How to install a huge tubular structure

Info

Publication number
JP3280228B2
JP3280228B2 JP10115196A JP10115196A JP3280228B2 JP 3280228 B2 JP3280228 B2 JP 3280228B2 JP 10115196 A JP10115196 A JP 10115196A JP 10115196 A JP10115196 A JP 10115196A JP 3280228 B2 JP3280228 B2 JP 3280228B2
Authority
JP
Japan
Prior art keywords
roof
tubular structure
huge
hanging
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP10115196A
Other languages
Japanese (ja)
Other versions
JPH09287314A (en
Inventor
正俊 吉崎
伸一 江幡
Original Assignee
日立プラント建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日立プラント建設株式会社 filed Critical 日立プラント建設株式会社
Priority to JP10115196A priority Critical patent/JP3280228B2/en
Publication of JPH09287314A publication Critical patent/JPH09287314A/en
Application granted granted Critical
Publication of JP3280228B2 publication Critical patent/JP3280228B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は筒状巨大構造物の据
付け方法に係り、特に、タンクや原子炉格納容器等の筒
状巨大構造物の据付け方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for installing a huge tubular structure, and more particularly, to a method for installing a huge tubular structure such as a tank or a containment vessel.

【0002】[0002]

【従来の技術】例えば、高さが50m、径が30m程度
の巨大な鋼製の筒状巨大構造物である。従来、このよう
な筒状巨大構造物の組立作業は、工場において、ある程
度の大きさまで製造した側壁板や屋根板を建設現場に搬
送する。そして、建設現場においてクレーン等を用いて
側壁板を吊り上げながら組立て溶接して所定高さの筒状
構造物を構築し、それを据付け位置に設置している。
2. Description of the Related Art For example, it is a huge steel tubular huge structure having a height of 50 m and a diameter of about 30 m. Conventionally, in assembling such a huge tubular structure, a side wall plate or a roof plate manufactured to a certain size is transported to a construction site in a factory. Then, at a construction site, a side wall plate is lifted up by using a crane or the like and assembled and welded to construct a tubular structure having a predetermined height, and the tubular structure is installed at an installation position.

【0003】[0003]

【発明が解決しようとする課題】したがって、現地には
専用の作業エリア(工事ヤード)を確保する必要がある
が、場所によってはこのような広い作業エリアを確保す
ることが難しい。また、作業エリアは屋外となるため、
組立作業を行う時は、風雨を防ぐ設備が必要となる。こ
れには、筒状巨大構造物の全体を覆うことのできるよう
な巨大テントを予め構築し、その中で組立工事を行うこ
とになるが、それには、高さが50m、径が30m程度
の筒状巨大構造物を覆うテントを構築する為の工期がか
かり、却って全体の工期が長くなる欠点があると共に、
巨大テント自体の費用がかかり設備のコストのアップに
なるという欠点がある。
Therefore, it is necessary to secure a dedicated work area (construction yard) on site, but it is difficult to secure such a wide work area depending on the location. Also, since the work area is outdoors,
When performing assembly work, equipment to prevent wind and rain is required. For this purpose, a huge tent capable of covering the entire cylindrical huge structure is constructed in advance, and assembling work is performed in the tent, which requires a height of about 50 m and a diameter of about 30 m. It takes construction time to build a tent that covers the huge tubular structure, and on the contrary there is a disadvantage that the overall construction time is longer,
There is a disadvantage that the cost of the huge tent itself is increased and the cost of the equipment is increased.

【0004】本発明はこのような事情に鑑みてなされた
もので、現地に専用の作業エリア(工事ヤード)を確保
する必要がなく、かつ風雨を防ぐための設備も必要とし
ない筒状巨大構造物の据付け方法を提供することを目的
とする。
The present invention has been made in view of such circumstances, and does not require a dedicated work area (construction yard) at the site and does not require facilities for preventing wind and rain. An object of the present invention is to provide an installation method of an object.

【0005】[0005]

【発明を解決するための手段】本発明は、前記目的を達
成するために、放射状に配設されて屋根骨格を形成する
と共に、吊り天秤機構の天秤棒となる複数の長尺部材、
及び前記屋根骨格を覆うシート部材からなる屋根体と、
前記複数の長尺部材の先端部近傍に設けられ、クレーン
にワイヤーを介して連結されるクレーン用吊り具とを備
えた吊り天秤機能付き屋根体を使用し、該吊り天秤機能
付き屋根体を、台車上で製作した筒状巨大構造物の上端
に設置し、前記吊り天秤機能付き屋根体が設置された筒
状巨大構造物を、台車上に設置した状態で据付け現場ま
で搬送し、該据付け現場において、クレーンによって前
記吊り天秤機能付き屋根体を介して前記筒状巨大構造物
を持ち上げて、前記筒状巨大構造物を据付け位置に据え
付けることを特徴とする。
In order to achieve the above object, the present invention provides a plurality of long members which are radially arranged to form a roof frame and serve as a balance rod of a hanging balance mechanism.
And a roof body made of a sheet member covering the roof frame,
Provided near the tip of the plurality of long members, using a roof with a hanging balance function provided with a crane hanging tool connected to the crane via a wire, the roof with a hanging balance function, A tube installed on the upper end of a huge tubular structure manufactured on a trolley and on which the roof with the hanging balance function is installed
When the huge structure is installed on the trolley,
And at the installation site, the crane lifts the huge tubular structure via the roof with the hanging balance function at the installation site, and installs the huge tubular structure at the installation position.

【0006】本発明によれば、吊り天秤機能付き屋根体
は、筒状巨大構造物を搬送する際に補強材および風雨を
防ぐ機能をもち、筒状巨大構造物を据付ける際には吊り
天秤としての機能をもつ。従って、筒状巨大構造物を工
場内で製作し、それを据付け現場まで搬送して据え付け
ても、筒状巨大構造物が搬送中に破損することがないの
で、工場製作から現地据え付けまでを一貫して行うこと
ができる。
According to the present invention, a roof with a hanging balance function has a reinforcing member and a function of preventing wind and rain when transporting a huge tubular structure, and a hanging balance when installing the huge tubular structure. Has the function as Therefore, even if a huge tubular structure is manufactured in a factory and transported to the installation site for installation, the huge tubular structure will not be damaged during transportation. You can do it.

【0007】[0007]

【発明の実施の形態】以下添付図面に従って本発明に係
る筒状巨大構造物の据付け方法の好ましい実施の形態に
ついて詳説する。本発明の筒状巨大構造物の据付け方法
で使用される吊り天秤機構付き屋根体10は、吊り天秤
機能と屋根機能との両方を兼ね備えるように構成された
ものであり、図1は切断側面図、図2は平面図である。
図1及び図2に示すように、吊り天秤機構付き屋根体1
0は、中央部のリングトラス12から多数の鉛直トラス
14、14…が対向して放射状に延設され、この鉛直ト
ラス14は円筒状の被吊り上げ物16を多点吊り(被吊
り上げ物16の上端周縁の複数箇所を吊る)する際の天
秤棒となる。また、鉛直トラス14同志は補助梁18を
介して接合されると共に、鉛直トラス14の先端部同志
は水平梁20を介して接合され、更に、リング形状をし
たリングトラス12の内側には十字状の十字梁22が設
けられる。これにより、天秤機能を有した強固な多角形
状の骨組が形成される。また、前記多数の鉛直トラス1
4の先端近傍には、鉛直トラス14の長手方向に沿って
所定距離だけ移動可能な吊りボルト24、24…が縦方
向に設けられる。そして、吊りボルト24の上端には吊
り上げ用シャックル24Aが取り付けられると共に、吊
りボルト24の下端には、ナット24Bが取り付けられ
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the method for installing a huge tubular structure according to the present invention will be described below in detail with reference to the accompanying drawings. The roof 10 with a hanging balance mechanism used in the method for installing a huge tubular structure according to the present invention is configured to have both the hanging balance function and the roof function, and FIG. FIG. 2 is a plan view.
As shown in FIGS. 1 and 2, a roof body 1 with a hanging balance mechanism
Numeral 0 indicates that a large number of vertical trusses 14, 14... Are radially extended from the ring truss 12 at the center, facing each other. It becomes a balance rod when hanging several places around the upper edge. Further, the vertical trusses 14 are joined via the auxiliary beams 18, and the distal end portions of the vertical trusses 14 are joined via the horizontal beams 20. Cross beam 22 is provided. Thereby, a strong polygonal skeleton having a balance function is formed. In addition, the plurality of vertical trusses 1
In the vicinity of the front end of the vertical truss 4, suspension bolts 24, 24. A lifting shackle 24A is attached to an upper end of the suspension bolt 24, and a nut 24B is attached to a lower end of the suspension bolt 24.

【0008】次に、吊り天秤機構付き屋根体10の屋根
機能としての構成を説明すると、前記リングトラス12
の内側には、中央雨養生屋根26が設けられると共に、
中央雨養生屋根26にはベンチレータ28が取り付けら
れる。また、多角形状に形成された骨組みには、採光を
考慮して透明シート30が被せられている。また、吊り
天秤機構付き屋根体10の中央雨養生屋根26の近傍に
は中央雨養生屋根26の外周に沿って融雪パイプ32が
配設されると共に、融雪パイプ32は図示しない給水管
に接続され、融雪パイプ32に形成された多数の孔から
融雪用の水が噴出される。また、図示しないが、吊り天
秤機構付き屋根体10には、照明設備が設けられる。ま
た、吊り天秤機構付き屋根体10の外周下側で前記吊り
ボルト24の配設位置より内側には、環状のレール34
が配設されると共に、そのレール34にはホイストクレ
ーン36が移動可能に吊設される。
Next, the structure of the roof body 10 with the hanging balance mechanism as a roof function will be described.
Inside, a central rain curing roof 26 is provided,
A ventilator 28 is attached to the central rain curing roof 26. Further, the transparent sheet 30 is covered on the framework formed in a polygonal shape in consideration of lighting. A snow-melting pipe 32 is provided along the outer periphery of the central rain-curing roof 26 near the central rain-curing roof 26 of the roof body 10 with a hanging balance mechanism, and the snow-melting pipe 32 is connected to a water supply pipe (not shown). Water for melting snow is blown out from a number of holes formed in the snow melting pipe 32. Although not shown, the roof 10 with the hanging balance mechanism is provided with lighting equipment. In addition, an annular rail 34 is provided on the lower side of the outer periphery of the roof body 10 with the hanging balance mechanism and inside the arrangement position of the hanging bolts 24.
And a hoist crane 36 is movably suspended from the rail 34.

【0009】次に、上記の如く構成された吊り天秤機構
付き屋根体10を用い、本発明の筒状巨大構造物の据付
け方法を、原子炉格納容器を例にとって説明する。図3
に示すように、工場40内で原子炉格納容器42がトレ
ーラ等の台車44上で輸送用架台46上に作製される。
そして、原子炉格納容器42の上端に天秤機構付き屋根
体10が吊りボルト24とナット24Bによって固定さ
れる。そして、原子炉格納容器42の周囲には、搬送,
吊り込み等のための補強材48が配設され、該補強材4
8に足場50,階段52等が設置される。また、ビニー
ルシートや鉄板等の防雨,防風,防雪,塩害防止のため
の養生材54が原子炉格納容器42を囲うようにして天
秤機構付き屋根体10に設置される。
Next, a method of installing a huge tubular structure according to the present invention using the roof 10 having the hanging balance mechanism configured as described above will be described with reference to a reactor containment vessel as an example. FIG.
As shown in (1), a reactor containment vessel 42 is manufactured on a transportation platform 46 on a truck 44 such as a trailer in a factory 40.
Then, the roof 10 with the balance mechanism is fixed to the upper end of the containment vessel 42 by the suspension bolts 24 and the nuts 24B. Then, around the reactor containment vessel 42,
A reinforcing member 48 for hanging or the like is provided.
The scaffold 50, the stairs 52, etc. are installed in 8. Further, a curing material 54 such as a vinyl sheet or an iron plate for rain protection, wind protection, snow protection, and salt damage prevention is installed on the roof body 10 with the balance mechanism so as to surround the reactor containment vessel 42.

【0010】このようにして、製作および梱包がなされ
た原子炉格納容器42は、台車44によって工場40か
ら搬出され(図4(a))、図4(b)に示すように、
港湾において台車44と共に筏(バージ)56に移載さ
れ、該筏56によって原子炉格納容器42の設置場所に
近い港湾まで海上輸送され(図4(c))、そこで台車
44と共に陸揚げされる(図3(d))。
[0010] The reactor containment vessel 42 thus manufactured and packed is carried out of the factory 40 by the cart 44 (FIG. 4A), and as shown in FIG.
At the harbor, it is transferred to a raft (barge) 56 together with the trolley 44, and is transported by the raft 56 to the port near the location where the reactor containment vessel 42 is installed (FIG. 4 (c)), where it is discharged with the trolley 44 (FIG. 4C). FIG. 3D).

【0011】陸揚げされた原子炉格納容器42は、台車
44によって原子炉格納容器42の設置場所まで搬送さ
れ、図5に示すように、設置場所で天秤機構付き屋根体
10にワイヤ58が掛けられ、該ワイヤ58にクレーン
60のフック62が係合されてクレーン60によって原
子炉建屋64の据付け位置66に設置される(図4
(e),(f))。そして、天秤機構付き屋根体10を
固定していた吊りボルト24とナット24Bによる固定
を外し、天秤機構付き屋根体10が原子炉格納容器42
から取り外され、補強材48,養生材54等も取り除か
れる。
The landed reactor containment vessel 42 is transported by the bogie 44 to the place where the reactor containment vessel 42 is installed, and as shown in FIG. 5, a wire 58 is hung on the roof 10 with the balance mechanism at the place of installation. The hook 58 of the crane 60 is engaged with the wire 58, and is installed at the installation position 66 of the reactor building 64 by the crane 60 (FIG. 4).
(E), (f)). Then, the fixing with the hanging bolts 24 and the nuts 24 </ b> B that fixed the roof body 10 with the balance mechanism is removed, and the roof body 10 with the balance mechanism is replaced with the reactor containment vessel 42.
, And the reinforcing material 48, the curing material 54, and the like are also removed.

【0012】本実施の形態では、輸送手段として筏(バ
ージ)56を使用することで説明したが、製作工場から
現地組立位置にいたる間の、工場積み出し設備、港湾設
備、道路状況によって選択することができる。また、船
輸送の場合には、特に塩害に注意する必要があり、筒状
巨大構造物全体を前述したように防水シートで覆う等の
海水がかからないような養生が必要である。
In this embodiment, the description has been made using the raft (barge) 56 as a transportation means. However, selection from a factory shipping facility, a harbor facility, and road conditions during a period from a manufacturing factory to a local assembling position is performed. Can be. In the case of ship transportation, it is particularly necessary to pay attention to salt damage, and it is necessary to cover the entire cylindrical large structure with a waterproof sheet, as described above, and to protect the large structure from seawater.

【0013】筒状巨大構造物のように重量の極めて重い
構造物を輸送する場合、筒状巨大構造物にかかる荷重割
増を考える必要がある。輸送条件にもよるが、一般的に
陸上輸送での荷重割増は自重の0.3倍程度であるが、
船輸送の場合は鉛直方向の荷重割増及び発生水平力とし
て自重の0.6倍程度を見込む必要があり、船輸送の方
が筒状巨大構造物が破損し易い。しかし、本発明で使用
した屋根体を、筒状巨大構造物に一体化して輸送すれ
ば、この荷重割増に対しても充分対応することができ
る。
When transporting an extremely heavy structure such as a huge tubular structure, it is necessary to consider an additional load applied to the huge huge structure. Although it depends on the transportation conditions, the load increase in land transportation is generally about 0.3 times its own weight,
In the case of ship transportation, it is necessary to expect about 0.6 times the own weight as the load increase in the vertical direction and the generated horizontal force, and the huge cylindrical structure is more likely to be damaged in ship transportation. However, if the roof used in the present invention is integrated with a huge tubular structure and transported, it is possible to sufficiently cope with this additional load.

【0014】また、上記実施の形態では、筏56を使用
して原子炉格納容器42を搬送しているが、トレーラー
等の台車44によって陸送するようにしてもよい。
In the above embodiment, the reactor containment vessel 42 is transported by using the raft 56, but it may be transported by land by a truck 44 such as a trailer.

【0015】上記実施の形態では、原子炉格納容器42
の据付け方法の例で説明したが、原子炉格納容器42に
限定されるものではなく、タンク等の筒上巨大構造物の
全てに適用することが出来る。
In the above embodiment, the reactor containment vessel 42
However, the present invention is not limited to the reactor containment vessel 42, and can be applied to all of the large on-cylinder structures such as tanks.

【0016】[0016]

【発明の効果】以上説明したように、本発明の筒状巨大
構造物の据付け方法によれば、屋根体が補強材及び吊り
天秤としての機能をもつので、台車上製作から現地据付
けまで一貫して行うことができ、現地据付け作業を大幅
に減らすことができ、現地据付け位置近傍に大規模な作
業エリアを確保する必要がなくなる。また、風雨を防ぐ
ための設備も特別に必要としない。
As described above, according to the method for installing a huge tubular structure according to the present invention, since the roof has functions as a reinforcing material and a suspension balance, it is consistent from the production on the trolley to the on- site installation. The installation work can be greatly reduced, and there is no need to secure a large-scale work area near the local installation position. Also, no special equipment is required to prevent wind and rain.

【0017】従って、据え付けに要するコストを大幅に
低減することができる。
Therefore, the cost required for installation can be greatly reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る筒状巨大構造物の据付け方法を実
施するための天秤機構付き屋根体の構造を説明する切断
断面図である。
FIG. 1 is a cross-sectional view illustrating the structure of a roof with a balance mechanism for implementing a method for installing a huge tubular structure according to the present invention.

【図2】図1の天秤機構付き屋根体の平面図である。FIG. 2 is a plan view of the roof with a balance mechanism of FIG. 1;

【図3】本発明に係る筒状巨大構造物を工場内で作製し
た状態を示す側面図である。
FIG. 3 is a side view showing a state in which the huge tubular structure according to the present invention is manufactured in a factory.

【図4】本発明に係る筒状巨大構造物の据付け方法の手
順を説明する概念図である。
FIG. 4 is a conceptual diagram illustrating a procedure of a method for installing a huge tubular structure according to the present invention.

【図5】本発明に係る筒状巨大構造物を据え付ける状態
を示す斜視図である。
FIG. 5 is a perspective view showing a state in which the huge tubular structure according to the present invention is installed.

【符号の説明】[Explanation of symbols]

10…天秤機構付き屋根体 40…工場 42…原子炉格納容器 44…台車 48…補強材 54…養生材 56…筏(バージ) 60…クレーン 66…据付け位置 DESCRIPTION OF SYMBOLS 10 ... Roof body with a balance mechanism 40 ... Factory 42 ... Reactor containment vessel 44 ... Dolly 48 ... Reinforcement material 54 ... Curing material 56 ... Raft (barge) 60 ... Crane 66 ... Installation position

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E04H 7/00 - 7/20 ──────────────────────────────────────────────────続 き Continued on front page (58) Field surveyed (Int.Cl. 7 , DB name) E04H 7/ 00-7/20

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 放射状に配設されて屋根骨格を形成する
と共に、吊り天秤機構の天秤棒となる複数の長尺部材、
及び前記屋根骨格を覆うシート部材からなる屋根体と、
前記複数の長尺部材の先端部近傍に設けられ、クレーン
にワイヤーを介して連結されるクレーン用吊り具とを備
えた吊り天秤機能付き屋根体を使用し、 該吊り天秤機能付き屋根体を、台車上で製作した筒状巨
大構造物の上端に設置し、前記吊り天秤機能付き屋根体が設置された筒状巨大構造
物を、台車上に設置した状態で据付け現場まで搬送し、 該据付け現場において、クレーンによって前記吊り天秤
機能付き屋根体を介して前記筒状巨大構造物を持ち上げ
て、 前記筒状巨大構造物を据付け位置に据え付けることを特
徴とする筒状巨大構造物の据付け方法。
1. A plurality of elongated members radially arranged to form a roof frame and serving as a balance rod of a hanging balance mechanism;
And a roof body made of a sheet member covering the roof frame,
A roof body with a hanging balance function, which is provided near the distal end portions of the plurality of long members and includes a crane hanging tool connected to the crane via a wire, using the roof body with a hanging balance function, A giant tubular structure installed on the top of a giant tubular structure manufactured on a trolley and on which the roof with the hanging balance function is installed
The object is transported to the installation site in a state where it is installed on a trolley, and at the installation site, the cylindrical huge structure is lifted by a crane through the roof with the hanging balance function, A method for installing a huge tubular structure, characterized by being installed at an installation position.
【請求項2】 搬送に際して前記筒状巨大構造物の周囲
に風雨等の防止のための養生材を配設することを特徴と
する請求項1に記載の筒状巨大構造物の据付け方法。
2. The method for mounting a huge tubular structure according to claim 1, wherein a curing material for preventing wind and rain is provided around the huge tubular structure during transportation.
JP10115196A 1996-04-23 1996-04-23 How to install a huge tubular structure Expired - Fee Related JP3280228B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10115196A JP3280228B2 (en) 1996-04-23 1996-04-23 How to install a huge tubular structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10115196A JP3280228B2 (en) 1996-04-23 1996-04-23 How to install a huge tubular structure

Publications (2)

Publication Number Publication Date
JPH09287314A JPH09287314A (en) 1997-11-04
JP3280228B2 true JP3280228B2 (en) 2002-04-30

Family

ID=14293064

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10115196A Expired - Fee Related JP3280228B2 (en) 1996-04-23 1996-04-23 How to install a huge tubular structure

Country Status (1)

Country Link
JP (1) JP3280228B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011083771A1 (en) * 2010-01-08 2011-07-14 日本通運株式会社 Marine transportation method using barge, and marine transportation barge

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5642639B2 (en) * 2011-09-12 2014-12-17 日立Geニュークリア・エナジー株式会社 RCCV liner construction method using RCCV all-weather shield
CN103498586B (en) * 2013-09-27 2015-12-23 天津二十冶建设有限公司 Winding-up tank upside-down method of hull-section construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011083771A1 (en) * 2010-01-08 2011-07-14 日本通運株式会社 Marine transportation method using barge, and marine transportation barge
JP2011140280A (en) * 2010-01-08 2011-07-21 Nippon Express Co Ltd Marine transportation method by barge and the barge for marine transportation

Also Published As

Publication number Publication date
JPH09287314A (en) 1997-11-04

Similar Documents

Publication Publication Date Title
CN113136853B (en) A prefabricated drilling platform and process for bare rock pile foundation in reservoir area
WO2005031159A1 (en) Method of conducting service on a wind turbine using equipment mounted on the hub
US4615154A (en) Utility line transmission tower apparatus
CN113137052A (en) Self-climbing safety hard protection and curtain wall circular rail hoisting integrated platform
JP3280228B2 (en) How to install a huge tubular structure
CN117403897A (en) Disassembly method of large diameter silo roof support system
CN216475153U (en) Construction template system of offshore wind power high-rise pile cap
JPH07310460A (en) Lighthouse
EP4317045B1 (en) Crane for confined spaces and base for installing such crane on corresponding target surfaces of building structures or similar supporting structures
JP2579715B2 (en) External tower crane
JP3242775B2 (en) Installation method of vertical container
JP2907264B2 (en) Method of assembling cylindrical huge structure and roof with hanging balance mechanism
CN117536335A (en) BIM-based starry sky garden steel structure hinge installation method
JP6534938B2 (en) Lining plate installation and rain curing jig and lining plate installation method using the jig
JP7264721B2 (en) Waterproof roof structure and its waterproof construction method
CN214462401U (en) Double-layer protection frame with novel structure
JP2965982B1 (en) Reinforcement method for countermeasures against strong wind in cylindrical tank during construction
CN209924407U (en) Combined working platform for steel structure high-altitude installation
CN213171372U (en) Light-duty assembled vertical transportation device
CN223048416U (en) Rotatable hanging basket structure
JP3671242B2 (en) How to install the equipment
JPH10237886A (en) Method for constructing underground tank
CN109944428A (en) Combined working platform for high-altitude installation of steel structure and its installation method
US3805369A (en) Method of making storage tank for liquids comprised of prefabricated and prepainted components
CN114809571A (en) Method for lifting high-altitude operation platform by adopting carrying pole beam

Legal Events

Date Code Title Description
S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080222

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090222

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090222

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100222

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110222

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110222

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120222

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130222

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140222

Year of fee payment: 12

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees