Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0833030B2 - Construction method - Google Patents
[go: Go Back, main page]

JPH0833030B2 - Construction method - Google Patents

Construction method

Info

Publication number
JPH0833030B2
JPH0833030B2 JP1112152A JP11215289A JPH0833030B2 JP H0833030 B2 JPH0833030 B2 JP H0833030B2 JP 1112152 A JP1112152 A JP 1112152A JP 11215289 A JP11215289 A JP 11215289A JP H0833030 B2 JPH0833030 B2 JP H0833030B2
Authority
JP
Japan
Prior art keywords
main
construction
main building
building
constructed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1112152A
Other languages
Japanese (ja)
Other versions
JPH02292433A (en
Inventor
宮崎  淳
康洋 江口
英武 谷口
一重 小林
洋光 嘉藤
高橋  元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP1112152A priority Critical patent/JPH0833030B2/en
Publication of JPH02292433A publication Critical patent/JPH02292433A/en
Publication of JPH0833030B2 publication Critical patent/JPH0833030B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 《産業上の利用分野》 この発明は、下層の主構築部分上で構築した上層とな
る主構築部分をリフトアップして所定高さ位置に固定す
ることを、ロボット等を備えた構築用プラントにより繰
り返し行い、それによって所望する高さの建築物を構築
するような建設方法に関する。
DETAILED DESCRIPTION OF THE INVENTION << Industrial Application Field >> The present invention relates to lifting a main building portion as an upper layer constructed on a main building portion of a lower layer and fixing it to a predetermined height position by a robot or the like. The present invention relates to a construction method in which a building having a desired height is repetitively performed by a construction plant equipped with.

《従来の技術》 一般に、中高層ビルなど各種の建築物の建設は、最上
階まで柱を構築した後、地上で組立てたスラブ等をウイ
ンチで順次引き上げて取付けていく方法、あるいはクレ
ーン等で躯体部材を持ち上げ、下層階から上層階まで1
階分毎に構築して積上げていく方法などにより行なわれ
ている。
《Prior art》 Generally, construction of various buildings such as middle- and high-rise buildings is performed by constructing pillars up to the top floor and then sequentially pulling up and installing slabs assembled on the ground with winches, or using frame members such as cranes. Lift, 1 from lower floor to upper floor
This is done by a method of building and stacking each floor.

また、最近では、例えば特公昭52−26044号公報など
に開示されているように、地上レベルで一階分の建物躯
体を集中的に生産し、一階分の躯体工事を完了した後、
ジャッキ等によりリフトアップして所定高さ位置に固定
する作業を繰り返し行って建物全体を構築するといった
方法も提案されており、工期の短縮と工費のコストダウ
ンを図っている。なお、上記公報開示の工法では、建築
物の両側端となる位置に階段室を予め構築すると共に、
それら階段室の最上部間に梁組を架設し、その梁組によ
りリフトアップ用のジャッキ等を支持している。
In addition, recently, for example, as disclosed in Japanese Patent Publication No. 52-26044, after intensively producing a building skeleton for the first floor at the ground level, after completing the skeleton construction for the first floor,
A method of constructing the entire building by repeatedly lifting up with a jack or the like and fixing it at a predetermined height position has also been proposed, aiming to shorten the construction period and reduce the construction cost. Incidentally, in the construction method disclosed in the above publication, a staircase is constructed in advance at positions that are on both sides of the building,
A beam assembly is installed between the tops of the staircases, and the beam assembly supports jacks for lifting.

《発明が解決しようとする課題》 しかしながら、前述したような従来の工法では、ウイ
ンチあるいはクレーンによりスラブや躯体部材の引き上
げを行ない、構築作業を進めていくため、作業者の熟練
と多数の人手を要し、機械力によるシステム的な建築物
の構築が困難であり、自動化率および工期短縮等の生産
性の向上を図り難いという問題があった。
<Problems to be solved by the invention> However, in the conventional construction method as described above, since the slab and the frame member are pulled up by the winch or the crane and the construction work is advanced, the skill of the worker and a large number of manpower are required. In other words, it is difficult to construct a systematic building by mechanical force, and there is a problem that it is difficult to improve productivity such as automation rate and shortening of construction period.

その点、前述の公報に開示されたような技術では、地
上レベルで建物躯体を集中的に生産することから施工は
専ら地上作業となり、作業用ロボット等の機械力を容易
に導入でき、上述のような問題をある程度は解消できる
ものの、梁組の支持塔となる階段室を先ず所望高さに構
築する必要があり、他の各工程と並行に作業を進めるこ
とができないため、工期の短縮には限界があった。
In that respect, in the technology disclosed in the above-mentioned publication, since the building skeleton is intensively produced at the ground level, the construction is exclusively ground work, and the mechanical force of the work robot or the like can be easily introduced. Although such problems can be solved to some extent, it is necessary to first construct the staircase that will be the support tower of the beam assembly at the desired height, and it is not possible to work in parallel with other processes, so the construction period can be shortened. There was a limit.

また、建設中は建物躯体を階段室により支持しなけれ
ばならず、その階段室の強度等からして建築物の高さに
限界があり、超高層な建築物には適用できないという問
題もあった。そこで、階段室を大型化してその強度を上
げれば、その分建築物を高くできるが、階段室部分がむ
やみと大きくなると共に、予め階段室を構築するために
費やされる工期が長びき、コストアップを招くなど不都
合があった。
In addition, the building frame must be supported by the staircase during construction, and the height of the building is limited due to the strength of the staircase, etc., which is not applicable to super high-rise buildings. It was Therefore, if you increase the size of the staircase and increase its strength, the building can be made higher by that amount, but the staircase part will become unnecessarily large and the construction period required to build the staircase in advance will increase and the cost will increase. There was a problem such as inviting.

この発明は、上述のような背景に鑑みてなされたもの
であり、人手による作業を不要にできると共に、工期短
縮等の生産性の向上を図れ、特に超高層の建築物を建設
する際に好ましく適用できる建築方法の提供をその目的
とする。
The present invention has been made in view of the background as described above, and it is possible to eliminate the need for manual work, improve productivity such as shortening the construction period, and particularly preferable when constructing a super high-rise building. The purpose is to provide applicable construction methods.

《課題を解決するための手段及び作用》 本発明は、複数の主柱を所定高さで構築し、これらの
主柱間に掛け渡され該主柱に沿って昇降可能な最上階主
構築部分を構築し、この最上階主構築部分を複数階数分
リフトアップし、該最上階主構築部分に設けられた構築
用プラントにより前記主柱間に最下主構築部分を固定的
に構築し、その後、前記最上階主構築部分の建築用プラ
ントにより該最上階主構築部分の直下に位置する主構築
部分上にて主柱間に新たな主構築部分を構築するととも
に、該最上階主構築部分及び新たな主構築部分を複数階
数分リフトアップして該新たな主構築部分を所定位置に
固定する工程を繰り返し、前記主柱の構築を前記最上階
主構築部分のリフトアップ位置まで該リフトアップに先
行して行うことを特徴とする。
<< Means and Actions for Solving the Problem >> The present invention constructs a plurality of main pillars at a predetermined height, and the uppermost floor main building portion that is hung between these main pillars and can be moved up and down along the main pillars. , The top main building part is lifted up by a plurality of floors, and the bottom main building part is fixedly constructed between the main columns by a building plant provided in the top main building part, and then , Constructing a new main building part between the main pillars on the main building part located directly below the top floor main building part by the building plant of the top floor main building part, and the top floor main building part and Repeat the process of lifting up the new main building portion for a plurality of floors and fixing the new main building portion in a predetermined position to build up the main pillar to the lift-up position of the top floor main building portion. It is characterized in that it is done in advance.

以上のような方法によれば、最上階主構築部分に備え
た構築用プラントにより最下階主構築部分を構築すると
共に、その後、“リフトアップした最上階主構築部分直
下に位置する既に構築した主構築部分の上で、その上方
に配置されるべき新たな主構築部分を構築し、その構築
した主構築部分を最上階主構築部分下方の所定高さ位置
にリフトアップさせて主柱群に固定するという作業を繰
り返す”ことで、上昇される最上階主構築部分と最下階
主構築部分との間に複数の主構築部分を順次高さ方向へ
積み上げて建築物を構築することとなるので、主構築部
分の構築作業と、その構築作業の基台ともなる既に構築
の完了した主構築部分のリフトアップ作業とを並行に進
めることができる。これにより、工期を格段に短縮で
き、生産性を向上できる。
According to the method as described above, the bottom floor main construction portion is constructed by the construction plant provided in the top floor main construction portion, and thereafter, the “lifted up top floor main construction portion is located immediately below and already constructed. On top of the main building section, build a new main building section to be placed above it, and lift up the built main building section to a predetermined height below the top floor main building section to form a main pillar group. By repeating the "fixing work", a plurality of main building parts are sequentially stacked in the height direction between the elevated top building part and the bottom floor building part to build a building. Therefore, the construction work of the main construction portion and the lift-up work of the main construction portion which has already been constructed and serves as the base of the construction work can be carried out in parallel. This can significantly reduce the construction period and improve productivity.

また、最上階主構築部分を、建築物の骨組となる主柱
群に掛け渡して支持させつつ構築作業を実施するので、
十分な支持強度を得ることができ、超高層の建築物の建
設にも好ましく適用することができる。
In addition, since the top floor main construction part is hung on and supported by the main pillar group that is the framework of the building,
Sufficient supporting strength can be obtained, and it can be preferably applied to the construction of super high-rise buildings.

更に、これら主柱群の構築は、最上階主構築部分のリ
フトアップ高さよりも若干先行させれば良く、従って前
述の各種構築作業等と並行させてこれら主柱群の構築作
業を進めることができ、より一層の工期短縮を達成でき
る。
Further, the construction of these main pillar groups may be carried out slightly ahead of the lift-up height of the main building portion of the top floor, so that the construction work of these main pillar groups can proceed in parallel with the above-mentioned various construction work and the like. It is possible to further shorten the construction period.

また本発明は、上記建設方法に関し、前記最上階主構
築部分のリフトアップ、該最上階主構築部分及び最下主
構築部分以外の主構築部分の構築、または前記主柱の構
築と並行して、高さ方向に隣接する二つの主構築部分間
に複数の副柱を立設するとともに、該二つの主構築部分
のうち下方に位置する主構築部分上で該副柱に沿って昇
降可能な副梁躯体を構築し、該副梁躯体をリフトアップ
して該二つの主構築部分間における最上階階位置に固定
し、その後、新たな副梁躯体を構築してこれをリフトア
ップして前記最上階階位置より順に下階となる位置に固
定する工程を繰り返すことを特徴とする。
Further, the present invention relates to the above-mentioned construction method, in parallel with lift-up of the top floor main building portion, construction of a main construction portion other than the top floor main building portion and bottom floor main building portion, or construction of the main pillar. , A plurality of sub pillars are erected between two main building portions adjacent to each other in the height direction, and can be moved up and down along the sub pillars on the lower main building portion of the two main building portions. Build a sub-beam structure, lift up the sub-beam structure and fix it to the uppermost floor position between the two main building parts, and then build a new sub-beam structure and lift it up. It is characterized in that the step of fixing the uppermost floor position to the lower floor position is repeated.

このように、上下の主構築部分間において進められる
副構築部分の構築に関しては、副柱群を構築した後にお
いて、副梁躯体の構築とそのリフトアップとの繰り返し
作業は、下方の主構築部分を基台として進められるの
で、これも他の各種構築作業等と並行して構築作業を進
めることができ、このような副構築部分を含む建築物に
あっても、その工期を著しく短縮することができる。
In this way, regarding the construction of the sub-construction part that is advanced between the upper and lower main construction parts, after the construction of the sub-column group, the construction work of the sub-beam skeleton and its lift-up work are repeated in the lower main construction part. The construction work can be carried out in parallel with other various construction work, etc., and the construction period can be significantly shortened even for buildings including such sub-construction parts. You can

《実施例》 以下、この発明の実施例を添付図面を参照しながら説
明する。
<< Embodiment >> An embodiment of the present invention will be described below with reference to the accompanying drawings.

第1図は、本発明の好適な一実施例を適用して建設を
進めている建築物の概略的な斜視図である。
FIG. 1 is a schematic perspective view of a building under construction by applying a preferred embodiment of the present invention.

本発明は基本的には、骨組を構成し最上階に達する主
柱30群と、これら主柱30に互いに高さ方向に間隔を隔て
て架設される複数の主構築部分14,40とから成る建築物1
0を建設するに際して、主構築部分40の構築よりも先行
させて主柱30群を高さ方向に順次構築しつつこれら主柱
30の構築過程において、建築物10の最下部位置で主柱30
群に昇降自在に掛け渡して構築用プラント2を備える最
上階主構築部分14を構築し、最上階主構築部分14の構築
用プラント2により主柱30間に最下階主構築部分を構築
し、その後最上階主構築部分14のリフトアップ作業、リ
フトアップ後の最上階主構築部分14直下の主構築部分40
上での構築用プラント2による直下の主構築部分40直上
に間隔を隔てて配置されるべき主構築部分40の構築作
業、構築された主構築部分40のリフトアップ作業並びに
主構築部分40の主柱30群への固定作業を順次繰り返して
行なうことによって、上昇される最上階主構築部分14と
最下階主構築部分との間に複数の主構築部分40を順次高
さ方向へ積み上げて建築物10を構築するようになってい
る。
The present invention is basically composed of a group of main columns 30 forming a frame and reaching the uppermost floor, and a plurality of main building portions 14 and 40 installed on these main columns 30 at intervals in the height direction. Building 1
In constructing 0, the main columns 30 group are sequentially constructed in the height direction prior to the construction of the main construction part 40, and these main columns are constructed.
In the construction process of 30, the main pillar 30 is at the lowest position of the building 10.
The top floor main building portion 14 including the construction plant 2 is constructed by vertically moving over the group, and the bottom floor main building portion is constructed between the main pillars 30 by the construction plant 2 of the top floor main building portion 14. After that, lift-up work of the main building part 14 on the top floor, the main building part 14 immediately below the main building part 14 on the top floor after lift-up
The construction work of the main construction part 40 which should be spaced apart immediately above the main construction part 40 just below by the construction plant 2 above, the lift-up work of the constructed main construction part 40 and the main construction part 40 By repeating the fixing work to the group of 30 pillars in sequence, a plurality of main building parts 40 are sequentially stacked in the height direction between the top building 14 and the bottom building It is designed to build Object 10.

また、主柱30に互いに高さ方向に間隔を隔てて架設さ
れる複数の主構築部分14,40の間に副構築部分18を構築
して建築物10を建設するに際して、最上階主構築部分14
のリフトアップ後の最上階主構築部分14直下の主構築部
分40上での構築用プラント2による直下の主構築部分40
直上に間隔を隔てて配置されるべき主構築部分40の構築
作業に次ぐ、構築された主構築部分40のリフトアップ作
業並びに主構築部分40の主柱30群への固定作業におい
て、上下の主構築部分40間に副柱12群を立設すると共に
下方の主構築部分40上で副梁躯体13を構築して、副梁躯
体13のリフトアップ作業及び副梁躯体13の副柱12群への
固定作業を順次繰り返して行なうことによって、上下の
主構築部分40間に複数の副梁躯体13を順次高さ方向へ積
み上げて副構築部分18を構築しつつ建築物10を構築する
ようになっている。
In addition, when constructing the building 10 by constructing the sub-construction portion 18 between the plurality of main construction portions 14 and 40 that are erected on the main pillar 30 at intervals in the height direction, the top floor main construction portion 14
Main building part 14 directly below the top floor after lift-up of the main building part 40 directly below the main building part 40 directly below the building plant 2 for construction
Following the construction work of the main construction part 40, which should be arranged directly above and with a space, in the lift-up work of the constructed main construction part 40 and the fixing work of the main construction part 40 to the main pillar 30 group, the upper and lower main Sub-column 12 groups are erected between the building portions 40, and the sub-beam body 13 is built on the main building portion 40 below, and the lift-up work of the sub-beam body 13 and the sub-column 12 groups of the sub-beam body 13 are performed. By sequentially repeating the fixing work of 1, the plurality of sub-beam skeletons 13 are sequentially stacked between the upper and lower main building portions 40 in the height direction to build the sub-building portion 18 and construct the building 10. ing.

この建築物10は主柱となる円筒形状のエレベータ室30
が複数構築されると共に、それらエレベータ室30に沿っ
て所定高さ毎に大梁11でなる主構築部分14,40が構築さ
れる。そして、大梁11による所定高さ毎の上下の主構築
部分14,40間に、副柱12および副梁躯体13により各副構
築部分18が構成される。
This building 10 has a cylindrical elevator room 30 that serves as the main pillar.
A plurality of are constructed, and main construction parts 14 and 40 composed of the girders 11 are constructed at predetermined heights along the elevator room 30. Further, the sub-columns 12 and the sub-beam skeleton 13 constitute each sub-construction portion 18 between the upper and lower main construction portions 14 and 40 of the large beam 11 at predetermined heights.

各エレベータ室30は、建築物10の最上階にまで延びて
構築され、その内部には略半円形状のエレベータ31が昇
降自在に設けられる。そして、このエレベータ室30の構
築は、上端に仮設した構造物構築プラント1により行な
われる。
Each elevator room 30 is constructed to extend to the uppermost floor of the building 10, and a substantially semicircular elevator 31 is provided inside the elevator room 30 so as to be able to move up and down. Then, the construction of the elevator room 30 is performed by the structure construction plant 1 temporarily installed at the upper end.

構造物構築プラント1は、集中制御された各種の作業
用ロボットを装備しており、エレベータ31で荷揚げされ
た部材の取付け,溶接,検査,塗装などを一貫して行な
うと共に、作業進行に伴い順次上昇されてエレベータ室
30の構築を行なう。
The structure construction plant 1 is equipped with various kinds of work robots that are centrally controlled, and consistently performs mounting, welding, inspection, painting, etc. of members unloaded by the elevator 31, and sequentially as work progresses. Lifted elevator room
Build 30.

この構造物構築プラント1は詳しくは、構築すべき構
造物(エレベータ室)30の上方に配設されその下方の構
造物30との間に施工作業空間50が形成される仮設の枠組
51と、枠組51に設けられこれより下方に伸長されて仮設
柱を成し構造物30との間に施工作業空間50を形成すると
共に収縮されて構造物30との間に本設部材52の装着スペ
ース53を形成する伸縮柱54群と、枠組51に設けられ装着
スペース53に本設部材52を装着する部材設置手段55とを
備えている。また、枠組51には、施工作業空間50を覆う
仮設覆い56を設けてある。
More specifically, the structure construction plant 1 is a temporary framework in which a construction work space 50 is formed above the structure (elevator room) 30 to be constructed and between the structure 30 below the structure 30.
51 and the frame 51, which is extended downward to form a temporary column and forms a construction work space 50 between the structure 30 and the structure 30, and is contracted between the structure 30 and the main member 52. It includes a group of telescopic columns 54 forming a mounting space 53, and member setting means 55 provided in the frame 51 for mounting the main member 52 in the mounting space 53. Further, the framework 51 is provided with a temporary cover 56 that covers the construction work space 50.

本発明では、まず複数個所のエレベータ室30の構築
を、各々に仮設した構造物構築プラント1により先行し
て進めると共に、それらエレベータ室30間に大梁11を渡
架して当該建築物10の最上階を構成する最上階主構築部
分14を昇降自在に構築する。なお、各エレベータ室30の
外壁には、油圧力によるクライミング装置15が装着され
ており、それらクライミング装置15により最上階主構築
部分14が昇降される。また、この最上階となる主構築部
分14には、搬送ロボット16や溶接ロボット17などの各種
作業用ロボットが組込まれ、構築用プラント2が構成さ
れている。
In the present invention, first, the construction of the elevator rooms 30 at a plurality of locations is preceded by the structure construction plant 1 that is temporarily installed in each of them, and at the same time, the girders 11 are bridged between the elevator rooms 30 so that the top of the building 10 is The top floor main building portion 14 that constitutes the floor is constructed so that it can be moved up and down. A climbing device 15 by hydraulic pressure is mounted on the outer wall of each elevator room 30, and the climbing device 15 raises and lowers the top floor main building portion 14. Further, various work robots such as a transfer robot 16 and a welding robot 17 are incorporated in the main building portion 14 which is the uppermost floor to configure the building plant 2.

次に、構築用プラント2により、まず最下階の主構築
部分(図示せず)を構築する。その後、最上階となる主
構築部分14を構築用プラント2と共に上昇させて直下の
主構築部分40(最下階主構築部分を含む)を基台とする
主構築部分構築用の作業空間41を形成し、その空間41
に、つまり構築用プラント2直下となる主構築部分40上
面に、それの直上に位置すべき大梁11等から成る主構築
部分40aを構築する。そして、最上階主構築部分14を上
昇させつつこの構築用プラント2による主構築部分40の
構築作業を繰り返すと共に、構築の完了した主構築部分
40を順次クライミング装置15によりリフトアップさせて
各々所定高さ位置でエレベータ室30に固定する。このと
き、そのリフトアップに伴い構築作業中の構築用プラン
ト2も同時に上昇されるので、その構築作業に支障をき
たすことはない。
Next, the construction plant 2 first constructs the main construction portion (not shown) at the bottom floor. After that, the main building portion 14, which is the top floor, is raised together with the building plant 2, and a working space 41 for building the main building portion based on the main building portion 40 (including the lowest floor main building portion) immediately below is formed. Form and space 41
That is, that is, on the upper surface of the main building portion 40 directly below the building plant 2, the main building portion 40a composed of the girders 11 and the like to be located immediately above it is constructed. Then, the construction work of the main construction portion 40 by the construction plant 2 is repeated while raising the top floor main construction portion 14, and the construction of the main construction portion completed is completed.
40 are sequentially lifted up by the climbing device 15 and fixed to the elevator room 30 at predetermined height positions. At this time, the construction plant 2 during the construction work is also raised simultaneously with the lift-up, so that the construction work is not hindered.

なお、上述の主構築部分40の構築作業においても、大
梁11などの各部材はエレベータ31により荷揚げされ、空
間41に取り込まれる。
In the construction work of the main construction portion 40 described above, each member such as the girder 11 is unloaded by the elevator 31 and taken into the space 41.

すなわち、本発明は、最上階となる主構築部分14の構
築用プラント2により下層となる主構築部分40を構築
し、構築したその主構築部分40をリフトアップさせて所
定高さ位置に固定するという作業を繰り返すものであ
り、これにより所望する高さに建築物10を建設できる。
このとき、構築の完了した主構築部分40上で直上に位置
すべき主構築部分40aを順次構築することとなるので、
主構築部分40aの構築作業と、その構築作業の基台とも
なる既に構築の完了した主構築部分40のリフトアップ作
業とを並行に進めることができる。これにより、工期を
格段に短縮でき、生産性を向上できる。また、最上階主
構築部分14を、建築物10の骨組となるエレベータ室30に
掛け渡して支持させつつ構築作業を実施するので、十分
な支持強度を得ることができ、超高層の建築物の建設に
も好ましく適用することができる。更に、これらエレベ
ータ室30の構築は、最上階主構築部分14のリフトアップ
高さよりも若干先行させれば良く、従って前述の各種構
築作業等と並行させてこれらエレベータ室30の構築作業
を進めることができ、より一層の工期短縮を達成でき
る。
That is, according to the present invention, the main building portion 40 which is the lower layer is constructed by the construction plant 2 of the main building portion 14 which is the uppermost floor, and the constructed main building portion 40 is lifted up and fixed at a predetermined height position. The above work is repeated, and thus the building 10 can be constructed at a desired height.
At this time, since the main building portion 40a that should be located immediately above the main building portion 40 that has been built will be built sequentially,
The construction work of the main construction part 40a and the lift-up work of the already constructed main construction part 40, which also serves as the base of the construction work, can be carried out in parallel. This can significantly reduce the construction period and improve productivity. Further, since the construction work is performed while the top floor main building portion 14 is hung over and supported by the elevator room 30 which is the frame of the building 10, it is possible to obtain sufficient supporting strength and to construct a super high-rise building. It can also be preferably applied to construction. Further, the construction of these elevator rooms 30 may be made slightly ahead of the lift-up height of the top floor main building portion 14, and therefore the construction work of these elevator rooms 30 should be carried out in parallel with the above-mentioned various construction work and the like. Therefore, the construction period can be further shortened.

また本発明では、主構築部分40をリフトアップした
際、先ず上下の主構築部分40間に副柱12群を構築し、そ
の後副梁躯体13の構築とそのリフトアップとを複数回繰
り返して副構築部分18を構築するようになっており、こ
の作業は、下方の主構築部分40を基台として進められる
ので、これも他の各種構築作業等と並行して構築作業を
進めることができ、このような副構築部分18を含む建築
物10にあっても、その工期を著しく短縮することができ
る。
Further, in the present invention, when the main building portion 40 is lifted up, first, the sub-column 12 group is constructed between the upper and lower main building portions 40, and then the construction of the sub-beam frame 13 and its lift-up are repeated a plurality of times to make the sub-columns. It is designed to build the building part 18, and this work can be carried out based on the main building part 40 below, so that this can also be carried out in parallel with other various building works, etc. Even in the building 10 including such a sub-construction portion 18, the construction period can be significantly shortened.

《発明の効果》 以上詳述した本発明にかかる建設方法によれば、次の
ような効果を奏することができる。
<< Effects of the Invention >> According to the construction method of the present invention described in detail above, the following effects can be achieved.

(1)構築した主構築部分上で直上に位置すべき主構築
部分を順次構築することとなるので、主構築部分の構築
作業とその構築作業の基台となっている既に構築の完了
した主構築部分のリフトアップ作業とを並行させて進め
ることができる。これにより、工期を各段に短縮でき、
生産性を向上できる。
(1) Since the main building portion that should be located immediately above the main building portion that has been built will be built sequentially, the construction work of the main construction portion and the main building that has already been completed that is the base of the construction work It is possible to proceed in parallel with the lift-up work of the building part. This can shorten the construction period,
Productivity can be improved.

(2)最上階主構築部分及び各主構築部分を、骨組とな
る主柱間に渡架させるので、充分な支持強度を得ること
ができ、超高層の建築物の建設に好ましく適用できる。
(2) Since the main building portion on the top floor and each main building portion are bridged between the main columns forming a frame, sufficient supporting strength can be obtained, which is preferably applicable to the construction of a super high-rise building.

(3)各構築作業を構築用プラントにより実施するの
で、人手による作業を不要とでき、24時間操業が可能と
なり、生産性の向上を図れる。
(3) Since each construction work is carried out by the construction plant, it is possible to eliminate the need for manual work, enable 24-hour operation, and improve productivity.

(4)主柱群は、渡架した最上階主構築部分の上昇より
も若干その構築を先行させれば良く、他の各構築作業と
並行して構築できるので、より一層の工期短縮を達成で
きる。
(4) The main pillar group can be constructed in parallel with each other construction work, as long as the construction of the main pillar group is slightly advanced before the rise of the main construction section on the top floor, and the construction period is further shortened. it can.

(5)上下の主構築部分間において進められる副梁躯体
の構築とそのリフトアップとの繰り返し作業は、所定高
さ位置に固定した下側の主構築部分を基台として進めら
れるので、これも他の各構築作業と並行させて進めるこ
とができ、生産性の向上を達成できる。
(5) The construction work of the sub-beam structure and the lift-up that are carried out between the upper and lower main building parts can be carried out with the lower main building part fixed at a predetermined height position as the base, so this also It is possible to proceed in parallel with each other construction work, and productivity improvement can be achieved.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明を適用して建設を進めている建築物の概
略的な斜視図である。 2……構築用プラント 10……建築物 12……副柱 13……副梁躯体 14……最上階主構築部分 18……副構築部分 30……主柱(エレベータ室) 40……主構築部分
FIG. 1 is a schematic perspective view of a building under construction to which the present invention has been applied. 2 …… Construction plant 10 …… Building 12 …… Sub-column 13 …… Sub-beam frame 14 …… Top floor main construction part 18 …… Sub-construction part 30 …… Main pillar (elevator room) 40 …… Main construction part

───────────────────────────────────────────────────── フロントページの続き (72)発明者 小林 一重 東京都千代田区神田司町2丁目3番地 株 式会社大林組東京本社内 (72)発明者 嘉藤 洋光 東京都千代田区神田司町2丁目3番地 株 式会社大林組東京本社内 (72)発明者 高橋 元 東京都千代田区神田司町2丁目3番地 株 式会社大林組東京本社内 (56)参考文献 特開 平1−235748(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Ichiko Kobayashi 2-3 Kandaji-cho, Chiyoda-ku, Tokyo Obayashi Corporation Tokyo headquarters (72) Inventor Yoko Kato 2-3-3 Kandaji-cho, Chiyoda-ku, Tokyo Obayashi Corporation Tokyo Head Office (72) Inventor Gen Takahashi 2-3 Kandajimachi, Chiyoda-ku, Tokyo Obayashi Corporation Tokyo Head Office (56) Reference JP-A-1-235748 (JP, A)

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】複数の主柱を所定高さで構築し、これらの
主柱間に掛け渡され該主柱に沿って昇降可能な最上階主
構築部分を構築し、この最上階主構築部分を複数階数分
リフトアップし、該最上階主構築部分に設けられた構築
用プラントにより前記主柱間に最下主構築部分を固定的
に構築し、その後、前記最上階主構築部分の構築用プラ
ントにより該最上階主構築部分の直下に位置する主構築
部分上にて主柱間に新たな主構築部分を構築するととも
に、該最上階主構築部分及び新たな主構築部分を複数階
数分リフトアップして該新たな主構築部分を所定位置に
固定する工程を繰り返し、前記主柱の構築を前記最上階
主構築部分のリフトアップ位置まで該リフトアップに先
行して行うことを特徴とする建設方法。
Claim: What is claimed is: 1. A plurality of main pillars are constructed at a predetermined height, and a top floor main building portion which is hung between these main pillars and which can be moved up and down along the main pillars is constructed. Is lifted up by a plurality of floors, and the bottom main building portion is fixedly constructed between the main pillars by the construction plant provided in the top floor main building portion, and then the top floor main building portion is constructed. A new main building part is constructed between main pillars on the main building part located directly under the top floor main building part by the plant, and the top floor main building part and the new main building part are lifted by several floors. A construction characterized by repeating the process of raising and fixing the new main building portion at a predetermined position, and building the main pillar up to the lift-up position of the top floor main building portion prior to the lift-up. Method.
【請求項2】前記最上階主構築部分のリフトアップ、該
最上階主構築部分及び最下主構築部分以外の主構築部分
の構築、または前記主柱の構築と並行して、高さ方向に
隣接する二つの主構築部分間に複数の副柱を立設すると
ともに、該二つの主構築部分のうち下方に位置する主構
築部分上で該副柱に沿って昇降可能な副梁躯体を構築
し、該副梁躯体をリフトアップして該二つの主構築部分
間における最上階階位置に固定し、その後、新たな副梁
躯体を構築してこれをリフトアップして前記最上階階位
置より順に下階となる位置に固定する工程を繰り返すこ
とを特徴とする請求項1に記載の建設方法。
2. The lift-up of the top floor main building portion, the construction of main building portions other than the top floor main building portion and the bottom main building portion, or in parallel with the construction of the main pillar, in the height direction. A plurality of sub-columns are erected between two adjacent main building portions, and a sub-beam structure that can be moved up and down along the sub-columns on the lower main building portion of the two main building portions is constructed. Then, the sub-beam structure is lifted up and fixed to the uppermost floor position between the two main building parts, and then a new sub-beam structure is constructed and lifted up to move from the uppermost floor position. The construction method according to claim 1, wherein a step of fixing the lower floors is sequentially repeated.
JP1112152A 1989-05-02 1989-05-02 Construction method Expired - Lifetime JPH0833030B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1112152A JPH0833030B2 (en) 1989-05-02 1989-05-02 Construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1112152A JPH0833030B2 (en) 1989-05-02 1989-05-02 Construction method

Publications (2)

Publication Number Publication Date
JPH02292433A JPH02292433A (en) 1990-12-03
JPH0833030B2 true JPH0833030B2 (en) 1996-03-29

Family

ID=14579539

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1112152A Expired - Lifetime JPH0833030B2 (en) 1989-05-02 1989-05-02 Construction method

Country Status (1)

Country Link
JP (1) JPH0833030B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0833031B2 (en) * 1990-08-14 1996-03-29 大成建設株式会社 How to build a building

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07122288B2 (en) * 1988-03-12 1995-12-25 道夫 倉持 Assembly and dismantling method of multi-story building using self-lifting jack-up device

Also Published As

Publication number Publication date
JPH02292433A (en) 1990-12-03

Similar Documents

Publication Publication Date Title
JP2957328B2 (en) Peripheral holding self-elevating construction method
JPH0833030B2 (en) Construction method
JPH08270081A (en) Construction method of frame structure
JP2997843B2 (en) Construction method
JPH0791904B2 (en) Push-up device
JP3179814B2 (en) Column and beam construction method and apparatus
JP2592980B2 (en) Construction method of steel frame material for high-rise structure
KR200200364Y1 (en) High building construction apparatus
JP2871468B2 (en) How to build a building
JPH08105229A (en) How to build a building
JP3115942B2 (en) Building construction method
JP2796448B2 (en) Building construction method and building construction equipment used for the construction method
JPH05230891A (en) Construction method of super-multistoried building
JPH1046838A (en) Demolition method of building
JP2876957B2 (en) Self-elevating construction equipment
JPH07259191A (en) All-weather construction method for structures
JPH0447072A (en) Construction method for multistory building and its device
JPH03235838A (en) Lift up method of construction using temporary pillar
JPS62244942A (en) Push-up method and apparatus
JPH07139042A (en) Construction method of frame and frame used therefor
JP2881503B2 (en) Temporary strut for stroke pole
JPH08312143A (en) Temporary frame device for construction
JPH08312144A (en) Temporary frame device for construction
JPH0762747A (en) Building method of pillar and beam and device therefor
JPH11131811A (en) Building method