Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP2552750B2 - Basic construction method for housing - Google Patents
[go: Go Back, main page]

JP2552750B2 - Basic construction method for housing - Google Patents

Basic construction method for housing

Info

Publication number
JP2552750B2
JP2552750B2 JP2089654A JP8965490A JP2552750B2 JP 2552750 B2 JP2552750 B2 JP 2552750B2 JP 2089654 A JP2089654 A JP 2089654A JP 8965490 A JP8965490 A JP 8965490A JP 2552750 B2 JP2552750 B2 JP 2552750B2
Authority
JP
Japan
Prior art keywords
foundation
building
members
work
house
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2089654A
Other languages
Japanese (ja)
Other versions
JPH03287917A (en
Inventor
明 岸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP2089654A priority Critical patent/JP2552750B2/en
Publication of JPH03287917A publication Critical patent/JPH03287917A/en
Application granted granted Critical
Publication of JP2552750B2 publication Critical patent/JP2552750B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、住宅のコンクリート製基礎を施工する方法
に係り、ユニット住宅の基礎や、鉄骨軸組みを含めた在
来工法による住宅の基礎を利用できるものである。
The present invention relates to a method for constructing a concrete foundation of a house, and relates to a foundation of a unit house and a foundation of a conventional house including a steel frame structure. It is available.

〔背景技術〕[Background technology]

複数の住宅ユニットを組み合わせることにより建てら
れるユニット住宅や、鉄骨軸組みを含めた在来工法によ
る住宅では、従来において、建設現場の捨てコンクリー
トの上に基礎を作り、この基礎の完成後、基礎の上に建
てられる建物の建築作業が始められていた。すなわち、
従来では、基礎を作る作業が終了した後に基礎の上の建
物の建築作業が行われていた。
In the case of a unit house constructed by combining a plurality of housing units or a house constructed by a conventional method including a steel frame structure, conventionally, a foundation is constructed on abandoned concrete at a construction site, and after this foundation is completed, The construction work of the building to be built above had been started. That is,
Conventionally, construction work of a building on the foundation was performed after the work of forming the foundation was completed.

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

このような従来技術によると、基礎が完成した後でな
ければ建物の建築作業を始めることができないため、そ
れだけ住宅の施工期間を長くなるという問題があった。
According to such a conventional technique, the construction work of the building can be started only after the foundation is completed, so that there is a problem that the construction period of the house is extended accordingly.

特に、ユニット住宅は、工場で予め生産された住宅ユ
ニットを使用するユニット工法で建てられ、工業化率の
向上、建設現場作業割合の低下を図ることにより建設現
場作業期間を短縮することを主要目的としており、基礎
の完成後でなければ基礎より上の建物の建築作業を始め
ることができないことは、基礎施工作業期間分だけ建設
現場での住宅の施工期間が長くなるため、ユニット住宅
の上記主要目的を基礎施工作業のため十分に達成できな
いことになる。
In particular, the unit housing is built by the unit construction method that uses the housing units pre-produced in the factory, and the main purpose is to shorten the construction site work period by improving the industrialization rate and reducing the construction site work ratio. However, the fact that the construction work of a building above the foundation cannot be started until after the completion of the foundation means that the construction period of the house on the construction site will be extended by the period of the foundation construction work. Will not be fully achieved due to the basic construction work.

本発明の目的な、基礎施工作業中に基礎より上の建物
の建築作業を行え、このため建設現場での住宅の施工期
間を短縮できるようになる住宅の基礎施工方法を提供す
るところにある。
It is an object of the present invention to provide a method of constructing a foundation of a house, which enables construction work of a building above the foundation to be performed during the foundation construction work and therefore can shorten the construction period of the house on the construction site.

〔課題を解決するための手段〕[Means for solving the problem]

本発明に係る基礎施工方法は、基礎用の骨組みを基礎
支持地盤の上の複数個所に立設された支柱部材と、これ
らの支柱部材を連結する直線部材とを含んで組み立て、
この骨組みの外側に基礎成形用の型枠を配置し、前記基
礎の上に建てられかつ柱の位置が前記支柱部材の位置と
一致している建物の建築作業をこの建物の重量を前記骨
組みで支持しながらこの骨組みの上で始めるとともに、
前記型枠内にコンクリートスラリーを打設し、このスラ
リーの養生と前記建築作業とを同時進行させることを特
徴とするものである。
The foundation construction method according to the present invention assembles a framework for a foundation including a column member standing upright at a plurality of places on the foundation support ground, and a linear member connecting these column members,
A formwork for forming a foundation is arranged on the outside of this frame, and the construction work of a building built on the foundation and the positions of columns of which correspond to the positions of the pillar members is performed by the weight of the building with the frame. While supporting and starting on this skeleton,
It is characterized in that a concrete slurry is poured into the formwork, and the curing of the slurry and the construction work are carried out simultaneously.

前記型枠内のスラリーを打設する作業は前記建物の建
築作業開始後に行ってもよいが、この建築作業開始前に
行ってもよい。
The operation of placing the slurry in the formwork may be performed after the construction work of the building is started, or may be performed before the construction work is started.

〔作用〕[Action]

本発明では、基礎用の骨組みが基礎支持地盤の上に立
設されて組み立てられたならば、基礎より上の建物の建
築作業がこの骨組みで建物重量の支持を行いながら開始
され、型枠内に打設されたコンクリートスラリーは建物
の建築作業と同時進行で養生、凝固し、コンクリートス
ラリーの凝固を待って建物の建築作業を始める必要がな
いため、建設現場における作業期間が短縮される。
According to the present invention, if the framework for the foundation is erected on the foundation supporting ground and assembled, the construction work of the building above the foundation is started while supporting the weight of the building by this framework, and The concrete slurry poured into the building is cured and solidified simultaneously with the construction work of the building, and it is not necessary to wait for the solidification of the concrete slurry to start the construction work of the building, so the work period at the construction site is shortened.

また、本発明では、基礎用の骨組みは基礎支持地盤の
上の複数個所に立設された支柱部材と、これらの支柱部
材を連結する直線部材とを含んで組み立てられ、建物の
柱の位置が支柱部材の位置と一致して基礎の上の建物の
建築作業が行われるため、コンクリートスラリーの凝固
前であっても、建物の重量をこれらの支柱部材で有効に
支持しながら建築作業を行える。さらに、コンクリート
スラリーは支柱部材と直線部材の外側に配置された型枠
内に打設されるため、スラリーの凝固で出来上がる基礎
を布基礎とすることができる。
Further, in the present invention, the framework for the foundation is assembled by including the pillar members erected at a plurality of places on the foundation supporting ground and the linear members connecting these pillar members, and the position of the pillar of the building is Since the construction work of the building on the foundation is performed in conformity with the positions of the pillar members, the construction work can be performed while the weight of the building is effectively supported by these pillar members even before the solidification of the concrete slurry. Further, since the concrete slurry is placed in the mold arranged outside the support members and the linear members, the foundation completed by solidifying the slurry can be used as the cloth foundation.

〔実施例〕〔Example〕

以下に本発明の一実施例を添付図面に基づいて説明す
る。
An embodiment of the present invention will be described below with reference to the accompanying drawings.

第1図は本実施例が適用された住宅1の全体概略図を
示し、この図では住宅1の基礎2は基礎用の骨組み3だ
けが示されている。本実施例に係る住宅1は基礎2の上
に建てられる建物4が複数の住宅ユニット5で形成され
たユニット住宅となっており、第14図はこの住宅ユニッ
ト5の骨組み6を示す。骨組み6は四隅の4本の柱7の
上端間、下端間を各4本の上梁8、下梁9で結合するこ
とにより構成され、骨組み6には工場で壁材や床材等が
取り付けられ、このように工場で予め生産された複数の
住宅ユニット5が建設現場で第15図の通り前後、左右、
上下に組み合わされることにより、ユニット住宅1の基
礎2より上の建物4がユニット工法で建てられる。
FIG. 1 shows an overall schematic view of a house 1 to which this embodiment is applied, and in this figure, a foundation 2 of the house 1 shows only a framework 3 for the foundation. The house 1 according to this embodiment is a unit house in which a building 4 built on a foundation 2 is formed by a plurality of housing units 5, and FIG. 14 shows a frame 6 of the housing unit 5. The skeleton 6 is configured by connecting the upper ends and the lower ends of the four columns 7 at the four corners with four upper beams 8 and lower beams 9, respectively. As shown in FIG. 15, the plurality of housing units 5 pre-produced in the factory are front, rear, left and right at the construction site.
By being combined vertically, the building 4 above the foundation 2 of the unit housing 1 is built by the unit construction method.

第1図において、基礎2用の骨組み3は、直線部材10
と、第1〜第4の4種類の支柱部材11〜14とで構成され
ている。直線部材10は住宅ユニット5の骨組み6を構成
している前記下梁9の下側に配置され、第1支柱部材11
は住宅ユニット5の骨組み6の柱7が複数本寄せ集まっ
ていない下側、すなわち本実施例では1本の柱7だけが
ある建物4の出隅みコーナ部分の下側に配置され、第2
支柱部材12および第3支柱部材13は柱7を2本寄せ集ま
っている部分の下側、すなわち2個の住宅ユニット5が
前後または左右に隣り合っている部分の下側に配置さ
れ、第4支柱部材14は柱7は4本寄せ集まっている部分
の下側、すなわち4個の住宅ユニット5が前後または左
右に隣り合っている部分の下側に配置される。このよう
に第1〜第4支柱部材11〜14は建物4の柱7の位置と一
致した位置に配置されるものとなっている。
In FIG. 1, the framework 3 for the foundation 2 is a linear member 10
And four column members 11 to 14 of the first to fourth types. The linear member 10 is arranged below the lower beam 9 that constitutes the frame 6 of the housing unit 5, and the first pillar member 11 is provided.
Is arranged on the lower side where the plurality of columns 7 of the frame 6 of the housing unit 5 are not gathered together, that is, on the lower side of the corner portion of the building 4 where there is only one column 7 in the present embodiment.
The pillar member 12 and the third pillar member 13 are arranged below the portion where the two pillars 7 are gathered together, that is, below the portion where the two housing units 5 are adjacent to each other in the front-rear direction or the left-right direction. The pillar member 14 is disposed below the portion where the four pillars 7 are gathered together, that is, below the portion where the four housing units 5 are adjacent to each other in the front-rear direction or the left-right direction. As described above, the first to fourth support members 11 to 14 are arranged at positions corresponding to the positions of the pillars 7 of the building 4.

第2図は直線部材10を示す。直線部材10は、上下の水
平材15,16が棒材を波型に屈曲させた連結材17で連結さ
れたものとなっている。下水平材16には水平材15,16と
直角方向に延びる複数の脚材18が結合され、これらの脚
材18の両方の端部には下向きのレベル調整ボルト19と上
向きの板状フック20とが設けられ、フック20は基礎用の
型枠を係止するためのものである。上水平材15には脚材
18と同じ方向に延びる複数のブラケット21が結合され、
これらのブラケット21の両方の端部には型枠連結ボルト
22が横向きに設けられている。また上水平材15には複数
の住宅ユニット連結ボルト23が上向きに突設されてい
る。
FIG. 2 shows the linear member 10. In the linear member 10, upper and lower horizontal members 15 and 16 are connected by a connecting member 17 in which a bar member is bent in a wave shape. A plurality of leg members 18 extending in a direction perpendicular to the horizontal members 15 and 16 are connected to the lower horizontal member 16, and both end portions of these leg members 18 have downward level adjusting bolts 19 and upward plate hooks 20. Are provided, and the hook 20 is for locking the foundation formwork. Upper horizontal material 15 is leg material
A plurality of brackets 21 extending in the same direction as 18 are joined,
Formwork connecting bolts on both ends of these brackets 21
22 is provided sideways. A plurality of housing unit connecting bolts 23 are provided on the upper horizontal member 15 so as to project upward.

第3図は第1支柱部材11を示す。この支柱部材11は、
柱24の上端、下端に各2本の上下のアーム材25,26が直
角をなして結合されたものとなっている。下アーム材26
には前記レベル調整ボルト19およびフック20付きの脚材
18が設けられているとともに、上アーム材25には前記型
枠連結ボルト22付きのブラケット21が設けられている。
柱24の頂部には前記住宅ユニット連結ボルト23が1本上
向きに突設されている。
FIG. 3 shows the first strut member 11. This support member 11 is
Two upper and lower arm members 25 and 26 are connected to the upper and lower ends of the column 24 at right angles. Lower arm material 26
Is a leg material with the level adjustment bolt 19 and hook 20 mentioned above.
18 is provided, and the upper arm member 25 is provided with a bracket 21 having the formwork connecting bolt 22.
At the top of the pillar 24, one housing unit connecting bolt 23 is provided so as to project upward.

第4図は第2支柱部材12を示す。この支柱部材12は、
柱27の上端、下端に各1本の上下のアーム材28,29の中
央部が結合されたものとなっており、下アーム材29には
前記レベル調整ボルト19およびフック20付きの脚材18が
設けられているとともに、上アーム材28には前記型枠連
結ボルト22付きのブラケット21が設けられている。また
上アーム材28には2本の前記住宅ユニット連結ボルト23
が柱27の両側において上向きに突設されている。
FIG. 4 shows the second support member 12. This support member 12 is
The upper and lower ends of the pillar 27 are connected to the central portions of upper and lower arm members 28 and 29, and the lower arm member 29 has the leg members 18 with the level adjusting bolt 19 and the hook 20. And the upper arm member 28 is provided with a bracket 21 with the formwork connecting bolt 22. In addition, the upper arm member 28 is provided with the two housing unit connecting bolts 23
Are projected upward on both sides of the pillar 27.

第5図は第3支柱部材13を示す。この支柱部材13は、
柱30の上端、下端に長短の上アーム材31,32、下アーム
材33,34を設けたものとなっており、長寸法の上アーム
材31、下アーム材33の中央部が柱30の上端、下端に結合
されているとともに、短寸法の上アーム材32、下アーム
材34がアーム材31,33と直角をなして柱30の上端、下端
に結合されている。下アーム材33,34には前記レベル調
整ボルト19およびフック20付きの脚材18が設けられ、上
アーム材31,32には前記型枠連結ボルト22付きのブラケ
ット21が設けられる。また上アーム材31には2本の前記
住宅ユニット連結ボルト23が柱30の両側において上向き
に突設されている。
FIG. 5 shows the third support member 13. This support member 13
The upper and lower ends of the pillar 30 are provided with long and short upper arm members 31, 32 and lower arm members 33, 34, and the central portions of the long-sized upper arm member 31 and lower arm member 33 are the pillar 30. The upper arm member 32 and the lower arm member 34, which are short in size, are joined to the upper end and the lower end, and are joined to the upper end and the lower end of the column 30 at right angles to the arm members 31 and 33. The lower arm members 33 and 34 are provided with the level adjusting bolt 19 and the leg member 18 with the hook 20, and the upper arm members 31 and 32 are provided with the bracket 21 with the formwork connecting bolt 22. Further, the two housing unit connecting bolts 23 are provided on the upper arm member 31 so as to project upward on both sides of the column 30.

第6図は第4支柱部材14を示す。この支柱部材14は、
柱35の上端、下端に各1本の上下のアーム材36,37の中
央部が結合されたものとなっており、下アーム材37には
前記レベル調整ボルト19およびフック20付きの脚材18が
設けられているとともに、上アーム材36には前記型枠連
結ボルト22付きのブラケット21が設けられている。また
上アーム材36の中央部にはリブ38やプレート39による補
強部40が設けられ、この補強部40に4本の前記住宅ユニ
ット連結ボルト23が上向きに突設されている。
FIG. 6 shows the fourth support member 14. This pillar member 14 is
The upper and lower ends of the pillar 35 are connected to the central portions of the upper and lower arm members 36 and 37, and the lower arm member 37 has the leg members 18 with the level adjusting bolt 19 and the hook 20. The upper arm member 36 is provided with a bracket 21 having the formwork connecting bolt 22. Further, a reinforcing portion 40 formed by a rib 38 and a plate 39 is provided in the central portion of the upper arm member 36, and the four housing unit connecting bolts 23 project upward from the reinforcing portion 40.

以上説明した直線部材10の上下水平材15,16と、第1
〜第4支柱部材11〜14の上下アーム材25,26,28,29,31〜
34,36,37とは、第2図で示したボルト41、ナット42締め
される板状の連結部材43を介して連結されるようになっ
ており、このため連結部材43にボルト41の挿通用の孔44
が設けられているとともに、上下水平材15,16の端部
と、上下アーム材25,26,28,29,31〜34,36,37の端部とに
も、ボルト41の挿通用の孔45が設けられている。
The upper and lower horizontal members 15, 16 of the linear member 10 described above, and the first
~ Upper and lower arm members 25, 26, 28, 29, 31 of the fourth support member 11 ~ 14 ~
34, 36 and 37 are connected via the plate-like connecting member 43 which is fastened with the bolt 41 and the nut 42 shown in FIG. Universal hole 44
Is provided, and the holes for inserting the bolts 41 are also formed in the ends of the upper and lower horizontal members 15 and 16 and the ends of the upper and lower arm members 25, 26, 28, 29, 31 to 34, 36, 37. 45 are provided.

第7図〜第9図は前記基礎2の成形用型枠を示す。 7 to 9 show a molding frame of the foundation 2.

第7図で示した型枠46,47は直線部材10の両側、第2
支柱部材12の両側および第4支柱部材14の両側に配置さ
れる型枠であり、このためこれらの型枠46,47は平面直
線状である。これらの型枠46,47は直線部材10や支柱部
材12,14の長さに応じた各種の長さ寸法に形成される。
第8図で示した型枠48,49は第1支柱部材11の両側に配
置され、このため型枠48は大型の平面L字型となってお
り、型枠49は小型の平面L字型となっている。第9図で
示した型枠50〜52は第3支柱部材13の両側に配置され、
型枠50は平面直線状であり、型枠51,52は小型の平面L
字型である。なお、以上の型枠46〜52のうち、型枠46と
47、および型枠49と51と52はそれぞれ共通化できる。
The forms 46 and 47 shown in FIG.
The molds are arranged on both sides of the strut member 12 and on both sides of the fourth strut member 14, and therefore, these molds 46, 47 are in a plane straight shape. These molds 46 and 47 are formed in various lengths according to the lengths of the linear member 10 and the pillar members 12 and 14.
The forms 48 and 49 shown in FIG. 8 are arranged on both sides of the first support member 11, so that the form 48 is a large plane L-shape, and the form 49 is a small plane L-shape. Has become. The molds 50 to 52 shown in FIG. 9 are arranged on both sides of the third support member 13,
The formwork 50 has a linear shape on a plane, and the formwork 51 and 52 are small planes L.
It is a letter shape. In addition, among the above-mentioned molds 46 to 52,
47, and the forms 49, 51 and 52 can be made common.

以上の型枠46〜52の下部には前記フック20が挿入可能
な長孔53が形成され、またそれぞれの上部内面には前記
型枠連結ボルト22が螺合可能なナット54が設けられてい
る。全ての型枠46〜52は上から下に延びるに伴って直線
部材10や第1〜第4支柱部材11〜14から離れる方向、す
なわち基礎2の幅方向外向きに滑らかに湾曲しながら延
びる円弧状断面を有している。またこれらの型枠46〜52
は例えばステンレス板やガラス繊維入りプラスチック
板、さらにはガラス繊維入りコンクリート板等によって
作られ、その表面は彩色されたり模様が表示されていて
もよい。
Long holes 53 into which the hooks 20 can be inserted are formed in the lower portions of the above molds 46 to 52, and nuts 54 into which the above mold frame connecting bolts 22 can be screwed are provided on the inner surfaces of the respective upper parts. . A circle extending smoothly while curving outward in the width direction of the foundation 2 in a direction away from the linear member 10 and the first to fourth support members 11 to 14 as all of the molds 46 to 52 extend downward. It has an arcuate cross section. Also these formwork 46-52
Is made of, for example, a stainless steel plate, a plastic plate containing glass fibers, or a concrete plate containing glass fibers, and the surface thereof may be colored or a pattern may be displayed.

次に基礎2の施工方法について説明する。 Next, the construction method of the foundation 2 will be described.

第10図の通り建設現場の根切り底には捨てコンクリー
ト55が設けられ、基礎支持地盤であるこの捨てコンクリ
ート55上の各所定位置(建物4の柱7の位置と一致した
位置)に第1〜第4支柱部材11〜14を第1図の通り立設
し、これらの支柱部材11〜14をレベル調整ボルト19の回
転操作で正確に垂直とさせるとともに、それぞれの高さ
を揃える。次いで支柱部材11〜14のそれぞれの間に直線
部材10を配置し、直線部材10の高さをレベル調整ボルト
19の回転操作で支柱部材11〜14と一致させながら、これ
らの支柱部材11〜14と直線部材10とを前記連結部材43で
連結する。
As shown in Fig. 10, a waste concrete 55 is provided at the root cutting bottom of the construction site, and the first concrete is placed at each predetermined position (the position corresponding to the position of the pillar 7 of the building 4) on the waste concrete 55 which is the foundation supporting ground. The fourth strut members 11 to 14 are erected as shown in FIG. 1, and the strut members 11 to 14 are accurately made vertical by the rotation operation of the level adjusting bolts 19 and the heights thereof are aligned. Next, the linear member 10 is arranged between each of the column members 11 to 14, and the height of the linear member 10 is adjusted by the level adjusting bolt.
The supporting members 11 to 14 and the linear member 10 are connected by the connecting member 43 while being aligned with the supporting members 11 to 14 by the rotation operation of 19.

これにより支柱部材11〜14は直線部材10を介して連結
されることになり、基礎2の前記骨組み3が直線部材10
と支柱部材11〜14とにより組み立てられたことになる。
As a result, the pillar members 11 to 14 are connected to each other through the linear member 10, and the frame 3 of the foundation 2 is connected to the linear member 10 by the linear member 10.
And the pillar members 11 to 14 are assembled.

この後、直線部材10の両側および支柱部材11〜14の両
側に型枠46〜52を配置し、基礎2の骨組み3の全体を型
枠で囲む。型枠46〜52の配置は、直線部材10の両側の型
枠46,47について示している第10図の通り、型枠46〜52
の下部に設けられた長孔53に直線部材10および支柱部材
11〜14に設けられたフック20を挿入して行い、また直線
部材10および支柱部材11〜14に設けられた型枠連結ボル
ト22を回転操作し、このボルト22を型枠46〜52に設けら
れた前記ナット54に螺合する。
After that, the molds 46 to 52 are arranged on both sides of the linear member 10 and both sides of the support members 11 to 14, and the entire frame 3 of the foundation 2 is surrounded by the molds. The layout of the molds 46 to 52 is as shown in FIG. 10 showing the molds 46 and 47 on both sides of the linear member 10, as shown in FIG.
The linear member 10 and the support member are provided in the long hole 53 provided at the bottom of the
The hooks 20 provided on 11 to 14 are inserted, and the formwork connecting bolts 22 provided on the linear member 10 and the strut members 11 to 14 are rotated to provide the bolts 22 on the formwork 46 to 52. The nut 54 is screwed.

これにより型枠46〜52はフック20の係止作用とボルト
22の連結作用とで基礎2の骨組み3に取り付けられるこ
とになり、骨組み3は型枠取付部材ともなる。
As a result, the molds 46 to 52 are locked by the hooks 20 and bolts.
It is attached to the skeleton 3 of the foundation 2 by the connecting action of 22, and the skeleton 3 also serves as a form fitting member.

以上のように骨組み3の外側に型枠46〜52が配置され
ることにより、型枠46〜52の内部にはコンクリートスラ
リーを打設するためのスラリー打設空間Sが形成される
ことになる。この空間Sは、第10図の通り、型枠46〜52
の前述した湾曲形状に基づいて上部から下部へ幅が連続
的に広がる末広がり形状となっている。
By arranging the molds 46 to 52 on the outside of the frame 3 as described above, the slurry pouring space S for pouring the concrete slurry is formed inside the molds 46 to 52. . This space S, as shown in FIG.
Based on the above-mentioned curved shape, the width is widened continuously from the upper part to the lower part.

以上の作業後、建設現場の根切り作業で生じた土56を
埋め戻す作業を行い、この埋め戻しは少なくとも前記フ
ック20を超える高さまで行う。
After the above work, a work for backfilling the soil 56 generated by the root cutting work at the construction site is performed, and this backfill is performed at least to a height exceeding the hook 20.

次いで、基礎2の骨組み3の上に前記建物4を建てる
建築作業を始める。具体的には、前記住宅ユニット5の
うち一階を形成する住宅ユニット5をクレーンで基礎2
の骨組み3の上に載せ、基礎2の骨組み3と住宅ユニッ
ト5の前記骨組み6とを連結するとともに、一階用住宅
ユニット5相互の骨組み6を互いに結合する。基礎2の
骨組み3と住宅ユニット5の骨組み6とを連結する作業
は、直線部材10と第1支柱部材11の部分を示している第
10図、第11図の通り、直線部材10および支柱部材11〜14
に設けられている前記住宅ユニット連結ボルト23を使用
して行われる。すなわち、住宅ユニット5の骨組み6を
構成している前記下梁9と前記柱7の底板7Aとに設けら
れた孔にボルト23を挿入し、これらのボルト23に螺合さ
れたレベル調整ナット57に下梁9、底板7Aが当接するま
で住宅ユニット5を降ろし、ナット57の回転操作で住宅
ユニット5の高さを所定高さとした後、ボルト23にロッ
クナット58を螺合することにより基礎2の骨組み3と住
宅ユニット5の骨組み6とを連結する。なお、第11図の
通り、柱7にはロックナット58の締め付け作業を行なえ
るようにするための開口部59が設けられている。
Then, the construction work for building the building 4 on the frame 3 of the foundation 2 is started. Specifically, the housing unit 5 forming the first floor of the housing units 5 is mounted on a foundation 2 by a crane.
The frame 3 of the base 2 and the frame 6 of the housing unit 5 are connected to each other, and the frames 6 of the first-floor housing units 5 are connected to each other. The work of connecting the skeleton 3 of the foundation 2 and the skeleton 6 of the housing unit 5 shows the parts of the linear member 10 and the first strut member 11.
As shown in FIGS. 10 and 11, the linear member 10 and the column members 11 to 14
Is performed using the housing unit connecting bolt 23 provided in the. That is, the bolts 23 are inserted into the holes provided in the lower beam 9 and the bottom plate 7A of the pillar 7 which form the framework 6 of the housing unit 5, and the level adjusting nut 57 screwed into the bolts 23 is inserted. The housing unit 5 is lowered until the lower beam 9 and the bottom plate 7A come into contact with each other, the housing 57 is rotated by a nut 57 to set the height of the housing unit 5 to a predetermined height, and then the lock nut 58 is screwed into the bolt 23 so that the foundation 2 The frame 3 and the frame 6 of the housing unit 5 are connected. As shown in FIG. 11, the column 7 is provided with an opening 59 for tightening the lock nut 58.

このように基礎2の骨組み3によって基礎2より上
の建物4の重量を支持しながらこの建物4の建築作業を
始めた後、前記スラリー打設空間Sにコンクリートスラ
リーを打設する作業を始める。このスラリー打設作業は
空間Sの上部開口部から行い、前記下梁9の脇からコン
クリートスラリーを打設する。コンクリートスラリーを
空間Sに容易に打設できるようにするため、一階用住宅
ユニット5の床部分にスラリー注入孔を設けてもよい。
After the construction work of the building 4 is started while supporting the weight of the building 4 above the foundation 2 by the frame 3 of the foundation 2 as described above, the work of placing concrete slurry in the slurry placing space S is started. This slurry pouring work is performed from the upper opening of the space S, and concrete slurry is poured from the side of the lower beam 9. In order to easily pour the concrete slurry into the space S, a slurry injection hole may be provided in the floor portion of the first-floor housing unit 5.

なお、空間Sにコンクリートスラリーを打設した後
に、基礎2の骨組み3の上に一階用住宅ユニット5を載
せ、前述した通り基礎2の骨組み3と住宅ユニット5の
骨組み6とを連結するようにしてもよい。すなわち、ス
ラリー打設作業後に建物4の建築作業を始めてもよい。
After placing the concrete slurry in the space S, the first-floor housing unit 5 is placed on the skeleton 3 of the foundation 2 and the skeleton 3 of the foundation 2 and the skeleton 6 of the housing unit 5 are connected to each other as described above. You may That is, the construction work of the building 4 may be started after the slurry casting work.

空間Sに打設されたコンクリートスラリーは、空間S
が上部から下部へと幅が広がる末広がり状であるため、
空間S内を滑らかに流下し、型枠内の全部に確実に充填
される。また、ユニット住宅1の基礎2は、第1図に示
されている通り、直線的な中通り60が設けられた平面目
の字のような単純な形状となっているため、コンクリー
トスラリーを空間Sに打設する作業を数少ない箇所から
行っても、空間Sの全部にコンクリートスラリーを確実
に行き渡らせることができる。
The concrete slurry cast in the space S is
Is a flared shape that widens from the top to the bottom,
It smoothly flows down in the space S and is surely filled in the entire mold. In addition, as shown in FIG. 1, the foundation 2 of the unit house 1 has a simple shape like a square with a straight middle street 60. Even if the work of placing in S is performed from a few places, the concrete slurry can be reliably spread over the entire space S.

本実施例では、以上のように空間Sにコンクリートス
ラリーが打設された後も基礎2の上で建物4を建てる建
築作業が続けられる。この建築作業は、例えば一階用住
宅ユニット5の上に二階用住宅ユニット5を載せて結合
する作業、さらにはそれぞれの住宅ユニット5内部の仕
上げ作業等である。このため、本実施例では、空間S内
におけるコンクリートスラリーの養生と建物4の建築作
業とが同時進行して行われることになり、コンクリート
スラリーが凝固するまで基礎2の骨組み3が建物4の重
量を支持し、建物4の建築作業が終了した頃にはコンク
リートスラリーは凝固して基礎2が出来上がる。
In this embodiment, the construction work for constructing the building 4 on the foundation 2 is continued even after the concrete slurry is poured into the space S as described above. This construction work is, for example, a work of mounting the second-floor housing unit 5 on the first-floor housing unit 5 and coupling the same, and further a finishing work of the inside of each housing unit 5. Therefore, in this embodiment, the curing of the concrete slurry in the space S and the construction work of the building 4 are simultaneously performed, and the skeleton 3 of the foundation 2 is the weight of the building 4 until the concrete slurry is solidified. The concrete slurry is solidified and the foundation 2 is completed by the time the construction work of the building 4 is completed.

特に、本実施例では、基礎2より上の建物4の柱7が
基礎2の骨組み3の構成部材である支柱部材11〜14の上
に配置され、これらの支柱部材11〜14は基礎支持地盤で
ある捨てコンクリート55上に立設されているため、コン
クリートスラリー打設空間Sに打設されたコンクリート
スラリーが凝固する全に建物4の建築作業を始めても、
柱7に作用する建物4の重量は支柱部材11〜14、捨てコ
ンクリート55で確実に支持されることになり、このた
め、スラリーの養生と建物4の建築作業を同時進行させ
ることができる。また、支柱部材11〜14は直線部材10で
連結され、これらの支柱部材11〜14と直線部材10の外側
に配置された型枠46〜52内のコンクリートスラリー打設
空間Sにコンクリートスラリーが打設されるため、スラ
リーの凝固で出来上がる基礎2を一般の建物で必要とさ
れる布基礎とすることができる。
Particularly, in this embodiment, the pillars 7 of the building 4 above the foundation 2 are arranged on the pillar members 11 to 14 which are the constituent members of the frame 3 of the foundation 2, and these pillar members 11 to 14 are the foundation supporting ground. Since it is erected on the discarded concrete 55 that is, even if the construction work of the building 4 is started until the concrete slurry cast in the concrete slurry casting space S solidifies,
The weight of the building 4 acting on the pillars 7 is surely supported by the pillar members 11 to 14 and the discarded concrete 55, so that the curing of the slurry and the construction work of the building 4 can be performed simultaneously. Further, the pillar members 11 to 14 are connected by the linear member 10, and the concrete slurry is poured into the concrete slurry placement space S in the form members 46 to 52 arranged outside the pillar members 11 to 14 and the linear member 10. Since it is installed, the foundation 2 completed by the solidification of the slurry can be a cloth foundation required in a general building.

第12図はコンクリートスラリーが凝固した後を示し、
コンクリートスラリーが凝固しても前記型枠46〜52はそ
のまま残される。すなわち、本実施例では、型枠46〜52
は基礎2の表面材としてそのまま使用され、基礎2の外
観性向上に役建つ。また、コンクリートスラリーの凝固
によって出来上がった基礎2は、第12図に示されている
ように、幅方向の断面が上部から下部へ連続的な末広が
りとなったものとなっており、基礎2の上に建てられた
建物4の重量を確実に支持できる大きな底面積を有す
る。また基礎2の骨組み3と、住宅ユニット5の骨組み
6すなわち基礎2の上に建てられた建物4の骨組みと
は、連結金具である前記住宅ユニット連結ボルト23を介
して強固に連結されている。
Figure 12 shows after the concrete slurry has solidified,
Even if the concrete slurry is solidified, the molds 46 to 52 are left as they are. That is, in this embodiment, the molds 46 to 52 are
Is used as it is as the surface material of the foundation 2, and helps improve the appearance of the foundation 2. In addition, as shown in FIG. 12, the foundation 2 completed by solidifying the concrete slurry has a cross-section in the width direction that continuously spreads from the upper part to the lower part. It has a large bottom area that can reliably support the weight of the building 4 built in. The skeleton 3 of the foundation 2 and the skeleton 6 of the housing unit 5, that is, the skeleton of the building 4 built on the foundation 2 are firmly connected to each other via the housing unit connecting bolt 23 which is a connecting fitting.

以上説明したように本実施例によれば、空間Sに打設
されたコンクリートスラリーの養生と基礎2の上に建物
4を建てる建築作業とを同時進行させ、基礎2が完成す
るのを待って建物4の建築作業を始める必要がないた
め、建設現場作業期間を基礎2の施工期間分だけ従来よ
りも短縮できる。特に、この効果は、工場で多くの作業
を終了してしまって建設現場作業期間を短縮することを
主要目的としているユニット住宅の場合に、顕著に発揮
される。
As described above, according to the present embodiment, the curing of the concrete slurry cast in the space S and the construction work for constructing the building 4 on the foundation 2 are simultaneously progressed, and the foundation 2 is completed. Since it is not necessary to start the construction work of the building 4, the construction site work period can be shortened by the construction period of the foundation 2 as compared with the conventional case. In particular, this effect is remarkably exhibited in the case of a unit house whose main purpose is to finish a lot of work in a factory and shorten a construction site work period.

また、完成する基礎2の幅方向の断面は上部から下部
へ連続的な末広がりとなっており、このように大きな底
面積を有する末広がり基礎2を空間Sにコンクリートス
ラリーを1回打設するだけで作ることができ、大きな底
面積を有する幅広のフーチング部とこのフーチング部の
上の立上部とからなる従来の基礎のように、初めにフー
チング部成形用コンクリートスラリーの打設作業を行
い、このスラリーの凝固後、その上に立上部成形用コン
クリートスラリーの打設作業を行うという2段階の作業
工程を行う必要がなくなり、このため基礎施工作業を簡
単化できる。
In addition, the cross-section in the width direction of the completed foundation 2 has a continuous divergence from the upper part to the lower part, and the divergent divergence base 2 having such a large bottom area can be poured into the space S only once with the concrete slurry. Like the conventional foundation consisting of a wide footing part that can be made and has a large bottom area and a rising part above this footing part, first, a concrete slurry for forming the footing part is placed, and this slurry is After the solidification of No. 2, it is not necessary to perform a two-step work process of placing a concrete slurry for forming a rising part on the solidified work, and therefore the foundation construction work can be simplified.

さらに、基礎2内の骨組み3と、基礎2の上に建てら
れた建物4の骨組みとは、連結金具である住宅ユニット
連結ボルト23を介して直接的に連結されているため、基
礎2と建物4との連結強度は極めて大きくなり、住宅1
が例えば台風通過地域に建てられる住宅であっても、住
宅1に作用する大きな荷重を基礎2に確実に伝達して基
礎2で受けることができるようになる。また、内部にコ
ンクリートスラリーが打設されるスラリー打設空間Sを
形成する型枠46〜52は、コンクリートスラリーの凝固後
もそのまま残されて基礎2の表面材として使用されるた
め、基礎2の完成後に型枠46〜52を取り外す作業を行う
必要がなく、このためその分だけ建設現場作業が少なく
なり、作業の容易化を達成できる。さらに、型枠46〜52
は基礎2の骨組み3に取り付けられ、骨組み3は型枠46
〜52の取付部材を兼ねているため、型枠46〜52を自立等
させるための特別の型枠取付部材を用意する必要がな
く、それだけ必要な部材点数を少なくできる。
Further, since the frame 3 in the foundation 2 and the frame of the building 4 built on the foundation 2 are directly connected to each other via the housing unit connecting bolt 23, which is a connecting fitting, the foundation 2 and the building 2 are connected. The connection strength with 4 becomes extremely large, and housing 1
However, even in a house built in a typhoon passage area, for example, a large load acting on the house 1 can be reliably transmitted to the foundation 2 and received by the foundation 2. Further, the molds 46 to 52 that form the slurry casting space S in which the concrete slurry is cast are left as they are after the solidification of the concrete slurry and are used as the surface material of the foundation 2. It is not necessary to remove the formwork 46 to 52 after completion, and therefore the work on the construction site is correspondingly reduced and the work can be facilitated. In addition, formwork 46-52
Is attached to the framework 3 of the foundation 2 and the framework 3 is a formwork 46
Since it also serves as a mounting member for the molds 52 to 52, it is not necessary to prepare a special mold mounting member for making the molds 46 to 52 self-supporting, and the number of necessary members can be reduced accordingly.

なお、末広がり基礎は第12図に示されているように幅
方向の両方の側面が上部から下部へと幅方向外向きに延
びるものでもよいが、他の末広がり形状とすることもで
き、例えば第13図の末広がり基礎2′としてもよい。こ
の基礎2′は住宅の外側に面する一方の側面が垂直面
で、他方の側面が湾曲面となっている。また、基礎の幅
方向断面を台形とし、側面を直線的な面としてもよい。
Note that the end flared foundation may be one in which both side faces in the width direction extend outward in the width direction from the upper part to the lower part as shown in FIG. 12, but may have other end flared shapes, for example, It may be the base 2'of the end of Fig. 13. In this foundation 2 ', one side surface facing the outside of the house is a vertical surface and the other side surface is a curved surface. Further, the cross section in the width direction of the foundation may be trapezoidal and the side surfaces may be linear surfaces.

また、本発明はユニット住宅に限定されるものではな
く、在来工法で建てられる住宅にも適用でき、この住宅
には鉄骨軸組みの住宅も含まれる。
Further, the present invention is not limited to a unit house, but can be applied to a house built by a conventional method, and this house also includes a steel frame house.

〔発明の効果〕〔The invention's effect〕

本発明によれば、建設現場での基礎施工作業中に基礎
より上の建物の建築作業を行なえるようになり、この結
果、住宅の施工期間を全体的に短縮できるようになり、
これにより住宅のコストの低減をも達成できるようにな
る。
According to the present invention, it becomes possible to perform the construction work of the building above the foundation during the foundation construction work at the construction site, and as a result, the construction period of the house can be shortened overall,
As a result, the cost of the house can be reduced.

【図面の簡単な説明】[Brief description of drawings]

第1図は基礎の骨組みを示した住宅の全体概略図、第2
図は基礎の骨組みを構成する直線部材を示す斜視図、第
3図、第4図、第5図、第6図は基礎の骨組みを構成す
る支柱部材を示す斜視図、第7図、第8図、第9図は基
礎成形用型枠を示す斜視図、第10図、第11図は基礎の骨
組みと建物の骨組みとの連結を示す図、第12図は完成し
た基礎を示す断面図、第13図は別実施例に係る基礎を示
す断面図、第14図はユニット住宅の構成要素である住宅
ユニットの骨組みを示す斜視図、第15図はユニット住宅
の全体を示す概略図である。 1……ユニット住宅、2,2′……基礎、3……骨組み、
4……建物、5……住宅ユニット、6……骨組み、10…
…直線部材、11〜14……支柱部材、19……レベル調整ボ
ルト、20……フック、22……型枠連結ボルト、23……連
結金具である住宅ユニット連結ボルト、46〜52……型
枠、S……スラリー打設空間。
Fig. 1 is an overall schematic view of the house showing the basic framework, 2
The figures are perspective views showing a linear member constituting the frame of the foundation, FIGS. 3, 4, 5, and 6 are perspective views showing the column members constituting the frame of the foundation, FIG. 7, FIG. Fig. 9 is a perspective view showing a base forming form, Fig. 10 and Fig. 11 are diagrams showing a connection between a framework of a foundation and a framework of a building, and Fig. 12 is a sectional view showing a completed foundation. FIG. 13 is a cross-sectional view showing a foundation according to another embodiment, FIG. 14 is a perspective view showing a framework of a housing unit which is a constituent element of a unit housing, and FIG. 15 is a schematic view showing an entire unit housing. 1 ... Unit housing, 2,2 '... Basic, 3 ... Framework,
4 ... Building, 5 ... Housing unit, 6 ... Frame, 10 ...
… Straight line members, 11 ~ 14 …… Staff members, 19 …… Level adjustment bolts, 20 …… Hooks, 22 …… Form frame connecting bolts, 23 …… Connecting bracket housing unit connecting bolts, 46 ~ 52 …… Type Frame, S ... Slurry casting space.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】基礎用の骨組みを基礎支持地盤の上の複数
個所に立設された支柱部材と、これらの支柱部材を連結
する直線部材とを含んで組み立て、この骨組みの外側に
基礎成形用の型枠を配置し、前記基礎の上に建てられか
つ柱の位置が前記支柱部材の位置と一致している建物の
建築作業をこの建物の重量を前記骨組みで支持しながら
この骨組みの上で始めるとともに、前記型枠内にコンク
リートスラリーを打設し、このスラリーの養生と前記建
築作業とを同時進行させることを特徴とする住宅の基礎
施工方法。
1. A base skeleton is assembled by including strut members which are erected at a plurality of locations on a foundation support ground and linear members which connect these strut members. The construction work of a building in which the formwork of the above is placed, and the position of the pillars is the same as the position of the pillar members, is built on the foundation while supporting the weight of the building with the frameworks. A method of constructing a basic structure of a house, which is characterized by placing concrete slurry in the formwork, and simultaneously curing the slurry and proceeding with the building work.
JP2089654A 1990-04-03 1990-04-03 Basic construction method for housing Expired - Lifetime JP2552750B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2089654A JP2552750B2 (en) 1990-04-03 1990-04-03 Basic construction method for housing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2089654A JP2552750B2 (en) 1990-04-03 1990-04-03 Basic construction method for housing

Publications (2)

Publication Number Publication Date
JPH03287917A JPH03287917A (en) 1991-12-18
JP2552750B2 true JP2552750B2 (en) 1996-11-13

Family

ID=13976748

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2089654A Expired - Lifetime JP2552750B2 (en) 1990-04-03 1990-04-03 Basic construction method for housing

Country Status (1)

Country Link
JP (1) JP2552750B2 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH601389A5 (en) * 1975-07-04 1978-07-14 Ciba Geigy Ag
JPH0512357Y2 (en) * 1987-09-17 1993-03-30

Also Published As

Publication number Publication date
JPH03287917A (en) 1991-12-18

Similar Documents

Publication Publication Date Title
JP2677144B2 (en) Construction method for column-beam joints
JPH05287901A (en) Construction of stairs
JP2552750B2 (en) Basic construction method for housing
JP3453895B2 (en) How to install anchor bolts on large steel frames
JP2554382B2 (en) Dwelling
JPH0881918A (en) Pipe and construction method thereof
JP2000160687A (en) Construction method of mixed structure and precast concrete column
JP2860501B2 (en) Concrete foundation
JPH03287920A (en) Foundation-forming formwork for housing
JP3519467B2 (en) Construction method of basement and integrated foundation
JP3245824B2 (en) Column and beam joint structure of RC structure and its construction method
JPS6347244Y2 (en)
JP2780055B2 (en) Construction method of reinforced concrete building
JPH09256631A (en) Construction method of reinforced concrete wall
JPH03279533A (en) Constructing method for rigid-frame type rc super-high building
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPH0427015A (en) Foundation of housing
JPH0674590B2 (en) Block for building legal framework and method for building legal framework
JPH03287918A (en) Foundation of housing
JP2724891B2 (en) Construction method of pillar half PCa formwork
JPH026901B2 (en)
JP2745238B2 (en) Temporary support for slab half PCa board erection
JP2723418B2 (en) Formwork for foundation construction
JP2530053B2 (en) Building foundation construction method
JP2722121B2 (en) Construction method of reinforced concrete building