JP2994827B2 - Construction plan creation device - Google Patents
[go: Go Back, main page]

JP2994827B2 - Construction plan creation device - Google Patents

Construction plan creation device

Info

Publication number
JP2994827B2
JP2994827B2 JP32558791A JP32558791A JP2994827B2 JP 2994827 B2 JP2994827 B2 JP 2994827B2 JP 32558791 A JP32558791 A JP 32558791A JP 32558791 A JP32558791 A JP 32558791A JP 2994827 B2 JP2994827 B2 JP 2994827B2
Authority
JP
Japan
Prior art keywords
amount
construction
labor
construction period
plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP32558791A
Other languages
Japanese (ja)
Other versions
JPH05158945A (en
Inventor
哲夫 金岩
良和 佐々木
幸一郎 田中
洋一 湯浅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP32558791A priority Critical patent/JP2994827B2/en
Publication of JPH05158945A publication Critical patent/JPH05158945A/en
Application granted granted Critical
Publication of JP2994827B2 publication Critical patent/JP2994827B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は建設工事の工程計画作成
装置に係り、特に、大規模な建設工事の工程計画を検討
する際に用いられる建設工事の工程計画作成装置に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus for creating a process plan for a construction work, and more particularly to an apparatus for creating a process plan for a construction work used when examining a process plan for a large-scale construction work.

【0002】[0002]

【従来の技術及び発明が解決しようとする課題】建設工
事では予め定められた工事期間に建設工事を完了するこ
とが重要であるが、工事期間内における施工量及び労務
量(作業員の数)の推移は工程計画によって異なる。例
として、寒冷地の工事では冬季に稼働率が低下するが、
この冬季の稼働率の低下に伴う施工量の低下を補うため
に冬季の労務量を増加させるようにした工程計画が作成
されることがある。
2. Description of the Related Art In construction work, it is important to complete the construction work during a predetermined work period, but the amount of work and the amount of labor (number of workers) during the work period Changes depending on the process plan. As an example, in the cold district construction, the operation rate decreases in the winter season,
In order to compensate for the decrease in the amount of construction due to the decrease in the operation rate in the winter, a process plan that increases the amount of labor in the winter may be created.

【0003】しかしながら、特に遠隔地の工事では人員
計画の関係から労務量が大きく変動することは好ましく
ない。また、施工量が変動すると、これに関連して建設
資材、電力、水等の資源量も変動するが、資材の安定供
給、建設工事用の電源設備、給水設備の規模の点から資
源量もなるべく一定であることが好ましい。このよう
に、工程計画の良否は建設工事の進行等に影響を及ぼす
ので、特に大規模な建設工事において施工者は、建設物
の設計の初期段階から工事期間、労務量及び資源量の推
移を考慮して工程計画案を検討、作成し、作成した工程
計画案を建設主及び設計者に提示することが多い。
However, it is not preferable that the amount of labor greatly fluctuates particularly in construction work in remote areas due to personnel planning. In addition, when the construction volume fluctuates, the amount of resources such as construction materials, electric power, and water also fluctuates.However, the amount of resources also increases in terms of the stable supply of materials, power supply facilities for construction work, and water supply facilities. It is preferably as constant as possible. In this way, the quality of the process plan affects the progress of the construction work, etc., especially in large-scale construction work, the builder changes the work period, labor amount and resource amount from the initial stage of the design of the structure. In many cases, a process plan is considered and prepared with consideration given thereto, and the prepared process plan is often presented to a constructor and a designer.

【0004】また、建設物の設計が進行し、設計が前記
初期段階の設計から変更された場合、または例えば原子
力発電所の建設等の大規模な建設工事において、電源設
備等の他の設備の工程計画が変更された等の場合には、
工程計画を修正したり代替案を作成することが頻繁に発
生する。このような場合には、工程計画の作成を短時間
でかつ綿密に行うことが要求されるが、特に工事期間が
長く、多種多量の資源、労務を必要とする大規模な建設
工事では、工程計画を作成するための情報量が多く、工
程計画の作成は煩雑な作業であった。
[0004] Further, when the design of a building is advanced and the design is changed from the design at the above-mentioned initial stage, or in a large-scale construction work such as a construction of a nuclear power plant, for example, other equipment such as a power supply facility is installed. If the process plan has been changed,
Frequently, process plans are modified or alternatives are created. In such a case, it is required that the process plan be prepared in a short time and in a thorough manner, but especially in a large-scale construction work requiring a long period of work and a large amount of resources and labor. The amount of information for creating a plan is large, and creating a process plan is a complicated task.

【0005】また、大量の情報に基づいて作業手順を決
定するためのCPM(Critical Path Method)等の大型
計画有効手順決定方法や、PERT(Program Evaluati
on and Review Techniqe)等のネットワーク手法等を用
いて工程計画を作成することも考えられるが、上記手法
では一連の作業が予め定められた順序に従って実行され
ることが前提となっている。建設工事では各工程の工事
順序にある程度の規則はあるものの、各工程の工事期間
が重なったり重なっている期間が伸縮することを許容す
る。また複数の建設物を建設する工事においては、各建
設物をどのような順序で建設してもよい場合が多い。
[0005] A large-scale planning effective procedure determining method such as a CPM (Critical Path Method) for determining a work procedure based on a large amount of information, and a PERT (Program Evaluati).
On and Review Techniqe) may be used to create a process plan, but it is premised that a series of operations are performed in a predetermined order. In the construction work, although there are some rules for the construction order of each process, the construction period of each process is allowed to overlap or the length of the overlapping period is allowed to expand or contract. In the construction of a plurality of structures, the structures may be constructed in any order.

【0006】しかしながら、前記手法を用いて工程計画
を作成する場合には、前記手法に適合させるために新た
な規則や建設順序等を予め定める必要があり、前記手法
によって作成された工程計画が必ずしも最適な工程計画
であるとは限らない。
However, when a process plan is created by using the above method, it is necessary to determine a new rule, a construction order, and the like in advance in order to conform to the method, and the process plan created by the method is not always required. It is not always the optimal process plan.

【0007】本発明は上記事実を考慮して成されたもの
で、最適な工程計画の作成を容易に行うことができる建
設工事の工程計画作成装置を得ることが目的である。
The present invention has been made in view of the above-mentioned facts, and has as its object to provide a construction work process planning device which can easily prepare an optimal process plan.

【0008】[0008]

【課題を解決するための手段】上記目的を達成するため
に本発明に係る建設工事の工程計画作成装置は、建設工
事の各工程の工事期間、各工程毎の施工量に関連する資
源量及び単位労務量当りの施工量を含むデータ及び前記
データを補正する補正データを入力する入力手段と、前
記入力手段によって入力されたデータと工事時期に応じ
て定められた稼働率とに基づいて、各工程の工事期間が
前記入力された工事期間に一致しかつ各工程の資源量が
前記工事期間を通じて平準化されるように前記工事期間
内の労務量の推移を調整した工程計画、各工程の工事期
間が入力された工事期間に一致しかつ各工程の労務量が
前記工事期間を通じて平準化されるように前記工事期間
内の資源量の推移を調整した工程計画、及び各工程の労
務量が各工程の工事期間を通じて平準化されるように各
工程の工事期間及び前記工事期間内の資源量の推移を調
整した工程計画の少なくとも1つを作成する作成手段
と、前記作成手段によって作成された工程計画及び前記
工程計画において各工程の所定期間毎の資源量及び労務
量を積算した結果を表示する表示手段と、入力手段によ
って入力された前記補正データに基づいて前記工程計画
を修正する修正手段と、を有している。
In order to achieve the above object, a construction schedule planning apparatus according to the present invention comprises: a construction period of each construction stage; a resource amount related to a construction amount for each stage; Input means for inputting data including the amount of construction per unit labor amount and correction data for correcting the data, based on the data input by the input means and an operation rate determined according to the construction time, A process plan in which the transition of the amount of labor during the construction period is adjusted so that the construction period of the process matches the input construction period and the resource amount of each process is leveled throughout the construction period, The process plan in which the change in the resource amount during the construction period is adjusted so that the period matches the input construction period and the labor amount of each process is leveled throughout the construction period, and the labor amount of each process is Process engineering Creating means for creating at least one of the work period of each process and a process plan in which a change in the amount of resources within the work period is adjusted so as to be leveled throughout the period; and a process plan created by the creating means. Display means for displaying the result of integrating the amount of resources and the amount of labor for each predetermined period in each step in the process plan; and a correcting means for correcting the process plan based on the correction data input by the input means. doing.

【0009】[0009]

【作用】本発明において、入力手段は建設工事の各工程
の工事期間、各工程毎の施工量に関連する、例えば建設
資材、電力、水等の資源量及び単位労務量当りの施工量
を含むデータを入力する。作成手段は入力されたデータ
と工事時期に応じて定められた稼働率とに基づいて、各
工程の工事期間が入力された工事期間に一致しかつ各工
程の資源量が前記工事期間を通じて平準化されるように
前記工事期間内の労務量の推移を調整した工程計画を作
成することができる。これにより、例えばある工程にコ
ンクリート打設作業が含まれている場合には、工事期間
内で稼働率が変動しているときにも、前記工程において
施工量に関連する資源量であるコンクリート量が工事期
間を通じて平準化された工程計画が作成される。このた
め、例えば施工時の条件として資源量を大きく変動させ
ることができない建設工事に適した工程計画が得られ
る。
In the present invention, the input means includes, for example, the construction period of each step of the construction work, the amount of construction material, electric power, water and other resources and the amount of construction per unit labor related to the amount of construction for each step. Enter the data. Based on the input data and the operation rate determined according to the construction time, the creating means matches the construction period of each process with the inputted construction period and equalizes the resource amount of each process throughout the construction period. Thus, it is possible to create a process plan in which the transition of the amount of labor during the construction period is adjusted. Thereby, for example, when the concrete casting work is included in a certain process, even when the operating rate fluctuates during the construction period, the concrete amount, which is the resource amount related to the construction amount in the process, A leveled process plan is created throughout the construction period. For this reason, for example, a process plan suitable for construction work in which the amount of resources cannot be largely varied as a condition at the time of construction can be obtained.

【0010】また作成手段は、各工程の工事期間が入力
された工事期間に一致しかつ各工程の労務量が前記工事
期間を通じて平準化されるように前記工事期間内の資源
量の推移を調整した工程計画を作成することができる。
この場合には、施工時の条件として労務量を大きく変動
させることができない建設工事に好適な工程計画が得ら
れる。また、工事期間がそれ程重要でない建設工事の場
合には、各工程の労務量が各工程の工事期間を通じて平
準化されるように各工程の工事期間及び前記工事期間内
の資源量の推移を調整した工程計画を作成することもで
きる。
[0010] Further, the creating means adjusts the transition of the resource amount during the construction period so that the construction period of each process coincides with the inputted construction period and the labor amount of each process is leveled throughout the construction period. It is possible to create a completed process plan.
In this case, it is possible to obtain a process plan suitable for construction work in which the amount of labor cannot be largely changed as a condition at the time of construction. In the case of construction work where the construction period is not so important, adjust the construction period of each process and the amount of resources during the construction period so that the labor amount of each process is leveled throughout the construction period of each process. It is also possible to create a completed process plan.

【0011】作成手段によって作成された工程計画は表
示手段によって表示され、さらに前記工程計画において
各工程の所定期間毎の資源量及び労務量を積算した結果
も表示される。このため、オペレータは前記積算結果に
基づいて資源量の推移及び労務量の推移が適切か否か、
すなわち作成された工程計画が適切か否かの検討を容易
に行うことができる。上記のように工程計画の検討を行
って、例えば工程計画が適切でない等の場合には、入力
手段によって、例えばある工程の工事時期を移動させ
る、各工程の工事期間の重なっている部分を伸縮する、
複数の建設物を建設する大規模な建設工事において各建
設物の建設順序を変更する等の補正データが入力され
る。
[0011] The process plan created by the creating means is displayed by the display means, and the result of integrating the amount of resources and the amount of labor for each predetermined period of each process in the process plan is also displayed. For this reason, the operator determines whether the transition of the resource amount and the transition of the labor amount are appropriate based on the accumulation result,
That is, it is possible to easily determine whether the created process plan is appropriate. After examining the process plan as described above, if the process plan is not appropriate, for example, move the construction time of a certain process by using the input means. Do
In large-scale construction work for constructing a plurality of structures, correction data such as changing the construction order of each structure is input.

【0012】修正手段はこの補正データに基づいて工程
計画を修正する。修正された工程計画及び該工程計画に
おいて各工程の資源量及び労務量を所定期間毎に積算し
た結果は再度表示手段に表示することができるので、工
程計画の検討及び修正を繰り返し行うことができ、最適
な工程計画の作成を容易に行うことができる。
The correction means corrects the process plan based on the correction data. Since the corrected process plan and the result of integrating the resource amount and labor amount of each process in the process plan for each predetermined period can be displayed again on the display means, it is possible to repeatedly examine and correct the process plan. In addition, it is possible to easily create an optimal process plan.

【0013】[0013]

【実施例】以下、図面を参照して本発明の実施例を詳細
に説明する。なお、本発明は本実施例に記載した数値に
限定されるものではない。図1には本実施例に係る建設
工事の工程計画作成装置10が示されている。
Embodiments of the present invention will be described below in detail with reference to the drawings. Note that the present invention is not limited to the numerical values described in the present embodiment. FIG. 1 shows a construction schedule creation device 10 according to the present embodiment.

【0014】工程計画作成装置10はパーソナルコンピ
ュータ12と、パーソナルコンピュータ12の入出力ポ
ート20に接続される各種の入出力機器と、から構成さ
れる。パーソナルコンピュータ12は、CPU14、R
OM16、RAM18及び入出力ポート20を備え、こ
れらは互いにバスによって接続されている。本実施例で
は入出力ポート20に接続される入出力機器として、フ
ロッピーディスク、ハードディスク等の記録媒体で構成
され記憶したプログラム、データが読み出されると共に
データが書き込まれる外部記憶装置22と、オペレータ
がデータ等を入力するためのキーボード24及びマウス
26と、処理結果を表示するためのディスプレイ28
と、処理結果を印刷するためのレーザビームプリンタ3
0と、を用いている。なお、レーザビームプリンタ30
に代えてXYプロッタ等を用いてもよい。
The process plan creation device 10 includes a personal computer 12 and various input / output devices connected to an input / output port 20 of the personal computer 12. The personal computer 12 includes a CPU 14 and an R
An OM 16, a RAM 18, and an input / output port 20 are provided, and these are connected to each other by a bus. In the present embodiment, as an input / output device connected to the input / output port 20, an external storage device 22 constituted by a recording medium such as a floppy disk, a hard disk, and the like, from which stored data is read and data is written; And a mouse 26 for inputting data and the like, and a display 28 for displaying a processing result.
And a laser beam printer 3 for printing processing results
0 and are used. The laser beam printer 30
Instead, an XY plotter or the like may be used.

【0015】パーソナルコンピュータ12及び各入出力
機器を工程計画作成装置10として作用させるためのプ
ログラムは、前記外部記憶装置22に記憶されている。
このプログラムは工程計画作成装置10に電源が投入さ
れると読み出され、実行される。なお本工程計画作成装
置10は、例えば複数の建設物を建設するような大規模
な建設工事の工程計画を作成できるようになっている。
前記のような大規模な建設工事では複数の建設物の工程
を同時に進行させることが多い。このため、工程表上の
混乱を避け各建設物に対する工事を区別するために、本
工程計画作成装置10では1つの工程を単工程と呼び、
特定の建設物に関する単工程の集まりを1つのグループ
工程として認識するようにしている。
A program for causing the personal computer 12 and each input / output device to function as the process plan creating device 10 is stored in the external storage device 22.
This program is read and executed when the power is turned on to the process plan creation device 10. The process plan creation device 10 is capable of creating a process plan for a large-scale construction work such as constructing a plurality of structures.
In large-scale construction work as described above, it is often the case that the processes of a plurality of constructions proceed simultaneously. For this reason, in order to avoid confusion on the process schedule and distinguish works for each building, the process plan creation device 10 calls one process a single process,
A group of single processes related to a specific building is recognized as one group process.

【0016】次に本実施例の作用として、工程計画の作
成処理を図2及び図3のフローチャートを参照して説明
する。本工程計画検討装置10では複数の工程計画案を
作成、記憶し、必要に応じて任意の工程計画案を表示、
印刷できるようになっている。図2のフローチャートの
ステップ100では、ディスプレイ28に図4に示すよ
うな工程計画案の選択・入力画面40を表示し、新たに
工程計画案の作成を行うか、または既に作成された工程
計画案の修正、表示、印刷を行うかをオペレータに選択
させる。また新たに工程計画案の入力を行う場合には、
計画案の名称、工事開始年月をキーボード24を介して
入力するよう指示する。
Next, as an operation of the present embodiment, a process of creating a process plan will be described with reference to the flowcharts of FIGS. The process plan review device 10 creates and stores a plurality of process plan plans, and displays an optional process plan plan as necessary.
It can be printed. In step 100 of the flow chart of FIG. 2, a process plan selection / input screen 40 as shown in FIG. 4 is displayed on the display 28, and a new process plan is prepared or a process plan already prepared is prepared. The operator to select whether to correct, display, or print. Also, when inputting a new process plan,
The user instructs to input the name of the plan and the construction start date via the keyboard 24.

【0017】次のステップ102では今回の工程計画案
の作成が特定の建設工事に対する最初の工程計画案の作
成であるか否か判定する。ステップ102の判定が肯定
された場合には、ステップ104で前記特定の建設工事
に特有のデータ、すなわち作業所の名称、グループ工程
の名称、単工程の名称、資材の名称、職種(労務の種
類)の名称等を入力させる。例えばグループ工程の名称
を入力させる場合には、図5に示すようなグループ工程
名データ入力画面42を表示し、各建設物及びトレンチ
(建設物間の地下の配管)毎にグループ工程の名称を入
力させる。なお資材の名称としては例えば「鉄筋」、
「型枠」、「コンクリート」等が入力され、職種の名称
としては例えば「型枠大工」、「鉄筋組立工」等が入力
される。
In the next step 102, it is determined whether or not the current process plan draft is the first process schedule draft for a specific construction work. If the determination in step 102 is affirmative, in step 104, data specific to the specific construction work, that is, the name of a work place, the name of a group process, the name of a single process, the name of a material, the type of job (the type of labor) ). For example, when the name of the group process is to be input, a group process name data input screen 42 as shown in FIG. 5 is displayed, and the name of the group process is set for each building and trench (underground piping between the structures). Input. The name of the material is, for example, "rebar"
"Form", "concrete" and the like are input, and as the name of the occupation, for example, "form carpenter" and "rebar assembler" are input.

【0018】次のステップ106では、複数の工程計画
案に共通の処理条件として、ディスプレイ28への表示
を行うときのグループ工程毎の表示色の設定を行う。こ
れにより、各グループ工程に関する情報、例えば各単工
程の工事期間、資材や労務の集計結果を同時に表示した
ときに、各グループ工程を容易に識別することができ
る。また、同様に単工程名毎の表示色の設定も行う。ス
テップ106を実行した後はステップ108へ移行す
る。なお、ステップ102の判定が否定された場合には
ステップ104及びステップ106の処理を実行するこ
となくステップ108へ移行する。
In the next step 106, a display color for each group process when displaying on the display 28 is set as a processing condition common to a plurality of process plans. This makes it possible to easily identify each group process when information on each group process, for example, the total time of the construction period, material, and labor of each single process is simultaneously displayed. Similarly, the display color is set for each single process name. After executing step 106, the process proceeds to step 108. If the determination in step 102 is negative, the process proceeds to step 108 without executing the processes in steps 104 and 106.

【0019】ステップ108乃至ステップ116では工
程表の作成処理を行う。すなわち、ステップ108では
工程表を作成するグループ工程を選択する。次のステッ
プ110では図6に示すような工程表表示画面44を表
示し、選択されたグループ工程を構成する単工程毎に工
程ライン46を描画させる。この工程ライン46は始点
46Aが単工程の工事開始時期を、終点46Bが単工程
の工事終了時期を表し、始点46Aの位置と終点46B
の位置とが指定されることによって工程ライン46が描
画され、単工程の工事期間が入力される。
In steps 108 to 116, a process chart is prepared. That is, in step 108, a group process for creating a process chart is selected. In the next step 110, a process chart display screen 44 as shown in FIG. 6 is displayed, and a process line 46 is drawn for each single process constituting the selected group process. In the process line 46, the start point 46A indicates the start time of the single-step construction, the end point 46B indicates the end time of the single-step construction, and the position of the start point 46A and the end point 46B
Is designated, the process line 46 is drawn, and the construction period of a single process is input.

【0020】次のステップ112では描画した工程ライ
ン46の単工程名及び該単工程の施工量に関連する資源
量として、使用する資材の名称及び数量を入力させる。
これにより、例として図6の工程ライン46では、単工
程名として「トレンチ躯体工事」が工程ライン46の近
傍に表示され、使用する資材「型枠」、「鉄筋」、「コ
ンクリート」とその数量が表示欄48に表示される。ス
テップ114では、単一のグループ工程を構成する全て
の単工程に対して工事期間及び資材の入力が終了したか
否か判定する。ステップ114の判定が否定された場合
にはステップ110へ戻り、ステップ114の判定が肯
定されるまでステップ110乃至ステップ114の処理
を繰り返す。
In the next step 112, the name and quantity of the material to be used are input as the name of the single process of the drawn process line 46 and the resource amount related to the construction amount of the single process.
Thus, as an example, in the process line 46 of FIG. 6, “trench body construction” is displayed near the process line 46 as a single process name, and the materials “form”, “reinforcing bar”, “concrete” and their quantities are used. Is displayed in the display field 48. In step 114, it is determined whether or not the input of the construction period and the materials has been completed for all the single processes constituting the single group process. If the determination in step 114 is negative, the process returns to step 110, and the processes in steps 110 to 114 are repeated until the determination in step 114 is affirmative.

【0021】ステップ114の判定が肯定された場合に
はステップ116へ移行し、全てのグループ工程に対す
る工事期間及び資材の入力が終了したか否か判定する。
ステップ116の判定が否定された場合にはステップ1
08へ戻り、他のグループ工程を選択させて同様の処理
を繰り返す。
If the determination in step 114 is affirmative, the process proceeds to step 116, where it is determined whether the input of the construction period and the materials for all the group processes has been completed.
If the determination in step 116 is negative, step 1
Returning to step 08, another group process is selected and the same processing is repeated.

【0022】全てのグループ工程に対する工事期間及び
資材の入力処理が終了するとステップ116の判定が肯
定され、ステップ118へ移行する。ステップ118で
は図7に示すような歩掛入力画面50を表示し、歩掛り
を入力させる。歩掛りは1人または1組の作業員の1月
の作業量、すなわち単位労務量当りの施工量を表してお
り、例えば型枠大工の場合の歩掛り=10〔m2 /人・
月〕は、1人の型枠大工が1月に10m2 の型枠を製作
することを示している。また、歩掛りは各単工程毎の所
謂作業効率の違いを考慮して、各単工程毎に定められて
いる。例えば作業を行う場所が上層になると、足場が必
要になる、資材の運搬に時間がかかる、等の理由によっ
て作業効率は低下する。このため、歩掛りは例えば作業
場所が上層の工程になるに従って低い値となるように設
定される。
When the input of the construction period and the materials for all the group processes is completed, the determination in step 116 is affirmed, and the process proceeds to step 118. In step 118, a step input screen 50 as shown in FIG. 7 is displayed, and a step is input. The step represents the amount of work performed by one person or a group of workers in January, that is, the amount of work per unit of labor. For example, the step in the case of a formwork carpenter is 10 [m 2 / person ·
Moon] is one of the formwork carpenter has shown that to produce a mold of 10m 2 in January. Also, the step is determined for each single process in consideration of the so-called difference in work efficiency for each single process. For example, when the place where the work is performed becomes an upper layer, the work efficiency is reduced due to the necessity of a scaffold, a long time for transporting materials, and the like. For this reason, the walk is set so that, for example, the work place becomes lower as the work place becomes the upper layer process.

【0023】次のステップ120では図8に示すような
月別稼働係数入力画面52を表示し、工事期間内の半月
毎の月別稼働係数を入力させる。稼働係数は工事時期に
よって左右される建設工事全体の稼働率を表しており、
例えば寒冷地での建設工事の場合には冬季の稼働率は大
幅に低下する。また、雨の多い時期や休日の多い時期も
稼働率は低下することになる。これらが考慮された稼働
係数が入力される。
In the next step 120, a monthly operating coefficient input screen 52 as shown in FIG. 8 is displayed, and a monthly operating coefficient for each half month during the construction period is input. The occupancy coefficient represents the occupancy rate of the entire construction work, which depends on the construction time.
For example, in the case of construction work in a cold region, the operation rate in the winter season is greatly reduced. In addition, the occupancy rate also decreases during periods of heavy rain and holidays. An operation coefficient considering these factors is input.

【0024】ステップ122では工程計画の検討処理を
行う。この工程計画検討処理について図3のフローチャ
ートを参照して詳細に説明すると、ステップ130では
図9に示す第1の作表条件設定画面54を表示し、山積
みグラフとして集計、表示する資材、労務を選択させ
る。例えば図9では太線の枠によって囲まれた部分、す
なわち集計する資材としては「型枠」が、集計する労務
としては「型枠大工」が選択されている。
In step 122, a process plan review process is performed. This process plan study processing will be described in detail with reference to the flowchart of FIG. 3. In step 130, the first tabulation condition setting screen 54 shown in FIG. 9 is displayed, and the materials and labor to be totaled and displayed as a pile graph are displayed. Let me choose. For example, in FIG. 9, “form” is selected as the portion surrounded by the thick line frame, that is, the material to be totaled, and “formwork carpenter” is selected as the labor to be totaled.

【0025】ステップ132では、図10に示す第2の
作表条件設定画面56を表示し、ステップ130で選択
された集計する資材及び労務について、どの工程を対象
として集計するかを選択させる。集計対象選択欄58に
表示されている「グループ別選択」が選択された場合に
は、特定のグループ工程の前記資材量及び労務量を集計
対象であると判断する。また、「単工程別選択」が選択
された場合には、特定の単工程の前記資材量及び労務量
を集計対象であると判断する。さらに集計対象選択欄5
8の表示が選択されなかった場合には全ての工程の前記
資材量及び労務量を集計対象であると判断する。
In step 132, the second tabulation condition setting screen 56 shown in FIG. 10 is displayed, and the user selects which process is to be totalized for the materials and labor to be totalized selected in step 130. When “select by group” displayed in the tallying target selection column 58 is selected, it is determined that the material amount and the labor amount in the specific group process are to be tallyed. When “selection by single process” is selected, it is determined that the material amount and labor amount of a specific single process are to be counted. In addition, the calculation target selection column 5
If the display of No. 8 is not selected, it is determined that the material amounts and labor amounts of all the processes are to be counted.

【0026】ステップ134では、ステップ132で選
択された集計対象に関係する歩掛り、月別稼働係数を取
り込む。次のステップ136では集計方法が資材固定で
あるか否か判定する。集計方法は図10の集計方法選択
欄60の「労務固定」または「資材固定」のいずれかが
選択されることによって指定される。ステップ136の
判定が肯定された場合にはステップ138へ移行し、集
計対象とされた単一あるいは複数の単工程の各々につい
て、工事期間を固定とし、かつ資材量が各月で一定とな
るように割付けたときの労務量の割付けを演算する。例
えば条件を、 集計する資材 :型枠面積 集計する労務 :型枠大工 集計対象の工事期間 :3か月 上記工事期間の資材量:900 m2 歩掛り :10.00 m2 /人・月 各月の稼働係数 :0.5 1.0 1.0 とすると、 毎月の資材量(一定)=900 ÷ 3 = 300m2 第1の月の労務量 =300 ÷10.00 ÷0.5 =60人 第2の月の労務量 =300 ÷10.00 ÷1.0 =30人 第3の月の労務量 =300 ÷10.00 ÷1.0 =30人 上記のように労務量の割付けが演算される(図15
(A)及び(B)参照)。このように、「資材固定」と
すると毎月の施工量及びこれに関連する資材量が一定と
なるように各月の労務量が調整されて割付けされる。上
記例では第1の月の稼働係数が低い値とされており、こ
れを考慮して第1の月の労務量が多くなるように割付け
される。
At step 134, the step and the monthly operating coefficient related to the tallying object selected at step 132 are fetched. In the next step 136, it is determined whether or not the counting method is material fixed. The tallying method is designated by selecting either “fixed labor” or “fixed material” in the tallying method selection column 60 in FIG. If the determination in step 136 is affirmative, the process proceeds to step 138, in which the construction period is fixed and the material amount is constant in each month for each of the single or multiple single processes to be counted. The assignment of the amount of labor when assigned to is calculated. For example, the conditions, aggregate materials: mold area aggregates to labor: formwork carpenter aggregate target of the construction period: material amount of three months the construction period: 900 m 2 steps consuming: 10.00 m 2 / person-month operation of each month Coefficient: 0.5 1.0 Assuming that 1.0, the amount of material every month (constant) = 900 ÷ 3 = 300 m 2 The amount of labor in the first month = 300 ÷ 10.00 ÷ 0.5 = 60 people The amount of labor in the second month = 300 ÷ 10.00 ÷ 1.0 = 30 people Labor amount in the third month = 300 ÷ 10.00 ÷ 1.0 = 30 people The labor amount allocation is calculated as described above (FIG. 15).
(See (A) and (B)). As described above, when “material fixation” is set, the amount of labor in each month is adjusted and allocated so that the amount of construction and the amount of material related thereto each month are constant. In the above example, the operation coefficient of the first month is set to a low value, and in consideration of this, the work amount is assigned so that the amount of labor in the first month is increased.

【0027】また、ステップ136の判定が否定された
場合にはステップ140で、集計対象とされた単一ある
いは複数の単工程の各々について、工事期間を固定と
し、かつ労務量が各月で一定となるように割付けたとき
の資材量の割付けを演算する。例えば前記と同一の条件
の場合には、 毎月の労務量(一定)=900 ÷10.00 ÷(0.5+1.0+1.0
)=36人 第1の月の資材量 =36×10.00 ×0.5 = 180m2 第2の月の資材量 =36×10.00 ×1.0 = 360m2 第3の月の資材量 =36×10.00 ×1.0 = 360m2 上記のように資材量の割付けが演算される(図15
(C)及び(D)参照)。このように、「労務固定」と
すると毎月の労務量が一定となるように各月の施工量及
びこれに関連する資材量が調整されて割付けされる。上
記例では第1の月の資材量が少なくなるように割付けさ
れる。次のステップ142では、集計対象とされた全て
の単工程について割付けた資材量及び労務量を積算し、
積算結果を例として図11に示すような山積みグラフ6
2として表示する。
If the determination in step 136 is negative, in step 140, the construction period is fixed and the amount of labor is constant for each month for each of the single or multiple single processes to be counted. Calculate the allocation of the material amount when allocating so that For example, in the case of the same conditions as above, monthly labor (constant) = 900 ÷ 10.00 ÷ (0.5 + 1.0 + 1.0
) = 36 people Material amount in the first month = 36 x 10.00 x 0.5 = 180 m 2 Material amount in the second month = 36 x 10.00 x 1.0 = 360 m 2 Material amount in the third month = 36 x 10.00 x 1.0 = 360m 2 The material amount allocation is calculated as described above (see FIG. 15).
(See (C) and (D)). In this way, if the “fixed labor” is set, the amount of construction and the amount of materials related to each month are adjusted and allocated so that the amount of labor is constant every month. In the above example, the allocation is performed so that the amount of materials in the first month is reduced. In the next step 142, the amount of materials and the amount of labor allocated for all the single processes to be counted are integrated,
A pile graph 6 as shown in FIG. 11 using the integration result as an example.
Display as 2.

【0028】ステップ144では表示された山積みグラ
フ62に基づいて資材量及び労務量の推移が適切か否か
判定する。例えば「労務固定」とした場合には各月の資
材量にばらつきが生ずるが、ばらつきが極端に大きい場
合、あるいは資材量のピーク値が施工時の条件としての
資材供給の限界を超えていた等の場合には、資材量及び
労務量の推移が適切でないと判断され、単工程の工事時
期を修正する補正データが入力される。この補正データ
が入力されるとステップ144の判定が否定されてステ
ップ146へ移行し、入力された補正データに応じて単
工程の工事時期を移動させたり、単工程の重なりを伸縮
する等によって工程計画を修正する。
In step 144, based on the displayed pile graph 62, it is determined whether the transition of the material amount and the labor amount is appropriate. For example, if "fixed labor" is used, the amount of material in each month will vary, but if the variation is extremely large, or if the peak value of the amount of material exceeds the limit of material supply as a condition at the time of construction, etc. In this case, it is determined that the changes in the material amount and the labor amount are not appropriate, and correction data for correcting the construction time of the single process is input. When the correction data is input, the determination in step 144 is denied, and the process proceeds to step 146. In accordance with the input correction data, the work time of the single process is moved, or the overlap of the single processes is expanded or contracted. Modify the plan.

【0029】例として、図12(A)に示す単工程6
4、66について、図12(B)に示す資材量または労
務量の山積みグラフに注目すると、単工程66に対応す
る部分の資材量または労務量が突出している。このた
め、単工程66の工事期間は単工程66の施工量に対し
て短かすぎると判断することができる。この場合には、
例えば単工程64と単工程66の工事期間の重なりを設
けることができる(図12(C)参照)。この工事期間
が重なっている部分の長さが適切か否はオペレータが判
断する必要があるが、これによって図12(D)に示す
ように、山積みグラフの資材量または労務量がある程度
平準化される。なお、工事の工法を変更することによっ
て単工程の工事順序を変えて平準化することもできる。
As an example, a single step 6 shown in FIG.
Regarding 4 and 66, when attention is paid to the pile graph of the material amount or the labor amount shown in FIG. 12B, the material amount or the labor amount of the portion corresponding to the single process 66 is prominent. Therefore, it can be determined that the construction period of the single process 66 is too short for the construction amount of the single process 66. In this case,
For example, an overlap between the construction periods of the single process 64 and the single process 66 can be provided (see FIG. 12C). It is necessary for the operator to judge whether or not the length of the portion where the construction period overlaps is appropriate. As a result, as shown in FIG. 12D, the material amount or the labor amount of the pile graph is leveled to some extent. You. In addition, by changing the construction method of the construction, it is also possible to change the construction order of the single process and to perform the leveling.

【0030】ステップ146を実行した後はステップ1
30へ戻り、ステップ130乃至ステップ142で修正
された工程計画に基づいて再度資材量及び労務量の割付
けを演算し、割付けた資材量及び労務量を積算して山積
みグラフとして表示する。
After executing step 146, step 1
Returning to 30, the allocation of the material amount and the labor amount is calculated again based on the process plan corrected in the steps 130 to 142, and the allocated material amount and the labor amount are integrated and displayed as a pile graph.

【0031】例えば型枠面積及び型枠大工数の推移が適
切であると判断されステップ144の判定が肯定された
場合にはステップ148へ移行し、全ての資材及び労務
の推移が適切か否か判定する。ステップ148の判定が
否定された場合にはステップ130に戻り、上記と同様
にして他の資材及び労務の推移が適切であるか否か判定
し、補正データが入力された場合には推移が適切でない
と判断し、工程計画を修正する。
For example, when it is determined that the transitions of the formwork area and the formwork man-hour are appropriate and the determination of step 144 is affirmative, the process proceeds to step 148 to determine whether the transition of all the materials and labor is appropriate. judge. If the determination in step 148 is denied, the process returns to step 130 to determine whether the transition of other materials and labor is appropriate in the same manner as described above, and if the correction data is input, the transition is appropriate. Judge that it is not, and correct the process plan.

【0032】ステップ148の判定が肯定された場合に
はステップ150へ移行し、建設工事の全工事期間にお
いて各資材量、各労務量の推移が適切か否か判定する。
各資材量及び各労務量の推移が適切でないと判断され、
工程計画を修正する補正データが入力されるとステップ
150の判定が否定され、ステップ152では入力され
た補正データに基づいてグループ工程の工事開始年月、
グループ工程の工事順序等を修正し、ステップ130へ
戻る。
If the determination in step 148 is affirmative, the process proceeds to step 150, in which it is determined whether the transition of each material amount and each labor amount during the entire construction period is appropriate.
It is determined that the transition of each material amount and each labor amount is not appropriate,
When the correction data for correcting the process plan is input, the determination in step 150 is denied, and in step 152, the construction start date and time of the group process are determined based on the input correction data.
Correct the construction order of the group process, etc., and return to step 130.

【0033】このように、作成された工程計画に対し
て、資材量及び労務量の推移を参照しながら単工程の重
なりやグループ工程の開始年月、工事順序等を修正する
ことにより、最適な工程計画を短時間で作成することが
できる。
As described above, by modifying the overlapped single process, the start date and time of the group process, the construction order, etc., with respect to the created process plan while referring to the changes in the material amount and the labor amount, the optimal process plan is obtained. A process plan can be created in a short time.

【0034】ステップ150の判定が肯定されると工程
計画の検討処理を終了し、図2のフローチャートのステ
ップ124へ移行する。ステップ124では、例として
図13及び図14に示すように、作成した工程計画案の
工程表68、山積みグラフ70をレーザビームプリンタ
30によって印刷する。このようにして1つの工程計画
案が作成されるが、さらに他の工法を用いた場合の工程
計画案を別途作成し、両者を比較検討することもでき
る。また、建設物の設計の変更、他の設備の工程変更等
が発生した場合には、既に作成された工程計画案を修正
して建設主及び設計者に提示することも可能である。
If the determination in step 150 is affirmative, the process plan reviewing process ends, and the routine goes to step 124 in the flowchart of FIG. In step 124, as shown in FIGS. 13 and 14, for example, the process chart 68 and the pile graph 70 of the created process plan are printed by the laser beam printer 30. One process plan is created in this way, but it is also possible to separately create a process plan in the case of using another method and compare the two. In addition, when a change in the design of a building, a change in the process of another facility, or the like occurs, it is also possible to modify the already created process plan and present it to the constructor and the designer.

【0035】なお、本実施例では工事期間を固定とし、
かつ各月の資材量が一定となるように割付けたときの労
務量の割付けを演算するか、または工事期間を固定と
し、かつ各月の労務量が一定となるように割付けたとき
の資材量の割付けを演算して工程計画を作成するように
していたが、工事期間をある程度伸縮できる場合には、
各月の労務量が一定となるように工事期間及び資材量を
調整するようにして工程計画を作成するようにしてもよ
い。例えば前述の条件において各月の労務量の限度が3
0人で、かつ工事期間をある程度伸縮できる場合、すな
わち、 集計する資材 :型枠面積 集計する労務 :型枠大工 上記工事期間の資材量:900 m2 歩掛り :10.00 m2 /人・月 各月の労務量の限度 :30人 各月の稼働係数 :0.5 1.0 1.0 0.5 上記の条件では3か月で工事が完了しないので工事期間
を1か月伸ばし、 毎月の労務量(一定)=900 ÷10.00 ÷(0.5+1.0+1.0+
0.5 )=30人 第1の月の資材量 =30×10.00 ×0.5 = 150m2 第2の月の資材量 =30×10.00 ×1.0 = 300m2 第3の月の資材量 =30×10.00 ×1.0 = 300m2 第4の月の資材量 =30×10.00 ×0.5 = 150m2 上記のように労務量及び資材量の割付けを演算すること
ができる(図15(E)及び(F)参照)。
In this embodiment, the construction period is fixed.
Calculate the amount of labor when allocating so that the amount of material in each month is constant, or calculate the amount of labor when the work period is fixed and the amount of labor in each month is constant. Was calculated to calculate the process plan, but if the construction period can be expanded or contracted to some extent,
A process plan may be created by adjusting the construction period and the amount of materials so that the amount of labor in each month is constant. For example, under the above conditions, the limit of the amount of labor each month is 3
0 people, and if the construction period to some extent elastic, i.e., materials to aggregate: mold area aggregate to labor: Material amount of formwork carpenter the construction period: 900 m 2 steps consuming: 10.00 m 2 / person, month each month Limit of the amount of labor of: 30 people Operating coefficient of each month: 0.5 1.0 1.0 0.5 Under the above conditions, the construction period is extended by one month because the construction is not completed in 3 months, and the amount of labor per month (constant) = 900 ÷ 10.00 ÷ (0.5 + 1.0 + 1.0 +
0.5) = 30 First month material quantity = 30 × 10.00 × 0.5 = 150m 2 Second month material quantity = 30 × 10.00 × 1.0 = 300m 2 Third month material quantity = 30 × 10.00 × 1.0 = 300 m 2 Material amount in the fourth month = 30 × 10.00 × 0.5 = 150 m 2 The allocation of labor and material amount can be calculated as described above (see FIGS. 15 (E) and (F)).

【0036】また、本実施例では施工量に関連する資源
量として、「型枠面積」、「コンクリート量」等の資材
量を用いて説明したが、本発明はこれに限定されるもの
ではなく、資源量として「消費電力量」、「水使用量」
等を加え、これらの推移も考慮して工程計画を作成する
ことも可能である。
Further, in this embodiment, the resource amount related to the construction amount has been described using the material amount such as "form area" and "concrete amount", but the present invention is not limited to this. , Power consumption and water usage as resources
It is also possible to create a process plan in consideration of these transitions.

【0037】さらに、本実施例では単工程の工事期間内
において資材量または労務量が一定となるように工程計
画を作成していたが、例えばある単工程においてコンク
リート打設作業が工事期間の後半に集中することが予め
予想される場合には、例えばコンクリート量が前記単工
程の後半に一定となるように工程計画を作成するように
してもよい。
Further, in this embodiment, the process plan is prepared so that the amount of materials or labor is constant during the construction period of a single process. If it is anticipated that concentration will occur in advance, a process plan may be created so that, for example, the amount of concrete is constant in the latter half of the single process.

【0038】[0038]

【発明の効果】以上説明したように本発明では、入力さ
れたデータと工事時期に応じて定められた稼働率とに基
づいて、各工程の工事期間が入力された工事期間に一致
しかつ各工程の資源量が工事期間を通じて平準化される
ように工事期間内の労務量の推移を調整した工程計画、
各工程の工事期間が入力された工事期間に一致しかつ各
工程の労務量が工事期間を通じて平準化されるように工
事期間内の資源量の推移を調整した工程計画、及び各工
程の労務量が各工程の工事期間を通じて平準化されるよ
うに各工程の工事期間及び工事期間内の資源量の推移を
調整した工程計画の少なくとも1つを作成し、作成され
た工程計画及び前記工程計画において各工程の所定期間
毎の資源量及び労務量を積算した結果を表示し、入力さ
れた補正データに基づいて前記表示された工程計画を修
正するようにしたので、最適な工程計画の検討を容易に
行うことができる、という優れた効果が得られる。
As described above, according to the present invention, the construction period of each process matches the entered construction period based on the input data and the operation rate determined according to the construction time. A process plan in which the amount of labor during the construction period is adjusted so that the resources of the process are leveled throughout the construction period,
A process plan in which the amount of resources during the construction period has been adjusted so that the construction period of each process matches the entered construction period and the amount of labor in each process is leveled throughout the construction period, and the amount of labor in each process Creates at least one of the work period of each process and a process plan in which the change in the amount of resources during the work period is adjusted so that the process plan is equalized throughout the work period of each process. Since the result of integrating the amount of resources and the amount of labor for each predetermined period of each process is displayed, and the displayed process plan is corrected based on the input correction data, it is easy to consider an optimal process plan. Excellent effect is obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本実施例に係る建設工事の工程計画作成装置の
概略構成を示すブロック図である。
FIG. 1 is a block diagram illustrating a schematic configuration of a construction work process plan creation device according to an embodiment.

【図2】本実施例の作用を説明するフローチャートであ
る。
FIG. 2 is a flowchart illustrating the operation of the present embodiment.

【図3】本実施例の工程計画の検討処理を説明するフロ
ーチャートである。
FIG. 3 is a flowchart illustrating a process plan review process according to the present embodiment.

【図4】工程計画案の選択・入力時の画面イメージであ
る。
FIG. 4 is a screen image when a process plan is selected / input.

【図5】グループ工程名データ入力時の画面イメージで
ある。
FIG. 5 is a screen image when inputting group process name data.

【図6】工程表作成時の画面イメージである。FIG. 6 is a screen image when a process chart is created.

【図7】単工程名毎の歩掛り入力時の画面イメージであ
る。
FIG. 7 is a screen image when a step is input for each single process name.

【図8】月別稼働係数入力時の画面イメージである。FIG. 8 is a screen image when a monthly operation coefficient is input.

【図9】山積みグラフを作成するための作表条件の一部
を設定する時の画面イメージである。
FIG. 9 is a screen image when a part of tabulation conditions for creating a pile graph is set.

【図10】山積みグラフを作成するための作表条件の一
部を設定する時の画面イメージである。
FIG. 10 is a screen image when a part of tabulation conditions for creating a pile graph is set.

【図11】山積みグラフの例として、労務を固定したと
きの型枠面積の山積みグラフが表示されたときの画面イ
メージである。
FIG. 11 is a screen image when a pile graph of the formwork area when labor is fixed is displayed as an example of the pile graph.

【図12】(A)は工程期間修正前の工程を示す概念
図、(B)は工程期間修正前の山積みグラフを示す概念
図、(C)は工程期間修正後の工程を示す概念図、
(D)は工程期間修正後の山積みグラフを示す概念図で
ある。
12A is a conceptual diagram showing a process before process period correction, FIG. 12B is a conceptual diagram showing a pile graph before process period correction, FIG. 12C is a conceptual diagram showing a process after process period correction,
(D) is a conceptual diagram showing a pile graph after a process period correction.

【図13】工程表の印刷例を示す図表である。FIG. 13 is a chart showing a print example of a process chart.

【図14】山積みグラフの印刷例を示す図表である。FIG. 14 is a chart showing a printing example of a pile graph.

【図15】(A)及び(B)は資材固定としたときの労
務量及び資材量の山積みの例を示す図表、(C)及び
(D)は労務固定としたときの労務量及び資材量の山積
みの例を示す図表、(E)及び(F)は本発明の他の例
として労務量を固定して期間を自由とした場合の山積み
の例を示す図表である。
FIGS. 15A and 15B are tables showing examples of the amount of labor and the amount of material when the material is fixed, and FIGS. 15C and 15D are the amounts of labor and the material when the labor is fixed. (E) and (F) are charts showing examples of piles when the amount of labor is fixed and the period is free as another example of the present invention.

【符号の説明】[Explanation of symbols]

10 建設工事の工程計画作成装置 12 パーソナルコンピュータ 24 キーボード 26 マウス 28 ディスプレイ 30 レーザビームプリンタ DESCRIPTION OF SYMBOLS 10 Construction process planning device 12 Personal computer 24 Keyboard 26 Mouse 28 Display 30 Laser beam printer

───────────────────────────────────────────────────── フロントページの続き (72)発明者 湯浅 洋一 東京都江東区南砂二丁目5番14号 株式 会社竹中工務店 技術研究所内 (56)参考文献 特開 平2−288972(JP,A) 特開 昭64−29965(JP,A) 特開 昭63−282566(JP,A) 第7回建築生産と管理技術シンポジウ ム論文集(1991−7)pp.103−108 第6回建築生産と管理技術シンポジウ ム論文集(1990−7)pp.13−18 (58)調査した分野(Int.Cl.6,DB名) G06F 17/60 E04G 21/00 B23Q 41/08 JICSTファイル(JOIS)──────────────────────────────────────────────────続 き Continuation of the front page (72) Inventor Yoichi Yuasa 2-5-1-14 Minamisuna, Koto-ku, Tokyo Inside Takenaka Corporation Technical Research Institute (56) References JP-A-2-288972 (JP, A) JP-A-64-29965 (JP, A) JP-A-63-282566 (JP, A) The 7th Symposium on Building Production and Management Technology (1991-7) pp. 103-108 6th Symposium on Building Production and Management Technology (1990-7) pp. 13-18 (58) Field surveyed (Int. Cl. 6 , DB name) G06F 17/60 E04G 21/00 B23Q 41/08 JICST file (JOIS)

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 建設工事の各工程の工事期間、各工程毎
の施工量に関連する資源量及び単位労務量当りの施工量
を含むデータ及び前記データを補正する補正データを入
力する入力手段と、 前記入力手段によって入力されたデータと工事時期に応
じて定められた稼働率とに基づいて、各工程の工事期間
が前記入力された工事期間に一致しかつ各工程の資源量
が前記工事期間を通じて平準化されるように前記工事期
間内の労務量の推移を調整した工程計画、各工程の工事
期間が入力された工事期間に一致しかつ各工程の労務量
が前記工事期間を通じて平準化されるように前記工事期
間内の資源量の推移を調整した工程計画、及び各工程の
労務量が各工程の工事期間を通じて平準化されるように
各工程の工事期間及び前記工事期間内の資源量の推移を
調整した工程計画の少なくとも1つを作成する作成手段
と、 前記作成手段によって作成された工程計画及び前記工程
計画において各工程の所定期間毎の資源量及び労務量を
積算した結果を表示する表示手段と、 入力手段によって入力された前記補正データに基づいて
前記工程計画を修正する修正手段と、 を有する建設工事の工程計画作成装置。
An input means for inputting data including a construction period of each step of construction work, a resource amount related to a construction amount for each step and a construction amount per unit labor amount, and correction data for correcting the data. Based on the data input by the input means and the operation rate determined according to the construction time, the construction period of each process matches the inputted construction period, and the resource amount of each process is the construction period A process plan that adjusts the transition of the amount of labor during the construction period so that it is leveled through, the construction period of each process matches the input construction period, and the amount of labor of each process is leveled through the construction period. And the amount of resources during the construction period of each process so that the amount of labor in each process is leveled throughout the construction period of each process. Transition Creating means for creating at least one of the adjusted process plans; display means for displaying the process plan created by the creating means and the result of integrating the resource amount and the labor amount for each predetermined period of each process in the process plan And a correcting means for correcting the process plan based on the correction data input by the input means.
JP32558791A 1991-12-10 1991-12-10 Construction plan creation device Expired - Fee Related JP2994827B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32558791A JP2994827B2 (en) 1991-12-10 1991-12-10 Construction plan creation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32558791A JP2994827B2 (en) 1991-12-10 1991-12-10 Construction plan creation device

Publications (2)

Publication Number Publication Date
JPH05158945A JPH05158945A (en) 1993-06-25
JP2994827B2 true JP2994827B2 (en) 1999-12-27

Family

ID=18178548

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32558791A Expired - Fee Related JP2994827B2 (en) 1991-12-10 1991-12-10 Construction plan creation device

Country Status (1)

Country Link
JP (1) JP2994827B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5247345B2 (en) * 2008-10-20 2013-07-24 旭化成ホームズ株式会社 Artisan rotation management system
JP7339195B2 (en) * 2020-03-19 2023-09-05 株式会社奥村組 How to select temporary scaffolding
CN114611749B (en) * 2022-01-14 2024-11-26 北京全路通信信号研究设计院集团有限公司 An optimization method and system for shortening construction period

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
第6回建築生産と管理技術シンポジウム論文集(1990−7)pp.13−18
第7回建築生産と管理技術シンポジウム論文集(1991−7)pp.103−108

Also Published As

Publication number Publication date
JPH05158945A (en) 1993-06-25

Similar Documents

Publication Publication Date Title
US5016170A (en) Task management
Burns et al. The LP/IP hybrid method for construction time-cost trade-off analysis
US5918219A (en) System and method for estimating construction project costs and schedules based on historical data
JP3337207B2 (en) Construction system support system
JP2994827B2 (en) Construction plan creation device
Dzeng et al. Critiquing contractors' scheduling by integrating rule-based and case-based reasoning
JPH0793408A (en) Process planning method and equipment
JP2023105861A (en) Process chart creation system and program
JP3067099B2 (en) Bar arrangement design support apparatus and method
Hassanein et al. Crew design methodology for construction contractors
Chevallier et al. Developing a draft schedule using templates and rules
JP2791197B2 (en) Prefabricated construction process control device
JPH0953324A (en) Device for supporting construction work
JP2000250975A (en) Production schedule creation system
JP2791201B2 (en) Construction work schedule management system
JPH06248800A (en) Stirrup design support device
JP2791202B2 (en) Construction work schedule management system
JP2791200B2 (en) Construction work schedule management system
Huang et al. Graphically based LP modelling for linear scheduling analysis: the POLO system
JP2000226937A (en) Schedule control table and preparation system therefor
Zaiman et al. Comparison Analysis for Implementation Time of Column Formwork Using Three Formwork Methods in a Building Project at Bandung Province
JP2000170379A (en) Construction schedule control instrument and recording medium
JP2791198B2 (en) Prefabricated construction process control device
Lee Automated interactive cost estimating system for reinforced concrete building structures
Abudayyeh et al. Integrated construction project management: a teaching case study

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071022

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081022

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091022

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091022

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101022

Year of fee payment: 11

LAPS Cancellation because of no payment of annual fees