JP3655351B2 - Spacer for removing hardened cement in hollow pile - Google Patents
Spacer for removing hardened cement in hollow pile Download PDFInfo
- Publication number
- JP3655351B2 JP3655351B2 JP11102595A JP11102595A JP3655351B2 JP 3655351 B2 JP3655351 B2 JP 3655351B2 JP 11102595 A JP11102595 A JP 11102595A JP 11102595 A JP11102595 A JP 11102595A JP 3655351 B2 JP3655351 B2 JP 3655351B2
- Authority
- JP
- Japan
- Prior art keywords
- spacer
- hollow pile
- concrete
- pile
- longitudinal groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Description
【0001】
【産業上の利用分野】
本発明は、オーガマシン等で拡底掘削され、根固め用のコンクリートが注入された竪杭内に沈設される中空パイルの上部に予め挿設されるスペーサであって、沈設された中空パイル内を上昇してパイル内を埋めて硬化するコンクリートを、その硬化後、中空パイル上端から所定の長さ分だけ除去するために用いるスペーサに関する。
【0002】
【従来の技術】
建物等の基礎工事の施工法として、オーガマシン等で拡底掘削した竪杭内に根固め用のコンクリートを注入した後、当該竪杭に中空パイルを沈設して、当該コンクリートを硬化させる工法が知られている。この工法における中空パイルの沈設時には、竪杭に注入されたコンクリートが中空パイル内を上昇して満たし、更に余剰のコンクリートは中空パイルから溢れ出ることになる。
【0003】
ところで、竪杭内に沈設された中空パイルの上部には、この中空パイルと地中梁を一体に連結して形成するため、かご状の鉄筋が挿設されるので、養生後、当該上部を満たして硬化したコンクリートを除去し、このかご状の鉄筋を入れる空間を中空パイル上部に形成し直す必要がある。
【0004】
上記中空パイルの上部を満たして硬化したコンクリートの除去をしやすくするために使用されるのが中空パイル内硬化セメント除去用スペーサである。
【0005】
上記用途のスペーサとしては、間隔保持部材を介して組み合わせた内外二重の厚紙製の円筒状スペーサと、合成樹脂発泡体製の円筒状で、縦方向に切欠部が形成されたスペーサとが知られている(特開平4−371610号公報)。いずれもかご状の支持材を、その把持部を上方に露出させた状態で内包して中空パイルの上部に挿設されるもので、スペーサ内に上昇硬化したコンクリートを、支持材の把持部を介してバックホウ等の重機で上方に引きながら左右に振ることで、その下方で中空パイルと一体化して硬化したコンクリートから分断して除去できるようにするものである。
【0006】
【発明が解決しようとする課題】
ところで、厚紙製の円筒状スペーサは、上記公開公報でも指摘されているように、固い厚紙製でしかも円筒状であるので、特に外筒を中空パイル内にぴったり挿入しにくい問題がある。特にコンクリートパイルの内面は不規則な凹凸が付いていることが多く、その内径精度もさほど高くないので、内面の凹凸や多少の内径の相違によらず挿入を可能にするためには、外筒の径をやや小さめにしておく必要があり、外筒と中空パイル内面間にある程度の隙間を生じるのが避けられない。このため、外筒と中空パイル内面間にコンクリートが浸入し、外筒を強固に中空パイル内面に付着させてしまい、外筒が中空パイル内に残留しがちであると共に、外筒が除去できたとしても、外筒と中空パイル内面との間に浸入したコンクリートが残留することになる。厳格に工事を行うためにはその除去が必要となり、除去作業に多大な手間がかかる問題がある。
【0007】
一方、合成樹脂発泡体製の円筒状で、縦方向に切欠部が形成されたスペーサは、材質的にある程度の柔軟性を有し、切欠部を狭めることで縮径できるので、やや大きめの径としておくことで、内面の凹凸や多少の内径の相違によらず中空パイル内面にフィットさせ得る利点がある。
【0008】
しかしながら、上記利点を有するものの、縮径はできても拡径はできないので、中空パイルの内径が予想以上に大きい場合には対応することができないばかりか、異なる径の中空パイル毎に対応する径のスペーサを用意しなければならず、異なる径の中空パイルへの融通性に欠ける問題がある。また、縦方向に切欠部を有するので、そのままでは、スペーサ内に上昇したコンクリートがこの切欠部を介して中空パイル内面と一体化してしまい、このスペーサ内の硬化コンクリートを分断除去する妨げとなる。従って、外周又は内周に合成樹脂フィルム等を巻き付けて挿設するか、切欠部の位置をずらせて内外二重に組み合わせて挿設する必要があり、現場での作業が煩わしい問題もある。
【0009】
本発明は、上記従来の問題点に鑑みてなされたもので、中空パイル内面の凹凸や径大小に拘わらず中空パイル内面にフィットさせることができ、しかも現場での挿設作業が容易なスペーサを提供することを目的とする。
【0010】
【課題を解決するための手段】
このために本発明では、図1ないし図3に示されるように、ポリオレフィン系合成樹脂発泡体製の板状体で、片面の少なくとも両側部に多数の縦溝1が並列して形成され、この縦溝1の形成面を内側にして縦溝1の並列方向に弾性復帰可能な状態で丸めて、中空パイル2内に挿入可能なスペーサ3としているものである。
【0011】
【実施例及び作用】
図1ないし図4に基づいて、本発明の一実施例を説明する。
【0012】
本発明に係るスペーサ3は、ポリオレフィン系合成樹脂発泡体製の板状体で、図1に明示されるように、片面に多数の縦溝1が並列して形成されている。この縦溝1は、次に述べるように、本スペーサ3を中空パイル2(図2参照)内面に沿った円筒形に丸めやすくするためのもので、湾曲させにくい本スペーサ3の両側部のみ縦溝1を設け、本スペーサ3の中央部の縦溝1を省略して、加工の手間及びコストを軽減することもできる。
【0013】
縦溝1は、図2及び図3に示されるように、本スペーサ3をこの縦溝1の形成面を内側にして縦溝1の並列方向に丸めて中空パイル2内に挿入できるようにするためのものである。縦溝1の断面形状は、方形や半円形でもよいが、丸めやすくなることから、図示されるような逆三角形状であることが好ましい。縦溝1の幅、間隔及び深さは、丸めやすく、しかも丸めた後の適度な弾性復帰力が得られるよう調整することが好ましい。
【0014】
本スペーサ3のほぼ中央部には、縦溝1と同方向に、図3に示される支持材4の縦材5を収容して保持する縦材保持溝6が形成されている。また、本スペーサ3の上部と下部には、夫々縦溝1と直交方向に、支持材4の横材7を収容して保持する横材保持溝8が形成されている。この縦材保持溝6と横材保持溝8は必須ではないが、これらを設けておくと、本スペーサ3内の一定位置に支持材4を内包させやすく、本スペーサ3の使用時に支持材4を包み込む作業が容易となる。特に横材保持溝8を設けて、これに支持材4の横材7をしっかり保持させると、丸めた本スペーサ3内で硬化したセメントの分離除去時に本スペーサ3も同時に除去しやすくなる。尚、図1では縦材保持溝6は1本であるが、これを複数本設けてもよい。
【0015】
本スペーサ3の縦溝1の並列方向の一縁には、本スペーサ3を丸めた時に他端縁に重ねられる薄肉の重ね合わせ片9が設けられている。重ね合わせ片9は、この重ね合わせ片9以外の部分である本体部分と一体に形成もしくは本体部分に溶着又は接着で設けられているものである。この重ね合わせ片9は必須のものではないが、重ね合わせ片9を設けておくと、本スペーサ3を丸めた時の両端縁部を、外面側に大きな段差を発生させることなく重ね合わせることができ、本スペーサ3の全外周をパイル2の内面に密着させやすくなる。
【0016】
本スペーサ3は、少なくとも上記重ね合わせ片9以外の部分である本体部分がポリオレフィン系合成樹脂発泡体製であることが必要である。ポリオレフィン系合成樹脂発泡体は、例えばポリスチレン発泡体等に比して腰が強くかつ可撓性及び弾性に優れ、割れや欠けを生じることなくパイル2の内面に密着させやすいと共に、コンクリートが付着しにくい利点がある。ポリオレフィン系合成樹脂としては、例えばポリエチレン、ポリプロピレン、これらを50重量%以上含む共重合体を挙げることができ、好ましくはポリエチレンである。
【0017】
上記本体部分を構成するポリオレフィン系合成樹脂発泡体の発泡倍率は、必要な強度、弾性等を得る上で、5〜100倍であることが好ましく、更に好ましくは20〜50倍である。また、このポリオレフィン系合成樹脂発泡体で構成される本スペーサ3の本体部分の厚みは、後述する硬化コンクリートの分断除去時に左右に揺すりやすいよう、20〜50mmであることが好ましい。
【0018】
前記重ね合わせ片9も上記のようなポリオレフィン系合成樹脂製であることが好ましい。また、この重ね合わせ片9は、薄く形成されているものの、腰が強い部分となっていると、本スペーサ3を丸めた時の重ね合わせ作業が行いやすいので、非発泡のポリオレフィン系合成樹脂若しくは発泡倍率が50倍以下のポリオレフィン系合成樹脂発泡体であることが好ましい。ポリオレフィン系合成樹脂発泡体とする場合、特に発泡倍率が5〜50倍であることが好ましい。
【0019】
次に、上述の本スペーサ3の使用方法を図2〜図6で説明する。
【0020】
まず、本スペーサ3を図2に示されるように丸める際に、図3に示されるように支持材4を包み込むようにして丸める。この時、支持材4の縦材5を本スペーサ3の縦材保持溝6に合わせ、横材7を横材保持溝8に合わせる。
【0021】
ここで支持材4について説明すると、支持材4は、本スペーサ3に内包された状態でパイル2の上部に挿設されるもので、通常鉄筋材料で構成され、略長円形状に屈曲させて端部同志を熔接した縦材5と、縦材5の周囲に取り付けられた環状の横材7とからなるかご状をなす部材である。支持材4の上部は、バックホウ等の重機で上方に引っ張るための把持部10となっている。支持材4は、この把持部10が上方に露出した状態で本スペーサ3に内包され、しかもパイル2内に挿設されるものである。
【0022】
支持材4の上部には、支持材4を中空パイル2の上端から吊っておくための支持環13が設けられている。また、支持材4の下端部には装着環12が設けられており、その下面側に仕切り板11が粘着テープや針金等の手段で取付けられている。この装着環12は必須のものではなく、これを設けずに、図2中点線で示すように支持材4の下端部に仕切り板11を取り付けてもよい。また、装着環12の有無に拘わらず、支持材4の取付位置は丸めた本スペーサ3に内包される位置でも、下端に露出した位置でもよい。
【0023】
上記装着環12に取り付けられる仕切り板11は、中空パイル2内に挿設された本スペーサ3内にその下方から上昇して入り込むコンクリートの流入口を狭め、中空パイル2内のコンクリートが硬化した後、本スペーサ3内の硬化コンクリートと、その下方の硬化コンクリートとの間の連結箇所を上記流入口のみに仕切って、両者を分断しやすくするためのものである。
【0024】
仕切り板11の具体例としては、図4(a)に示されるように、例えばゴムや合成樹脂等の可撓性を有する材料で構成された円板の中央部に十字形もしくは放射状に切れ目14を入れて複数の舌片15を形成し、この舌片15がまくれ上がることでコンクリートの流入を許容するもの、図4(b)に示されるように、コンクリートの流入口となる細幅のスリット16を形成したもの、図4(c)に示されるように、丸められた本スペーサ3との間にコンクリートの流入口となる隙間17を残すもの等が挙げられる。
【0025】
上述のような支持環13、装着環12及び仕切り板11を備えた支持材4を本スペーサ3でくるんだ後、これを中空パイル2内に挿設する。また、根固め用のコンクリートを注入した竪杭内に当該中空パイル2を沈設した時に、中空パイル2内を上昇するコンクリートによって本スペーサ3が浮き上がらないよう、本スペーサ3を押え具(図示されていない)で止めておく。本スペーサ3の浮き上がり防止のためには、支持材4の上端を横断して、かんざし筋と称される鉄筋材を固定しておき、通常鉄枠が嵌め込まれている中空パイル2の上端に、このかんざし筋を仮熔接止めしておくことでも行うことができる。この場合支持環13は省略できる。
【0026】
本スペーサ3を丸めて中空パイル2内に挿入するに際し、丸めた本スペーサ3の挿入先端側(下端側)から中央部分の1〜2箇所を例えば紐、テープファスナー付テープ等で仮止めし、ある程度挿入した後にこの仮止めを外すようにすると、挿入作業が容易となる。
【0027】
本スペーサ3は、単に丸められた状態で挿設されるもので、丸め方によって径を自在に調整できるので、中空パイル2内面の凹凸や内径の誤差はもとより、同じスペーサ3を径の異なる異種類の中空パイル2に対して使用することが可能である。また、中空パイル2内に挿入された本スペーサ3は弾性復帰して拡径すると共に、本スペーサ3は適度な弾力性を有するので、中空パイル2内面の凹凸や内径の相違に拘わらず、中空パイル2の内面に密着しやすく、中空パイル2の内面との間にほとんど隙間が残らない。従って、中空パイル2内を上昇するコンクリートが、中空パイル2の内面と本スペーサ3の間にほとんど浸入しないことに加え、本スペーサ3がコンクリートが付着しにくいポリオレフィン系合成樹脂発泡体製であるので、養生後の本スペーサ3の除去が容易である。
【0028】
ところで、本スペーサ3が重ね合わせ片9を有する場合、中空パイル2の内径が小さいと、丸めた本スペーサ3の端縁部がこの重ね合わせ片9を越えて重ね合わされる場合がある。このような場合、本スペーサ3を適宜切断して長さ調節すればよいが、本スペーサ3は多数の縦溝1を有するので、適宜の位置の縦溝1を介して手で引き裂いて長さ調節することができ、現場での作業が容易である。特に、縦溝1が図1に示されるような断面逆三角形状であると、この手での引き裂きが行いやすい利点がある。
【0029】
本スペーサ3を図3に示されるように中空パイル2にセットした後、中空パイル2を建て込み、図5に示されるように、根固め用のコンクリートを注入した竪杭内に沈設する。そして、養生の後、図6に示されるように、本スペーサー3内の硬化コンクリートをその下方の硬化コンクリートから分断して除去する。
【0030】
上記分断除去は、支持材4の把持部10をバックホウ等の重機に接続し、引き上げると共に左右に揺することで、本スペーサ3内の硬化コンクリートと、その下方で中空パイル2と一体となった硬化コンクリートを分断することで行うことができる。
【0031】
上記分断は、前述の仕切り板11を設けておかなくても可能ではあるが、前述した通り、この仕切り板11を設けておくと、本スペーサ3内の硬化コンクリートとその下方の硬化コンクリート間がこれで仕切られ、分断しやすくなるので好ましい。また、本スペーサ3は、前述のように中空パイル2の内面との間にコンクリートが浸入しにくく、しかもコンクリートが付着しにくいので、本スペーサ3内の硬化コンクリートと共に抜き出されやすく、その残留を防止しやすい。また、仮に硬化コンクリートのみが抜き出され、本スペーサ3が残留したとしても、これを再度引っ張ることで容易に抜き取ることができ、抜き取りに手間がかからない。
【0032】
このようにして、本スペーサ3及び本スペーサ3内の硬化コンクリートを除去した後は、これによって開けられた中空パイル2上部の空間にかご状の鉄筋を挿設し、地中梁を構築が進められることになる。
【0033】
図7は本スペーサ3の他の実施例を示すもので、縦溝1の形成面側の少なくとも縦溝1方向一端縁(少なくとも中空パイル2内への挿入先端側)が外向きのテーパ面18となっている。
【0034】
このようにすると、根固め用のコンクリートを注入した竪坑内に中空パイル2を沈設したときに上昇して来るコンクリートは、図7中矢印で示すようにテーパ面18に沿って流れ、本スペーサ3の下端部を中空パイル2の内面に押し付けることになる。従って、本スペーサ3と中空パイル2の内面間にコンクリートが侵入しにくくなる。
【0035】
【発明の効果】
本発明は、以上説明した通りのものであり、次の効果を奏するものである。
【0036】
(1)現場で丸めて中空パイル2に挿入し、中空パイル2内で弾性復帰させるものであるので、中空パイル2内面の凹凸や、中空パイル2の内径誤差に拘わらず、中空パイル2の内面に密着させることができる。
【0037】
(2)上記と同じ理由から、径の異なる異種の中空パイル2に対して同じスペーサ3を使用でき、汎用性が高い。
【0038】
(3)弾性復帰力によって中空パイル2の内面に密着するので、スペーサ3と中空パイル2の内面間にコンクリートが浸入しにくいと共に、コンクリートが付着しにくいポリオレフィン系合成樹脂発泡体製であるので、除去が容易で、はつり等の後処理の手間を省略できる。
【0039】
(4)単品で構成され、複数の部品を組み合わせて使用する必要がないので、現場での作業性がよい。
【図面の簡単な説明】
【図1】本発明に係るスペーサの一実施例を示す斜視図である。
【図2】図1のスペーサを丸めた状態を示す斜視図である。
【図3】図1のスペーサに支持材を内包させて中空パイル上部にセットした状態を示す断面図である。
【図4】仕切り板を示す図である。
【図5】図1のスペーサをセットした中空パイルを、根固めコンクリートを注入した竪杭に沈設した状態の断面図である。
【図6】スペーサ内の硬化コンクリートをその下方の硬化コンクリートから分断して抜き出す途中状態の断面図である。
【図7】本発明に係るスペーサの他の実施例を示す断面図である。
【符号の説明】
1 縦溝
2 中空パイル
3 スペーサ
4 支持材
5 縦材
6 縦材保持溝
7 横材
8 横材保持溝
9 重ね合わせ部
10 把持部
11 仕切り板
12 装着環
13 支持環
14 切れ目
15 舌片
16 スリット
17 隙間
18 テーパ面[0001]
[Industrial application fields]
The present invention is a spacer that is inserted in advance in the upper part of a hollow pile that has been excavated by an auger machine or the like and is set in a pile pile that has been filled with concrete for consolidation, and the inside of the set hollow pile The present invention relates to a spacer that is used for removing a predetermined length from the upper end of a hollow pile after the concrete that rises and fills and hardens in the pile.
[0002]
[Prior art]
As a construction method of foundation work for buildings, etc., a method is known in which concrete for solidification is poured into a pile that has been excavated with an auger machine or the like, and then a hollow pile is set in the pile to harden the concrete. It has been. When the hollow pile is set in this construction method, the concrete poured into the pile pile rises and fills the hollow pile, and the surplus concrete overflows from the hollow pile.
[0003]
By the way, since the hollow pile and the underground beam are integrally connected to the upper part of the hollow pile set in the pile, a cage-like reinforcing bar is inserted. It is necessary to remove the filled and hardened concrete and re-create the space for the cage-like reinforcing bars in the upper part of the hollow pile.
[0004]
A spacer for removing the hardened cement in the hollow pile is used to easily remove the hardened concrete by filling the upper part of the hollow pile.
[0005]
As spacers for the above applications, there are known inner and outer double cardboard cylindrical spacers combined via a spacing member, and synthetic resin foam cylindrical spacers with cutouts formed in the vertical direction. (Japanese Patent Laid-Open No. 4-371610). In either case, the cage-shaped support material is encased with the gripping portion exposed upward, and is inserted into the upper part of the hollow pile. By swinging left and right while pulling upward with a heavy machine such as a backhoe, it is possible to separate and remove from the hardened concrete integrated with the hollow pile below.
[0006]
[Problems to be solved by the invention]
By the way, as pointed out in the above-mentioned publication, the cylindrical spacer made of cardboard has a problem that it is difficult to insert the outer cylinder exactly into the hollow pile because it is made of hard cardboard and is cylindrical. In particular, the inner surface of concrete piles often has irregular irregularities, and the accuracy of the inner diameter is not so high. To make it possible to insert regardless of the irregularities on the inner surface or slight differences in inner diameter, the outer cylinder It is necessary to make the diameter slightly smaller, and it is inevitable that a certain amount of gap is generated between the outer cylinder and the inner surface of the hollow pile. For this reason, concrete entered between the outer cylinder and the inner surface of the hollow pile, and the outer cylinder was firmly attached to the inner surface of the hollow pile, and the outer cylinder was likely to remain in the hollow pile, and the outer cylinder could be removed. Even so, the concrete that has entered between the outer cylinder and the inner surface of the hollow pile remains. In order to perform the construction strictly, the removal is necessary, and there is a problem that the removal work takes a lot of time and effort.
[0007]
On the other hand, a spacer made of a synthetic resin foam and having a notch in the vertical direction has a certain degree of flexibility in material and can be reduced in diameter by narrowing the notch. Therefore, there is an advantage that it can be fitted to the inner surface of the hollow pile regardless of the unevenness of the inner surface or some difference in inner diameter.
[0008]
However, although it has the above-mentioned advantages, even if it can be reduced in diameter, it cannot be expanded. Therefore, it cannot cope with the case where the inner diameter of the hollow pile is larger than expected. Spacers have to be prepared, and there is a problem that flexibility to hollow piles of different diameters is lacking. Moreover, since it has a notch part in the vertical direction, as it is, the concrete that has risen in the spacer is integrated with the inner surface of the hollow pile via the notch part, and this prevents the hardened concrete in the spacer from being separated and removed. Therefore, it is necessary to wrap and insert a synthetic resin film or the like around the outer periphery or the inner periphery, or shift the position of the notch portion and insert it in combination with the inner and outer doubles, resulting in troublesome work on site.
[0009]
The present invention has been made in view of the above-described conventional problems, and a spacer that can be fitted to the inner surface of the hollow pile regardless of the unevenness or the diameter of the inner surface of the hollow pile, and that can be easily inserted in the field is provided. The purpose is to provide.
[0010]
[Means for Solving the Problems]
For this reason, in the present invention, as shown in FIGS. 1 to 3, a plate-like body made of a polyolefin-based synthetic resin foam has a large number of longitudinal grooves 1 formed in parallel on at least both sides of one side. The
[0011]
Example and operation
An embodiment of the present invention will be described with reference to FIGS.
[0012]
The
[0013]
As shown in FIG. 2 and FIG. 3, the longitudinal groove 1 can be inserted into the
[0014]
A vertical material holding groove 6 for receiving and holding the
[0015]
A thin overlapping piece 9 is provided at one edge in the parallel direction of the longitudinal grooves 1 of the
[0016]
In the
[0017]
The foaming ratio of the polyolefin-based synthetic resin foam constituting the main body is preferably 5 to 100 times, more preferably 20 to 50 times, in order to obtain necessary strength, elasticity and the like. Moreover, it is preferable that the thickness of the main part of this
[0018]
The overlapping piece 9 is also preferably made of a polyolefin-based synthetic resin as described above. In addition, although the overlapping piece 9 is formed thin, it is easy to perform the overlapping operation when the
[0019]
Next, a method of using the above-described
[0020]
First, when the
[0021]
Here, the
[0022]
A
[0023]
After the
[0024]
As a specific example of the
[0025]
After the
[0026]
When the
[0027]
The
[0028]
By the way, when the
[0029]
After the
[0030]
The above-mentioned parting removal is performed by connecting the
[0031]
Although the above-mentioned division is possible even if the
[0032]
After removing the
[0033]
FIG. 7 shows another embodiment of the
[0034]
In this way, the concrete that rises when the
[0035]
【The invention's effect】
The present invention is as described above, and has the following effects.
[0036]
(1) Since it is rolled up on site and inserted into the
[0037]
(2) For the same reason as described above, the
[0038]
(3) Because it is in close contact with the inner surface of the
[0039]
(4) Since it is composed of a single product and does not need to be used in combination with a plurality of parts, workability on site is good.
[Brief description of the drawings]
FIG. 1 is a perspective view showing an embodiment of a spacer according to the present invention.
FIG. 2 is a perspective view showing a state in which the spacer of FIG. 1 is rounded.
3 is a cross-sectional view showing a state in which a support material is included in the spacer of FIG.
FIG. 4 is a view showing a partition plate.
FIG. 5 is a cross-sectional view of a state where the hollow pile with the spacers of FIG. 1 is set on a pile pile poured with solidified concrete.
FIG. 6 is a cross-sectional view showing a state in which the hardened concrete in the spacer is being cut out from the hardened concrete below the spacer.
FIG. 7 is a cross-sectional view showing another embodiment of the spacer according to the present invention.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP11102595A JP3655351B2 (en) | 1995-02-27 | 1995-04-13 | Spacer for removing hardened cement in hollow pile |
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP6156195 | 1995-02-27 | ||
| JP7-61561 | 1995-02-27 | ||
| JP11102595A JP3655351B2 (en) | 1995-02-27 | 1995-04-13 | Spacer for removing hardened cement in hollow pile |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH08296224A JPH08296224A (en) | 1996-11-12 |
| JP3655351B2 true JP3655351B2 (en) | 2005-06-02 |
Family
ID=26402609
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP11102595A Expired - Fee Related JP3655351B2 (en) | 1995-02-27 | 1995-04-13 | Spacer for removing hardened cement in hollow pile |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3655351B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102677689A (en) * | 2012-03-28 | 2012-09-19 | 天津二十冶建设有限公司 | Structure for pouring column foundation cup mouth and pouring method |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB2395509B (en) * | 2002-11-20 | 2005-10-26 | Cordek Ltd | Improvements in or relating to casting of piles |
| CN113463457B (en) * | 2021-05-17 | 2022-06-14 | 衡阳公路桥梁建设有限公司 | Roadbed structure for penetrating through slurry section and construction method thereof |
-
1995
- 1995-04-13 JP JP11102595A patent/JP3655351B2/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102677689A (en) * | 2012-03-28 | 2012-09-19 | 天津二十冶建设有限公司 | Structure for pouring column foundation cup mouth and pouring method |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH08296224A (en) | 1996-11-12 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO2010037211A1 (en) | Apparatus and methods for lining concrete structures with flexible liners of textile or the like | |
| JP3655351B2 (en) | Spacer for removing hardened cement in hollow pile | |
| JP3670340B2 (en) | Embedding method | |
| JP3609485B2 (en) | Spacer for removing hardened cement in hollow pile | |
| JP2651813B2 (en) | Processing method of joints in reverse driving method | |
| JP3808554B2 (en) | Pile spacer | |
| JP2001182054A (en) | Method and implement for removing pile head extra-fill of cast-in-place concrete pile | |
| JP3808546B2 (en) | Pile spacer | |
| JP2576756B2 (en) | Pile head treatment method for ready-made prestressed concrete pile | |
| JP3016009B2 (en) | Pile spacer | |
| JP3247955B2 (en) | Pile spacer | |
| JP2001073393A (en) | Building material for civil-engineering building, usage of the building material for civil-engineering building, the civil-engineering building, and anchor for wall surface material | |
| JPH10273913A (en) | Pile spacer | |
| JP2000096558A (en) | Pile spacer | |
| JPH05179804A (en) | Concrete placing joint method in reverse depositing | |
| JP2004332368A (en) | Construction method of concrete foundation | |
| JP2005023657A (en) | Seismically strengthening method for reinforced concrete structure | |
| JP3848345B2 (en) | Pile removal tool in pile | |
| JP4197383B2 (en) | Underground continuous wall | |
| JP2002081039A (en) | Construction stone for civil engineering structure | |
| JPH06240698A (en) | Block for bottom form and inverted concrete construction method | |
| JPS5811218A (en) | Removal of head of on-site pile | |
| JPH0211477Y2 (en) | ||
| JP2002081040A (en) | Construction stone for civil engineering structure | |
| JPH073780A (en) | Pile head treatment method for cast-in-place concrete pile |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040924 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20041012 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20041130 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050222 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050303 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080311 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090311 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090311 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100311 Year of fee payment: 5 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100311 Year of fee payment: 5 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110311 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110311 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120311 Year of fee payment: 7 |
|
| LAPS | Cancellation because of no payment of annual fees |