JP2874830B2 - Push-up method - Google Patents
Push-up methodInfo
- Publication number
- JP2874830B2 JP2874830B2 JP13714494A JP13714494A JP2874830B2 JP 2874830 B2 JP2874830 B2 JP 2874830B2 JP 13714494 A JP13714494 A JP 13714494A JP 13714494 A JP13714494 A JP 13714494A JP 2874830 B2 JP2874830 B2 JP 2874830B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- push
- span
- work
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、大規模鉄骨建築物を施
工するプッシュアップ工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a push-up method for constructing a large-scale steel building.
【0002】[0002]
【従来の技術】プッシュアップ工法は周知であり、工期
の短縮を図るものとして多用されている。2. Description of the Related Art The push-up method is well known, and is often used to shorten the construction period.
【0003】[0003]
【発明が解決しようとする課題】従来のプッシュアップ
工法においては、プッシュアップする階は、プッシュア
ップ済みの階の下において、躯体工事、設備工事及び仕
上工事を順に行ったのち、プッシュアップを行ってい
る。In the conventional push-up method, the floor to be pushed up is constructed by performing a frame work, an equipment work, and a finishing work in order below the floor that has been pushed up, and then performing the push-up. ing.
【0004】したがって、特に躯体工事は揚重作業を狭
い空間で行うため作業性が悪い。また、各工事はシリー
ズに行うので、プッシュアップのサイクルタイムが長く
なる。[0004] Therefore, especially in the framing work, since the lifting work is performed in a narrow space, the workability is poor. Also, since each work is performed in series, the cycle time of push-up becomes longer.
【0005】本発明は、躯体工事の作業性を向上すると
共に、プッシュアップのリサイクルタイムを短縮するプ
ッシュアップ工法を提供することを目的としている。[0005] It is an object of the present invention to provide a push-up method for improving the workability of skeleton construction and shortening the recycle time of push-up.
【0006】[0006]
【課題を解決するための手段】本発明による工法は、プ
ッシュアップ架台を組立てるプッシュアップ架台組立工
程と、最上階の建方を行う最上階建方工程と、該最上階
をプッシュアップ架台によりプッシュアップする第1回
プッシュアップ工程と、プッシュアップした最上階をプ
ッシュアップ架台にカンヌキで支持すると共に、ジャッ
キダウンする最上階支持工程と、作業床の一外側の仮設
地組サイトにおいて台車上に次階の中央スパンの1ブロ
ックづつの躯体工事を行って作業床に移動し内方部側か
ら順に設備工事及び仕上工事を移動完了時までに行う中
央スパン建入れ工程と、側方から外スパンを台車で中央
スパンに建入れる外スパン建入れ工程と、中央スパン及
び外スパンの建入れを完了したのち最上階及び次階を結
合してカンヌキを解除するカンヌキ解除工程と、最上階
及び次階全体をプッシュアップする第2回プッシュアッ
プとを含み、以下同様の工程を最下階まで繰り返すこと
を特徴としている。According to the construction method of the present invention, a push-up gantry assembling process for assembling a push-up gantry, a top floor erection process for constructing a top floor, and pushing the top floor with the push-up gantry. The first push-up process to raise, the top floor that was pushed up is supported by a push-up stand with kanuki, the top floor support process to jack down, and the next on the bogie at the temporary construction site outside the work floor The center span building process is to carry out the frame work for each block of the center span of the floor, move to the work floor, and perform the equipment work and the finishing work in order from the inside to the completion of the movement, and the outer span from the side. After completing the outer span building process to build the center span and the outer span with a trolley, and combining the top floor and the next floor, A yoke releasing step of dividing, and a second time push-up to push up the entire top floor and Tsugikai is characterized by repeating the same steps until the bottom floor below.
【0007】[0007]
【作用】本発明においては、最上階は露天下で、次階は
露天下の仮設地組サイトでクレーン等により作業性良く
躯体工事が施工できる。In the present invention, the skeleton work can be performed with good workability by using a crane or the like at a temporary ground site on the top floor under the open pit and the next floor under the open pit.
【0008】また、次階は、スライドしながら躯体工
事、設備工事及び仕上工事を行うので、プッシュアップ
のサイクルタイムが短縮される。In the next floor, since skeletal construction, facility construction and finishing construction are performed while sliding, the cycle time of push-up is shortened.
【0009】[0009]
【実施例】以下図面を参照して本発明の実施例を説明す
る。Embodiments of the present invention will be described below with reference to the drawings.
【0010】図1には、施工する基準階の伏図が示され
ている。その基準階の鉄骨1は、複数の内柱2a〜2e
(以下総称する場合は符号2を用いる)と、これら内柱
2を連結する複数の梁3a〜3e(以下総称する場合は
符号3を用いる)と、複数の梁4a〜4d(以下総称す
る場合は符号4を用いる)とからなる中央スパン1A
と、複数の外柱5a〜5e(以下総称する場合は符号5
を用いる)と、これら外柱5を内柱2に連結する複数の
梁6a〜6e(以下総称する場合は符号6を用いる)
と、複数の梁7a〜7d(以下総称する場合は符号7を
用いる)とからなり中央スパン1Aに組付けられる外ス
パン1B、1Bとからなっている。FIG. 1 is a plan view of a reference floor to be constructed. The steel frame 1 on the reference floor has a plurality of inner pillars 2a to 2e.
(Hereinafter, reference numeral 2 is used when collectively referred to), a plurality of beams 3a to 3e connecting these inner columns 2 (hereinafter, reference numeral 3 is used when collectively referred to), and a plurality of beams 4a to 4d (hereinafter collectively referred to as Uses a symbol 4).
And a plurality of outer pillars 5a to 5e (hereinafter collectively referred to as 5
) And a plurality of beams 6 a to 6 e connecting these outer pillars 5 to the inner pillar 2 (the reference numeral 6 will be used when collectively referred to below).
And a plurality of beams 7a to 7d (hereinafter referred to as a reference numeral 7 when collectively referred to) and outer spans 1B and 1B assembled to the center span 1A.
【0011】(1) プッシュアップ架台組立工程(図
2)。(1) Push-up gantry assembly process (FIG. 2).
【0012】作業床A上の所定箇所に、全体を符号10
で示すプッシュアップ架台を組立てる。この架台10
は、4本の柱を備えた架台11と、その架台11の頂部
に設けられ側方に突出自在な複数のカンヌキ12と、架
台10の中心線上に立設されたジャッキ13とからなっ
ている。なお、図中の符号2A、5Aはそれぞれ内柱
2、外柱5に対応する内柱、外柱、Sはスペーサ、15
は後記する中央スパン用台車16用のレールである。At a predetermined location on the work floor A, the entirety is denoted by reference numeral 10.
Assemble the push-up stand shown by. This stand 10
The gantry 11 includes a gantry 11 having four columns, a plurality of cannus 12 provided on the top of the gantry 11 and capable of protruding laterally, and a jack 13 erected on the center line of the gantry 10. . In the drawings, reference numerals 2A and 5A denote inner pillars and outer pillars corresponding to the inner pillar 2 and the outer pillar 5, respectively, S denotes a spacer, 15
Is a rail for the truck 16 for the center span described later.
【0013】(2) 最上階建方工程(図3)。(2) Top floor construction process (FIG. 3).
【0014】屋根R及び床部R−1、R−2からなる最
上階Bの鉄骨建方及び屋根Rの本防水施工を行う。The main waterproof construction of the roof R and the steel frame construction of the top floor B consisting of the floors R-1 and R-2 is performed.
【0015】(3) 第1回プッシュアップ工程(図
4)。(3) First push-up step (FIG. 4).
【0016】ジャッキ13をリフトし、最上階Bをプッ
シュアップする。The jack 13 is lifted, and the top floor B is pushed up.
【0017】(4) 最上階支持工程(図5)。(4) Top floor support step (FIG. 5).
【0018】最上階Bをカンヌキ12を突出して支持
し、ジャッキ13をダウンする。The top floor B is supported by projecting the cannus 12 and the jack 13 is lowered.
【0019】(5) 中央スパン建入れ工程(図6ない
し図11) 作業床Aの長手方向一外側の仮設地組サイトCにおい
て、レール15、15上を移動する中央スパン用台車1
6上に、クレーン17を使用して床部R3、R4からな
る次階B1の中央スパン1Aの第1ブロックD1の鉄骨
建方とデッキプレート床18(図10)の敷き込みすな
わち躯体工事E1を施工する(図6及び図7)。(5) Central span building process (FIGS. 6 to 11) At the temporary construction site C on the outer side in the longitudinal direction of the work floor A, the center span truck 1 moving on the rails 15, 15
6, the crane 17 is used to lay the steel frame of the first block D1 of the first block D1 of the center span 1A of the next floor B1 composed of the floor portions R3 and R4 and lay the deck plate floor 18 (FIG. 10), that is, erection work E1. Perform construction (FIGS. 6 and 7).
【0020】次いで、台車16を作業床A側に1ブロッ
ク分だけ移動し、次の第2ブロックD2の躯体工事E1
を施工すると共に、第1ブロックD1に対し天井内の設
備工事E2を施工する(図8及び図9)。Then, the carriage 16 is moved toward the work floor A by one block, and the skeleton work E1 of the next second block D2 is moved.
And the facility work E2 in the ceiling is performed on the first block D1 (FIGS. 8 and 9).
【0021】次いで、台車16を作業床A1に順次1ブ
ロック分だけ移動し、第1ブロックD1に仕上工事E3
を、第2、第3ブロックD2、D3に仕上工事E3を施
工する(図10)。Next, the carriage 16 is sequentially moved to the work floor A1 by one block, and the finishing work E3 is moved to the first block D1.
Is applied to the second and third blocks D2 and D3 (FIG. 10).
【0022】このようにして台車16が移動して第1〜
第4ブロックD1〜D4が作業床A内に入った時点で
は、全ブロックD1〜D4に対し全工事E1〜E3が略
完了状態となっている(図11)。The carriage 16 moves as described above,
When the fourth blocks D1 to D4 enter the work floor A, all the constructions E1 to E3 are substantially completed for all the blocks D1 to D4 (FIG. 11).
【0023】(6) 外スパン建入れ工程(図12及び
図9)。(6) Outer span setting step (FIGS. 12 and 9).
【0024】レール15、15に直交するレール19、
19上を移動する外スパン用台車20上に、クレーン1
7を使用して外スパンB1の第1ブロックF1の鉄骨建
入れ、デッキプレートを敷き込む。そこで、台車20を
移動して第1ブロックF1をジャッキ13上に載せ、中
央スパン1Aに連結する。ジャッキ13を若干ジャッキ
アップさせ、最上階Bと次階B1の各柱5a、5b、6
a、6bとを溶接して固定する。A rail 19 orthogonal to the rails 15, 15
The crane 1 is placed on the outer span trolley 20 moving on
7, the steel frame of the first block F1 of the outer span B1 is laid, and a deck plate is laid. Then, the carriage 20 is moved to place the first block F1 on the jack 13 and connected to the center span 1A. The jack 13 is slightly jacked up, and the pillars 5a, 5b, 6 of the top floor B and the next floor B1 are respectively.
a and 6b are fixed by welding.
【0025】(7) カンヌキ解除工程(図13)。(7) Canceling step (FIG. 13).
【0026】フリーになっているカンヌキ12を桁方に
移動して解除する。The free Kannuki 12 is moved to the digit side and released.
【0027】(8) 第2回プッシュアップ工程(図1
4)。(8) Second push-up step (FIG. 1)
4).
【0028】ジャッキ13をリフトアップし、最上階B
及び次階B1の第2回プッシュアップを行う。The jack 13 is lifted up and the top floor B
And the second push-up of the next floor B1 is performed.
【0029】以下、(5)中央スパン建入れ工程から
(8)第2回プッシュアップ工程を最下階まで繰り返し
行いながら外壁21(図9)を取付けて完了する。Thereafter, the outer wall 21 (FIG. 9) is mounted while repeating the steps (5) from the center span building step to (8) the second push-up step to the lowest floor, and is completed.
【0030】[0030]
【発明の効果】以上説明したように本発明によれば、露
天下でクレーンにより躯体工事の作業性を向上し、ま
た、次階をスライドしながら躯体工事、設備工事及び仕
上工事を行うので、プッシュアップのサイクルタイムを
短縮することができる。As described above, according to the present invention, the workability of the skeleton work is improved by the crane under the open-air, and the skeleton work, the equipment work and the finish work are performed while sliding on the next floor. The cycle time of push-up can be shortened.
【図1】施工する基準階の伏図。FIG. 1 is a floor plan of a reference floor to be constructed.
【図2】プッシュアップ架台組立工程を説明する側面
図。FIG. 2 is a side view illustrating a push-up gantry assembling process.
【図3】最上階建方工程を説明する側面図。FIG. 3 is a side view illustrating a top floor construction process.
【図4】第1回プッシュアップ工程を説明する側面図。FIG. 4 is a side view illustrating a first push-up step.
【図5】最上階支持工程を説明する側面図。FIG. 5 is a side view illustrating a top floor support step.
【図6】中央スパン建入れ工程の第1ブロック鉄骨建方
等を説明する平面図。FIG. 6 is a plan view for explaining a first block steel frame construction method and the like in a center span construction process.
【図7】図6の正面図。FIG. 7 is a front view of FIG. 6;
【図8】中央スパン建入れ工程の第2ブロック鉄骨建方
等を説明する平面図。FIG. 8 is a plan view illustrating a second block steel frame construction method and the like in the center span construction process.
【図9】図8の斜視図。FIG. 9 is a perspective view of FIG. 8;
【図10】中央スパン建入れ工程の途中経過を説明する
正面図。FIG. 10 is a front view illustrating the progress of the center span setting process.
【図11】中央スパン建入れ工程の最終状態を説明する
側面図。FIG. 11 is a side view illustrating the final state of the center span setting step.
【図12】外スパン建入れ工程を説明する側面図。FIG. 12 is a side view illustrating an outer span setting step.
【図13】カンヌキ解除工程を説明する側面図。FIG. 13 is a side view for explaining a kanuki releasing step.
【図14】第2回プッシュアップ工程を説明する側面
図。FIG. 14 is a side view illustrating a second push-up step.
A・・・作業床 B・・・最上階 B1・・・次階 C・・・仮設地組サイト D1、D2・・・ブロック E1・・・躯体工事 E2・・・設備工事 E3・・・仕上工事 F1、F2・・・ブロック R・・・屋根 R1、R2・・・床部 S・・・スペーサ 1・・・鉄骨 1A・・・中央スパン 1B・・・外スパン 2・・・内柱 3、4、6、7・・・梁 5・・・外柱 10・・・プッシュアップ架台 11・・・架台 12・・・カンヌキ 13・・・ジャッキ 14・・・仮設柱 15、19・・・レール 16・・・中央スパン用台車 17・・・クレーン 18・・・デッキプレート 20・・・外スパン用台車 21・・・外壁 A: Work floor B: Top floor B1: Next floor C: Temporary site construction site D1, D2: Block E1: Frame work E2: Facility work E3: Finish Construction F1, F2 ... Block R ... Roof R1, R2 ... Floor S ... Spacer 1 ... Steel frame 1A ... Central span 1B ... Outer span 2 ... Inner pillar 3 , 4, 6, 7 ... Beam 5 ... Outer pillar 10 ... Push-up stand 11 ... Stand 12 ... Kannuki 13 ... Jack 14 ... Temporary pillar 15, 19 ... Rail 16: Truck for central span 17: Crane 18: Deck plate 20: Truck for outer span 21: Outer wall
───────────────────────────────────────────────────── フロントページの続き (72)発明者 池田 秀機 東京都港区元赤坂一丁目3番8号 鹿島 建設株式会社 東京支店内 (72)発明者 富田 昭夫 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (72)発明者 荻原 行正 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (72)発明者 大脇 光久 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (58)調査した分野(Int.Cl.6,DB名) E04B 1/35 E04G 21/14 ──────────────────────────────────────────────────の Continuing on the front page (72) Inventor Hideki Ikeda 1-3-8 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. Tokyo Branch (72) Inventor Akio Tomita 1-2-2 Moto-Akasaka, Minato-ku, Tokyo No. 7 Kashima Construction Co., Ltd. (72) Inventor Yukimasa Ogihara 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Mitsuhisa Owaki 1-2-2 Moto-Akasaka, Minato-ku, Tokyo 7 Kashima Construction Co., Ltd. (58) Field surveyed (Int. Cl. 6 , DB name) E04B 1/35 E04G 21/14
Claims (1)
アップ架台組立工程と、最上階の建方を行う最上階建方
工程と、該最上階をプッシュアップ架台によりプッシュ
アップする第1回プッシュアップ工程と、プッシュアッ
プした最上階をプッシュアップ架台にカンヌキで支持す
ると共に、ジャッキダウンする最上階支持工程と、作業
床の一外側の仮設地組サイトにおいて台車上に次階の中
央スパンの1ブロックづつの躯体工事を行って作業床に
移動し内方部側から順に設備工事及び仕上工事を移動完
了時までに行う中央スパン建入れ工程と、側方から外ス
パンを台車で中央スパンに建入れる外スパン建入れ工程
と、中央スパン及び外スパンの建入れを完了したのち最
上階及び次階を結合してカンヌキを解除するカンヌキ解
除工程と、最上階及び次階全体をプッシュアップする第
2回プッシュアップとを含み、以下同様の工程を最下階
まで繰り返すことを特徴とするプッシュアップ工法。1. A push-up gantry assembly process for assembling a push-up gantry, a top floor erection process for constructing a top floor, and a first push-up process for pushing up the top floor with the push-up gantry. The top floor that has been pushed up is supported by a push-up stand with a kanuki and the top floor support process of jacking down, and a frame of one block of the center span of the next floor on a bogie at a temporary construction site outside the work floor Central span building process where construction work is carried out to the work floor and equipment and finishing work is completed in order from the inside to the completion of the movement, and outer span construction where the outer span is built from the side with a trolley to the center span After completing the installation of the center span and the outer span, combining the top floor and the next floor to release the kanuki, And a second push-up for pushing up the entire next floor, and thereafter repeating the same steps up to the lowest floor.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13714494A JP2874830B2 (en) | 1994-06-20 | 1994-06-20 | Push-up method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13714494A JP2874830B2 (en) | 1994-06-20 | 1994-06-20 | Push-up method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH084122A JPH084122A (en) | 1996-01-09 |
| JP2874830B2 true JP2874830B2 (en) | 1999-03-24 |
Family
ID=15191850
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP13714494A Expired - Lifetime JP2874830B2 (en) | 1994-06-20 | 1994-06-20 | Push-up method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2874830B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2024000633A (en) * | 2022-06-21 | 2024-01-09 | 株式会社大林組 | construction method |
-
1994
- 1994-06-20 JP JP13714494A patent/JP2874830B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH084122A (en) | 1996-01-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2874830B2 (en) | Push-up method | |
| JP3732586B2 (en) | Method and apparatus for constructing steel structure | |
| JP2022089706A (en) | Building inside staircase preceding construction method | |
| JP2979039B2 (en) | Large space building construction equipment | |
| JP2985110B2 (en) | Construction method of steel roof | |
| JP2746321B2 (en) | Push-up construction method of steel structure | |
| JP2723620B2 (en) | Wooden construction method | |
| JPS6237439A (en) | Traveling method | |
| JP2884396B2 (en) | Construction method of building structure and lifting device of building structure | |
| JP2583462B2 (en) | Reconstruction construction method of building in operation | |
| JPH06185120A (en) | Construction method for upper structure of roof, etc. | |
| JP2547920B2 (en) | Push-up method and equipment for large span structures | |
| JPH0518132A (en) | Jack-up type construction method for steel structure such as tower type stereoscopic parking lot | |
| JP3122915B2 (en) | Single layer truss roof push-up method | |
| JPH11324307A (en) | Mobile scaffold | |
| JPH0431524A (en) | Construction method of dome frame | |
| JPH06193275A (en) | Temporary roof at construction site and building construction method using the same | |
| JPS5942155B2 (en) | Building extension method | |
| JP3225455B2 (en) | How to build a building | |
| JPH08120785A (en) | How to construct a portal frame structure | |
| JP2755043B2 (en) | How to install long structures | |
| JPH06146594A (en) | Building construction method | |
| JPS6332939B2 (en) | ||
| JPH056621B2 (en) | ||
| JPH05311749A (en) | Construction method of building |