JPH0718253B2 - Setting method and setting device for anchor bolts for steel columns - Google Patents
Setting method and setting device for anchor bolts for steel columnsInfo
- Publication number
- JPH0718253B2 JPH0718253B2 JP16093990A JP16093990A JPH0718253B2 JP H0718253 B2 JPH0718253 B2 JP H0718253B2 JP 16093990 A JP16093990 A JP 16093990A JP 16093990 A JP16093990 A JP 16093990A JP H0718253 B2 JPH0718253 B2 JP H0718253B2
- Authority
- JP
- Japan
- Prior art keywords
- pillar
- fixed
- primary
- transfer member
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Foundations (AREA)
- Joining Of Building Structures In Genera (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明は鉄骨構造建築物の建築工事において、基礎コン
クリート上の所定位置に鉄骨柱を建てるために用いるア
ンカーボルトのセット工法及びセット装置に関する。Description: TECHNICAL FIELD The present invention relates to an anchor bolt setting method and a setting device used for building a steel column at a predetermined position on a foundation concrete in the construction work of a steel structure building.
(従来の技術) まず第11図及び第12図により基礎コンクリートの一般的
な構造及びアンカーボルトのセット状態を説明する。第
11図において掘削された穴底にぐり石8が敷設されると
共に厚さ50mmくらいの捨てコンクリート1が打設され、
その上に基礎コンクリートが打設される。基礎コンクリ
ートは方形状の下側ベースコンクリート部13と、これよ
り面積が小さい方形状の柱型コンクリート部14よりなっ
ており、柱型コンクリート部14の上端面には、モルタル
製あるいは鉄製の柱水平度調節用まんじゅう19が設けら
れている。基礎コンクリート内には、下側のベース筋
2、L形立上り状の柱主筋5及び第12図の地中梁用梁筋
7等が埋め込まれると共に、例えば4本のアンカーボル
ト9が埋め込まれている。柱主筋5及び梁筋7はそれぞ
れフープ筋6により結束されている。(Prior Art) First, a general structure of foundation concrete and a set state of anchor bolts will be described with reference to FIGS. 11 and 12. First
In the bottom of the excavated hole in Fig. 11, a stone 8 was laid and a discarded concrete 1 with a thickness of about 50 mm was placed.
Foundation concrete is placed on it. The basic concrete is composed of a square lower base concrete portion 13 and a square columnar concrete portion 14 having a smaller area. A manju 19 for adjusting degree is provided. In the base concrete, the lower base reinforcement 2, the L-shaped upright column main reinforcement 5, the beam reinforcement 7 for the underground beam of FIG. 12 and the like are embedded, and, for example, four anchor bolts 9 are embedded. There is. The column main bar 5 and the beam bar 7 are bound by a hoop bar 6.
鉄骨柱17の下端部にはアンカーボルト挿通孔孔を有する
ベースプレート18が一体に備えられており、建方時にベ
ースプレート18をまんじゅう19に載せ、水平調節をしな
がらアンカーボルト9の上部に固定する。A base plate 18 having an anchor bolt insertion hole is integrally provided at the lower end portion of the steel column 17, and the base plate 18 is placed on the manju 19 at the time of erection and is fixed to the upper portion of the anchor bolt 9 while being horizontally adjusted.
上記アンカーボルト9は、基礎コンクリートを打設する
前に、梁間方向H6及び桁行方向Kの柱位置を決定するた
めの柱芯C1、C2に対して、正確な位置にセットし、固定
する必要がある。It is necessary to set and fix the anchor bolts 9 at accurate positions with respect to the pillar cores C1 and C2 for determining the pillar positions in the beam-to-beam direction H6 and girder row direction K before placing the concrete foundation. is there.
アンカーボルトのセット工法としては、従来より配筋及
び型枠設置後にセットする工法と、配筋及び型枠設置前
にセットする工法とがある。As an anchor bolt setting method, conventionally, there are a method of setting after the reinforcement and the formwork are installed and a method of setting before the reinforcement and the formwork.
まず前者の配筋後のセット工法を説明する。First, the former set method after rebar arrangement will be described.
(A)配筋前において、捨てコンクリート1の上面に墨
系により各柱芯C1、C2のマーク(地墨)を付す。(A) Before rebar arrangement, marks (posterior ink) of each pillar core C1 and C2 are made on the upper surface of the discarded concrete 1 by a black system.
(B)次にベース筋2、柱主筋5及び梁筋7を配筋する
と共にコンクリート型枠11、12を組み付ける。(B) Next, the base reinforcement 2, the column main reinforcement 5, and the beam reinforcement 7 are laid out, and the concrete formwork 11, 12 is assembled.
(C)第13図のように柱型枠12の上端にベースプレート
18と同形状の型板(ゲージ)21を配置し、下げぶりによ
り捨てコンクリート上の柱芯の地墨に合わせて型板21を
位置決めし、型枠12に固定する。(C) Base plate on top of pillar formwork 12 as shown in FIG.
A template (gauge) 21 having the same shape as that of 18 is arranged, and the template 21 is positioned according to the ground ink of the pillar core on the discarded concrete by lowering it and fixed to the template 12.
(d)そしてアンカーボルト9を型板21の所定の孔22に
吊り下げ、アンカーボルト9の下端部を柱主筋等に溶接
により固着する。(D) Then, the anchor bolt 9 is suspended in a predetermined hole 22 of the template 21, and the lower end portion of the anchor bolt 9 is fixed by welding to the column main bar or the like.
ところがこのような工法では、次のような不具合があ
る。However, such a construction method has the following problems.
(イ)配筋後にアンカーボルト9を配置するので、第13
図のように柱主筋5や梁筋7が邪魔になり、アンカーボ
ルト9の所定位置への施工に手間がかかる。(A) Since the anchor bolt 9 is placed after the reinforcement,
As shown in the figure, the column main bars 5 and the beam bars 7 become an obstacle, and it takes time to construct the anchor bolt 9 at a predetermined position.
特に梁筋7に当たって所定の位置に配置できなくなる
と、コンクリート打設後、第14図のようにアンカーボル
ト9を加熱して所定の位置に曲げ寄せる、いわゆる台直
しをする必要が生じる。しかしこの台直し作業はアンカ
ーボルトの強度低下になるため、実際に行なうことはで
きない。In particular, when it becomes impossible to place the beam 7 at a predetermined position by hitting the beam bar 7, it is necessary to heat the anchor bolt 9 and bend it to a predetermined position after pouring the concrete, that is, so-called re-mounting. However, this reworking work cannot be actually performed because the strength of the anchor bolt is reduced.
(ロ)柱芯C1、柱芯C2の地墨が捨てコンクリート1の上
面に付され、それに合わせて上方位置に下げぶりにより
型板21を設置するため、捨てコンクリート1上の地墨が
確認しにくく、また下げぶりが揺れるため、柱芯出し作
業に手間がかかり、アンカーボルト9のセット位置が不
正確になりやすい。(B) The ground ink of the pillar core C1 and the pillar core C2 is attached to the upper surface of the discarded concrete 1, and the template 21 is installed by lowering it to the upper position accordingly, so the ground ink on the discarded concrete 1 is confirmed. Since it is difficult and the swinging of the lowering swings, it takes a lot of time to perform the centering work of the column, and the setting position of the anchor bolt 9 tends to be inaccurate.
(ハ)捨てコンクリート1の表面は凹凸が多く、また障
害物等も突出している場合が多いので、その上面に柱芯
の地墨を正確に打つには手間がかかる。また捨てコンク
リート1の上面には雨や地下水等が溜り易く、それによ
り地墨が消えたりすることもある。(C) Since the surface of the abandoned concrete 1 has many irregularities and obstacles and the like are often projected, it is troublesome to accurately hit the pole stick ground ink on the upper surface thereof. Further, rain, groundwater, etc. are likely to collect on the upper surface of the discarded concrete 1, which may cause the ground ink to disappear.
次に第15図により後者の配筋前のセット工法を説明す
る。配筋前において、捨てコンクリート1の上に墨糸に
より各柱芯C1、C2の地墨を付し、捨てコンクリート1上
に釘25等によりフレーム台26を固定し、該フレーム台26
上に、アンカーボルト9を取り付けた型板(ゲージ)21
を配置し、下げぶり28により捨てコンクリート1上の柱
芯マークに合わせて型板21を位置決めする。Next, the latter set-up method before rebar arrangement will be described with reference to FIG. Before rebar arrangement, the ground ink of each pillar core C1 and C2 is attached on the discarded concrete 1 by the ink thread, and the frame base 26 is fixed on the discarded concrete 1 by the nail 25 or the like.
