JP3263782B2 - Construction method of building structure and lifting device of building structure - Google Patents
Construction method of building structure and lifting device of building structureInfo
- Publication number
- JP3263782B2 JP3263782B2 JP00032799A JP32799A JP3263782B2 JP 3263782 B2 JP3263782 B2 JP 3263782B2 JP 00032799 A JP00032799 A JP 00032799A JP 32799 A JP32799 A JP 32799A JP 3263782 B2 JP3263782 B2 JP 3263782B2
- Authority
- JP
- Japan
- Prior art keywords
- lifting
- floor
- pillar
- building structure
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【発明の属する技術分野】 本発明は、ビル、マンショ
ンなど建物構造体の全天候型建築工法及び扛重装置に係
る技術的分野に属する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention belongs to the technical field of an all-weather construction method and a lifting device for building structures such as buildings and condominiums.
【0002】[0002]
【従来の技術】 従来、全天候型の建物構造体の基礎工
法としては、特開平3−107037号公報、又は特開
平3−107038号公報に開示されているように、コ
ア部1を、仮設支柱、型枠部、ジャッキ及びブラケット
からなる自動上昇型枠により構築するとともに、建築物
の柱13が立設される個所にもジャッキ12を設置す
る。次に2層分のコア部1を先行構築した後、建築物の
最上部から3層分の梁14,柱13を同時構築し、柱用
底型枠、柱用型枠を配設し、柱13及びスラブ24のコ
ンクリートを打設する。そして柱13が自立可能な状態
まで降下した段階で、ジャッキ12などを伸長して躯体
を1層分上方に押し上げ、順次下階の構築作業を継続
し、これを繰り返す建築工法などが知られている。又、
他の工法として特開平5−25864号公報に示すよう
に、建造物の柱10を施工した後、この柱10に沿って
床スラブSを上昇させるという操作を逐次繰り返し実施
して、各床スラブSをそれぞれ各階の床部に配設する。
このような建築躯体の構築方法において、床スラブSを
上昇させる工程を、最上階の床スラブSから次層階側の
床スラブ1Sへ順次に実施する。そして床スラブSの下
面に配置された上昇装置2によって床スラブSを支持し
ながら上昇させる建築工法などが知られている。また、
他の工法として特公平7−33689号公報に示すよう
に、地上レベルで1階分の躯体を集中的に施工し、1階
分の躯体工事完了後に階高分だけ上方に躯体の柱をプッ
シュアップすることを繰り返すことにより建物を施工
し、その場合において、プッシュアップ用ピン穴と固定
用ピン穴を有するフランジを柱に取付けるとともに、当
該プッシュアップ用ピン穴と係合可能なピンを備えるセ
ンターホールジャッキと当該固定用ピン穴と係合可能な
ピンを備える躯体保持装置とを前記柱の周囲に配し、こ
れをもって躯体の柱をプッシュアップする建築工法など
が知られている。2. Description of the Related Art Conventionally, as a foundation construction method for an all-weather building structure, as disclosed in JP-A-3-103737 or JP-A-3-107038, a core 1 is provided with a temporary support. , And a jack 12 is installed at the place where the pillar 13 of the building is erected. Next, after preliminarily constructing the core portion 1 for two layers, the beams 14 and columns 13 for three layers are simultaneously constructed from the top of the building, and a bottom formwork for columns and a formwork for columns are provided. The concrete of the pillar 13 and the slab 24 is cast. At the stage when the pillar 13 is lowered to a state where the pillar 13 can be self-supported, the jack 12 and the like are extended to push up the frame by one layer, and the construction work on the lower floor is sequentially continued. I have. or,
As another construction method, as shown in Japanese Patent Application Laid-Open No. Hei 5-25864, after constructing a pillar 10 of a building, an operation of raising a floor slab S along the pillar 10 is sequentially and repeatedly performed. S is placed on the floor of each floor.
In such a construction method of the building frame, the step of raising the floor slab S is sequentially performed from the floor slab S on the top floor to the floor slab 1S on the next floor. A construction method of raising the floor slab S while supporting the floor slab S by a lifting device 2 arranged on the lower surface of the floor slab S is known. Also,
As another construction method, as shown in Japanese Patent Publication No. 7-33689, one frame of the skeleton is intensively constructed at the ground level, and after completing the framing of the first floor, the pillar of the skeleton is pushed upward by the height of the floor. A building having a push-up pin hole and a flange having a fixing pin hole attached to a pillar, and a center having a pin engageable with the push-up pin hole. There is a known construction method in which a hole jack and a skeleton holding device having a pin that can be engaged with the fixing pin hole are arranged around the pillar, and the pillar of the skeleton is pushed up with this.
【0003】上述した従来の建物構造体の建築工法に
は、次のような特質が認められている。 (a)全天候下での作業がなし得られ、天候に左右され
ない。 (b)高所作業が少ないため安全な施工ができ、而も近
隣に資材落下、飛散などの不安を与えない。 (c)建物の上部にタワークレーンなどの仮設設備を設
けないため、電波などに影響を与えない。The following characteristics are recognized in the above-mentioned conventional construction method for building structures. (A) Work can be performed in all weather conditions and is not affected by weather conditions. (B) Since there is little work at high altitudes, safe construction can be performed, and there is no fear of falling or scattering materials nearby. (C) No temporary equipment such as a tower crane is installed above the building, so there is no effect on radio waves.
【0004】しかしながら、この種従来例のうちの2件
は建物構造体の全天候型建築工法は、最上階から未完の
骨組躯体を順次押し上げてゆく方式であるため、次に示
すような課題が依然として残されている。 (a)各階層における未完躯体の高所建築作業がそのま
ま残されており、資材の落下や飛散などの不安がある。 (b)地層毎に躯体構築用の資材を搬送する設備を要
し、建築作業量の平準化が望めない。また、従来例の他
の1件は、地上レベルで1階分の躯体を施工し、これを
順次プッシュアップする方式であるため、上記の課題は
ないものの次のような課題が残されている。 (c)プッシュアップ用の専用仮設フランジを柱に取り
付けるなど、躯体に取り付ける特別の仮設が必要であ
る。 (d)躯体の柱のプッシュアップ時に、フレームが柱を
囲むためプッシュアップ以前に躯体の梁を柱に取付ける
ことができず、従って梁取付けを中空位置で行わざるを
得ない。[0004] However, two of the conventional examples of this kind are all-weather construction methods for building structures, in which an unfinished frame structure is sequentially pushed up from the top floor, and the following problems still remain. Is left. (A) Unfinished high-level building work at each level is left as it is, and there is concern about falling or scattering of materials. (B) Equipment for transporting building construction materials is required for each stratum, making it impossible to equalize the amount of construction work. Another example of the conventional example is a method in which a frame of one floor is constructed at the ground level and sequentially pushed up, so the following problems are left though the above problems are not present. . (C) It is necessary to provide a special temporary mounting to the frame, such as mounting a dedicated temporary flange for push-up on the pillar. (D) At the time of pushing up the pillar of the skeleton, the frame surrounds the pillar, so that the beam of the skeleton cannot be attached to the pillar before the push-up. Therefore, the beam must be attached in the hollow position.
【0005】上記技術的課題を解決するため、本件発明
者等は、特開平9−88185号公報に示すような、建
物構造体の建築工法及び建物構造体の扛重構造体の扛重
装置を提案している。この公開された先行技術は、地上
近傍で最上階の建物躯体を略完成させ、最上階から完成
した建物躯体を順次扛重し、所要階数の中高層階の建物
構造体を構築せしめ、高所作業のない安全な施工がなし
うるとともに、安定した品質の建物が効能的に得られる
建築工法と扛重装置を提供することにある。In order to solve the above technical problems, the present inventors have proposed a construction method for a building structure and a lifting device for a lifting structure of a building structure as disclosed in Japanese Patent Application Laid-Open No. 9-88185. is suggesting. This published prior art is to complete the building structure on the top floor near the ground, lift the completed building structure from the top floor in order, and build the required number of mezzanine and high-rise building structures. It is an object of the present invention to provide a construction method and a lifting device capable of performing safe construction without any trouble and efficiently obtaining a building of stable quality.
【0006】本発明の目的は、上記特開平9−8818
5号公報に示された建築工法及び扛重装置の技術的事項
をそのまま利用するとともに、この技術に更に建物構造
体を構成する中間主柱の建柱に別個の扛重手段を用い、
更に安定した品質の建物が高能率的に得られる建築工法
と扛重装置を提供することにある。An object of the present invention is to solve the above-mentioned problem described in Japanese Patent Laid-Open No. 9-8818.
In addition to utilizing the technical matters of the construction method and the lifting device shown in Japanese Patent Publication No. 5 as it is, a separate lifting device is used for the pillars of the intermediate main pillars constituting the building structure.
Another object of the present invention is to provide a construction method and a lifting device capable of efficiently obtaining a building of stable quality.
【0007】[0007]
【課題を解決するための手段】 上記課題を解決する手
段として本発明は、次のょうな建物構造体の建築工法を
採用する。Means for Solving the Problems As means for solving the above problems, the present invention employs the following construction method for a building structure.
【0008】上記目的は、基礎上において中高層階建物
構造物の屋上階及び最上階を組立てたのち、建物構造体
を構成する外周主柱近傍の両側梁下面を扛重手段の
(A)の閂にて支持して扛上し、この扛上により生ずる
作業空間部に下層階を順次組み立てて構築するようにし
た建物構造体の建築工法において、建築構造体を構成す
る中間主柱を建柱する基礎杭または地層階主柱上に、建
柱される中間主柱を乗載結合する施工ブロック(埋め殺
し柱)を挟むように、基礎又は地中梁上に配置される2
個一組の架台間に、中間主柱の両側に設けた梁仕口の下
面に接し、中間主柱を扛上する水平姿勢の昇降ビーム
(閂)を夫々設け、昇降ビーム(閂)の一端が、架台に
正、逆回動可能に立設したスクリュー軸に螺合せるナッ
トをもち、かつ、架台に回り止めとした昇降ブロックに
対して旋回可能に軸支するとともに、他端を架台に正、
逆回動可能に立設したスクリュー軸に螺合せるナットを
もち、架台に回り止めとした昇降ブロックに対して着脱
可能に連結した扛重手段(D)を配設せしめ、一方、1
層階分高さの外周主柱の搬入組立てと前後して施工ブロ
ック上に上記外周主柱と略同高の中間主柱を搬入乗載
し、この中間主柱および外周主柱相互間の梁の組立て、
天井部材、小梁などを取付て建物構造体の屋上階及び最
上階を組立てるとともに、この組立て作業と前後して中
間主柱の両側梁下面に、扛重手段(D)の昇降ビーム
(閂)を配設する第1工程、扛重手段(A)と同調し
て、扛重手段(D)により最上階層を1層階分高さに満
たない高さ分だけ扛上したのち、施工ブロック(埋め殺
し柱)上に短尺の仮受け柱を乗載するとともに、最上階
層を若干降下させ、全荷重を仮受け柱に預け、昇降ビー
ム(閂)をフリーにする第2工程、フリーとなった扛重
手段(D)の昇降ビーム(閂)と扛重手段(A)の閂を
さらに降下させ、扛重手段(D)の昇降ビームと梁下面
との間に梁受け台を介装する第3工程、扛重装置
(A)、(D)により建築構造体を扛上し、フリーとなっ
た仮受け柱を退避させるとともに、建築構造体を第1工
程時点より1層階分より若干高く扛上したのち、1層階
分の高さをもつ次層階の外周主柱を扛重手段(A)にお
ける施工ブロック上に、また、次層階の中間主柱を施工
ブロック(埋め殺し柱)上に搬入設置し、扛重手段
(A)の閂、及び扛重手段(D)の昇降ビーム(閂)を
若干降下して全荷重を各施工ブロックに預け、前後して
次層階の梁を各主柱間に組立てる第4工程、フリーとな
った扛重手段(A)の閂を新たに設置された次階層の梁
と干渉しないように引き込み、及び扛重装置(D)の昇
降ビーム(閂)を外方向に約90度旋回移動して新たに
設置された次層階の梁との干渉を避けながら最下位まで
降下させたのち、昇降ビーム(閂)を原位置に復帰さ
せ、次いで若干量上昇させて各主柱両側の梁下面部に臨
ませる第5工程、前記第2〜5工程を繰り返し行い、所
要階層の建築構造体を構築し2階以上の扛上ののちに、
1,2階間の高さに調整した所定長さの外周主柱および
中間主柱を施工ブロック上に組立て、各主柱の上部を2
階の各主柱の下端と結合し、中間主柱の下端を施工ブロ
ックと結合する第6工程、そののち扛重手段(D)におけ
る施工ブロック(埋殺し柱)を恒久部材として残し扛重手
段(A)および扛重手段(D)を解体撤去し、前後して1
階層の建築作業を完了させることにより達成される。[0008] The above object is to assemble the top floor and the top floor of a middle- and high-rise building structure on the foundation, and then to lower the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure by using the bar of lifting means (A). In the construction method of a building structure that is constructed by assembling and constructing lower floors sequentially in the work space generated by the lifting, the intermediate main pillars that constitute the building structure are built. 2 Placed on a foundation or underground beam so as to sandwich a construction block (buried-in pillar) that mounts and connects an intermediate main pillar to be built on a foundation pile or stratum main pillar
Under the beam connection provided on both sides of the intermediate main column between a pair of mountings
Lifting beam in horizontal position that lifts the middle main pillar in contact with the surface
(Bars) are provided, and one end of the lifting beam (bar) is attached to the base.
A nut that is screwed into a screw shaft that can
The lifting block which has
In addition to pivoting on the other side, the other end is
A nut to be screwed into a screw shaft that can be turned upside down
Sticky, attachable and detachable to elevating blocks that are detented on the base
Arresting means (D), which are connected as much as possible,
Before and after the loading and assembling of the outer pillars at the height corresponding to the story, an intermediate pillar having substantially the same height as the outer pillars is loaded and loaded on the construction block, and the beam between the intermediate pillar and the outer pillar is interposed. Assembly,
Attach ceiling members, small beams, etc. to assemble the rooftop and top floors of the building structure, and before and after this assembling work, lift beams (bars) of lifting means (D) on the lower surfaces of the beams on both sides of the intermediate main pillar In the first step of arranging the lift, the lifting means (D) lifts the top floor by the lifting means (D) by a height less than the height of one floor, and then the construction block ( The second process of placing a short temporary support pillar on the buried pillar), lowering the uppermost floor slightly, depositing all the load on the temporary support pillar, and freeing the lifting beam (bar) is free. The lifting beam (bar) of the lifting means (D) and the bar of the lifting means (A) are further lowered, and a beam support is interposed between the lifting beam of the lifting means (D) and the lower surface of the beam. In three steps, lifting structures (A) and (D) are used to lift the building structure and evacuation of the free temporary receiving columns. After lifting the building structure slightly higher than the first floor from the time of the first step, the outer main columns of the next floor having the height of the first floor are placed on the construction block in the lifting means (A). In addition, the intermediate main pillar of the next floor is loaded and installed on the construction block (buried pillar), and the bar of the lifting means (A) and the lifting beam (bar) of the lifting means (D) are slightly lowered. The 4th process of assembling the beam of the next floor between each main column before and after the entire load is deposited in each construction block, and the bar of the free lifting means (A) is newly installed on the next level. Pull in so that it does not interfere with the beams, and move the lifting beam (bar) of the lifting device (D) outward about 90 degrees to move it around the bottom while avoiding interference with the newly installed beam on the next floor. After returning to the original position, the lifting beam (bar) is returned to its original position, and then slightly raised to reach the beam underside on both sides of each main column. Fifth step, repeated the second to fifth step, after the jack up the architectural structure of the building of the second floor above the required hierarchy which,
Assemble an outer main column and an intermediate main column of a predetermined length adjusted to the height between the first and second floors on a construction block, and set the upper part of each main column to 2
The sixth step in which the lower end of each main pillar on the floor is connected to the lower end of the intermediate main pillar, and the lower end of the intermediate main pillar is connected to the construction block. After that, the construction block (buried pillar) in the lifting means (D) is left as a permanent member. (A) and lifting means (D) are dismantled and removed,
Achieved by completing the building work on the level.
【0009】上記目的は、基礎上において中高層階建物
構造物の屋上階及び最上階を組立てたのち、建物構造体
を構成する外周主柱近傍の両側梁下面を扛重手段の
(A)の閂にて支持して扛上し、この扛上により生ずる
作業空間部に下層階を順次組み立てて構築するようにし
た建物構造体の建築工法において、建築構造体を構成す
る中間主柱を建柱する基礎杭または地層階主柱上に、建
柱される中間主柱を乗載結合する施工ブロック(埋め殺
し柱)を挟むように、基礎又は地中梁上に配置される2
個一組の架台間に、中間主柱の両側に設けた梁仕口の下
面に接し、中間主柱を扛上する水平姿勢の昇降ビーム
(閂)を夫々設け、昇降ビーム(閂)の一端が、架台に
正、逆回動可能に立設したスクリュー軸に螺合せるナッ
トをもち、かつ、架台に回り止めとした昇降ブロックに
対して旋回可能に軸支するとともに、他端を架台に正、
逆回動可能に立設したスクリュー軸に螺合せるナットを
もち、架台に回り止めとした昇降ブロックに対して着脱
可能に連結した扛重手段(D)を配設せしめ、一方、1
層階分高さの外周主柱の搬入組立てと前後して施工ブロ
ック上に、上記外周主柱と略同高の中間主柱を搬入乗載
し、この中間主柱および外周主柱相互間の梁の組立て、
天井部材、小梁などを取付て建物構造体の屋上階及び最
上階を組立てるとともに、この組立て作業と前後して中
間主柱の両側梁下面に、扛重手段(D)の昇降ビーム
(閂)を配設する第1工程、扛重手段(A)と同調し
て、扛重手段(D)により最上階層を一層階分高さを越
す高さだけ扛上したのち、扛上手段(A)の施工ブロッ
クおよび扛重手段(D)の施工ブロック(埋め殺し柱)
上に一層階分の高さをもつ次層階の外周主柱と中間主柱
を搬入設置し、扛重手段(A)の閂を新たに設置された
次階層の梁と干渉しないように引き込み、及び扛重装置
(D)の昇降ビーム(閂)を若干降下して全荷重を施工
ブロック(埋め殺し柱)に預け、前後して次層階の梁を
各主柱間に組立てる第2工程、フリーとなった昇降ビー
ム(閂)を外方向に90度旋回移動して新たに設置され
た次層階の梁との干渉を避けながら最下位まで降下させ
たのち、昇降ビーム(閂)を原位置に復帰させ、次いで昇
降ビームを若干量上昇させて各主柱両側の梁下面に臨ま
せる第3工程、 前記2、3工程を繰り返し行い、所要
階層の建築構造体を構築して2階以上の扛上ののちに、
1,2階間の高さに調整した所定長さの外周主柱および
中間主柱を各施工ブロック上に組立て、各主柱の上部を
2階の各主柱の下端と結合し、中間主柱の下端を施工ブ
ロック(埋め殺し柱)と結合する第4工程、そののち扛
重手段(D)における施工ブロック(埋殺し柱)を恒久部
材として残し、扛重手段(A),(D)を解体撤去し、
前後して1階層の建築作業を完了させることにより達成
される。The above object is to assemble the roof top floor and the top floor of the middle and high-rise building structure on the foundation and then to lower the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure by using the bar of lifting means (A). In the construction method of a building structure that is constructed by assembling and constructing lower floors sequentially in the work space generated by the lifting, the intermediate main pillars that constitute the building structure are built. 2 Placed on a foundation or underground beam so as to sandwich a construction block (buried-in pillar) that mounts and connects an intermediate main pillar to be built on a foundation pile or stratum main pillar
Under the beam connection provided on both sides of the intermediate main column between a pair of mountings
Lifting beam in horizontal position that lifts the middle main pillar in contact with the surface
(Bars) are provided, and one end of the lifting beam (bar) is attached to the base.
A nut that is screwed into a screw shaft that can
The lifting block which has
In addition to pivoting on the other side, the other end is
A nut to be screwed into a screw shaft that can be turned upside down
Sticky, attachable and detachable to elevating blocks that are detented on the base
Arresting means (D), which are connected as much as possible,
Before and after the loading and assembling of the outer pillars at the height of the story, the intermediate pillars having substantially the same height as the outer pillars are loaded and loaded on the construction block, and between the intermediate pillars and the outer pillars. Assembling beams,
Attach ceiling members, small beams, etc. to assemble the rooftop and top floors of the building structure, and before and after this assembling work, lift beams (bars) of lifting means (D) on the lower surfaces of the beams on both sides of the intermediate main pillar In the first step, the lifting means (A) is synchronized with the lifting means (A), and the lifting means (D) is used to lift the uppermost level by a height that exceeds the height of one floor, and then the lifting means (A) Construction block and lifting means (D) construction block (buried pillar)
The upper and lower main pillars of the next floor with a height of one floor are loaded and installed on the top, and the bar of the lifting means (A) is pulled in so as not to interfere with the newly installed beam of the next floor. The second step of assembling the beam of the next floor between the main pillars before and after, by slightly lowering the lifting beam (bar) of the lifting device (D) and depositing the entire load on the construction block (fill-in-place pillar) After the free lifting beam (bar) is turned 90 degrees outward and lowered to the lowest position while avoiding interference with the newly installed beam on the next floor, the lifting beam (bar) is The third step of returning to the original position, and then slightly raising the elevating beam so as to reach the lower surfaces of the beams on both sides of each main column. After the above lifting,
Assemble an outer main column and an intermediate main column of a predetermined length adjusted to the height between the first and second floors on each construction block, connect the upper part of each main column to the lower end of each main column on the second floor, The fourth step in which the lower end of the column is joined with the construction block (buried pillar), after which the construction block (buried pillar) in the lifting means (D) is left as a permanent member, and the lifting means (A), (D) Dismantling and removing
This is achieved by completing one level of building work before and after.
【0010】上記目的は、建築構造体を構築する建物内
部の主柱である中間主柱の両側に近接し、かつ、基礎又
は地中梁上に配置される2個一組の架台間に、中間主柱
の両側に設けた梁仕口の下面に接し、中間主柱を扛上す
る水平姿勢の昇降ビーム(閂)を夫々設け、昇降ビーム
(閂)の一端が、架台に正、逆回動可能に立設したスク
リュー軸に螺合せるナットをもち、かつ、架台に回り止
めとした昇降ブロックに対して旋回可能に軸支するとと
もに、他端を架台に正、逆回動可能に立設したスクリュ
ー軸に螺合せるナットをもち、架台に回り止めとした昇
降ブロックに対して着脱可能に連結したことにより達成
される。An object of the present invention is to provide a building in which a building structure is constructed .
On the underside of the beam connection provided on both sides of the intermediate main column between two sets of pedestals that are located on both sides of the intermediate main column, which is the main column of the part , and are placed on the foundation or underground beam A lifting beam (bar) is provided in a horizontal position that lifts up the intermediate main column in contact with it, and one end of the lifting beam (bar) has a nut that is screwed to a screw shaft that stands upright and reversely rotatable on the base. , And has a nut that is rotatably supported on an elevating block that is detented on the gantry and that has the other end screwed to a screw shaft erected on the gantry so that it can rotate forward and backward, and is detented on the gantry. This is achieved by being detachably connected to the lifting block.
【0011】上記目的は、請求項3において、扛重装置
(D)は、架台と機構系より成り、機構系は少なくとも
2個の昇降ビーム(閂)がそれぞれ2個のナットを有
し、各ナットは鉛直に配したスクリュー軸と螺合し、ス
クリュー軸は正回転、逆回転可能であるように構成され
ていることにより達成される。[0011] The above object is achieved by a lifting device according to claim 3.
(D) consists of a gantry and a mechanical system, and the mechanical system has at least two lifting beams (bars) each having two nuts, and each nut is screwed with a vertically arranged screw shaft, Is achieved by being configured to be capable of normal rotation and reverse rotation.
【0012】上記目的は、請求項4において、スクリュ
ー軸を架台に固定し、回転不可とし、ナットが正回転、
逆回転することにより昇降ビームの昇降を行うようにし
たことにより達成される。[0012] The object of the present invention is to fix the screw shaft to the gantry, disable rotation, and rotate the nut forward.
This is achieved by raising and lowering the lifting beam by reverse rotation.
【0013】上記目的は、請求項3〜5の何れかにおい
て、両昇降ビーム(閂)に中間主柱盛り替え酔うの梁受
け台をスライド可能に設けたことにより達成される。[0013] The above object is achieved by any of the third to fifth aspects of the present invention, in which the two main beams (bars) are slidably provided with a beam holder for replacing the main pillar.
【0014】上記目的は、請求項6において、梁受け台
をスイング可能に設けたことにより達成される。[0014] The above object is achieved by providing the beam receiving base in claim 6 so as to be swingable.
【0015】上記目的は、請求項3〜7の何れかにおい
て、昇降ビーム(閂)の降下時に梁との干渉を避けるに
際して、昇降ビームを外方向に約90度旋回可能にした
ことにより達成される。[0015] The above object is achieved by any of the third to seventh aspects of the present invention, in which the elevating beam can be pivoted outward by about 90 degrees in order to avoid interference with the beam when the elevating beam (bar) descends. You.
【0016】上記目的は、請求項3〜8の何れかにおい
て、架台は輸送時の便宜、解体搬出時の便宜および、重
量、寸法を建築設計上の許容値を考慮してブロックに分
割しておくことにより達成される。The above object is achieved in any one of claims 3 to 8 in that the gantry is divided into blocks in consideration of convenience for transportation, convenience for dismantling and carrying out, and weight and dimensions in consideration of allowable values in architectural design. It is achieved by putting.
【0017】[0017]
【発明の実施の形態】 次に、図面について本発明の建
築工法及び扛重装置の詳細を説明する。Next, the construction method and the lifting device according to the present invention will be described in detail with reference to the drawings.
【0018】先ず、特開平9−88185号公報に開示
され、本発明の建築工法に併用するとともに、1層階分
より若干高く建物躯体を一挙に扛上する機能をもつ扛重
装置Aの構成を、図2、図10〜図14について説明す
る。First, the construction of a lifting device A disclosed in Japanese Patent Application Laid-Open No. 9-88185, which is used together with the construction method of the present invention and has a function of lifting a building frame at a time slightly higher than one floor. 2 and FIGS. 10 to 14 will be described.
【0019】1は、建物構造体Bの外周に配設建柱され
る外周主柱2の外側左右に配設される1層階分の高さよ
り背高とした架台であって、該架台1は外周主柱2およ
び梁または梁仕口3と干渉しないよう配置されている。
前記架台1には、外周主柱2側鉛直面に沿うように上下
動する昇降梁5が介設されており、この昇降梁5には前
記架台1に対して脱抜可能に垂設装架したスクリューロ
ッド6を貫通するとともに、このスクリューロッド6は
昇降梁5の左右下部に固定したナット部材7に脱抜可能
に挿入螺合されている。又、前記スクリューロッド6の
上端にはスプロケット8と、両架台1の外側上方に夫々
配設した駆動モータ9の軸に設けたスプロケットとがチ
ェンによって接続されており、駆動モータ9の駆動によ
り回転するスクリューロッド6と、前記昇降梁5に固定
したナット部材7の相関関係により、昇降梁5が架台1
の外側1Aを案内として上下動するように構成されてい
る。図中13はベアリングである。Reference numeral 1 denotes a pedestal having a height higher than the height of a single story disposed on the left and right sides of an outer main pillar 2 disposed on the outer periphery of the building structure B. Are arranged so as not to interfere with the outer main column 2 and the beam or beam connection 3.
The gantry 1 is provided with an elevating beam 5 that moves up and down along the vertical plane on the outer peripheral main column 2 side, and the elevating beam 5 is vertically mounted detachably with respect to the gantry 1. The screw rod 6 penetrates the screw rod 6, and the screw rod 6 is detachably inserted and screwed into a nut member 7 fixed to the lower left and right portions of the lifting beam 5. A sprocket 8 is connected to the upper end of the screw rod 6 and a sprocket provided on a shaft of a drive motor 9 disposed outside and above the gantry 1 by a chain. The sprocket 8 is rotated by the drive of the drive motor 9. Due to the correlation between the screw rod 6 and the nut member 7 fixed to the elevating beam 5, the elevating beam 5
It is configured to move up and down with the outer side 1A as a guide. In the figure, reference numeral 13 denotes a bearing.
【0020】次に前記昇降梁5の構成について説明す
る。昇降梁5の上面左右側、詳しくは、昇降梁5に挿貫
した前記両スクリューロッド6の夫々内側部位に、昇降
梁5の左右軸線方向と直行する前後軸線方向にそって進
退移動可能で、かつ、閂構造からなる2個の荷重受け梁
14を平行に乗載せしめる。この両荷重受け梁14は昇
降梁5の上面に立設された2枚一組の案内板15間にス
ライド自在に挿嵌することとともに、夫々の荷重受け梁
14の先端上部に、梁の歪調整用の円筒座16を上面に
もつ調整ブロック17を設ける。なお、調整ブロック1
7は場合により省略できる。18は、前記昇降梁5の後
部に設けた正面形状が門構形をした前記荷重受け梁14
の反力を支受する連絡梁で、昇降梁5の上面と連結梁1
8の下面間に荷重受け梁14をスライド可能に挟持し、
荷重受け梁14の先端に掛かる荷重の反力を連結梁18
で支承するようにしたものである。図中19は連結梁1
8補助梁18の補強用の支持梁である。Next, the structure of the lifting beam 5 will be described. The upper and lower sides of the elevating beam 5, specifically, the inside portions of the two screw rods 6 inserted into the elevating beam 5, can move forward and backward along the front-rear axis direction perpendicular to the left-right axis direction of the elevating beam 5, At the same time, two load receiving beams 14 having a bar structure are mounted in parallel. The load receiving beams 14 are slidably inserted between a pair of guide plates 15 erected on the upper surface of the elevating beam 5, and a distortion of the beam is placed on the upper end of each load receiving beam 14. An adjustment block 17 having a cylindrical seat 16 for adjustment on the upper surface is provided. Adjustment block 1
7 can be omitted in some cases. Reference numeral 18 denotes the load receiving beam 14 provided at the rear of the lifting beam 5 and having a frontal gate shape.
A connecting beam that receives the reaction force of
8, the load receiving beam 14 is slidably held between the lower surfaces,
The reaction force of the load applied to the tip of the load receiving beam 14 is
It is intended to be supported by. 19 in the figure is connecting beam 1
8 is a support beam for reinforcing the auxiliary beam 18.
【0021】前記昇降梁5の両側端面に比較的広巾の凹
所20を形成するとともに、この凹所20に嵌合介入す
る凸部ガイド(図示略)を前記架台1の外側壁の内面上
下方向に形成したものである。そして、凸部ガイドの前
後面又は前記凹所20を構成する前部壁面及び前記連結
梁18の前面上部に、両者の摺動を円滑にするためのテ
フロン樹脂板などの摺動部材22を張設せしめる。尚、
このテフロン樹脂板に代え、凹所20又は凸部ガイドの
何れかの前後面にローラ(図示略)を設けるものであ
る。そして、図2、図11から明らかなように、前記2
本の荷重受け梁14が外周主柱2を挟むようにして架台
1が配置され、該外周主柱2間に取り合う両側の梁の基
部、詳しくは、外周主柱2に設けた梁または梁仕口3の
下面を両荷重受け梁14によって支持し、建築作業が略
完了した建物躯体Cを一層階分余扛上するようにしたも
のである。図中3cは、コーナー部主柱2に梁仕口3が
片側にしかないため、この梁仕口3と対称位置に設ける
仮仕口である。扛重装置Aは上述のように構成されてい
る。A relatively wide recess 20 is formed on both end surfaces of the lifting beam 5 and a convex guide (not shown) which fits into the recess 20 is provided in the vertical direction of the inner surface of the outer wall of the gantry 1. It is formed in. Then, a sliding member 22 such as a Teflon resin plate for facilitating sliding between the two is provided on the front and rear surfaces of the convex guide or on the front wall surface forming the recess 20 and the upper front surface of the connecting beam 18. I will set it up. still,
Instead of the Teflon resin plate, rollers (not shown) are provided on the front and rear surfaces of either the concave portion 20 or the convex portion guide. Then, as is apparent from FIGS.
The gantry 1 is arranged so that the load receiving beams 14 sandwich the outer peripheral main column 2, and the bases of the beams on both sides that are interposed between the outer peripheral main columns 2, more specifically, the beam or beam connection 3 provided on the outer main column 2. Is supported by both load receiving beams 14, so that the building skeleton C, for which the construction work has been substantially completed, is further lifted by a floor. In the figure, reference numeral 3c denotes a temporary connection provided at a position symmetrical to the beam connection 3 because the beam connection 3 is only on one side of the corner main pillar 2. The lifting device A is configured as described above.
【0022】次に、前述した扛重装置Aを使用する建物
構造体Bの建築工法を図14について説明する。図14
aに示すように、施工レベルを調整した施工用ブロック
23の外方に扛重装置Aを配設し、前記扛重装置Aを構
成する平行2条の荷重受け梁14の中間に施工用ブロッ
ク23を位置させる。該施工用ブロック23は建物構造
体Bの基礎上に設け、建物本来の主柱1の一部を転用し
てもよい。該施工用ブロック23上に最上階の外周主柱
2を立設し、この外周主柱2に最上階の屋上構成用の柱
間梁53を取り付けるとともに、最上階床面構成用の柱
間梁53、を夫々とりつけ、最上階の建物躯体Cの建築
作業を完成させる。(図2参照)Next, a construction method of a building structure B using the above-described lifting device A will be described with reference to FIG. FIG.
As shown in a, the lifting device A is disposed outside the construction block 23 whose construction level has been adjusted, and the construction block is provided between the two parallel load receiving beams 14 constituting the lifting device A. Position 23. The construction block 23 may be provided on the foundation of the building structure B, and a part of the main pillar 1 of the building may be diverted. On the construction block 23, the outermost main pillar 2 of the top floor is erected, and the outer main pillar 2 is attached with a stud 53 for the rooftop structure of the top floor, and a stud beam for the top floor structure. 53, respectively, to complete the construction work of the building skeleton C on the top floor. (See Fig. 2)
【0023】最上階の建物躯体Cが完成したら図14b
に示すように、両荷重受け梁14を前進させ、これの先
端に設けた調整ブロック17を梁仕口3,仮仕口3cの
下側に夫々臨ませたのち、前記駆動モータ9の駆動にス
クリューロッド6を回転させ、ナット部材を介して昇降
梁5を梁仕口3,仮仕口3cの下面に当接せしめ、図1
4cに示すように全ての外周主柱2を若干扛重して全荷
重受け梁14への載荷を確認するようにして、全ての扛
重装置Aの零点調整制御を行う。(図11参照)When the building structure C on the top floor is completed, FIG.
As shown in (2), the load receiving beams 14 are advanced, and the adjustment blocks 17 provided at the ends thereof are made to face under the beam ports 3 and the temporary ports 3c, respectively. By rotating the screw rod 6, the lifting beam 5 is brought into contact with the lower surface of the beam connection 3 and the temporary connection 3c via the nut member, and FIG.
As shown in FIG. 4c, zero lifting adjustment of all the lifting devices A is performed by slightly lifting all the outer main pillars 2 and confirming the load on all the load receiving beams 14. (See Fig. 11)
【0024】このように扛重装置Aの零点調整制御が完
了したら、図14dのように、例えば約20mm/min
の上昇スピードで約3時間で最上階建物躯体Cを一層階
分余扛重し、最上階の建物躯体Cの下方に次層階の作業
空間24を形成する。When the zero-point adjustment control of the lifting device A is completed in this way, as shown in FIG.
In about 3 hours at the rising speed, the top-floor building frame C is lifted by one more floor, and a work space 24 of the next floor is formed below the top-layer building frame C.
【0025】次いで、図14eに示すように、作業空間
24を利用して前記全てのブロック23上に一層階分の
長さを有する外周主柱2を搬入して最上階外周主柱2の
下部に取付け、最上階の建物躯体Cの扛重姿勢を保持し
たまま、この立設された外周主柱2に次層階床面構成用
の梁仕口3を取り付け、最上階建物期待Cを構成する外
周主柱2の下端と、次層階構成用の外周主柱2の上端と
を溶接又はガセットを用いた結合手段にて連結連合して
次層階の建築作業を管理用させて、次層階建物躯体Cを
構成したのち、図14fに示すように、駆動モータ9を
逆転させてスクリューボルト6の作用で昇降梁5を若干
下降させて、建物躯体Cの全荷重を施工用ブロック23
に載せ替え、次いで荷重受け梁14による最上階建物躯
体C、梁仕口3,仮仕口3c下面の支持を解除する。そ
して、図14g〜図14iに示すように、前記荷重受け
梁14を梁仕口3,仮仕口3cと無関係な後方に退避さ
せることにより、昇降梁5を次層階の梁仕口3に干渉し
ない状態で最下位まで下降させた上で、荷重受け梁14
を前進させて調整ブロック17を次層階建物躯体Cを構
成する梁仕口3,仮仕口3cの下方に臨ませる。Next, as shown in FIG. 14e, the outer peripheral main pillar 2 having a length corresponding to one floor is loaded onto all the blocks 23 by using the working space 24, and the lower part of the outermost main pillar 2 on the uppermost floor is taken. , While maintaining the lifting posture of the building frame C on the top floor, a beam connection 3 for the floor of the next floor is attached to the standing outer pillar 2 to form the expected building C on the top floor. The lower end of the outer main column 2 to be connected to the upper end of the outer main column 2 for the next floor is welded or connected by connecting means using gussets to manage the construction work of the next floor, and After constructing the multi-story building frame C, as shown in FIG. 14f, the drive motor 9 is reversed and the lifting beam 5 is slightly lowered by the action of the screw bolt 6, so that the entire load of the building frame C is applied to the construction block 23.
Then, the support of the uppermost building frame C, the beam connection 3, and the temporary connection 3c under the load receiving beam 14 is released. Then, as shown in FIGS. 14g to 14i, the load receiving beam 14 is retracted to the rear irrespective of the beam connection 3 and the temporary connection 3c, so that the lifting beam 5 is moved to the beam connection 3 on the next floor. After lowering to the lowest position without interference, the load receiving beam 14
To make the adjustment block 17 face below the beam connection 3 and the temporary connection 3c constituting the next-story building frame C.
【0026】次に図14jのように、前記と同様な手段
で昇降梁5を上昇させて調整ブロック17を梁仕口3,
仮仕口3cの下面に当接せしめ、次層階を含む最上階の
建物躯体Cを若干上昇させ、円筒座16で梁仕口3をも
つ梁の歪調整と全ての扛重装置Aの零点調整制御を行っ
たのち、図14kで示すように、建物躯体Cを1層階分
余扛上し、これの下方に次々層階の作業空間を構成し、
以下所要階層n−2層〜2階まで上層から下層に向かっ
て図14e、図14kの工法を繰り返し行う。Next, as shown in FIG. 14j, the lifting beam 5 is raised by means similar to the above, and the adjustment block 17 is moved to the beam connection 3,
Abut the lower surface of the temporary connection 3c, slightly raise the building frame C on the top floor including the next floor, adjust the distortion of the beam having the beam connection 3 with the cylindrical seat 16, and set the zero point of all lifting devices A. After performing the adjustment control, as shown in FIG. 14k, the building skeleton C is lifted up by one floor, and a work space of the next floor is formed below the floor,
14e and 14k are repeatedly performed from the upper layer to the lower layer from the (n-2) th layer to the second floor.
【0027】図14lに示すように、2階までの建物躯
体Cが完了したら、施工用ブロック23を撤去するか、
あるいは、施工用ブロック23を本来の1階外周主柱2
の一部として埋殺し、1階高さを補足する短柱25を2
階外周主柱2の下部に結合するか、あるいは1階の構築
に必要な高さまで扛重し、2階建物躯体を構成する外周
主柱2との間に1階の外周主柱2を乗載結合したのち、
2階を含む建物躯体Cを図14mに示すように下降さ
せ、2階構成用の外周主柱2の下端と短柱25の上端と
を結合してから荷重受け梁14を下降し、2階構成用の
外周主柱2の梁仕口3B、仮仕口3cに対する下面支持
を解除したのち、全ての扛重装置Aを外側方に退去さ
せ、1階の建築作業を完了させ、所要階層の建物構造体
Bを得る。As shown in FIG. 14L, when the building frame C up to the second floor is completed, the construction block 23 is removed or
Alternatively, the construction block 23 may be replaced with the main pillar 2 on the first floor.
2 short pillars 25 that are buried as part of
It is connected to the lower part of the outer peripheral main pillar 2 or lifted to the height required for the construction of the first floor, and the outer main pillar 2 of the first floor is placed between the outer main pillar 2 and the outer main pillar 2 constituting the second-floor building frame. After joining
The building skeleton C including the second floor is lowered as shown in FIG. 14m, the lower end of the outer main column 2 for the second floor configuration is joined to the upper end of the short column 25, and then the load receiving beam 14 is lowered, and the second floor is lowered. After releasing the lower surface support of the outer peripheral main column 2 for the beam connection 3B and the temporary connection 3c of the configuration, all the lifting devices A are retreated outward and the construction work on the first floor is completed, and A building structure B is obtained.
【0028】次に、図2〜図6について、建物内部の主
柱である中間主柱32に関し本発明の建築工法を実施す
るための扛重装置Dに係る実施の形態を説明する。Next, with reference to FIGS. 2 to 6, an embodiment of a lifting device D for implementing the construction method of the present invention with respect to an intermediate main column 32 which is a main column inside a building will be described.
【0029】52は、建物完成時の1階の中間主柱32
の下端の一部を切り出した施工ブロック(埋殺し柱)であ
り、施工終了後は1階の中間主柱の一部として恒久材と
するものである。31は、施工ブロック(埋殺し柱)に結
合され、凡そ1層階分の高さを持つ架台である。この架
台31は、中間主柱32の組立位置を挟むように、これ
の両側に近接して配設される2個一組で、而も上下方向
に複数に分割可能な架台構成体31a、31bからなる。
扛重手段Dは施工ブロック(埋め殺し柱)52を介して
基礎杭あるいは地層階の中間主柱33で支持される。補
助的にライナー33bで安定性を増すこともできる。Reference numeral 52 denotes an intermediate main pillar 32 on the first floor when the building is completed.
It is a construction block (buried pillar) cut out from the lower end, and after the construction is completed, it will be made a permanent material as a part of the middle main pillar on the first floor. Reference numeral 31 denotes a gantry connected to a construction block (buried pillar) and having a height of about one floor. The gantry 31 is a set of two pedestals 31a and 31b which are arranged close to both sides of the intermediate main column 32 so as to sandwich the assembly position of the intermediate main column 32, and which can be divided into a plurality of vertically. Consists of
The lifting means D is supported by a foundation pile or an intermediate main pillar 33 on a stratum floor via a construction block (buried pillar) 52. In addition, the stability can be increased by the liner 33b.
【0030】図2、図3から明らかなように、各架台構
成体31a、31bの両側下部は、分解可能な継ぎ部材3
4によって結合されるとともに、両架台構成体31a、
31bの両側下部には、スプロケット35をもつ回転伝
達体36が夫々設けられており、この回転伝達体36の
上部に架台31よりやや背低のスクリュー軸37がキー
構造を介して回動可能に、かつ、嵌脱自在に垂設されて
いる。又、両架台構成体31a、31bの両外側部には駆
動モータ38を夫々設け、この駆動モータ38の駆動軸
に設けたスプロケット39と、前記スプロケット35と
がチェンまたは別途トルク伝達系40によって連結され
ており、各駆動も38の正逆、逆転駆動が回転伝達体3
6を介して各別にスクリュー軸37に伝達される。As is clear from FIGS. 2 and 3, the lower portions on both sides of each of the gantry members 31a and 31b are provided with disassemblable joining members 3
4, and both gantry structures 31a,
Rotation transmission bodies 36 each having a sprocket 35 are provided at the lower portion on both sides of 31b, and a screw shaft 37 slightly shorter than the gantry 31 is rotatable above the rotation transmission body 36 via a key structure. And it is vertically installed so that it can be freely inserted and removed. Driving motors 38 are provided on both outer sides of both gantry structures 31a and 31b, respectively. A sprocket 39 provided on a driving shaft of the driving motor 38 and the sprocket 35 are connected by a chain or a separate torque transmission system 40. Each drive also has 38 forward / reverse and reverse rotation drives.
6 to the screw shaft 37 separately.
【0031】スクリュー軸37は、閂構造とした昇降ブ
ロック41に固定したナット部材42に対して脱抜可能
に夫々挿入螺合されている。一方、各昇降ブロック41
の両側には対称的に案内凸部41aを設け、この案内凸
部41aは架台31の両側縦方向に形成した案内凹溝3
1cに嵌合してあり、ナット部材42、詳しくは、スク
リュー軸37の回動作用が昇降ブロック41の昇降作用
に変換せさめられ、全ての昇降ブロック41が均等に而
も同期昇降しうるように構成されている。又、案内凹溝
31cの内面または、案内凸部41aの周面に、テフロン
樹脂板などの摺動部材43を設け、両者の摺動を円滑に
する。又、この摺動部材43に代え、何れかにローラ
(図示略)を転動可能に付設してもよい。また、図示は
してないがスクリュー軸37を架台31a、31bに対
して回転しないよう固定し、ナット部材42を回転させ
るように構成してもよい。The screw shaft 37 is removably inserted and screwed into a nut member 42 fixed to an elevating block 41 having a bar structure. On the other hand, each lifting block 41
Are provided symmetrically on both sides of the base 31. The guide protrusions 41a are formed in the guide grooves 3 formed in the longitudinal direction on both sides of the gantry 31.
1c, the rotation of the nut member 42, more specifically, the screw shaft 37 is converted into the lifting and lowering of the lifting block 41, so that all the lifting blocks 41 can be raised and lowered equally and synchronously. Is configured. Further, a sliding member 43 such as a Teflon resin plate is provided on the inner surface of the guide groove 31c or on the peripheral surface of the guide convex portion 41a to make the sliding of both members smooth. Instead of the sliding member 43, a roller (not shown) may be rotatably attached to any of the members. Further, although not shown, the screw shaft 37 may be fixed to the frames 31a and 31b so as not to rotate, and the nut member 42 may be rotated.
【0032】一方の架台構成体31aの両昇降ブロック
41が他方の架台構成体31bに対面する側に、昇降ビ
ーム44のいったんを旋回可能に夫々軸支するととも
に、昇降ビーム44の遊動他端に連結用の孔44aを垂
設する。又、他方の架台構成体31bに設けた両昇降ブ
ロック41が、一方の架台構成体31aに対面するする
側に、前記連結用の孔44aに適用する孔44bを設け、
両孔44a、44bが適合したときに、この両孔44a、
44bに上方よりノックピン45を共通的に挿入し、両
昇降ブロック41間に昇降ビーム44が橋架的に連結固
定される。両昇降ブロック41間に橋架された昇降ビー
ム44は、図から明らかなように、中間主柱32の側面
に固装されている梁仕口32aの下面に対応するように
構成してある。又、両架台構成体31a、31bのスクリ
ュー軸37及びこれの三方を囲うようにした案内凹溝3
1cを設けた架台部分を除いた基部は、比較的平面部分
が広く構成されているので、この平面部分を口述する盛
り替え用の仮受け柱32bの退避場所として利用しう
る。The two lifting / lowering blocks 41 of one of the gantry structures 31a support the traverse beam 44 once so as to be pivotable on the side facing the other gantry structure 31b. A connecting hole 44a is vertically provided. Further, the two lifting blocks 41 provided on the other gantry structure 31b are provided with holes 44b to be applied to the connection holes 44a on the side facing one gantry structure 31a,
When the two holes 44a, 44b are fitted, the two holes 44a, 44b,
A knock pin 45 is commonly inserted from above into 44b, and the lifting beam 44 is fixedly connected between the lifting blocks 41 in a bridge manner. The lifting beam 44 bridged between the lifting blocks 41 is configured to correspond to the lower surface of the beam connection 32a fixed to the side surface of the intermediate main column 32, as is apparent from the drawing. Further, the screw shaft 37 of each of the gantry constituting bodies 31a and 31b and the guide groove 3 surrounding the three sides thereof are provided.
Since the base portion excluding the pedestal portion provided with 1c has a relatively wide flat portion, the flat portion can be used as a retreat place for the temporary receiving pillars 32b for dictation.
【0033】図から明らかなように、昇降ビーム44に
はこれの軸線にそってスライド移動可能なスライド筒4
6が被嵌されており、該スライド筒46上には梁仕口3
2aの下部に臨み、かつ、中間主柱32の盛り替え用と
して用いる梁受け台47が付設してある。扛重装置D
は、上述のように構成されている。As is apparent from the figure, the lifting cylinder 44 has a sliding cylinder 4 slidable along its axis.
6 are fitted, and the beam connection 3 is placed on the slide cylinder 46.
A beam support 47 which faces the lower portion of 2a and is used for refilling the intermediate main pillar 32 is additionally provided. Lifting device D
Is configured as described above.
【0034】図7は、前述した実施の形態の昇降ビーム
44の遊動端部の内側面に、係合ロック凹部48を形成
したものを示し、この係合ロック凹部48が、他方の昇
降ブロック41に形成した係合ロック凸部49に係合離
脱しうるように構成する。その他の構成は実施の形態で
説明したものと同様であることから、同一構成部分には
同一符号を付すことにより詳細な説明は省略する。FIG. 7 shows an embodiment in which an engaging lock recess 48 is formed on the inner surface of the floating end of the lifting beam 44 of the above-described embodiment. Is configured to be able to be disengaged from and engaged with the engagement lock convex portion 49 formed in the above. Since other configurations are the same as those described in the embodiment, the same components are denoted by the same reference numerals, and detailed description is omitted.
【0035】図8は、前述した実施の形態の梁受け台4
7の別形態を示している。この形態は、中間主柱32の
梁仕口32aの下部から外れた位置の昇降ビーム44の
上面に、梁受け台50を反転可能、詳しくは、この梁受
け台50の梁仕口32a側の下端角隅部を昇降ビーム4
4に軸支せしめ、この状態の梁受け台50を反転させる
ことにより梁仕口32aの直下部に梁受け台50が隣設
されるようにしたものである。FIG. 8 shows the beam support 4 of the above-described embodiment.
7 shows another embodiment. In this embodiment, the beam receiving base 50 can be inverted on the upper surface of the elevating beam 44 at a position deviated from the lower part of the beam opening 32a of the intermediate main column 32. More specifically, the beam receiving base 50 is located on the side of the beam opening 32a. Lift beam 4 at lower corner
4 and the beam receiving base 50 in this state is inverted so that the beam receiving base 50 is provided immediately below the beam connection 32a.
【0036】図9は、前述した実施の形態の梁受け台4
7の更に別形態を示している。この形態は、中間主柱3
2の梁仕口32aの下方に対応する昇降ビーム44の側
面に、この昇降ビーム44の上面と同一平面となる梁受
け台51の上端角隅部を軸支せしめ、この状態の梁受け
台51を反転して昇降ビーム44の上面に乗載支持して
梁仕口32aの直下32aの直下に梁受け台51を臨ま
せ、中間主柱32の盛り替えとして使用しうるように構
成したものである。FIG. 9 shows the beam receiver 4 of the above-described embodiment.
7 shows still another embodiment. This form is an intermediate main pillar 3
The upper end corner of a beam receiving base 51 coplanar with the upper surface of the lifting / lowering beam 44 is axially supported on the side surface of the lifting / lowering beam 44 below the second beam connection 32a. And the beam supporting base 51 is mounted on the upper surface of the elevating beam 44 and supported so as to face the beam receiving base 51 directly below the beam connection 32a, so that the intermediate main column 32 can be used as a rearrangement. is there.
【0037】昇降ビーム(44)に対する梁受け台の装着
手段としては特に図示してないが、前述した実施の形態
以外多々想定しうることから、図示のものに特定される
ことはない。Although the means for attaching the beam support to the elevating beam (44) is not specifically shown, it is not limited to the one shown in the drawings since it can be supposed in many ways other than the embodiment described above.
【0038】次に、前述した扛重装置Dを使用する建物
構造体Bの建築工法を、図1a〜eについて説明する。
尚、この建築工法については、前述した扛重装置Aを扛
重装置Dと同調した挙動で使用することは勿論である。Next, a construction method of a building structure B using the above-described lifting device D will be described with reference to FIGS.
In this construction method, it goes without saying that the above-mentioned lifting device A is used in synchronism with the lifting device D.
【0039】図1aは、扛重装置D、詳しくは、架台3
1を構成する架台構成体31a、31bを全ての中間主柱
32の両側に設置し、両架台構成体31a、31b間に橋
架した昇降ビーム44を中間主柱32の両側に設けた梁
仕口32aの下部に臨ませた姿勢を示している。図中5
2は、中間主柱33上に溶接された短尺の施工用ブロッ
ク(埋め殺し柱)である。この図1aは昇降開始準備完
了後の姿勢を示しており、主柱2の梁仕口32aと、こ
れに対応する中間主柱32の梁仕口32a間には柱間梁
53が接続されている。FIG. 1A shows a lifting device D, more specifically, a gantry 3
1 is provided on both sides of all of the intermediate main columns 32, and a beam connection is provided on both sides of the intermediate main columns 32, with elevating beams 44 bridged between the two main columns 31 a and 31 b. It shows a posture facing the lower portion of the lower portion 32a. 5 in the figure
Reference numeral 2 denotes a short construction block (buried pillar) welded onto the intermediate main pillar 33. FIG. 1a shows the posture after completion of the preparation for starting the elevating operation. An inter-column beam 53 is connected between the beam connection 32a of the main column 2 and the corresponding beam connection 32a of the intermediate main column 32. I have.
【0040】図1aの状態において、全てのスクリュー
軸37を同期駆動して昇降ビーム44を上昇させ、梁仕
口32aを介して中間主柱32を定められたストロー
ク、詳しくは、仮受け柱32bの高さより若干高い位置
まで上昇させる。次いで、架台31の基部上に待機させ
ていた仮受け柱32bを埋め殺し柱52の上に搬送乗載
したのち、スクリュー軸37を逆回転させて昇降ビーム
44を下降せしめて中間主柱32の下端を仮受け柱46
上に乗せ全ての荷重を預ける。(図1b参照)In the state shown in FIG. 1A, all the screw shafts 37 are driven synchronously to raise and lower the elevating beam 44, and the intermediate main column 32 is set to a predetermined stroke through the beam connection 32a. To a position slightly higher than the height of Next, after the temporary receiving column 32b that has been waiting on the base of the gantry 31 is buried and transported and mounted on the column 52, the screw shaft 37 is rotated in the reverse direction to lower the lifting beam 44 to lower the intermediate main column 32. Temporary receiving pillar 46 at the lower end
Put it on top and keep all the load. (See Fig. 1b)
【0041】この状態で、更に昇降ビーム44を下降さ
せ、これに設けた梁受け台47の上面が梁仕口32aの
下面より若干下方となるように下降させた時点で、梁受
け台47を昇降ビーム44に沿って横移動(紙面右方
向)して梁受け台47を梁仕口32aの下方にセットす
る。(図1c参照)In this state, the elevating beam 44 is further lowered, and when the upper surface of the beam receiver 47 provided on the lower beam is lowered slightly below the lower surface of the beam connection 32a, the beam receiver 47 is lowered. The beam receiver 47 is moved laterally (rightward on the paper) along the elevating beam 44 to set the beam receiver 47 below the beam connection 32a. (See Fig. 1c)
【0042】次いで、スクリュー軸37を駆動して中間
主柱32を大きく、詳しくは、1層階より若干高く上昇
させ、この中間主柱32の下面と埋め殺し柱52の上面
との開きが、1層階分高さの中間主柱32の高さより若
干高く扛上した時点で昇降ビーム44の上昇を止め、上
層階の中間主柱32の下部空間に新たな中間主柱32を
搬入介装する。(図1d参照)Next, the screw shaft 37 is driven to make the intermediate main column 32 larger, specifically, slightly higher than the first floor, so that the lower surface of the intermediate main column 32 and the upper surface of the buried column 52 are opened. The lifting beam 44 is stopped when the vehicle is lifted slightly higher than the height of the intermediate main column 32 at the height of the first floor, and a new intermediate main column 32 is inserted into the lower space of the intermediate main column 32 on the upper floor. I do. (See Fig. 1d)
【0043】この状態て昇降ビーム44を下降させ、そ
の下降途中で上層階の中間主柱32の下端を、新たに搬
入された中間主柱32の上端に乗載支持せしめるととも
に、荷重を預け、更に下降する昇降ビーム44により梁
仕口32a から解放された状態にある昇降ビーム44の
遊動端と、昇降ブロック41を連結しているノックピン
45を外し、フリーとなった昇降ビーム44を外方向に
約90度旋回させる。旋回された昇降ビーム44は、新
たに搬入された中間主柱32の梁仕口32aの領域から
外側方にあるため、昇降ビーム44は最下位の上昇移動
開始準備位置まで降下する。(図1e参照)In this state, the elevating beam 44 is lowered, and the lower end of the intermediate main column 32 of the upper floor is supported on the upper end of the newly introduced intermediate main column 32 during the descent, and the load is deposited. Further, the floating end of the lifting beam 44 released from the beam connection 32a by the lowering lifting beam 44 and the knock pin 45 connecting the lifting block 41 are removed, and the free lifting beam 44 is moved outward. Turn about 90 degrees. Since the swiveled elevating beam 44 is located outside the region of the beam connection 32a of the newly-loaded intermediate main column 32, the elevating beam 44 descends to the lowest elevating movement start preparation position. (See Fig. 1e)
【0044】そして昇降ビーム44を逆方向に約90度
旋回してに戻し、これの遊動端をノックピン45で昇降
ブロック41に結合す。(図1a参照)Then, the elevating beam 44 is turned back by about 90 degrees in the reverse direction, and its free end is connected to the elevating block 41 by the knock pin 45. (See Fig. 1a)
【0045】図1a〜図1eの作業を扛重装置Dと、こ
れの挙動に同期する扛重装置Aを用いて繰り返し行うこ
とにより、所望階層の建物を構築することができる。そ
して全ての扛重装置A、Dを外側方に分解し撤去したの
ち、1階の建築作業を完了させて所要階層の建物構造体
Bが完了する。By repeating the operations shown in FIGS. 1A to 1E using the lifting device D and the lifting device A synchronized with the behavior of the lifting device D, a building of a desired floor can be constructed. Then, after all the lifting devices A and D are disassembled outward and removed, the construction work on the first floor is completed to complete the building structure B on the required level.
【0046】[0046]
【発明の効果】 上述のように本発明の構成によれば、
次のような効果が得られ。According to the configuration of the present invention as described above,
The following effects are obtained.
【0047】全天候下での作業がなし得られ、天候に左
右されずに工期の大巾 短縮が図れ、高所作業がないた
め安全な施工ができ、資材の落下、飛散などによる不安
がなく、最上階から所要階層に至る角隅層の建物躯体を
順次完了させる工法であるため、作業は全て地上階での
施工となり安定した品質の建物が得られ、更に、略完成
された建物躯体の扛重作用点が、全ての外周、中間主柱
近傍の両側梁下面支持によって行われるため、階層が進
むにつれて増加される荷重に充分耐えることができると
ともに、各階層の建物躯体の完了毎に支持梁の歪取り調
整と全ての扛重装置の零点調整制御が行なわれるため、
すでに完成された建物躯体の扛重による損傷のない中高
層建物の構築が効率よく行えることは勿論のこと。Work can be performed under all weather conditions, the construction period can be shortened without being affected by the weather, and work can be performed safely because there is no work at high altitudes. Since this is a construction method that sequentially completes the corner framing from the top floor to the required floor, all work is done on the ground floor and a stable quality building is obtained.Furthermore, the almost completed building framing is lifted. Since the point of heavy action is provided by the support on both sides of the beam near the outer periphery and the middle main column, it is possible to withstand the load that increases as the story progresses, and to support the beam every time the building frame of each story is completed. Adjustment and zero point adjustment control of all lifting devices are performed.
Of course, it is possible to efficiently build a mid- to high-rise building without damage due to the lifting of the completed building frame.
【0048】扛重装置Aと扛重装置Dを同調させて扛上
することにより、夫々の扛重装置が分担する扛重荷重が
軽減され、扛重装置の小型化が図れるとともに、扛重装
置Dが盛り替え工法可能であることから、扛重装置Dの
高さを建築される1階層分より背低に構成できる。By lifting the lifting device A and the lifting device D in synchronization with each other, the lifting load shared by each lifting device can be reduced, and the lifting device can be downsized. Since D can be refilled, the height of the lifting device D can be configured to be lower than one level of the building.
【図1】 扛重装置Dによる本発明工法を示す流れ図で
ある。FIG. 1 is a flowchart showing a construction method of the present invention using a lifting device D.
【図2】扛重装置A、Dの配置と主柱、梁の取合関係を
示す平面図である。FIG. 2 is a plan view showing the arrangement of the lifting devices A and D and the connection relationship between the main columns and beams.
【図3】 扛重装置Dの平面図である。FIG. 3 is a plan view of the lifting device D.
【図4】 図1の一部切欠正面図である。FIG. 4 is a partially cutaway front view of FIG. 1;
【図5】 図1の正面図である。FIG. 5 is a front view of FIG. 1;
【図6】 図1の側面図である。FIG. 6 is a side view of FIG. 1;
【図7】 昇降ビームの別形態を示す扛重装置Dの平面
図である。FIG. 7 is a plan view of a lifting device D showing another form of the lifting beam.
【図8】 梁受け台の別形態を示す要部の正面図であ
る。FIG. 8 is a front view of a main part showing another form of the beam support.
【図9】 梁受け台の更に別形態を示す要部の側面図で
ある。FIG. 9 is a side view of a main part showing still another form of the beam support.
【図10】 扛重装置Aによる建物躯体の構築状態を示
す建物構造体の斜視図である。FIG. 10 is a perspective view of a building structure showing a building state of the building frame by the lifting device A.
【図11】 扛重装置Aと主柱、梁の取合関係を示す斜
視図である。FIG. 11 is a perspective view showing an assembling relationship between the lifting device A, the main pillar, and the beam.
【図12】 扛重装置Aの斜視図である。FIG. 12 is a perspective view of a lifting device A.
【図13】 扛重装置Aの内部構造を示す斜視図であ
る。FIG. 13 is a perspective view showing the internal structure of the lifting device A.
【図14】 扛重装置Aによる建築工法を示す流れ図で
ある。FIG. 14 is a flowchart showing a construction method using the lifting device A.
A 扛重装置 D 扛重装置 31 基礎 31a 架台構成体 31c 案内凹溝 32 中間主柱 32a 梁仕口 32b 仮受け柱 33 地中中間主柱 33b ライナー 34 継ぎ部材 35 スプロケット 36 回転伝達体 37 スクリュー軸 38 駆動モータ 39 スプロケット 40 チェン 41 昇降ブロック 41a 案内凸部 42 ナット部材 43 摺動部材 44 昇降ビーム 44a 孔 44b 孔 45 ノックピン 46 カラー 47 梁受け台 48 係合ロック凹部 49 係合ロック凸部 50 梁受け台 51 梁受け台 52 埋め殺し柱 53 柱間梁 Reference Signs List A A lifting device D A lifting device 31 Foundation 31a Frame structure 31c Guide groove 32 Intermediate main column 32a Beam connection 32b Temporary receiving column 33 Underground intermediate main column 33b Liner 34 Splicing member 35 Sprocket 36 Rotating transmission body 37 Screw shaft 38 Drive motor 39 Sprocket 40 Chain 41 Elevating block 41a Guide convex part 42 Nut member 43 Sliding member 44 Elevating beam 44a Hole 44b hole 45 Knock pin 46 Collar 47 Beam receiving base 48 Engagement lock concave part 49 Engagement lock convex part 50 Beam receiver Stand 51 Beam support 52 Buried pillar 53 Beam between pillars
フロントページの続き (72)発明者 石田 公成 東京都江東区南砂二丁目6番5号 川崎 重工業株式会社 東京事務所内 (72)発明者 高橋 敬 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (72)発明者 水谷 亮 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (72)発明者 喜井 昭捷 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (56)参考文献 特開 平9−88185(JP,A) 特開 平7−4060(JP,A) 特開 平6−212806(JP,A) 特開 平3−107038(JP,A) 特開 昭50−79918(JP,A) 特開 平7−324491(JP,A) (58)調査した分野(Int.Cl.7,DB名) E04B 1/35 E04G 21/14 - 21/22 Continued on the front page (72) Inventor Kosei Ishida 2-6-5 Minamisuna, Koto-ku, Tokyo Kawasaki Heavy Industries, Ltd. Tokyo Office (72) Inventor Takashi Takahashi 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Ryo Mizutani Kashima 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Inventor Akitoshi Kii 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima (56) References JP-A-9-88185 (JP, A) JP-A-7-4060 (JP, A) JP-A-6-212806 (JP, A) JP-A-3-107038 (JP) , A) JP-A-50-79918 (JP, A) JP-A-7-3244491 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) E04B 1/35 E04G 21/14- 21/22
Claims (9)
上階及び最上階を組立てたのち、建物構造体を構成する
外周主柱近傍の両側梁下面を扛重手段の(A)の閂にて
支持して扛上し、この扛上により生ずる作業空間部に下
層階を順次組み立てて構築するようにした建物構造体の
建築工法において、 建築構造体を構成する中間主柱を建柱する基礎杭または
地層階主柱上に、建柱される中間主柱を乗載結合する施
工ブロック(埋め殺し柱)を挟むように、基礎又は地中
梁上に配置される2個一組の架台間に、中間主柱の両側
に設けた梁仕口の下面に接し、中間主柱を扛上する水平
姿勢の昇降ビーム(閂)を夫々設け、昇降ビーム(閂)
の一端が、架台に正、逆回動可能に立設したスクリュー
軸に螺合せるナットをもち、かつ、架台に回り止めとし
た昇降ブロックに対して旋回可能に軸支するとともに、
他端を架台に正、逆回動可能に立設したスクリュー軸に
螺合せるナットをもち、架台に回り止めとした昇降ブロ
ックに対して着脱可能に連結した扛重手段(D)を配設
せしめ、一方、1層階分高さの外周主柱の搬入組立てと
前後して施工ブロック上に上記外周主柱と略同高の中間
主柱を搬入乗載し、この中間主柱および外周主柱相互間
の梁の組立て、天井部材、小梁などを取付て建物構造体
の屋上階及び最上階を組立てるとともに、この組立て作
業と前後して中間主柱の両側梁下面に、扛重手段(D)
の昇降ビーム(閂)を配設する第1工程、 扛重手段(A)と同調して、扛重手段(D)により最上
階層を1層階分高さに満たない高さ分だけ扛上したの
ち、施工ブロック(埋め殺し柱)上に短尺の仮受け柱を
乗載するとともに、最上階層を若干降下させ、全荷重を
仮受け柱に預け、昇降ビーム(閂)をフリーにする第2
工程、 フリーとなった扛重手段(D)の昇降ビーム(閂)と扛
重手段(A)の閂をさらに降下させ、扛重手段(D)の
昇降ビームと梁下面との間に梁受け台を介装する第3工
程、 扛重装置(A)、(D)により建築構造体を扛上し、フリ
ーとなった仮受け柱を退避させるとともに、建築構造体
を第1工程時点より1層階分より若干高く扛上したの
ち、1層階分の高さをもつ次層階の外周主柱を扛重手段
(A)における施工ブロック上に、また、次層階の中間
主柱を施工ブロック(埋め殺し柱)上に搬入設置し、扛
重手段(A)の閂、及び扛重手段(D)の昇降ビーム
(閂)を若干降下して全荷重を各施工ブロックに預け、
前後して次層階の梁を各主柱間に組立てる第4工程、 フリーとなった扛重手段(A)の閂を新たに設置された
次階層の梁と干渉しないように引き込み、及び扛重装置
(D)の昇降ビーム(閂)を外方向に約90度旋回移動
して新たに設置された次層階の梁との干渉を避けながら
最下位まで降下させたのち、昇降ビーム(閂)を原位置
に復帰させ、次いで若干量上昇させて各主柱両側の梁下
面部に臨ませる第5工程、 前記第2〜5工程を繰り返し行い、所要階層の建築構造
体を構築し2階以上の扛上ののちに、1,2階間の高さ
に調整した所定長さの外周主柱および中間主柱を施工ブ
ロック上に組立て、各主柱の上部を2階の各主柱の下端
と結合し、中間主柱の下端を施工ブロックと結合する第
6工程、 そののち扛重手段(D)における施工ブロック(埋殺し柱)
を恒久部材として残し扛重手段(A)および扛重手段
(D)を解体撤去し、前後して1階層の建築作業を完了
させることを特徴とする建物構造体の建築工法。1. After assembling the top floor and the top floor of a middle- and high-rise building structure on a foundation, the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure are fixed by a bar of lifting means (A). In the construction method of a building structure, which is constructed by assembling and constructing lower floors sequentially in a work space generated by the lifting by supporting and lifting, a foundation pile for constructing an intermediate main pillar constituting the building structure. Or on the stratum main pillar , the foundation or underground so as to sandwich the construction block (buried pillar) that mounts and connects the intermediate main pillar to be built
Between the pair of pedestals placed on the beam, on both sides of the intermediate main pillar
Horizontal contact with the lower surface of the beam connection provided at
Elevating beam (bar) is provided for each posture,
One end of the screw is mounted on the base so that it can rotate forward and backward.
It has a nut to be screwed to the shaft, and it is used as a detent on the base
While pivotably supporting the raised lifting block,
The other end is mounted on a stand with a screw shaft that can be rotated forward and backward.
Elevating block with nuts to be screwed and non-rotating on the base
A lifting means (D) detachably connected to the rack is provided, and on the other hand, before and after the loading and assembling of the outer pillar of the height equivalent to one floor, the outer pillar is substantially similar to the outer pillar. The intermediate main pillars at the same height are loaded and mounted, the beams between the intermediate main pillars and the outer main pillars are assembled, ceiling members, small beams, etc. are attached, and the roof floor and the top floor of the building structure are assembled. Before and after the assembling work, lifting means (D)
The first step of arranging the lifting beam (bar) of the first floor, in synchronization with the lifting means (A), the lifting means (D) lift the uppermost level by a height less than the height of one floor. After that, a short temporary support pillar is mounted on the construction block (buried pillar), the uppermost story is lowered slightly, all loads are deposited on the temporary support pillar, and the lifting beam (bar) is freed.
Step: The lifting beam (bar) of the lifting means (D) and the bar of the lifting means (A) are further lowered, and the beam receiver is placed between the lifting beam and the lower surface of the lifting means (D). In the third step of interposing a platform, the building structure is lifted by the lifting devices (A) and (D), the free temporary receiving pillars are evacuated, and the building structure is removed from the point of the first step by 1 hour. After lifting a little higher than the floor, the outer main pillar of the next floor having the height of one floor is placed on the construction block in the lifting means (A), and the middle main pillar of the next floor is lifted. After loading and installing on the construction block (buried pillar), the bar of the lifting means (A) and the lifting beam (bar) of the lifting means (D) are slightly lowered and all the load is deposited in each construction block.
The fourth step of assembling the beam of the next floor between the main columns before and after, and pulling in the bar of the free lifting means (A) so as not to interfere with the newly installed beam of the next floor, and lifting. The lifting beam (bar) of the heavy equipment (D) is turned about 90 degrees outward and lowered to the lowest position while avoiding interference with the newly installed beam on the next floor. ) Is returned to the original position, and then slightly raised to face the lower surface of the beam on both sides of each main pillar. The second to fifth steps are repeated to construct a building structure of a required level and the second floor. After the above lifting, assemble the outer pillars and the intermediate pillars of the specified length adjusted to the height between the first and second floors on the construction block, and connect the upper part of each pillar to each pillar on the second floor. The sixth step in which the lower end of the intermediate main pillar is connected to the construction block by combining with the lower end, and then the construction block in the lifting means (D) Click (horse killing column)
The lifting means (A) and the lifting means (D) are dismantled and removed, leaving one as a permanent member, and completing one-story building work before and after.
上階及び最上階を組立てたのち、建物構造体を構成する
外周主柱近傍の両側梁下面を扛重手段の(A)の閂にて
支持して扛上し、この扛上により生ずる作業空間部に下
層階を順次組み立てて構築するようにした建物構造体の
建築工法において、 建築構造体を構成する中間主柱を建柱する基礎杭または
地層階主柱上に、建柱される中間主柱を乗載結合する施
工ブロック(埋め殺し柱)を挟むように、基礎又は地中
梁上に配置される2個一組の架台間に、中間主柱の両側
に設けた梁仕口の下面に接し、中間主柱を扛上する水平
姿勢の昇降ビーム(閂)を夫々設け、昇降ビーム(閂)
の一端が、架台に正、逆回動可能に立設したスクリュー
軸に螺合せるナットをもち、かつ、架台に回り止めとし
た昇降ブロックに対して旋回可能に軸支するとともに、
他端を架台に正、逆回動可能に立設したスクリュー軸に
螺 合せるナットをもち、架台に回り止めとした昇降ブロ
ックに対して着脱可能に連結した扛重手段(D)を配設
せしめ、一方、1層階分高さの外周主柱の搬入組立てと
前後して施工ブロック上に、上記外周主柱と略同高の中
間主柱を搬入乗載し、この中間主柱および外周主柱相互
間の梁の組立て、天井部材、小梁などを取付て建物構造
体の屋上階及び最上階を組立てるとともに、この組立て
作業と前後して中間主柱の両側梁下面に、扛重手段
(D)の昇降ビーム(閂)を配設する第1工程、 扛重手段(A)と同調して、扛重手段(D)により最上
階層を一層階分高さを越す高さだけ扛上したのち、扛上
手段(A)の施工ブロックおよび扛重手段(D)の施工
ブロック(埋め殺し柱)上に一層階分の高さをもつ次層
階の外周主柱と中間主柱を搬入設置し、扛重手段(A)
の閂を新たに設置された次階層の梁と干渉しないように
引き込み、及び扛重装置(D)の昇降ビーム(閂)を若
干降下して全荷重を施工ブロック(埋め殺し柱)に預
け、前後して次層階の梁を各主柱間に組立てる第2工
程、 フリーとなった昇降ビーム(閂)を外方向に90度旋回
移動して新たに設置された次層階の梁との干渉を避けな
がら最下位まで降下させたのち、昇降ビーム(閂)を原位
置に復帰させ、次いで昇降ビームを若干量上昇させて各
主柱両側の梁下面に臨ませる第3工程、 前記2、3工程を繰り返し行い、所要階層の建築構造体
を構築して2階以上の扛上ののちに、1,2階間の高さ
に調整した所定長さの外周主柱および中間主柱を各施工
ブロック上に組立て、各主柱の上部を2階の各主柱の下
端と結合し、中間主柱の下端を施工ブロック(埋め殺し
柱)と結合する第4工程、 そののち扛重手段(D)における施工ブロック(埋殺し
柱)を恒久部材として残し、扛重手段(A),(D)を
解体撤去し、前後して1階層の建築作業を完了させるこ
とを特徴とする建物構造体の建築工法。2. After assembling the rooftop floor and the top floor of a middle- and high-rise building structure on a foundation, the lower surfaces of both side beams near the outer peripheral main pillars constituting the building structure are fixed with a bar of lifting means (A). In the construction method of a building structure, which is constructed by assembling and constructing lower floors sequentially in a work space generated by the lifting by supporting and lifting, a foundation pile for constructing an intermediate main pillar constituting the building structure. Or on the stratum main pillar , the foundation or underground so as to sandwich the construction block (buried pillar) that mounts and connects the intermediate main pillar to be built
Between the pair of pedestals placed on the beam, on both sides of the intermediate main pillar
Horizontal contact with the lower surface of the beam connection provided at
Elevating beam (bar) is provided for each posture,
One end of the screw is mounted on the base so that it can rotate forward and backward.
It has a nut to be screwed to the shaft, and it is used as a detent on the base
While pivotably supporting the raised lifting block,
The other end is mounted on a stand with a screw shaft that can be rotated forward and backward.
Elevating block with nuts to be screwed and non- rotating on the base
A lifting means (D) detachably connected to the rack is provided, and on the other hand, before and after the loading and assembling of the outer main pillar having a height of one floor, the outer main pillar is mounted on the construction block. Loading and loading the intermediate main pillars of approximately the same height, assembling beams between the intermediate main pillars and the outer peripheral main pillars, attaching ceiling members, small beams, etc., assembling the rooftop floor and the top floor of the building structure, Before and after this assembling work, the first step in which lifting beams (bars) of lifting means (D) are arranged on the lower surfaces of the beams on both sides of the intermediate main pillar, in synchronization with the lifting means (A), the lifting means (D) After the uppermost floor is lifted by a height that exceeds the floor height by one floor, the floor is further raised on the construction block of the lifting means (A) and the construction block (buried pillar) of the lifting means (D). The outer main pillar and intermediate main pillar of the next floor with a height of one minute are loaded and installed, and lifting means (A)
The bar is pulled in so that it does not interfere with the newly installed beam on the next level, and the lifting beam (bar) of the lifting device (D) is slightly lowered to deposit the entire load on the construction block (built-in pillar). The second step of assembling the beam on the next floor before and after between the main pillars, and turning the free lifting beam (bar) outward by 90 degrees to the beam on the newly installed next floor. After descending to the lowest position while avoiding interference, return the elevating beam (bar) to the original position, and then raise the elevating beam by a small amount to face the beam lower surface on both sides of each main column. After repeating the three steps, constructing the building structure of the required level and lifting the second floor or more, the outer main pillar and the middle main pillar of a predetermined length adjusted to the height between the first and second floors are each Assemble on the construction block, connect the upper part of each main column with the lower end of each main column on the second floor, and attach the lower end of the intermediate main column. 4th process to connect with the work block (buried pillar), after which the construction block (buried pillar) in the lifting means (D) is left as a permanent member, and the lifting means (A) and (D) are dismantled and removed. A building construction method for a building structure, wherein one-story building work is completed before and after.
ある中間主柱の両側に近接し、かつ、基礎又は地中梁上
に配置される2個一組の架台間に、中間主柱の両側に設
けた梁仕口の下面に接し、中間主柱を扛上する水平姿勢
の昇降ビーム(閂)を夫々設け、昇降ビーム(閂)の一
端が、架台に正、逆回動可能に立設したスクリュー軸に
螺合せるナットをもち、かつ、架台に回り止めとした昇
降ブロックに対して旋回可能に軸支するとともに、他端
を架台に正、逆回動可能に立設したスクリュー軸に螺合
せるナットをもち、架台に回り止めとした昇降ブロック
に対して着脱可能に連結したことを特徴とする建物構造
体の扛重装置。3. A main pillar inside a building for building a building structure.
Between two pairs of pedestals that are located on both sides of an intermediate main pillar and located on a foundation or underground beam, contact the lower surface of the beam connection provided on both sides of the intermediate main pillar, The lifting beam (bar) is provided in a horizontal position to lift the bar, and one end of the lifting beam (bar) has a nut that is screwed to a screw shaft that is installed on the gantry so that it can rotate forward and backward. The lifting block, which pivotally supports the lifting block as a non-rotating shaft and has a nut screwed to the screw shaft with the other end mounted on the base so that it can rotate forward and backward, and has a rotation stop on the mounting base. A lifting device for building structures, which is detachably connected to the building.
架台と機構系より成り、機構系は少なくとも2個の昇降
ビーム(閂)がそれぞれ2個のナットを有し、各ナット
は鉛直に配したスクリュー軸と螺合し、スクリュー軸は
正回転、逆回転可能であるように構成されていることを
特徴とする建物構造体の扛重装置。4. The lifting device (D) according to claim 3, wherein
It consists of a gantry and a mechanical system. The mechanical system has at least two lifting beams (bars) each with two nuts. Each nut is screwed with a vertically arranged screw shaft, and the screw shaft rotates forward and reverse. A lifting device for a building structure, wherein the lifting device is configured to be rotatable.
に固定し、回転不可とし、ナットが正回転、逆回転する
ことにより昇降ビームの昇降を行うようにしたことを特
徴とする建物構造体の扛重装置。5. The building structure according to claim 4, wherein the screw shaft is fixed to the gantry so as not to rotate, and the lifting beam is raised and lowered by forward and reverse rotation of the nut. Lifting equipment.
ビーム(閂)に中間主柱盛り替え用の梁受け台をスライ
ド可能に設けたことを特徴とする建物構造体の扛重装
置。6. A lifting device for a building structure according to claim 3, wherein a beam receiving base for changing the intermediate main pillar is slidably provided on both lifting beams (bars). .
可能に設けたことを特徴とする建物構造体の扛重装置。7. The lifting device for a building structure according to claim 6, wherein the beam receiving base is provided to be swingable.
ーム(閂)の降下時に梁との干渉を避けるに際して、昇
降ビームを外方向に約90度旋回可能にしたことを特徴
とする建物構造体の扛重装置。8. A building according to any one of claims 3 to 7, wherein the elevating beam can be turned about 90 degrees outward in order to avoid interference with the beam when the elevating beam (bar) descends. Structure lifting equipment.
輸送時の便宜、解体搬出時の便宜および、重量、寸法を
建築設計上の許容値を考慮してブロックに分割しておく
ことを特徴とする建物構造体の扛重装置。9. The pedestal according to claim 3, wherein the pedestal is divided into blocks in consideration of convenience in transportation, convenience in dismantling and carrying out, and weight and dimensions in consideration of allowable values in architectural design. A lifting device for a building structure characterized by the following.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP00032799A JP3263782B2 (en) | 1999-01-05 | 1999-01-05 | Construction method of building structure and lifting device of building structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP00032799A JP3263782B2 (en) | 1999-01-05 | 1999-01-05 | Construction method of building structure and lifting device of building structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2000199277A JP2000199277A (en) | 2000-07-18 |
| JP3263782B2 true JP3263782B2 (en) | 2002-03-11 |
Family
ID=11470822
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP00032799A Expired - Fee Related JP3263782B2 (en) | 1999-01-05 | 1999-01-05 | Construction method of building structure and lifting device of building structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3263782B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113136805B (en) * | 2021-04-27 | 2022-09-13 | 福建省亿方建设工程有限公司 | Bracket-free construction method for bent cap |
| CN114737790B (en) * | 2022-05-07 | 2023-02-28 | 中国十九冶集团有限公司 | Reverse dismantling method for high-rise frame structure |
-
1999
- 1999-01-05 JP JP00032799A patent/JP3263782B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2000199277A (en) | 2000-07-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US10392818B2 (en) | Climbing formwork for erecting a concrete structure | |
| CA3132733A1 (en) | Vertical slip form construction system with multi-function platform, and method of constructing a building therewith | |
| CA2741750C (en) | Assembly system for modular building units | |
| JP2001010780A (en) | Climbing tower crane and its climbing method | |
| JP3398839B2 (en) | Building construction method | |
| JP3263782B2 (en) | Construction method of building structure and lifting device of building structure | |
| JP2884397B2 (en) | Construction method of building structure and lifting device of building structure | |
| JP2884396B2 (en) | Construction method of building structure and lifting device of building structure | |
| JP2990593B2 (en) | Demolition method and demolition equipment for building structures | |
| JP2754196B2 (en) | Lifting equipment for building structures | |
| JPH04161566A (en) | Constructing apparatus for large space building | |
| JP3780475B2 (en) | Construction method of super tall tower | |
| JP2884398B2 (en) | Construction method of building structure and lifting device of building structure | |
| JPH062434A (en) | How to build a steel frame roof | |
| JPH0733689B2 (en) | Push-up method and apparatus | |
| JPH0733688B2 (en) | Push-up method | |
| JPH03197734A (en) | Lift up method by replacement of scaffold body | |
| JPH0125858B2 (en) | ||
| JP2946372B2 (en) | Construction method of structure | |
| JPH04118438A (en) | Method and apparatus for construction of building | |
| JPH1162244A (en) | Frame for frame building and frame building method using the same | |
| JPH0237468B2 (en) | ||
| JPH07229206A (en) | Method of rebuilding building | |
| JPH05330792A (en) | Lift-up crane | |
| JPS5918836A (en) | Construction of prefabricated house |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |