JP3660177B2 - Construction method of lightweight embankment - Google Patents
Construction method of lightweight embankment Download PDFInfo
- Publication number
- JP3660177B2 JP3660177B2 JP32927099A JP32927099A JP3660177B2 JP 3660177 B2 JP3660177 B2 JP 3660177B2 JP 32927099 A JP32927099 A JP 32927099A JP 32927099 A JP32927099 A JP 32927099A JP 3660177 B2 JP3660177 B2 JP 3660177B2
- Authority
- JP
- Japan
- Prior art keywords
- block
- stock solution
- foam
- gap
- blocks
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、ポリウレタンフォームの現場発泡による軽量盛土構造及びその構築方法に関するものである。
【0002】
【従来技術】
近年、軟弱地盤、急傾斜地、構造物への軽量盛土材料として硬質ポリウレタンフォームやポリスチレンフォームが使用されている。
▲1▼.硬質ポリウレタンフォームを使用して盛土を形成する方法は、盛土現場に硬質ウレタンフォーム作製用原液を運搬し、硬質ウレタン発泡装置にて盛土箇所に前記原液を注入又は吹付けて、硬質ウレタンフォームを生成せしめることにより行われる。
▲2▼.ポリスチレンフォームを使用して盛土を形成する方法は、盛土現場に予め工場生産した多数のポリスチレンフォームのブロックを運搬し、盛土箇所にブロックを積層することによって行われる。
しかし、▲1▼の方法においては、注入又は吹付けで一度に生成可能な硬質ポリウレタンフォームの高さは限られており、硬質ポリウレタンフォームの生成において発熱反応をともなうので一度目の注入又は吹付けの硬質ポリウレタンフォームが硬化しある程度冷却してから二度目の注入又は吹付けを行うので工期が長くなるという問題がある。
▲2▼の方法において、特開平1−66316号に軽量ブロックの一体性を確保した盛土が記載されているが、各ブロックの寸法の高さ、幅、奥行が設計図面のとおり正確であり、かつ表面が平滑でないと一体性のある盛土が困難であると思われる。
【0003】
ポリスチレンフォームからなるブロックの製造は、設備的理由により一般に工場にて行われ、各ブロックの寸法は、ほぼ設計図面とおりに加工することが可能でありぐらつきのない盛土を構築することが可能である。しかし、軽量であるがために価格に対する運搬コストの比率が高くなることを免れない。
【0004】
また、一般に建屋等の断熱材の材料として使用される硬質ウレタンフォーム作製用原液、及び運搬の容易なウレタン発泡機等を使用してブロックを作製することにより運搬コストを低減することが考えられるが、現場での硬質ウレタンの発泡に際しては、周囲温度をコントロールすることが困難である等の理由で、ブロックの六面全てを平滑にすること、及び各ブロックの寸法を同じにすることも困難であるという問題があった。
【0005】
【発明が解決しようとする課題】
本発明は上記問題を解決するためになされたものであり、工期を短縮し、寸法がまちまちで平滑性のないブロックを使用しても、一体性のある軽量盛土の構築方法を提供するものである。
【0006】
【問題を解決するための手段】
本発明の軽量盛土の構築方法は、硬質ウレタンフォームからなる多数のブロックと硬質ウレタンフォーム作成用原液とを用いた軽量盛土の構築方法であって、硬質ウレタンフォーム作成用原液は、主としてブロックを積み重ねる際のブロック上部と下部とを接着する発泡接着層形成原液と、主としてブロックと地盤やブロックと型枠との間にできる隙間を発泡充填する発泡隙間充填原液とからなり、ブロック敷設箇所に、発泡接着層形成原液を注入又は吹付けて前記原液が硬化する前に多数のブロックを敷設し、前記原液の硬化によりブロック下部を接着固定し、発泡隙間充填原液を、前記下部を固定したブロックと地盤やブロックと型枠との間にできた隙間に注入又は吹付け、前記原液の硬化によりブロックの側面を接着固定し、下部と側面を固定したブロックの上部を次なるブロック敷設箇所として、上記と同様なブロックの下部の接着固定とブロックの側面の接着固定とを繰り返すことを特徴とするものである。
【0007】
また、第一層目の工程として、地盤上に発泡隙間充填原液を注入又は吹付け発泡及び硬化させることによりレベリング層を形成し、前記レベリング層上に、発泡接着層形成原液を注入又は吹付けて前記原液が硬化する前に第一層目のブロックを多数敷設し前記原液の硬化によりブロック下部を接着固定し、前記下部を固定したブロックと地盤やブロックと型枠との間にできた隙間に、必要に応じてブロックの上部を覆う位置まで、発泡隙間充填原液を注入又は吹付けて前記原液の硬化によりブロックの側面を接着固定し、第二層目の工程として、前記第一層目のブロック上に発泡接着層形成原液を注入又は吹付けて前記原液が硬化する前に第二層目のブロックを多数敷設し前記原液の硬化によりブロック下部を接着固定し、前記下部を固定したブロックと地盤やブロックと型枠との間にできた隙間に、必要に応じてブロックの上部を覆う位置まで、発泡隙間充填原液を注入又は吹付けて前記原液の硬化によりブロックの側面を接着固定し、以下第二層目と同様な行程を繰り返し、所望の高さまで硬質ウレタンフォームからなるブロックを、硬質ウレタンフォーム中に埋設することを特徴とするものである。
【0008】
また、前記発泡接着層形成原液は、前記発泡隙間充填原液と比較して反応性の遅いものであることを特徴とするものである。
【0009】
本発明では、強固の盛土とするため略同一高さに敷設するブロックとブロックの間に、ブロック側面を接着固定するために隙間を設け、ブロックと地盤やブロックと型枠との隙間充填作業と平行して前記隙間を充填することが好ましい。なお、ブロックとブロックとの間の隙間充填は、発泡接着層形成原液又は発泡隙間充填原液のどちらでも使用できるが、作業を早めるために下述の発泡隙間充填原液の使用が好ましい。
【0010】
また、地盤上にレベリング層を形成するに際して、地盤とレベリング層の間に排水シートを敷設することができる。特に地盤が傾斜地の場合、山からの湧き出てくる地下水を排水するために排水シートを設けることが好ましい。
排水シートは、排水可能なものであれば特に制限はないがフェルト状不織布、編布、織布、ダブルラッセル又はメッシュ構造の排水パイプを内蔵したシート等が使用できる。
【0011】
本発明に使用する硬質ウレタンフォーム作製用原液は、ブロックの作製、発泡接着層の形成、レベリング層の形成、及び隙間の充填に使用するもので、一般に建築物の断熱施工の現場発泡に使用されるもので良く、ポリオール成分とポリイソシアネート成分からなる。この両者を混合することによって硬質ウレタンフォームが生成される。多数のブロックは、前もって又は後から注入等で生成される硬質ウレタンフォームの自己接着性により強固に接着され一体化する。
【0012】
硬質ウレタンフォーム作製用原液である発泡接着層形成原液と発泡隙間充填原液とは、同一のものであってもよいが、作業性を向上するために発泡接着層形成原液の反応性が、前記発泡隙間充填原液の反応性よりも遅いものであることが好ましい。すなわち作業スピードを向上するために特にレベリング層の形成及びブロックと地盤、ブロックと型枠との間の隙間の充填は、反応性の早い原液を使用することで作業時間の短縮を図り、発泡接着層の形成は、ブロックの下部と上部との接着の作業時間を確保するため反応性の遅い原液を使用することが好ましい。
【0013】
硬質ウレタンフォーム作成用原液の反応性は、触媒等の添加量を変化させることにより簡単に行うことができる。例えば、工場にて反応性の異なる2種類の原液を作製して現場に運搬しても良いし、反応性の遅い原液を工場にて作製し現場に運搬したのち、触媒を増量することで反応性の早い原液を作製することもできる。
発泡隙間充填原液の反応性は現場の状況に合わせて調整するが、ライズタイムで通常15〜20秒が好ましい。
発泡接着層形成原液の反応性も現場の状況に合わせて調整するが、ライズタイム120〜180秒が好ましい。
【0014】
上述の原液は、ドラム缶等で運搬され硬質ウレタン発泡機等に汲み上げられ混合撹拌吐出され、ブロックの作製、レベリング層の形成、各隙間の接着充填、ブロックの上部とその上に載る別のブロックの下部の接着等に使用される。また発泡接着層形成原液は、反応性が遅いので撹拌時間に余裕があり発泡機を使用しなくともポリ袋等にポリオール成分とイソシアネート成分を投入してから、該ポリ袋を揺らすことで2成分を混合撹拌することができる。
【0015】
本発明に使用するブロックは、運搬コストを低減するために盛土現場及びその近くにおいて作製することができる。また現場の雨仕舞の状況にもよるが、雨天でも別の限られた狭い場所でブロックを作製することで決められた作業工程どおりに作業を進めることができる。
【0016】
また、現場でブロックを作製する場合の型枠は、運搬が容易なように構造が簡単で軽量なものが好ましい。現場においては、周囲温度や原液の温度を正確にコントロールすることが難しいことにより、発泡倍率を一定にすることが困難である。そのため密閉式の型枠であると、構造自体複雑になる上に型枠に過大の発泡圧がかかり堅固な型枠でないと型枠を破損する虞があり、そのため型枠が重くなってしまうので、構造が簡単で軽量な上部開放の型枠が好ましい。ブロック作製するための型枠の一例を図4に示す。
但し上部が開放された型枠を使用して得られるブロックは、図5に示すように上部が平滑でないものとなる。また、ブロックのサイズは、特に制限されるものではないが奥行き、幅、高さとも品質面を維持するために0.4〜1.0mが好ましい。
本発明は、このようにブロック寸法が正確にでていなくとも一体なる硬質ウレタンフォームによる盛土を構築できることを特徴とするものである。
【0017】
【発明の実施の形態】
以下本発明の実施の形態例を図面に基づき説明する。
図1は急傾斜地に本発明の軽量盛土の構築方法によって得られる盛土構造の一例を示すものである。図2は略平坦の軟弱地盤等に本発明の軽量盛土の構築方法によって得られる盛土構造の一例を示すものである。なお、型枠8’は硬質ウレタンフォームによる盛土を形成するために必要なものであり盛土形成後に解体されるものである。
図3は、本発明の軽量盛土の構築方法の説明図である。図3において、
(a) 地盤12にメッシュ構造の排水パイプを内蔵したシート2を敷設し、
(b) 発泡隙間充填原液を注入又は吹付けによりレベリング層3を形成し、
(c) レベリング層3の上に発泡接着層形成原液を注入又は吹付けて、
(d) 前記原液が硬化する前に、予め現場近くでブロックを作製するための型枠を用いて作製したブロック5を敷設する。この際、ブロックは、自重等により発泡接着層4の中に沈み込み前記原液の硬化によりその下部がレベリング層上に固定される。
(e) レベリング層とブロック下部とが発泡接着層を介して一体化した後、下部の固定されたブロックとブロックとの隙間、及びブロックと型枠B(図3において型枠Bは擁壁)8や地盤との間に生まれる隙間に発泡隙間充填原液を注入又は吹付けて硬化させる。また、本実施例ではブロックの上部を覆う位置まで発泡隙間充填原液を注入又は吹付け、ブロックの上部にまで覆った発泡隙間充填層6を形成する。
(f) 前記発泡隙間充填層上に、又はブロック上に再び発泡接着層形成原液を注入又は吹付け、以下(d)〜(f)を繰り返し実施することにより軽量盛土を構築する。
上記のように形成した軽量盛土上に土砂7等をもって土木構造物が設けられることになる。
【0018】
【発明の効果】
以上説明したとおり本発明の軽量盛土の構築方法によれば、硬質ウレタンフォームからなるブロックが、同じ硬質ウレタンフォームによって一体的に接着固定されるので、異種の素材のものと比較して強固な盛土構造が得られる。
また、発泡接着層が硬化する前にブロックを敷設することにより、ブロックが発泡接着層の中に沈み込むので、ブロックの下部がより強固に固定される一方、ブロックの側面も、後から隙間充填原液を注入又は吹付けて発泡させることにより、ブロックと地盤やブロック同士等の間の隙間が広くても狭くても簡単に硬質ウレタンフォームで充填できるので、より強固に固定される。
さらに、盛土箇所全部を硬質ウレタンフォームの注入又は吹付ける方法に比べ工期を短縮することができる。
しかも運搬コストを低減するため盛土現場で作製した寸法がまちまちで平滑でないブロックを使用した場合においても上記と同じ理由で、すなわちブロックの下部は接着層中に沈み込むし、ブロックの側面にできる隙間が広くても狭くても充填できることからブロックサイズのばらつき及びブロック表面の凹凸の盛土強度に対する影響はない。
【図面の簡単な説明】
【図1】本発明によって得られる盛土構造の一例の説明図。
【図2】本発明によって得られる盛土構造の一例の説明図。
【図3】本発明の軽量盛土の構築方法の説明図。
【図4】.本発明の実施例で使用するブロックを作製するための型枠の説明図。(a)のような状態で硬質ウレタンフォーム作製用原液を注入又は吹付けてブロックを作製し(b)のようにしてブロックを脱型する。
【図5】本発明の実施例で作製されるブロックの一例を半裁したときの断面図。
【符号の説明】
1 軽量盛土
1’ 軽量盛土
2 メッシュ構造の排水パイプを内蔵したシート
3 レベリング層
4 発泡接着層
5 ブロック
6 発泡隙間充填層
7 土砂
8 型枠B(擁壁)
8’ 型枠B
11 排水パイプ
12 地盤[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a lightweight embankment structure by in-situ foaming of polyurethane foam and a construction method thereof.
[0002]
[Prior art]
In recent years, rigid polyurethane foam or polystyrene foam has been used as a lightweight embankment material for soft ground, steep slopes, and structures.
(1). The method of forming embankment using rigid polyurethane foam is to transport the stock solution for making rigid urethane foam to the embankment site and inject or spray the stock solution to the embankment location with a rigid urethane foaming device to produce rigid urethane foam. It is done by damaging.
(2). The method of forming embankment using polystyrene foam is carried out by transporting a large number of polystyrene foam blocks produced in advance to the embankment site and laminating the blocks at the embankment site.
However, in the method (1), the height of the rigid polyurethane foam that can be produced at one time by injection or spraying is limited, and an exothermic reaction is involved in the production of the rigid polyurethane foam. Since the rigid polyurethane foam is cured and cooled to some extent, the second injection or spraying is performed, so that the construction period becomes long.
In the method of (2), Japanese Patent Application Laid-Open No. 1-66316 describes embankments that ensure the integrity of lightweight blocks, but the height, width, and depth of each block are accurate as shown in the design drawings. And if the surface is not smooth, it seems that it is difficult to form a solid embankment.
[0003]
Production of blocks made of polystyrene foam is generally performed in factories for equipment reasons, and the dimensions of each block can be processed almost as per the design drawing, and it is possible to construct an embankment without wobble. . However, since it is lightweight, it is inevitable that the ratio of transportation cost to price will increase.
[0004]
In addition, it is conceivable to reduce transportation costs by preparing blocks using a hard urethane foam preparation stock solution generally used as a material for heat insulating materials such as buildings, and urethane foaming machines that are easy to transport. When foaming hard urethane in the field, it is difficult to smooth all six surfaces of the block and make the dimensions of each block the same because it is difficult to control the ambient temperature. There was a problem that there was.
[0005]
[Problems to be solved by the invention]
The present invention has been made to solve the above-mentioned problems, and provides a method for constructing a lightweight embankment that can reduce the construction period and can be integrated even when a block with various dimensions and no smoothness is used. is there.
[0006]
[Means for solving problems]
The construction method of the lightweight embankment of the present invention is a construction method of a lightweight embankment using a large number of blocks made of rigid urethane foam and a stock solution for producing rigid urethane foam, and the stock solution for producing rigid urethane foam mainly stacks blocks. Foam adhesive layer forming stock solution that adheres the upper and lower parts of the block, and a foam gap filling stock solution that foams and fills the gap formed between the block and the ground or between the block and the formwork. Before the stock solution is cured by injecting or spraying the adhesive layer forming stock solution, a large number of blocks are laid, and the lower part of the block is bonded and fixed by curing of the stock solution, and the foam gap filling stock solution is fixed to the block and the ground with the lower part fixed. Inject or spray into the gap formed between the block and the mold, and fix the side of the block by curing the stock solution, As next block laying position the top of the fixed block, and is characterized in that the repeating bonded and aspects of bonded and blocking a lower portion of the same block.
[0007]
Also, as the first layer process, a foaming gap filling stock solution is injected or sprayed on the ground to form a leveling layer by foaming and curing, and a foaming adhesive layer forming stock solution is injected or sprayed onto the leveling layer. Before the stock solution hardens, a number of blocks of the first layer are laid, and the lower part of the block is bonded and fixed by hardening of the stock solution, and the gap formed between the block to which the lower part is fixed and the ground or the block and the formwork If necessary, the foam gap filling stock solution is injected or sprayed to a position covering the upper part of the block, and the side surface of the block is bonded and fixed by curing the stock solution. Before the stock solution is cured by injecting or spraying a foam adhesive layer forming stock solution onto the block, a number of blocks in the second layer are laid, and the lower portion of the block is bonded and fixed by curing the stock solution, and the lower portion is secured. The foam gap filling stock solution is injected or sprayed into the gap formed between the block and the ground or the block and the formwork as needed to cover the top of the block, and the side of the block is bonded and fixed by curing the stock solution Then, the same process as the second layer is repeated, and a block made of rigid urethane foam is embedded in the rigid urethane foam to a desired height.
[0008]
In addition, the foamed adhesive layer forming stock solution is characterized in that it has a slower reactivity than the foaming gap filling stock solution.
[0009]
In the present invention, a gap is provided between the blocks laid at substantially the same height to form a strong embankment, and the side surfaces of the blocks are bonded and fixed, and a gap filling operation between the block and the ground or the block and the formwork is performed. It is preferable to fill the gap in parallel. The gap filling between the blocks can be either a foamed adhesive layer forming stock solution or a foaming gap filling stock solution, but the use of the foaming gap filling stock solution described below is preferred in order to speed up the work.
[0010]
Moreover, when forming a leveling layer on the ground, a drainage sheet can be laid between the ground and the leveling layer. In particular, when the ground is an inclined ground, it is preferable to provide a drainage sheet in order to drain groundwater that springs up from the mountain.
The drainage sheet is not particularly limited as long as it can drain, but a felt-like nonwoven fabric, a knitted fabric, a woven fabric, a double raschel or a sheet having a mesh-structured drainage pipe can be used.
[0011]
The stock solution for producing rigid urethane foam used in the present invention is used for the production of blocks, the formation of foamed adhesive layers, the formation of leveling layers, and the filling of gaps. It may be a thing, and consists of a polyol component and a polyisocyanate component. A rigid urethane foam is produced by mixing the two. A large number of blocks are firmly bonded and integrated by the self-adhesiveness of a rigid urethane foam produced by injection or the like afterwards or later.
[0012]
The foamed adhesive layer forming stock solution and the foam gap filling stock solution that are the stock solutions for producing rigid urethane foam may be the same, but the reactivity of the foamed adhesive layer forming stock solution is not limited to the above foaming in order to improve workability. It is preferably slower than the reactivity of the gap filling stock solution. That is, in order to improve the working speed, especially the formation of the leveling layer and the filling of the gap between the block and the ground, the block and the mold form, the working time is shortened by using a reactive solution, and foam bonding is performed. In forming the layer, it is preferable to use a stock solution having a low reactivity in order to secure a working time for adhesion between the lower part and the upper part of the block.
[0013]
The reactivity of the stock solution for producing rigid urethane foam can be easily performed by changing the amount of addition of a catalyst or the like. For example, two types of stock solutions with different reactivities may be prepared at the factory and transported to the site. A slow reacting stock solution is prepared at the factory and transported to the site, and the reaction is increased by increasing the amount of catalyst. It is also possible to produce a stock solution with high properties.
The reactivity of the foam gap filling stock solution is adjusted according to the situation at the site, but the rise time is usually preferably 15 to 20 seconds.
Although the reactivity of the foamed adhesive layer forming stock solution is also adjusted according to the situation at the site, a rise time of 120 to 180 seconds is preferable.
[0014]
The above-mentioned stock solution is transported in a drum can etc., pumped up to a rigid urethane foaming machine, etc., mixed and discharged, mixed with a block, formed a leveling layer, adhesively filled each gap, the top of the block and another block on it Used for bonding the lower part. In addition, since the foamed adhesive layer forming stock solution has low reactivity, it has a sufficient stirring time, and even if a foaming machine is not used, a polyol component and an isocyanate component are added to a plastic bag, etc., and then the two components are shaken. Can be mixed and stirred.
[0015]
The blocks used in the present invention can be made at and near the embankment site to reduce transportation costs. Also, depending on the situation of rain at the site, work can be carried out according to the work process determined by making blocks in another limited and narrow place even in rainy weather.
[0016]
In addition, it is preferable that the formwork in the case of producing a block on site is simple and light in weight so that it can be easily transported. In the field, it is difficult to keep the foaming ratio constant because it is difficult to accurately control the ambient temperature and the temperature of the stock solution. For this reason, if the mold is a sealed mold, the structure itself becomes complicated and excessive foaming pressure is applied to the mold, which may damage the mold if it is not a rigid mold, and as a result, the mold becomes heavy. An open top form with a simple structure and light weight is preferable. An example of a mold for making a block is shown in FIG.
However, the block obtained by using the mold with the upper part opened is not smooth as shown in FIG. The block size is not particularly limited, but is preferably 0.4 to 1.0 m in order to maintain the quality of the depth, width and height.
The present invention is characterized in that it is possible to construct an embankment with an integral rigid urethane foam even if the block dimensions are not accurate.
[0017]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below with reference to the drawings.
FIG. 1 shows an example of an embankment structure obtained by the method of constructing a lightweight embankment of the present invention on a steep slope. FIG. 2 shows an example of the embankment structure obtained by the light embankment construction method of the present invention on a substantially flat soft ground or the like. Note that the mold 8 'is necessary for forming a bank with hard urethane foam, and is disassembled after the bank is formed.
FIG. 3 is an explanatory diagram of the construction method of the lightweight embankment of the present invention. In FIG.
(A) Laying the
(B) Forming the
(C) Injecting or spraying a foamed adhesive layer forming stock solution on the
(D) Before the undiluted solution is cured, the
(E) After the leveling layer and the lower part of the block are integrated via the foamed adhesive layer, the gap between the lower fixed block and the block, and the block and the mold B (in FIG. 3, the mold B is a retaining wall) 8 or a foaming gap filling stock solution is injected or sprayed into the gap created between the ground and the ground. In the present embodiment, the foam gap filling stock solution is injected or sprayed to a position covering the top of the block to form the foam
(F) A foamed adhesive layer forming stock solution is again injected or sprayed on the foam gap filling layer or on the block, and the following (d) to (f) are repeatedly performed to construct a lightweight embankment.
The civil engineering structure is provided with the earth and
[0018]
【The invention's effect】
As described above, according to the construction method of the lightweight embankment of the present invention, since the block made of rigid urethane foam is integrally bonded and fixed by the same rigid urethane foam, the embankment is stronger than those of different materials. A structure is obtained.
Also, by laying the block before the foamed adhesive layer is cured, the block sinks into the foamed adhesive layer, so that the lower part of the block is fixed more firmly, while the side of the block is also filled with a gap later By injecting or spraying the stock solution to cause foaming, it can be easily filled with rigid urethane foam regardless of whether the gap between the block and the ground or between the blocks is wide or narrow.
Furthermore, the construction period can be shortened as compared with a method of injecting or spraying hard urethane foam at all embankment locations.
Moreover, even when using non-smooth blocks with mixed dimensions produced at the embankment site to reduce transportation costs, the same reason as above, that is, the lower part of the block sinks into the adhesive layer, and the gap formed on the side of the block Since it can be filled regardless of whether it is wide or narrow, there is no influence on the unevenness of the block size and the embankment strength of the irregularities on the block surface.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram of an example of a banking structure obtained by the present invention.
FIG. 2 is an explanatory diagram of an example of a banking structure obtained by the present invention.
FIG. 3 is an explanatory diagram of a method for constructing a lightweight embankment according to the present invention.
FIG. 4 is an explanatory view of a mold for producing a block used in an embodiment of the present invention. In the state as shown in (a), a stock solution for producing rigid urethane foam is injected or sprayed to produce a block, and the block is removed as shown in (b).
FIG. 5 is a cross-sectional view of an example of a block manufactured in an embodiment of the present invention when cut in half.
[Explanation of symbols]
DESCRIPTION OF
8 'Formwork B
11 Drainage pipe 12 Ground
Claims (3)
硬質ウレタンフォーム作成用原液は、主としてブロックを積み重ねる際のブロック上部と下部とを接着する発泡接着層形成原液と、主としてブロックと地盤やブロックと型枠との間にできる隙間を発泡充填する発泡隙間充填原液とからなり、
ブロック敷設箇所に、発泡接着層形成原液を注入又は吹付けて前記原液が硬化する前に多数のブロックを敷設し、前記原液の硬化によりブロック下部を接着固定し、
発泡隙間充填原液を、前記下部を固定したブロックと地盤やブロックと型枠との間にできた隙間に注入又は吹付け、前記原液の硬化によりブロックの側面を接着固定し、
下部と側面を固定したブロックの上部を次なるブロック敷設箇所として、上記と同様なブロックの下部の接着固定とブロックの側面の接着固定とを繰り返すことを特徴とする軽量盛土の構築方法。It is a construction method of a lightweight embankment using a large number of blocks made of rigid urethane foam and a stock solution for producing rigid urethane foam,
The stock solution for making rigid urethane foam is mainly a foam adhesive layer forming stock solution that adheres the upper and lower parts of the block when stacking the blocks, and a foam gap that mainly fills the gap between the block and the ground or between the block and the formwork. Consisting of a filling stock solution,
Before the stock solution is cured by injecting or spraying the foam adhesive layer forming stock solution to the block laying location, laying a large number of blocks, and adhesively fixing the lower part of the block by curing the stock solution,
Injecting or spraying the foam gap filling stock solution into the gap formed between the block and the ground or the block and the mold with the lower part fixed, and fixing the side surface of the block by curing the stock solution,
A method for constructing a lightweight embankment, characterized in that the upper part of a block with a fixed lower part and side faces is used as the next block laying place, and the same adhesive fixing of the lower part of the block and adhesive fixing of the side face of the block are repeated.
硬質ウレタンフォーム作成用原液は、主としてブロックを積み重ねる際のブロック上部とブロック下部とを接着する発泡接着層形成原液と、主としてブロックと地盤やブロックと型枠との間にできる隙間を発泡充填する発泡隙間充填原液とからなり、
第一層目の工程として、地盤上に発泡隙間充填原液を注入又は吹付け発泡及び硬化させることによりレベリング層を形成し、前記レベリング層上に、発泡接着層形成原液を注入又は吹付けて前記原液が硬化する前に第一層目のブロックを多数敷設し前記原液の硬化によりブロック下部を接着固定し、前記下部を固定したブロックと地盤やブロックと型枠との間にできた隙間に発泡隙間充填原液を注入又は吹付けて前記原液の硬化によりブロックの側面を接着固定し、
第二層目の工程として、前記第一層目のブロック上に発泡接着層形成原液を注入又は吹付けて前記原液が硬化する前に第二層目のブロックを多数敷設し前記原液の硬化によりブロック下部を接着固定し、前記下部を固定したブロックと地盤やブロックと型枠との間にできた隙間に発泡隙間充填原液又は発泡接着層形成原液を注入又は吹付けて前記原液の硬化によりブロックの側面を接着固定し、
以下第二層目と同様な行程を繰り返し、所望の高さまで硬質ウレタンフォームからなるブロックを、硬質ウレタンフォーム中に埋設することを特徴とする請求項1記載の軽量盛土の構築方法。It is a construction method of a lightweight embankment using a large number of blocks made of rigid urethane foam and a stock solution for producing rigid urethane foam,
The stock solution for making rigid urethane foam is mainly a foam adhesive layer forming stock solution that adheres the upper part of the block and the lower part of the block when the blocks are stacked, and a foam that mainly fills the gap between the block and the ground or between the block and the formwork. Consisting of gap filling stock solution,
As a first layer process, a foaming gap filling stock solution is injected or sprayed on the ground to form a leveling layer by foaming and curing, and a foamed adhesive layer forming stock solution is injected or sprayed onto the leveling layer to form the leveling layer. Before the stock solution hardens, lay many blocks of the first layer and fix the lower part of the block by curing the stock solution, and foam in the gap created between the block with the lower part and the ground or between the block and the formwork Injecting or spraying the gap filling stock solution to fix the side surface of the block by curing the stock solution,
As a process of the second layer, by injecting or spraying a foam adhesive layer forming stock solution on the first layer block and laying a number of blocks of the second layer before the stock solution is cured, by curing the stock solution The lower part of the block is bonded and fixed, and a foam gap filling stock solution or a foam adhesive layer forming stock solution is injected or sprayed into a gap formed between the block to which the lower part is fixed and the ground or the block and the mold, and the block is obtained by curing the stock solution. Adhering and fixing the sides of the
2. The method for constructing a lightweight embankment according to claim 1, wherein the same process as in the second layer is repeated, and a block made of rigid urethane foam is embedded in the rigid urethane foam to a desired height.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP32927099A JP3660177B2 (en) | 1999-11-19 | 1999-11-19 | Construction method of lightweight embankment |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP32927099A JP3660177B2 (en) | 1999-11-19 | 1999-11-19 | Construction method of lightweight embankment |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2001146748A JP2001146748A (en) | 2001-05-29 |
| JP3660177B2 true JP3660177B2 (en) | 2005-06-15 |
Family
ID=18219580
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP32927099A Expired - Fee Related JP3660177B2 (en) | 1999-11-19 | 1999-11-19 | Construction method of lightweight embankment |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3660177B2 (en) |
Families Citing this family (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006225926A (en) * | 2005-02-16 | 2006-08-31 | Tokura Construction Co Ltd | Banking construction method utilizing backfilling material such as fluidized soil, pit sand, local soil and crushed stone |
| KR101117354B1 (en) | 2009-07-01 | 2012-03-07 | 동서에코소일 주식회사 | Lightweight material mounding structure and method for constructing the same |
| KR101036039B1 (en) | 2010-10-18 | 2011-05-19 | (주)지오알앤디 | Construction of Embankment using Hollow Structure and Construction Method of Embankment Using It |
| JP5616804B2 (en) * | 2011-01-18 | 2014-10-29 | イノアック特材株式会社 | Lightweight embankment and lightweight embankment method |
| KR101199522B1 (en) | 2011-01-21 | 2012-11-09 | 박이근 | Shell structure for protecting ground subsidence thereby |
| JP6005473B2 (en) * | 2012-10-26 | 2016-10-12 | イノアック特材株式会社 | Method for laminating rigid foam |
| CN111636266B (en) * | 2020-07-06 | 2024-06-11 | 西安科技大学 | Expressway pile wall type composite roadbed and construction method thereof |
| JP7691153B1 (en) | 2024-01-25 | 2025-06-11 | Pcサポート株式会社 | How to build an embankment structure |
-
1999
- 1999-11-19 JP JP32927099A patent/JP3660177B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2001146748A (en) | 2001-05-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CA2443759C (en) | Foam pile system | |
| JP3660177B2 (en) | Construction method of lightweight embankment | |
| EP1002903B1 (en) | Base structure of building and construction method thereof | |
| JPH07252841A (en) | Reinforced earth structure | |
| JPH0849237A (en) | Slope face covering structure and mat | |
| JP4384321B2 (en) | Lightweight embankment structure | |
| JP2775693B2 (en) | Lightweight embankment method | |
| JP4283407B2 (en) | Construction method of lightweight embankment structure | |
| JP3458174B2 (en) | Construction method of reinforced soil retaining wall | |
| JP3247082B2 (en) | Lightweight embankment method | |
| JP4680426B2 (en) | Construction method of lightweight embankment structure | |
| JP2002030674A (en) | Polystyrene resin foam plate assembly, lightweight ground construction method, foundation construction method, and lightweight embankment construction method | |
| JPH0650466A (en) | Method of constructing underground culvert | |
| JP3217027B2 (en) | Lightweight embankment method | |
| KR20210115197A (en) | Concrete composite mat which is pattern backstitch for preventing damage of reinforcement member | |
| JPH11140859A (en) | Method for improving weak ground | |
| JPH08100427A (en) | Water-permeable lightweight block | |
| JP2020180489A (en) | Waterproof construction method for structure requiring waterproofing | |
| JP7695080B2 (en) | Composite structure and method for suppressing stone rolling | |
| JP2025042274A (en) | Slope structure and waste disposal site | |
| JP4148824B2 (en) | Lightweight embankment construction method | |
| JP3155456B2 (en) | Pile structure to be joined to floor slab connected to foam resin material, and construction method of pile structure | |
| KR20010095260A (en) | A block for recycling waste tire and the method for forming soil which utilize it | |
| JP3832804B2 (en) | Construction method using urethane foam mixed soil | |
| JP2003027484A (en) | Work method for lightweight embankment |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040601 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040608 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050315 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050316 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090325 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090325 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090325 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090325 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100325 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110325 Year of fee payment: 6 |
|
| LAPS | Cancellation because of no payment of annual fees |