Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP3760306B2 - Seismic isolation method - Google Patents
[go: Go Back, main page]

JP3760306B2 - Seismic isolation method - Google Patents

Seismic isolation method Download PDF

Info

Publication number
JP3760306B2
JP3760306B2 JP2000354146A JP2000354146A JP3760306B2 JP 3760306 B2 JP3760306 B2 JP 3760306B2 JP 2000354146 A JP2000354146 A JP 2000354146A JP 2000354146 A JP2000354146 A JP 2000354146A JP 3760306 B2 JP3760306 B2 JP 3760306B2
Authority
JP
Japan
Prior art keywords
seismic isolation
horizontal displacement
isolation device
existing building
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000354146A
Other languages
Japanese (ja)
Other versions
JP2002155641A (en
Inventor
和彦 前林
豊 斎藤
稔 秋山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2000354146A priority Critical patent/JP3760306B2/en
Publication of JP2002155641A publication Critical patent/JP2002155641A/en
Application granted granted Critical
Publication of JP3760306B2 publication Critical patent/JP3760306B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、既存建物を免震化するための免震化工法に関する。
【0002】
【従来の技術】
既存建物の耐震性能を向上させるために、積層ゴム等の免震装置を既存建物の基礎もしくは中間階に設置し、この設置した免震装置によってその上側部分を免震支持する免震化工法が行われている。
【0003】
ところで、上記免震化工法の一つとして、仮設材で既存建物の免震化しようとする部分全体を一時的に仮受けし、免震装置を設置した後ジャッキを用いて仮設材から免震装置に建物重量を移し換える方法が考えられている。
【0004】
【発明が解決しようとする課題】
しかしながら、上述の免震化工法にあっては、既存建物の免震化しようとする部分全体を仮設材で一旦支持するため、その間は、既存建物の免震装置を設置しようとする各柱の直下近傍に多くの仮設材を配置する必要があり、使用する仮設材の数量が多くなるという問題があった。
【0005】
また、特に、中間階以上を免震化する場合には、図10、図11に示すように、例えば免震装置100が設置される柱101と接続される梁102を支持するために、階高分の比較的長いサポート103が必要になる場合があり、しかもそのときのサポート103の数量が多くなり、かつ、サポート103を固定するための固定部材を含めた、サポート設置のための工事が大がかりになるという新たな問題が生じるおそれがあった。加えて、足場104もフロア全面に設置しなければならないという問題も生じるおそれがあった。
【0006】
また、仮受け時の地震対策として、既存建物の全重量に一定値(例えば、15パーセント)を乗じた水平力に抵抗するだけの仮設材を設置する必要があるが、この水平力抵抗のための仮設材は、建物周辺部数ヶ所にまとめて設置する場合が多く、このため、1箇所当たりの水平力抵抗のための仮設材が大がかりになるという問題もあった。
【0007】
本発明は、上記事情に鑑みてなされたもので、その目的とするところは、使用する仮設材の数量を減少でき、また、中間階以上を免震化する場合であっても、大がかりで多量のサポートを必要とせず、加えて、大規模な足場も不要となる免震化工法を提供することにある。
また、免震装置の設置工程中の地震対策として水平力抵抗のための大がかりな仮設材を不要とすることができる免震化工法を提供することも目的としている。
【0008】
【課題を解決するための手段】
前記課題を解決するため請求項1にかかる発明は、既存建物に免震装置を設置して免震化するための免震化工法であって、既存建物の複数本ある柱のうち所定本数の柱毎に、該柱が負担する既存建物の重量分を仮設材で受け、該柱を切断するとともにその切断箇所に免震装置を設置し、その後設置した免震装置に前記柱が負担する既存建物の重量分を前記仮設材から移し換えて該仮設材を撤去する作業を繰り返し行うことにより、前記複数本の柱全てに対して免震装置を順次設置するとともに前記仮設材を順次撤去していき、しかも、それら柱全てに対して免震装置を順次設置していきかつ仮設材を順次撤去していく工程中には、既存建物の重量分を仮設材から各免震装置に移し換えるに先立って、各免震装置の周囲にそれぞれ個別水平変位拘束手段を順次設置していくことにより、該個別水平変位拘束手段によって、既存建物の免震装置を設置する箇所より上側の部分の水平変位を拘束することを特徴としている。
請求項2にかかる発明は、請求項1にかかる発明において、前記個別水平変位拘束手段として、柱の切断部の上下にそれぞれ固定されて個々の免震装置の上下にそれぞれ設置されている取付板部の相対的な水平変位を拘束する個別水平変位拘束ユニットを用いるとともに、該個別水平変位拘束ユニットは、上下の取付板部にまたがって係合する一対の台座と、それら台座どうしを所定荷重で互いに近づくように引っ張る緊張棒材とにより構成され、該個別水平変位拘束ユニットを、それらの軸線が互いに直交する2方向を指向する状態で各免震装置を取り囲むようにしてその周囲に複数組配置することを特徴としている。
【0009】
本発明によれば、既存建物の所定本数の柱毎に、既存建物の垂直荷重を仮設材で支えながら柱を切断して免震装置を設置しつつ、その設置した免震装置に荷重を移し換えて仮設材を速やかに撤去していく作業を繰り返し行うことにより、全ての免震装置を設置するのと同時に既存建物の重量の移し換えを完了する。
また、順次撤去した垂直荷重用の仮設材を繰り返し使用できるので、その使用量は従来の工法に比べて大幅に減少する。
【0010】
また、上述のように、設置した免震装置に荷重を順次移し換えて仮設材を速やかに撤去していくことにより、全ての免震装置を設置するのと同時に既存建物の重量の移し換えが完了するので、従来別途行っていた、免震設置後のジャッキを用いた仮設材から免震装置への建物全体の重量を一括して移し換える工程が不要になり、その分工期が短縮する。
また、建物全体のバランスを考慮しながら、例えば既存建物の左右両側の2方あるいは前後左右の4方等の複数箇所から同時に免震装置の設置工事を進めることができ、この点においても工期の短縮が図れる。
【0011】
しかも、各免震装置のそれぞれに対してその周囲に個別水平変位拘束手段を順次設置していくので、建物周辺部に地震時の水平力抵抗のための大がかりな仮設材を設置する必要がなく、スペースが節約できる。なお、個別水平変位拘束手段としては、一対の台座を緊張棒材により緊張することで免震装置の上下の取付板部の相対的な水平変位を拘束する構成の個別水平拘束ユニットを採用して、それを各免震装置を取り囲むようにしてその周囲に水平2方向を指向するように設置することが好ましい。
【0012】
【発明の実施の形態】
以下、図面に基づいて本発明の免震化工法の実施の形態を説明する。
図1〜図9は本発明の実施の形態を示すものであって、図1は既存建物の免震装置を設置する部分を示す横断面図、図2〜図5は、免震装置の具体的な設置方法を説明する断面図、図6は免震装置の上下の取付板部の相対的な水平変位を拘束する個別水平変位拘束手段を説明する側面図、図7は同個別水平変位拘束手段を説明する平面図、図8は個別水平拘束手段の他の例を示す側面図、図9は個別水平変位拘束手段のさらに他の例を示す側面図である。
【0013】
図1において符号1は既存建物を示し、この既存建物1の複数本ある柱2にそれぞれ積層ゴム等の免震装置3を設置する(図4、5参照)。免震装置3が設置する柱は、既存建物1の基礎部分でもあるいは中間階でもいずれであってもよい。
本発明の免震化工法の最も大きな特徴は、柱の荷重を仮設材4で受けて柱2に加わる荷重をゼロとして免震装置3を設置し、その後荷重を仮設材4から免震装置に移し換えて仮設材4を取り除く作業を、既存建物1の複数本ある柱2のうち所定本数の柱2毎に繰り返し行うことにある。
【0014】
すなわち、本発明の免震化工法では、既存建物1の複数本ある柱2のうち所定本数の柱2毎に、該柱2が負担する既存建物1の重量分のみを仮設材4で受け、該柱2を切断するとともにその切断箇所に免震装置3を設置し、その後設置した免震装置3に前記柱2が負担する既存建物1の重量分を前記仮設材4から移し換えて該仮設材4を取り除く作業を繰り返し行いながら、前記複数本の柱2全てに対して免震装置3を設置する点に最も大きな特徴がある。
【0015】
既存建物1への免震装置3の設置方法は、この実施の形態の場合、施工中に発生する地震等を考慮し、既存建物1の左右両側からバランス良く免震装置3を設置していく。図1は既存建物1の全体のうち略左半分しか示していないが、実際にはこの図1で示す右方向にも建物は延びている。そして、この図において、符号Aー1、Bー1(図示略)、…Aーn、Bーn、…(nは16以下の整数)はそれぞれ柱2の番号を示しており、これらの柱2の番号順に、建物の左右両側から2本の柱2毎に免震装置3を設置していく。
なお、同時に免震装置3を設置する柱の本数は、2本に限られることなく、1本毎、あるいは3本毎または4本毎でも良く、その本数は既存建物1の規模や設置されている柱2の本数等によって決定する。
【0016】
柱2への免震装置3の具体的な設置方法について説明すると、例えば、柱2(Aー7)に免震装置3を設置するには、まず、柱2(Aー7)と接続される前後左右の大梁6とその下側の小梁7との間に仮設材4としてジャッキ4aを取り付ける(図1、図2参照)。そして、これら取り付けられたジャッキ4aに柱2(Aー7)が負担する既存建物1の重量分を受けさせる。ジャッキ4aの本数はこの図では4本としているが、これに限られることなく、ジャッキ4aが受けもつ荷重が少ない場合には、例えば3本であってもあるいは2本であってもよい。
【0017】
次に、柱2の一部分であって免震装置3を設置しようとする部分を切り取る(図3参照)。柱2(Aー7)の切り取った端部である、切断下端部8および切断上端部9にそれぞれベースプレート10(取付板部)を溶接等の適宜固定手段で取り付ける。ベースプレート10は、柱の端部に直接取り付けてもよいが、図4に示すようにアンカー6aを介して大梁6あるいは小梁7に固定して取り付けてもよい。そして、これら上下のベースプレート10間に免震装置3を設置して固定する。
【0018】
次に、柱2(Aー7)の端部とベースプレート10との間の隙間に無収縮モルタル等のグラウト材を注入する。この注入したグラウト材が固化し十分な強度を発揮するようなった時点で、ジャッキダウンし、ジャッキ4aから設置した免震装置3へ、柱2(Aー7)が負担する既存建物1の重量分を移し換える。その後、ジャッキ4aを取り除く。
以上のジャッキセット→柱切断→ベースプレート取付→免震装置の設置→グラウト材注入→ジャッキ撤去といった一連の作業を、仮設材4であるジャッキ4aを移動させながら所定数の柱2毎に繰り返し行い、既存建物1の複数本ある柱2全てに対して免震装置3を設置する。
【0019】
なお、上記ジャッキセットからジャッキ撤去までの間は、複数日(例えば、4日程度)要し、その間は柱2が切断された状態となっていて、ジャッキ4aによる支持では主に該柱2に加わる鉛直荷重しか受けもたない。このため、施工中の柱2は水平方向の抵抗力をほとんど有しないこととなる。したがって、施工時の水平荷重に対する安全性を考慮し、柱2の同時切断本数は所定本数(例えば4本)以下に保つものとする。
【0020】
この実施の形態では、既存建物1の左右からそれぞれ1本ずつ合計2本ずつの柱2毎に免震装置3の設置工事を進めることとしているが、片側から進める柱2の切断状態が重なるオーバーラップ本数は2本までとする。つまり、建物の左側の柱2を例に挙げて説明すれば、免震装置3の設置工事開始時期を2日ずらして施工する場合には、前述したようにジャッキセットからジャッキ撤去までの間は4日程度要するので、柱2(Aー1)と柱2(Aー2)、あるいは柱2(Aー2)と柱2(Aー3)というように2本の柱2が同時に切断状態になり、なんら支障は生じないが、免震装置3の設置工事開始時期を1日しかずらさない場合には、例えば柱2(Aー1)と柱2(Aー2)と柱2(Aー3)と柱2(Aー4)の合計4本の柱が同時に切断状態となるため、好ましくない。このような事態を避けるため、柱2の同時切断本数は所定本数(例えば4本)以下に保つものとする。
【0021】
ところで、上述のように複数ある柱2に対し免震装置3を順に設置するが、ある程度の数設置が完了した時点で例えば地震が発生すると、未だ施工していない柱2へ水平力が集中することとなり、未施工柱2を損傷しかねない。
このため、免震装置3の全ての柱2への設置が完了するまでは、水平変位拘束手段12によって、既存建物1の免震装置3を設置する箇所より上側の部分の水平変位を拘束する。
【0022】
水平変位拘束手段12としては、個々の免震装置3に対し該免震装置3の免震部3aを挟んだ上下のベースプレート10の相対的な水平変位を拘束する個別水平変位拘束手段12A(図5〜図7、図8、図9参照)を用いる。
【0023】
図5〜図7は個別水平変位拘束手段12Aの例を示している。すなわち、この例では、上側のベースプレート10と下側のベースプレート10との間に、またがってそれらに係合する台座14が一対互いに離間して設けられ、それら対をなす台座14がPC鋼材等からなる緊張棒材15によって所定荷重で互いに近づくように引っ張られる構造になっている。
さらに、この例では、前記一対の台座14並びに前記緊張棒材15からなる個別水平変位拘束ユニット16がそれらの軸線を水平面に沿う互いに直交するX、Y方向に指向して2組、合計一つの柱2に4組配置されている(図7参照)。
【0024】
そして、この個別水平変位拘束手段12Aによれば、対をなす台座14が緊張棒材15によって互いに引っ張られており、このため、これら対をなす台座14は、下側のベースプレート10を両側から強く挟み込むことで、下側のベースプレート10に固定される一方、該台座14は上側のベースプレート10を両側から強く挟み込んでおり、これにより、上側ベースプレート10の緊張棒材15の長手方向に沿った変位を拘束している。この結果、個別水平拘束ユニット16は、上下のベースプレート10の緊張棒材15の長手方向に沿う相対的な水平変位を拘束できる。また、個別水平拘束ユニット16は、水平面に沿う互いに直交するX、Y方向に指向して配置されており、したがって、上下のベースプレート10はあらゆる方向の相対的な水平変位を拘束されることとなる。
【0025】
個別水平変位拘束手段12Aは、必ずしも図5〜図7に示すものに限られることなく、他の構造のものを用いてもよく、要は、個々の免震装置3に対し免震装置3の上下に配されるベースプレート10の相対的な水平変位を拘束する構造であればよい。
例えば、図8に示すものは、免震装置3が設置される柱2に接続される大梁6と小梁7の間にそれぞれ上下にH形鋼18が取り付けられ、これら上下のH形鋼18に鋼板19が固定的に取り付けられた構造になっている。
また、図9に示すものは、同大梁6と小梁7の間にそれぞれ溝形鋼20が取り付けられ、これら上下の溝型鋼20に複数の鋼板21が固定的に取り付けられた構造になっている。
このような構造では、個別水平変位拘束手段12Aを構成する部材が、直接ベースプレート10に接触することなく、大梁6および小梁7を介して上下のベースプレートの水平変位を拘束しているが、このような構成であってもよく、要は、免震装置3の上下に配されるベースプレート10の相対的な水平変位を拘束すればよい。
【0026】
上述のような個別水平変位拘束手段12Aが免震装置3に組み付けられる時期は、前記柱2に免震装置3が取り付けられ、柱2の端部とベースプレート10との間の隙間に注入されるグラウト材が硬化した後であって、ジャッキ4aから免震装置3へ既存建物1の重量分が移し換えられる前である。
【0029】
上述した免震装置3の柱2への取付手順Aー1,Bー1→Aー2,Bー2→Aー3,Bー3→……は、事前に十分な応力解析を行った上で決定し、施工中は所要箇所に監視用カメラ等を設置し、既存建物1の挙動を24時間監視する体制とするのが好ましい。
【0030】
次の、上記の構成の免震化工法の作用について説明する。
上述の免震化工法によれば、既存建物1の所定本数の柱2毎に、該柱2が負担する既存建物1の重量分をジャッキ4a等の仮設材4で支え、この状態で免震装置3を柱2の切断部分に設置する作業を、仮設材4を移動しながら繰り返し行い、これにより、全ての柱2に対して免震装置3を設置する工法であり、このように垂直荷重用の仮設材4を繰り返し使用できるので、これら仮設材4の使用量は従来考えられている工法にに比べて大幅に減少する。
【0031】
また、全ての免震装置3を設置するのと同時に既存建物1の重量の免震装置3への移し換えが完了するので、従来別途行っていた、免震設置後のジャッキを用いた仮設材から免震装置3への建物重量の移し換え工程が不要になり、その分工期が短縮する。
また、建物全体のバランスを考慮しながら、例えば既存建物1の左右両側の2方あるいは前後左右の4方等の複数箇所から同時に免震装置3の設置工事を進めることができ、この点においても工期の短縮が図れる。
【0032】
また、たとえ、施工途中に地震が発生しても、水平変位拘束手段12によって既存建物1の免震装置3が設置する個所より上側の部分の水平変位を拘束しているので、未施工柱2に水平力が集中して、未施工柱2を損傷するといった事態を回避できる。
【0033】
さらに、水平変位拘束手段12として、個々の免震装置3に対し上下のベースプレート10の相対的な水平変位を拘束する個別水平拘束手段12A、特に一対の台座14を上下のベースプレート10に係合させて緊張棒材15によって緊張する構成の個別水平変位拘束ユニット16を採用し、それを免震装置を取り囲むようにしてその周囲に水平2方向を向くように設置することにより、施工中の水平変位を有効に拘束できることはもとより、建物周辺部に地震時の水平力抵抗のための大がかりな仮設材や免震ピット等を設置する必要がなくなり、スペースが節約でき、かつコストも低減できる。
【0034】
なお、上記実施の形態では、長方形状の既存建物1を免震化する場合を例に挙げて説明したが、勿論、断面正方形状の既存建物であってもあるいは断面円形の既存建物であっても勿論免震化できるのは言うまでもない。
また、免震化に用いる免震装置についても積層ゴムに限られることなく、他の構成の免震装置を用いてもかまわない。
【0035】
【発明の効果】
請求項1にかかる発明によれば、既存建物の所定本数の柱毎に、該柱が負担する既存建物の重量分をジャッキ等の仮設材で支え、この状態で免震装置を柱の切断部分に設置する作業を、仮設材を移動しながら繰り返し行い、これにより、全ての柱に対して免震装置を設置する工法であり、垂直荷重用の仮設材を繰り返し使用できるので、これら仮設材の使用量を、従来考えられていた工法に比べて大幅に減少することができる。
【0036】
また、全ての免震装置を設置するのと同時に既存建物の重量の免震装置への移し換えが完了するので、従来別途行っていた、免震設置後のジャッキを用いた仮設材から免震装置への建物重量の移し換え工程が不要になり、その分工期が短縮する。
建物全体のバランスを考慮しながら、例えば既存建物の左右両側の2方あるいは前後左右の4方等の複数箇所から同時に免震装置の設置工事を進めることができ、この点においても工期の短縮が図れる。
また、中間階以上を免震化する場合でも、大がかりで多量のサポートを必要とせず、また、足場も移動しながら使用できるので、ごく小規模の足場があれば足りる。
【0037】
しかも、免震装置の設置工程中においては個々の免震装置の周囲にそれぞれ個別水平変位拘束手段を順次設置していくので、施工中の水平変位を有効に拘束できることはもとより、建物周辺部に地震時の水平力抵抗のための大がかりな仮設材や免震ピット等を設置する必要がなくなり、スペースが節約でき、かつコストも大幅に低減できる。
【0038】
請求項2にかかる発明によれば、個別水平変位拘束手段として、一対の台座を緊張棒材により緊張することで免震装置の上下の取付板部の相対的な水平変位を拘束する構成の個別水平拘束ユニットを採用し、それを各免震装置を取り囲むようにしてその周囲に水平2方向を指向するように設置することにより、上下の取付板部のあらゆる方向の相対的な水平変位を有効に拘束することができる。
【図面の簡単な説明】
【図1】 本発明の免震化工法の実施の形態を示すもので、既存建物の免震装置を設置する部分を表す横断面図である。
【図2】 本発明の免震化工法の実施の形態を示すもので、免震装置の具体的な設置工程を説明する断面図である。
【図3】 本発明の免震化工法の実施の形態を示すもので、免震装置の具体的な設置工程を説明する断面図である。
【図4】 本発明の免震化工法の実施の形態を示すもので、免震装置の具体的な設置工程を説明する断面図である。
【図5】 本発明の免震化工法の実施の形態を示すもので、免震装置の具体的な設置工程を説明する断面図である。
【図6】 本発明の免震化工法の実施の形態を示すもので、個別水平変位拘束手段を説明する側面図である。
【図7】 本発明の免震化工法の実施の形態を示すもので、免震装置の具体的な設置工程を説明する平面図である。
【図8】 本発明の免震化工法の実施の形態を示すもので、個別水平拘束手段の他の例を示す側面図である。
【図9】 本発明の免震化工法の実施の形態を示すもので、個別水平変位拘束手段のさらに他の例を示す側面図である。
【図10】 従来の免震化工法を示す建物全体の側面図である。
【図11】 図10のX円部の拡大図である。
【符号の説明】
1 既存建物
2 柱
3 免震装置
4 仮設材
4a ジャッキ
6 大梁
7 小梁
10 ベースプレート(取付板部)
12 水平変位拘束手段
12A 個別水平変位拘束手段
14 台座
15 緊張棒材
16 個別水平変位拘束ユニット
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a seismic isolation method for isolating existing buildings.
[0002]
[Prior art]
In order to improve the seismic performance of existing buildings, there is a seismic isolation method in which seismic isolation devices such as laminated rubber are installed on the foundations or intermediate floors of existing buildings, and the upper part is seismically isolated by this installed seismic isolation device. Has been done.
[0003]
By the way, as one of the above seismic isolation methods, the entire part of the existing building that is going to be seismic isolated temporarily is temporarily installed with temporary materials, and after the seismic isolation device is installed, the jack is used to isolate the temporary building from the temporary materials. A method of transferring the building weight to the device is considered.
[0004]
[Problems to be solved by the invention]
However, in the above-mentioned seismic isolation method, the entire part of the existing building to be seismically isolated is temporarily supported by temporary materials. There is a problem that a lot of temporary materials need to be arranged in the immediate vicinity, and the number of temporary materials to be used increases.
[0005]
In particular, in the case of seismic isolation of the intermediate floor and above, as shown in FIGS. 10 and 11 , for example, in order to support the beam 102 connected to the column 101 on which the seismic isolation device 100 is installed, In some cases, a relatively long support 103 may be required, and the number of supports 103 at that time increases, and a work for installing the support including a fixing member for fixing the support 103 is required. There was a possibility that a new problem of large scale would arise. In addition, there is a possibility that the scaffold 104 must be installed on the entire floor.
[0006]
In addition, as a countermeasure against earthquakes at the time of temporary reception, it is necessary to install temporary materials that can resist the horizontal force obtained by multiplying the total weight of the existing building by a certain value (for example, 15 percent). In many cases, these temporary materials are installed together in several places around the building, and there is also a problem that the temporary materials for horizontal force resistance per location become large.
[0007]
The present invention has been made in view of the above circumstances, and the object of the present invention is to reduce the number of temporary materials to be used, and even in the case of seismic isolation of intermediate floors or more, it is a large and large amount. The purpose of this is to provide a seismic isolation method that does not require large-scale support and does not require a large-scale scaffolding.
Another object of the present invention is to provide a seismic isolation method that can eliminate the need for large temporary materials for horizontal force resistance as a measure against earthquakes during the installation process of the seismic isolation device.
[0008]
[Means for Solving the Problems]
In order to solve the above-mentioned problem, the invention according to claim 1 is a seismic isolation method for seismic isolation by installing a seismic isolation device in an existing building, and a predetermined number of columns among a plurality of pillars of the existing building. For each pillar, the weight of the existing building borne by the pillar is received by a temporary material, the pillar is cut and a seismic isolation device is installed at the cut location, and the existing pillar is borne by the installed seismic isolation device By repeating the work of transferring the weight of the building from the temporary material and removing the temporary material, seismic isolation devices are sequentially installed on all of the plurality of pillars and the temporary material is sequentially removed. In addition, during the process of installing seismic isolation devices sequentially for all of these pillars and removing temporary materials, the weight of the existing building will be transferred from the temporary materials to each seismic isolation device. prior to each individual horizontal displacement around each isolator By sequentially installed bundle means, by the individual by horizontal displacement restraining means, it is characterized in that to restrain the horizontal displacement of the upper portion than places to install a seismic isolation device of an existing building.
According to a second aspect of the present invention, there is provided the mounting plate according to the first aspect of the invention, wherein the individual horizontal displacement restraining means is fixed above and below the column cutting portion and is respectively installed above and below each seismic isolation device. The individual horizontal displacement restraining unit restrains the relative horizontal displacement of the parts, and the individual horizontal displacement restraining unit includes a pair of pedestals engaged across the upper and lower mounting plate parts, and the pedestals with a predetermined load. A plurality of sets of individual horizontal displacement restraining units are arranged around each seismic isolation device so that the axes are oriented in two directions orthogonal to each other. It is characterized by doing.
[0009]
According to the present invention, for each predetermined number of pillars in an existing building, while the vertical load of the existing building is supported by temporary materials, the pillar is cut and the seismic isolation device is installed, and the load is transferred to the installed seismic isolation device. In addition, by repeating the work of quickly removing the temporary material, all the seismic isolation devices are installed, and at the same time, the transfer of the weight of the existing building is completed.
Moreover, since the temporary materials for vertical loads that have been sequentially removed can be used repeatedly, the amount used is greatly reduced as compared with the conventional construction method.
[0010]
In addition, as described above, the weight of the existing building can be transferred simultaneously with the installation of all the seismic isolation devices by transferring the load to the seismic isolation devices installed and removing the temporary materials promptly. Since it is completed, the process of transferring the entire weight of the entire building from the temporary material to the seismic isolation device using the jack after the seismic isolation has been eliminated, and the construction period is shortened accordingly.
In addition, considering the balance of the entire building, it is possible to proceed with the installation of seismic isolation devices simultaneously from multiple locations such as two sides on the left and right sides of the existing building or four sides on the front and rear sides. It can be shortened.
[0011]
Moreover, since individual horizontal displacement restraining means are sequentially installed around each seismic isolation device, there is no need to install a large temporary material for horizontal force resistance at the time of the earthquake. Save space. As the individual horizontal displacement restraint means, an individual horizontal restraint unit configured to restrain the relative horizontal displacement of the upper and lower mounting plate parts of the seismic isolation device by tensioning a pair of pedestals with a tension bar is adopted. It is preferable to install each of the seismic isolation devices so that they are oriented in two horizontal directions.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the seismic isolation method of the present invention will be described with reference to the drawings.
1 to 9 show an embodiment of the present invention. FIG. 1 is a cross-sectional view showing a part of an existing building where a seismic isolation device is installed, and FIGS. 2 to 5 are specific examples of the seismic isolation device. FIG. 6 is a side view for explaining the individual horizontal displacement restraining means for restraining the relative horizontal displacement of the upper and lower mounting plate portions of the seismic isolation device, and FIG. FIG. 8 is a side view showing another example of the individual horizontal restraint means, and FIG. 9 is a side view showing still another example of the individual horizontal displacement restraint means .
[0013]
In FIG. 1, reference numeral 1 denotes an existing building, and seismic isolation devices 3 such as laminated rubber are respectively installed on a plurality of pillars 2 of the existing building 1 (see FIGS. 4 and 5). The pillar installed by the seismic isolation device 3 may be either the base portion of the existing building 1 or an intermediate floor.
The most significant feature of the seismic isolation method of the present invention is that the seismic isolation device 3 is installed with the column load received by the temporary material 4 and the load applied to the column 2 being zero, and then the load is transferred from the temporary material 4 to the seismic isolation device. The task of transferring and removing the temporary material 4 is to be repeated for each of a predetermined number of pillars 2 among the plurality of pillars 2 of the existing building 1.
[0014]
That is, in the seismic isolation method of the present invention, for each predetermined number of pillars 2 out of a plurality of pillars 2 of the existing building 1, only the weight of the existing building 1 borne by the pillar 2 is received by the temporary material 4, The base 2 is cut and a seismic isolation device 3 is installed at the cut location, and then the weight of the existing building 1 borne by the pillar 2 is transferred from the temporary material 4 to the seismic isolation device 3 installed thereafter. The greatest feature is that the seismic isolation device 3 is installed on all of the plurality of pillars 2 while the work of removing the material 4 is repeated.
[0015]
In the case of this embodiment, the method of installing the seismic isolation device 3 in the existing building 1 is to install the seismic isolation device 3 in a well-balanced manner from both the left and right sides of the existing building 1 in consideration of earthquakes that occur during construction. . FIG. 1 shows only approximately the left half of the entire existing building 1, but the building actually extends in the right direction shown in FIG. In this figure, symbols A-1, B-1 (not shown),..., An, Bn,... (N is an integer of 16 or less) indicate the numbers of the pillars 2, respectively. The seismic isolation device 3 is installed for each of the two pillars 2 from the left and right sides of the building in the order of the numbers of the pillars 2.
The number of pillars for installing the seismic isolation device 3 at the same time is not limited to two, and may be every one, every three, or every four. It is determined by the number of pillars 2 that are present.
[0016]
The specific installation method of the seismic isolation device 3 on the pillar 2 will be described. For example, in order to install the seismic isolation device 3 on the pillar 2 (A-7), first, the pillar 2 (A-7) is connected. A jack 4a is attached as a temporary member 4 between the front and rear left and right large beams 6 and the lower beam 7 below (see FIGS. 1 and 2). And the weight of the existing building 1 which the pillar 2 (A-7) bears to the attached jack 4a is received. The number of the jacks 4a is four in this figure, but is not limited to this, and may be three or two, for example, when the load that the jack 4a bears is small.
[0017]
Next, a part of the pillar 2 where the seismic isolation device 3 is to be installed is cut out (see FIG. 3). A base plate 10 (attachment plate portion) is attached to the lower end portion 8 and the upper end portion 9 that are the cut ends of the column 2 (A-7) by appropriate fixing means such as welding. The base plate 10 may be directly attached to the end of the column, but may be fixedly attached to the large beam 6 or the small beam 7 via the anchor 6a as shown in FIG. Then, the seismic isolation device 3 is installed and fixed between the upper and lower base plates 10.
[0018]
Next, a grout material such as non-shrink mortar is injected into the gap between the end of the column 2 (A-7) and the base plate 10. The weight of the existing building 1 that the pillar 2 (A-7) bears from the jack 4a to the seismic isolation device 3 when the injected grout material solidifies and exhibits sufficient strength. Change minutes. Thereafter, the jack 4a is removed.
A series of operations such as the above jack setting → column cutting → base plate mounting → seismic isolation device installation → grouting material injection → jack removal is repeated for each predetermined number of columns 2 while moving the jack 4a which is the temporary material 4. The seismic isolation device 3 is installed for all the pillars 2 of the existing building 1.
[0019]
In addition, it takes a plurality of days (for example, about 4 days) from the jack set to the jack removal, and during that time, the pillar 2 is in a state of being cut, and in the support by the jack 4a, the pillar 2 is mainly used. It only receives the applied vertical load. For this reason, the pillar 2 under construction has almost no resistance in the horizontal direction. Therefore, in consideration of safety against horizontal load during construction, the number of columns 2 that are simultaneously cut shall be kept below a predetermined number (for example, four).
[0020]
In this embodiment, the installation work of the seismic isolation device 3 is advanced for each of the two pillars 2 in total, one from each of the left and right sides of the existing building 1, but the cutting state of the pillars 2 advanced from one side overlaps. The number of laps is limited to two. In other words, taking the pillar 2 on the left side of the building as an example, when the construction start time of the seismic isolation device 3 is shifted by two days, as described above, the period from the jack set to the jack removal is Since it takes about 4 days, two pillars 2 are cut simultaneously, such as pillar 2 (A-1) and pillar 2 (A-2), or pillar 2 (A-2) and pillar 2 (A-3). However, in the case where the installation work start time of the seismic isolation device 3 is shifted only one day, for example, pillar 2 (A-1), pillar 2 (A-2) and pillar 2 (A Since a total of four columns of −3) and column 2 (A-4) are simultaneously cut, it is not preferable. In order to avoid such a situation, it is assumed that the number of pillars 2 that are simultaneously cut is kept below a predetermined number (for example, four).
[0021]
By the way, as described above, the seismic isolation devices 3 are sequentially installed on the plurality of pillars 2. When a certain number of installations are completed, for example, when an earthquake occurs, horizontal force concentrates on the pillars 2 that have not yet been constructed. As a result, the unconstructed pillar 2 may be damaged.
For this reason, until the installation to all the pillars 2 of the seismic isolation device 3 is completed, the horizontal displacement restraining means 12 restrains the horizontal displacement of the portion above the location where the seismic isolation device 3 of the existing building 1 is installed. .
[0022]
As the horizontal displacement restraining means 12, individual horizontal displacement restraining means 12A for restraining the relative horizontal displacement of the upper and lower base plates 10 sandwiching the seismic isolation part 3a of the seismic isolation device 3 with respect to each seismic isolation device 3 (FIG. 5-7, 8 and 9) .
[0023]
5 to 7 show examples of the individual horizontal displacement restraining means 12A. In other words, in this example, a pair of pedestals 14 that engage with the base plate 10 is provided between the upper base plate 10 and the lower base plate 10 so as to be spaced apart from each other, and the pedestals 14 that form the pair are made of PC steel or the like. The tension bar 15 is pulled so as to approach each other with a predetermined load.
Further, in this example, the individual horizontal displacement restraining unit 16 composed of the pair of bases 14 and the tension bar 15 is oriented in the X and Y directions perpendicular to each other along the horizontal plane, and two sets in total. Four sets are arranged on the pillar 2 (see FIG. 7).
[0024]
According to the individual horizontal displacement restraining means 12A, the pair of pedestals 14 are pulled together by the tension bar 15, so that the pair of pedestals 14 strongly press the lower base plate 10 from both sides. While being fixed to the lower base plate 10 by being sandwiched, the pedestal 14 strongly sandwiches the upper base plate 10 from both sides, so that the displacement of the upper base plate 10 along the longitudinal direction of the tension bar 15 is reduced. Restrained. As a result, the individual horizontal restraint unit 16 can restrain the relative horizontal displacement along the longitudinal direction of the tension bar 15 of the upper and lower base plates 10. Further, the individual horizontal restraint units 16 are arranged in the X and Y directions orthogonal to each other along the horizontal plane. Therefore, the upper and lower base plates 10 are restrained from relative horizontal displacement in any direction. .
[0025]
The individual horizontal displacement restraining means 12 </ b> A is not necessarily limited to that shown in FIGS. 5 to 7, and other structures may be used. In short, the seismic isolation device 3 is different from the individual seismic isolation device 3. Any structure that restrains the relative horizontal displacement of the base plates 10 disposed above and below may be used.
For example, what is shown in FIG. 8 is that H-shaped steels 18 are vertically attached between the large beam 6 and the small beam 7 connected to the column 2 on which the seismic isolation device 3 is installed. The steel plate 19 is fixedly attached to the structure.
Further, the structure shown in FIG. 9 has a structure in which a grooved steel 20 is attached between the large beam 6 and the small beam 7 and a plurality of steel plates 21 are fixedly attached to the upper and lower grooved steels 20. Yes.
In such a structure, the members constituting the individual horizontal displacement restraining means 12A restrain the horizontal displacement of the upper and lower base plates via the large beam 6 and the small beam 7 without directly contacting the base plate 10. What is necessary is just to restrain the relative horizontal displacement of the baseplate 10 distribute | arranged to the upper and lower sides of the seismic isolation apparatus 3 in short.
[0026]
When the individual horizontal displacement restraining means 12A as described above is assembled to the seismic isolation device 3, the seismic isolation device 3 is attached to the column 2 and injected into the gap between the end of the column 2 and the base plate 10. This is after the grout material has hardened and before the weight of the existing building 1 is transferred from the jack 4a to the seismic isolation device 3.
[0029]
The installation procedure A-1, B-1 → A-2, B-2 → A-3, B-3 → …… of the seismic isolation device 3 described above was subjected to sufficient stress analysis in advance. It is preferable to set a system for monitoring the behavior of the existing building 1 for 24 hours by installing a monitoring camera or the like at a required location during the construction.
[0030]
Next, the operation of the seismic isolation method having the above configuration will be described.
According to the above-mentioned seismic isolation method, for each predetermined number of pillars 2 of the existing building 1, the weight of the existing building 1 borne by the pillar 2 is supported by the temporary material 4 such as the jack 4a, and the seismic isolation is performed in this state. This is a method of installing the seismic isolation device 3 for all the pillars 2 by repeatedly performing the work of installing the device 3 on the cut portion of the pillar 2 while moving the temporary material 4, and thus the vertical load. Since the temporary material 4 for use can be used repeatedly, the amount of the temporary material 4 used is greatly reduced as compared with a conventionally considered method.
[0031]
Moreover, since the transfer of the weight of the existing building 1 to the seismic isolation device 3 is completed at the same time that all the seismic isolation devices 3 are installed, temporary materials using jacks after the seismic isolation installation, which has been conventionally performed separately This eliminates the need to transfer the building weight from the seismic isolation device 3 to the seismic isolation device 3, thereby shortening the work period.
In addition, while considering the balance of the entire building, the installation work of the seismic isolation device 3 can proceed simultaneously from a plurality of locations, such as two sides on the left and right sides of the existing building 1 or four sides on the left and right sides. The construction period can be shortened.
[0032]
Even if an earthquake occurs in the middle of construction, the horizontal displacement restraining means 12 restrains the horizontal displacement of the portion above the place where the seismic isolation device 3 of the existing building 1 is installed. It is possible to avoid a situation where the horizontal force is concentrated on the non-worked pillar 2 and the unworked pillar 2 is damaged.
[0033]
Further, as the horizontal displacement restraining means 12, individual horizontal restraining means 12 A for restraining the relative horizontal displacement of the upper and lower base plates 10 with respect to the individual seismic isolation devices 3 , particularly a pair of bases 14 are engaged with the upper and lower base plates 10. By adopting the individual horizontal displacement restraint unit 16 configured to be tensioned by the tension bar 15 and installing it so as to surround the seismic isolation device so as to face the two horizontal directions around it, horizontal displacement during construction In addition to being able to effectively restrain the structure, it is no longer necessary to install large temporary materials or seismic isolation pits for horizontal force resistance in the vicinity of the building, saving space and reducing costs.
[0034]
In the above embodiment, the case where the rectangular existing building 1 is seismically isolated has been described as an example. However, of course, even an existing building having a square cross section or an existing building having a circular cross section is used. However, it goes without saying that seismic isolation is possible.
Also, the seismic isolation device used for seismic isolation is not limited to laminated rubber, and other types of seismic isolation devices may be used.
[0035]
【The invention's effect】
According to the invention of claim 1, for each predetermined number of pillars of the existing building, the weight of the existing building borne by the pillar is supported by temporary materials such as a jack, and in this state, the seismic isolation device is a part of the pillar cut This is a construction method that installs seismic isolation devices for all the pillars by moving the temporary materials while moving the temporary materials, and the temporary materials for vertical loads can be used repeatedly. The amount of use can be greatly reduced compared to a conventionally considered method.
[0036]
In addition, since the transfer of the existing building's weight to the seismic isolation device is completed at the same time as installing all the seismic isolation devices, the seismic isolation has been carried out from the temporary material using jacks after the seismic isolation has been performed separately. The process of transferring the building weight to the equipment becomes unnecessary, and the construction period is shortened accordingly.
Considering the balance of the entire building, for example, it is possible to proceed with the installation work of seismic isolation devices from multiple locations, such as two on the left and right sides of the existing building or four on the front, back, left and right. This also shortens the construction period. I can plan.
In addition, even if the base floor is seismically isolated, a large scale does not require a large amount of support, and the scaffold can be used while moving, so a very small scale is sufficient.
[0037]
Moreover, during the installation process of the seismic isolation devices, individual horizontal displacement restraining means are sequentially installed around each seismic isolation device, so that the horizontal displacement during construction can be effectively restrained, as well as around the building periphery. There is no need to install large temporary materials or seismic isolation pits for horizontal force resistance during an earthquake, saving space and significantly reducing costs.
[0038]
According to the second aspect of the present invention, the individual horizontal displacement restraining means is configured to restrain the relative horizontal displacement of the upper and lower mounting plate portions of the seismic isolation device by tensioning the pair of bases with the tension bar. By adopting a horizontal restraint unit and surrounding each seismic isolation device so that it is oriented in two horizontal directions around it, effective relative horizontal displacement in all directions of the upper and lower mounting plates is effective. Can be restrained.
[Brief description of the drawings]
FIG. 1 shows an embodiment of the seismic isolation method of the present invention, and is a cross-sectional view showing a part where an existing base isolation device is installed.
FIG. 2 shows an embodiment of the seismic isolation method of the present invention, and is a cross-sectional view illustrating a specific installation process of the seismic isolation device.
FIG. 3 shows an embodiment of the seismic isolation method of the present invention, and is a cross-sectional view illustrating a specific installation process of the seismic isolation device.
FIG. 4 shows an embodiment of the seismic isolation method of the present invention, and is a cross-sectional view for explaining a specific installation process of the seismic isolation device.
FIG. 5 shows an embodiment of the seismic isolation method of the present invention, and is a cross-sectional view illustrating a specific installation process of the seismic isolation device.
FIG. 6 is a side view illustrating an individual horizontal displacement restraining means according to the embodiment of the seismic isolation method of the present invention.
FIG. 7 shows an embodiment of the seismic isolation method of the present invention and is a plan view for explaining a specific installation process of the seismic isolation device.
FIG. 8 is a side view showing another embodiment of the individual horizontal restraint means according to the embodiment of the seismic isolation method of the present invention.
FIG. 9 is a side view showing still another example of the individual horizontal displacement restraining means according to the embodiment of the seismic isolation method of the present invention.
FIG. 10 is a side view of the entire building showing a conventional seismic isolation method.
FIG. 11 is an enlarged view of an X circle part of FIG.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Existing building 2 Pillar 3 Seismic isolation device 4 Temporary material 4a Jack 6 Large beam 7 Small beam 10 Base plate (mounting plate part)
12 Horizontal displacement restraint means 12A Individual horizontal displacement restraint means
14 pedestal
15 Tension bar
16 Individual horizontal displacement restraint unit

Claims (2)

既存建物に免震装置を設置して免震化するための免震化工法であって、
既存建物の複数本ある柱のうち所定本数の柱毎に、該柱が負担する既存建物の重量分を仮設材で受け、該柱を切断するとともにその切断箇所に免震装置を設置し、その後設置した免震装置に前記柱が負担する既存建物の重量分を前記仮設材から移し換えて該仮設材を撤去する作業を繰り返し行うことにより、前記複数本の柱全てに対して免震装置を順次設置するとともに前記仮設材を順次撤去していき、
しかも、それら柱全てに対して免震装置を順次設置していきかつ仮設材を順次撤去していく工程中には、既存建物の重量分を仮設材から各免震装置に移し換えるに先立って、各免震装置の周囲にそれぞれ個別水平変位拘束手段を順次設置していくことにより、該個別水平変位拘束手段によって、既存建物の免震装置を設置する箇所より上側の部分の水平変位を拘束することを特徴とする免震化工法。
A seismic isolation method for seismic isolation by installing seismic isolation devices in existing buildings,
For each of a certain number of pillars in an existing building, the temporary building material receives the weight of the existing building borne by the pillar, cuts the pillar, and installs a seismic isolation device at the cut location. The seismic isolation device is applied to all the plurality of pillars by repeatedly transferring the weight of the existing building borne by the pillar to the installed seismic isolation device from the temporary material and removing the temporary material. We install sequentially and remove the temporary materials sequentially ,
Moreover, during the process of sequentially installing seismic isolation devices for all of these pillars and removing temporary materials in sequence , prior to transferring the weight of the existing building from the temporary materials to each seismic isolation device. , constrained by going respectively sequentially placed individually horizontal displacement restraining means around each isolator, the individual by horizontal displacement restraining means, the horizontal displacement of the upper portion than places to install a seismic isolation device of an existing building Seismic isolation method characterized by
前記個別水平変位拘束手段として、柱の切断部の上下にそれぞれ固定されて個々の免震装置の上下にそれぞれ設置されている取付板部の相対的な水平変位を拘束する個別水平変位拘束ユニットを用いるとともに、
該個別水平変位拘束ユニットは、上下の取付板部にまたがって係合する一対の台座と、それら台座どうしを所定荷重で互いに近づくように引っ張る緊張棒材とにより構成され、 該個別水平変位拘束ユニットを、それらの軸線が互いに直交する2方向を指向する状態で各免震装置を取り囲むようにしてその周囲に複数組配置することを特徴とする請求項1記載の免震化工法。
As the individual horizontal displacement restraining means, an individual horizontal displacement restraining unit that restrains the relative horizontal displacement of the mounting plate portions fixed respectively above and below the column cutting portions and installed above and below each seismic isolation device. While using
Individual by horizontal displacement restraining unit has a pair of pedestals engaging over the top and bottom of the mounting plate portion is constituted by a tension rod pulling them pedestal each other to be closer to each other at a predetermined load, the individual by horizontal displacement restraining unit The seismic isolation method according to claim 1 , wherein a plurality of sets are arranged around the seismic isolation devices in a state where their axes are oriented in two directions orthogonal to each other .
JP2000354146A 2000-11-21 2000-11-21 Seismic isolation method Expired - Fee Related JP3760306B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000354146A JP3760306B2 (en) 2000-11-21 2000-11-21 Seismic isolation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000354146A JP3760306B2 (en) 2000-11-21 2000-11-21 Seismic isolation method

Publications (2)

Publication Number Publication Date
JP2002155641A JP2002155641A (en) 2002-05-31
JP3760306B2 true JP3760306B2 (en) 2006-03-29

Family

ID=18826795

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000354146A Expired - Fee Related JP3760306B2 (en) 2000-11-21 2000-11-21 Seismic isolation method

Country Status (1)

Country Link
JP (1) JP3760306B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5998858B2 (en) * 2012-11-05 2016-09-28 株式会社大林組 Seismic isolation method for existing buildings
CN113513185A (en) * 2021-07-19 2021-10-19 上海建工一建集团有限公司 Structural integral jacking transformation device and construction method thereof
JP7787673B2 (en) * 2021-09-09 2025-12-17 株式会社竹中工務店 How to replace or reinforce construction structures

Also Published As

Publication number Publication date
JP2002155641A (en) 2002-05-31

Similar Documents

Publication Publication Date Title
JP6022631B1 (en) Seismic isolation device replacement method and seismic isolation structure
KR20180137268A (en) Aseismatic Reinforcement Steel Frame with Friction Slip Brace and Aseismatic Reinforcement Method using thereof
JP2014114581A (en) Aseismic base isolation bearing mechanism and aseismic base isolation building
JP3772248B2 (en) Seismic isolation method for intermediate floors of existing buildings
JP2003020618A (en) Existing bridge reinforcement method and reinforced existing bridge
JP3760306B2 (en) Seismic isolation method
CN113357435A (en) Assembled back rest device for pipe jacking construction
KR200286390Y1 (en) The connecting structure of maintained-load test device
CN214302987U (en) Connecting device for connecting joint of buckling restrained brace and existing concrete beam
JP4658006B2 (en) Seismic isolation method for existing buildings and temporary seismic control panel
JP2004308330A (en) Raised floor steel foundation beam structure
JP6066849B2 (en) Seismic isolation method for existing buildings
JP6031626B1 (en) Replacing the seismic isolation device in the pile head seismic isolation structure
JP3551816B2 (en) Seismic isolation method for existing buildings
JP2017115392A (en) Manufacturing method for hollow girder
JP3822125B2 (en) Temporary restraint jig for seismic isolation device and restraint method
JP3918705B2 (en) Seismic isolation method for existing buildings
JP3055081B2 (en) How to fix tension material
JP3691226B2 (en) Seismic isolation method for existing reinforced concrete structures with columnar structural members
JP2001049873A (en) Existing building seismic isolation method
JPH0649982A (en) Formwork unit and its construction
JP4658005B2 (en) Seismic isolation method for existing buildings
KR102000082B1 (en) Aseismatic Reinforcement Device with Toggle Type Friction Slip Brace, and Aseismatic Reinforcement Method using thereof
JP6114071B2 (en) Seismic isolation method for existing buildings and temporary structure under construction
JP3700127B2 (en) Horizontal displacement restraint jig for seismic isolation devices

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050601

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050607

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050721

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050728

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050913

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20051108

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051206

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051221

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3760306

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120120

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120120

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130120

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130120

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140120

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140120

Year of fee payment: 8

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140120

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150120

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees