Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP2878055B2 - Raw material transport control system - Google Patents
[go: Go Back, main page]

JP2878055B2 - Raw material transport control system - Google Patents

Raw material transport control system

Info

Publication number
JP2878055B2
JP2878055B2 JP5070493A JP5070493A JP2878055B2 JP 2878055 B2 JP2878055 B2 JP 2878055B2 JP 5070493 A JP5070493 A JP 5070493A JP 5070493 A JP5070493 A JP 5070493A JP 2878055 B2 JP2878055 B2 JP 2878055B2
Authority
JP
Japan
Prior art keywords
tank
raw material
time
plan
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP5070493A
Other languages
Japanese (ja)
Other versions
JPH06263231A (en
Inventor
島 徹 二 福
任 利 関
井 良 和 冨
田 修 司 冨
田 野 哲 史 羽
山 健 丸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP5070493A priority Critical patent/JP2878055B2/en
Publication of JPH06263231A publication Critical patent/JPH06263231A/en
Application granted granted Critical
Publication of JP2878055B2 publication Critical patent/JP2878055B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Control Of Conveyors (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、原料ヤードにおける原
料搬送制御に関し、特に、原料ヤードから下工程工場の
原料槽へ搬送し入槽する原料ヤード設備において複数の
搬送作業を同時並行して行う搬送制御に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to raw material transfer control in a raw material yard, and more particularly, to a plurality of transfer operations performed simultaneously and simultaneously in a raw material yard facility for transferring and entering a raw material tank from a raw material yard to a raw material tank of a lower process plant. Related to transport control.

【0002】[0002]

【従来の技術】原料ヤードにおける搬送制御において、
その搬送計画の立案では、操業者が原料ヤードの現況,
受入,払出,搬送設備の現況,槽現況,設備修理計画,
設備故障現況,天候,槽と原料銘柄の割付計画,搬送先
工場からの要請、等々のデータから、槽の原料レベル推
移を計算して入槽タイミングと受入,払出,搬送設備稼
動状況を試行錯誤的にシミュレーションしながら、槽の
原料レベルが管理範囲から外れず、かつ、受入,払出,
搬送設備の競合,系統干渉や接近干渉を避けるように決
定するという方法がとられていた。
2. Description of the Related Art In transport control in a raw material yard,
In the planning of the transfer plan, the operator was asked
Receiving, dispensing, transport equipment status, tank status, equipment repair plan,
Based on data such as equipment failure status, weather, allocation plan of tank and raw material brand, request from destination factory, etc., change of raw material level of tank is calculated, and the timing of tank input and receiving, dispensing, operating state of transfer equipment are trial and error. The raw material level of the tank does not deviate from the control range while receiving the
The decision was made to avoid transport equipment competition, system interference and approach interference.

【0003】この従来の、操業者による知的処理方法で
は、大規模な原料ヤード設備では考慮すべき項目が極め
て多く計算量も多いため、熟練操業者以外では実用的な
計画立案ができず、8時間程度の搬送作業を立案をする
のに1時間以上かかり、その個人差も大きく、設備の突
発的な故障などによるリアルタイムでの計画修正も困難
であるという問題があった。この問題を解決するため、
さまざまな自動制御方法が提案されている。たとえば、
特開平3−243508号公報には、知識ベースに基
づいたヤード計画に則した自動制御方法が提示され、
特開平4−89708号公報には、知識ベースに基づい
た鉱石ヤードの搬送能率を最大とするような自動制御方
法が提示され、特開平4−89709号公報には、槽
の原料在庫シミュレーションに基づき、知識ベース推論
により石炭ヤードの搬送能率を最大とするような自動制
御方法が提示され、 特開平3−279124号公報に
は、ヤード計画を中心とした搬送作業の競合解消方法が
提示されている。
[0003] With this conventional, intelligent processing method by the operator,
Are the most important items to consider in large-scale material yard facilities
And the amount of calculation is large, making it practical for non-expert operators.
Unable to make a plan and make a transportation work of about 8 hours
It takes more than one hour, and the individual differences are large.
It is also difficult to correct plans in real time due to sudden failure etc.
There was a problem that is. To solve this problem,
Various automatic control methods have been proposed. For example,
Japanese Patent Application Laid-Open No. 3-243508 discloses a knowledge base.
Automatic control method based on the yard plan based on
Japanese Patent Application Laid-Open No. Hei 4-89708 discloses a technique based on a knowledge base.
Automatic control method that maximizes the transportation efficiency of a closed ore yard
A method is proposed, and JP-A-4-89709 discloses a tank.
Knowledge base based on material simulationinference
ByAutomatic system to maximize coal yard transport efficiency
Your way is presented, JP-A-3-279124
Is a method for resolving conflicts in transport work centering on yard planning.
Has been presented.

【0004】[0004]

【発明が解決しようとする課題】従来の方法において
は、積付/払出設備の競合解消はヤード計画を中心に行
っているものがあるが、複数搬送作業間で受入・払出,
搬送設備(系統)を共有しており、積付/払出設備間の
接近干渉が頻繁に起こるような原料ヤード設備の作業に
おいては、ヤード計画(日単位)上は搬送設備の競合あ
るいは積付機/払出機間の接近干渉が起こる計画とせざ
るを得ず、実際の搬送作業計画(時分単位)において、
積付/払出設備の競合,接近干渉や搬送設備の系統干渉
を避けるような実行搬送計画を立案する必要があった。
In the conventional method, the conflict between the loading / unloading facilities is resolved mainly by a yard plan.
In the operation of the raw material yard facility where the transfer equipment (system) is shared and the approach interference between the loading / unloading equipment frequently occurs, competition of the transfer equipment or loading equipment is required in the yard plan (daily unit). / It must be a plan that causes interference between the dispensers, and in the actual transfer work plan (hour and minute unit),
It was necessary to formulate an effective transfer plan to avoid competition between loading / unloading equipment, approach interference, and system interference of the transfer equipment.

【0005】また、従来の方法においては、搬送作業
(系統)毎の優先度を固定して順番に搬送作業を割付け
ていく方法が提案されているが、この方法では複数作業
間での柔軟な計画調整を行うことが困難であった。
Further, in the conventional method, a method has been proposed in which the priority of each transfer operation (system) is fixed and the transfer operations are sequentially assigned. In this method, a flexible operation among a plurality of operations is provided. It was difficult to make plan adjustments.

【0006】本発明においては、複数搬送作業間で積
付,払出,搬送設備(系統)を共有しており、積付/払
出設備間の競合,干渉,接近干渉が起こるような原料ヤ
ード設備の原料搬送制御において、複数作業間の払出
山,方向,量,開始/終了時刻などについて、全体を俯
瞰してきめ細かい時分単位の計画調整を行うことによ
り、積付/払出設備の競合,接近干渉や搬送設備の系統
干渉を避け、搬送能率を最大にすることができるような
原料搬送計画を立案し、自動制御を行うことを目的とす
る。
In the present invention, the loading, unloading and transfer equipment (system) is shared among a plurality of transfer operations, and the raw material yard equipment in which competition, interference and approach interference between the loading and unloading equipment occurs. In raw material transport control, by comprehending a detailed plan adjustment in units of hours and minutes with respect to the dispensing mountain, direction, amount, start / end time, etc. between multiple operations, competition of loading / dispensing equipment, interference with approaching The purpose of the present invention is to formulate a raw material transfer plan that can maximize the transfer efficiency while avoiding system interference of the transfer equipment and transfer equipment, and to perform automatic control.

【0007】[0007]

【課題を解決するための手段】本発明の、原料ヤード設
備の原料搬送制御システムは、原料受入計画,原料使用
計画,原料ヤード計画,工場稼動計画,設備修理計画,
原料ヤード現況,槽現況,設備現況,搬送作業実績,操
業者からの操業前提条件データである槽/銘柄割付計画
を取込む入力手段A;入力手段Aで取り込んだ 入力データに基づいて、入槽先
槽毎に、基準時刻の現況を基準として槽の原料在庫推移
を計算して、設備修理や故障時間帯を回避し槽在庫が管
理下限切れしないための次回入槽時刻および量の実行可
能範囲を計算する手段B; 前記入槽のための払出山候補を選択し、該当払出山にひ
もつく払出設備候補および払出設備候補にひもつく搬送
設備を選択し、その払出作業における設備接近干渉範囲
を計算する手段C; 複数の次回搬送作業候補に関する前記手段BおよびCの
計算結果から、該当時点で操業優先度の高い作業を判断
し、複数搬送作業間での払出/搬送設備の取合い競合,
干渉,接近干渉を回避するように調整して、搬送作業毎
に使用する払出設備,搬送設備,払出山および前記手段
Bが算出し実行可能範囲内の入槽開始/終了時刻,量を
決定する手段D; 手段Dの計算結果から、直近の計画確定時刻まで槽の原
料在庫推移,原料ヤード推移,受入・払出・搬送設備稼
動状況をシミュレーション計算する手段E; 直近の計画確定時刻を基準時刻として前記手段B〜Eの
処理を計画立案時間分繰返す計算手段F; 計算結果を操業者に提示するための出力手段G; 計算結果に基づいて受入・払出・搬送設備を制御する制
御手段H;および、 計画と実績の差が発生する毎に前記A〜Hによる計算お
よび制御を行なう計算制御手段I; を備える。
According to the present invention, a raw material transfer control system for a raw material yard facility includes a raw material receiving plan, a raw material use plan, a raw material yard plan, a factory operation plan, a facility repair plan, and the like.
Input means A for taking in the raw material yard state, tank state, equipment state, transfer operation results, and tank / brand allocation plan as operation precondition data from the operator; based on the input data taken in by the input means A Then, for each destination tank, calculate the change in the stock of raw material in the tank based on the current status of the reference time, and avoid the time of equipment repairs or failures, and the next entry time and quantity to prevent the tank inventory from running out of the control lower limit. Means B for calculating the feasible range of the equipment; selecting a dispensing mountain candidate for entering the tank, selecting a dispensing facility candidate associated with the corresponding dispensing mountain and a transport facility associated with the dispensing facility candidate , and selecting equipment for the dispensing work. Means C for calculating the approach interference range; from the calculation results of the means B and C relating to a plurality of next transfer work candidates, the work having the highest operation priority at the corresponding point in time is determined, and the payout / transfer equipment between the plurality of transfer works is determined. Competition,
Adjustment is made so as to avoid interference and approaching interference, and the dispensing equipment, transport equipment, dispensing hill used for each transfer operation and the means B are calculated and the start / end time and amount of tanks within the executable range are determined. Means D; means E for simulating the change of the stock of raw material in the tank, the change of the raw material yard, and the operation status of the receiving / discharging / transportation facility from the calculation result of the means D to the latest plan fixed time; the latest planned fixed time as a reference time Calculation means F for repeating the processing of the means B to E for the planning time; output means G for presenting the calculation results to the operator; control means H for controlling the receiving / paying / transporting equipment based on the calculation results; Calculation control means I for performing calculation and control by A to H each time a difference between a plan and an actual result occurs.

【0008】[0008]

【作用】この原料搬送制御システムは、複数の搬送作業
間で積付,払出,搬送設備(系統)を共有しており、複
数作業を並行して行うため受入,払出設備間の接近干渉
が起こり得るような原料ヤ−ド設備に適用すると、設備
修理および故障を回避し、槽在庫が管理下限切れを起こ
さず、複数搬送作業間での積付,搬送設備の取合い競
合,干渉,接近干渉を回避し、個別の計画を俯瞰して、
総合的に調整して搬送能率を最大にすることができるよ
うに、搬送作業毎の払出山,方向,使用する払出,搬送
設備,入槽開始/終了時刻,量を決定し、これに基づい
て自動搬送制御を行う。
This material transfer control system shares the loading, unloading, and transfer equipment (system) between multiple transfer operations, and because the multiple operations are performed in parallel, approach interference between the receiving and discharging equipment occurs. When applied to raw material yard equipment that can be obtained, equipment repairs and breakdowns can be avoided, tank inventory does not exceed the lower limit of control, stowage among multiple transport operations, conflict of transport equipment, interference, and approach interference. Avoid, look at individual plans,
In order to maximize the transfer efficiency by comprehensively adjusting, the dispensing hill, direction, dispensing, transfer equipment, tank start / end time, and quantity for each transfer operation are determined and based on this. Performs automatic transfer control.

【0009】[0009]

【実施例】次に本発明の、鉱石ヤードを対象とした一実
施例を説明する。この一実施例のシステム構成を図1に
示す。図1において、100は生産管理用計算機(ビジ
コン)であり、ここで入船荷役計画,高炉・焼結生産計
画,高炉・焼結稼動休止計画,均鉱配合計画などの月次
日単位の原料ヤード入出荷計画が作成される。
Next, an embodiment of the present invention for an ore yard will be described. FIG. 1 shows a system configuration of this embodiment. In FIG. 1, reference numeral 100 denotes a computer for production control (a vidicon). Here, a raw material yard on a monthly basis, such as a ship loading / unloading plan, a blast furnace / sintering production plan, a blast furnace / sintering operation stop plan, and a soaking ore mixing plan. A receipt / shipment plan is created.

【0010】200は原料ヤードプロセス制御用計算機
(原料プロコン)である。上記ビジコン100が作成し
た生産計画情報が原料プロコン200に送信入力され
る。原料プロコン200において入力情報は、受信編集
処理210を介して需給計画機能群220、具体的には
原料ヤード配置計画機能,均鉱積付需給計画機能,均鉱
払出需給計画機能,鉱石処理需給計画機能,焼結鉱需給
計画機能,荷役受入計画機能、に入力される。
Reference numeral 200 denotes a computer for controlling a raw material yard process (raw material processing computer). The production plan information created by the vidicon 100 is transmitted and input to the raw material processing computer 200. The input information in the raw material processing computer 200 is supplied to the supply and demand planning function group 220 through the reception editing process 210, specifically, the raw material yard arrangement planning function, the soot supply and demand planning function, the ore dispensing supply and demand planning function, the ore processing supply and demand plan. Function, sinter ore supply and demand planning function, and cargo handling acceptance planning function.

【0011】500は原料プロコンと操業者とのI/F
(インタ−フェイス)をとりもつ入出力用CRT端末装
置、250はCRTの入出力を制御する入出力処理機能
であり、操業者は、日毎時分単位の設備修理計画や、槽
/銘柄の割付計画などの操業条件240を、計画立案機
能220および230の前提条件情報としてCRT端末
装置500より入力することができる。
Reference numeral 500 denotes an I / F between a raw material process control and an operator.
An input / output CRT terminal device having an (interface) 250 is an input / output processing function for controlling the input / output of the CRT. Operating conditions 240 can be input from the CRT terminal device 500 as prerequisite information for the planning functions 220 and 230.

【0012】需給計画機能220において、原料ヤード
配置計画は日単位の入出荷原料のヤード山推移の計画,
均鉱積付需給計画は日単位の銘柄毎均鉱積付計画,均鉱
払出需給計画は日単位の均鉱払出/備蓄計画,鉱石処理
需給計画は日単位の銘柄毎鉱石処理(鉱石整粒粉砕)計
画,焼結鉱需給計画は日単位の焼結鉱払出/備蓄計画,
荷役受入計画は時間単位の受入作業JOB計画,をそれ
ぞれ作成する。
In the supply and demand planning function 220, a raw material yard arrangement plan is a plan of a yard change of incoming and outgoing raw materials on a daily basis,
The ore-loading supply and demand plan is a daily uniform ore loading plan for each brand, the ore payout supply-and-demand plan is a daily ore payout / reserve plan, and the ore processing supply and demand plan is a daily ore processing for each brand (ore ore sizing). Pulverization) plan, sinter ore supply and demand plan
For the cargo handling acceptance plan, an acceptance work JOB plan is prepared for each hour.

【0013】一方、400は原料ヤードの現場設備機器
群のブロック図であり、410が移動機群(受入機およ
び払出機),420がコンベア群,430が秤量機群を
示す。 300は現場設備機器制御用下位コントローラ
であり、現場設備機器400を制御し、その稼動実績お
よび現況を管理する。コントローラ機器は、移動機群の
制御に移動機制御用PC(プログラマブルコントロー
ラ)310,コンベヤ群の制御はコンベヤ制御用PC3
20により構成される。この現場機器制御用下位コント
ローラ300は、搬送,秤量実績情報,設備稼動,故障
実績情報を原料プロコン200にリアルタイムで送信す
る。原料プロコン200は、実績収集・編集処理290
にて該当情報を受信入力し、設備現況情報270として
設備稼動現況および設備故障現況,操業情報280とし
て搬送作業実績,ヤード現況および槽現況情報としてデ
ータファイルに格納する。
On the other hand, reference numeral 400 is a block diagram of a group of on-site equipment in the raw material yard. Reference numeral 410 denotes a mobile unit group (acceptor and dispenser), 420 denotes a conveyor group, and 430 denotes a weighing machine group. Reference numeral 300 denotes a lower-level controller for controlling the on-site equipment, which controls the on-site equipment 400 and manages the operation results and the current state. The controller device includes a mobile device control PC (programmable controller) 310 for controlling the mobile device group, and a conveyor control PC 3 for controlling the conveyor group.
20. The lower-level controller 300 for controlling the on-site equipment transmits the transport, weighing result information, equipment operation, and failure result information to the raw material process controller 200 in real time. The raw material process control 200 is used to collect and edit results 290
Then, the corresponding information is received and input, and stored in the data file as the equipment operation status and equipment failure status as the equipment status information 270, and the transfer work results, the yard status and the tank status information as the operation information 280.

【0014】本発明の中心機能である搬送制御計画立案
機能230は、上述した原料ヤード入出荷生産計画,需
給計画220,設備修理計画などの前提条件240,設
備現況270,操業現況280などの各情報を入力し、
搬送系統毎、すなわち鉱石ヤードの場合、均鉱積付系
統,鉱石(整粒/粉砕)処理輸送系統,高炉単味輸送系
統,焼結単味輸送系統,焼結鉱輸送系統,均鉱払出輸送
系統などの各搬送制御計画を立案し、オペレータ入出力
処理250を介してCRT端末装置500に表示して、
同時に設定制御処理260を介して現場機器制御用下位
コントローラ300に搬送制御情報として送信し出力に
設定する。
The transport control planning function 230, which is a central function of the present invention, includes the above-mentioned prerequisites 240 such as the above-mentioned raw material yard receipt / shipment production plan, supply / demand plan 220, equipment repair plan, equipment status 270, and operation status 280. Enter the information,
For each transport system, that is, for ore yards, ore stacking system, ore (sizing / grinding) processing and transport system, blast furnace plain transport system, sintered plain transport system, sinter ore transport system, uniform ore dispensing transport Each transport control plan such as a system is drafted and displayed on the CRT terminal device 500 via the operator input / output processing 250,
At the same time, it is transmitted as transport control information to the field device control lower-level controller 300 via the setting control process 260 and is set for output.

【0015】現場機器制御用下位コントローラ300
は、この搬送制御情報に従って搬送制御を行い、その搬
送実績情報を原料プロコン200に送信する。原料プロ
コン200では、該当実績情報を基に搬送制御計画立案
機能230によりリアルタイムで必要都度計画を見直
し、搬送制御情報を現場機器制御用下位コントローラ3
00に送信し出力に設定する,・・・、というサイクル
を繰返して自動搬送制御を行う。
Lower controller 300 for controlling field devices
Performs transport control according to the transport control information, and transmits the transport result information to the raw material process control 200. In the raw material processing computer 200, the transfer control information is reviewed in real time by the transfer control planning function 230 based on the corresponding actual information, and the transfer control information is transferred to the lower level controller 3 for controlling the on-site equipment.
The automatic transfer control is performed by repeating the cycle of transmitting to 00 and setting the output,....

【0016】次に、本発明の中心処理である原料プロコ
ン200の搬送制御計画立案機能230(図1)の、入
槽作業計画立案部の処理手順について図2のフローチャ
ートにしたがって説明する。
Next, the processing procedure of the tank entry work planning section of the transfer control planning function 230 (FIG. 1) of the raw material process control 200, which is the central processing of the present invention, will be described with reference to the flowchart of FIG.

【0017】 (1)データ入力,初期値,条件設定(図2のF10) 本処理に必要な情報(原料入出荷計画,需給計画,設備
修理計画,操業前提条件,設備稼動現況,設備故障現
況,ヤード現況,槽在庫現況,搬送作業実績)を各ファ
イルから入力し編集する。
(1) Data input, initial value, condition setting (F10 in FIG. 2) Information required for this processing (raw material receipt / shipment plan, supply / demand plan, equipment repair plan, operation precondition, equipment operation status, equipment failure status , Current status of yard, current status of tank inventory, actual results of transfer work) are input from each file and edited.

【0018】(2)搬送系統毎搬送作業JOB開始時間範
囲計算(図2のF20) 各系統毎,槽毎に、基準時刻(シミュレーションを行う
時刻で、最初は現時刻)において、槽在庫と切出速度か
ら槽在庫推移計算を行い、系統・移動機修理,故障,槽
修理・故障,工場休止,決定済上位搬送JOBとの系統
干渉を考慮して、槽在庫が管理下限を切らず、設備修理
や系統干渉を避ける実行可能入槽JOB開始時間範囲を
計算する。図3〜6に計算結果の一例を示す。なお搬送
作業JOB開始時間範囲としては入槽時間から移動機移
動セット時間を引いた値である。 (3)移動機接近干渉範囲計算(図2のF30) 決定済受入JOBと決定済払出JOBの移動機稼動範囲
の接近干渉範囲を、干渉範囲周辺の山毎に計算する。ま
た、F20で計算した槽銘柄に対応した払出候補となる
山を東西各々の方向から払出した場合の接近干渉範囲を
周辺の山毎に計算し、上記干渉範囲との重ね合わせ処理
を行い、該当時点での山毎の東側払出可能量および西側
払出可能量として計算する(本例は東西の敷設されたヤ
ードの場合)。図7〜9に干渉範囲の数例を示す。表1
に計算結果の一例を示す。
(2) Calculation of transfer job JOB start time range for each transfer system (F20 in FIG. 2) For each system and for each tank, the tank stock is cut off at the reference time (simulation time, the current time is first). The tank inventory is calculated based on the output speed, and the tank inventory does not fall below the lower control limit in consideration of system / mobile equipment repair, failure, tank repair / failure, factory shutdown, and system interference with the determined upper-level transfer JOB. Calculate the feasible entry JOB start time range to avoid repair and system interference. 3 to 6 show examples of calculation results. Note that the transfer job JOB start time range is a value obtained by subtracting the moving device moving set time from the tank entering time. (3) Calculating interference range of mobile device approaching (F30 in FIG. 2) The approaching interference range of the determined receiving JOB and the determined payout JOB in the operating range of the mobile device is calculated for each mountain around the interference range. Also, the approach interference range when paying out the candidate mountain corresponding to the tank brand calculated in F20 from each of the east and west directions is calculated for each of the surrounding mountains, and the overlapping process with the above interference range is performed. It is calculated as the eastern payable amount and the west payable amount for each mountain at the time (in this example, yards laid east and west). 7 to 9 show several examples of the interference range. Table 1
Shows an example of the calculation result.

【0019】[0019]

【表1】 [Table 1]

【0020】(4)JOB割付,山,移動機,系統ひもつ
け(図2のF40) 系統の重要性と、F20およびF30で計算した槽在庫
下限管理切れ時刻と搬送JOB開始時間範囲の自由度か
ら、複数ある次回の搬送JOB候補の中から、優先すべ
き搬送JOBを選択し、搬送JOB開始時間範囲内から
搬送JOB開始時刻および量を決定し、払出山,払出方
向,移動機,搬送系統を同時に決定し、次に優先すべき
搬送JOBについて同様に繰返す。搬送JOBの決定は
時間軸方向に未定のものがないように進め、ある系統の
搬送JOB開始時間範囲が決定した搬送JOBの終了時
刻よりさらに未来にある場合は、該当搬送JOBの割付
は次の基準時刻で行う。図10,11に割付の一例を示
す。
(4) Job allocation, mountain, mobile, system linking (F40 in FIG. 2) Importance of the system, flexibility of tank inventory lower limit management time calculated at F20 and F30 and transfer job start time range , A transport job to be given priority is selected from a plurality of next transport job candidates, a transport job start time and an amount are determined from within a transport job start time range, and a payout mountain, a payout direction, a mobile device, and a transport system are determined. Are determined at the same time, and the same is repeated for the next priority transport job. The transport job is determined in such a way that there is no undetermined transport job in the time axis direction. If the transport job start time range of a certain system is further in the future than the determined transport job end time, the relevant transport job is assigned the following. Perform at the reference time. 10 and 11 show an example of the assignment.

【0021】特に干渉する作業がない場合は、搬送JO
B開始時刻および量について、効率上入槽量が最大にな
るように、搬送JOB開始時間範囲の最大時刻で満槽ま
で入槽し、払出山および方向はヤード計画結果に従う。
また同銘柄を連続入槽することにより作業効率を上げ
る。
If there is no interference work, the transport JO
Regarding the start time and amount of B, the tank is filled up to the full tank at the maximum time of the transfer job start time range so that the tank entry amount is maximized for efficiency, and the payout mountain and direction follow the yard plan result.
In addition, work efficiency is improved by continuously loading the same brand.

【0022】干渉する作業がある(搬送JOB開始時間
範囲に重なりがあり、払出機または搬送設備が競合,干
渉あるいは接近干渉する)場合は以下のように搬送JO
B計画を調整する; 競合,接近干渉の場合の払出山,方向調整 同銘柄山が複数ある場合はF30の計算結果から払出山
を選択して競合,接近干渉を防止する。一つの山しかな
い場合は払出方向の選択により接近干渉を防止する。な
お競合,接近干渉が防止できない場合はの処理とす
る, 競合,干渉,接近干渉の場合の時間調整 搬送JOB開始時間の最大時刻が大きいものはその最大
時刻に割付け、競合または干渉する一方の作業はその時
刻から溯り、可能な限り入槽量が大きくできる時刻に割
付け、時間的に競合,干渉または接近干渉を防止し、搬
送作業効率を最大にする。
If there is an interfering operation (the delivery JOB start time range overlaps and the dispensing machine or the transportation equipment competes, interferes or interferes closely), the transportation JOB is performed as follows.
Adjust Plan B; Dispense Mountain and Direction Adjustment in Case of Competition and Approaching Interference If there are a plurality of the same brands, select a dispensing mountain from the calculation result of F30 to prevent competition and approaching interference. When there is only one peak, approach interference is prevented by selecting the payout direction. If the conflict or approach interference cannot be prevented, the process is performed. Time adjustment in the case of conflict, interference or approach interference If the maximum time of the transport JOB start time is large, it is assigned to the maximum time, and one of the tasks that competes or interferes Is assigned to a time that can be as large as possible, as far back as possible from that time, to prevent competition, interference or approach interference in terms of time, and to maximize transport work efficiency.

【0023】(5)基準時刻更新(図2のF50) 上記(4)において決定した搬送JOBから、時間軸上で
未定のものがない時刻、すなわち計画が全て決定した時
点まで、計算処理上の基準時刻を進める。
(5) Update of reference time (F50 in FIG. 2) From the transport job determined in (4) above, to the time when there are no undetermined items on the time axis, that is, the time when all plans have been determined, Advance the reference time.

【0024】(6)計画範囲終了判断(図2のF60) 基準時刻を進めて計画を立案していき、基準時刻が計画
立案時間範囲(例えば1シフト相当分、即ち現在時刻か
ら8時間分)を超えたかどうか比較し、超えていれば終
了とする。
(6) Judgment of end of plan range (F60 in FIG. 2) The plan is drafted by advancing the reference time, and the reference time is within the plan preparation time range (for example, one shift equivalent, ie, eight hours from the current time). Are compared, and if it is exceeded, the process is terminated.

【0025】(7)槽在庫量更新(図2のF70) 基準時刻更新処理F50で進めた基準時刻における各槽
の在庫量を計算する。 (8)ヤードマップ更新(図2のF80) 基準時刻更新処理F50で進めた基準時刻におけるヤー
ド各山の在庫量,東位置,西位置を計算する。同時に移
動機の位置を計算する。
(7) Updating of Tank Stock (F70 in FIG. 2) The stock of each tank at the reference time advanced in the reference time update processing F50 is calculated. (8) Updating the yard map (F80 in FIG. 2) The stock amount, east position, and west position of each yard at the reference time advanced in the reference time update processing F50 are calculated. At the same time, the position of the mobile device is calculated.

【0026】(9)搬送作業計画編集(図2のF90) 以上の処理で決定した搬送JOB計画情報について、設
備機器制御用下位コントローラに設定する設定制御情報
に編集する。
(9) Edit of transfer work plan (F90 in FIG. 2) The transfer job plan information determined in the above processing is edited into setting control information to be set in the lower controller for equipment control.

【0027】以上の処理フローに従って、本発明が目的
とする、複数の搬送作業を同時並行して行う搬送制御に
関して、受入,払出設備間の競合,干渉,接近干渉が起
こるような原料ヤード設備において、複数作業間の時間
単位の払出山,方向,量などのきめ細かい計画調整によ
り、競合,干渉,接近干渉を避け、搬送能率を最大にす
ることができるような原料搬送計画立案,制御を行う。
In accordance with the above-described processing flow, with respect to the transport control for simultaneously carrying out a plurality of transport operations, which is the object of the present invention, in a raw material yard facility in which competition, interference, and approach interference between receiving and discharging facilities occur. In addition, by performing detailed planning and adjustment of the dispensing hill, direction, amount, and the like in units of time between a plurality of operations, competition, interference, and approach interference are avoided, and material transfer planning and control that can maximize transfer efficiency are performed.

【0028】次に、図2のフローチャートの搬送系統毎
入槽作業JOB開始時間範囲計算(F20)における計
算例を、図3,図4および図5で説明する。
Next, an example of the calculation in the entry work JOB start time range calculation (F20) for each transport system in the flowchart of FIG. 2 will be described with reference to FIGS. 3, 4, and 5. FIG.

【0029】図3のグラフは、任意の入槽先槽の基準時
刻以後の在庫推移を示すものであり、縦軸が在庫レベル
(ton),横軸が基準時刻からの時間(分)であり、右
下がりの実線が入槽しない場合の在庫推移である。槽毎
に在庫量の管理上下限値(破線)があり、在庫量がその
破線の範囲内から外れないように操業を行う。
The graph of FIG. 3 shows the change in inventory of an arbitrary destination tank after the reference time, with the vertical axis representing the inventory level (ton) and the horizontal axis representing the time (minutes) from the reference time. , The solid line falling to the right indicates the inventory change when the tank does not enter. Each tank has a management upper and lower limit value (broken line), and the operation is performed so that the stock amount does not deviate from the range of the broken line.

【0030】図3の通常ケース、すなわち移動機,搬送
系統,槽の修理や故障がない場合は、次の入槽JOB開
始時間範囲は、図に示す通り、最小JOB入槽可能時刻
から槽在庫が下限となり入槽量として最大となる時刻ま
での範囲であり、JOB数は一つである。なお最小JO
Bとは作業効率上の下限定数値である。
In the normal case shown in FIG. 3, that is, when there is no repair or failure of the mobile unit, the transport system, and the tank, the next entry JOB start time range is as shown in FIG. Is the lower limit and reaches the maximum time as the tank entry amount, and the number of JOBs is one. Note that the minimum JO
B is a lower limit numerical value in terms of work efficiency.

【0031】図4の(a),(b),(c)および
(d)に示す、移動機,搬送系統に修理や故障があるケ
ースにおいては、 修理時間帯に該設備が使用できない、 従ってその時間帯に槽在庫が下限切れしないための在
庫を確保する入槽作業を行う必要がある、という制約が
ある。この場合、図4中の右下がりの点線が、修理また
は故障終了時刻において管理下限値に到達する線であ
り、修理前にこの点線以上の在庫を確保すれば良い。以
下その方法について4つのケースで例示説明する。
In the case shown in FIGS. 4 (a), (b), (c) and (d) where the mobile unit and the transport system have a repair or a failure, the equipment cannot be used during the repair time. There is a restriction that it is necessary to perform a tank entry operation to secure the stock so that the tank stock does not run out during the time period. In this case, the dotted line falling to the right in FIG. 4 is the line that reaches the control lower limit value at the time of repair or failure end, and it is sufficient to secure inventory above this dotted line before repair. Hereinafter, the method will be exemplified and described in four cases.

【0032】図4の(a)では、最小JOBで入槽した場
合は修理時間帯で下限切れとなるため小さいJOBでは
2JOBの入槽が必要となり、大きめのJOBで入槽す
れば図の破線範囲を上回り1JOBで満足できるような
ケースであり、その時の入槽作業JOB開始時間範囲は
図のように2JOB狙いと1JOB狙いの2通りとな
る。図4の(b)は、最小JOBでも1回入槽すれば修理
時間帯での下限切れが防ぐことができるケースであり、
この場合は1JOBとなる。図4の(c)の例は、直近に
修理時間がある場合であり、この場合は修理時間帯の入
槽ができないため時間範囲が修理前後の2つに分かれ
る。図4の(d)の例は、基準時刻において故障中の場合
であり、この場合は故障復旧後に入槽可能となる。
In FIG. 4 (a), when entering the tank with the minimum JOB, the lower limit is expired in the repair time zone. Therefore, entering the tank with a small JOB requires 2 JOBs. This is the case where the range is larger than the range and 1 job can be satisfied. At that time, the tank entry job start time range is two types, 2 job aim and 1 job aim. FIG. 4B shows a case where even if the minimum JOB is entered once, it is possible to prevent the lower limit from being exhausted during the repair period.
In this case, it is 1 JOB. The example of FIG. 4C is a case where there is a repair time in the latest, and in this case, it is not possible to enter the tank during the repair time zone, so the time range is divided into two before and after the repair. The example of FIG. 4D is a case where a failure occurs at the reference time, and in this case, it becomes possible to enter the tank after recovery from the failure.

【0033】図5は槽修理があり、修理槽を空槽にし
て、その間別の予備槽を使用するケースであり、この場
合は空槽指定時刻に空槽にするような、図5中に実線で
示す空槽狙い線に沿うように在庫を制御する。図5の
(a)は、1JOBでは空槽狙い線に乗らないが、2JO
Bで乗せられる例で、この場合1JOB目は最小JOB
から2回目に最小JOB入槽ができるまでの範囲とな
る。図5の(b)は、1JOBで空槽狙い線に乗ることが
できる例であり、図5の(c)は、最小JOBでも修理槽
は空槽狙い線をオーバーし予備槽で修理終了時刻までま
かなう例である。図5の(d)は、予備槽に最小JOBで
入槽しても修理終了時刻を超える例である。
FIG. 5 shows a case in which the tank is repaired, the repair tank is emptied, and another spare tank is used during that time. In this case, the tank is emptied at the designated time in FIG. The inventory is controlled along the empty tank target line shown by the solid line. In FIG.
(a) does not get on the empty tank aim line in 1JOB, but 2JO
In this example, the first JOB is the minimum JOB
From the time when the minimum JOB tank is formed for the second time. FIG. 5 (b) is an example in which the user can get on the empty tank aiming line at 1 JOB, and FIG. 5 (c) shows that even with the minimum JOB, the repair tank exceeds the empty tank aiming line and the repair end time in the spare tank. This is an example that covers up. FIG. 5 (d) shows an example in which even if the spare tank is entered with the minimum JOB, the repair end time is exceeded.

【0034】また、槽修理があり、修理槽に空槽指定が
ないケース,槽切出速度に変更があるケースも方法は同
様である。計算式の例を、図6にしたがって説明する。
The method is the same in the case where the tank is repaired and no empty tank is specified in the repair tank, and the case where the tank cutting speed is changed. An example of the calculation formula will be described with reference to FIG.

【0035】図6は、図3,4における入槽作業JOB
開始時間範囲と、その間の任意の時刻における入槽JO
Bの最大時間を計算する方法の説明である。図6に示す
グラフにおいて、横軸Xが時間,縦軸Yが槽在庫量を示
す。計算式のパラメータとしては、α:入槽時の入槽速
度(ton/h),β:槽切出速度(ton/h),Tmin:最
小JOB時間(h),ZU :槽在庫上限管理値(to
n),ZL :槽在庫下限管理値(ton),ZS :基準時刻
(X=0)槽在庫量(ton),Tn :任意の入槽JOB
開始時刻(h)であり、JOB割付処理に渡すため計算
するデータは、T1:入槽JOB開始時間範囲最小値
(h),T2 :入槽JOB開始時間範囲最大値(h)で
ある。この場合、T1 ,T2 は以下の(1),(2)式で計
算される; T1 ={ZS −ZU +(α−β)×Tmin}/β(h) ・・・(1) T2 =(ZS −ZL )/β(h) ・・・(2) なお、計算結果でT1 <0の時はT1 =0とする。ま
た、T1 ≦Tn ≦T2 の任意のTn におけるJOB最大
時間、すなわち満槽までに要する時間Jtmax は、以下
の(3)式で計算される; Jtmax =(ZU −ZS +βTn )/(α−β)(h) ・・・(3) 図2のフローチャートの移動機接近干渉範囲計算(F3
0)における計算例を図7,図8および図9で説明す
る。
FIG. 6 is a view showing the job entering job JOB shown in FIGS.
Start time range and entry JO at any time in between
5 is a description of a method of calculating the maximum time of B. In the graph shown in FIG. 6, the horizontal axis X indicates time, and the vertical axis Y indicates tank stock. As parameters of the calculation formula, α: entry speed at the time of entry (ton / h), β: tank cut-out speed (ton / h), Tmin: minimum JOB time (h), Z U : upper limit of tank inventory management Value (to
n), Z L : tank stock lower limit management value (ton), Z S : reference time (X = 0) tank stock quantity (ton), T n : arbitrary tank JOB
The start time (h), and the data to be calculated to be passed to the job assignment processing, are T 1 : minimum value of the entry job start time range (h), and T 2 : maximum value of the entry job start time range (h). . In this case, T 1 and T 2 are calculated by the following equations (1) and (2): T 1 = {Z S −Z U + (α−β) × T min} / β (h) (1) T 2 = (Z S −Z L ) / β (h) (2) When T 1 <0 in the calculation result, T 1 = 0. Further, JOB maximum time at any T n of T 1 ≦ T n ≦ T 2 , i.e. the time J tmax required until Mitsuruso is calculated by the following equation (3); J tmax = (Z U -Z S + βT n ) / (α-β) (h) (3) Calculation of the mobile station approach interference range (F3) in the flowchart of FIG.
The calculation example in (0) will be described with reference to FIGS. 7, 8, and 9. FIG.

【0036】図7は、東西に敷設された原料ヤードの模
式図であり、Y10およびY20がヤード,Y30およ
びY40がヤードに置かれている原料山,Y50が払出
機(または積付機),Y60がブーム,斜線のハッチン
グ部分Y70およびY80が払出機Y50の払出中接近
干渉範囲,Y90が山Y30の西側払出可能部分(山Y
30は東側払出不可),Y100が山Y40の西側払出
可能部分,同じくY110が東側払出可能部分である。
すなわち接近干渉とは、ある払出機または積付機が作業
中に、他の払出機が接近できないため、近傍の山を全量
は払出せない(図のY70およびY80)状態を言う。
以下に積付と払出、あるいは払出と払出の接近干渉の計
算の仕方をいくつかのケース毎に例示する。
FIG. 7 is a schematic view of a raw material yard laid in the east and west. Y10 and Y20 are yards, Y30 and Y40 are raw materials piles placed in the yard, Y50 is a dispensing machine (or loading machine), Y60 is a boom, hatched portions Y70 and Y80 are hatching interference areas during dispensing of dispensing machine Y50, and Y90 is a west distributable portion of mountain Y30 (mountain Y).
Reference numeral 30 denotes an east side payout unavailable), Y100 denotes a west side payable portion of the mountain Y40, and Y110 denotes an east side payable portion.
That is, the approach interference refers to a state in which a certain dispensing machine or a stowage machine is not working and another dispensing machine is inaccessible, so that all of the nearby mountains cannot be dispensed (Y70 and Y80 in the drawing).
Hereinafter, a method of calculating the loading and dispensing or the approach interference between dispensing and dispensing will be illustrated for each of several cases.

【0037】図8は積付(定点積付)と払出の接近干渉
の例、すなわちある山にある積付機が積付作業中、その
近傍の山が払出せない例である。なお、図8において払
出機および積付機の配置としては、aヤードの北側に払
出機が2台(RC1,RC2)あり、aヤードとbヤー
ドの間に積付機が1台(ST)あり、bヤードの南側に
払出機が2台(RC3,RC4)あり、RC1とRC2
は東西両側の払出しができるがRC3とRC4は西側の
払出しかできない、という制約条件の例で説明する。
FIG. 8 shows an example of interference between stowage (fixed-point stowage) and payout, that is, an example in which a stowage machine at a certain mountain cannot carry out a stowage while a stowage machine is in a stowage operation. In FIG. 8, the dispensing machine and the loading machine are arranged as follows: two dispensing machines are located on the north side of the a yard (RC1, RC2), and one loading machine is between the a yard and the b yard (ST). Yes, there are 2 payout machines (RC3, RC4) on the south side of b yard, RC1 and RC2
Will be described with an example of a constraint condition that payouts on both sides of the east and west can be made, but RC3 and RC4 cannot be paid out on the west side.

【0038】図8の(a)は、図のB山を積付するケース
である。この場合、A山,D山は影響なく全量払出可能
である。B山については積付中であり一般に払出不可で
ある。C山,E山については、西側からの払出は、払出
機のブーム長を含めた接近干渉範囲(本例では64m)
に含まれるため払出不可となる。C山は東側については
図のmの部分は払出可能であるが、E山については、R
C3またはRC4が東側払出不能のため東側払出不可と
なる。
FIG. 8A shows a case where the mountain B in the figure is stacked. In this case, all the peaks A and D can be paid out without any influence. Mountain B is currently being stowed and generally cannot be paid out. As for the payout from the west side, the approach interference range including the boom length of the payout machine (64 m in this example) for the mountains C and E.
And cannot be paid out. On the east side, you can pay out the part m in the figure.
Since C3 or RC4 cannot be paid out on the east side, it cannot be paid out on the east side.

【0039】図8の(b)は、図のD山を積付するケース
である。この場合、A山,D山は影響なく全量払出可能
である。D山については積付中であり一般に払出不可で
ある。B山,E山については、西側からの払出は、払出
機のブーム長を含めた接近干渉範囲(本例では64m)
に含まれるため払出不可となる。B山は東側については
図のmの部分は払出可能であるが、E山については、R
C3またはRC4が東側払出不能のため東側払出不可と
なる。
FIG. 8B shows a case where the mountain D in the figure is stacked. In this case, all the peaks A and D can be paid out without any influence. D is being stowed and cannot be paid out. With regard to Mt. B and Mt. E, the payout from the west side is the approach interference range including the boom length of the payout machine (64 m in this example).
And cannot be paid out. For Mt. B, the part m in the figure can be paid for the east side, but for Mt.
Since C3 or RC4 cannot be paid out on the east side, it cannot be paid out on the east side.

【0040】図9は払出と払出の接近干渉の例、すなわ
ちある山にある払出機が払出作業中、その近傍の山が払
出せない例である。なお、図9において払出機および積
付機の配置としては、cヤードとaヤードの間に払出機
が2台(RC1,RC2)あり、RC1とRC2は東西
両側の払出しができる、という例で説明する。
FIG. 9 shows an example of interference between dispensing and dispensing, that is, an example in which a dispensing machine on a certain mountain cannot perform dispensing while a dispensing machine on the mountain is dispensing. In FIG. 9, the dispensing machine and the stowage machine are arranged as two dispensing machines (RC1 and RC2) between the c yard and the a yard, and RC1 and RC2 can pay both east and west. explain.

【0041】図9の(a)は、図のB山あるいはD山を
RC1で西側払出するケースで、RC2も同方向(西
側)の払出を行うケースである。この場合、RC2によ
る払出が接近干渉により制約を受ける。接近干渉範囲と
してはRC1の西側の接近干渉範囲(本例では42.5
m)の山はRC2での西側払出が不可となる。すなわち
図のような場合、A山,C山については東側からの払出
不可で、西側からは図のm,1(アルファベットのエ
ル)に対応した部分が払出可能となる。
FIG. 9A shows a case where the mountain B or D shown in FIG. 9 is paid out westward by RC1, and a case where RC2 is also paid out in the same direction (west side). In this case, payout by RC2 is restricted by approach interference. The approach interference range is the approach interference range on the west side of RC1 (42.5 in this example).
In the case of m), west payment by RC2 is not possible. That is, in the case shown in the figure, it is impossible to pay out the east side of the mountain A and the mountain C, and it is possible to pay out the portion corresponding to m, 1 (L in the alphabet) of the figure from the west side.

【0042】図9の(b)は、図のC山あるいはF山をR
C1で西側払出するケースで、RC2は逆方向(東側)
の払出を行うケースである。この場合も、RC2による
払出が接近干渉により制約を受ける。接近干渉範囲とし
てはRC1の西側の、RC2のブーム長を含めた接近干
渉範囲(本例では116.5m)の山はRC2での東側
払出が不可となる。すなわち図のような場合、B山,E
山については払出不可で、A山,D山は全量払出可能と
なる。
FIG. 9B shows a case where the peak C or the peak F in FIG.
In the case of paying west at C1, RC2 is in the opposite direction (east)
This is the case of paying out. Also in this case, the payout by RC2 is restricted by the approach interference. As the approach interference range, a mountain in the approach interference range (116.5 m in this example) including the boom length of RC2 on the west side of RC1 cannot be disbursed on the east side in RC2. That is, in the case shown in FIG.
Mountains cannot be paid out, and Mountains A and D can all be paid out.

【0043】以上のような考え方で、任意の積付または
払出作業に対する、該当作業時間帯の、積付機あるいは
払出機の仕様および各ヤードの山配置に応じた、接近干
渉による山毎払出可能量を計算する。
With the above concept, it is possible to pay out each mountain by approach interference according to the specifications of the stowage machine or the payout machine and the mountain arrangement of each yard in an appropriate working time zone for an arbitrary stowage or payout operation. Calculate the amount.

【0044】次に、上記の計算で作業毎に個別に計算し
た値について、複数作業間での時間および空間での重ね
合わせ計算を論理的にORを取ることで行う。たとえ
ば、15:10〜16:00の作業の接近干渉によりA山
の東側払出可能量が3,000t、西側払出可能量が2,
000tであり、別の15:30〜15:50の作業の接
近干渉によりA山の東側払出可能量が1,000t、西
側払出可能量が1,000tであれば、結果的にA山の
払出可能量は15:10〜15:30が東側3,000
t、西側2,000t、15:10〜15:30が東側1,
000t、西側1,000t、15:50〜16:00が
東側3,000t、西側2,000tとなる。このデータ
を表1のような形で編集して、払出山選択時に該当時間
帯の払出可能量判定に使用する。
Next, with respect to the values individually calculated for each operation in the above calculation, the superposition calculation in time and space between a plurality of operations is logically ORed. For example, due to the approach interference of the work from 15:00 to 16:00, the eastern payable amount of Mt. A is 3,000t, and the west payable amount is 2,000t.
000t, and if the eastward payable amount of Mt. A is 1,000t and the westward payable amount is 1,000t due to another interference of work from 15:30 to 15:50, the payout of Mt. Possible amount is 15:10 to 15:30, east side 3,000
t, 2,000 t on the west, 15: 10-15: 30 on the east
000t, west 1,000t, 15: 50-16: 00 becomes east 3,000t and west 2,000t. This data is edited in the form shown in Table 1 and is used to determine the payable amount in the corresponding time zone when the payout mountain is selected.

【0045】従来の原料搬送計画制御においては、この
ような接近干渉まで考慮したものはなく、本発明によ
り、実用的な計画の立案が可能となった。
In the conventional raw material transfer plan control, there is no consideration of such approach interference, and a practical plan can be made by the present invention.

【0046】図2のフローチャートのJOB割付(F4
0)における処理方法を図10および図11で説明す
る。
Job allocation (F4) in the flowchart of FIG.
The processing method in (0) will be described with reference to FIGS.

【0047】図10は、図2のフローチャートの搬送作
業JOB開始時間範囲計算で計算(図3,図4,図5お
よび図6で説明)した、基準時刻におけるある系統の槽
毎の次の入槽JOB開始時間範囲であり、縦軸が槽、横
軸が基準時刻からの時間を示す。一般に槽毎の次の入槽
JOB開始時間範囲は図のように重複する。この中で実
際に入槽する次JOBおよび次々JOBを割付ける方法
としては、 現JOBとの連続入槽(銘柄が同一)、 在庫下限管理切れ時刻(入槽JOB開始時間範囲の最
大時刻)の緊急度などによって基準に従って決定する。
図の例では、在庫下限管理切れ時刻が迫っている順に次
JOBおよび次々JOBを選択した例である。
FIG. 10 shows the next input for each tank of a certain system at the reference time calculated by the transfer job JOB start time range calculation of the flowchart of FIG. 2 (described in FIGS. 3, 4, 5, and 6). The tank JOB start time range, the vertical axis represents the tank, and the horizontal axis represents the time from the reference time. Generally, the next entry JOB start time range for each tank overlaps as shown in the figure. In this method, the next job and the next job that are actually entered are assigned as follows: continuous entry with the current job (the same brand), inventory lower limit management end time (maximum time in the entry job start time range). It is determined according to the standard depending on the degree of urgency.
In the example shown in the figure, the next job and the next job are selected in the order in which the inventory lower limit management end time is approaching.

【0048】図11は、選択したJOBの開始,終了時
刻を決定する方法の例を示したものである。通常であれ
ば1回の入槽量は多いほど搬送作業効率が向上するた
め、搬送作業JOB開始時間範囲の最大時刻で入槽する
計画とするが、干渉のある上位搬送作業がある場合や、
次々JOBの在庫管理下限切れ時刻が迫っている場合
は、時刻を調整する。
FIG. 11 shows an example of a method for determining the start and end times of the selected job. Normally, the larger the amount of one tank, the greater the transfer work efficiency. Therefore, it is planned to enter the tank at the maximum time of the transfer job JOB start time range.
If the JOB inventory management lower limit time is approaching one after another, the time is adjusted.

【0049】図11の(a)は、選択した次JOBの先に
既に優先度の高い上位JOBが割付けられている例であ
り、この場合は、図のように上位JOBに作業がつなが
る範囲で、最大入槽ができる時刻に次JOBを割付け
る。
FIG. 11A shows an example in which a high-order job having a higher priority is already assigned to the end of the selected next job. In this case, as shown in FIG. The next job is allocated at the time when the maximum entry is possible.

【0050】図11の(b)は、次々JOBの在庫管理下
限切れ時刻が迫っている例であり、この場合も、図のよ
うに次々JOBに作業がつながる範囲で最大入槽ができ
る時刻に次JOBを割付ける。
FIG. 11 (b) shows an example in which the job management lower limit time of the next job is approaching one after another. In this case as well, as shown in FIG. Assign the next job.

【0051】以上のような処理で、基準時刻において、
ある系統の複数槽に対する搬送作業JOB開始時間範囲
の重複のある組合せの中から次のJOBの割付順番およ
び開始終了時刻を決定することができる。そして、一連
のJOBの確定した時点まで基準時刻を更新して、同様
の処理を繰返す。
With the above processing, at the reference time,
The assignment order and start / end time of the next job can be determined from the overlapping combinations of the transfer job JOB start time ranges for a plurality of tanks in a certain system. Then, the reference time is updated until the time when a series of jobs is determined, and the same processing is repeated.

【0052】このようにして、図2のフローチャートに
従って各系統毎,槽毎の入槽搬送作業計画を調整しなが
ら立案することができ、図1に示した搬送制御システム
(下位システム構成は従来と同様)によって自動搬送制
御を実施することができる。
In this way, it is possible to make a plan while adjusting the tank transfer work plan for each system and each tank in accordance with the flowchart of FIG. 2, and the transfer control system shown in FIG. Automatic transport control can be performed by the same method.

【0053】[0053]

【発明の効果】以上のように、鉄鉱石や石炭などの原料
ヤード設備における搬送制御に関して、複数の搬送作業
間で受入,払出,搬送設備(系統)を共有しており、複
数作業を並行して行うため受入,払出設備間の接近干渉
が起こり得るような設備の原料搬送制御において、本発
明の制御システムにより以下のような効果が実現でき
た。
As described above, with respect to the transfer control in the raw material yard equipment for iron ore and coal, the receiving, discharging, and transfer equipment (system) are shared among a plurality of transfer operations, and the plurality of operations are performed in parallel. The following effects can be realized by the control system of the present invention in the raw material transport control of equipment that may cause approach interference between the receiving and discharging equipment.

【0054】(1)自動搬送制御において、設備修理およ
び故障を回避し、槽在庫が管理下限切れを起こさず、複
数搬送作業間での払出,搬送設備の競合,系統干渉を避
けるのみでなく、従来頻発していた払出機/積付機の接
近干渉を回避できるようになった。
(1) In automatic transfer control, equipment repairs and breakdowns are avoided, the tank inventory does not run out of the lower limit of control, and not only avoidance of payout among a plurality of transfer operations, transfer equipment conflicts, and system interference, but also It has become possible to avoid the interference between the dispensing machine and the loading machine, which has frequently occurred in the past.

【0055】(2)搬送作業計画を、従来のように系統毎
の優先順に決定するのではなく、複数系統作業の実行可
能範囲を俯瞰して、搬送作業間の開始/終了時刻の決定
や搬送設備のひもつけを互いに調整しながら行うため、
よりきめの細かい計画が立案できるようになった。
(2) Instead of deciding the transfer work plan in order of priority for each system as in the prior art, it is possible to determine the start / end times between transfer works and to carry out the transfer by taking a bird's-eye view of the executable range of the work of a plurality of systems. In order to adjust the linkage of the equipment while adjusting each other,
More detailed plans can now be made.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の一実施例のシステム構成を示すブロ
ック図である。
FIG. 1 is a block diagram illustrating a system configuration according to an embodiment of the present invention.

【図2】 図1に示すプロセス制御用計算材200の中
心機能である入槽作業計画立案機能の処理内容を示すフ
ローチャートである。
2 is a flowchart showing processing contents of a tank entry work planning function, which is a central function of the process control calculation material 200 shown in FIG.

【図3】 図2に示す搬送作業JOB開始時間範囲計算
F20の計算結果の一例を示すグラフである。
FIG. 3 is a graph showing an example of a calculation result of a transport job JOB start time range calculation F20 shown in FIG. 2;

【図4】 図2に示す搬送作業JOB開始時間範囲計算
F20の計算結果の数例を示すグラフである。
FIG. 4 is a graph showing several examples of calculation results of a transport work JOB start time range calculation F20 shown in FIG. 2;

【図5】 図2に示す搬送作業JOB開始時間範囲計算
F20の計算結果の数例を示すグラフである。
FIG. 5 is a graph showing several examples of calculation results of a transport job JOB start time range calculation F20 shown in FIG. 2;

【図6】 図2に示す搬送作業JOB開始時間範囲計算
F20の計算式の一例を示すグラフである。
FIG. 6 is a graph showing an example of a calculation formula of a transfer job JOB start time range calculation F20 shown in FIG. 2;

【図7】 原料ヤ−ドにおける積付機および払出機の接
近干渉範囲を示す平面図である。
FIG. 7 is a plan view showing an approach interference range of a loading machine and a dispensing machine in a raw material yard.

【図8】 原料ヤ−ドにおける積付機および払出機の接
近干渉範囲を示す平面図である。
FIG. 8 is a plan view showing an approach interference range of a loading machine and a dispensing machine in a raw material yard.

【図9】 原料ヤ−ドにおける積付機および払出機の接
近干渉範囲を示す平面図である。
FIG. 9 is a plan view showing the approach interference range of the loading machine and the dispensing machine in the raw material yard.

【図10】 図2に示すJOB割付、山,移動機,系統
ひもつけF40の計算結果の一例を示すグラフである。
10 is a graph showing an example of a calculation result of job allocation, mountain, mobile device, and system linking F40 shown in FIG. 2;

【図11】 図2に示すJOB割付、山,移動機,系統
ひもつけF40の計算結果の数例を示すグラフである。
11 is a graph showing several examples of calculation results of the job allocation, mountain, mobile device, and system link F40 shown in FIG. 2;

───────────────────────────────────────────────────── フロントページの続き (72)発明者 冨 田 修 司 大分市大字西ノ洲1番地 新日本製鐵株 式会社 大分製鐵所内 (72)発明者 羽 田 野 哲 史 大分市大字西ノ洲1番地 新日本製鐵株 式会社 大分製鐵所内 (72)発明者 丸 山 健 大分市大字西ノ洲1番地 新日本製鐵株 式会社 大分製鐵所内 (58)調査した分野(Int.Cl.6,DB名) B65G 43/00 ──────────────────────────────────────────────────の Continuing on the front page (72) Inventor, Shuji Tomita 1 Oshinoshi, Oita, Nippon Steel Corporation Inside Oita Works (72) Inventor, Satoshi Hatano 1st Nishinosu, Oita, Oita Nippon Steel Corporation Oita Works (72) Inventor Takeshi Ken Maruyama 1 Oshino-shi, Oita City Nippon Steel Corporation Oita Works (58) Fields surveyed (Int.Cl. 6 , DB name) ) B65G 43/00

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】原料受入計画,原料使用計画,原料ヤード
計画,工場稼動計画,設備修理計画,原料ヤード現況,
槽現況,設備現況,搬送作業実績,操業者からの操業前
提条件データである槽/銘柄割付計画を取込む入力手段
A;入力手段Aで取り込んだ 入力データに基づいて、入槽先
槽毎に、基準時刻の現況を基準として槽の原料在庫推移
を計算して、設備修理や故障時間帯を回避し槽在庫が管
理下限切れしないための次回入槽時刻および量の実行可
能範囲を計算する手段B; 前記入槽のための払出山候補を選択し、該当払出山にひ
もつく払出設備候補および払出設備候補にひもつく搬送
設備を選択し、その払出作業における設備接近干渉範囲
を計算する手段C; 複数の次回搬送作業候補に関する前記手段BおよびCの
計算結果から、該当時点で操業優先度の高い作業を判断
し、複数搬送作業間での払出/搬送設備の取合い競合,
干渉,接近干渉を回避するように調整して、搬送作業毎
に使用する払出設備,搬送設備,払出山および前記手段
Bが算出し実行可能範囲内の入槽開始/終了時刻,量を
決定する手段D; 手段Dの計算結果から、直近の計画確定時刻まで槽の原
料在庫推移,原料ヤード推移,受入・払出・搬送設備稼
動状況をシミュレーション計算する手段E; 直近の計画確定時刻を基準時刻として前記手段B〜Eの
処理を計画立案時間分繰返す計算手段F; 計算結果を操業者に提示するための出力手段G; 計算結果に基づいて受入・払出・搬送設備を制御する制
御手段H;および、 計画と実績の差が発生する毎に前記A〜Hによる計算お
よび制御を行なう計算制御手段I; を備える、原料ヤード設備の原料搬送制御システム。
1. Raw material receiving plan, raw material use plan, raw material yard plan, factory operation plan, equipment repair plan, raw material yard current situation,
Input means A for taking in the current state of the tank, the current state of the equipment, the actual results of the transfer work, and the tank / brand allocation plan which is the operation prerequisite data from the operator; based on the input data taken in by the input means A, each input tank A , Means to calculate the raw material stock transition of the tank based on the current situation at the reference time, and to calculate the feasible range of the next entry time and quantity so as to avoid equipment repair and failure time zone and the tank stock does not exceed the lower limit of management B: means C for selecting a dispensing mountain candidate for entering the tank, selecting a dispensing facility candidate associated with the dispensing mountain and a transport facility associated with the dispensing facility candidate , and calculating an equipment approach interference range in the dispensing work. From the calculation results of the means B and C concerning the plurality of next transfer work candidates, the work having the highest operation priority at the time is determined, and the competition of the dispensing / transportation equipment among the plurality of transfer works,
Adjustment is made so as to avoid interference and approaching interference, and the dispensing equipment, transport equipment, dispensing hill used for each transfer operation and the means B are calculated and the start / end time and amount of tanks within the executable range are determined. Means D; means E for simulating the change of the stock of raw material in the tank, the change of the raw material yard, and the operation status of the receiving / discharging / transportation facility from the calculation result of the means D to the latest plan fixed time; the latest planned fixed time as a reference time Calculation means F for repeating the processing of the means B to E for the planning time; output means G for presenting the calculation results to the operator; control means H for controlling the receiving / paying / transporting equipment based on the calculation results; A raw material transport control system for raw material yard equipment, comprising: calculation control means I for performing calculation and control by the above A to H each time a difference between a plan and an actual result occurs.
JP5070493A 1993-03-11 1993-03-11 Raw material transport control system Expired - Lifetime JP2878055B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5070493A JP2878055B2 (en) 1993-03-11 1993-03-11 Raw material transport control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5070493A JP2878055B2 (en) 1993-03-11 1993-03-11 Raw material transport control system

Publications (2)

Publication Number Publication Date
JPH06263231A JPH06263231A (en) 1994-09-20
JP2878055B2 true JP2878055B2 (en) 1999-04-05

Family

ID=12866294

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5070493A Expired - Lifetime JP2878055B2 (en) 1993-03-11 1993-03-11 Raw material transport control system

Country Status (1)

Country Link
JP (1) JP2878055B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100865315B1 (en) * 2002-11-28 2008-10-27 주식회사 포스코 Control Method of Dispensing Shape of Lead and Raw Material Files
JP4344275B2 (en) * 2004-05-07 2009-10-14 新日本製鐵株式会社 Method and apparatus for creating a tank plan for a raw material storage tank
JP4612389B2 (en) * 2004-10-08 2011-01-12 新日本製鐵株式会社 Production and / or distribution plan creation device and method, process control device and method, and computer program
JP5068623B2 (en) * 2007-10-16 2012-11-07 新日本製鐵株式会社 Method and apparatus for creating a tank plan for a raw material storage tank
CN105731095A (en) * 2014-12-09 2016-07-06 中国中轻国际工程有限公司 Solid hot material quantitative charging system and control method thereof
JP6777040B2 (en) * 2017-08-01 2020-10-28 Jfeスチール株式会社 Planning device and planning method

Also Published As

Publication number Publication date
JPH06263231A (en) 1994-09-20

Similar Documents

Publication Publication Date Title
KR20150124958A (en) System and method for controlling at least two automated non-passing rail mounted gantry cranes
JP2878055B2 (en) Raw material transport control system
Temeng et al. A nonpreemptive goal programming approach to truck dispatching in open pit mines
JP6428435B2 (en) Transportation plan creation device and transportation plan creation method
CN113084148A (en) Method and system for controlling molten iron transportation
JP4612409B2 (en) Production and / or distribution plan creation device and method, process control device and method, and computer program
JPH08143134A (en) Sintered ore transportation plan control system
JPH08272402A (en) Inference device for material transportation and dispatch planning
JPH11236116A (en) Material carry control system
JP6602026B2 (en) Logistics processing schedule creation device in steelmaking factory
CN110737255A (en) Automatic processing method for multi-station disordered process paths
JP2626201B2 (en) Optimal transfer control device for raw material yard
CN117102755B (en) Automatic welding station feeding and discharging scheduling system and method suitable for frame production
JP4340089B2 (en) Arrangement plan creation method and apparatus, arrangement distribution control method and apparatus, computer-readable storage medium, and computer program
JP4373275B2 (en) Discharge plan management apparatus, payout plan management method, and program
JP3508597B2 (en) Production line distribution control method
JP5011954B2 (en) Raw material transport allocation plan system and raw material transport allocation plan planning method
JP2009173369A (en) Method, apparatus and program for creating a plan for entering a raw material storage tank
JP2889798B2 (en) Raw material transport control system
JPH0816206A (en) Method and apparatus for determining start order
JP2002175106A (en) Tank entry plan creation method and device, and raw material distribution control method and device
KR100340567B1 (en) Determination method of economical vehicle routings
JPH11116057A (en) Preparation method of material handling yard
JP7770866B2 (en) Fuel operation system for power generation facilities
JP2024157659A (en) Production management system and production management method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990105