JP2583462B2 - Reconstruction construction method of building in operation - Google Patents
Reconstruction construction method of building in operationInfo
- Publication number
- JP2583462B2 JP2583462B2 JP2404382A JP40438290A JP2583462B2 JP 2583462 B2 JP2583462 B2 JP 2583462B2 JP 2404382 A JP2404382 A JP 2404382A JP 40438290 A JP40438290 A JP 40438290A JP 2583462 B2 JP2583462 B2 JP 2583462B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- existing building
- building
- constructed
- roof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は稼動中の工場等の建物を
改築する施工法に係るものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for remodeling a building such as an operating factory.
【0002】[0002]
【従来の技術】図12及び図13は従来のこの種の施工
法の概要を示し、稼動中の建物Aの外周に沿って、新設
の外周基礎a、外周柱b、桁梁c等を構築するととも
に、稼動中の建物内に内部基礎d、中柱e、仮設梁fを
構築し、前記各梁上にスライド用レールgを敷設すると
ともに、建物妻側外周に屋根トラスh、1スライド分地
組する作業構台iを仮設する。2. Description of the Related Art FIGS. 12 and 13 show an outline of a conventional construction method of this kind, in which a new outer foundation a, an outer pillar b, a girder beam c and the like are constructed along the outer periphery of a building A in operation. At the same time, an internal foundation d, a middle pillar e, and a temporary beam f are constructed in the operating building, a slide rail g is laid on each of the beams, and a roof truss h on the outer side of the building wife side for one slide. A work gantry i to be laid is temporarily provided.
【0003】同作業構台i上で1スライド分の屋根トラ
スhを地組して前記スライド用レールg上に載置して後
述のスライド工法によって同レール上を横引きし、前記
屋根トラスhを稼動中の建物A上に移設し、固定してか
ら屋根仕上げ及び外装をする。なお作業構台i上で屋根
仕上げ等を先行して施工してからスライドしてもよい。On the work gantry i, a roof truss h for one slide is laid, mounted on the slide rail g, and laterally pulled on the rail by a slide method described later, to thereby remove the roof truss h. After being relocated to the building A in operation and fixed, the roof is finished and the exterior is finished. The work may be slid on the work gantry i after finishing the roof finishing or the like in advance.
【0004】図13は前記屋根トラスhのスライド状態
を示し、図14は同屋根トラスhに装架された移動装置
jで前記レールg上を移動せしめるもので、前記屋根ト
ラスhより垂設した一双のブラケツトkに装架された揺
れ止め滑車lで前記レールgを挟着し、屋根トラスhが
前記レールg上を円滑にスライドせしめるものである。FIG. 13 shows the sliding state of the roof truss h, and FIG. 14 shows the roof truss h which is moved on the rail g by a moving device j mounted on the roof truss h. The rail g is sandwiched between the anti-sway pulleys 1 mounted on a pair of brackets k, and the roof truss h slides smoothly on the rail g.
【0005】かくして稼動中の既存建物Aを被覆するよ
うに、新設の建物を建築したのち、前記建物Aを改築す
るものである。なお複数階の新設建物の場合には、前記
屋根トラスの代りに2階梁をスライド工法で横引きし
て、2階床を施工してから複数階の建物に改築すること
も可能である。[0005] Thus, after a new building is constructed so as to cover the existing building A in operation, the building A is renovated. In the case of a new building having a plurality of floors, it is also possible to rebuild the building with a plurality of floors after constructing the second floor by traversing the second floor beam by a sliding method instead of the roof truss.
【0006】図中mは既存の柱、nは作業エリヤを囲む
仮囲い、qは支柱である。In the figure, m is an existing column, n is a temporary enclosure surrounding the work area, and q is a column.
【0007】[0007]
【発明が解決しようとする課題】前記従来工法において
は、内部基礎、中柱、仮設梁を構築する必要があり、稼
動中の建物内に作業スペースと機材等の搬出入路を確保
して工事をするので、改築工事の期間中は大面積の建築
工事用のスペースを取られ、生産スペースが犠牲とな
り、また仮囲いや通行車両等により生産ラインの動線が
遮断されるため、生産活動が阻害されるという問題があ
った。In the above-mentioned conventional method, it is necessary to construct an internal foundation, a center pillar and a temporary beam, and a work space and a carry-in / out path for equipment and the like are secured in an operating building. During the renovation work, a large area of construction space will be taken up, and production space will be sacrificed.Also, production lines will be interrupted by temporary enclosures and traffic vehicles. There was a problem of being inhibited.
【0008】本発明は前記従来技術の有する問題点に鑑
みて提案されたもので、その目的とする処は、稼動中の
工場等の建物を、生産活動をできるだけ阻害しないよう
に改築することができる施工法を提供する点にある。The present invention has been proposed in view of the above-mentioned problems of the prior art. It is an object of the present invention to rebuild an operating factory or the like so as to minimize production activities. The point is to provide a possible construction method.
【0009】[0009]
【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る稼動中建物の改築工法は、稼動中の既
存建物の外周に沿って新設の基礎を構築するとともに、
同基礎上に外周柱を施工し、同新設外周柱の柱頭近傍に
設けたブラケツト上、及び前記既存建物の支柱上にスラ
イド用レールを架設する第1工程と、前記既存建物の妻
側外周に仮設した作業構台上で、屋根トラスまたは2階
梁を1スライド相当分地組し、前記レール上を横引きし
て1スライド分づつ移動せしめ、前記屋根トラスまたは
2階梁で前記既存建物の外部上面を被覆したのち、屋根
または2階床を構築する第2工程と、同屋根または2階
床を作業スペース及び搬出入路として前記既存建物の内
部に内部基礎及び中柱を新設するとともに、前記屋根の
仕上げ、または上層階の施工及び前記既存建物の外装を
する第3工程と、前記屋根仕上げまたは上層階の施工及
び既存建物の外装が完了したのち、同既存建物を解体し
て内部を改修する第4工程とから構成されている。In order to achieve the above object, the present invention relates to a method for rebuilding an operating building according to the present invention, which constructs a new foundation along the periphery of an existing operating building.
A first step of constructing an outer pillar on the same foundation, erection of a rail for sliding on a bracket provided near the capital of the new outer pillar, and on a support of the existing building; On the temporary work gantry, lay the roof truss or the second floor beam equivalent to one slide, move it sideways on the rail and move it one slide at a time, and move the roof truss or the second floor beam outside the existing building with the roof truss or the second floor beam. After covering the upper surface, a second step of constructing a roof or a second floor, and installing a new internal foundation and a middle pillar inside the existing building as a work space and a loading / unloading path using the same roof or the second floor, After finishing the roof, or the upper floor construction and exterior of the existing building, and the roof finishing or upper floor construction and exterior of the existing building, disassemble the existing building and renovate the interior Do It is composed of a 4 step.
【0010】また請求項2の発明は稼動中の既存建物の
外周に沿って新設の基礎を構築するとともに、同基礎上
に外周柱等の構造材を施工し、同新設外周柱の柱頭近傍
のブラケツト上と、前記既存建物の支柱上にスライド用
レールを架設する第1工程と、前記既存建物の妻側外周
に仮設した作業構台上で2階梁を1スライド相当分づつ
地組し、前記レール上を横引きして1スライド分づつ移
動せしめ、2階梁で前記既存建物の外部上面を被覆する
ように架構したのち屋根または2階床を構築する第2工
程と、前記既存建物の支柱で前記2階梁を仮支持して、
2階床上を作業スペース及び搬出入路として上階層を施
工するとももに、前記既存建物階の外装をする第3工程
と、前記上階層の施工及び既存建物階の外装が完了し、
稼動していた装置を上階層に移設したのち、前記既存建
物内の内部基礎及び中柱を施工したのち、前記既存建物
を解体して2階梁の仮支持状態を解放して、同既存建物
の内部を改修する第4工程とから構成されている。According to a second aspect of the present invention, a new foundation is constructed along the outer periphery of an existing building in operation, and a structural material such as an outer pillar is constructed on the foundation. A first step of erection of a slide rail on a bracket and on a column of the existing building, and erection of a second-story beam equivalent to one slide on a work gantry temporarily provided on a wife side outer periphery of the existing building; A second step of laterally pulling on the rail and moving one slide at a time, constructing a roof or a second floor after framing the outer upper surface of the existing building with a second floor beam, and supporting columns of the existing building; Temporarily support the second floor beam with
While the upper floor is constructed as a work space and a loading / unloading path on the second floor, the third step of exteriorizing the existing building floor, and the construction of the upper floor and the exterior of the existing building floor are completed,
After relocating the operating device to the upper level, constructing the internal foundation and the center pillar in the existing building, dismantling the existing building and releasing the temporary support of the second floor beams, And a fourth step of repairing the inside of the device.
【0011】[0011]
【作用】本発明によれば既存建物の外周に沿って構築さ
れた新設の基礎上の外周柱と、既存建物の支柱上に架設
されたスライド用レールに沿って、同既存建物の妻側外
周に仮設された作業構台で地組された屋根トラス、また
は2階梁を地組して横引きし、前記既存建物の外部上面
を被覆したのち屋根または2階床を構築して、これに稼
動中の既存建物内の内部基礎及び中柱、仮設梁の施工ス
ペースと搬出入路を設けることによって、基礎工事と1
階中柱の建方工事に必要な小面積の仮囲いを設けるだけ
でよくなり、また車両等は2階床上が通行することによ
り、稼動中の既存建物の生産ラインの動線を遮断するこ
とがなく、生産活動が阻害されることがない。According to the present invention, the outer peripheral pillar on the new foundation constructed along the outer periphery of the existing building and the outer peripheral side of the existing building along the sliding rail erected on the support of the existing building are provided. A roof truss or a two-story beam laid on a temporary work gantry is laid and laid sideways to cover the external upper surface of the existing building, and then a roof or a two-story floor is constructed and operated. By providing the construction space and loading / unloading path for the internal foundation, center pillars, and temporary beams in the existing building inside,
It is only necessary to provide a temporary enclosure with a small area necessary for the construction of the middle floor pillars, and vehicles etc. should block the flow line of the production line of the existing building in operation by passing on the second floor. And production activities are not hindered.
【0012】請求項2の発明は前記スライド用レールに
沿って2階梁を1スライド分づつ移動せしめ、2階梁で
既存建物の外部上面を被覆して2階床を作業スペース及
び搬出入路として上層階の施工と、既存建物の外装を完
了したのち生産装置を上層階に移動して、既存建物内の
基礎、中柱を施工することによって改築期間中でも生産
活動を阻害することのないようにしたものである。According to a second aspect of the present invention, the second floor beam is moved by one slide along the slide rail, and the outer floor of the existing building is covered with the second floor beam, and the second floor is used as a work space and a loading / unloading path. After completing the construction of the upper floor and the exterior of the existing building, move the production equipment to the upper floor and construct the foundation and center pillar in the existing building so that production activities will not be hindered even during the renovation period It was made.
【0013】[0013]
【実施例】以下本発明を図面について説明すると、図1
乃至図6は本発明の第1の実施例を示し、1は稼動中の
既存建物で、図示の実施例では平家建鋸屋根造工場であ
る。また2は、支柱を示す。而して前記既存建物1の外
周に基礎3及び外周柱4を構築する(図1参照)図中5
は外周柱4の柱頭付近に設けられたブラケツト、6は地
中梁である。BRIEF DESCRIPTION OF THE DRAWINGS FIG.
FIG. 6 to FIG. 6 show a first embodiment of the present invention, in which 1 is an existing building in operation, and in the embodiment shown in FIG. Reference numeral 2 denotes a support. Thus, a foundation 3 and an outer pillar 4 are constructed on the outer periphery of the existing building 1 (see FIG. 1).
Is a bracket provided near the capital of the outer column 4, and 6 is an underground beam.
【0014】次いで前記ブラケツト5及び支柱2の上部
に既存建物1の外部よりクレーンによってスライド用レ
ール7を敷設したのち、前記従来例と同様に既存建物1
の妻側外周に仮設された作業構台で地組された1スライ
ド相当分の2階梁8を既述のスライド工法によって建屋
の屋根を覆うように順次前記レール7上をスライドさ
せ、既存建物1の全面積に亘って建方する。(図2参
照)次いで前記2階梁8上に2階床9を施工する。なお
同2階床9は例えば2階梁8上にデツキプレートを敷設
したのち、床鉄筋を配筋してコンクリートを打設して施
工する。次いで既存建物1の1階床に新設する内部基礎
10、1階中柱11の施工に必要な面積の仮囲い12と
昇降用の梯子(図示せず)を設置し、2階床9を作業ス
ペースとするとともに、同床9に設けた開口部を機材等
の搬出入路として、既存建物1の内部基礎10や1階中
柱11を構築して、同中柱11を2階梁8と結合して、
床の開口部を閉鎖する。(図3参照)図中13は2階床
9上に設置された走行クレーンである。Next, a slide rail 7 is laid by a crane from the outside of the existing building 1 above the bracket 5 and the column 2 and then the existing building 1 is reconstructed in the same manner as in the conventional example.
The second floor beam 8 corresponding to one slide erected by the work gantry temporarily provided on the wife's side outer periphery is sequentially slid on the rail 7 so as to cover the roof of the building by the slide method described above. Is built over the entire area of. Next, a second floor 9 is constructed on the second beam 8 (see FIG. 2). The second floor 9 is constructed, for example, by laying a deck plate on the second floor beam 8 and then arranging floor reinforcing bars and casting concrete. Next, a temporary enclosure 12 and a ladder (not shown) for ascending and descending are installed on the first floor of the existing building 1 for the inner foundation 10 and the middle pillar 11 on the first floor, and the second floor 9 is worked. In addition to providing a space, the opening provided in the floor 9 is used as a carry-in / out path for equipment and the like, and the internal foundation 10 and the first floor middle pillar 11 of the existing building 1 are constructed. Combine
Close floor openings. (See FIG. 3) 13 is a traveling crane installed on the second floor 9.
【0015】次いで2階床9を作業スペース及び機材の
搬出入路として、従来工法またはスライド工法によって
2階建屋14を施工する。(図4参照)図中15は2階
柱、16は2階外壁、17は2階屋根である。かくして
新設の2階建屋14の建設が完了すると、前記既存建物
1の生産設備を2階に移設して生産を継続する。(図5
参照)次いで新設1階建屋18内の既存建物1を解体し
たのち、新設1階建屋18の改修及び外装をして新らし
い生産設備を設置する。(図6参照)図7乃至図11は
本発明の他の実施例を示し、平建鋸屋根工場よりなる既
存建物1の外周に基礎3及び外周柱4を構築する。(図
7参照)前記外周柱4の柱頭付近に設けられたブラケツ
ト5及び既存建物1の支柱2にスライド用レール7を敷
設し、前記実施例と同様にスライド工法により2階梁8
を建屋の屋根を覆うように全面積に亘って建方したの
ち、前記実施例と同様に2階床9を施工する。(図8参
照)次いで既存建物1の支柱2で前記2階梁8を仮支持
して、2階床9を作業スペース及び機材の搬出入路とし
て公知の工法で2階新設建屋19を施工する。(図9参
照)2階新設建屋19の施工と1階外周の外装20が完了
し、既存建物1内において稼動していた装置を、2階新
設建屋19に移したのち、既存建物1内で内部基礎2
1、中柱22を公知の工法で施工してから、既存建物1
の屋根を解体するとともに、2階梁8を仮支持状態から
解放する。(図10参照)次いで新設1階建屋18内の
既存建物1を解体した後、新設1階建屋23の内部を改
装して新しい生産設備を新設する。(図11参照)Next, a second floor building 14 is constructed by a conventional method or a slide method using the second floor 9 as a work space and a path for carrying in and out equipment. (See FIG. 4) In the figure, 15 is a second floor pillar, 16 is a second floor outer wall, and 17 is a second floor roof. When the construction of the new two-story building 14 is completed, the production facilities of the existing building 1 are relocated to the second floor to continue the production. (FIG. 5
Next, after dismantling the existing building 1 in the new one-story building 18, the new one-story building 18 is repaired and exteriorly installed to install new production facilities. (See FIG. 6) FIGS. 7 to 11 show another embodiment of the present invention, in which a foundation 3 and an outer pillar 4 are constructed on the outer periphery of an existing building 1 consisting of a flat-saw roof factory. (See FIG. 7) A slide rail 7 is laid on the bracket 5 provided near the capital of the outer peripheral column 4 and the column 2 of the existing building 1, and the second floor beam 8 is formed by the slide method in the same manner as in the previous embodiment.
Is constructed over the entire area so as to cover the roof of the building, and then the second floor 9 is constructed in the same manner as in the above embodiment. (See FIG. 8) Next, the second floor beams 8 are temporarily supported by the columns 2 of the existing building 1, and the second floor building 9 is constructed by a known construction method using the second floor 9 as a work space and a loading / unloading path for equipment. . (Refer to FIG. 9) After the construction of the new building 19 on the second floor and the exterior 20 on the outer circumference of the first floor are completed, the equipment operating in the existing building 1 is moved to the new building 19 on the second floor, Internal foundation 2
1. After the middle pillar 22 is constructed by a known construction method, the existing building 1
Is dismantled, and the second floor beams 8 are released from the temporarily supported state. (See FIG. 10) Next, after dismantling the existing building 1 in the new first-floor building 18, the inside of the new first-floor building 23 is renovated to newly install a new production facility. (See Fig. 11)
【0016】[0016]
【発明の効果】本発明に係る稼動中建物の改築施工法に
よれば前記したように、既存建物の外周に沿って構築さ
れた外周柱に設けたブラケツト、及び既存建物の支柱上
に敷設されたスライド用レールに沿って移動させ、屋根
トラスまたは2階梁で前記既存建物の外部上面を被覆し
たのち構築された2階床に稼動中の建物内部における内
部基礎、中柱、梁を施工するための作業スペースと機材
搬出入路を設けることによって、作業スペースが基礎工
事と一階中柱の建方工事に必要な仮囲い内の小面積に限
られる。また通行車両等は前記2階床上を通行するの
で、生産ラインの動線を遮断することはなく、平常通り
の安全作業が行なわれるとともに、生産活動を阻害する
ことがない。According to the method for rebuilding an operating building according to the present invention, as described above, the bracket provided on the outer peripheral column constructed along the outer periphery of the existing building, and the bracket installed on the supporting column of the existing building. After moving along the sliding rails and covering the external upper surface of the existing building with a roof truss or a second floor beam, construct the internal foundation, middle pillars and beams inside the operating building on the constructed second floor. The work space is limited to a small area within the temporary enclosure required for the foundation work and the construction of the middle pillar on the first floor. Further, since the passing vehicles and the like pass on the second floor, the traffic lines of the production line are not interrupted, the safety work is performed as usual, and the production activities are not hindered.
【0017】請求項2の発明によれば、2階以上の建築
が完了して稼動中の既存建物内の生産装置を移設してか
ら、稼動中であった1階建物の内部で基礎工事や1階中
柱の建方工事等を施工することになるので、改築期間中
でも生産活動を一切阻害することがない。また2階以上
に新規の生産ラインを稼動させてから1階の生産設備を
移設することによって、生産ラインの一時停止期間をな
くすことも可能となる。According to the second aspect of the present invention, after the construction on the second floor or more is completed and the production equipment in the existing building that is operating is relocated, foundation work and the like are performed inside the operating first-floor building. Since the construction work for the middle pillar on the first floor will be performed, production activities will not be hindered at all during the renovation period. In addition, by moving a new production line to the second floor or higher and then relocating production equipment on the first floor, it is possible to eliminate the suspension period of the production line.
【図1】本発明に係る稼動中建物の改築工法の一実施例
の第1の工程を示す縦断面図である。FIG. 1 is a longitudinal sectional view showing a first step of an embodiment of a method for rebuilding an operating building according to the present invention.
【図2】前記工法の第2の工程を示す縦断面図である。FIG. 2 is a vertical sectional view showing a second step of the method.
【図3】前記工法の第3の工程を示す縦断面図である。FIG. 3 is a longitudinal sectional view showing a third step of the method.
【図4】前記工程の第4の工程を示す縦断面図である。FIG. 4 is a vertical sectional view showing a fourth step of the above step.
【図5】前記工程の第5の工程を示す縦断面図である。FIG. 5 is a longitudinal sectional view showing a fifth step of the above step.
【図6】前記工法の第6の工程を示す縦断面図である。FIG. 6 is a longitudinal sectional view showing a sixth step of the method.
【図7】本発明の工法の他の実施例の第1の工程を示す
縦断面図である。FIG. 7 is a longitudinal sectional view showing a first step of another embodiment of the method of the present invention.
【図8】前記工法の第2の工程を示す縦断面図である。FIG. 8 is a vertical sectional view showing a second step of the method.
【図9】前記工法の第3の工程を示す縦断面図である。FIG. 9 is a longitudinal sectional view showing a third step of the method.
【図10】前記工法の第4の工程を示す縦断面図であ
る。FIG. 10 is a longitudinal sectional view showing a fourth step of the method.
【図11】前記工程の第5の工程を示す縦断面図であ
る。FIG. 11 is a longitudinal sectional view showing a fifth step of the above step.
【図12】従来工法の実施状況を示す平面図である。FIG. 12 is a plan view showing an implementation state of a conventional method.
【図13】屋根トラスの移動状態を示す縦断側面図であ
る。FIG. 13 is a vertical side view showing a moving state of the roof truss.
【図14】移動装置の要部拡大図である。FIG. 14 is an enlarged view of a main part of the moving device.
1 既存建物 2 支柱 3 基礎 4 外周柱 5 ブラケツト 6 梁 7 スライド用レール 8 2階梁 9 2階床 10 内部基礎 11 1階中柱 14 2階建屋 15 2階柱 18 新設1階建屋 19 2階新設建屋 21 内部基礎 22 中柱 DESCRIPTION OF SYMBOLS 1 Existing building 2 Support 3 Foundation 4 Perimeter pillar 5 Bracket 6 Beam 7 Slide rail 8 2nd floor beam 9 2nd floor 10 Internal foundation 11 1st floor middle pillar 14 2nd floor building 15 2nd floor pillar 18 New 1st floor building 19 2nd floor New building 21 Internal foundation 22 Middle pillar
フロントページの続き (72)発明者 朋田 秀一 東京都渋谷区千駄ヶ谷四丁目6番15号 株式会社フジタ内 (72)発明者 迫田 英裕 東京都渋谷区千駄ヶ谷四丁目6番15号 株式会社フジタ内 (56)参考文献 特開 昭63−67349(JP,A) 特公 昭61−14302(JP,B2)Continued on the front page (72) Inventor Shuichi Tomoda 4-6-115 Sendagaya, Shibuya-ku, Tokyo Fujita Co., Ltd. 56) References JP-A-63-67349 (JP, A) JP-B-61-14302 (JP, B2)
Claims (2)
基礎を構築するとともに、同基礎上に外周柱を施工し、
同新設外周柱の柱頭近傍に設けたブラケツト上、及び前
記既存建物の支柱上にスライド用レールを架設する第1
工程と、前記既存建物の妻側外周に仮設した作業構台上
で、屋根トラスまたは2階梁を1スライド相当分地組
し、前記レール上を横引きして1スライド分づつ移動せ
しめ、前記屋根トラスまたは2階梁で前記既存建物の外
部上面を被覆したのち、屋根または2階床を構築する第
2工程と、同屋根または2階床を作業スペース及び搬出
入路として前記既存建物の内部に内部基礎及び中柱を新
設するとともに、前記屋根の仕上げ、または上層階の施
工及び前記既存建物の外装をする第3工程と、前記屋根
仕上げまたは上層階の施工及び既存建物の外装が完了し
たのち、同既存建物を解体して内部を改修する第4工程
とからなることを特徴とする稼動中建物の改築施工法。1. A new foundation is constructed along the periphery of an existing building in operation, and an outer pillar is constructed on the foundation.
A first slide rail is to be installed on a bracket provided near the capital of the new outer column and on a column of the existing building.
A roof truss or a second-floor beam is laid by an amount equivalent to one slide on a work gantry temporarily provided on the wife side outer periphery of the existing building, and the rail is laterally moved to move one slide at a time. A second step of constructing a roof or a second floor after covering the outer top surface of the existing building with a truss or a second floor beam, and using the roof or the second floor as a work space and a loading / unloading path inside the existing building. After the completion of the roof finishing, or the construction of the upper floor and the exterior of the existing building, and the completion of the roof finishing or construction of the upper floor and the exterior of the existing building, the new foundation and the inner pillar are newly constructed. And rebuilding the existing building and renovating the interior.
基礎を構築するとともに、同基礎上に外周柱等の構造材
を施工し、同新設外周柱の柱頭近傍のブラケツト上と、
前記既存建物の支柱上にスライド用レールを架設する第
1工程と、前記既存建物の妻側外周に仮設した作業構台
上で2階梁を1スライド相当分づつ地組し、前記レール
上を横引きして1スライド分づつ移動せしめ、2階梁で
前記既存建物の外部上面を被覆するように架構したのち
屋根または2階床を構築する第2工程と、前記既存建物
の支柱で前記2階梁を仮支持して、2階床上を作業スペ
ース及び搬出入路として上階層を施工するとももに、前
記既存建物階の外装をする第3工程と、前記上階層の施
工及び既存建物階の外装が完了し、稼動していた装置を
上階層に移設したのち、前記既存建物内の内部基礎及び
中柱を施工したのち、前記既存建物を解体して2階梁の
仮支持状態を解放して、同既存建物の内部を改修する第
4工程とからなることを特徴とする稼動中の既存建物の
改築施工法。2. A new foundation is constructed along an outer periphery of an existing building in operation, and a structural material such as an outer pillar is constructed on the foundation, on a bracket near a capital of the newly installed outer pillar,
A first step of erecting a slide rail on the support of the existing building, and laying a second-story beam equivalent to one slide on a work gantry temporarily installed on the outer periphery of the existing building on the side of the wife, and traverse the rail. A second step of pulling and moving one slide at a time, constructing a roof or a second-floor floor after covering the outer upper surface of the existing building with a second-floor beam, and supporting the second floor with a support of the existing building. A third step of temporarily supporting the beams and constructing the upper floor as a work space and a loading / unloading path on the second floor, and exteriorizing the existing building floor, and performing the upper floor construction and the existing building floor After the exterior has been completed and the operating equipment has been relocated to the upper level, the internal foundation and the middle pillar in the existing building have been constructed, and then the existing building has been dismantled to release the temporary support of the second floor beams. And the fourth process of renovating the interior of the existing building Renovation construction methods of the existing building in operation, wherein the door.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2404382A JP2583462B2 (en) | 1990-12-20 | 1990-12-20 | Reconstruction construction method of building in operation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2404382A JP2583462B2 (en) | 1990-12-20 | 1990-12-20 | Reconstruction construction method of building in operation |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH04221173A JPH04221173A (en) | 1992-08-11 |
| JP2583462B2 true JP2583462B2 (en) | 1997-02-19 |
Family
ID=18514061
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2404382A Expired - Fee Related JP2583462B2 (en) | 1990-12-20 | 1990-12-20 | Reconstruction construction method of building in operation |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2583462B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4971006B2 (en) * | 2007-03-30 | 2012-07-11 | 安藤建設株式会社 | Clean room renovation method and temporary facilities for renovation |
| CN103114736A (en) * | 2013-01-31 | 2013-05-22 | 攀钢集团工程技术有限公司 | Online renovation method of sintering material-loading system |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0237442B2 (en) * | 1984-06-29 | 1990-08-24 | Kensetsu Kiso Eng | DOROKAKUFUKUKOHO |
| JPH0633627B2 (en) * | 1986-09-10 | 1994-05-02 | 清水建設株式会社 | New construction method on existing facility |
-
1990
- 1990-12-20 JP JP2404382A patent/JP2583462B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH04221173A (en) | 1992-08-11 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106894639A (en) | The hanging reverse construction method of installation of steel construction under a kind of | |
| JP2002235443A (en) | Intermediate story steel frame traveling construction method | |
| JP3042310B2 (en) | Rebuilding system and rebuilding method of existing building | |
| JP2583462B2 (en) | Reconstruction construction method of building in operation | |
| JPH10169209A (en) | Repair method for building | |
| JP7500408B2 (en) | Pre-construction method for interior stairs of buildings | |
| JPH0483060A (en) | Building construction | |
| Tanijiri et al. | Development of automated weather-unaffected building construction system | |
| JP2829363B2 (en) | Formwork equipment for pillar construction | |
| JPH05133016A (en) | Peripheral supporting self-rising type building engineering method | |
| CN116021625A (en) | An assembled building component production line | |
| JP3192543B2 (en) | Building demolition method | |
| KR102910761B1 (en) | Structure construction method for apartment remodeling using climbing bracket | |
| JP2527686B2 (en) | Tower-suspended building construction method | |
| JP3247735B2 (en) | Construction method of large building | |
| JP2001226055A (en) | Elevator house | |
| JP3289216B2 (en) | Work facility having pits and method of constructing the same | |
| JP3049584B2 (en) | All-weather construction method | |
| JP2874830B2 (en) | Push-up method | |
| JPH06193275A (en) | Temporary roof at construction site and building construction method using the same | |
| JPH07229206A (en) | Method of rebuilding building | |
| JP2025130797A (en) | Building construction method | |
| JP2006111369A (en) | Reinforcement method of tower crane installation part | |
| JPH06158672A (en) | Method for constructing underground structure | |
| JPH0733689B2 (en) | Push-up method and apparatus |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081121 Year of fee payment: 12 |
|
| LAPS | Cancellation because of no payment of annual fees |