JP3579704B2 - Underwater shield method and shield machine - Google Patents
Underwater shield method and shield machine Download PDFInfo
- Publication number
- JP3579704B2 JP3579704B2 JP31843399A JP31843399A JP3579704B2 JP 3579704 B2 JP3579704 B2 JP 3579704B2 JP 31843399 A JP31843399 A JP 31843399A JP 31843399 A JP31843399 A JP 31843399A JP 3579704 B2 JP3579704 B2 JP 3579704B2
- Authority
- JP
- Japan
- Prior art keywords
- shield machine
- shield
- earth
- sand
- underwater
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、水中シールド工法およびシールドマシンに関するものである。
【0002】
【発明が解決しようとする課題】
従来、水底トンネルの施工においては、沈埋工法、シールド工法などが用いられている。シールド工法による水底トンネルは、掘削土量が少なく、大規模な躯体製作ヤードを必要としない等の利点があるが、土被りが大きく、トンネルの計画高が深くなるという短所がある。そこで本発明は、水中シールド工法において土被りを減らし、かつシールドマシンの後方に構築したセグメントトンネルを効率良く埋め戻すことを課題とする。
【0003】
【課題を解決するための手段】
【0006】
上記課題を解決するための手段として本発明の手段として本発明は、後方にセグメントを組み立てながらシールドマシンを水中において推進させ、推進に際して取り除いたシールドマシンの切羽側の土砂をシールドマシン内に流入させ、シールドマシンのスキンプレートを貫通して内外に連通し、後方の既設セグメントまで到達する埋戻し管を介して後方の既設セグメントを埋め戻すことを特徴とした、水中シールド工法を提供する。
【0007】
また、上記に記載の水中シールド工法において、シールドマシン内に流入させた土砂の一部は後方既設セグメントの埋戻しに使用し、他の部分はシールドマシン内の排泥設備を介してトンネル後方より搬出することを特徴とした、水中シールド工法を提供する。
【0008】
そして、シールドマシンの切羽側の土砂の一部を水上からの掘削手段で取り除き、後方にセグメントを組み立てながらシールドマシンを水中において推進させ、推進に際して取り除いたシールドマシンの切羽側の土砂の他の部分をシールドマシン内に流入させ、シールドマシンのスキンプレートを貫通して内外に連通し、後方の既設セグメントまで到達する埋戻し管を介して後方の既設セグメントを埋め戻すことを特徴とした、水中シールド工法を提供する。
【0009】
さらに、上記に記載の水中シールド工法に用いるシールドマシンにおいて、シールドマシンの切羽側の土砂をシールドマシン内に取り込む手段と、シールドマシンのスキンプレートを貫通して内外に連通し、後方の既設セグメントまで到達してシールドマシン内に取り込んだ土砂を後方の既設セグメントの周囲まで搬送する埋戻し管と、を有することを特徴とした、シールドマシンを提供する。
【0010】
また、上記に記載の水中シールド工法に用いるシールドマシンにおいて、シールドマシンの切羽側の土砂をシールドマシン内に取り込む手段と、シールドマシンのスキンプレートを貫通して内外に連通し、後方の既設セグメントまで到達してシールドマシン内に取り込んだ土砂の一部を後方の既設セグメントの周囲まで搬送する埋戻し管と、取り込んだ土砂の他の部分をトンネル後方より搬出する排泥設備と、を有することを特徴とした、シールドマシンを提供する。以下、図面を参照しながら、本発明の実施の形態について説明する。
【0011】
【発明の実施の形態1】
<イ>シールドマシンの構造
図1に示すように、本実施の形態1のシールドマシン100は、前面にカッタ装置を設けない構造である。円筒形や矩形のスキンプレートの前面に隔壁110を有し、その底部側に土砂取込口111が開設されている。また、必要に応じて土砂取込口111を受けるように外側に刃口112を突設する。なお、土砂の取り込みを容易にするためには、カッタ装置や攪拌装置を設ける場合もある。
【0012】
土砂取込口111の内部には、土砂取込装置120が装備され、トンネル後方の所定の排土場所まで到達する排泥管121の一端が連通している。なお、シールドマシン100内には、シールドジャッキ130やセグメント自動組立装置131のほか、排泥設備などのシールドトンネルの施工に必要な設備を配備している。
【0013】
<ロ>シールドマシンの推進
シールドマシン100の後方にセグメント200を組立ながら、シールドジャッキ130によりシールドマシン100を推進させる。このとき、土被りはゼロか非常に小さい状態で推進させる。シールドマシン100の切羽側の土砂は、水上の浚渫船300などの掘削手段によって掘削する。これによって、シールドマシン100の推進力を軽減させることができる。
【0014】
切羽側の土砂のうちシールドマシン100の底部付近の掘り残した土砂は、土砂取込口111から土砂取込装置120内に流入させ、排泥管121を介してトンネル後方より排出する。このように、浚渫船300による掘削と、シールドマシン100の推進力による土砂の取込によって、切羽側の土砂を取り除くことができるため、シールドマシン100の前面にカッタ装置を設ける必要が無い。なお、図示しないが、土砂取込口111の付近に、外側に向けてジェット式や機械式の土砂攪拌装置を設けておき、土砂の取込を容易にすることも考えられる。
【0015】
構築完了したトンネルの底部には、移動可能な作業台210を連続的に設置し、排泥管121等をその上に搭載することによってシールドマシン100の推進に追従できるようにする。また、埋戻し前のトンネルの浮上を防止するため、シールドマシン100の推進に追従して前進するウェイト台車220を設置する。
【0016】
<ハ>後方既設セグメントの埋戻し
浚渫船300により掘削した土砂は、水上の搬送手段を介して後方の既設セグメント200の周囲まで逐次搬送して、埋戻し土砂400とする。従って、シールドマシン100の推進に追従して、効率的に既設セグメント200の埋め戻しが可能となる。
【0017】
搬送手段の具体例としては、浚渫船300の後方にベルトコンベア台船310を連結し、これらの船上に、土砂を投入するホッパ320と、搬送するべルトコンベア330と、後方の既設セグメント200の周囲に土砂を投入する複数のトレミー管340とより構成したもの等が考えられる。なお、搬送手段の途上において、掘削土砂の流動化又は固化材の混合による土質の改良等を行うと良い。
【0018】
【発明の実施の形態2】
<イ>シールドマシンの構造
図2、3に示すように、本実施の形態2のシールドマシン500は、前面にカッタ装置を設けない構造である。スキンプレートの前面に隔壁510を有し、その底部側に土砂取込口511が開設されている。また、隔壁510の前方には、土砂取込口511を受けるように外側に刃口512を突設する。なお、土砂の取り込みを容易にするためには、カッタ装置や攪拌装置を設ける場合もある。
【0019】
土砂取込口511の内部には、土砂取込装置520が装備され、トンネル内に設置した土砂選別プラント530との間を土砂取込管521により連通されている。土砂選別プラント530は、取込んだ土砂のうち埋戻しに必要分を選別する機能を有し、不要分は排泥管531等の排泥設備を介して、トンネル後方の所定の排土場所に搬出される。
【0020】
必要分の土砂は、土砂改良プラント540等に送られ、そこで、流動化又は固化材の混合による土質の改良が行なわれる。また、土砂改良プラント540には埋戻し管550の一端が連通している。この埋戻し管550は、シールドマシン500のスキンプレートの例えば上面を貫通して、後方の既設セグメント600まで到達している。
【0021】
また、埋戻し管550は、埋戻しを均等に効率良く行えるように、セグメント600上で枝分かれしてかつ下方に伸びた複数の分岐管551を有している。このとき、埋戻し管を複数の独立した配管で構成する場合もある。さらに、シールドマシン500の推進に追従できるように、セグメント600上の埋戻し管550には、ローラーなどの移動装置552を設けておく。
【0022】
なお、シールドマシン500内には、シールドジャッキ560やセグメント自動組立装置561等のほか、シールドトンネルの施工に必要な設備を配備している。
【0023】
<ロ>シールドマシンの推進
シールドマシン500の後方にセグメント600を組立ながら、シールドジャッキ560によりシールドマシン500を推進させる。このとき、シールドマシン500の切羽側の土砂は、推進力によって土砂取込口511から土砂取込装置520内に取り込む。
【0024】
このように、シールドマシン500の推進力による土砂の取り込みによって、切羽側の土砂を取り除くことができるため、シールドマシン500の前面にカッタ装置を設ける必要が無い。なお、図示しないが、土砂取込口511の付近に、外側に向けてジェット式や機械式の土砂攪拌装置を設けておき、土砂の取込を容易にすることも考えられる。
【0025】
構築完了したトンネルの底部には、移動可能な作業台610を連続的に設置し、土砂選別プラント530、土砂改良プラント540、排泥管531をその上に搭載することによってシールドマシン500の推進に追従できるようにする。また、埋戻し前のトンネルの浮上を防止するため、シールドマシン500の推進に追従して前進するウェイト台車620を設置する。
【0026】
<ハ>後方既設セグメントの埋戻し
土砂取込装置520に取込んだ土砂は、土砂取込管521を介して土砂選別プラント530に送り、不要分は排泥管531を介してトンネル後方に逐次排土する。必要分は土砂改良プラント540で改良した後、埋戻し管550を介して後方の既設セグメント600の周囲まで逐次搬送し、埋戻し土砂700とする。従って、シールドマシン500の推進に追従して、効率的に既設セグメント600の埋め戻しが可能となる。
【0027】
【発明の実施の形態3】
実施の形態2のシールドマシン500を用いて推進する際に、切羽土砂の一部を、実施の形態1で用いたような浚渫船300により水上から掘削する場合もある。水上からの浚渫土量とシールドマシン500内への取り込み土量とをバランスさせ、掘削土砂の一部を浚渫土として水上経由で処分する。
【0028】
【発明の効果】
本発明は以上のように構成されるため、以下のような効果を得ることができる。
<イ>切羽側の土砂を、水上の搬送手段又はシールドマシン内の埋戻し管を介して、後方の既設セグメントの周囲に逐次搬送できる。従って、シールドマシンの推進に追従して、効率的に既設セグメントの埋め戻しが可能となる。
【0029】
<ロ>推進に追従して逐次埋戻しを行なうため、セグメントが水中に露出する期間が短くて済み、施工中のトンネルの安全性が向上する。
【0030】
<ハ>シールドマシンの前面にカッタ装置を設けない構造の場合、経済的であると共に、故障も少なくて済む。
【0031】
<ニ>土被りがゼロか非常に小さい状態でシールドマシンを掘進させるため、トンネルの計画高を浅くでき、トンネルの全長を短くすることができる。
【0032】
<ホ>切羽土砂の一部を水上から掘削して浚渫土として処分することによって、掘削土砂の処分コストを低減することができる場合がある。
【図面の簡単な説明】
【図1】本発明の実施の形態1の説明図
【図2】本発明の実施の形態2の説明図
【図3】本発明の実施の形態2の説明図[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to an underwater shield method and a shield machine.
[0002]
[Problems to be solved by the invention]
Conventionally, in the construction of underwater tunnels, a submerging method, a shield method, and the like have been used. The submerged tunnel using the shield method has the advantages of a small amount of excavated soil and no need for a large-scale frame-building yard. However, it has disadvantages such as large earth covering and a large planned height of the tunnel. Therefore, an object of the present invention is to reduce the earth covering in the underwater shield construction method and efficiently backfill the segment tunnel constructed behind the shield machine.
[0003]
[Means for Solving the Problems]
[0006]
As a means of the present invention as a means for solving the above-mentioned problems, the present invention as a means of the present invention is to propel the shield machine underwater while assembling the segment at the rear, and let the earth and sand on the face side of the shield machine removed during propulsion flow into the shield machine. The present invention provides an underwater shield construction method characterized by penetrating a skin plate of a shield machine, communicating inside and outside, and backfilling the existing rear segment through a backfill pipe reaching the existing rear segment.
[0007]
Also, in the underwater shield method described above, part of the earth and sand that has flowed into the shield machine is used for backfilling the existing segment behind, and the other part is from the rear of the tunnel through the mud exhaust equipment inside the shield machine. To provide an underwater shield method characterized by carrying out.
[0008]
Then, part of the earth and sand on the face side of the shield machine is removed by means of excavation from above the water, and the shield machine is propelled underwater while assembling the segments at the rear. was flowing in the shield machine, communicates with the inside and outside through the skin plate of the shield machine, and wherein the backfill behind the existing segment through the pipe backfill reaching behind the existing segment, water shield Provide construction methods.
[0009]
Further, in the shield machine used in the underwater shield method described above , a means for taking in the earth and sand on the face side of the shield machine into the shield machine, and penetrating through the skin plate of the shield machine to the inside and outside, to the existing segment at the rear. and characterized in that it has a, a backfill tube for conveying to ambient behind the existing segments sediment captured in the shield machine reached, providing shielding machine.
[0010]
Also, in the shield machine used in the underwater shield method described above , a means for taking in the earth and sand on the face side of the shield machine into the shield machine, and penetrating through the skin plate of the shield machine to the inside and outside, to the existing segment at the rear. A backfill pipe for transporting a portion of the earth and sand that has arrived and taken into the shield machine to the periphery of the existing segment at the rear , and a mud discharging facility for carrying another portion of the earth and sand taken in from the rear of the tunnel. Provide a specially-designed shield machine. Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0011]
Embodiment 1 of the present invention
<A> Structure of Shield Machine As shown in FIG. 1, the shield machine 100 of the first embodiment has a structure in which a cutter device is not provided on the front surface. A partition wall 110 is provided on the front surface of a cylindrical or rectangular skin plate, and a
[0012]
Inside the
[0013]
<B> Propulsion of the shield machine While assembling the segment 200 behind the shield machine 100, the shield machine 100 is propelled by the
[0014]
The earth and sand left uncut near the bottom of the shield machine 100 among the earth and sand on the face side is allowed to flow into the earth and
[0015]
A movable worktable 210 is continuously installed at the bottom of the completed tunnel, and a
[0016]
<C> Backfill existing segments Back excavated by dredging
[0017]
As a specific example of the conveying means, a belt conveyor barge 310 is connected to the rear of the
[0018]
Embodiment 2 of the present invention
<A> Structure of Shield Machine As shown in FIGS. 2 and 3, the
[0019]
A
[0020]
The required amount of earth and sand is sent to an earth and
[0021]
The
[0022]
In the
[0023]
<B> Propulsion of the shield machine The
[0024]
As described above, since the sediment on the face side can be removed by taking in the earth and sand by the propulsive force of the
[0025]
A movable workbench 610 is continuously installed at the bottom of the completed tunnel, and a
[0026]
<C> The sediment taken into the back-filled
[0027]
Third Embodiment of the Invention
When propelling using the
[0028]
【The invention's effect】
Since the present invention is configured as described above, the following effects can be obtained.
<B> The face-side earth and sand can be successively conveyed around the existing segment at the rear through a conveying means on the water or a backfill pipe in the shield machine. Therefore, the existing segment can be efficiently backfilled following the propulsion of the shield machine.
[0029]
<B> Since backfilling is performed sequentially following the propulsion, the period during which the segments are exposed to the water can be shortened, and the safety of the tunnel during construction is improved.
[0030]
<C> In the case where the cutter device is not provided on the front surface of the shield machine, it is economical and requires less trouble.
[0031]
<D> Since the shield machine is excavated with zero or very small earth cover, the planned height of the tunnel can be reduced and the total length of the tunnel can be shortened.
[0032]
<E> In some cases, the disposal cost of excavated soil can be reduced by excavating part of the face earth and sand from the water and disposing it as dredged soil.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram of a first embodiment of the present invention; FIG. 2 is an explanatory diagram of a second embodiment of the present invention; FIG. 3 is an explanatory diagram of a second embodiment of the present invention;
Claims (5)
推進に際して取り除いたシールドマシンの切羽側の土砂をシールドマシン内に流入させ、The earth and sand on the face side of the shield machine removed during propulsion flow into the shield machine,
シールドマシンのスキンプレートを貫通して内外に連通し、後方の既設セグメントまで到達する埋戻し管を介して後方の既設セグメントを埋め戻すことを特徴とした、水中シールド工法。An underwater shield method, characterized by penetrating the skin plate of the shield machine and communicating inside and outside, and backfilling the existing segment at the back via a backfill pipe reaching the existing segment at the rear.
シールドマシン内に流入させた土砂の一部は後方既設セグメントの埋戻しに使用し、他の部分はシールドマシン内の排泥設備を介してトンネル後方より搬出することを特徴とした、水中シールド工法。Underwater shield method, in which part of the earth and sand that has flowed into the shield machine is used for backfilling the existing segment behind, and the other part is carried out from the back of the tunnel through the mud exhaust equipment inside the shield machine. .
推進に際して取り除いたシールドマシンの切羽側の土砂の他の部分をシールドマシン内に流入させ、The other part of the earth and sand on the face side of the shield machine removed during propulsion flows into the shield machine,
シールドマシンのスキンプレートを貫通して内外に連通し、後方の既設セグメントまで到達する埋戻し管を介して後方の既設セグメントを埋め戻すことを特徴とした、水中シールド工法。An underwater shield method, characterized by penetrating the skin plate of the shield machine and communicating inside and outside, and backfilling the existing segment at the back via a backfill pipe reaching the existing segment at the rear.
シールドマシンの切羽側の土砂をシールドマシン内に取り込む手段と、Means for taking the earth and sand on the face side of the shield machine into the shield machine,
シールドマシンのスキンプレートを貫通して内外に連通し、後方の既設セグメントまで到達してシールドマシン内に取り込んだ土砂を後方の既設セグメントの周囲まで搬送する埋戻し管と、を有することを特徴とした、シールドマシン。A backfill pipe that penetrates through the skin plate of the shield machine and communicates inside and outside, reaches the existing segment at the rear, and conveys the earth and sand taken into the shield machine to the periphery of the existing segment at the back, and A shield machine.
シールドマシンの切羽側の土砂をシールドマシン内に取り込む手段と、Means for taking the earth and sand on the face side of the shield machine into the shield machine,
シールドマシンのスキンプレートを貫通して内外に連通し、後方の既設セグメントまで到達してシールドマシン内に取り込んだ土砂の一部を後方の既設セグメントの周囲まで搬送する埋戻し管と、A backfill pipe that penetrates through the skin plate of the shield machine and communicates inside and outside, reaches a rear existing segment, and conveys a part of the earth and sand taken into the shield machine around the rear existing segment,
取り込んだ土砂の他の部分をトンネル後方より搬出する排泥設備と、を有することを特徴とした、シールドマシン。A shield machine, comprising: a sludge discharging device for discharging another portion of the sediment taken in from behind the tunnel.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP31843399A JP3579704B2 (en) | 1999-11-09 | 1999-11-09 | Underwater shield method and shield machine |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP31843399A JP3579704B2 (en) | 1999-11-09 | 1999-11-09 | Underwater shield method and shield machine |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2001132385A JP2001132385A (en) | 2001-05-15 |
| JP3579704B2 true JP3579704B2 (en) | 2004-10-20 |
Family
ID=18099106
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP31843399A Expired - Fee Related JP3579704B2 (en) | 1999-11-09 | 1999-11-09 | Underwater shield method and shield machine |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3579704B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4531298B2 (en) * | 2001-06-26 | 2010-08-25 | ジャパントンネルシステムズ株式会社 | Underwater shield shield machine |
| JP4276441B2 (en) * | 2003-01-08 | 2009-06-10 | 株式会社小松製作所 | Backing material injection apparatus and back material injection method |
| JP6488175B2 (en) * | 2015-04-08 | 2019-03-20 | 株式会社技研製作所 | Earth disposal equipment |
| CN110318428B (en) * | 2019-06-21 | 2024-11-05 | 中交第二航务工程局有限公司 | Open-type shield machine suitable for prefabrication and assembly of shallow underwater tunnels |
| CN116296304B (en) * | 2022-09-30 | 2025-09-02 | 盾构及掘进技术国家重点实验室 | Segment floating test device with stable and accurate process |
-
1999
- 1999-11-09 JP JP31843399A patent/JP3579704B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2001132385A (en) | 2001-05-15 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP2281091B1 (en) | Improvements in and relating to underwater excavation apparatus | |
| US4992000A (en) | Underwater trenching system | |
| JP3579704B2 (en) | Underwater shield method and shield machine | |
| CN111576517A (en) | Integrated high-pressure anti-blocking suction excavation dredging equipment | |
| RU2507431C2 (en) | Production method of excavation and laying works at routing of underwater pipelines, and device for its implementation | |
| JPH11117658A (en) | Sea bottom excavating device and method | |
| CN102124164A (en) | Method for conveying large volumes of submerged soil to fill areas | |
| CN104264732A (en) | Dredging machine and dredger comprising same | |
| JP3211875B2 (en) | Effective use of rising soil by improving the ground over water | |
| KR20100136027A (en) | Dredgers using dredgers to transfer dredges | |
| CN210369048U (en) | Open type shield machine suitable for underwater shallow tunnel prefabrication assembly construction | |
| JP3971241B2 (en) | Method of laying pipe in submarine ground and excavation tip device used for pipe laying method | |
| JP3053179B2 (en) | Solidification and transfer processing method for earth and sand such as dredging | |
| JP2683820B2 (en) | Subsea tunnel construction method and construction equipment | |
| US4903419A (en) | Method of and apparatus for dredging sludge in high density | |
| Huston | Dredging fundamentals | |
| JP3031506B2 (en) | Shield method | |
| CN111648425A (en) | Construction process for sand mining in high-compactness high-impurity-content water area | |
| JP3480699B2 (en) | Land transfer method for sediment transfer such as dredging | |
| JPS5513326A (en) | Dredging method and dredge boat | |
| JPS6073920A (en) | Settled-mud dredger | |
| JP2000238692A (en) | Unloader-cum-spreader barge | |
| JP2895595B2 (en) | Landfill work boat | |
| JPH03110295A (en) | Method and apparatus for constructing tunnel under water | |
| JPH1037674A (en) | Discharge soil disposal device in small-diameter pipe jack method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A975 | Report on accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A971005 Effective date: 20031209 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20040203 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040304 |
|
| A911 | Transfer of reconsideration by examiner before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20040420 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20040608 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20040622 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080730 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090730 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100730 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110730 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110730 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120730 Year of fee payment: 8 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130730 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130730 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140730 Year of fee payment: 10 |
|
| LAPS | Cancellation because of no payment of annual fees |