Template (gauge) 21 with anchor bolt 9 attached on top
Is arranged, and the template 21 is positioned in accordance with the pillar core mark on the discarded concrete 1 by the lowering 28.
しかしこの方法でも捨てコンクリート1の上面に柱芯マ
ークとして地墨を付けるので、前記(ロ)〜(ニ)で説
明した不具合と同様な不具合が生じる。However, even in this method, since ground ink is attached as a pillar core mark to the upper surface of the discarded concrete 1, the same problems as those described in (b) to (d) above occur.
(発明の目的) アンカーボルトを所定の位置に簡単かつ正確にセットで
きる鉄骨柱用アンカーボルトのセット工法及びセット装
置を提供することである。(Object of the Invention) It is an object of the present invention to provide a setting method and a setting device of an anchor bolt for a steel column, which can set the anchor bolt in a predetermined position easily and accurately.
(目的を達成するための技術的手段) 上記目的を達成するために本発明は、配筋前における各
柱設置箇所の4隅に、柱型枠断面より広い範囲で縦杭を
固定し、桁行方向あるいは梁間方向のいずれかに間隔を
隔てて対向する1対の1次渡し部材を、水平かつ同一高
さに縦杭の上部に固定し、1次渡し部材に、1次渡し部
材と交又する方向に延びる1次柱芯のマークを付し、1
対の2次渡し部材を1次渡し部材上に井桁状に架け渡し
て固定し、2次渡し部材には、1次柱芯と直角方向に延
びる2次柱芯のマークを付し、上記両柱芯を梁間方向及
び桁行方向の各中心として、2次渡し部材上に上面型板
を固定し、該上面型板に複数本のアンカーボルトを吊り
下げ、アンカーボルトの下端部を振れ止め固定するよう
にしている。(Technical Means for Achieving the Purpose) In order to achieve the above-mentioned object, the present invention is to fix vertical piles in four corners of each column installation place before bar arrangement in a range wider than the cross section of the column form, and to carry the girder. A pair of primary transfer members facing each other in the direction of the beam or the direction between the beams are fixed to the upper part of the vertical pile at the same horizontal level, and the primary transfer member is connected to the primary transfer member. Mark the primary column core extending in the direction
The pair of secondary transfer members are laid over and fixed on the primary transfer member in a cross beam shape, and the secondary transfer member is marked with a secondary pillar core extending in a direction perpendicular to the primary pillar core. An upper surface template is fixed on the secondary transfer member with the pillar core as each center in the beam direction and column direction, and a plurality of anchor bolts are suspended on the upper surface template, and the lower end portions of the anchor bolts are fixed by steadying. I am trying.
(実施例) 第3図〜第10図は本発明によるセット工法に従ってセッ
ト装置を設置する過程を順に示し、第1図及び第2図は
アンカーボルトのセット完了時の状態を示している。図
面に従ってセット工法を説明する。(Embodiment) FIGS. 3 to 10 sequentially show the process of installing the setting device according to the setting method according to the present invention, and FIGS. 1 and 2 show the state when the setting of the anchor bolt is completed. The setting method will be described with reference to the drawings.
(A)第3図及び第4図において、各柱設置用箇所の4
隅に、アングル材製の4本の縦杭30を打ち込み、捨てコ
ンクリートを打設して確実に固定する。この場合縦杭30
は例えば300mm程度打ち込み、また捨てコンクリート1
は縦杭30周辺部分を厚肉(100mm以上)に打設してい
る。(A) In FIG. 3 and FIG. 4, 4 of each column installation location
Drive four vertical piles 30 made of angle material into the corners, and cast waste concrete to secure it securely. Vertical pile 30 in this case
Is about 300 mm, for example, and concrete is discarded 1
Has a thick wall (100 mm or more) around the vertical pile 30.
各縦杭30は、ベースコンクリート部13の範囲内に配置さ
れるが、柱型枠及び梁型枠等が後で楽に設置できるよう
に、柱型コンクリート部14の形成範囲から梁間方向H及
び桁行方向Kに一定の間隔D(例えば200mm以上)離れ
ている。Each vertical pile 30 is arranged within the range of the base concrete part 13, but in order to easily install the pillar formwork and the beam formwork later, from the forming range of the pillar form concrete part 14 to the beam direction H and the girder row. It is separated by a constant distance D (for example, 200 mm or more) in the direction K.
上記のように縦杭30を固定した後、各縦杭30にはベース
プレート下面位置に相当する高さにレベル墨Lを付す。After fixing the vertical piles 30 as described above, a level ink L is attached to each vertical pile 30 at a height corresponding to the position of the bottom surface of the base plate.
(B)第5図及び第6図において、アングル材製の1対
の渡し部材31を、互いに桁行方向Kに間隔を隔てて対向
するように配置し、それぞれ前記レベル墨Lにより同一
高さに水平に揃え、縦杭30に溶接する。即ち各1次渡し
部材31は、桁行方向Kに間隔を隔てて対向すると共に水
平にかつ同一高さにセットされる。(B) In FIG. 5 and FIG. 6, a pair of transfer members 31 made of an angle member are arranged so as to face each other at intervals in the column direction K, and are made to have the same height by the level ink L, respectively. Align horizontally and weld to vertical pile 30. That is, the respective primary transfer members 31 face each other in the column direction K at intervals and are set horizontally and at the same height.
次に梁間方向Hの柱位置を決めるための梁間設定用1次
柱芯C1をトランシットにより計測し、1次渡し部材31に
1次柱芯マークG1を付す。この時桁行方向Kに並ぶすべ
ての柱設置用箇所の1次渡し部材31に同時にマークG1を
付す。Next, the primary pillar core C1 for setting the beam interval for determining the pillar position in the beam-to-beam direction H is measured by transit, and the primary transfer core 31 is marked with the primary pillar core mark G1. At this time, the marks G1 are simultaneously attached to the primary transfer members 31 at all the column installation positions arranged in the column row direction K.
(C)第7図及び第8図において、角型パイプ材製の1
対の2次渡し部材32を1次渡し部材31の上に井桁状に架
け渡し、かつ前記1次柱芯C1を中心(対称面)として梁
間方向Hに所定間隔Wを隔てて対称に位置させ、1次渡
し部材31に溶接する。上記所定間隔Wとは後述する上面
型板35の梁間方向Hの幅に相当する寸法である。(C) In FIGS. 7 and 8, 1 made of square pipe material is used.
The pair of secondary transfer members 32 are laid across in parallel to each other on the primary transfer member 31, and are positioned symmetrically with a predetermined interval W in the beam direction H with the primary pillar core C1 as the center (symmetry plane). Weld to the primary transfer member 31. The predetermined distance W is a dimension corresponding to the width of the upper surface template 35 in the inter-beam direction H, which will be described later.
次に桁行方向Kの柱位置を決めるための桁行設定用2次
柱芯C2をトランシットにより計測し、2次渡し部材32に
2次柱芯マークG2を付す。この時梁間方向Hに並ぶすべ
ての柱設置箇所の2次渡し部材32に同時にマークG2を付
す。Next, a secondary column core C2 for setting column columns for determining the column position in the column direction K is measured by a transit, and a secondary column core mark G2 is attached to the secondary transfer member 32. At this time, the marks G2 are simultaneously attached to the secondary transfer members 32 at all the column installation locations arranged in the beam direction H.
(D)第9図及び第10図において、2次渡し部材32上に
取り付けられる上面型板35は、鉄骨柱下端のベースプレ
ート(第11図の18)と同形状に形成されており、その表
面には例えば梁間方向幅及び桁行方向幅の各位置決め用
中心線が十文字状に付されると共に、4つのアンカーボ
ルト挿通孔36が上記中心線に対して正確な位置に形成さ
れている。さらに中心部にはまんじゅう用孔37が形成さ
れている。(D) In FIGS. 9 and 10, the upper surface template 35 mounted on the secondary transfer member 32 is formed in the same shape as the base plate (18 in FIG. 11) at the lower end of the steel column, and its surface For example, each positioning center line having a width in the beam direction and a width in the girder direction is provided in a cross shape, and four anchor bolt insertion holes 36 are formed at accurate positions with respect to the center line. Further, a steamed bun hole 37 is formed in the center.
このような形状の上面型板35を2次渡し部材32に載せ、
上面型板21の梁間方向幅の中心線をマークG1により1次
柱芯C1に合わせ、桁行方向幅の中心線をマークG2により
2次柱芯C2に合わせ、そして上面型35を2次渡し部材32
に溶接する。The upper surface template 35 having such a shape is placed on the secondary transfer member 32,
The center line of the width between beams of the upper surface template 21 is aligned with the primary pillar core C1 by the mark G1, the center line of the width direction of the column is aligned with the secondary pillar core C2 by the mark G2, and the upper surface mold 35 is the secondary transfer member. 32
Weld to.
(E)第1図及び第2図において、上面型板35の各挿通
孔36にアンカーボルト40の上端を挿通し、上側ナット41
より所定寸法にアンカーボルト40を吊り下げる。(E) In FIGS. 1 and 2, the upper end of the anchor bolt 40 is inserted through each insertion hole 36 of the upper template 35, and the upper nut 41 is inserted.
The anchor bolt 40 is suspended to a predetermined size.
アンカーボルト40の吊り下げが完了すると、アンカーボ
ルト下端部に、定着板42及び上記上面型板35と同形状の
下面型板43をナット49により固定する。下面型板43には
振れ止め用の鉄筋45を設けており、該鉄筋45を縦杭30に
溶接等で固定することにより、アンカーボルト40を振れ
止めしている。これでアンカーボルト40のセットが完了
する。When the suspension of the anchor bolt 40 is completed, the fixing plate 42 and the lower surface template 43 having the same shape as the upper surface template 35 are fixed to the lower end portion of the anchor bolt by the nut 49. The lower template 43 is provided with a steel rod 45 for steadying, and the anchor bolt 40 is steady by fixing the steel bar 45 to the vertical pile 30 by welding or the like. This completes the setting of the anchor bolt 40.
(F)上述のようにしてアンカーボルト40を所定位置に
セットした後、第11図及び第12図のような各鉄筋、即ち
ベース筋2、柱主筋5、梁筋7及びフープ筋6を配筋
し、ベースコンクリート部型枠11、柱型枠12及び地中梁
用型枠12a等を組み付け、コンクリートを打設し、基礎
コンクリートを造ると共にまんじゅうう19を設ける。(F) After the anchor bolts 40 are set in the predetermined positions as described above, the reinforcing bars as shown in FIGS. 11 and 12, that is, the base bars 2, the column main bars 5, the beam bars 7, and the hoop bars 6 are arranged. The base concrete part formwork 11, the column formwork 12, the underground beam formwork 12a, etc. are assembled, the concrete is placed, the basic concrete is made, and the manjuu 19 is provided.
そして型枠11、12を外して基礎コンクリート周囲を第2
図の高さEまで埋め戻す。この時基礎コンクリートの上
端部は地面上に露出する。Then remove the formwork 11 and 12 and put the second around the foundation concrete.
Backfill to height E in the figure. At this time, the upper end of the foundation concrete is exposed on the ground.
(G)埋め戻し後、渡し部材31、32上のマークG1、G2を
利用して基礎コンクリートの上端面に各柱芯C1、C2を墨
により付す。(G) After backfilling, the pillar cores C1 and C2 are attached to the upper end surface of the basic concrete by black ink using the marks G1 and G2 on the transfer members 31 and 32.
(H)第2図の上面型板35、1次、2次渡し部材31、32
を縦杭30からガス切断等で取り除き、そして建方時にお
いて、アンカーボルト40の上端部に第11図のような鉄骨
柱17の下端ベースプレート18を締着する。この時基礎コ
ンクリート表面に印した柱芯C1、C2のマークを利用して
一層正確に柱用鉄骨16を取り付けることができる。(H) Upper surface mold plate 35 of FIG. 2, primary and secondary transfer members 31, 32
Is removed from the vertical pile 30 by gas cutting or the like, and at the time of erection, the lower end base plate 18 of the steel column 17 as shown in FIG. 11 is fastened to the upper end portion of the anchor bolt 40. At this time, the pillar steel frames 16 can be attached more accurately by using the marks of the pillar cores C1 and C2 marked on the surface of the basic concrete.
(別の実施例) (1)図示の実施例では1次渡し部材31を桁行方向と直
角に、2次渡し部材32を梁間方向と直角に配置している
が、1次渡し部材31を梁間方向と直角に、2次渡し部材
32を桁行方向と直角に配置してもよい。(Another embodiment) (1) In the illustrated embodiment, the primary transfer member 31 is arranged at right angles to the column direction, and the secondary transfer member 32 is arranged at right angles to the beam-to-beam direction. Secondary passing member at right angles to the direction
32 may be arranged at right angles to the column direction.
(2)アンカーボルトの数は4本に限らず、要求される
強度に応じて任意の数をセットできる。(2) The number of anchor bolts is not limited to four, and any number can be set according to the required strength.
(3)1次渡し部31、2次渡し部材32及び上面型板35
は、ボルトで固定するようにしてもよい。(3) Primary transfer part 31, secondary transfer member 32 and upper surface template 35
May be fixed with bolts.
(発明の効果) 以上説明したように本発明によると: (1)柱主筋5や梁筋7等の配筋前にアンカーボルト40
のセットを行なうので、上記各鉄筋に邪魔されることな
く、また折り曲げたり傾斜させたりすることなく、アン
カーボルト40を所定の位置及び姿勢に容易にかつ正確に
セットできる。(Effects of the Invention) According to the present invention as described above: (1) Anchor bolts 40 before the reinforcement of the column main bars 5, beam bars 7, etc.
Since the setting is performed, the anchor bolt 40 can be easily and accurately set in a predetermined position and posture without being hindered by the respective reinforcing bars and without being bent or inclined.
(2)梁間方向H及び桁行方向Kの位置決めをするため
の各柱芯C1、C2のマークG1、G2を、従来のように地墨を
捨てコンクリート上に付すのではなく、縦杭30の上部に
固定した渡し部材31、32に付すようにしているので、マ
ークを付けるのに上から見易くかつ正確に印し易い。し
かも下げぶりを使うことなく、トランシットにより各柱
部分の芯出しを同時に、簡単に、かつ正確に行なえる。(2) The marks G1 and G2 of the column cores C1 and C2 for positioning in the beam-to-beam direction H and girder row direction K are placed on the top of the vertical pile 30 instead of attaching the ground ink to the concrete as in the conventional method. Since it is attached to the transfer members 31 and 32 fixed to the above, it is easy to see the mark from above and it is easy to accurately mark it. Moreover, it is possible to easily and accurately perform centering of each pillar portion at the same time by the transit without using the lowering.
(3)各柱芯C1、C2のマークG1、G2を、縦杭30の上部に
固定した渡し部材31、32に付すので、捨てコンクリート
上に付す場合に比べ、芯出しが鉄骨柱18の取り付け高さ
と略同一の高さで行なえ、芯狂いが解消される。(3) Since the marks G1 and G2 of the pillar cores C1 and C2 are attached to the transfer members 31 and 32 fixed to the upper portion of the vertical pile 30, the steel pillars 18 are centered more than when mounted on the discarded concrete. It can be performed at almost the same height as the height, eliminating misalignment.
(4)各柱芯C1、C2のマークG1、G2を、縦杭30の上部に
固定した渡し部材31、32に付すので、捨てコンクリート
上に付す場合に比べ、配筋後にスケール,テープ等によ
りアンカーボルトの位置を確認する作業が容易である。(4) Since the marks G1 and G2 of the pillar cores C1 and C2 are attached to the transfer members 31 and 32 fixed to the upper part of the vertical pile 30, as compared with the case where they are attached to abandoned concrete, scales, tapes, etc. can be used after reinforcement. The work to check the position of the anchor bolt is easy.
(5)各柱芯C1、C2のマークG1、G2を、縦杭30の上部に
固定した渡し部材31、32に付すので、雨や地下水等でマ
ークが消えることはなく、しかも埋め戻し後までマーク
が保管できるので、基礎コンクリートの上面への柱芯の
墨出しが容易にかつ正確に行なえる。(5) Since the marks G1 and G2 of each pillar core C1 and C2 are attached to the transfer members 31 and 32 fixed to the upper part of the vertical pile 30, the marks will not disappear due to rain or groundwater, and even after backfilling. Since the mark can be stored, the pillar core can be easily and accurately marked on the upper surface of the foundation concrete.
(4)作業員が現場で下げぶりや水準器を用いる必要が
ないので、作業に熟練を要する必要がなくなり、現場で
の芯出し誤差等が少くなり、作業が単純、正確になる。(4) Since it is not necessary for the worker to lower or use a level on site, it is not necessary for the work to be skilled, and centering errors and the like on site are reduced, and the work is simple and accurate.
第1図は本発明に従ってアンカーボルトのセットを完了
した状態のセット装置の平面図、第2図は第1図の正面
図、第3図、第5図、第7図及び第9図はそれぞれ本発
明によるセット工法の過程を順に示す平面図、第4図、
第6図、第8図及び第10図はそれぞれ第3図、第5図、
第7図及び第9図の正面図、第11図は一般的な基礎コン
クリートの縦断面図、第12図は第11図のXII−XII断面
図、第13図及び第14図は従来工法におけるアンカーボル
トセット時の断面図、第15図は別の従来工法を示す正面
図である。30……縦杭、31……1次渡し部材、32……2
次渡し部材、35……上面型板、40……アンカーボルト、
43……下面型板、45……振り止め用鉄筋FIG. 1 is a plan view of a setting device in a state where anchor bolts have been set according to the present invention, FIG. 2 is a front view of FIG. 1, FIG. 3, FIG. 5, FIG. 7, FIG. The plan view which shows the process of the set construction method by this invention in order, FIG.
FIGS. 6, 8 and 10 are FIGS. 3, 5 and 5, respectively.
7 and 9 are front views, FIG. 11 is a vertical cross-sectional view of general foundation concrete, FIG. 12 is a XII-XII cross-sectional view of FIG. 11, and FIGS. 13 and 14 show conventional construction methods. FIG. 15 is a cross-sectional view when the anchor bolt is set, and FIG. 15 is a front view showing another conventional method. 30 …… Vertical pile, 31 …… Primary transfer member, 32 …… 2
Next-passing member, 35 ... Top template, 40 ... Anchor bolt,
43 …… Bottom template, 45 …… Steel bar
Claims (2)
型枠断面より広い範囲で縦杭を固定し、桁行方向あるい
は梁間方向のいずれかに間隔を隔てて対向する1対の1
次渡し部材を、水平かつ同一高さに縦杭の上部に固定
し、1次渡し部材に、1次渡し部材と交叉する方向に延
びる1次柱芯のマークを付し、1対の2次渡し部材を1
次渡し部材上に井桁状に架け渡して固定し、2次渡し部
材には、1次柱芯と直角方向に延びる2次柱芯のマーク
を付し、上記両柱芯を梁間方向及び桁行方向の各中心と
して、2次渡し部材上に上面型板を固定し、該上面型板
に複数本のアンカーボルトを吊り下げ、アンカーボルト
の下端部を振れ止め固定することを特徴とする鉄骨柱用
アンカーボルトのセット工法。1. A pair of vertical piles are fixed at four corners of each column installation place before the bar arrangement in a range wider than the cross section of the column form, and face each other in the girder direction or the beam direction with a space. 1
The secondary transfer member is fixed horizontally and at the same height on the upper part of the vertical pile, and the primary transfer member is marked with a primary pillar core extending in a direction intersecting with the primary transfer member. 1 transfer member
It is laid in the shape of a cross girder on the next passing member and fixed, the secondary passing member is marked with a secondary pillar core extending in the direction perpendicular to the primary pillar core, and the both pillar cores are arranged in the beam direction and girder direction. As a center of each of the above, for fixing the upper surface template on the secondary transfer member, suspending a plurality of anchor bolts on the upper surface template, and fixing the lower end portion of the anchor bolt to the steady rest, Anchor bolt setting method.
り大きい範囲で固定される縦杭と、水平にかつ同一高さ
に縦杭に固定されると共に桁行方向あるいは梁間方向の
いずれかに間隔を隔てて対向しかつ1次柱芯が付される
1対の1次渡し部材と、該1次渡し部材に井桁状に固定
されて1次柱芯と直角方向の2次柱芯が付される1対の
2次渡し部材と、上記両柱芯を梁間方向及び桁行方向の
各中心として、2次渡し部材の上に固定されるアンカー
ボルト吊り下げ用の上面型板を備えたことを特徴とする
鉄骨柱用アンカーボルトのセット装置。2. Vertical piles fixed to four corners of each place where columns are installed in a range larger than the cross section of the pillar formwork, and fixed vertically to the vertical piles at the same height and in the girder direction or beam direction. A pair of primary transfer members facing each other with a space between them and having a primary pillar core, and secondary pillars fixed to the primary transfer member in a cross beam shape in a direction perpendicular to the primary pillar core. A pair of secondary bridging members to which a core is attached, and an upper surface template for suspending anchor bolts fixed on the secondary bridging member with the pillar cores as the centers in the beam direction and column direction. An anchor bolt setting device for steel columns, which is characterized in that
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16093990A JPH0718253B2 (en) | 1990-06-19 | 1990-06-19 | Setting method and setting device for anchor bolts for steel columns |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16093990A JPH0718253B2 (en) | 1990-06-19 | 1990-06-19 | Setting method and setting device for anchor bolts for steel columns |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0452378A JPH0452378A (en) | 1992-02-20 |
| JPH0718253B2 true JPH0718253B2 (en) | 1995-03-01 |
Family
ID=15725498
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16093990A Expired - Fee Related JPH0718253B2 (en) | 1990-06-19 | 1990-06-19 | Setting method and setting device for anchor bolts for steel columns |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0718253B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110468874A (en) * | 2019-07-30 | 2019-11-19 | 中国一冶集团有限公司 | Auxiliary device and its application method for the installation of pipe gallery finished product steel wind pavilion |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5563409B2 (en) * | 2010-09-03 | 2014-07-30 | 株式会社住金システム建築 | Anchor bolt installation jig and pile foundation construction method using the installation jig |
| CN108532773B (en) * | 2018-07-06 | 2023-08-15 | 中国人民解放军63926部队 | A device (integral type) and positioning method suitable for high-precision pre-embedding of vertical shaft strip keels |
| JP7608077B2 (en) * | 2020-06-18 | 2025-01-06 | センクシア株式会社 | Set of column base anchor structures |
| JP7613873B2 (en) * | 2020-10-12 | 2025-01-15 | センクシア株式会社 | Set of column base anchor structures |
| JP2023008022A (en) * | 2021-07-05 | 2023-01-19 | 日鉄エンジニアリング株式会社 | Foundation structure, and construction method of foundation structure |
-
1990
- 1990-06-19 JP JP16093990A patent/JPH0718253B2/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110468874A (en) * | 2019-07-30 | 2019-11-19 | 中国一冶集团有限公司 | Auxiliary device and its application method for the installation of pipe gallery finished product steel wind pavilion |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0452378A (en) | 1992-02-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0718253B2 (en) | Setting method and setting device for anchor bolts for steel columns | |
| JP2867080B2 (en) | Basement building construction method | |
| JPH09291545A (en) | How to connect columns and piles | |
| JPH02164931A (en) | Foundation construction method for building | |
| JP3612600B2 (en) | Unit anchor and structural steel foundation beam | |
| JPH07247557A (en) | Foundation, column mold, and underground beam made of precast reinforced concrete | |
| US20090165408A1 (en) | Construction elements and methods of construction | |
| JP2567631Y2 (en) | Level adjuster for steel foundation beams | |
| JP2630623B2 (en) | Anchor bolt installation method and anchor bolt support device used for it | |
| JPH066861B2 (en) | Construction method of Kumashindai | |
| JPH0138947B2 (en) | ||
| JPH10317390A (en) | Method for constructing pile-column top end level adjustment structure in building using pile as column | |
| JPH0384165A (en) | Execution of setting of anchor bolt and setting apparatus therefor | |
| JP3244102U (en) | Steel house foundation structure and anchor set used therein | |
| JP3700119B2 (en) | Pillar construction method | |
| JP2504578B2 (en) | Steel frame construction method | |
| JPH11140883A (en) | Positioning support device for foundation bolts for foundation construction | |
| JPH04128430A (en) | concrete foundation | |
| JP2759131B2 (en) | Foundation beam construction method for steel reinforced concrete columns | |
| JPH08246587A (en) | Lacing formwork and wall piecing method using it | |
| JPS6195136A (en) | Construction of multistoried building skeletal by precast reinforced concrete unit | |
| JPH04128429A (en) | Reinforced concrete foundation | |
| JPH06212628A (en) | Anchor bolt fixing device | |
| JP2784449B2 (en) | Steel reinforced concrete foundation | |
| JPS6039816B2 (en) | Anchor bolt burial method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |