JP2867080B2 - Basement building construction method - Google Patents
Basement building construction methodInfo
- Publication number
- JP2867080B2 JP2867080B2 JP3089483A JP8948391A JP2867080B2 JP 2867080 B2 JP2867080 B2 JP 2867080B2 JP 3089483 A JP3089483 A JP 3089483A JP 8948391 A JP8948391 A JP 8948391A JP 2867080 B2 JP2867080 B2 JP 2867080B2
- Authority
- JP
- Japan
- Prior art keywords
- pillar
- column
- ring
- joint
- basement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Rod-Shaped Construction Members (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は、構真柱を用いたラー
メン架構の地階躯体の構築工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a basement frame of a ramen frame using straight columns.
【0002】[0002]
【従来の技術】地階躯体の構造形式は図8及び図9に示
すように、ラーメン架構が殆どで、柱30と大梁31は
剛接合している。2. Description of the Related Art As shown in FIGS. 8 and 9, most of the basement frames have a rigid frame structure, and columns 30 and girders 31 are rigidly connected.
【0003】またその多くは、基礎杭32の打設と柱3
0の建込みとを先行させ、一階から最地階へと土地を掘
削しながら地下躯体の施工作業を進行する逆打ち工法を
採用している。[0003] In many cases, the driving of the foundation pile 32 and the pillar 3
The construction of the underground skeleton is carried out while excavating the land from the first floor to the lowest floor.
【0004】この逆打ち工法では、先ず地中に所要深さ
の柱の孔を掘削し、その掘削孔の底部に場所打コンクリ
ート杭を打設した後、所要階高ごとにブラケットを設け
た鋼管コンクリート柱による構真柱を掘削孔に挿入し、
下端部を場所打コンクリートの基礎杭に埋設して柱を垂
直に建込んでいる。In this reverse driving method, first, a hole of a pillar having a required depth is excavated in the ground, a cast-in-place concrete pile is cast at the bottom of the excavation hole, and then a steel pipe provided with a bracket for each required floor height. Insert a concrete pillar with a concrete pillar into the drill hole,
The lower end is buried in cast-in-place concrete foundation piles, and columns are built vertically.
【0005】上記構真柱と大梁との接合は、予め所要階
ごとに設けたブラケットを介して行われるが、地面より
上に位置する一階のブラケットと大梁の接続を先行し、
次に土の掘削除去と、露出したブラケットと大梁との接
合を順次下方へと繰り返し行って、ラーメン架構の地階
躯体を完成している。[0005] The connection between the straight pillar and the girder is performed via brackets provided in advance for each required floor, but prior to the connection between the bracket on the first floor and the girder located above the ground,
Next, the excavation and removal of the soil and the joining of the exposed bracket and the girder are repeated sequentially downward to complete the basement frame of the ramen frame.
【0006】[0006]
【発明が解決しようとする課題】このような従来工法で
は、予めブラケットを設けた構真柱を地中に建込んでい
ることから、下記のごとき課題を有する。The conventional construction method has the following problems because a straight pillar provided with a bracket is built in the ground.
【0007】 ブラケットにより柱の運搬及び建込み
に手数を要する。[0007] The bracket requires time and effort to transport and build the pillar.
【0008】 ブラケットによって柱の建込み方向が
定められていることから、基礎杭に建込む時の柱のレベ
ル設置及び平面,x,y方向の墨出しに時間を要する。[0008] Since the mounting direction of the pillar is determined by the bracket, it takes time to install the pillar at the time of building on the foundation pile and to mark the plane, x, and y directions.
【0009】 ブラケットの柱からの突出長さは、予
め定められているので、柱の鉛直精度が要求され、僅か
な狂いでも柱上端部では、その誤差は拡大されて大梁の
納まりが困難となり、柱相互のブラケットの間隔が設定
間隔よりも20mm以上長くなると、大梁を納めることが
不可能となり、その間隔に適合した大梁を新たに製作し
なければならない。[0009] Since the length of the bracket projecting from the column is predetermined, vertical accuracy of the column is required. Even at a slight deviation, the error is enlarged at the top of the column, making it difficult to accommodate the girder. If the interval between the brackets of the columns is longer than the set interval by 20 mm or more, it becomes impossible to accommodate the girder, and a girder suitable for the interval must be newly manufactured.
【0010】 柱相互のブラケットの間隔が適正か否
かは、掘削により地中から露出した後でなければ知るこ
とができず、その間隔が設定長さと著しく異なって、大
梁の接合が無理な時には、その部分の大梁の施工を中断
しなければならず、作業工程の変更が強いられ、時には
工期の遅延となることもある。[0010] It is impossible to know whether or not the interval between the brackets of the columns is appropriate only after excavation from the ground by excavation. When the interval is significantly different from the set length and the joining of the girder is impossible, However, the construction of the girder in that part must be interrupted, and the work process must be changed, sometimes leading to a delay in the construction period.
【0011】上記従来工法における課題は、予め構真柱
に設けられたブラケットが原因であるとのことから、こ
の発明では、構真柱と大梁とを接合する部材とを別体と
し、構真柱を掘削孔に鉛直に建込んだ後に、接合部材を
構真柱に取付けることによって、その課題を解決しよう
とするものである。Since the problem in the conventional method is caused by a bracket previously provided on the trussed pillar, in the present invention, the member for joining the trussed pillar and the girder is separated from each other, The object is to solve the problem by mounting the joining member to the straight pillar after the pillar is vertically built in the excavation hole.
【0012】[0012]
【課題を解決するための手段】上記目的によるこの発明
の特徴は、地階躯体の柱に鋼管コンクリート柱の構真柱
を用い、その構真柱の建込み後に、柱外径よりも内径が
大径で柱との間に所要のクリアランスを形成する鋼管製
のリング本体と、断面形状が鉄骨梁と同一でリング本体
の外側四方に一体形成したガセットとからなる接合リン
グの所要数を、構真柱の上部に嵌挿し、その接合リング
を各階の柱と梁との接合部周囲に後付けした支持部材に
載置した後、上記ガセットと鉄骨梁との剛接合と、上記
クリアランスへの充填物による柱への接合リングの固定
とを行い、これにより構真柱と鉄骨梁とによる地階躯体
をラーメンに構成してなることにある。The feature of the present invention according to the above object is that a steel pipe concrete pillar is used as a pillar of a basement skeleton, and the inner diameter of the pillar is larger than the outer diameter of the pillar after the construction of the pillar. The required number of joint rings consisting of a steel pipe ring main body that forms the required clearance between the column and the column and gussets that have the same cross-sectional shape as the steel beam and are integrally formed on the outer four sides of the ring main body, After the fitting ring is inserted into the upper part of the column and the joint ring is placed on a support member that is retrofitted around the joint between the column and the beam on each floor, the rigid connection between the gusset and the steel beam, and the filling of the clearance The joint ring is fixed to the column, thereby forming the basement frame composed of the timber column and the steel beam into a ramen.
【0013】[0013]
【作用】上記工法では、構真柱と接合リングとが別体
で、鉛直に建込んだ構真柱に対して、接合リングを鉄骨
梁の接合前に水平方向に自由に回動することができるた
め、平面x,yの位置修正が容易にでき、また柱とリン
グ本体とのクリアランスにより、柱相互のガセット間隔
を或る程度修正することができるので、鉄骨梁の納まり
が設計通りに行われる。According to the above-mentioned construction method, the trussed pillar and the joint ring are separate bodies, and the joint ring can be freely rotated in the horizontal direction before the steel beam is joined to the vertically erected trussed pillar. This makes it easy to correct the positions of the planes x and y, and the clearance between the column and the ring body can correct the gusset interval between the columns to some extent, so that the steel beam can be accommodated as designed. Will be
【0014】[0014]
【実施例】図1に示すように、鋼管コンクリート柱によ
る構真柱1に嵌挿する接合リング2は、柱外径よりも内
径が大径で柱との間に所要のクリアランス3を形成する
鋼管製のリング本体4と、リング本体の外側四方に一体
形成したガセット5とから構成されている。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS As shown in FIG. 1, a joint ring 2 to be inserted into a steel column 1 made of a steel pipe concrete column has an inner diameter larger than an outer diameter of the column and forms a required clearance 3 between the column and the column. It comprises a ring main body 4 made of a steel pipe and gussets 5 integrally formed on four outer sides of the ring main body.
【0015】またガセット5は、リング本体4の上下外
周囲に形成したダイアフラム6,6から水平に突設した
上下フランジ7,7と、該フランジ7,7及びリング本
体4とに一体形成したウエブ8とからなり、その断面形
状と寸法は、大梁となる鉄骨梁9と同一に造られてい
る。The gusset 5 includes upper and lower flanges 7 and 7 horizontally projecting from diaphragms 6 and 6 formed on the upper and lower outer periphery of the ring main body 4, and a web integrally formed with the flanges 7 and 7 and the ring main body 4. 8, the cross-sectional shape and dimensions of which are the same as those of the steel beam 9 serving as a large beam.
【0016】上記接合リング2は、構真柱1の周囲に柱
上端から挿入され、柱と梁との接合部周囲に後付けした
支持部材10に載置して柱に取付けられる。また上記鉄
骨梁9との接合は、上記クリアランス3を保った状態
で、図2に示すように、ウエブジョイントプレート11
を用いて行い、その後にクリアランス3に充填材12を
充填して、接続リング5を構真柱1に固定している。The joint ring 2 is inserted from the top end of the pillar 1 around the straight pillar 1 and is mounted on a support member 10 attached to the periphery of the joint between the pillar and the beam to be attached to the pillar. As shown in FIG. 2, the joint with the steel beam 9 is maintained while maintaining the clearance 3.
After that, the clearance 3 is filled with the filler 12, and the connection ring 5 is fixed to the straight pillar 1.
【0017】次に上記接合リング5を用いた地階躯体の
構築施工例を、図4から図7により順に説明する。Next, an example of construction of a basement frame using the above-mentioned joint ring 5 will be described in order with reference to FIGS.
【0018】図4 先ず地中20に所要深さの柱の孔2
1を掘削し、孔底部に場所打コンクリートによる基礎杭
22を打設する。FIG. 4 First, a hole 2 of a pillar having a required depth
1 is excavated, and a foundation pile 22 made of cast-in-place concrete is placed at the bottom of the hole.
【0019】次に地下三層階の高さの上記構真柱1を柱
孔21に挿入する。この際、レベル、建込みチェック等
を入念に行って、下端部を上記基礎杭22に埋込み、構
真柱1を垂直に建てる。Next, the straight pillar 1 having the height of the third basement floor is inserted into the pillar hole 21. At this time, the level, the construction check, etc. are carefully performed, the lower end is embedded in the foundation pile 22, and the timber pillar 1 is vertically built.
【0020】地階躯体の全柱の建込みが完了したら、地
下二層階分の上記接合リング2a,2bを構真柱1の上
部に嵌挿し、一階の柱と梁の接合部より下側の柱周囲に
任意の手段により仮止めする。When the construction of all the columns of the basement frame is completed, the above-mentioned connecting rings 2a and 2b for the two basement floors are inserted into the upper part of the timber column 1, and the lower side of the joint between the column and the beam on the first floor. Temporarily fix around the pillar by any means.
【0021】仮止め後に一階の柱と梁の接合部のレベル
設定を行い、一階の鉄骨梁の下フランジレベルの柱周囲
に、上記支持部材10を水平に後付け溶接する。After the temporary fixing, the level of the joint between the column and the beam on the first floor is set, and the support member 10 is horizontally retrofitted around the column at the lower flange level of the steel beam on the first floor.
【0022】支持部材10を取付けた後、地下二層階分
の接合リング2a,2bはそのままにして、柱上端から
支持部材10上に一階の接合リング2を挿入し載置す
る。After the support member 10 is attached, the joint rings 2 of the first floor are inserted and placed on the support member 10 from the upper ends of the columns, while the joint rings 2a and 2b for the two basement floors are kept as they are.
【0023】支持部材10上の接合リング2と構真柱1
との間には、図では省略しているが、上記クリアランス
3があるので、このクリアランス3の許容範囲にて接合
リング2の位置決めを行う。Joining ring 2 and support pillar 1 on support member 10
Although not shown in the figure, there is the clearance 3, so that the joining ring 2 is positioned within the allowable range of the clearance 3.
【0024】この位置決めは、平面x,y方向(図8参
照)については接合リング2を回動して行い、またガセ
ット5の位置ずれは、接合リング2を横移動して行う。This positioning is performed by rotating the joining ring 2 in the plane x and y directions (see FIG. 8), and the displacement of the gusset 5 is performed by moving the joining ring 2 laterally.
【0025】図5 位置決めにより各ガセット5,5の
方向及びガセット間隔が正しく設定されたならば、一階
の鉄骨梁9をガセット間に吊り入れ、図2に示すよう
に、ウエブジョイントプレート11を用いて鉄骨梁9を
ガセット5のウエブ8にジョイントする。また図では省
略したが、ジョイント後に支持部材10と鉄骨梁9の下
フランジとを溶接する。FIG. 5 If the directions of the gussets 5 and 5 and the gusset intervals are correctly set by the positioning, the steel beams 9 on the first floor are suspended between the gussets, and the web joint plate 11 is attached as shown in FIG. To join the steel beam 9 to the web 8 of the gusset 5. Although not shown in the drawing, the support member 10 and the lower flange of the steel beam 9 are welded after the joint.
【0026】ジョイントが済んだら、図2に示すように
クリアランス3にモルタル等の充填物12を注入し、そ
の充填物12により接合リング2を構真柱1に固着す
る。なお、この充填物としては、モルタルに限定され
ず、圧縮強度が大きく、確実にクリアランスに注入でき
る物であれば良い。After the joint is completed, a filler 12 such as mortar is injected into the clearance 3 as shown in FIG. 2, and the joining ring 2 is fixed to the column 1 by the filler 12. The filler is not limited to the mortar, and may be any material that has a high compressive strength and can be reliably injected into the clearance.
【0027】一階の施工が完了したら、土を地下一階の
下側まで掘下げ、地下二階の接合リング2bだけを地下
一階の柱と梁の接合部より下側まで降ろし、柱周囲に再
仮止めする。そして一階の場合と同様にレベル設定を行
い、地下一階の鉄骨梁の下フランジレベルの柱周囲に、
支持部材10aを水平に後付け溶接する。When the construction on the first floor is completed, the soil is dug down to the lower side of the first basement floor, and only the joint ring 2b on the second basement floor is lowered below the joint between the column and the beam on the first basement floor, and re-mounted around the column. Temporarily fix. Then, set the level as in the case of the first floor, and around the column at the lower flange level of the steel beam on the first basement floor,
The support member 10a is horizontally post-welded.
【0028】支持部材10aの上に接合リング2aを降
ろし、一階の場合と同様に接合リング2aの位置決めを
行う。The joining ring 2a is lowered onto the supporting member 10a, and the joining ring 2a is positioned in the same manner as in the case of the first floor.
【0029】図6 位置決めを行ったら、地下二階の鉄
骨梁9aの吊り込みとジョイントとを行い、モルタルの
充填により接合リング2aを固定して地下二階の施工を
完了する。FIG. 6 After positioning, the steel beams 9a on the second basement are suspended and jointed, and the joining ring 2a is fixed by filling with mortar to complete the construction on the second basement.
【0030】次に土を地下二階の下側まで掘下げる。そ
してレベル設定後に地下二階の鉄骨梁の下フランジレベ
ルの柱周囲に、支持部材10bを水平に後付け溶接す
る。そして支持部材10bの上に接合リング2bを降ろ
し、位置決めを行う。Next, the soil is dug down to the lower side of the second basement floor. After the level is set, the supporting member 10b is horizontally retrofitted and welded around the column at the lower flange level of the steel beam on the second basement floor. Then, the joining ring 2b is lowered onto the support member 10b to perform positioning.
【0031】図7 前記と同様に、地下二階の鉄骨梁9
bの吊り込みとジョイント及び接合リング2bの固定と
を行って地下二階の施工を完了し、更に土の掘削を基礎
杭22の上端部まで行って、図8及び図9に示すラーメ
ン架構の地下躯体の施工を完了する。FIG. 7 As described above, the steel beams 9 on the second basement floor
b and fixing of the joint and the joint ring 2b to complete the construction of the second basement, and further excavation of the soil to the upper end of the foundation pile 22, and the basement of the ramen frame shown in FIG. 8 and FIG. Complete the construction of the frame.
【0032】[0032]
【発明の効果】この発明は上述のように、は構真柱を地
中に建込んだ後に、その柱に嵌挿する接合リングを介し
て構真柱と鉄骨梁との剛接合を行い、またその接合リン
グを、柱外径よりも内径が大径で柱との間に所要のクリ
アランスを形成する鋼管製のリング本体と、断面形状が
鉄骨梁と同一でリング本体の外側四方に一体形成したガ
セットとから構成し、接合前に柱間に生じたクリアラン
スにより位置修正を行えるようにしたことから、下記の
ごとき効果を奏する。As described above, according to the present invention, after a trussed pillar is erected in the ground, the trussed pillar and the steel beam are rigidly joined to each other through a joint ring inserted into the pillar. In addition, the joint ring is formed integrally with the steel pipe ring body, whose inner diameter is larger than the column outer diameter and forms the required clearance between the column and the outside of the ring body with the same cross-sectional shape as the steel beam Gussets, and the position can be corrected by the clearance generated between the columns before joining, so that the following effects can be obtained.
【0033】 構真柱と接合リングは別体であるの
で、ブラケットを有する従来の柱の場合よりも運搬や建
込みが容易となり、特に建込み時に構真柱の方向性を考
慮する必要が無くなるので、建込み作業が極めて簡単と
なり、作業時間も大幅に短縮される。Since the trussed pillar and the joining ring are separate bodies, transportation and erection are easier than in the case of the conventional pillar having a bracket, and it is not necessary to particularly consider the directionality of the trussed pillar at the time of erection. Therefore, the construction work becomes extremely simple, and the work time is greatly reduced.
【0034】 クリアランスにより接合リングを柱に
対して自由に回動できるので、嵌挿の際にガセットの向
きを厳密に定める必要がなく、おおよその見当で嵌挿し
ても差し支えないため、接合リングを建込み後に嵌挿す
るものであっても、作業に手数を要しない。Since the joint ring can be freely rotated with respect to the pillar by the clearance, it is not necessary to strictly determine the orientation of the gusset at the time of insertion and the joint ring can be inserted with an approximate register. Even if it is inserted after installation, no trouble is required for the work.
【0035】 接合リングのレベル設定は、土を掘削
した後に行い、そのレベルは鉄骨梁の下フランジレベル
に後付けした支持部材によって確保されるので正確であ
り、また設定も容易である。The level setting of the joining ring is performed after excavating the soil, and the level is secured by a support member attached to the lower flange level of the steel beam, so that it is accurate and easy to set.
【0036】 接合リングは回転自在に支持部材上に
載置されているので、平面x,yの位置修正が回動によ
り容易に行え、ブラケットを有する構真柱の場合に比べ
て、設定手段が簡略化される。Since the joining ring is rotatably mounted on the support member, the position of the plane x, y can be easily corrected by the rotation, and the setting means can be more easily compared with the case of a straight column having a bracket. Simplified.
【0037】 構真柱と接合リングとのクリアランス
は、設計により任意に設定できるので、大梁となる鉄骨
梁を取付けるときに左右の誤差を吸収し易く、ガセット
間隔の狂いから鉄骨梁の接合が不可能となるようなこと
はない。Since the clearance between the trussed pillar and the joining ring can be set arbitrarily by design, it is easy to absorb left and right errors when attaching a steel beam to be a large beam. Nothing is possible.
【0038】 接合リングの固定は、クリアランスに
充填材を充填することにより行われるので、ボルトや溶
接などにより固定する場合よりも簡単で、確実でもあ
る。The fixing of the joining ring is performed by filling the clearance with a filler, so that it is simpler and more reliable than the case of fixing with a bolt or welding.
【図1】この発明に係わる地階躯体構築工法に用いられ
る構真柱と接合リング及び鉄骨梁とを示す斜視図であ
る。FIG. 1 is a perspective view showing a timber column, a joint ring, and a steel beam used in a basement building construction method according to the present invention.
【図2】接合リングを介しての構真柱と鉄骨梁との接合
状態を示す縦断面図である。FIG. 2 is a vertical cross-sectional view showing a joining state between a straight pillar and a steel beam via a joining ring.
【図3】同上の平面図である。FIG. 3 is a plan view of the same.
【図4】構真柱の建込みから一階の支持部材の後付けま
での工程説明図である。FIG. 4 is an explanatory diagram of a process from the installation of a tall pillar to the attachment of a support member on the first floor.
【図5】一階の鉄骨梁の接合から地下一階の接合リング
の設定までの工程説明図である。FIG. 5 is an explanatory diagram of a process from joining a steel beam on the first floor to setting a joining ring on the first basement floor.
【図6】地下一階の鉄骨梁の接合から地下二階の接合リ
ングの設定までの工程説明図である。FIG. 6 is a process explanatory view from joining of a steel beam on the first basement floor to setting of a joining ring on the second basement floor.
【図7は】地下二階の鉄骨梁の接合から地下三階の掘削
までの工程説明図である。FIG. 7 is an explanatory view of a process from joining of steel beams on the second basement floor to excavation on the third basement floor.
【図8】地階躯体の略示平面図である。FIG. 8 is a schematic plan view of a basement skeleton.
【図9】地階躯体の略示断面図である。FIG. 9 is a schematic sectional view of a basement skeleton.
1 構真柱 2 接合リング 3 クリアランス 4 リング本体 5 ガセット 6 ダイヤフラム 7 フランジ 8 ウエブ 10 支持部材 11 ウエブジョイントプレート 12 充填物 REFERENCE SIGNS LIST 1 straight pillar 2 joint ring 3 clearance 4 ring body 5 gusset 6 diaphragm 7 flange 8 web 10 support member 11 web joint plate 12 filler
───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.6,DB名) E02D 29/045 E04C 3/32 E21D 13/00 E04B 1/24──────────────────────────────────────────────────続 き Continued on the front page (58) Fields surveyed (Int. Cl. 6 , DB name) E02D 29/045 E04C 3/32 E21D 13/00 E04B 1/24
Claims (1)
真柱を用い、その構真柱の建込み後に、柱外径よりも内
径が大径で柱との間に所要のクリアランスを形成する鋼
管製のリング本体と、断面形状が鉄骨梁と同一でリング
本体の外側四方に一体形成したガセットとからなる接合
リングの所要数を、構真柱の上部に嵌挿し、その接合リ
ングを各階の柱と梁との接合部周囲に後付けした支持部
材に載置した後、上記ガセットと鉄骨梁との剛接合と、
上記クリアランスへの充填物による柱への接合リングの
固定とを行い、構真柱と鉄骨梁とをラーメンに構成して
なることを特徴とする地階躯体構築工法。1. A steel pillar concrete pillar is used as a pillar of a basement skeleton, and after the construction of the pillar, the required clearance is formed between the pillar and the pillar having an inner diameter larger than an outer diameter of the pillar. The required number of joint rings consisting of a steel pipe ring body and gussets having the same cross-sectional shape as the steel beam and integrally formed on the outer four sides of the ring body are inserted into the upper part of the trussed pillar, and the joint ring is attached to each floor. After being mounted on a support member that is retrofitted around the joint between the column and the beam, a rigid connection between the gusset and the steel beam,
A basement building construction method, comprising fixing a joint ring to a column with a filler in the clearance, and forming a straight column and a steel beam into a rigid frame.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3089483A JP2867080B2 (en) | 1991-03-28 | 1991-03-28 | Basement building construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3089483A JP2867080B2 (en) | 1991-03-28 | 1991-03-28 | Basement building construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH05214736A JPH05214736A (en) | 1993-08-24 |
| JP2867080B2 true JP2867080B2 (en) | 1999-03-08 |
Family
ID=13971989
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP3089483A Expired - Fee Related JP2867080B2 (en) | 1991-03-28 | 1991-03-28 | Basement building construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2867080B2 (en) |
Families Citing this family (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2697532B2 (en) * | 1992-11-19 | 1998-01-14 | 鹿島建設株式会社 | How to build an architectural frame |
| JP5050228B2 (en) * | 2005-11-10 | 2012-10-17 | 株式会社横河ブリッジ | Ramen bridge construction method with cane member |
| JP2008095499A (en) * | 2007-12-28 | 2008-04-24 | East Japan Railway Co | Beam-column joint structure |
| JP5638905B2 (en) * | 2010-09-30 | 2014-12-10 | 株式会社竹中工務店 | Steel pipe column joint reinforcement structure |
| JP5948838B2 (en) * | 2011-12-12 | 2016-07-06 | 株式会社大林組 | Column and beam joining method |
| JP6438349B2 (en) * | 2015-05-18 | 2018-12-12 | 鹿島建設株式会社 | Beam-to-column steel structure |
| JP6396356B2 (en) * | 2016-03-30 | 2018-09-26 | 株式会社カナサシテクノサービス | Reinforcement structure of volumetric structure buried underground |
| CN113958133B (en) * | 2021-10-27 | 2022-12-13 | 中铁三局集团建筑安装工程有限公司 | Construction method of steel structure factory building roof truss girder |
| KR102630184B1 (en) * | 2023-08-01 | 2024-01-29 | 주식회사 이솔구조건축사사무소 | Joint member for modular construction and construction method using the same |
| KR102630179B1 (en) * | 2023-08-01 | 2024-01-29 | 주식회사 이솔구조건축사사무소 | Joint member for modular construction and construction method using the same |
-
1991
- 1991-03-28 JP JP3089483A patent/JP2867080B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH05214736A (en) | 1993-08-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101687495B1 (en) | Partial top-down construction method for building underground structures | |
| JP2867080B2 (en) | Basement building construction method | |
| KR20190022132A (en) | Top-down method using precast-concrete colum | |
| JPH0726568A (en) | Joint structure of steel columns, piles and foundation beams | |
| JP3175586B2 (en) | Column and pile connection method | |
| KR100629437B1 (en) | Guide casing structure for pillar construction and pillar construction method using the same | |
| JP3491116B2 (en) | Pillar and pile joints | |
| JP3671344B2 (en) | Joint structure between foundation pile and column base and its construction method | |
| JP3107716B2 (en) | Soil retaining wall | |
| CN109235453B (en) | Assembled support method of PRC pipe piles for deep foundation pits | |
| JP3612600B2 (en) | Unit anchor and structural steel foundation beam | |
| JP2002242302A (en) | Beam-column joint structure of building steel frame and joint method | |
| JPH10317371A (en) | Method for erecting pile-column in building using pile as column, and pile-column support band for use therein | |
| JP2002021096A (en) | Building and its construction method | |
| JPH0925637A (en) | Method of connected construction of pile head and beam | |
| JP3890666B2 (en) | Joining method and structure of the structural column and main body steel in the reverse driving method | |
| JPH04366229A (en) | Temporary corresponding standard used for method of reverse driving construction | |
| JP3246321B2 (en) | Column and pile joint structure | |
| JPH0718253B2 (en) | Setting method and setting device for anchor bolts for steel columns | |
| JPH07119465B2 (en) | Underground excavation construction method | |
| KR102942222B1 (en) | Top down method for underground structures using suspensory shoring columns | |
| JP2002088782A (en) | Column-beam joint structure of underground building | |
| JPH0996108A (en) | Method of erecting steel frame column | |
| JPH0748847A (en) | Steel column column base structure and building construction method of building with basement | |
| JP2772397B2 (en) | Underground building construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091225 Year of fee payment: 11 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091225 Year of fee payment: 11 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101225 Year of fee payment: 12 |
|
| LAPS | Cancellation because of no payment of annual fees |