JPH089868B2 - Construction method of main slab in underground space - Google Patents
Construction method of main slab in underground spaceInfo
- Publication number
- JPH089868B2 JPH089868B2 JP2076470A JP7647090A JPH089868B2 JP H089868 B2 JPH089868 B2 JP H089868B2 JP 2076470 A JP2076470 A JP 2076470A JP 7647090 A JP7647090 A JP 7647090A JP H089868 B2 JPH089868 B2 JP H089868B2
- Authority
- JP
- Japan
- Prior art keywords
- slab
- underground space
- underground
- construction method
- main
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、建築物を構築するための地下工事に際して
の、地下空間側面部の支持を行う本設スラブの構築工法
に関するものである。TECHNICAL FIELD The present invention relates to a method for constructing a permanent slab that supports a side surface portion of an underground space during an underground construction for constructing a building.
〔従来の技術〕 従来、建築物を構築するために地面を掘下げて形成さ
れた地下空間では、この地下空間の側面に配設された矢
板などに腹起こしを横方向に渡し、この腹起こしに切り
粱を連結するようにして、地下空間周囲の土圧を支えて
おり、この腹起こし、切り粱を多く配置した地下空間
で、さらに掘り下げを行ったり基礎工事などの地下工事
を行っている。[Prior Art] Conventionally, in an underground space formed by digging down the ground to construct a building, the abdomen is laterally passed to a sheet pile or the like arranged on the side surface of the underground space to raise the abdomen. The soil pressure around the underground space is supported by connecting the cut soil, and in this underground space where a lot of cut soil is placed, which is angry, further underground work such as digging and foundation work is performed.
しかしながら、地下空間には上述したように腹起こし
を支えるようにして数多くの切り粱を渡していることか
ら、掘削工事や基礎工事などの地下工事における揚重作
業が制約され、大型の部材などの揚重が行えないため、
地下躯体、構工法の制約が生じるという不都合があっ
た。However, as mentioned above, since a large number of cut soil is passed to support the abdomen as described above, lifting work in underground work such as excavation work and foundation work is restricted, and large-sized members such as Because lifting is not possible,
There was an inconvenience that there were restrictions on the underground structure and construction method.
そこで本発明においては、地下空間周囲の土圧を確実
に支持し、かつ揚重作業が行い易い開口部を形成するこ
とを課題とし、地下工事における作業効率の向上を目的
とする。Therefore, in the present invention, it is an object to surely support earth pressure around the underground space and to form an opening portion in which lifting work is easily performed, and an object thereof is to improve work efficiency in underground work.
本発明は、上記した課題を考慮してなされたもので、
掘下げてなる地下空間の内周の亘って、前記地下空間に
構築する構築物の外周スパン部分にあたるスラブを先行
打ちして、土圧に抗する口型状の本設スラブを構築する
ことにより、上記課題を解消するものである。The present invention has been made in consideration of the above problems,
Over the inner circumference of the underground space to be dug down, by precedingly striking the slab that corresponds to the outer peripheral span of the structure to be built in the underground space, by constructing a mouth-shaped main slab that resists earth pressure, It solves the problem.
本発明においては、腹起こしや切り粱の代わりに口型
状の本設スラブを構築して地下空間の土圧を支持し、そ
して前記本設スラブの中央に開口部が形成されて、本設
スラブを搬入用などの構台として利用し前記開口部から
揚重作業が行われるようになる。In the present invention, a mouth-shaped main slab is constructed to support earth pressure in an underground space in place of abdominal acclimation and cuts, and an opening is formed in the center of the main slab, and the main slab is formed. The slab is used as a gantry for carrying in, and the lifting work is performed from the opening.
つぎに、本発明を第1図から第3図に示す実施例に基
づいて詳細に説明する。Next, the present invention will be described in detail based on the embodiments shown in FIGS. 1 to 3.
図中1は建物などの地下部分を構築する地下空間であ
って、矢板などの土止め壁2によって囲まれた内部を掘
下げることによって形成される。そして所定深さまで掘
下げながら、地下空間1の内周に亘る粱40、スラブ41を
有する本設スラブ4が複数本の構真柱3を支持として構
築される。In the figure, reference numeral 1 is an underground space for constructing an underground portion such as a building, which is formed by digging the inside surrounded by an earth retaining wall 2 such as a sheet pile. Then, while digging down to a predetermined depth, a main slab 4 having a slab 40 and a slab 41 extending over the inner circumference of the underground space 1 is constructed with a plurality of true columns 3 as supports.
この本設スラブ4は、地下空間1に構築する構築物の
外周スパン部分にあたるスラブを先行打ちすることによ
って設けられるもので、略口型状にして中央に開口部5
を有しているとともに、地下空間1の周囲の土圧Aを受
け止めて支持するように設けられている。そして最上位
の1階の本設スラブ4を構築した後、順次地面を掘下げ
ながら下階の本設スラブ4を構築していく。The main slab 4 is provided by precedingly striking the slab corresponding to the outer peripheral span of the structure to be built in the underground space 1.
It is provided so as to receive and support earth pressure A around the underground space 1. After constructing the first-floor permanent slab 4 on the highest floor, the lower-floor permanent slab 4 is constructed by sequentially digging down the ground.
地下空間1の掘削が終了し最下位の本設スラブが構築
されることによって、第2図に示すように、複数の本設
スラブ4が地下空間1の周囲の土圧を支持し、この地下
空間1の中央には、従来の切り粱などの支持部分が存在
しない上記開口部5からなるオープンスペースBが形成
されるようになる。By excavating the underground space 1 and constructing the lowest permanent slab, a plurality of permanent slabs 4 support earth pressure around the underground space 1 as shown in FIG. At the center of the space 1, there is formed an open space B formed of the above-mentioned opening 5 in which a conventional supporting portion such as cut rice cake does not exist.
こののち最上位の本設スラブ4などを搬入用の構台と
して利用し、大型の部材、機器などをオープンスペース
Bにて揚重して地下工事を行うようにする。After that, the uppermost permanent slab 4 and the like are used as a gantry for loading, and large members and equipment are hoisted in the open space B to perform underground construction.
また地下空間1における外壁部も耐震要素として働く
ようになることから、第3図に示すように、本設スラブ
4をフラットスラブとすることも可能である。特に周囲
の土圧が大きいことからスラブ厚を大としなければなら
ないが、このフラットスラブとすることによって粱型を
省略でき、逆にこのフラットスラブである本設スラブ4
を粱として使用できるため、より経済的なものとなる。Further, since the outer wall portion in the underground space 1 also works as a seismic element, the main slab 4 can be a flat slab as shown in FIG. Since the earth pressure around the slab is particularly large, it is necessary to make the slab thick. However, by using this flat slab, the flat shape can be omitted, and conversely, the main slab 4 which is this flat slab.
Can be used as a gruel, which makes it more economical.
なお、上記オープンスペースBにおいては、地上と同
様の構工法が選択できる。In the open space B, the construction method similar to that on the ground can be selected.
〔発明の効果) 以上説明したように、本発明によると、掘下げてなる
地下空間の内周に亘って、前記地下空間に構築する構築
物の外周スパン部分にあたるスラブを先行打ちして、土
圧に抗する口型状の本設スラブを構築するので、地下空
間の中央部分にオープンスペースができ、よって前記本
設スラブを搬入用などの構台として利用し、中央部分か
ら大型の部材、機器を揚重することができ、腹起こし、
切り粱、乗り入れ構台などの仮設費が大幅に削減できる
ようになる。このため切り粱など制限されることなく地
下工事において各種の手法が採用でき、効率の良い作業
が行えるようになる。(Effects of the Invention) As described above, according to the present invention, the slab corresponding to the outer peripheral span portion of the structure constructed in the underground space is preliminarily striking over the inner circumference of the underground space to be dug, and the earth pressure is increased. Since a mouth-shaped main slab that resists construction is constructed, an open space is created in the central part of the underground space, so the main slab can be used as a gantry for carrying in, and large parts and equipment can be lifted from the central part. Can be overweight, angry,
It will be possible to significantly reduce temporary costs such as cuts and boarding gantry. For this reason, various methods can be adopted for underground construction without being restricted by cutting and polishing, and efficient work can be performed.
また本設スラブをフラットスラブとすれば、型枠作業
を減らすことができ、コストダウンや施工性が向上し、
土を型枠とすることも可能となる。そしてスラブ全体が
土圧を受ける粱となり、土圧による曲げに対してきわめ
て有効であるなど、実用性にすぐれた効果を奏するもの
である。Also, if the main slab is a flat slab, it is possible to reduce the work of formwork, reduce costs and improve workability,
It is also possible to use soil as a formwork. Then, the entire slab becomes a soil that receives earth pressure, and it is extremely effective against bending due to earth pressure, and it has excellent practical effects.
第1図は本発明に係る地下空間における本設スラブの構
築工法の一実施例を示す説明図、第2図は本設スラブを
階層状に配した状態を示す説明図、第3図は本設スラブ
の他の例を示す説明図である。 1……地下空間 3……構真柱 4……本設スラブ 5……開口部 A……土圧 B……オープンスペースFIG. 1 is an explanatory view showing an embodiment of a method for constructing a permanent slab in an underground space according to the present invention, FIG. 2 is an explanatory diagram showing a state in which the permanent slabs are arranged in layers, and FIG. 3 is a book. It is explanatory drawing which shows the other example of an installation slab. 1 …… Underground space 3 …… Structured pillar 4 …… Main slab 5 …… Opening A …… Soil pressure B …… Open space
───────────────────────────────────────────────────── フロントページの続き (72)発明者 山田 利行 東京都中央区京橋2丁目16番1号 清水建 設株式会社内 (72)発明者 福士 昭治 東京都中央区京橋2丁目16番1号 清水建 設株式会社内 (72)発明者 正藤 倫宏 東京都中央区京橋2丁目16番1号 清水建 設株式会社内 (72)発明者 山本 和伸 東京都中央区京橋2丁目16番1号 清水建 設株式会社内 (72)発明者 戸沢 正美 東京都中央区京橋2丁目16番1号 清水建 設株式会社内 ─────────────────────────────────────────────────── ─── Continued Front Page (72) Inventor Toshiyuki Yamada 2-16-1 Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Shoji Fukushi 2-16-1 Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Norihiro Shoto 2-16-1 Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Kazunobu Yamamoto 2-16-1 Kyobashi, Chuo-ku, Tokyo Ken Shimizu (72) Inventor Masami Tozawa 2-16-1, Kyobashi, Chuo-ku, Tokyo Shimizu Ken Co., Ltd.
Claims (2)
記地下空間に構築する構築物の外周スパン部分にあたる
スラブを先行打ちして、土圧に抗する口型状の本設スラ
ブを構築することを特徴とする地下空間における本設ス
ラブの構築工法。1. A mouth-shaped permanent slab that resists earth pressure is constructed by preliminarily striking the slab that corresponds to the outer peripheral span of the structure constructed in the underground space over the inner circumference of the underground space dug down. A construction method of a permanent slab in an underground space characterized by:
である請求項1に記載の地下空間における本設スラブの
構築工法。2. The method for constructing a main slab in an underground space according to claim 1, wherein the mouth-shaped main slab is a flat slab.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2076470A JPH089868B2 (en) | 1990-03-26 | 1990-03-26 | Construction method of main slab in underground space |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2076470A JPH089868B2 (en) | 1990-03-26 | 1990-03-26 | Construction method of main slab in underground space |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH03275816A JPH03275816A (en) | 1991-12-06 |
| JPH089868B2 true JPH089868B2 (en) | 1996-01-31 |
Family
ID=13606061
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2076470A Expired - Fee Related JPH089868B2 (en) | 1990-03-26 | 1990-03-26 | Construction method of main slab in underground space |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH089868B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4787010B2 (en) * | 2005-12-05 | 2011-10-05 | 株式会社竹中工務店 | Mechanical parking lot on the basement floor |
| JP2010001701A (en) * | 2008-06-23 | 2010-01-07 | Shimizu Corp | Method of constructing underground structure |
| JP5811389B2 (en) * | 2010-11-17 | 2015-11-11 | 清水建設株式会社 | Construction method for underground structures |
| JP2015025292A (en) * | 2013-07-26 | 2015-02-05 | 株式会社大林組 | Building construction method and building |
| JP2019173453A (en) * | 2018-03-29 | 2019-10-10 | 三井住友建設株式会社 | Construction method of building |
-
1990
- 1990-03-26 JP JP2076470A patent/JPH089868B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH03275816A (en) | 1991-12-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2009167660A (en) | Tower crane foundation structure and method of constructing the same | |
| US4648752A (en) | Marine template retaining wall and method of construction | |
| CN115030186A (en) | Foundation pit supporting construction method for multi-layer basement requiring dismantling of existing foundation pit diaphragm wall | |
| KR101262357B1 (en) | Inclined Earth Retaining Structure Method | |
| JP3724320B2 (en) | Construction method for underground structures | |
| JPH03158525A (en) | High horizontal load bearing foundation practice using solidification method | |
| JPH089868B2 (en) | Construction method of main slab in underground space | |
| JPH04155018A (en) | Foundation structure of building | |
| JPH10168915A (en) | Ground excavation method in deadline sheet pile | |
| JP2000129696A (en) | Pile foundation method and pile foundation constructed by the method | |
| JP3648651B2 (en) | Construction method of base-isolated building by the reverse driving method | |
| JPH0381422A (en) | Caisson method | |
| JPS59150810A (en) | Coastal structure with caisson and its construction | |
| JP2819008B2 (en) | Existing building seismic isolation method | |
| JP7726606B2 (en) | Ground excavation method | |
| JP2583830B2 (en) | Construction method of concrete deep foundation pile | |
| JPH0960311A (en) | Lift-up dismantling method | |
| JP4879582B2 (en) | How to extend the basement floor under the foundation of an existing building | |
| JPH06173278A (en) | Basic structure of building structure | |
| JP2673902B2 (en) | Construction method of underground structure | |
| JP2766889B2 (en) | Underground floor construction method for buildings | |
| JPH0730564B2 (en) | Construction method of underground structure | |
| JP3785089B2 (en) | Construction method of residential ground | |
| JP2634101B2 (en) | Building construction method and equipment | |
| JPH0759813B2 (en) | Underground construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |