化剤を混入させることが推賞される。また更
に、軽量土Aの設計仕様に応じた圧縮強度,剪断強度の
確保は固結剤Eとしてのセメント,フライアッシュ,高
炉スラグ微粉末,石灰などを単独ないしは組合せて用い
ることができる。
Further, in consideration of promotion of weight reduction and cost reduction, it is recommended to mix artificial lightweight soil A with a lightening agent such as porous blast furnace rapidly cooled slag or blast furnace expanded slag. Furthermore, in order to secure the compressive strength and the shear strength according to the design specifications of the lightweight soil A, cement as the solidifying agent E, fly ash, blast furnace slag fine powder, lime or the like can be used alone or in combination.

透水性が必要な場合には、固結剤Eの単位水量を減ず
ればよい。
When water permeability is required, the unit water content of the solidifying agent E may be reduced.

また、前記実施例では施工現場において軽量土混合物
を作製したが、予め製造し、混合撹拌しながらダンプカ
ー等で打設現場まで搬送するようにしてもよい。
Further, although the lightweight soil mixture was prepared at the construction site in the above-mentioned embodiment, it may be manufactured in advance and conveyed to the construction site by a dump truck while mixing and stirring.

第3図はこの発明の第二実施例を示すものである。 FIG. 3 shows a second embodiment of the present invention.

図における実施例は、既存用地20の想像線で示す法面
Wを削土して新たな急勾配の法面W′とし、この法面
W′に沿って平行して前記第一実施例と同様に型枠2の
構築と軽量土混合物Aの積層状の打設作業を交互に繰り
返すことによって、型枠2の裏面に軽量土構造物6が一
体化した擁壁21の築造を完成するようにしている。
In the embodiment shown in the drawing, the slope W shown by the imaginary line of the existing site 20 is ground to form a new steep slope W ', and along the slope W'parallel to the first embodiment. Similarly, by alternately repeating the construction of the formwork 2 and the work of placing the lightweight soil mixture A in a laminated form, the construction of the retaining wall 21 in which the lightweight soil structure 6 is integrated on the back surface of the formwork 2 is completed. I have to.

この実施例では勾配差に応じて、既存用地20が幅L1だ
け拡幅されるとともに、下部側用地20aも幅L2だけ拡幅
される。
In this embodiment, the existing site 20 is expanded by the width L1 and the lower site 20a is expanded by the width L2 in accordance with the gradient difference.

第4図はこの発明の第三実施例を示すものである。 FIG. 4 shows a third embodiment of the present invention.

この実施例では、既存盛土30の下部側にこれの法面W
よりも急勾配のコンクリート製擁壁本体31を構築し、そ
の裏面に軽量土混合物Aを順次積層状に打設することで
擁壁本体31と軽量土構造物6とが一体化した擁壁32の築
造を完成するようにしている。この実施例でも前記第一
実施例と同様上部側用地30aを拡幅できる。
In this embodiment, the slope W of the existing embankment 30 is located on the lower side of the embankment 30.
Retaining wall 32 in which the retaining wall body 31 and the lightweight earth structure 6 are integrated by constructing a concrete retaining wall body 31 having a steeper slope than that and placing the lightweight soil mixture A on the back surface thereof in a layered order. I am trying to complete the construction of. In this embodiment as well, the upper site 30a can be widened as in the first embodiment.

《発明の効果》 以上実施例によって詳細に説明したように、この発明
による人工軽量土を用いた擁壁の施工方法にあっては、
打設された軽量土混合物が固結した後、同様にして順次
打設されるので、従来の石積み工法と異なり、機械化施
工が可能であり、工期も短縮する。また、構築された擁
壁は勾配が急であっても、自己崩壊することがなく、擁
壁の勾配と既存用地の法面の勾配との差に応じて、上部
側用地面積、または下部側用地面積を拡幅できる。
<< Effects of the Invention >> As described in detail with reference to the above examples, in the construction method of the retaining wall using the artificial lightweight soil according to the present invention,
Unlike the conventional masonry method, mechanized construction is possible and the construction period is shortened, because the placed lightweight soil mixture is solidified and then sequentially placed in the same manner. In addition, the constructed retaining wall does not collapse on its own even if the slope is steep, and depending on the difference between the retaining wall slope and the slope of the existing site, the upper side land area or the lower side The land area can be expanded.

構築された人工軽量土構造物は、軽量であり、順次固
化するため型枠に土圧などの負荷をかけず、また打設後
地盤沈下を生じない。
The constructed artificial lightweight soil structure is lightweight and does not apply a load such as earth pressure to the formwork because it solidifies sequentially, and does not cause ground subsidence after placement.

型枠としてコンクリート擁壁を用いた場合には、裏込
め土砂としての機能と、擁壁の補強としての機能を兼用
する。
When a concrete retaining wall is used as the formwork, it has both the function of backfilling earth and sand and the function of reinforcing the retaining wall.

【図面の簡単な説明】[Brief description of drawings]

第1図はこの発明の第一実施例を示す断面説明図、第2
図(a),(b)は同実施例に用いるコンクリート製型
枠の説明図、第3図はこの発明の第二実施例を示す断面
説明図、第4図はこの発明の第三実施例を示す断面説明
図である。 A……軽量土混合物、B……土砂 C……水溶液、D……気泡 E……固結剤 1,20,30……既存盛土(既存用地) 1a……高速道路用地(上部側用地) 2……型枠 3,21,32……擁壁 6……人工軽量土構造物 20a……下部側用地 30a……上部側用地 31……擁壁本体 W,W′……法面
FIG. 1 is a sectional explanatory view showing a first embodiment of the present invention, and FIG.
(A) and (b) are explanatory views of a concrete formwork used in the same embodiment, FIG. 3 is a sectional explanatory view showing a second embodiment of the present invention, and FIG. 4 is a third embodiment of the present invention. It is sectional explanatory drawing which shows. A: Lightweight soil mixture, B: Sediment C: Aqueous solution, D: Air bubbles E: Solidifying agent 1,20,30 ... Existing embankment (existing site) 1a ... Expressway site (upper site) 2 …… Formwork 3,21,32 …… Retaining wall 6 …… Artificial lightweight earth structure 20a …… Lower side site 30a …… Upper side site 31 …… Retaining wall body W, W ′ …… Slope

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】擁壁を構成する土砂として、砂質土や粘性
土等の自然土やフライアッシュ、高炉スラグなどの産業
副産物の単独もしくはこれらの混合物と、気泡を発生さ
せる発泡剤もしくは起泡剤を発泡させた起泡および固結
剤とを混合撹拌した混合物を用い、該混合物を既存用地
の法面と型枠との間に順次所定の高さで打設し固結させ
ることを繰り返すことによって既存用地の法面に所定勾
配の軽量土構造物を積層状に構築することを特徴とする
人工軽量土を用いた擁壁の施工方法。
1. As earth and sand constituting a retaining wall, natural soil such as sandy soil and cohesive soil, and industrial by-products such as fly ash and blast furnace slag, or a mixture thereof, and a foaming agent or foaming agent for generating bubbles. Using a mixture obtained by mixing and stirring a foaming agent and a solidifying agent, the mixture is repeatedly placed and fixed at a predetermined height between the slope of the existing site and the formwork to repeat the solidification. By doing so, a method for constructing a retaining wall using artificial lightweight soil is characterized in that a lightweight soil structure with a predetermined slope is constructed in layers on the slope of the existing site.
【請求項2】前記型枠はコンクリートなどで構成された
板状の本体と、この本体の背面側に設けられたアンカー
材とを備え、この型枠の背面に前記軽量土構造物を積層
状に構築し、前記アンカー材をこの軽量土構造物中に埋
設することで前記型枠を埋め殺し状態に一体化すること
を特徴とする請求項1に記載の人工軽量土を用いた擁壁
の施工方法。
2. The formwork comprises a plate-shaped main body made of concrete or the like, and an anchor material provided on the back side of the main body, and the lightweight earth structure is laminated on the backside of the formwork. 2. The retaining wall using artificial lightweight soil according to claim 1, characterized in that the formwork is buried and integrated by burying the anchor material in the lightweight soil structure. Construction method.
【請求項3】前記既存用地の法面を削りとって新たな急
勾配の擁壁を築造するようにしたことを特徴とする請求
項1または2に記載の人工軽量土を用いた擁壁の施工方
法。
3. The retaining wall using artificial lightweight soil according to claim 1 or 2, wherein the slope of the existing site is shaved to construct a new steep retaining wall. Construction method.
JP63254827A 1988-10-12 1988-10-12 Retaining wall construction method using artificial lightweight soil Expired - Lifetime JPH083183B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63254827A JPH083183B2 (en) 1988-10-12 1988-10-12 Retaining wall construction method using artificial lightweight soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63254827A JPH083183B2 (en) 1988-10-12 1988-10-12 Retaining wall construction method using artificial lightweight soil

Publications (2)

Publication Number Publication Date
JPH02104823A JPH02104823A (en) 1990-04-17
JPH083183B2 true JPH083183B2 (en) 1996-01-17

Family

ID=17270413

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63254827A Expired - Lifetime JPH083183B2 (en) 1988-10-12 1988-10-12 Retaining wall construction method using artificial lightweight soil

Country Status (1)

Country Link
JP (1) JPH083183B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02269228A (en) * 1989-04-07 1990-11-02 Kazuo Fujimura Structure for retaining wall and construction method for retaining wall
JP2612412B2 (en) * 1993-09-20 1997-05-21 強化土エンジニヤリング株式会社 Reinforced soil structure
JP2665323B2 (en) * 1995-04-21 1997-10-22 卓生 行本 Self-supporting sabo lock form method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59187923A (en) * 1983-04-11 1984-10-25 Furii Kogyo Kk Construction of retaining wall
JPH0721136B2 (en) * 1984-09-04 1995-03-08 株式会社シモダ技術研究所 Grout
JPS6168934A (en) * 1984-09-10 1986-04-09 Tadamichi Ao Sheathing work
JPS62148353A (en) * 1985-12-23 1987-07-02 東京電力株式会社 Back injecting material for shield
JPS6344025A (en) * 1986-08-12 1988-02-25 Keihan Concrete Kogyo Kk Foamed block back-filling material for foamed block structure

Also Published As

Publication number Publication date
JPH02104823A (en) 1990-04-17

Similar Documents

Publication Publication Date Title
JP3452330B2 (en) Solidified material mixed with crushed stone powder and construction method using solidified material mixed with crushed stone powder
CN107859062B (en) The earth-filling method of underground pipe gallery
JPH083183B2 (en) Retaining wall construction method using artificial lightweight soil
JPH02263890A (en) Quick ground-preventing method and soil-coagulant
JPH01163309A (en) Artificial light-weight soil
JPH09158158A (en) Filling concrete dam and its construction method
JPH0528285B2 (en)
EP0541998A1 (en) Refilling material and refilling method
JP3007940B2 (en) Lightweight ground to be cast on soft ground and construction method thereof
JP2802815B2 (en) Embankment structure
JP3099040B2 (en) Embankment culvert
JPH0960012A (en) Water-permeable temporary earth retaining member and method for constructing concrete wall using the same
JP3177723B2 (en) Embankment method
JP3099039B2 (en) Embankment culvert
JPH11303060A (en) Prevention of settlement of soil floor
JPH01142117A (en) Light-weight banking work
JPH1193174A (en) Concrete slope, vegetation slope, and construction method
JPH03191115A (en) Method of backfilling ground
JP3545641B2 (en) Backfill method
JPH06146307A (en) Construction method of construction structure
JP2797144B2 (en) Side hole embedding method
JP2001049994A (en) Tunnel backfill method using surplus soil
JPH04149309A (en) Lightweight banking and constructing method thereof
CN116240765A (en) Construction Method of Foam Concrete Subgrade of Expressway
JP3037169U (en) Concrete block