Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP3848280B2 - Reconstruction method of multi-level crossing bridge - Google Patents
[go: Go Back, main page]

JP3848280B2 - Reconstruction method of multi-level crossing bridge - Google Patents

Reconstruction method of multi-level crossing bridge Download PDF

Info

Publication number
JP3848280B2
JP3848280B2 JP2003082204A JP2003082204A JP3848280B2 JP 3848280 B2 JP3848280 B2 JP 3848280B2 JP 2003082204 A JP2003082204 A JP 2003082204A JP 2003082204 A JP2003082204 A JP 2003082204A JP 3848280 B2 JP3848280 B2 JP 3848280B2
Authority
JP
Japan
Prior art keywords
girder
bridge
lane
new
existing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2003082204A
Other languages
Japanese (ja)
Other versions
JP2004285795A (en
Inventor
勉 志村
秀智 佐々木
弘行 森下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawada Industries Inc
Original Assignee
Kawada Industries Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawada Industries Inc filed Critical Kawada Industries Inc
Priority to JP2003082204A priority Critical patent/JP3848280B2/en
Publication of JP2004285795A publication Critical patent/JP2004285795A/en
Application granted granted Critical
Publication of JP3848280B2 publication Critical patent/JP3848280B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、既設の立体交差橋を交通遮断することなく新設橋に架け替えることのできる工法に関するものである。
【0002】
【従来の技術】
従来における立体交差橋の架け替え工法としては、第1に、既設橋を一括して撤去し、この撤去部分に新設橋を架設するという工法と、第2に、まず、架け替えるべき既設橋の半分を上り下りの対面通行車線として利用し、既設橋の残る半分を撤去して最初の複数車線分の新設橋を架設し、次に、この新設橋を上り下り用の対面通行車線に使用して、残りの既設橋を撤去し、そこに後の複数車線分の新設橋を架設して、架け替え完了とする工法が知られている。
【0003】
【発明が解決すべき課題】
上記の架け替え工法のうち、第1の、既設橋を一括して撤去して、その部分に新設橋を架設する工法は、架け替え期間中車両が全面通行止めとなるため、よほどの条件がそろわない限り実施は困難であり、利用性はきわめて低いという問題がある。
【0004】
一方、上記の架け替え工法のうち、第2の工法は、例えば、橋幅が上り側複数車線50%、下り側複数車線50%からなるような既設橋において、いずれか一方の複数車線を上り側と下り側の対面通行二車線に分けて利用し、残る他方の複数車線を撤去するという方法であるが、橋幅の50%に相当する片側複数車線に相当する部分を撤去してしまうと、残る50%の橋幅の複数線では、対面通行二車線としては、十分な路幅を確保することができず、通行に危険が生ずるという問題を有している。
【0005】
このような理由から、既設橋に上り側と下り側の対面通行二車線を残す工法では、そのための車線幅として既設橋の橋幅の55〜60%程度を確保しておかなければならず、従って、撤去した既設橋の橋幅の40〜45%程の範囲に新設橋を架設したとしても、この新設橋では、上り下り側の対面通行二車線を設けるためには橋幅が狭すぎて、対面通行に必要な中央分離線を備える十分な広さの車線幅を得ることができないという問題を有している。
【0006】
さらに、第2の工法では、既設橋における桁の構造や桁の配置によって、対面通行二車線の確保ができないことがあり、工事の途中で、全面通行止めあるいは片側通行として工事を進めなければならないという問題を有している。
【0007】
【課題を解決するための手段】
本発明は、従来の立体交差橋架け替え工事における上記のような問題点を解決するための手段として、交通を遮断することなく、既設橋の一部解体から新設橋の架設完了までの期間中に、暫定的な対面通行車線を得るための既設橋の橋幅を大きく確保でき、安全かつ迅速に工事が進められる架け替え工法の提供を目的としたものである。
【0008】
本発明に係る立体交差橋の架け替え工法は、そのための具体的手段として、既設の立体交差橋を、交通遮断することなく新設橋に架け替えるための工法であって、既設橋の上り側複数車線と下り側複数車線のうち、いずれか一方の複数車線で上り側と下り側の対面通行車線を確保しておいて、他方の複数車線を閉鎖し、閉鎖複数車線における新設桁架設可能な幅範囲の既設橋を撤去して、この撤去された部分に第1新設桁を架設し、前記対面通行車線における一方の車線を前記第1新設桁上に移し替えた後に、既設橋における別の新設桁架設可能な幅範囲を撤去して、この撤去された部分に第2新設桁を架設し、前記対面通行車線における他方の車線を前記第2新設桁上に移し替えて、この第2新設桁と前記第1新設桁とにより上下側対面通行車線を確保しておいて、既設橋の残部を全て撤去し、この撤去部分に残りの複数車線幅からなる新設桁を架設することを特徴とする。
【0009】
既設橋の一部を撤去して、第1新設桁を架設した後に、第2新設桁を架設する部分としては、第1新設桁と隣接した位置でもよく、また、既設橋の一部を撤去して、第1新設桁を架設した後に、第2新設桁を架設する部分が、第1新設桁とは既設橋の他の一部を隔てて離間した位置であってもよい。
【0010】
【発明の実施の形態】
次に、本発明に係る立体交差橋の架け替え工法を、図面に示す自動車道路の実施例について説明すると、図1はこの工法の一工程における既設橋1と新設桁9の形状を示す斜視図、図2から図11は、いずれも橋脚4の部分における橋桁2により支持された片側二車線の床版3を有する既設橋1と、間隔をおいて立設された橋脚10により支持される新設桁9,14,15,16の同じ位置の断面図である。
【0011】
図2は、架け替え工事開始前における既設橋1の形状を示しており、床版3上には、上り側複数車線5と下り側複数車線6が、中央分離線7を隔てて設けられている。なお、この実施例では、上り側複数車線5および下り側複数車線6はいずれも二車線として示されているが、上り側複数車線5および下り側複数車線6は二車線に限られることはなく、三車線、四車線であってもよい。また、この架け替え工事に直接関係はないが、既設橋1の両側には上り用および下り用の側道8が設けられている。
【0012】
工事は、図3に示すように、まず、上り側複数車線5もしくは下り側複数車線6のいずれか一方の複数車線、例えば、下り側複数車線6の通行を停止して閉鎖し、上り側複数車線5のみで、上り側車線と下り側車線の対面通行車線を確保し既設橋1における左側の一車線分を含む新設桁架設可能な幅範囲W1を橋の長さ方向に沿って撤去する。
【0013】
次に、図4に示すように、この撤去された部分に一車線分の幅からなる第1新設桁9を架設する。この第1新設桁9は、間隔をおいて立設され複数の橋脚10によって支持された橋桁11と、この橋桁11上に設けられた両側縁に安全柵13を備えた床版12とから構成されている。なお、この実施例の図面では、新設桁9の橋桁11として箱桁を使用した形状を示したが、橋桁11としては既設橋1のようなI型形状であってもよい。
【0014】
第1新設桁9が架設されたなら、図5に示すように、上り側複数車線5で使用していた下り側および上り側の対面通行二車線のうち、いずれか一方の車線、例えば中央分離線7寄りの下り側車線Bを前記第1新設桁9上に移し替える。また、その時、既設橋1の右外側に、両側縁に安全柵13を備えた上り側車線Aを残しておき、既設橋1における中央分離線7側の一車線分を含む新設桁架設可能な幅範囲W2を橋の長さ方向に沿って撤去する。
【0015】
図5に示すように、既設橋1における中央分離線7側の新設桁架設可能な幅範囲W2を撤去したのち、図6に示すように、この撤去部分に第2新設桁14を第1新設桁9と平行に架設する。この第2新設桁14の架設に際しては、第1新設桁9の既設橋1側に設けられた一方の安全柵13を撤去して、第1新設桁9の床版12と第2新設桁14の床版12とを一体に接続し、第2新設桁14の既設橋1側に安全柵13を設ける。
【0016】
上記のように、第2新設桁14が架設されたのち、図7のように、既設橋1に使用されていた上り側車線Aを第2新設桁14上に移し替えて、第1新設桁9と第2新設桁14とにより、上り側車線Aと下り側車線Bによる対面通行二車線を確保する。
【0017】
次いで、既設橋1の残りの幅範囲W3を撤去して、この撤去した跡のスペースに図8に示すように、前記第1新設桁9および第2新設桁14と同様な第3新設桁15と第4新設桁16とを架設し、第2新設桁14と第3新設桁15との間に中央分離線17を設けるとともに、第4新設桁16の外側に安全柵13を設けて架け替え作業を完了する。
【0018】
図8に示すように、第3新設桁15と第4新設桁16とが架設されたのちは、図7で示した第1新設桁9と第2新設桁14とによる対面通行二車線を閉鎖して、第3新設桁15と第4新設桁16とをいずれも上り側複数車線25とし、第1新設桁9および第2新設桁14とをいずれも下り側複数車線26として全面交通開放とする。
【0019】
上記の実施例では、工程順として、図3に示すように、上り側および下り側複数車線5、6のうち、下り側複数車線6を閉鎖して、上り側複数車線5で上り側と下り側車線の対面通行車線を確保し、既設橋1における左側の一車線分を含む新設桁架設可能な幅範囲W1を撤去したが、必ずしもこの順序に限られることはなく、上り側複数車線5を閉鎖して、下り側複数車線6で、上り側と下り側車線の対面通行車線を確保し、最初に、既設橋1における右側の一車線分を含む新設桁架設可能な幅範囲を撤去して、ここに第1新設桁を架設してもよい。
【0020】
また、上記実施例では、既設橋1の新設桁架設可能な幅範囲W1,W2を、一車線分を含むものとしたが、幅範囲W1,W2は必ずしも一車線分を含むことに限られることはなく、二車線分、三車線分を含むものであってもよい。従って、第1新設桁9,第2新設桁14についても、一車線分の幅からなることに限定されるわけではなく、二車線分、三車線分を含むものであってもよい。
【0021】
図9乃至図11は、架設工法の第2の実施例を示している。この架設工法では、図9の状態に到る前の方法が、前記第1の実施例における図2、図3、図4と同じであり、図9、図10、図11に示す状態が、第1実施例の図4、図5、図6に示す工法とは別の工法として説明されている。
【0022】
第1の実施例の図3、図4に示すように、下り側複数車線6の一部W1を撤去して、この位置に第1新設桁9を架設した後、この第2実施例の工法では、図9の状態となる。つまり、上り側複数車線5で使用していた上下二車線A,B(図4参照)のうちの、いずれか一方の車線、例えば中央分離線7寄りの下り側車線Bを第1新設桁9に移し替える。
【0023】
また、その時、図3、図4に示されている既設橋1の中央分離線7を撤去して、図9のように、この既設橋1の中央部分に、両側に安全柵13を設けた上り側車線Aを設けるとともに、既設橋1における第1新設桁9と対称的な位置の一車線分を含む新設桁架設可能な幅範囲W2を橋の長さ方向に沿って撤去して、図10に示すように、既設橋1の一部W2を撤去した跡に第2新設桁14を架設し、次いで図11のように、既設橋1の中央部分の上り側車線Aを、この第2新設桁14に移し換える。
【0024】
その後、第1新設桁9と第2新設桁14との間の残る幅範囲W3を撤去し、この既設橋1の撤去された跡に、図8で示したように第3新設桁15と第4新設桁16とを架設し、次いで、図11で示した第1新設桁9と第2新設桁14とによる二車線を閉鎖して、第3新設桁15と第4新設桁16とをいずれも上り側複数車線25とし、第1新設桁9および第2新設桁14とをいずれも下り側複数車線26として全面交通開放とする。
【0025】
【発明の効果】
この発明に係る架け替え工法では、第一の工程として、閉鎖した複数車線を橋幅全てにわたり撤去してしまうのではなく、既設橋における左側もしくは右側の一車線分を含む新設桁架設可能な幅範囲W1を撤去して、その部分に一車線分の第1新設桁9を架設するので、図3および図4に示すように、この第1新設桁9を架設している期間中に、既設橋1に、上り下り用の対面通行車線としては十分に広い車線幅を確保することができ、余裕のあるスペースで安全な対面通行二車線を運行することができる。
【0026】
第1新設桁9が架設されたなら、対面通行車線における一車線を第1新設桁に移し替えることができ、また、図5のように、既設橋1における中央分離線付近の左内側一車線分を含む新設桁架設工可能な幅範囲W2か、もしくは図9のように、既設橋1の右外側一車線分を含む新設桁架設可能な幅範囲W2を撤去するので、いずれも残された既設橋1には、一車線分としては十分に広くて安全な車線を確保でき、第1新設桁9とともに幅の広い安全な対面通行車線を得ることができる。
【0027】
図7および図11のように、第2新設桁14が架設されて、既設橋1上の対面通行一車線がこの第2新設桁14に移し替えられると、これらの新設桁はもともと一車線分の十分な幅を有するような大きさに設計されているので、第1新設桁9と第2新設桁14とによって、安全な対面通行車線として使用することができる。
【0028】
この発明の工法では、閉鎖した既設橋の一部を撤去して、一車線分の第1新設桁9を架設し、架設された第1新設桁9は、早速対面通行用一車線として利用するので、対面通行用の別の一車線の残されている既設桁の一部を撤去することで、第2新設桁14を架設することができるが、これらの第1と第2の新設桁は、いずれも既設桁の構造や桁の配置、形状などに依存することなく施工できるので、最後の工程まで、既設桁の構造による影響を受けずに安全に工事を進めることができる。
【0029】
第1新設桁9と第2新設桁14とが架設された後は、図7では右側に残された既設橋1、もしくは、図11では中央部に残された既設橋1を一度に撤去して、図8のように、第3新設桁15と第4新設桁16とを一度に併行して架設することができるので、第3新設桁15と第4新設桁16とによる残りの二車線を短期間に能率よく架設でき、複数車線の立体交差橋を交通遮断することなく安全に架設することができる。
【図面の簡単な説明】
【図1】本発明に係る架け替え工事の一工程における既設桁と新設桁の断面形状を示す斜視図。
【図2】架け替え工事開始前の既設橋の断面形状を示す断面図。
【図3】既設橋の撤去すべき範囲と、残る既設橋を対面通行車線に使用している状態の断面図。
【図4】既設橋の一部を撤去した跡に第1新設桁を架設した状態の断面図。
【図5】第1新設桁を対面通行一車線に使用している状態と、既設橋の次に撤去すべき範囲を示す断面図。
【図6】図5で示した既設橋の撤去部分に第2新設桁を架設した状態の断面図。
【図7】第1新設桁と第2新設桁とを対面通行二車線に使用し、既設橋の次に撤去すべき範囲を示す断面図。
【図8】第1および第2新設桁の隣に第3および第4新設桁を架設して、架け替えを完了した状態の断面図。
【図9】別の実施例としての架設法であり、図5に対応する断面図。
【図10】図9の実施例による架設法であって、図6に対応する断面図。
【図11】図9の実施例による架設法であって、図7に対応する断面図。
【符号の説明】
1:既設橋、
2:橋桁、
3:床版、
4:ブロック、
5:上り側複数車線、
6:下り側複数車線、
7:中央分離線、
8:側道、
9:第1新設桁、
10:橋脚、
11:橋桁、
12:床版、
13:安全柵、
14:第2新設桁、
15:第3新設桁、
16:第4新設桁
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method that can replace an existing three-dimensional intersection bridge with a new bridge without blocking traffic.
[0002]
[Prior art]
The conventional methods for replacing multi-level crossing bridges are as follows: first, the existing bridges are removed in a lump, and a new bridge is installed at the removed part; Half will be used as an up / down facing traffic lane, the remaining half of the existing bridge will be removed and the first multi-lane new bridge will be built, and then this new bridge will be used as an up / down facing traffic lane. In addition, a method is known in which the remaining existing bridge is removed and a new bridge for a plurality of subsequent lanes is built there to complete the replacement.
[0003]
[Problems to be Solved by the Invention]
Of the above-mentioned replacement methods, the first method of removing existing bridges and installing a new bridge on that part of the construction method is because all vehicles are closed during the replacement period. Unless it is implemented, it is difficult to implement and there is a problem that its availability is very low.
[0004]
On the other hand, among the above-described replacement methods, the second method is, for example, an ascending of a plurality of lanes on an existing bridge having a bridge width of 50% ascending lanes and 50% ascending lanes. It is a method of separating and using the other two lanes that are divided into two lanes facing each other on the side and the down side, but if you remove the part corresponding to one side lane corresponding to 50% of the bridge width The remaining 50% of the bridge width has a problem that a sufficient road width cannot be secured as a two-way traffic lane, resulting in danger of traffic.
[0005]
For this reason, in the construction method that leaves two lanes facing each other on the existing bridge, it is necessary to secure 55 to 60% of the bridge width of the existing bridge as the lane width for that, Therefore, even if a new bridge is installed in the range of about 40 to 45% of the bridge width of the removed existing bridge, this new bridge is too narrow to provide two-way traffic on the up and down sides. There is a problem that it is not possible to obtain a sufficiently wide lane width provided with a central separation line necessary for face-to-face traffic.
[0006]
Furthermore, in the second construction method, due to the structure of the girders and the arrangement of the girders in the existing bridge, it may not be possible to secure two-way traffic, and it is necessary to proceed with the construction as a full-passage or one-way traffic in the middle of the construction. Have a problem.
[0007]
[Means for Solving the Problems]
The present invention is a means for solving the above-mentioned problems in conventional multilevel crossover replacement work, during the period from the partial dismantling of the existing bridge to the completion of the construction of the new bridge without blocking traffic. In addition, the purpose of this project is to provide a replacement method that can secure a large width for existing bridges to obtain a provisional face-to-face traffic lane, and allows the construction to proceed safely and quickly.
[0008]
The construction method of the multilevel crossing bridge according to the present invention is a construction method for replacing the existing multilevel crossing bridge with a new bridge without blocking traffic as a specific means for that purpose. Width and lane and multiple lanes on the downside, the width that allows the installation of the new girder in the closed multiple lanes by securing the upside and downside facing lanes on either lane and closing the other lane After removing the existing bridge in the area, laying the first new girder on the removed part, moving one lane in the face-to-face traffic lane onto the first new girder, then another new construction in the existing bridge The width range in which the girder can be installed is removed, a second newly installed girder is installed in the removed part, and the other lane in the facing traffic lane is moved onto the second newly installed girder. And the first newly installed girder And set aside the lane, and remove all the remainder of the existing bridges, characterized by erection of new digits consisting of the remaining plurality lane width to the removal portion.
[0009]
After removing the part of the existing bridge and installing the first new girder, the part to install the second new girder may be a position adjacent to the first new girder, or part of the existing bridge is removed. Then, after the first new girder is erected, the portion where the second new girder is erected may be at a position separated from the first new girder by separating another part of the existing bridge.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
Next, the construction method of the multilevel crossing bridge according to the present invention will be described with reference to the embodiment of the motorway shown in the drawings. FIG. 1 is a perspective view showing the shapes of the existing bridge 1 and the new girder 9 in one step of this construction method. FIGS. 2 to 11 are both an existing bridge 1 having a two-lane floor slab 3 supported by a bridge girder 2 in a portion of a pier 4 and a new installation supported by a pier 10 standing upright at intervals. It is sectional drawing of the same position of the girders 9, 14, 15, and 16. FIG.
[0011]
FIG. 2 shows the shape of the existing bridge 1 before the start of replacement work. On the floor slab 3, a plurality of ascending lanes 5 and a plurality of descending lanes 6 are provided with a central separation line 7 therebetween. Yes. In this embodiment, the upside multiple lanes 5 and the downside multiple lanes 6 are both shown as two lanes, but the upside multiple lanes 5 and the downside multiple lanes 6 are not limited to two lanes. Three lanes or four lanes may be used. In addition, although there is no direct relationship with this replacement work, upside and downside roads 8 are provided on both sides of the existing bridge 1.
[0012]
As shown in FIG. 3, the construction is performed by first stopping and closing the plurality of lanes 5 on either the upside lanes 5 or the downside lanes 6, for example, the downside lanes 6, With the lane 5 alone, a face-to-face lane of the upside lane and the downside lane is secured, and the width range W1 in which the newly installed girder including the left lane of the existing bridge 1 can be installed is removed along the length direction of the bridge.
[0013]
Next, as shown in FIG. 4, a first newly installed girder 9 having a width corresponding to one lane is installed on the removed portion. The first newly installed girder 9 is composed of a bridge girder 11 that is erected at intervals and supported by a plurality of bridge piers 10 and a floor slab 12 that is provided with safety fences 13 on both side edges provided on the bridge girder 11. Has been. In the drawing of this embodiment, a shape using a box girder as the bridge girder 11 of the newly installed girder 9 is shown, but the bridge girder 11 may be an I-shaped shape like the existing bridge 1.
[0014]
When the first newly installed girder 9 is installed, as shown in FIG. 5, one of the two lanes on the downside and the upside facing two lanes used in the upside multiple lanes 5, for example, the central branch The down lane B close to the separation line 7 is moved onto the first newly installed girder 9. Further, at that time, an upside lane A having safety fences 13 on both side edges is left on the right outside of the existing bridge 1, and a new girder including one lane portion on the center separation line 7 side in the existing bridge 1 can be installed. The width range W2 is removed along the length direction of the bridge.
[0015]
As shown in FIG. 5, after removing the width range W <b> 2 where the newly installed girder can be installed on the center separation line 7 side in the existing bridge 1, the second newly installed girder 14 is installed in the removed portion as shown in FIG. 6. Install in parallel with the girder 9. When the second new girder 14 is installed, one safety fence 13 provided on the existing bridge 1 side of the first new girder 9 is removed, and the floor slab 12 and the second new girder 14 of the first new girder 9 are removed. And a safety fence 13 is provided on the existing bridge 1 side of the second newly installed girder 14.
[0016]
After the second newly installed girder 14 is installed as described above, the upside lane A used for the existing bridge 1 is moved onto the second newly installed girder 14 as shown in FIG. 9 and the second newly installed girder 14 secure a two-way traffic lane with an upside lane A and a downside lane B.
[0017]
Subsequently, the remaining width range W3 of the existing bridge 1 is removed, and a third newly installed girder 15 similar to the first newly installed girder 9 and the second newly installed girder 14 is formed in the space of the removed trace as shown in FIG. And the fourth newly installed girder 16 are installed, the center separating line 17 is provided between the second newly installed girder 14 and the third newly installed girder 15, and the safety fence 13 is provided outside the fourth newly installed girder 16 for replacement. Complete the work.
[0018]
As shown in FIG. 8, after the third newly installed girder 15 and the fourth newly installed girder 16 are installed, the two-way traffic lane with the first newly installed girder 9 and the second newly installed girder 14 shown in FIG. 7 is closed. Then, the third newly established girder 15 and the fourth newly established girder 16 are both made up of a plurality of ascending lanes 25, and the first newly constructed girder 9 and the second newly established girder 14 are both made up of a plurality of descending lanes 26, and traffic is completely opened To do.
[0019]
In the above embodiment, as shown in FIG. 3, as shown in FIG. 3, among the upstream and downstream multiple lanes 5, 6, the downstream multiple lane 6 is closed and the upstream multiple lane 5 is in the upstream and downstream. The width lane W1 where the newly installed girder including the left lane of the existing bridge 1 can be installed is secured, but the order is not necessarily limited to this. Close and secure two-way lane 6 on the opposite side of the lane on the upside and downside lanes. First, remove the width range in which the new girder can be installed, including one lane on the right side of the existing bridge 1. The first new girder may be installed here.
[0020]
Moreover, in the said Example, although the width range W1, W2 which can construct the newly installed girder of the existing bridge 1 shall contain one lane part, the width ranges W1, W2 are not necessarily limited to including one lane part. It may include two lanes or three lanes. Accordingly, the first new girder 9 and the second new girder 14 are not limited to the width of one lane, and may include two lanes and three lanes.
[0021]
9 to 11 show a second embodiment of the erection method. In this erection method, the method before reaching the state of FIG. 9 is the same as FIG. 2, FIG. 3, FIG. 4 in the first embodiment, and the states shown in FIG. 9, FIG. 10, and FIG. This is described as a construction method different from the construction method shown in FIGS. 4, 5, and 6 of the first embodiment.
[0022]
As shown in FIGS. 3 and 4 of the first embodiment, after removing a part W1 of the plurality of descending lanes 6 and installing the first newly installed girder 9 at this position, the construction method of the second embodiment Then, it will be in the state of FIG. That is, one of the two upper and lower lanes A and B (see FIG. 4) used in the up-side multiple lanes 5, for example, the down-side lane B near the center separation line 7 is changed to the first newly installed girder 9. Move to.
[0023]
At that time, the central separation line 7 of the existing bridge 1 shown in FIGS. 3 and 4 was removed, and safety fences 13 were provided on both sides in the central portion of the existing bridge 1 as shown in FIG. The upside lane A is provided, and the width range W2 in which the newly installed girder including one lane portion symmetrical to the first newly installed girder 9 in the existing bridge 1 is removed along the length of the bridge. As shown in FIG. 10, the second newly installed girder 14 is erected on the trace of the part W2 of the existing bridge 1 removed, and then, as shown in FIG. Move to the new girder 14.
[0024]
Thereafter, the remaining width range W3 between the first newly installed girder 9 and the second newly installed girder 14 is removed, and the third newly installed girder 15 and the second newly installed girder 15 as shown in FIG. 4 new girder 16 is installed, then the two lanes of the first new girder 9 and the second new girder 14 shown in FIG. 11 are closed, and the third new girder 15 and the fourth new girder 16 are Also, the upside multiple lanes 25 are used, and the first new girder 9 and the second newly installed girder 14 are both downside multiple lanes 26, and the traffic is fully open.
[0025]
【The invention's effect】
In the replacement method according to the present invention, as a first step, the width capable of installing a new girder including one lane portion on the left or right side of the existing bridge is not removed as a first step over the entire width of the bridge. Since the range W1 is removed and the first new girder 9 for one lane is installed in that part, as shown in FIGS. 3 and 4, the existing new girder 9 is installed while the first new girder 9 is installed. A sufficiently wide lane width can be secured on the bridge 1 as a two-way traffic lane for going up and down, and a safe two-way traffic lane can be operated in a sufficient space.
[0026]
If the first new girder 9 is installed, one lane in the two-way traffic lane can be transferred to the first new girder, and the left inner one lane near the central separation line in the existing bridge 1 as shown in FIG. The width range W2 in which the new girder can be constructed including the minute or the width range W2 in which the new girder can be installed including the right outer lane of the existing bridge 1 as shown in FIG. 9 is removed, so both remain. The existing bridge 1 can secure a sufficiently wide and safe lane for one lane, and a wide and safe two-way lane along with the first newly installed girder 9 can be obtained.
[0027]
As shown in FIGS. 7 and 11, when the second newly installed girder 14 is installed and the one-way traffic lane on the existing bridge 1 is transferred to the second newly installed girder 14, these newly installed girder are originally one lane worth. Therefore, the first newly installed girder 9 and the second newly installed girder 14 can be used as a safe two-way traffic lane.
[0028]
In the construction method of the present invention, a part of the closed existing bridge is removed and the first new girder 9 for one lane is installed, and the first newly installed girder 9 is immediately used as a one-way lane for two-way traffic. So, by removing a part of the existing girder remaining in another lane for face-to-face traffic, the second new girder 14 can be installed, but these first and second new girder are Since both can be constructed without depending on the structure of the existing girder, the arrangement and shape of the girder, etc., the construction can be safely proceeded to the last process without being affected by the structure of the existing girder.
[0029]
After the first new girder 9 and the second new girder 14 are installed, the existing bridge 1 left on the right side in FIG. 7 or the existing bridge 1 left in the center in FIG. 11 is removed at once. As shown in FIG. 8, since the third newly installed girder 15 and the fourth newly installed girder 16 can be installed in parallel at the same time, the remaining two lanes by the third newly installed girder 15 and the fourth newly installed girder 16 are provided. Can be installed efficiently in a short period of time, and it is possible to construct a multi-lane crossing bridge safely without blocking traffic.
[Brief description of the drawings]
FIG. 1 is a perspective view showing the cross-sectional shapes of an existing girder and a new girder in one step of the replacement work according to the present invention.
FIG. 2 is a cross-sectional view showing a cross-sectional shape of an existing bridge before the start of replacement work.
FIG. 3 is a cross-sectional view of a state where an existing bridge is to be removed and the remaining existing bridge is used for a two-way traffic lane.
FIG. 4 is a cross-sectional view showing a state in which a first newly installed girder is installed on a mark obtained by removing a part of an existing bridge.
FIG. 5 is a cross-sectional view showing a state in which the first newly installed girder is used for a one-way lane and a range to be removed next to an existing bridge.
6 is a cross-sectional view showing a state in which a second newly installed girder is installed on the removed portion of the existing bridge shown in FIG.
FIG. 7 is a cross-sectional view showing a range to be removed next to an existing bridge using the first new girder and the second new girder in a two-way traffic lane.
FIG. 8 is a cross-sectional view showing a state where the third and fourth new girders are installed next to the first and second new girders and the replacement is completed.
FIG. 9 is a cross-sectional view corresponding to FIG. 5, showing a construction method as another embodiment.
10 is a cross-sectional view corresponding to FIG. 6, which is a construction method according to the embodiment of FIG.
11 is a cross-sectional view corresponding to FIG. 7, which is a erection method according to the embodiment of FIG. 9;
[Explanation of symbols]
1: Existing bridge,
2: Bridge girder,
3: Floor slab,
4: Block,
5: Upward multiple lanes,
6: Downward multiple lanes,
7: Center separation line,
8: Side road,
9: First new girder,
10: Pier
11: Bridge girder,
12: Floor slab,
13: Safety fence,
14: Second new girder,
15: Third new girder,
16: 4th new girder

Claims (3)

既設の立体交差橋を、交通遮断することなく新設橋に架け替えるための工法であって、
既設橋の上り側複数車線と下り側複数車線のうち、いずれか一方の複数車線で上り側と下り側の対面通行車線を確保しておいて、他方の複数車線を閉鎖し、
閉鎖複数車線における新設桁架設可能な幅範囲の既設橋を撤去して、この撤去された部分に第1新設桁を架設し、
前記対面通行車線における一方の車線を前記第1新設桁上に移し替えた後に、既設橋における別の新設桁架設可能な幅範囲を撤去して、この撤去された部分に第2新設桁を架設し、
前記対面通行車線における他方の車線を前記第2新設桁上に移し替えて、この第2新設桁と前記第1新設桁とにより上下側対面通行車線を確保しておいて、既設橋の残部を全て撤去し、
この撤去部分に残りの複数車線幅からなる新設桁を架設する立体交差橋の架け替え工法。
It is a construction method to replace an existing three-dimensional intersection bridge with a new bridge without blocking traffic,
Of the existing multiple ascending lanes and descending lanes of the existing bridge, either one of the multiple lanes secures the inbound and outbound lanes, and the other lane is closed,
Remove the existing bridge within the width range where new girder can be installed in closed multiple lanes, and install the first new girder on this removed part,
After moving one lane in the two-way lane onto the first new girder, the width range where another newly installed girder can be installed in the existing bridge is removed, and a second new girder is installed in the removed part. And
The other lane in the two-way traffic lane is moved onto the second newly installed girder, and the second new girder and the first new girder secure an up-and-down two-way traffic lane, and the remaining part of the existing bridge is removed. All removed,
This is a method of replacing a three-dimensional crossing bridge in which a new girder consisting of the remaining multiple lane widths is installed in the removed part.
既設橋の一部を撤去して、第1新設桁を架設した後に第2新設桁を架設する部分が、第1新設桁と隣接した位置である請求項1に記載の立体交差橋の架け替え工法。The part of the existing crossing bridge according to claim 1, wherein a part of the existing bridge is removed and a part where the second newly installed girder is installed after the first newly installed girder is installed is a position adjacent to the first newly installed girder. Construction method. 既設橋の一部を撤去して、第1新設桁を架設した後に第2新設桁を架設する部分が、第1新設桁とは既設橋の他の一部を隔てて離間した位置である請求項1に記載の立体交差橋の架け替え工法。The part where the second new girder is installed after the part of the existing bridge is removed and the first new girder is installed is located at a position spaced apart from the first new girder through the other part of the existing bridge Item 3. A method for replacing a three-dimensional intersection bridge according to item 1.
JP2003082204A 2003-03-25 2003-03-25 Reconstruction method of multi-level crossing bridge Expired - Lifetime JP3848280B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003082204A JP3848280B2 (en) 2003-03-25 2003-03-25 Reconstruction method of multi-level crossing bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003082204A JP3848280B2 (en) 2003-03-25 2003-03-25 Reconstruction method of multi-level crossing bridge

Publications (2)

Publication Number Publication Date
JP2004285795A JP2004285795A (en) 2004-10-14
JP3848280B2 true JP3848280B2 (en) 2006-11-22

Family

ID=33295558

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003082204A Expired - Lifetime JP3848280B2 (en) 2003-03-25 2003-03-25 Reconstruction method of multi-level crossing bridge

Country Status (1)

Country Link
JP (1) JP3848280B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4671912B2 (en) * 2006-06-01 2011-04-20 三菱重工鉄構エンジニアリング株式会社 Bridge replacement method
JP6063795B2 (en) * 2013-03-28 2017-01-18 日立造船株式会社 Bridge girder replacement method
JP6627177B2 (en) * 2016-03-09 2020-01-08 Jfeエンジニアリング株式会社 Construction method of vehicle-mounted lifter and pier
JP6618116B2 (en) * 2016-03-09 2019-12-11 Jfeエンジニアリング株式会社 Construction method of pier
JP6830023B2 (en) * 2017-04-12 2021-02-17 鹿島建設株式会社 Floor slab replacement method
CN110184950B (en) * 2019-05-21 2021-02-09 宁波市政工程建设集团股份有限公司 Construction method for rebuilding and expanding new bridge at original site of bridge under condition of ensuring communication
CN113215965A (en) * 2021-05-07 2021-08-06 上海市城市建设设计研究总院(集团)有限公司 Pier capping beam structure for building new bridge at existing bridge position and construction method
CN115787517A (en) * 2022-06-29 2023-03-14 山西省交通新技术发展有限公司 A Shear Strengthening Method of Concrete Hollow Slab Beam without Interrupting Traffic
CN118835522B (en) * 2024-07-16 2025-11-04 福州大学 A connection structure and construction method for widening old and new bridges using expandable steel bars.

Also Published As

Publication number Publication date
JP2004285795A (en) 2004-10-14

Similar Documents

Publication Publication Date Title
CN100473782C (en) Non-traffic light non-barrier urban multi-level fast traffic road structure
JP3848280B2 (en) Reconstruction method of multi-level crossing bridge
CN103938511B (en) Be applicable to overpass bridge and the passing control method thereof of city crossroad
WO2005031069A1 (en) A full interchange urban road system and the traffic method of using it
CN106638259B (en) The superstructure and its assembling and construction method of prefabricated uncovered beam type combined steel plate beam bridge
WO2011140926A1 (en) Composite bridge or composite tunnel for left-hand traffic comprising two y-shaped units
US2946267A (en) Traffic intersection
CN106012851A (en) Synchronous construction method of steel box girder and concrete pier studs
RU2003123129A (en) COMPLEX OF DEVICES DIVIDING TRANSPORT AND PEDESTRIAN FLOWS MOVING THROUGH THE CROSSROADS OF THE MAIN AND SECONDARY ROAD
CN202017171U (en) Three-layer flyover for urban roads
CN202099708U (en) Novel low overpass for road intersection
RU2385378C2 (en) Complex of dividers of traffic and pedestrian flows, which cross on roads
CN203307697U (en) Crossroad overpass
JP2003268722A (en) Improvement work method for intersection and its adjacent part having bridge pier of viaduct on road median strip
JP4280208B2 (en) Viaduct replacement method
CN105421217B (en) Steel plate shear connector and construction of novel steel plate shear connector in rapid construction of reinforced concrete composite bridge
CN201990907U (en) Urban overpass
CN115852765A (en) Method for reconstructing and expanding road under existing operating railway bridge
JP2006274542A (en) Viaduct
CN105986533A (en) Crossroad structure without traffic lights
CN209338933U (en) Compact viaduct
JP3999556B2 (en) Three-dimensional intersection construction method and three-dimensional intersection
CN106065551A (en) A kind of without waiting for quickly through crossroad
CN113123248A (en) Construction process of prefabricated small box girder bridge with half-first and whole-second
CN109505242B (en) Superimposed beam for temporary covering system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040915

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060801

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060824

R150 Certificate of patent or registration of utility model

Ref document number: 3848280

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120901

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150901

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term