JPH086311B2 - Ground improvement body construction method and its equipment - Google Patents
Ground improvement body construction method and its equipmentInfo
- Publication number
- JPH086311B2 JPH086311B2 JP32012991A JP32012991A JPH086311B2 JP H086311 B2 JPH086311 B2 JP H086311B2 JP 32012991 A JP32012991 A JP 32012991A JP 32012991 A JP32012991 A JP 32012991A JP H086311 B2 JPH086311 B2 JP H086311B2
- Authority
- JP
- Japan
- Prior art keywords
- slime
- blade
- injection pipe
- pipe
- ground improvement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 title claims description 8
- 238000002347 injection Methods 0.000 claims description 45
- 239000007924 injection Substances 0.000 claims description 45
- 238000009412 basement excavation Methods 0.000 claims description 18
- 239000003795 chemical substances by application Substances 0.000 claims description 13
- 239000013505 freshwater Substances 0.000 claims description 13
- 239000004848 polyfunctional curative Substances 0.000 claims description 10
- 238000005553 drilling Methods 0.000 claims description 5
- 239000010802 sludge Substances 0.000 claims description 5
- 238000000034 method Methods 0.000 claims description 3
- 239000002689 soil Substances 0.000 description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 238000007599 discharging Methods 0.000 description 2
- 238000009825 accumulation Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 238000003756 stirring Methods 0.000 description 1
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、軟弱地盤の改良、建築
構造物基礎等を主目的として施工される地盤改良体造成
工法及びその装置に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a ground improvement body and an apparatus therefor for the purpose of improving soft ground, building structure foundation and the like.
【0002】[0002]
【従来の技術】硬化剤噴射による地盤改良工法は、これ
まで様々な試行錯誤を経て発展してきた。本件発明者等
による攪拌翼や掘削翼を付した地盤改良装置の開発、更
にはスパイラル溝による回転機能を伴う硬化剤及びエア
の噴射を利用した工法並びに装置の開発(平成3年7月
26日、及び同年8月19日出願等)は、大口径かつ強
靭な地盤改良体造成において、画期的な前進を持たらし
た。更にまた、本件発明者等は、掘削目標地点における
空気やスライムの滞留を排除し、地内泥水圧を一定化さ
せるための機構を備えた工法及び装置(平成3年8月1
4日出願)をも開発した。これら発明については、既に
出願済である。2. Description of the Related Art A ground improvement method by spraying a curing agent has been developed through various trials and errors. The inventors of the present invention developed a ground improvement device equipped with a stirring blade and an excavation blade, and further developed a construction method and device using a curing agent and air injection with a rotating function by a spiral groove (July 26, 1991) , And the application filed on August 19, of the same year) made a breakthrough in the construction of a large-diameter and tough ground improvement body. Furthermore, the inventors of the present invention have proposed a construction method and device equipped with a mechanism for eliminating the accumulation of air and slime at the target point of excavation and making the soil mud pressure constant (August 1st, 1991).
4th application) was also developed. We have already applied for these inventions.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、本件発
明者にとって、経済性と確実性を維持しつつ、より均一
かつ強靭な地盤改良体を造成することが永遠の課題であ
り、発明者は、様々な角度から研究を重ねてきた。本発
明は、このような開発研究の中で考案されたもので、地
内のスライムをよりスムーズに排除し、地内泥水圧の一
定化をより円滑に行うことにより、掘削対象地盤におい
て、一層均一な改良地盤を造成することを目的とする。However, it is an eternal problem for the inventor of the present invention to create a more uniform and tough ground improvement body while maintaining economic efficiency and certainty. I have been studying from various angles. The present invention was devised in the course of such development research, and more smoothly removes slime in the ground, and more smoothly stabilizes the mud pressure in the ground, so that the ground to be excavated is more uniform. The purpose is to create improved ground.
【0004】[0004]
【課題を解決するための手段】上記目的を達成するため
に、硬化剤注入管、加圧気体注入管、スライム排出管、
清水噴射管または/及びエア噴射管を内蔵すると共に、
モニタ部、ロッド本体部掘削用ビット、掘削翼ビット及
び掘削翼を有する硬化剤注入ロッドにおいて、排泥翼を
有すると共に、該排泥翼に開閉自在のスライム吸入孔を
設けて成ることを特徴とする地盤改良体造成装置を提供
する。さらに、硬化剤注入管、加圧気体注入管、スライ
ム排出管、清水噴射管または/及びエア噴射管を内蔵す
ると共に、モニタ部、ロッド本体部掘削用ビット、掘削
翼ビット及び掘削翼を有する硬化剤注入ロッドを用いた
工法において、掘削翼先端のノズル部から加圧気体で包
合しつつ硬化剤を回転噴射すると共に、排泥翼に設けた
スライム吸入孔からスライムを吸入し、吸入したスライ
ムを清水または/及びエアの噴射力によって上方または
排出方向に押し上げ、更にスライム排出管から該スライ
ムを外部に排出することを特徴とする地盤改良体造成工
法を提供する。 In order to achieve the above object, a curing agent injection pipe, a pressurized gas injection pipe, a slime discharge pipe,
With a built-in fresh water injection pipe and / or air injection pipe,
In a hardener injection rod having a monitor part, a rod body part excavating bit, an excavating blade bit, and an excavating blade, a mud exhaust blade is provided, and a slime suction hole that can be opened and closed is provided in the exhaust mud blade.
It is made provided to provide a soil improvement material reclamation device comprising a. In addition, hardener injection pipe, pressurized gas injection pipe, slide
Built-in exhaust pipe, fresh water injection pipe and / or air injection pipe
In addition, monitor part, rod body excavation bit, excavation
Using a hardener injection rod with wing bits and drilling wings
During the construction method, the gas at the tip of the excavation blade was wrapped with pressurized gas
The curing agent was rotated and sprayed while being combined, and it was installed in the mud blade.
Slime was inhaled through the slime suction port and
The upper or lower side by the jet force of fresh water and / or air.
Push it up in the discharge direction, and then use the slime discharge pipe to
Ground improvement body construction work characterized by discharging the soil to the outside
Provide the law.
【0005】[0005]
【作用】上記手段を採用した結果、掘削時のスライムの
スムーズな排出による地内泥水圧の均一化が確実にはか
られ、よりすぐれた地盤改良体の造成が可能となる。As a result of adopting the above means, it is possible to surely make the soil mud pressure uniform by smooth discharge of slime at the time of excavation, and to make a better ground improvement body.
【0006】[0006]
【実施例】以下、本発明の実施例を図面を参照しつつ説
明する。図1は、本発明にかかる一実施例の実施状況を
示した概略斜視図である。即ち、内部に硬化剤注入管1
1、加圧気体注入管12、スライム排出管13、清水噴
射管14及びエア噴射管15を具備すると共に、本体部
下方に、ビット17を有する掘削翼16と更にその下部
にモニタ部22及び掘削用ビット23を備えた硬化剤注
入ロッド10において、該掘削翼16の上方に排泥翼2
0を設けた地盤改良体造成装置を示している。ここで、
排泥翼20は、掘削翼16の上方で、掘削翼16先端の
周囲ノズル19から噴射される加圧気体で包合され、核
ノズル18から高圧噴射される硬化剤を吸入しない程度
の適当な高さに設ける必要がある。そして、本実施例に
あっては、該排泥翼20は、その側端部の一方を比較的
厚く、他方を比較的薄く形成し、その側端部に開閉自在
のスライム吸入孔21を設けると共に、排泥翼20の先
端部にも同様に開閉自在のスライム吸入孔21を設けて
いる。勿論、このスライム吸入孔21は、側端部、先端
部のいずれか一方に設けるだけでもよく、また、スライ
ム吸入孔21の大きさや数は、自由に設けることができ
る。Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a schematic perspective view showing an implementation situation of an embodiment according to the present invention. That is, the hardening agent injection pipe 1
1, a pressurized gas injection pipe 12, a slime discharge pipe 13, a fresh water injection pipe 14 and an air injection pipe 15, and an excavation blade 16 having a bit 17 below the main body, and a monitor 22 and excavation further below the excavation blade 16. In the hardening agent injecting rod 10 provided with the working bit 23, the drainage blade 2 is provided above the excavation blade 16.
The ground improvement body construction apparatus which provided 0 is shown. here,
The drainage blade 20 is surrounded by the pressurized gas jetted from the peripheral nozzle 19 at the tip of the excavation blade 16 above the excavation blade 16, and is suitable for not inhaling the hardening agent jetted at high pressure from the nuclear nozzle 18. It must be installed at the height. Further, in the present embodiment, the sludge removal blade 20 is formed such that one of its side ends is relatively thick and the other is relatively thin, and a slime suction hole 21 which can be opened and closed is provided at the side end. At the same time, a slime suction hole 21 that can be opened and closed is also provided at the tip of the sludge discharge blade 20. Of course, this slime suction hole 21 may be provided only at one of the side end portion and the tip end portion, and the size and number of the slime suction hole 21 can be freely provided.
【0007】本構成にあっては、排泥翼20の側端部の
スライム吸入孔21は、ロッド10の回転方向に設けら
れていることになる。勿論、逆方向に設けることも可能
であるが、地内において、ロッドの回転方向に該吸入孔
21を設ける方がよりスライム吸入力を増強できるの
で、ロッドの回転方向に設けることが望ましい。これに
よって、開閉自在の構成(図示なし)とも相俟って、掘
削地盤の状況、スライム発生量等に応じて調整を容易に
行いつつ、スムーズなスライム吸入ができる。尚、該ス
ライム孔21を、硬化剤注入ロッド本体10自体、即ち
掘削翼16の上方の適当な位置に設けることも勿論可能
であるが、かかる実施例については、既に出願済であ
る。In this structure, the slime suction hole 21 at the side end of the sludge discharge blade 20 is provided in the rotation direction of the rod 10. Of course, it is also possible to provide the suction holes 21 in the reverse direction, but it is desirable to provide the suction holes 21 in the rotation direction of the rod in the ground because the slime suction force can be further enhanced. Accordingly, in combination with the openable and closable structure (not shown), smooth slime intake can be performed while easily adjusting according to the condition of the excavated ground, the slime generation amount, and the like. The slime hole 21 may be provided at an appropriate position above the hardener injection rod body 10 itself, that is, above the excavation blade 16, but such an embodiment has already been applied for.
【0008】スライム吸入孔21を掘削翼16に設ける
本発明にあっては、ロッド本体部10のみに1箇所設け
た場合よりも、スムーズなスライム吸入並びに排出がで
き、地内泥水圧をより円滑に均一化できることとなる。
尚、この場合、ロッド内部で連通しているスライム排出
管13までの距離がある点で、スライム吸入孔21をロ
ッド本体部10に設けた場合よりも排出に時間を要する
可能性があるが、スライムの吸上げ力を増すことにより
かかる問題は解決できる。即ち、図1によれば、硬化剤
注入管11とは別に、清水噴射管14及びエア噴射管1
5をロッド本体10内に設けるとともに、更に排泥翼2
0から該ロッド本体上方へ連通しているスライム排出管
13が排泥翼20の接合部(付け根)の曲折部におい
て、吸入されたスライムを上方の排出方向へ強力に押し
上げるべく、エアに包合された清水を該曲折部の下部に
設けた噴射口(図示なし)より上方へ高圧噴射すること
により、スライムを軟化させるとともに排出力を増強さ
せ、スムーズな泥水排出が可能となる。また、この清水
とエアを常に同時に噴射する必要はなく、場合によって
は、清水のみ、あるいはエアのみを噴射することも可能
である。それぞれの噴射管が、別個独立のものだからで
ある。他方、上記のスムーズなスライムの排出のために
は、地上に吸入用モータを設置することも無論可能であ
る。In the present invention in which the slime suction hole 21 is provided in the excavation blade 16, the slime can be smoothly sucked in and discharged, and the mud pressure in the ground can be made smoother than in the case where the slime suction hole 21 is provided at only one place in the rod body 10. It can be made uniform.
In this case, since there is a distance to the slime discharge pipe 13 communicating with the inside of the rod, it may take longer time to discharge than the case where the slime suction hole 21 is provided in the rod body portion 10. This problem can be solved by increasing the suction power of slime. That is, according to FIG. 1, in addition to the curing agent injection pipe 11, a fresh water injection pipe 14 and an air injection pipe 1
5 is provided in the rod body 10, and the sludge removal blade 2 is further provided.
The slime discharge pipe 13 communicating from 0 to the upper part of the rod main body is mixed with air in order to strongly push the sucked slime upward in the discharge direction at the bent portion of the joint (root) of the mud blade 20. By high-pressure injecting the produced fresh water from an injection port (not shown) provided in the lower portion of the bent portion, the slime is softened and the discharge force is enhanced, so that the muddy water can be smoothly discharged. Further, it is not always necessary to inject the fresh water and the air at the same time, and in some cases, it is possible to inject only the fresh water or only the air. This is because each injection pipe is independent and independent. On the other hand, in order to smoothly discharge the slime, it is of course possible to install a suction motor on the ground.
【0009】以上の構成にかかる本発明の装置を使用す
ることによって、改良体造成位置において、掘削翼16
とその側端部に設けた掘削翼ビット17にて回転掘削し
つつ、該掘削翼16先端のノズル部18、19より加圧
気体で包合された硬化剤の高圧噴射を開始し、注入ロッ
ド10の回転、揺動及び引き上げと相俟って、排泥翼2
0に設けたスライム吸入孔21からスライムを吸入し、
更に清水叉は/及びエアのジェット噴射力により、スラ
イム排出管13からスライムをスムーズに排出すること
により、余剰水たる泥水を排出せしめ地内泥水圧を略一
定に保ちつつ地盤造成を行うこととなる。By using the apparatus of the present invention having the above-mentioned structure, the excavating blade 16 is provided at the improved body forming position.
While rotating and excavating with the excavating blade bit 17 provided at the side end portion of the excavating blade, high-pressure injection of the hardener encapsulated with the pressurized gas is started from the nozzle portions 18 and 19 at the tip of the excavating blade 16 to inject the injection rod. Combined with the rotation, rocking and pulling up of 10, the mud blade 2
Intake slime from the slime suction hole 21 provided in 0,
Further, the jet injection force of Shimizu or / and air smoothly discharges the slime from the slime discharge pipe 13, thereby discharging the mud water which is the surplus water, and performing the ground preparation while keeping the mud pressure in the ground substantially constant. .
【0010】図2(A)(B)は、本発明の一実施例に
おける硬化剤注入ロッド10の断面図を示す。即ち、注
入ロッド10に内蔵された各種管の構成状態を示したも
のである。ここで、(A)は、スライム排出管13、清
水噴射管14及びエア噴射管15を同心円状に構成した
構成であるのに対し、(B)は、当該3種の管をそれぞ
れ別々の単管とした構成を示す。これらは、掘削対象地
盤の地質、深度等、ひいてはスライムの硬軟の程度、量
等に応じて、適宜選択することができる。2A and 2B are sectional views of the hardener injection rod 10 in one embodiment of the present invention. That is, it shows the configuration of various tubes built in the injection rod 10. Here, (A) has a configuration in which the slime discharge pipe 13, the fresh water injection pipe 14, and the air injection pipe 15 are concentrically configured, while (B) shows the three types of pipes, each of which is a single unit. The configuration as a tube is shown. These can be appropriately selected depending on the geology, depth, etc. of the ground to be excavated, and by extension, the degree and amount of the slime.
【0011】[0011]
【発明の効果】本発明によれば、掘削時のスライムをよ
りスムーズに外部に排出できるため、地内泥水圧の均一
化が確実となり、大口径で強度の均一な優れた地盤改良
体の造成が可能となる。EFFECTS OF THE INVENTION According to the present invention, slime during excavation can be discharged to the outside more smoothly, so that the soil mud pressure can be made uniform, and an excellent ground improvement body having a large diameter and uniform strength can be constructed. It will be possible.
【0012】[0012]
【図1】 本発明の一実施例における概略斜視図で
ある。FIG. 1 is a schematic perspective view of an embodiment of the present invention.
【図2(A)】本発明の一実施例における硬化剤注入ロ
ッドの断面図である。FIG. 2 (A) is a cross-sectional view of a hardener injection rod in one embodiment of the present invention.
【図2(B)】本発明の他の実施例における硬化剤注入
ロッドの断面図である。FIG. 2B is a cross-sectional view of a hardener injection rod according to another embodiment of the present invention.
10 硬化剤注入ロッド 11 硬化剤注入管 12 加圧気体注入管 13 スライム排出管 14 清水噴射管 15 エア噴射管 16 掘削翼 17 掘削翼ビット 18 核ノズル 19 周囲ノズル 20 排泥翼 21 スライム吸入孔 22 モニタ部 23 ロッド本体部掘削用ビット 10 Curing Agent Injection Rod 11 Curing Agent Injection Pipe 12 Pressurized Gas Injection Pipe 13 Slime Discharge Pipe 14 Fresh Water Injection Pipe 15 Air Injection Pipe 16 Drilling Blade 17 Drilling Blade Bit 18 Nuclear Nozzle 19 Surrounding Nozzle 20 Exhaust Mud Blade 21 Slime Intake Hole 22 Monitor part 23 Rod body excavating bit
Claims (3)
(12)、スライム排出管(13)、清水噴射管(1
4)、または/及びエア噴射管(15)を内蔵すると共
に、モニタ部(22)、ロッド本体部掘削用ビット(2
3)、掘削翼ビット(17)及び掘削翼(16)を有す
る硬化剤注入ロッド(10)において、排泥翼(20)
を有すると共に、該排泥翼(20)にスライム吸入孔を
設けて成ることを特徴とする地盤改良体造成装置。1. Hardener injection pipe (11), pressurized gas injection pipe (12), slime discharge pipe (13), fresh water injection pipe (1)
4) or / and a built-in air injection pipe (15), a monitor part (22), a rod body excavating bit (2)
3), in a hardener injection rod (10) having a drilling blade bit (17) and a drilling blade (16), a mud blade (20)
And has a slime suction hole in the drainage blade (20).
A ground improvement body constructing device characterized by being provided .
閉自在に設置されたことを特徴とする地盤改良体造成装
置。2. A ground improvement body constructing device, wherein the slime suction hole (21) of claim 1 is installed so as to be openable and closable.
(12)、スライム排出管(13)、清水噴射管(1
4)叉は/及びエア噴射管(15)を内蔵すると共に、
モニタ部(22)、ロッド本体部掘削用ビット(2
3)、掘削翼ビット(17)及び掘削翼(16)を有す
る硬化剤注入ロッド(10)を用いた工法において、 掘削翼先端のノズル部から加圧気体で包合しつつ硬化剤
を回転噴射すると共に、排泥翼(20)に設けたスライ
ム吸入孔(21)からスライムを吸入し、吸入したスラ
イムを清水叉は/及びエアの噴射力によって上方叉は排
出方向に押し上げ、更にスライム排出管(13)から該
スライムを外部に排出することを特徴とする地盤改良体
造成工法。3. A hardening agent injection pipe (11), a pressurized gas injection pipe (12), a slime discharge pipe (13), and a fresh water injection pipe (1).
4) Incorporating the or / and air injection pipe (15),
Monitor part (22), rod body excavating bit (2
3), a method of using a hardening agent injection rod (10) having an excavation blade bit (17) and an excavation blade (16), in which a curing agent is rotationally jetted while being encapsulated by a pressurized gas from a nozzle portion at the tip of the excavation blade. At the same time, the slime is sucked from the slime suction hole (21) provided in the sludge discharge blade (20), and the sucked slime is pushed upward by the fresh water or / and the jetting force of the air in the discharge direction, and further, the slime discharge pipe. The ground improvement body construction method, wherein the slime is discharged from (13).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP32012991A JPH086311B2 (en) | 1991-09-27 | 1991-09-27 | Ground improvement body construction method and its equipment |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP32012991A JPH086311B2 (en) | 1991-09-27 | 1991-09-27 | Ground improvement body construction method and its equipment |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0586614A JPH0586614A (en) | 1993-04-06 |
| JPH086311B2 true JPH086311B2 (en) | 1996-01-24 |
Family
ID=18118029
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP32012991A Expired - Lifetime JPH086311B2 (en) | 1991-09-27 | 1991-09-27 | Ground improvement body construction method and its equipment |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH086311B2 (en) |
Families Citing this family (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20020043475A (en) * | 2002-04-20 | 2002-06-10 | 이정우 | The method of soil improvement and its device |
| KR20020035082A (en) * | 2002-04-20 | 2002-05-09 | 이정우 | JSP and its device |
| KR20040040791A (en) * | 2002-11-08 | 2004-05-13 | 정성필 | The anchor method which uses the ground improvement shoe |
| KR100770647B1 (en) * | 2007-02-14 | 2007-10-29 | 성안산업개발 주식회사 | Drive separation type ground improvement device and ground improvement method using the device |
| KR100944857B1 (en) * | 2009-05-19 | 2010-03-04 | 이성남 | Apparatus for improvement soft ground |
| CN102817347B (en) * | 2012-09-05 | 2015-07-22 | 北京东方新星石化工程股份有限公司 | Reaming device for reinforcing soft soil foundation |
| CN107837574A (en) * | 2017-10-27 | 2018-03-27 | 上海市政工程设计研究总院(集团)有限公司 | A kind of sludge discharging method of sludge drainage system of settling pond |
| CN114607282B (en) * | 2022-03-30 | 2023-12-01 | 山东高速建设管理集团有限公司 | A construction drill bit and method capable of constructing multi-form cement and soil mixing piles |
| CN119118464B (en) * | 2024-11-06 | 2025-06-27 | 迁安市泓承瑞再生资源利用有限公司 | A dredging device for precious metal waste treatment |
-
1991
- 1991-09-27 JP JP32012991A patent/JPH086311B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0586614A (en) | 1993-04-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH086311B2 (en) | Ground improvement body construction method and its equipment | |
| KR960003746B1 (en) | Full-angle ground reformer composition method and device | |
| JPS6151117B2 (en) | ||
| JP4679705B2 (en) | Equipment for constructing mechanically stirred air cement milk mixed pressure feeding method | |
| JP3663503B2 (en) | High pressure injection ground improvement method | |
| JP3046549B2 (en) | Suction port structure of sand pump for sediment collection | |
| TW200829754A (en) | Equipment and construction method for creating underground consolidation body | |
| JP3825896B2 (en) | Ground improvement body construction method and apparatus | |
| JPS5824020A (en) | Construction work for large-diameter hardened layer | |
| JP2001040662A (en) | Concrete pile and embedding method therefor | |
| JP3125033B2 (en) | Construction method of improved wall | |
| JP2727153B2 (en) | Ground improvement equipment and construction method | |
| JP3886433B2 (en) | Ground hardening layer construction method and equipment | |
| JPH0826539B2 (en) | Ground improvement body construction method and its equipment | |
| JP3574488B2 (en) | Ground improvement method for soft ground | |
| JPH086308B2 (en) | Deformation ground improvement body construction method | |
| JPS6229611A (en) | Ground improvement method using widening equipment | |
| JP2005188253A (en) | Tunnel receiving method | |
| JPH06264676A (en) | Underwater drilling equipment and underwater drilling method | |
| JPH06257379A (en) | Excavation method for tunnels, etc. | |
| JP2864243B2 (en) | Shaft construction method | |
| KR100216681B1 (en) | Indentation promotion method for water, sewage pipes, etc. | |
| JP4080343B2 (en) | Ground hardening material high pressure injection improvement method | |
| JPH06128943A (en) | All round subsoil improvement method and device thereof | |
| JPH06185047A (en) | Establishing method for underground pile and monitoring mechanism for establishment device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090124 Year of fee payment: 13 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100124 Year of fee payment: 14 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120124 Year of fee payment: 16 |
|
| EXPY | Cancellation because of completion of term | ||
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120124 Year of fee payment: 16 |