JP2791201B2 - Construction work schedule management system - Google Patents
Construction work schedule management systemInfo
- Publication number
- JP2791201B2 JP2791201B2 JP23290390A JP23290390A JP2791201B2 JP 2791201 B2 JP2791201 B2 JP 2791201B2 JP 23290390 A JP23290390 A JP 23290390A JP 23290390 A JP23290390 A JP 23290390A JP 2791201 B2 JP2791201 B2 JP 2791201B2
- Authority
- JP
- Japan
- Prior art keywords
- work
- data
- construction
- section
- input
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title description 47
- 238000000034 method Methods 0.000 claims description 141
- 238000007726 management method Methods 0.000 description 22
- 239000000725 suspension Substances 0.000 description 17
- 238000010586 diagram Methods 0.000 description 13
- 238000007639 printing Methods 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 2
- 239000004035 construction material Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000001934 delay Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000003203 everyday effect Effects 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は建設工事工程計画管理装置に係り、特に多工
区分割工法を採用した建設工事に有効な建設工事工程計
画管理装置に関する。Description: BACKGROUND OF THE INVENTION The present invention relates to a construction work process plan management device, and more particularly to a construction work process plan management device effective for construction work employing a multi-division division method.
建設工事では作業員の不足、建設資材を発注してから
仕上がるまでの期間の増大等が深刻な問題となってお
り、これらは工程遅延の原因となっている。また、一方
で工期短縮の要求も高まっており、この要求を満たすた
めに本出願人は多工区分割工法を提案している。In construction work, a shortage of workers and an increase in the period from the ordering of construction materials to finishing are serious problems, which cause delays in the process. On the other hand, the demand for shortening the construction period is also increasing, and in order to satisfy this demand, the present applicant has proposed a multi-zone division method.
この多工区分割工法は建設物の1フロアを多数の工区
(例えば3工区以上)に分割し、各工区に1職種1作業
を割当てると共に各々の工区の作業を並行して行わせて
工事を進めていく工法である。この工法では工事期間内
における1日毎の作業員、建設資材、建設機械等の資源
を平均化することが容易であり、資源を有効利用するこ
とができる。例えば、従来は作業日毎の必要作業員数は
大きく変動し、作業日によって作業員が不足したり余っ
たりしていた。しかし、多工区分割工法を採用すれば作
業日毎の必要作業員数を平均化できるので確保すべき作
業員数を少なくできる。また、作業員は作業期間中、同
一の作業を繰り返し行うため作業に対して習熟し、建設
物の品質も向上する。In this multi-division division method, one floor of a construction is divided into a number of divisions (for example, three or more divisions), one work is assigned to each division, and work in each division is performed in parallel. It is a construction method. With this construction method, it is easy to average resources such as workers, construction materials, construction machines and the like every day during the construction period, and the resources can be used effectively. For example, conventionally, the required number of workers for each work day fluctuates greatly, and the number of workers is insufficient or surplus depending on the work day. However, if the multi-zone division method is adopted, the required number of workers for each work day can be averaged, so that the number of workers to be secured can be reduced. In addition, since the worker repeatedly performs the same work during the work period, the worker becomes proficient in the work and the quality of the construction is improved.
しかしながら、建設工事を行う場合は各工区毎の作業
日程を表す工程表を参照して行っているが、多工区分割
工法では多数の工区で異なる作業を並行して行うため、
各作業を行う作業員に対して作業を指示することは煩雑
な作業であり、誤った指示を与えることもあった。However, when performing construction work, we refer to the work schedule that shows the work schedule for each work section, but in the multi-works division method, different works are performed in parallel in many work sections,
Instructing a worker who performs each task to perform a task is a complicated task, and sometimes gives an incorrect instruction.
本発明は上記事実を考慮して成されたもので、各作業
員に対する作業の指示を容易に行うことができる建設工
事工程計画管理装置を得ることが目的である。The present invention has been made in view of the above-described facts, and has as its object to obtain a construction work process plan management device that can easily give a work instruction to each worker.
上記目的を達成するために本発明に係る建設工事工程
計画管理装置は、各工区に対して行う一連の作業の順序
及び作業の所要日数を表す作業データと各工区毎の作業
開始日データとを入力する入力手段と、前記作業データ
を記憶する記憶手段と、前記一連の作業の開始を前記各
工区毎の作業開始日に一致させると共に所要日数を考慮
して各工区毎の作業日程を表す工程表を作成する処理手
段と、前記工程表を表示する表示手段と、を有する建設
工事工程計画管理装置において、前記作成された工程表
に基づいて各作業毎の作業日に対応する工区を判断する
判断手段と、前記判断手段の判断結果に基づいて作業日
と工区とを対応させて表す対応表を各作業毎に編集して
出力する出力手段と、を備えたことを特徴としている。In order to achieve the above object, a construction work process plan management device according to the present invention includes: work data representing the sequence of a series of works to be performed for each work section and the number of days required for work; and work start date data for each work section. Input means for inputting, storage means for storing the work data, and a step of matching the start of the series of work with the work start date of each work section and representing a work schedule for each work section in consideration of the required number of days In a construction work process plan management device having a processing unit for preparing a table and a display unit for displaying the process table, a work section corresponding to a work day for each work is determined based on the prepared process table. It is characterized by comprising: a judging means; and an output means for editing and outputting a correspondence table indicating the correspondence between work dates and work sections for each work based on the judgment result of the judging means.
本発明では、作成された工程表に基づいて各作業毎の
作業日に対応する工区を判断し、作業日と工区とを対応
させて表す対応表を各作業毎に編集して出力する。この
ため、この対応表に基づいて作業員へ作業を指示する、
または出力された対応表を作業員へ配布して作業指示の
代わりとすることができる。従って、各作業員に対する
作業の指示を正確かつ容易に行うことができる。また、
前記のように作成された工程表に基づいて対応表を編集
して出力するので、前記対応表を出力するために新たに
データを入力する必要もない。According to the present invention, a work section corresponding to a work day for each work is determined based on the created process table, and a correspondence table representing the work day and the work section corresponding to each work is edited and output for each work. For this reason, instruct the worker to work based on this correspondence table,
Alternatively, the output correspondence table can be distributed to the worker and used as a substitute for the work instruction. Accordingly, it is possible to accurately and easily instruct each worker to perform a work. Also,
Since the correspondence table is edited and output based on the process chart created as described above, there is no need to input new data to output the correspondence table.
以下、図面を参照して本発明の実施例を詳細に説明す
る。Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
第1図に示すように、本実施例に係る建設工事工程計
画管理装置10は、パーソナルコンピユータ12と、パーソ
ナルコンピユータ12の入出力ポート20に接続される各種
の入出力機器と、から構成される。パーソナルコンピユ
ータ12は、CPU14、ROM16、RAM18及び入出力ポート20を
備え、これらは互いにバスによって接続されている。本
実施例では入出力ポート20に接続される入出力機器とし
て、フロツピーデイスク、ハードデイスク等の記憶媒体
で構成され記憶したプログラム、データが読出されると
共にデータが書込まれる外部記憶装置32と、オペレータ
がデータ等を入力するためのキーボード24及びマウス26
と、処理結果を表示するデイスプレイ28と、処理結果を
印刷するためのプリンタ30と、を用いている。As shown in FIG. 1, the construction work process plan management device 10 according to the present embodiment includes a personal computer 12, and various input / output devices connected to the input / output port 20 of the personal computer 12. . The personal computer 12 includes a CPU 14, a ROM 16, a RAM 18, and an input / output port 20, which are connected to each other by a bus. In the present embodiment, as an input / output device connected to the input / output port 20, a program stored and stored in a storage medium such as a floppy disk or a hard disk, an external storage device 32 from which data is read and data is written, Keyboard 24 and mouse 26 for the operator to input data etc.
And a display 28 for displaying the processing result, and a printer 30 for printing the processing result.
パーソナルコンピユータ12及び各入出力機器を建設工
事工程計画管理装置10として作用させるためのプログラ
ムは前記外部記憶装置32の記憶媒体に記憶されている。
このプログラムは建設工事工程計画管理装置10を構成す
る各機器に電源が投入されると読出され、実行される。A program for causing the personal computer 12 and each input / output device to operate as the construction work process plan management device 10 is stored in the storage medium of the external storage device 32.
This program is read out and executed when the power of each device constituting the construction work schedule management device 10 is turned on.
次に本実施例の作用を説明する。 Next, the operation of the present embodiment will be described.
本実施例の建設工事工程計画管理装置10は第18図のフ
ローチヤートに示すような処理を行って多工区分割工法
を採用した建設工事の工程計画、管理を支援する。ステ
ツプ100では工事全体に関係するデータ、すなわち作業
所名データ、作業名辞書データ、工事種別名データ、作
業休止日データ、階名データ、工区名データ等の共通デ
ータを入力するようオペレータに指示する。これによ
り、オペレータは前記共通データを順次入力する。すな
わち、最初にオペレータは作業所名データとして建設を
行う建物の名称等を入力する。次にオペレータは作業名
辞書を作成するための作業名辞書データを入力する。こ
の作業名辞書データとしては使用頻度の高い名称、例え
ば「柱」、「壁」等の名称を表すデータが入力され、作
業名辞書に登録される。これにより、以降の入力作業の
作業量を低減している。The construction process schedule management device 10 of this embodiment performs the process shown in the flowchart of FIG. 18 to support the process planning and management of the construction using the multi-division division method. In step 100, the operator is instructed to input common data such as work site name data, work name dictionary data, work type name data, work suspension date data, floor name data, work section name data, etc. . Thus, the operator sequentially inputs the common data. That is, first, the operator inputs the name of a building to be constructed or the like as work place name data. Next, the operator inputs work name dictionary data for creating a work name dictionary. As the work name dictionary data, data representing names frequently used, for example, names such as "pillar" and "wall" are input and registered in the work name dictionary. This reduces the amount of work for the subsequent input work.
次にオペレータは工事種別名を入力する。建設工事工
程計画管理装置10では建設工事を躯体工事、仕上工事等
の工事種別毎に分けて処理する。次に第2図に示すよう
なカレンダー40が表示され、オペレータは工事期間中の
作業休止日を入力する。この作業休止日はカレンダー40
において□で囲まれた日として表現される。次にオペレ
ータは建物の階名及び工区名を入力する。第3図に示す
ように、建設工事工程計画管理装置10では建物42を鉛直
方向に沿って複数に分割したときの各々を1つの工区と
して定義している。前記工区名は各々の工区に便宜的に
付与される名称であり、例えば、第3図に矢印Aで示す
部分を「5階のA工区」として特定することができる。
上記のように入力されたデータは共通データとして外部
記憶装置32の記憶領域内に記憶され、必要に応じて読出
される。Next, the operator inputs a construction type name. The construction work schedule management device 10 processes construction works by dividing them into work types such as frame work and finish work. Next, a calendar 40 as shown in FIG. 2 is displayed, and the operator inputs a work suspension date during the construction period. This work suspension day is calendar 40
Are represented as days enclosed by □. Next, the operator inputs the floor name and the section name of the building. As shown in FIG. 3, the construction work schedule management device 10 defines each of the buildings 42 divided into a plurality of sections along the vertical direction as one construction section. The section name is a name given for convenience to each section, and for example, a portion indicated by an arrow A in FIG. 3 can be specified as “A section on the fifth floor”.
The data input as described above is stored as common data in the storage area of the external storage device 32, and is read as needed.
ステツプ102では資源名データ、作業名データ、作業
と資源との対応を表すデータ、資源別同時作業数データ
等の工事別データを入力するようオペレータに指示す
る。これにより、オペレータは前記工事別データを順次
入力する。すなわち、最初に第4図に示すような資源名
データ入力画面44が表示され、オペレータは「鉄骨」、
「コンクリート」等の建設資材及び「大工」、「鉄筋
工」等の作業者を資源として入力する。次に第5図に示
すような作業名入力画面46が表示され、オペレータは
「墨」、「配筋」等の作業名を入力する。なお、このと
き前述の作業名辞書に登録した名称を参照して作業名を
入力することができるようになっている。In step 102, the operator is instructed to input resource-specific data such as resource name data, task name data, data representing the correspondence between tasks and resources, and data on the number of simultaneous tasks per resource. Thus, the operator sequentially inputs the work-specific data. That is, first, a resource name data input screen 44 as shown in FIG. 4 is displayed, and the operator selects “steel frame”,
Input construction resources such as "concrete" and workers such as "carpentry" and "reinforcing" as resources. Next, a work name input screen 46 as shown in FIG. 5 is displayed, and the operator inputs a work name such as "ink" or "arrangement". At this time, the work name can be input by referring to the name registered in the work name dictionary.
次に第6図に示すような作業別資源設定画面が表示さ
れ、オペレータは各作業で使用する資源の設定、すなわ
ち作業と資源との対応を表すデータを入力する。例え
ば、第6図では配筋作業においては資源として鉄筋工を
使用し、鉄骨建て作業においては資源として鉄骨及びと
び工を使用するという設定がされたことを表している。
次に第7図に示すような資源別同時作業数データ入力画
面50が表示され、オペレータは同時に使用することが可
能な資源の数を表す資源別同時作業数データを各資源毎
に入力する。この資源別同時作業数データは後述する資
源平準化処理で使用される。このようにして入力された
データは工事別データとして外部記憶装置32の記憶領域
内に記憶され、必要に応じて読出される。Next, a task-specific resource setting screen as shown in FIG. 6 is displayed, and the operator inputs data indicating the setting of resources used in each task, that is, the correspondence between tasks and resources. For example, FIG. 6 shows that a setting has been made such that a reinforcing bar is used as a resource in the rebar arrangement work, and a steel frame and a jumper are used as the resource in the steel-frame building work.
Next, a resource-specific simultaneous work number data input screen 50 as shown in FIG. 7 is displayed, and the operator inputs the resource-specific simultaneous work number data indicating the number of resources that can be used simultaneously for each resource. The data on the number of simultaneous operations per resource is used in a resource leveling process described later. The data input in this manner is stored in the storage area of the external storage device 32 as construction-specific data, and is read as needed.
ステツプ104ではサイクル工程作成処理を行う。多工
区分割工事では各工区に対して共通な一連の作業を行
う。本実施例の建設工事工程計画管理装置10ではこの共
通な一連の作業をサイクル工程として定義し、登録する
ようになっている。このサイクル工程作成処理について
第19図のフローチヤートを参照して説明すると、ステツ
プ130では第8図に示すようなサイクル工程入力画面52
を表示する。ステツプ132ではサイクル工程を構成する
作業の開始日を表す始点を入力するようオペレータへ指
示する。これによりオペレータはマウス26を操作して始
点を描画する。この始点の描画はマウス26を操作してマ
ークを始点位置へ移動させ、データの入力を表すキーを
押すことによって行われる。In step 104, a cycle process creation process is performed. In multi-division division work, a series of common operations are performed for each division. In the construction process schedule management device 10 of the present embodiment, this common series of operations is defined and registered as a cycle process. This cycle process creation processing will be described with reference to the flowchart of FIG. 19. In step 130, a cycle process input screen 52 as shown in FIG.
Is displayed. In step 132, the operator is instructed to input a starting point indicating the starting date of the work constituting the cycle process. Thus, the operator operates the mouse 26 to draw the starting point. The drawing of the starting point is performed by operating the mouse 26 to move the mark to the starting point position, and pressing a key representing data input.
ステツプ134では第9図に矢印Bで示すように、ステ
ツプ132で描画された始点からマークが示す位置までの
入力画面52上での日数を表示する。ステツプ136では作
業の終了日を表す終点を描画するようオペレータへ指示
し、終点を描画したか否か判定する。オペレータは始点
と終点との間の入力画面52上での距離が作業の所要日数
に対応するように終点の位置を定め、前記位置に終点を
描画する。終点を描画していないと判定した場合にはス
テツプ134へ戻り、終点が描画されるまでステツプ134及
びステツプ136を繰り返す。これにより、終点を描画せ
ずにマークを移動させると移動されたマークの位置に応
じた日数が表示されるので、作業日数が長い作業であっ
ても終点位置を誤って描画して作業を登録することはな
い。At step 134, as indicated by the arrow B in FIG. 9, the number of days on the input screen 52 from the starting point drawn at step 132 to the position indicated by the mark is displayed. In step 136, the operator is instructed to draw an end point representing the end date of the work, and it is determined whether or not the end point has been drawn. The operator determines the position of the end point so that the distance on the input screen 52 between the start point and the end point corresponds to the number of days required for the work, and draws the end point at the position. If it is determined that the end point is not drawn, the process returns to step 134, and steps 134 and 136 are repeated until the end point is drawn. By doing this, if you move the mark without drawing the end point, the number of days according to the position of the moved mark is displayed, so even if the work is long, the end point position is drawn by mistake and the work is registered I will not do it.
ステツプ136の判定が肯定されるとステツプ138へ移行
し、始点と終点を描画した作業の作業名を選択するよう
にオペレータに指示する。既に入力され登録された作業
名は入力画面52下方にキーボード24の図示しないフアン
クシヨンキーと対応されて表示されており、オペレータ
は作業名に対応するフアンクシヨンキーを押して作業名
を選択する。選択された作業名は入力画面上に表示され
る。なお、入力画面52に表示されたリードタイムとはコ
ンクリートの養生等の待ち時間を意味し、例えばコンク
リート打設後、28日間コンクリートを養生してから梁型
枠の解体を行う等のように作業の実施前に待ち時間を必
要とする作業をリードタイム有りの作業としている。リ
ードタイム有りの作業は入力画面の下段に描画される。
前記始点と終点とによって定まる時間が待ち時間、すな
わちリードタイムである場合には作業名とし「LTM」が
選択される。If the determination in step 136 is affirmative, the process moves to step 138, and the operator is instructed to select the work name of the work in which the start point and the end point are drawn. The already entered and registered work name is displayed below the input screen 52 in correspondence with a function key (not shown) of the keyboard 24, and the operator presses the function key corresponding to the work name to select the work name. The selected work name is displayed on the input screen. Note that the lead time displayed on the input screen 52 means the waiting time for curing of concrete and the like.For example, after placing concrete, cure concrete for 28 days and then disassemble the beam formwork. The work requiring a waiting time before the implementation of the above is defined as the work with a lead time. Work with lead time is drawn in the lower part of the input screen.
If the time determined by the start point and the end point is a waiting time, that is, a lead time, “LTM” is selected as the work name.
次のステツプ140では選択された作業名が「LTM」であ
るか否かを判定する。ステツプ140の判定が肯定された
場合には、ステツプ142の始点と終点との間を点線54を
表示してステツプ144へ移行する。また、ステツプ140の
判定が否定された場合にはステツプ142を実行せずにス
テツプ144へ移行する。以上の処理によってサイクル工
程を構成する1つの作業の作業データの入力が終了す
る。ステツプ144ではサイクル工程を構成する全ての作
業の作業データの入力が終了したか否かを判定する。ス
テツプ144の判定が否定された場合にはステツプ132へ戻
りサイクル工程を構成する一連の作業の順序に従って作
業データを順に入力し、ステツプ144の判定が肯定され
るまでステツプ132乃至ステツプ144を繰り返す。In the next step 140, it is determined whether or not the selected work name is "LTM". If the determination at step 140 is affirmative, a dotted line 54 is displayed between the start point and the end point of step 142, and the routine proceeds to step 144. If the determination at step 140 is negative, the process proceeds to step 144 without executing step 142. With the above processing, the input of the work data of one work constituting the cycle process is completed. At step 144, it is determined whether or not the input of the operation data of all operations constituting the cycle process has been completed. If the determination at step 144 is denied, the process returns to step 132 to input the work data in sequence according to the sequence of a series of operations constituting the cycle process, and repeats steps 132 to 144 until the determination at step 144 is affirmed.
ステツプ144の判定が肯定されると、ステツプ146では
第10図に示すように、サイクル工程を構成する各作業及
びリードタイムを一本化してサイクル工程を作成する。
これにより、サイクル工程は作業期間56と待ち期間58が
交互に存在する一連の作業工程となる。またこのとき、
矢印60によって示されるサイクル工程の次工程開始日を
設定する。この次工程開始日については後述する。ステ
ツプ148では作業期間56及び待ち期間58の日数を計算
し、次のステツプ150ではサイクル工程に関するデー
タ、すなわち前記各期間の日数を含めた作業データを外
部記憶装置32の記憶領域内に記憶する。以上で1つのサ
イクル工程に対する処理は終了し、ステツプ152では他
のサイクル工程の登録を行うか否を判定する。本実施例
の建設工事工程計画管理装置10では複数のサイクル工程
を記憶可能となっており、ステツプ152の判定が肯定さ
れた場合にはステツプ130へ戻って前記処理を繰り返
す。ステツプ152の判定が否定された場合にはサイクル
工程の作業処理を終了し、第18図のステツプ106へ移行
する。If the determination in step 144 is affirmative, in step 146, as shown in FIG. 10, the operations and the lead times constituting the cycle process are unified to create the cycle process.
Thus, the cycle process is a series of work processes in which the work periods 56 and the waiting periods 58 alternate. At this time,
The next process start date of the cycle process indicated by the arrow 60 is set. This next process start date will be described later. In step 148, the number of days in the working period 56 and the waiting period 58 is calculated, and in the next step 150, data relating to the cycle process, that is, working data including the number of days in each of the above periods, is stored in the storage area of the external storage device 32. Thus, the processing for one cycle step is completed, and in step 152, it is determined whether or not to register another cycle step. The construction work process plan management device 10 of this embodiment can store a plurality of cycle processes. If the determination in step 152 is affirmed, the process returns to step 130 and repeats the above process. If the determination in step 152 is negative, the work process in the cycle process ends, and the flow shifts to step 106 in FIG.
ステツプ106では作業工程を表す工程表を作成する処
理を行う。この工程表作成処理について第20図のフロー
チヤートを参照して説明すると、ステツプ160では工程
表を作成するためのデータを入力する工区を指定するよ
うオペレータに指示し、第11図に示すように、オペレー
タが指定した工区に対応する配置管理テーブル62を表示
する。ステツプ162では前記工区内の各階の工程着手順
序及び各階で作業を行うサイクル工程を識別するデータ
を入力するように指示する。これによりオペレータは前
記工程着手順序を表すデータ及び前記のサイクル工程を
表すデータを各階毎に入力する。ステツプ164では前記
工区の作業開始日データをオペレータに入力させる。In step 106, a process for creating a process chart representing the work process is performed. The process chart creation process will be described with reference to the flowchart of FIG. 20. In step 160, the operator is instructed to designate a section for inputting data for creating a process chart, and as shown in FIG. Then, the layout management table 62 corresponding to the section designated by the operator is displayed. At step 162, an instruction is given to input data for identifying the process start order of each floor in the construction section and the cycle process for performing the work on each floor. Thereby, the operator inputs the data representing the process start order and the data representing the cycle process for each floor. In step 164, the operator inputs the work start date data of the section.
次のステツプ166以降では前記入力されたデータ及び
前記作業データに基づいて、各階毎に作業の所要日数を
考慮して工程表を作成する。すなわち、ステツプ166で
は前記工程着手順序が最初である階について、該階のサ
イクル工程の開始を前記入力された作業開始日と一致さ
せると共にカレンダー40を参照し、該階の作業工程内に
作業休止日が存在するか否かを判定する。作業工程内に
作業休止日が存在すると判定された場合は、ステツプ16
8で該作業休止日は作業期間56内に存在するか否かを判
定する。例として第12図(A)に示すように、サイクル
工程の開始を作業開始日である8月3日と一致させた場
合に作業期間56内に作業休止日(8月5日)が存在した
ときにはステツプ168の判定が肯定されてステツプ170へ
移行する。ステツプ170では期間内に作業休止日が存在
する作業期間について、前記作業開始日を変更すること
なく日数を作業休止日数分だけ延長する。例えば前記の
ように作業休止日である8月5日が作業期間56内である
場合には、第12図(B)に示すように期間内に作業休止
日が存在する作業期間56の日数を1日分だけ延長する。
上記ステツプ170を実行した後はステツプ172へ移行す
る。In the next step 166 and subsequent steps, a process chart is created based on the input data and the work data in consideration of the number of days required for work for each floor. That is, in step 166, for the floor whose process start order is the first, the start of the cycle process of the floor is matched with the input work start date, and the calendar 40 is referred to, and the work is suspended during the work process of the floor. Determine if the day exists. If it is determined that a work suspension date exists in the work process, step 16
At 8, it is determined whether or not the work suspension date is within the work period 56. As an example, as shown in FIG. 12 (A), when the start of the cycle process is coincident with the work start date of August 3, a work suspension date (August 5) exists in the work period 56. At times, the determination at step 168 is affirmed, and the routine proceeds to step 170. In step 170, for a work period in which a work suspension date exists in the period, the number of days is extended by the number of work suspension days without changing the work start date. For example, as described above, when August 5 which is the work suspension day is within the work period 56, the number of days in the work period 56 in which the work suspension day exists within the period as shown in FIG. Extend by one day.
After the execution of step 170, the process proceeds to step 172.
一方、ステツプ166またはステツプ168の判定が否定さ
れた場合には、ステツプ170を実行することなくステツ
プ172へ移行する。例えば第12図(C)に示すように、
待ち時間58内に作業休止日(9月9日)が存在した場
合、期間内に作業休止日が存在する待ち時間58の日数を
延長することなくステツプ172へ移行する。上記処理に
より、作業休止日が存在する作業期間は作業休止日数だ
け期間が延長されて実働日数が確保され、作業休止日が
存在する待ち期間は期間が延長されず暦日日数が確保さ
れる。On the other hand, if the determination at step 166 or 168 is negative, the process proceeds to step 172 without executing step 170. For example, as shown in FIG.
If there is a work suspension date (September 9) within the waiting time 58, the process proceeds to step 172 without extending the number of days of the waiting time 58 during which the work suspension date exists. By the above processing, the work period in which the work suspension day exists is extended by the number of work suspension days to secure the actual working days, and the waiting period in which the work suspension day exists does not extend the period, and the calendar days are secured.
ステツプ172では工区内の単一の階の作業工程に対し
ての処理が終了したか否かを判定する。ステツプ172の
判定が否定された場合にはステツプ166へ戻る。これに
より、作業期間56の延長に伴って作業期間56内に新たな
作業休止日が存在した場合についても、前述の処理が繰
り返され作業休止日が判断されて作業期間が再度延長さ
れる。At step 172, it is determined whether or not the processing for the work process on a single floor in the construction section has been completed. If the determination in step 172 is denied, the process returns to step 166. Accordingly, even when a new work suspension date exists within the work period 56 with the extension of the work period 56, the above-described processing is repeated, the work suspension date is determined, and the work period is extended again.
ステツプ172の判定が肯定された場合にはステツプ174
で工区内の全ての階の作業工程に対しての処理が終了し
たか否かを判定する。ステツプ174の判定が否定された
場合にはステツプ176で作業順序が次である階のサイク
ル工程の開始日を設定する。このサイクル工程の開始日
にはステツプ172以前のステツプで設定した作業工程の
次工程開始日を設定する。例として第13図(A)に示す
ように、工程着手順序が基礎、1階、2階、・・・であ
る場合、第13図(B)に示すように、工程着手順序が最
初である基礎のサイクル工程開始日には工区の作業開始
日である1989年3月2日が設定され、その他の階のサイ
クル工程開始日には着手順序が前の階る作業工程の次工
程開始日(矢印60で図示)が設定される。ステツプ176
を実行した後はステツプ166へ戻り、設定されたサイク
ル工程開始日に基づいてステツプ166乃至ステツプ176で
前述の処理を行ない、前記ステツプ174の判定が肯定さ
れるまでステツプ166乃至ステツプ176を繰り返す。If the determination in step 172 is affirmative, step 174
It is determined whether or not the processing for the work processes on all floors in the construction section has been completed. If the determination in step 174 is negative, in step 176, the start date of the cycle process of the next floor in the work order is set. As the start date of this cycle process, the next process start date of the work process set in the step before step 172 is set. As an example, as shown in FIG. 13 (A), when the process start order is basic, first floor, second floor,..., The process start order is first as shown in FIG. 13 (B). The start date of the basic cycle process is set to March 2, 1989, which is the work start date of the construction section, and the start date of the cycle process of the other floors is the next process start date of the work process with the preceding floor (starting order). (Illustrated by arrow 60). Step 176
After executing step 166, the process returns to step 166, and the above-described processing is performed in steps 166 to 176 based on the set cycle process start date, and steps 166 to 176 are repeated until the determination in step 174 is affirmed.
ステツプ174の判定が肯定されると1つの工区に対し
ての工程表の作成処理は終了してステツプ178へ移行
し、他の工区に対しても処理を行なうか否か判定する。
ステツプ178の判定が肯定された場合にはステツプ160へ
戻り上記の処理を他の工区に対しても繰り返して行な
う。ステツプ178の判定が否定された場合には、例とし
て第14図に示すような工程表64を表示すると共に工程表
データを記憶して工程表作成処理を終了し、第18図のフ
ローチヤートのステツプ108へ移行する。このように、
サイクル工程に関するデータ、すなわち作業データを記
憶しておき各工区の作業開始日を入力することによって
工程表が作成されるので、工程表を作成するためのデー
タ量を小さくすることができ、工程計画作業を容易に行
うことができる。また、作業データに基づいて工程表が
作成されるので、工程表上の全ての作業工程に対して作
業の順序が妥当か否かをチエツクする必要もない。If the determination in step 174 is affirmative, the process of creating a process chart for one section is completed, and the process proceeds to step 178 to determine whether or not to perform processing for another section.
If the determination in step 178 is affirmative, the process returns to step 160 and the above processing is repeated for other sections. If the determination in step 178 is denied, the process chart 64 as shown in FIG. 14 is displayed as an example, the process chart data is stored, and the process chart creation process is terminated. Move on to step 108. in this way,
Since the process chart is created by storing the data related to the cycle process, that is, the work data and inputting the work start date of each work section, the amount of data for creating the process chart can be reduced, and the process plan can be reduced. Work can be performed easily. Further, since the process chart is created based on the work data, it is not necessary to check whether or not the work order is appropriate for all the work processes on the process chart.
ステツプ108では資源の平準化処理を行なう。すなわ
ち、ステツプ106で作成された工程表64に基づいて工事
期間内の各作業日に各工区で行なわれる作業の数を各作
業毎に演算する。次にステツプ102で設定された作業と
資源との対応を表すデータに基づいて、工事期間内の各
作業日に使用される各資源の数を演算する。次にステツ
プ102で入力された資源別同時作業数データに基づい
て、使用される資源の数が資源別同時作業数を超えた作
業日と資源名とを求める。次に工区または階毎に予め定
められた優先順位に基づいて、使用される資源数が資源
別同時作業数を超えないように前記優先順位の低い工区
または階の工程を変更する。さらに変更した工程に基づ
いて再度上記処理を繰り返す。これにより、工事期間内
の各作業日に使用される全ての資源の数が資源別同時作
業数を超えることがなくなり、資源が平準化される。In step 108, a resource leveling process is performed. That is, the number of works performed in each work section on each work day in the construction period is calculated for each work based on the process chart 64 created in step 106. Next, the number of resources used on each work day in the construction period is calculated based on the data indicating the correspondence between work and resources set in step 102. Next, based on the data on the number of simultaneous work per resource input in step 102, a work date and a resource name in which the number of resources used exceeds the number of simultaneous work per resource are obtained. Next, based on the priority determined in advance for each work section or floor, the process of the work section or floor having the lower priority is changed so that the number of resources used does not exceed the number of simultaneous operations per resource. The above process is repeated again based on the changed process. As a result, the number of all resources used on each work day in the construction period does not exceed the number of simultaneous work for each resource, and the resources are leveled.
次のステツプ110では3か月分の工程表を印刷する。
これによってオペレータは全体的な工程を把握すること
ができる。ステツプ112では各作業の作業日と該作業日
に作業を行う工区との対応を示す対応表、所謂作業予定
を印刷する処理を行なう。この作業予定を印刷する処理
について第21図のフローチヤートを参照して説明する
と、ステツプ190では作業予定の編集、出力方法を選択
するようオペレータに指示する。本実施例の建設工事工
程計画管理装置10では、作業予定として作業一覧表及び
作業予定リストを出力する。作業一覧表はある工区で各
作業がいつ行なわれるか、または各資源がいつ使用され
るかを工区毎に順に並べて表示した表であり、作業予定
リストはある作業日に各作業をどの工区で行なうか、ま
たは各資材をどの工区で使用するかをカレンダーと対応
させて示した表である。オペレータは作業一覧表または
作業予定リストのいずれかを選択する。In the next step 110, a process chart for three months is printed.
This allows the operator to grasp the overall process. In step 112, a process of printing a correspondence table indicating the correspondence between the work day of each work and the work section on which the work is performed, that is, a so-called work schedule is performed. The process for printing the work schedule will be described with reference to the flowchart of FIG. 21. In step 190, the operator is instructed to select a method of editing and outputting the work schedule. The construction work schedule management device 10 of this embodiment outputs a work list and a work schedule list as work schedules. The work list is a table that displays when each work is performed in a certain work section or when each resource is used in order for each work section. It is a table showing in correspondence with a calendar which is to be performed or in which section each material is used. The operator selects either the work list or the work schedule list.
ステツプ192及びステツプ194ではデータの検索条件を
設定する。すなわち、ステツプ192で第15図に示すよう
な期間設定表66を表示して、前記いずれかの表として編
集する工事期間、すなわち開始日及び終了日を指定する
ようオペレータに指示する。例えば開始日の月を期間設
定表66に表示されている月よりも後にしたい場合には、
オペレータはマウス26を操作し、開始日の月の項目近傍
の「+」が表示された部分68にマーク70の先端部分を一
致させ、入力を示すキーを押す。これによって表示され
ている月が加算されて表示され、開始日が変更される。
また、開始日の日付を表示された日付よりも前にしたい
場合には開始日の日付の項目近傍の「−」が表示された
部分72にマーク70の先端部分を一致させ、入力を示すキ
ーを押せば表示されている日付が減算されて表示され、
開始日が変更される。終了日についても上記と同様の方
法で指定する。これによりオペレータが数値を入力する
ことなく開始日及び終了日を指定できるので、操作に不
慣れなオペレータが入力を行なう場合であっても違和感
を感じることはない。In steps 192 and 194, data search conditions are set. That is, at step 192, the period setting table 66 as shown in FIG. 15 is displayed, and the operator is instructed to designate a construction period to be edited as any of the tables, that is, a start date and an end date. For example, if you want the start date month to be later than the month displayed in the period setting table 66,
The operator operates the mouse 26 to match the leading end of the mark 70 with the portion 68 where "+" is displayed near the start date month item, and presses a key indicating an input. As a result, the displayed month is added and displayed, and the start date is changed.
If the start date is desired to be earlier than the displayed date, the leading end of the mark 70 is made to coincide with the portion 72 indicated by "-" near the item of the start date, and the key indicating the input is displayed. If you press, the displayed date is subtracted and displayed,
The start date changes. The end date is specified in the same manner as above. This allows the operator to specify the start date and the end date without inputting numerical values, so that even if the operator who is unfamiliar with the operation performs the input, the user does not feel uncomfortable.
ステツプ194では第15図に示す選択表74等を表示し
て、編集、出力する作業、資源または資材をオペレータ
に指定させる。ステツプ196ではステツプ192及びステツ
プ194で指定された条件に基づいて、外部記憶装置32に
記憶された各種のデータを検索し、記憶する。この検索
に際しては前記工程表データを参照し、各作業毎の作業
日に対応する工区を判断しながら行う。このため、作業
予定の編集出力時に作業日等のデータを新たに入力する
必要はない。In step 194, the selection table 74 shown in FIG. 15 is displayed, and the operator specifies an operation to be edited and output, a resource or a material. In step 196, various data stored in the external storage device 32 are retrieved and stored based on the conditions specified in steps 192 and 194. The search is performed while referring to the process chart data and determining a work section corresponding to a work day for each work. Therefore, it is not necessary to newly input data such as a work date when editing and outputting the work schedule.
ステツプ198では選択された編集、出力方法が作業一
覧表が否かを判定する。ステツプ198の判定が肯定され
た場合は、ステツプ200で前記検索されたデータを第16
図に示すような作業日一覧表76として編集する。また、
ステツプ198の判定が否定された場合は、ステツプ200で
前記検索されたデータを第17図に示すような作業予定リ
スト78として編集する。At step 198, it is determined whether the selected editing and output method is the work list. If the determination in step 198 is affirmative, in step 200 the searched data is added to the 16th data.
The work day list 76 is edited as shown in the figure. Also,
If the determination in step 198 is negative, the data searched in step 200 is edited as a work schedule list 78 as shown in FIG.
次のステツプ204ではプリンタ30が作動させ、ステツ
プ200で編集した作業日一覧表76またはステツプ202で編
集した作業予定リスト78を印刷する。この作業日一覧表
76及び作業予定リスト78に基づいて作業員へ作業を指示
する、または印刷された作業日一覧表76及び作業予定リ
スト78を作業員へ配布して作業指示の代わりとすること
により、各作業員への作業の指示を正確にかつ容易に行
うことができる。In the next step 204, the printer 30 is operated to print the work date list 76 edited in step 200 or the work schedule list 78 edited in step 202. This work day list
Each worker can be instructed to work based on the work schedule 76 and the work schedule list 78, or the printed work day list 76 and work schedule list 78 can be distributed to the workers and replaced with the work order. Can be accurately and easily instructed.
ステツプ206では作業予定を印刷する処理を終了する
か否かを判定する。ステツプ206の判定が否定される場
合にはステツプ190へ戻り、前回と異なる編集、出力方
法または検索条件で作業予定を印刷する処理を繰り返
す。ステツプ206の判定が肯定された場合には、第18図
のステツプ114へ移行する。ステツプ114では上記処理で
設定した工程計画に変更が有るか否かを判定する。変更
がない場合にはステツプ116で工事が終了したか否か判
定する。工事が終了していない場合にはステツプ110へ
戻り、作業の進行に応じて工程表、作業予定等を出力し
て工程管理を行なう。また、作業予定の変更が発生した
場合にはステツプ114の判定が肯定され、ステツプ118へ
移行する。At step 206, it is determined whether or not to end the process of printing the work schedule. If the determination at step 206 is negative, the process returns to step 190, and the process of printing the work schedule with the editing, output method, or search condition different from the previous time is repeated. If the determination in step 206 is affirmative, the flow shifts to step 114 in FIG. At step 114, it is determined whether or not the process plan set in the above process is changed. If there is no change, it is determined in step 116 whether the construction has been completed. If the construction is not completed, the process returns to step 110, and a process chart, a work schedule, and the like are output according to the progress of the work to perform the process management. If a change in the work schedule has occurred, the determination in step 114 is affirmed, and the process proceeds to step 118.
ステツプ118では変更量が大きいか否かを判定する。
サイクル工程の変更や天候等の不測の要因による全体的
な工程の変更等の場合には、ステツプ118の判定が肯定
されてステツプ104に戻り、基本的なデータの変更を行
なう。また、各資源の同時作業数の変更等により資源の
平準化等を再度行なう場合にはステツプ118の判定が否
定され、ステツプ108へ戻って工程計画の細部を変更す
る。At step 118, it is determined whether or not the change amount is large.
In the case of a change in the cycle process or a change in the overall process due to an unexpected factor such as weather, etc., the determination in step 118 is affirmed, and the process returns to step 104 to change the basic data. If the resource leveling or the like is performed again due to a change in the number of simultaneous operations for each resource, the determination in step 118 is denied, and the process returns to step 108 to change the details of the process plan.
このように、工事中に各種の条件の変更に対しても柔
軟に工程計画を変更することができ、変更された工程計
画に基づいて工程表、作業予定等が編集、出力されるの
で工程管理を容易に行なうことができる。In this way, the process plan can be flexibly changed even when various conditions are changed during the construction, and the process schedule, work schedule, etc. are edited and output based on the changed process plan, so that the process management is performed. Can be easily performed.
なお、本実施例では建設工事工程計画管理装置10を多
工区分割工法を採用した建設工事に適用した例を示した
が、本発明は特にこれに限定されるものではなく、通常
の建設工事に適用することもできる。In the present embodiment, an example is shown in which the construction work process plan management device 10 is applied to a construction work employing a multi-section division method, but the present invention is not particularly limited to this, and is applied to a normal construction work. It can also be applied.
以上説明したように本発明では、作成された工程表に
基づいて各作業毎の作業日に対応する工区を判断し、作
業日と工区とを対応させて表す対応表を各作業毎に編集
して出力するようにしたので、各作業員に対する作業の
指示を容易に行うことができる、という優れた効果が得
られる。As described above, in the present invention, the work section corresponding to the work day for each work is determined based on the created process table, and the correspondence table representing the work day and the work section is edited for each work. Output is provided, so that an excellent effect is obtained in that it is possible to easily give a work instruction to each worker.
第1図は本実施例に係る建設工事工程計画管理装置の概
略構成図、第2図はカレンダーを示す概念図、第3図は
工区の概念を示す概念図、第4図は資源名の入力画面を
示す概略図、第5図は作業名の入力画面を示す概略図、
第6図は作業別資源設定画面を示す概略図、第7図は資
源別同時作業数の入力画面を示す概略図、第8図はサイ
クル工程入力画面を示す概略図、第9図はサイクル工程
の入力方法を説明する概略図、第10図は作成されたサイ
クル工程を説明する概略図、第11図は配置管理テーブル
を示す概略図、第12図(A)乃至(C)は作業工程内に
作業休止日が有る場合の処理を説明する概略図、第13図
(A)及び(B)は配置管理テーブルの内容と作業工程
との関係を説明する説明図、第14図は工程表を示す概略
図、第15図は作業予定を印刷するための条件入力画面を
示す概略図、第16図は作業日一覧表の例を示す図表、第
17図は作業予定リストの例を示す図表、第18図乃至第21
図は本実施例の作用を説明するフローチヤートである。 10……建設工事工程計画管理装置、 12……パーソナルコンピユータ、 24……キーボード、 26……マウス、 28……デイスプレイ、 30……プリンタ、 32……外部記憶装置。FIG. 1 is a schematic configuration diagram of a construction work process plan management device according to the present embodiment, FIG. 2 is a conceptual diagram showing a calendar, FIG. 3 is a conceptual diagram showing a concept of a work section, and FIG. Schematic diagram showing a screen, FIG. 5 is a schematic diagram showing a work name input screen,
FIG. 6 is a schematic diagram showing a resource setting screen for each work, FIG. 7 is a schematic diagram showing a screen for inputting the number of simultaneous operations per resource, FIG. 8 is a schematic diagram showing a screen for inputting a cycle process, and FIG. FIG. 10 is a schematic diagram illustrating a created cycle process, FIG. 11 is a schematic diagram illustrating an arrangement management table, and FIGS. FIG. 13A and FIG. 13B are explanatory diagrams for explaining the relationship between the contents of the arrangement management table and the work process, and FIG. FIG. 15 is a schematic diagram showing a condition input screen for printing a work schedule, FIG. 16 is a diagram showing an example of a work day list, and FIG.
FIG. 17 is a chart showing an example of the work schedule list, and FIGS. 18 to 21.
The figure is a flowchart for explaining the operation of the present embodiment. 10 …………………………………………………………………………………………………………………………………………………………………………………….
───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平2−311664(JP,A) 特開 平1−175072(JP,A) (58)調査した分野(Int.Cl.6,DB名) E04G 21/14 E04G 21/00────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-2-311664 (JP, A) JP-A-1-175072 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E04G 21/14 E04G 21/00
Claims (1)
各作業の所要日数を表す作業データと各工区毎の作業開
始日データとを入力する入力手段と、前記作業データを
記憶する記憶手段と、前記一連の作業の開始を前記各工
区毎の作業開始日に一致させると共に所要日数を考慮し
て各工区毎の作業日程を表す工程表を作成する処理手段
と、前記工程表を表示する表示手段と、を有する建設工
事工程計画管理装置において、前記作成された工程表に
基づいて各作業毎の作業日に対応する工区を判断する判
断手段と、前記判断手段の判断結果に基づいて作業日と
工区とを対応させて表す対応表を各作業毎に編集して出
力する出力手段と、を備えたことを特徴とする建設工事
工程計画管理装置。1. An input means for inputting work data representing the sequence of a series of works to be performed for each work section and the number of days required for each work, and work start date data for each work section, and storage for storing the work data. Means, processing means for matching the start of the series of work with the work start date for each of the work sections, and creating a process chart representing the work schedule for each of the work sections in consideration of the required number of days, and displaying the process chart Display means, and a judgment means for judging a work section corresponding to a work day for each work based on the created process table, based on the judgment result of the judgment means. An output means for editing and outputting a correspondence table indicating a correspondence between a work day and a work section for each work, and outputting the work table.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP23290390A JP2791201B2 (en) | 1990-09-03 | 1990-09-03 | Construction work schedule management system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP23290390A JP2791201B2 (en) | 1990-09-03 | 1990-09-03 | Construction work schedule management system |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH04115059A JPH04115059A (en) | 1992-04-15 |
| JP2791201B2 true JP2791201B2 (en) | 1998-08-27 |
Family
ID=16946648
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP23290390A Expired - Fee Related JP2791201B2 (en) | 1990-09-03 | 1990-09-03 | Construction work schedule management system |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2791201B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4647800B2 (en) * | 2001-01-30 | 2011-03-09 | 三菱重工業株式会社 | Shipbuilding production planning equipment |
-
1990
- 1990-09-03 JP JP23290390A patent/JP2791201B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH04115059A (en) | 1992-04-15 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US20250021707A1 (en) | Building structure automatic design and automatic drawing | |
| JP3772814B2 (en) | Structural design support system | |
| JP2791201B2 (en) | Construction work schedule management system | |
| JP2791200B2 (en) | Construction work schedule management system | |
| JP2791202B2 (en) | Construction work schedule management system | |
| JP3067099B2 (en) | Bar arrangement design support apparatus and method | |
| JP2791197B2 (en) | Prefabricated construction process control device | |
| JPH0953324A (en) | Device for supporting construction work | |
| JP2994827B2 (en) | Construction plan creation device | |
| JPH06248800A (en) | Stirrup design support device | |
| JP2791198B2 (en) | Prefabricated construction process control device | |
| JP3001297B2 (en) | Drawing equipment for PC parts | |
| JP2791199B2 (en) | Prefabricated construction process control device | |
| JP2000170379A (en) | Construction schedule control instrument and recording medium | |
| JP2024006095A (en) | Allocation program and allocation system | |
| JP3001295B2 (en) | Drawing equipment for PC parts | |
| JP3001296B2 (en) | Drawing equipment for PC parts | |
| JPH10205130A (en) | Finishing work schedule control device and its using method | |
| JPS63275374A (en) | Sorting instruction device for production system | |
| JPH06332909A (en) | Plan managing system | |
| JP2942457B2 (en) | Structural integration system | |
| JP3639965B2 (en) | Model wage output device | |
| JPH10198715A (en) | Base design system, and its recording medium | |
| JPH09158479A (en) | Process planning method and apparatus | |
| JPH05307553A (en) | Working information input device for construction works |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |