Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH086549B2 - Work management device for tunnel construction - Google Patents
[go: Go Back, main page]

JPH086549B2 - Work management device for tunnel construction - Google Patents

Work management device for tunnel construction

Info

Publication number
JPH086549B2
JPH086549B2 JP23551789A JP23551789A JPH086549B2 JP H086549 B2 JPH086549 B2 JP H086549B2 JP 23551789 A JP23551789 A JP 23551789A JP 23551789 A JP23551789 A JP 23551789A JP H086549 B2 JPH086549 B2 JP H086549B2
Authority
JP
Japan
Prior art keywords
signal
spraying
machine
work
tunnel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP23551789A
Other languages
Japanese (ja)
Other versions
JPH03100298A (en
Inventor
正信 高木
弘 水口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP23551789A priority Critical patent/JPH086549B2/en
Publication of JPH03100298A publication Critical patent/JPH03100298A/en
Publication of JPH086549B2 publication Critical patent/JPH086549B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Earth Drilling (AREA)

Description

【発明の詳細な説明】 《産業上の利用分野》 この発明は、トンネル工事用作業管理装置に関し、特
に、一連の作業手順で施工されるトンネル工事の実際の
作業時間を作業の進行状態とともに自動的に表示できる
管理装置に関する。
Description: TECHNICAL FIELD The present invention relates to a tunnel work management apparatus, and more particularly, to an actual working time of tunnel construction that is carried out by a series of working procedures, together with the progress status of the work. Management device that can be displayed on a screen.

《発明の背景》 岩盤を掘削してトンネルなどを構築する方法として爆
薬を用いる発破工法が知られている。
<< Background of the Invention >> A blasting method using an explosive is known as a method for constructing a tunnel or the like by excavating rock mass.

この種の発破工法では、通常、切羽の穿孔工程、穿孔
に爆薬を装着し、爆薬を爆破する装薬爆破工程、ズリだ
し工程、1次吹付け工程、ロックボルトの装着工程、2
次吹付け工程、止水工程の順に作業を進行し、この工程
を繰り返すことによりトンネルが構築される。
In this type of blasting method, usually, a face piercing process, a charge blasting process in which an explosive is attached to the piercing and explodes the explosive, a slipping process, a primary spraying process, a lock bolt attaching process, 2
A tunnel is constructed by advancing the work in the order of the next spraying process and the water stopping process and repeating this process.

ところで、岩盤中に原油貯蔵タンクを構築する場合な
どでは、岩盤タンク掘削用やタンク間の連絡用トンネル
などで多数の切羽が同じ工事現場で施工されることがあ
る。
By the way, when constructing a crude oil storage tank in bedrock, a large number of facets may be constructed at the same construction site in a bedrock excavation tunnel or a connection tunnel between tanks.

このような施工状況において、各切羽の作業管理は、
従来、前述した施工工程ごとに管理責任者を選定し、選
定された管理責任者が日報などにより現場事務所に作業
時間などを報告していた。
In such a construction situation, work management of each face is
Conventionally, a manager has been selected for each of the above-mentioned construction processes, and the selected manager has reported the work hours and the like to the on-site office by daily reports.

しかしながら、このような作業管理手段では、日報の
提出は作業が行われた翌日になり、リアルタイムでの情
報を得ることができない上に、多数の切羽における作業
の進捗状態を全体的に把握するための集計に時間がかか
るという問題もあった。
However, with such a work management means, the daily report is submitted on the day after the work is performed, real-time information cannot be obtained, and the progress status of the work on many facets is grasped as a whole. There was also a problem that it took time to count.

この発明は、このような従来の問題点に鑑みてなされ
たものであり、その目的とするところは、作業情報がリ
アルタイムで把握できるとともに、多数の切羽における
作業の集計が簡単にできるトンネル工事用作業管理装置
を提供することにある。
The present invention has been made in view of such conventional problems, and an object thereof is for tunnel construction in which work information can be grasped in real time and work of many facets can be easily aggregated. To provide a work management device.

《課題を解決するための手段》 上記目的を達成するために、本発明は、切羽の穿孔工
程、穿孔に爆薬を装着して爆破する装薬爆破工程、ズリ
だし工程、1次吹付け工程、ロックボルトの装着工程、
2次吹付け工程、止水工程の順に繰り返されるトンネル
工事において、前記穿孔工程の穿孔掘削機の駆動信号
と、前記装薬爆破工程の作業開始信号および発破器の稼
動信号と、前記ズリだし工程でズリを土砂運搬車に積載
する積載機の稼動信号およびズリ搬出用の土砂運搬車の
出入坑信号と、前記1次吹付け工程の吹付機の稼動信号
と、前記ロックボルト装着工程のナット締付機の駆動信
号と、前記2次吹付け工程の吹付機の稼動信号と、前記
止水工程の釘打機の駆動信号とをそれぞれ入力信号と
し、これらの入力信号に基づき前記各工程の作業時間を
工程順に作表する演算装置とを有することを特徴とす
る。
<Means for Solving the Problems> In order to achieve the above object, the present invention provides a facet piercing step, a charge blasting step of blasting with an explosive attached to the piercing hole, a slipping step, a primary spraying step, Lock bolt installation process,
In the tunnel construction in which the secondary spraying process and the water stopping process are repeated in this order, the driving signal for the drilling excavator in the drilling process, the work start signal for the charging and blasting process, and the operation signal for the blaster, and the slipping process. The operation signal of the loading machine for loading the sludge on the earth and sand carrier and the entrance / exit signal of the earth and sand carrier for unloading the sludge, the operation signal of the spraying machine in the primary spraying process, and the nut tightening in the lock bolt mounting process. The drive signal of the attached machine, the operation signal of the spray machine of the secondary spraying process, and the drive signal of the nailing machine of the water stopping process are used as input signals, and the work of each process is performed based on these input signals. And a computing device for tabulating time in process order.

《発明の作用効果》 上記構成のトンネル工事用作業管理装置によれば、穿
孔から止水の各工程において、それぞれ作業の開始およ
び終了に相当する電気信号が出力されるので、各工程に
おける作業状況をリアルタイムで把握できる。
<< Advantageous Effects of the Invention >> According to the tunnel construction work management apparatus having the above-described configuration, electric signals corresponding to the start and end of the work are output from the drilling in each of the steps of the water stoppage. Can be grasped in real time.

また、各工程から出力された信号は、演算装置で自動
的に処理されて工程順に作表されるので、切羽が多数あ
っても簡単に対応でき、集計も容易になる。
Further, the signals output from the respective steps are automatically processed by the arithmetic device and tabulated in the order of the steps, so that even if there are many facets, it is possible to easily deal with them, and the tabulation becomes easy.

《実施例》 以下、この発明の好適な実施例について添付図面を参
照にして詳細に説明する。
Embodiment Hereinafter, a preferred embodiment of the present invention will be described in detail with reference to the accompanying drawings.

第1図から第4図は、この発明にかかるトンネル工事
用作業管理装置の一実施例を示している。
1 to 4 show an embodiment of a tunnel construction work management apparatus according to the present invention.

同図に示す管理装置は、第1図に示す工程で施工され
るトンネル工事に適用されるものであり、トンネル工事
は順に繰り返される切羽の穿孔工程、穿孔に爆薬を
装着して爆破する装薬爆破工程、ズリだし工程、1
次吹付け工程、ロックボルトの装着工程、2次吹付
け工程、止水工程からなっている。
The management device shown in the same figure is applied to the tunnel construction carried out in the process shown in FIG. 1, and the tunnel construction is repeated in order, and the explosive charge is attached to the drilling to explode the explosive charge. Blasting process, slipping process, 1
It consists of a secondary spraying process, a lock bolt mounting process, a secondary spraying process, and a water stopping process.

作業管理装置は、上記〜の各工程で使用される各
種機械の稼動により発せられる信号s1〜s10と、この信
号s1〜s10に基づいて前記工程〜の作業時間を工程
順に作表する演算装置CPUとから構成されている。
The work management device includes signals s1 to s10 generated by the operation of various machines used in each of the above steps, and an arithmetic unit CPU that tabulates the work times of the steps to the step order based on the signals s1 to s10. It consists of and.

上記信号s1〜s10の詳細について説明すると、切羽の
穿孔工程から送られる信号S1は、穿孔装置の駆動開始
信号と終了信号とを含んでおり、これらの信号以外に、
例えば、穿孔装置が一般的に採用されているジャンボ機
であれば、その削孔ロッドの速度信号,打撃油圧の大き
さ,押し付け油圧の大きさなどの信号も含ませて、これ
らの信号に基づいて最大削孔速度を演算装置CPUで計算
して穿孔作業のより詳細な管理をすることもできる。
Explaining the details of the signals s1 ~ s10, the signal S1 sent from the face punching step includes a driving start signal and an end signal of the punching device, in addition to these signals,
For example, if the boring device is a jumbo machine that is generally adopted, signals such as the speed signal of the drilling rod, the magnitude of the impact hydraulic pressure, and the magnitude of the pressing hydraulic pressure are also included, and based on these signals. It is also possible to calculate the maximum drilling speed with the computing device CPU for more detailed control of drilling work.

穿孔に爆薬を装着して爆破する装薬爆破工程から送
られる信号は、装薬の開始でセットされる開始信号s2
と、発破器の稼動により送出される停止信号s3である。
The signal sent from the explosive blasting process in which explosives are attached to the hole to explode is the start signal s2 that is set at the start of explosive
And the stop signal s3 sent by the operation of the blasting machine.

ズリだし工程から送られてくる信号は、ズリを外部
に搬出するためのダンプトラックDにズリを載せるホイ
ールローダ(土砂積載機)の稼動と、ダンプトラックD
の稼動との情報を含んでいる。
The signal sent from the slipping process is the operation of the wheel loader (earth and sand loading machine) that puts the slip on the dump truck D for carrying the slip to the outside and the dump truck D.
It contains information about the operation of.

ホイールローダーに関する信号s4では、バケットの上
昇および下降で発せられる信号と、ホイールローダの走
行時間信号とがある。
The signal s4 relating to the wheel loader includes a signal issued when the bucket is raised and lowered and a traveling time signal of the wheel loader.

第3図にダンプトラックDの稼動で送られてくる信号
s5の詳細を示している。
Fig. 3 Signals sent by the operation of the dump truck D
It shows the details of s5.

同図では、現在作業が進行している切羽を有するトン
ネルTの入口近傍に、受光器Rと、その制御器Cとが取
付けられたポールPが立設されている。
In the figure, a pole P to which a light receiver R and its controller C are attached is erected in the vicinity of the entrance of a tunnel T having a face where the work is currently in progress.

また、トンネルTの出口通路上には、重量計Wが設置
されている。
A weight scale W is installed on the exit passage of the tunnel T.

一方、トンネルTに出入りするダンプトラックDに
は、送信器Sと発光器Pとが装備されている。
On the other hand, the dump truck D entering and leaving the tunnel T is equipped with a transmitter S and a light emitter P.

トンネルTに入るダンプトラックDは、送信器Sを駆
動して発光器Pから光信号を受光器Rに送るとともに、
ズリを搭載してトンネルTから出てきたダンプトラック
Dは、重量計W上に停止して搭載されているズリの量を
計測し、再び送信器Sを駆動して受光器Rに信号を送
る。
The dump truck D entering the tunnel T drives the transmitter S to send an optical signal from the light emitter P to the light receiver R, and
The dump truck D loaded with the slip and coming out from the tunnel T stops on the weighing scale W, measures the amount of the mounted slip, and drives the transmitter S again to send a signal to the light receiver R. .

以上の内容を含んだ信号s5を受けた演算装置CPUで
は、ズリだしの作業時間、ダンプトラックDの坑内滞留
時間、排出ズリ量の集計などが演算される。
The arithmetic unit CPU that has received the signal s5 including the above contents calculates the slipping work time, the mine retention time of the dump truck D, and the total amount of the discharge slippage.

1次吹付け工程から送られる信号s6は、コンクリー
ト吹付け機械の駆動,停止信号であり、これにより1次
吹付け工程の所要時間が演算される。
The signal s6 sent from the primary spraying step is a drive / stop signal for the concrete spraying machine, and the time required for the primary spraying step is calculated by this.

ロックボルトの装着工程から送られる信号は、モル
タルフィダーの駆動,停止信号s7と、ロックボルトナッ
トの締付け機の駆動、停止信号s8であり、締付け機のか
らの信号s8には、ナットの締付けトルクの大きさも含ま
せて、作業の品質管理に利用することもできる。
The signals sent from the lock bolt mounting process are the mortar feeder drive / stop signal s7 and the lock bolt nut tightening machine drive / stop signal s8. The tightening machine signal s8 contains the nut tightening torque. The size of can be included and used for quality control of work.

2次吹付け工程からの信号s9は、上記1次吹付けと
同様にコンクリート吹付け機械の駆動,停止信号であ
る。
The signal s9 from the secondary spraying step is a drive / stop signal for the concrete spraying machine as in the case of the primary spraying.

止水工程からの信号s10は、釘打機の駆動,停止信
号である。
The signal s10 from the water stopping process is a drive / stop signal for the nail driver.

なお、上記信号s1〜s10を演算装置CPUに入力する際に
は、有線で直接接続すること以外に、無線により信号の
伝達をすることもできる。
When the signals s1 to s10 are input to the arithmetic unit CPU, the signals can be wirelessly transmitted instead of being directly connected by wire.

以上の信号s1〜s10を受けた演算装置CPUでは、必要な
各種計算処理をし、第4図に示すように各工程〜の
作業時間を工程順に表示する。
The arithmetic unit CPU that has received the above signals s1 to s10 performs various necessary calculation processes and displays the work time of each process step in the order of steps as shown in FIG.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明にかかるトンネル工事用作業管理装置が
適用される作業工程のフローチャート図、第2図は同管
理装置の構成を示すブロック図、第3図はズリだし工程
における信号の収集状態の説明図、第4図は演算装置に
より作成された表の一例を示す説明図である。 CPU……演算装置 D……ダンプトラック S……送信器 R……受信器
FIG. 1 is a flowchart of a work process to which the tunnel construction work management device according to the present invention is applied, FIG. 2 is a block diagram showing the configuration of the management device, and FIG. 3 is a signal collection state in the slipping process. And FIG. 4 is an explanatory view showing an example of a table created by the arithmetic unit. CPU: arithmetic unit D: dump truck S: transmitter R: receiver

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】切羽の穿孔工程、穿孔に爆薬を装着して爆
破する装薬爆破工程、ズリだし工程、1次吹付け工程、
ロックボルトの装着工程、2次吹付け工程、止水工程の
順に繰り返されるトンネル工事において、前記穿孔工程
の穿孔掘削機の駆動信号と、前記装薬爆破工程の作業開
始信号および発破器の稼動信号と、前記ズリだし工程で
ズリを土砂運搬車に積載する積載機の稼動信号およびズ
リ搬出用の土砂運搬車の出入坑信号と、前記1次吹付け
工程の吹付機の稼動信号と、前記ロックボルト装着工程
のナット締付機の駆動信号と、前記2次吹付け工程の吹
付機の稼動信号と、前記止水工程の釘打機の駆動信号と
をそれぞれ入力信号とし、これらの入力信号に基づき前
記各工程の作業時間を工程順に作表する演算装置とを有
することを特徴とするトンネル工事用作業管理装置。
1. A face piercing process, a charge blasting process in which an explosive is attached to the piercing to explode, a slipping process, a primary spraying process,
In a tunnel construction in which a lock bolt mounting process, a secondary spraying process, and a water stopping process are repeated in this order, a driving signal for the drilling excavator in the drilling process, a work start signal in the charge blasting process, and a blaster operation signal. And an operation signal of a loading machine that loads the debris on the earth and sand carrier in the slipping process, an entrance and exit signal of the earth and sand carrier for carrying out the debris, an operation signal of the spraying machine in the primary spraying step, and the lock. The drive signal of the nut tightening machine in the bolt mounting process, the operation signal of the spraying machine in the secondary spraying process, and the drive signal of the nailing machine in the water stopping process are used as input signals. A work management device for tunnel construction, comprising: a computing device for tabulating the work time of each process in the order of processes.
JP23551789A 1989-09-13 1989-09-13 Work management device for tunnel construction Expired - Lifetime JPH086549B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23551789A JPH086549B2 (en) 1989-09-13 1989-09-13 Work management device for tunnel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23551789A JPH086549B2 (en) 1989-09-13 1989-09-13 Work management device for tunnel construction

Publications (2)

Publication Number Publication Date
JPH03100298A JPH03100298A (en) 1991-04-25
JPH086549B2 true JPH086549B2 (en) 1996-01-24

Family

ID=16987158

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23551789A Expired - Lifetime JPH086549B2 (en) 1989-09-13 1989-09-13 Work management device for tunnel construction

Country Status (1)

Country Link
JP (1) JPH086549B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5361444B2 (en) * 2009-02-24 2013-12-04 株式会社演算工房 Cycle time measurement method in tunnel construction
JP6942553B2 (en) * 2017-07-28 2021-09-29 大成建設株式会社 Tunnel construction process recording device and tunnel cycle time management device, tunnel construction process recording method and tunnel cycle time management method

Also Published As

Publication number Publication date
JPH03100298A (en) 1991-04-25

Similar Documents

Publication Publication Date Title
CN203559895U (en) Electric mining rope excavator, electric mining drilling machine and system
JPH03202513A (en) Method of automaticall controlling impact ripper
WO2012109192A2 (en) Pile installation and monitoring system and method of using the same
AU726098B2 (en) Shot-rock diggability monitor
JPH086549B2 (en) Work management device for tunnel construction
JPH11294080A (en) Tunnel excavation system
Bullock Trends in non-coal underground mining technology at the close of the millennium
JPH09328745A (en) Ground improvement method
US6122598A (en) Measurement and display of load of excavating blasted ground
Williams et al. 11 DESIGN IMPLEMENTATION
JP2916596B2 (en) Rock excavation method in the pneumatic caisson method.
Kirsten Efficient use on construction of tractor mounted rippers
RU2098629C1 (en) Method for sinking of shallow mine shafts
Ndhlovu et al. Global mine productivity issues: a review
JP3472953B2 (en) Tunnel digging device and tunnel digging method
JP3652062B2 (en) Automatic excavation load measuring device for blasting ground
SU810906A1 (en) Device for formating horizontal wells
JPS63255492A (en) Method of excavating raw ore
Scoble et al. A study of surface mine equipment monitoring
Morton New Blasthole Drill Rigs Feature More Autonomy
JPH06280467A (en) Tunnel cutting face information administration device
Anderson et al. Extending Excavator Performance with Boom Mounted Attachments
Esterhuyse The influence of geometry on dragline bucket filling performance
Fjellborg Controlled drifting and estimation of blast damage
JPH06280479A (en) Carrying method for waste in tunnel