JP3899866B2 - Joint structure of steel plate concrete structure - Google Patents
Joint structure of steel plate concrete structure Download PDFInfo
- Publication number
- JP3899866B2 JP3899866B2 JP2001239551A JP2001239551A JP3899866B2 JP 3899866 B2 JP3899866 B2 JP 3899866B2 JP 2001239551 A JP2001239551 A JP 2001239551A JP 2001239551 A JP2001239551 A JP 2001239551A JP 3899866 B2 JP3899866 B2 JP 3899866B2
- Authority
- JP
- Japan
- Prior art keywords
- steel plate
- joint
- steel
- plate unit
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/06—Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional [3D] extent, e.g. lattice girders
- E04C5/0645—Shear reinforcements, e.g. shearheads for floor slabs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/02—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
- E04B1/14—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements being composed of two or more materials
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
- E04B2/86—Walls made by casting, pouring, or tamping in situ made in permanent forms
- E04B2/8647—Walls made by casting, pouring, or tamping in situ made in permanent forms with ties going through the forms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
- E04B2/86—Walls made by casting, pouring, or tamping in situ made in permanent forms
- E04B2/8652—Walls made by casting, pouring, or tamping in situ made in permanent forms with ties located in the joints of the forms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/29—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
- E04C3/293—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/01—Reinforcing elements of metal, e.g. with non-structural coatings
- E04C5/06—Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional [3D] extent, e.g. lattice girders
- E04C5/0627—Three-dimensional reinforcements composed of a prefabricated reinforcing mat combined with reinforcing elements protruding out of the plane of the mat
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
- E04B2/86—Walls made by casting, pouring, or tamping in situ made in permanent forms
- E04B2002/867—Corner details
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Joining Of Building Structures In Genera (AREA)
- Reinforcement Elements For Buildings (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、発電施設、一般産業用施設、事務所ビル及び集合住宅等の建物もしくは構造物の部材に、所定空間を有して配設された表面鋼板、該空間内に充填されるコンクリート及び両者を−体化するためのスタッド等の補強兼ずれ止め機構等からなる複合構造である鋼板コンクリート構造(SC構造)に於いて、該表面鋼板又は表面鋼板とその構成材からなるSC鋼板ユニットの水平方向継手、鉛直方向継手等の継手構造に関するものである。
【0002】
【従来技術】
従来より、鋼板コンクリー卜構造(SC構造)は、表面鋼板とコンクリートとの一体化により、在来の鉄筋コンクリート構造に比較し、優れた耐力と変形性能を有する構造形式である。また、SC構造は、表面鋼板となるSC鋼板をコンクリート打設時の仮設型枠を兼用する構造材として使用できるので、鉄筋コンクリート構造に於いて必要となる鉄筋と型粋が不要となり、工数の大幅な低減が可能で、工期の短縮が期待できるものであった。
【0003】
また、SC構造の各部材の施工は、一般に、表面鋼板及びその形状保持のための仮設の鋼材等からなるSC鋼板ユニットを、工場又は近接する加工場等で製作した後、施工現場に搬入、据え付けし、所定の形状に組み立て、該SC鋼板ユニット相互を現場溶接によって接合していた。
更に、SC鋼板を直接施工現場で組み立て、SC鋼板相互を溶接することにより取り付けすることも行われていた。いずれにしても、溶接手段により組み立て接合した後、その内側にコンクリートを充填し、当該コンクリートが硬化することにより、表面鋼板とコンクリートとからなる複合一体構造として所用の強度を発現する構造形式のものであった。
【0004】
なお、上記現場溶接による接合以外に、SC鋼板ユニット又はSC鋼板をボルト接合等による接合手段も考えられるが、以下の点で現実的とはいえず、実用には問題があった。
(1)膨大な量のボルト締めを行う必要があり、施工現場での工数が増大する。
(2)壁厚等が薄い場合には、内側からの作業が困難で、ボルト締めを行うことができない。
(3)ボルトの頭が表面鋼板の外側に露出し、外観上目立つ他、構成しようとする空間の有効体積を低減させることになる。
【0005】
【発明が解決しようとする課題】
上記の通り、鋼板コンクリート構造(SC構造)は、一般的に、構造上は極めて優れた性能を有するが、施工面ではSC鋼板ユニット相互を施工現場に於いて溶接接合する必要があり、そのため、以下の解決すべき課題を有していた。
【0006】
図21、22に、従来のSC鋼板ユニットの現場溶接による一般的接合の実施例を示している。
(1)SC鋼板ユニット相互を接合するために、膨大な量(溶接長さ)の現場溶接(図21、22に於けるYの部分)を行う必要があり、施工現場での工数が増大する。
(2)膨大な量となるユニット相互の表面鋼板の継手が、全て現場溶接にならざるを得ず、施工性が悪い。
(3)現場溶接は、工場溶接等と同様の良好な施工環境の確保が不可能であり、信頼性の確保が困難となる他、溶接状況確認のための全工程に渡る溶接管理が不可欠となる。また、溶接管理のための工数が付加される。
【0007】
(4)接合される表面鋼板の強度を相互に確実に伝えるために、突き合わせ溶接が必要となるが、当該溶接接合部の間隔、目違い等の精度が、ユニットの据え付け精度によって決定されるため、精度確保が困難となる。
(5)ユニット相互が溶接接合されるので、施工上、各々のユニットの据え付け精度による誤差の吸収を現場溶接によって行わなくてはならないが、現場溶接では、誤差の吸収幅に限界がある。特に、ユニット周囲全体の表面鋼板を現場溶接によって接合する場合には、当該吸収は困難となる。
(6)現場溶接の信頼性と施工精度は、施工環境に依存しており、気候によって施工可能日が限定されたり、或いは相応の養生を必要とする。
【0008】
【課題を解決するための手段】
本発明は、鋼板コンクリート構造(SC構造)の優れた性質を確保しながら、従来技術に於いて、施工手順上必要であった現場溶接を省き、表面鋼板又は表面鋼板とその構成材からなるSC鋼板ユニット相互の継手構造を提供するものである。なお、内側に充填するコンクリートの継手部からの漏れは、当該継手部にシール等を施すことにより確実に防止することができ、型枠としての機能を達成することができる。
【0009】
本発明では、上記目的を達成する継手構造として、図1ないし図9に示す通り、接合されるSC鋼板ユニット相互に跨がる位置に鋼板或いは鉄筋等の鋼棒等よりなるH型ないしはI型の継手部材を配置し、SC鋼板ユニットの据え付け後に打設するコンクリートによりSC鋼板ユニットの表面鋼板に生じる応力を伝達するように構成した鋼板コンクリート構造の継手構造を提供する。
【0010】
また、図10ないし図12に示す通り、SC鋼板ユニット相互に跨がる位置にスタッド付き鋼板等よりなるH型ないしはI型の継手部材を配置し、当該継手部を覆い、SC鋼板ユニットの据え付け後に打設するコンクリートによりSC鋼板ユニットの表面鋼板に生じる応力を伝達するように構成した鋼板コンクリート構造の継手構造を提供する。
【0011】
更に、図13ないし図16に示す通り、SC鋼板ユニット相互をその端部に形成した段差部或いは凹凸部によって接合し、当該接合部の外側よりボルト等の連結具によりSC鋼板ユニット相互を機械的に接合し、当該SC鋼板ユニットの据え付け後にSC鋼板ユニットの空間内に打設したコンクリートによりSC鋼板ユニットの表面鋼板に生じる応力を伝達するように構成した鋼板コンクリート構造の継手構造を提供する。
【0012】
また、図17ないし図20に示す通り、端部を噛み合わせ形状となるように凹凸部状としたSC鋼板ユニットを、当該SC鋼板ユニットの凹凸部を相互に組み合わせて配置し、SC鋼板ユニットの空間内に打設したコンクリートによりSC鋼板ユニットの表面鋼板に生じる応力を伝達するように構成した鋼板コンクリート構造の継手構造を提供する。
【0013】
【発明の実施の形態】
【実施形態1】
図1、図2は、本発明の鋼板コンクリート構造の継手構造の一実施例である。表面鋼板(以下、実施例ではSC鋼板という)1、2は、所定空間Aを有して対向して配設される。該SC鋼板1、2の一端部に隣接して他のSC鋼板3、4を配設する。該SC鋼板3、4も、上記同様に所定空間Aを有して対向して配設される。上記SC鋼板1〜4の各々の裏面側には、各々適宜間隔毎に多数のスタッド5〜8が空間A側へ立設され、当該鋼板コンクリート構造の補強及びずれ止めの役割をする。
【0014】
上記SC鋼板1、2及びSC鋼板3、4によって各々SC鋼板ユニットが形成され、該SC鋼板ユニットの端部相互に跨って位置するように連結鋼板9、10を配設する。該連結鋼板9、10の裏面側は、鋼板ないし鉄筋等の鋼棒或いは鋼板11によって相互に連結され、所定空間A幅を確保するための間隔保持部材としての役割をしている。更に、対向するSC鋼板1、2及びSC鋼板3、4によって形成されている空間Aの上記鋼棒或いは鋼板11の略中央部分には、該SC鋼板1〜4と同様の鋼板12が、該SC鋼板1〜4と略平行方向に配設され、その表面から該SC鋼板1〜4の裏面側に向かって補強及びずれ止めの役割をする多数のスタッドが立設形成されている。
【0015】
上記連結鋼板9、10、鋼棒11、ずれ止め鋼板12、スタッド等によってH型或いはI型の継手部材を形成している。上記SC鋼板ユニット相互の据え付け後、当該空間Aにコンクリートを打設する。上記コンクリートの打設により、SC鋼板ユニット相互が一体化され、SC鋼板ユニットのSC鋼板1〜4に生じる面内応力を相互に伝達することが可能となる。
【0016】
上記図1は、SC鋼板ユニットの水平方向の継手構造を示しているが、図2は、鉛直方向の継手構造を示している。上記鉛直方向の継手構造も水平方向の継手構造と同様に、SC鋼板1’〜4’よりなるSC鋼板ユニットを、連結鋼板9’、10’、鋼棒或いは鋼板11’、ずれ止め鋼板12’、スタッド等による継手部材により連結している。
【0017】
【実施形態2】
図3は、本発明の鋼板コンクリート構造の継手構造の他の実施例であり、上記実施形態1と同様、所定間隔Aを有するSC鋼板13、14及び該SC鋼板13、14の一端部に隣接して他の所定間隔Aを有するSC鋼板15、16を配設する。従って、両者は対向する位置に配設されることになる。
上記SC鋼板13、14及びSC鋼板15、16によって各々SC鋼板ユニットが形成され、上記対向する位置に該SC鋼板ユニットの端部相互に跨って連結鋼板17、18を配設する。該連結鋼板17、18の裏面側は、鋼板19によって相互に連結され、継手部材を形成している。また、所定空間Aの幅を確保するための間隔保持部材としての役割もしている。
【0018】
上記鋼板19は、図4の拡大断面図に示すようにその両面より、補強及びずれ止めの役割をする適数個の突起20を空間Aに向けて突設形成している。
上記連結鋼板17、18、該連結鋼板17、18相互を連結する鋼板19及び突起20により継手部材が形成されるが、工場等に於いて溶接等により図3、図4に示す形状のH型或いはI型の継手部材として予め一体に形成し、当該継手部材を施工現場に於いてSC鋼板ユニット間に取り付けることにより、継手構造が形成され、SC鋼板ユニット相互が連結される。その後、空間A内にコンクリートを打設することによりSC鋼板ユニット相互が一体化され、コンクリートとの一体性が確保され、応力を相互に伝達することが可能となる。
【0019】
上記図3は、SC鋼板ユニットの水平方向の継手構造を示しているが、図5は、鉛直方向の継手構造を示している。上記鉛直方向の継手構造も水平方向の継手構造と同様、SC鋼板13’〜16’よりなるSC鋼板ユニットを、連結鋼板17’、18’、鋼板19’及び定着ボルト、定着部を有する鋼棒等20’等による継手部材により連結している。
【0020】
【実施形態3】
図6は、本発明の鋼板コンクリート構造の継手構造の他の実施例で、上記実施形態1、2と同様、所定空間Aを有するSC鋼板21、22及び該SC鋼板21、22の一端部に隣接して他の所定空間Aを有するSC鋼板23、24を配設する。従って、両者は対向する位置に配設されることになる。
上記SC鋼板21、22及びSC鋼板23、24によって各々SC鋼板ユニットが形成され、上記対向する位置に該SC鋼板ユニットの端部相互に跨って連結鋼板25、26を配設する。該連結鋼板25、26の裏面側は、鋼棒或いは鋼板27によって相互に連結され継手部材を形成している。また、所定空間Aの幅を確保するための間隔保持部材としての役割もしている。
【0021】
上記鋼棒或いは鋼板27の略中央部分には、図6に示すようにその両面より、該SC鋼板21〜24と略平行方向に鋼板28が形成され、該鋼板28にはその表面からSC鋼板21〜24の裏面側に向かって補強及びずれ止めの役割をする多数の円柱状の定着ボルト、定着部を有する鋼棒等29を形成している。
上記連結鋼板25、26、該連結鋼板25、26相互を連結する鋼棒或いは鋼板27及び円柱状突起29により継手部材が形成されるが、工場等に於いて溶接等により予め図6に示す形状の継手部材を一体形成してH型或いはI型の継手部材として、当該継手部材を施工現場に於いてSC鋼板ユニット間に取り付けることによって継手構造が形成され、SC鋼板ユニット相互が連結される。その後、空間A内にコンクリートを打設することによりSC鋼板ユニット相互が一体化され、コンクリートとの一体性が確保され、応力を相互に伝達することが可能となる。
【0022】
上記図6は、SC鋼板ユニットの水平方向の継手構造を示しているが、図7は、鉛直方向の継手構造を示している。上記鉛直方向の継手構造も水平方向の継手構造と同様、SC鋼板21’〜24’よりなるSC鋼板ユニットを、連結鋼板25’、26’、鋼棒或いは鋼板27’及び円柱状突起29’等による継手部材により連結している。
【0023】
【実施形態4】
図8は、本発明の鋼板コンクリート構造の継手構造の他の実施例で、上記実施形態1〜3と同様、所定空間Aを有するSC鋼板31、32及び該SC鋼板31、32の一端部に隣接して他の所定空間Aを有するSC鋼板33、34を配設する。従って、両者は対向する位置に配設されることになる。
上記SC鋼板31、32及びSC鋼板33、34によって各々SC鋼板ユニットが形成され、上記対向する位置に該鋼板ユニットの端部相互に跨って連結鋼板35、36を配設する。該連結鋼板35、36の裏面側は、鋼棒或いは鋼板37によって相互に連結され継手部材を形成している。また、所定空間Aの幅を確保するための間隔保持部材としての役割もしている。
【0024】
上記継手部の鋼棒或いは鋼板37には、該SC鋼板31〜34と同様の鋼板38が該SC鋼板31〜34と略平行方向に配設され、その表面からSC鋼板31〜34の裏面側へ向かって補強及びずれ止めの役割をする多数のスタッド39が形成されている。本実施例は、空間Aの間隔が広い場合や継手部を一層強固に連結したい場合に採用されるもので、各々のSC鋼板ユニット側に各々2箇所、鋼板38を突設形成している。上記のように、必要に応じて適宜数設けることができ、所定厚や大断面を有する構造にも対応することができる。上記実施態様1〜3と同様、空間Aにコンクリートを打設することによりSC鋼板に生じる面内応力を有効に伝達することが可能となる。
【0025】
上記図8は、SC鋼板ユニットの水平方向の継手構造を示しているが、図9は、鉛直方向の継手構造を示している。上記鉛直方向の継手構造も水平方向の継手構造と同様、鋼板31’〜34’よりなるSC鋼板ユニットを、連結鋼板35’、36’、鋼棒或いは鋼板37’、該鋼板37’より突出した鋼板38’及びその表面から補強及びずれ止めの役割をするスタッド39’等による継手部材により連結している。
【0026】
上記図1ないし図9に示す継手金物は、接合されるSC鋼板ユニット相互に跨って位置するようにSC鋼板又は鉄筋等の鋼棒を固定するための機能を果たす他、SC鋼板ユニットの据え付けに先行して設置し、SC鋼板ユニットの据え付けの際のガイドとすることができる。
更に、継手金物とSC鋼板との位置関係を、図4の拡大断面図に示す配置とすることにより、SC鋼板ユニットの製作精度上の誤差又は継手金物の設置上のずれ等を容易に吸収して接合することができる。
上記構成により、SC鋼板の優れた性能を確保しながら、従来に於いて施工手順上必ず必要となる現場溶接を必要としない、SC鋼板又はSC鋼板とその構成材からなるSC鋼板ユニット相互の機械的接合が可能となる。
【0027】
【実施形態5】
上記継手構造の他、下記の継手部材の構成によっても、現場溶接を必要としないSC鋼板又はSC鋼板とその構成材からなるSC鋼板ユニットの接合が可能となる。
図10は、本発明の鋼板コンクリート構造の継手構造の他の実施例である。SC鋼板41、42は、所定空間Aを有して対向して配設される。該SC鋼板41、42の一端部に隣接して他のSC鋼板43、44を配設する。該SC鋼板43、44も、上記同様に所定空間Aを有して対向して配設される。上記SC鋼板41〜44の各々の裏面側には各々適宜間隔毎に多数のスタッド45〜48が空間A内へ立設され、当該鋼板コンクリート構造の補強及びずれ止めの役割をする。
【0028】
上記SC鋼板41、42及びSC鋼板43、44によって各々SC鋼板ユニットが形成され、該SC鋼板ユニットの端部相互に跨って位置するように帯状の連結金物49、50を配設する。該連結金物49、50の裏面側は、図11(a)の拡大断面図に示すように、補強兼ずれ止め機構となる適宜数のスタッド51、52を立設形成する。帯状の連結金物49、50は、接合されるSC鋼板ユニット相互に跨ってSC鋼板ユニット外側に配置され、該スタッド51、52は、SC鋼板41〜44に予め設けた孔53、54、55、56から各々空間A内に貫入され、その後、打設するコンクリートにより一体化される。当該コンクリートの打設によりSC鋼板に生じる応力を相互に伝達することが可能となる。
【0029】
該SC鋼板41〜44に予め設けた孔53〜56は、予め適宜大きく形成しているので、連結金具49、50の設置時に於いて、部材上或いは施工上の誤差が生じても、クリアランス分となり、当該誤差を容易に吸収して取り付けすることができる。更に、空間A内側に特別の手段を施すことを必要としないで、当該継手部の外側より連結金物49、50のスタッド51、52を空間A内に挿入することのみでSC鋼板ユニット相互の取り付けを容易に行なうことが可能となる。
【0030】
上記図10は、SC鋼板ユニットの水平方向の継手構造を示しているが、図12は、鉛直方向の継手構造を示している。上記鉛直方向の継手構造も水平方向の継手構造と同様、SC鋼板41’〜44’よりなるSC鋼板ユニットを、連結金物49’、50’及び該連結金物49’、50’より突出した補強及びずれ止めの役割をするスタッド51’、52’等による継手部材により連結している。
また、図11(b)に示すように、鋼板41〜44の端部側に形成したスタッド51、52を、他の鋼板41〜44の他端部に設けた孔53〜56より空間A内に直接貫入させ、その後のコンクリートの打設により鋼板相互を一体化させている。従って、鋼板はその端部において重合することになる。
図11(b)では、端部に形成したスタッドと孔とは、対向する鋼板41,42及び鋼板43,44においてその位置関係を逆にして連結している。
【0031】
【実施形態6】
図13は、本発明の鋼板コンクリート構造の継手構造の他の実施例である。
図13に示す通り、SC鋼板61、62は、所定空間Aを有して対向して配設される。該SC鋼板61、62の一端部に隣接して他のSC鋼板63、64を配設する。該SC鋼板63、64も、上記同様に所定空間Aを有して対向して配設される。上記SC鋼板61〜64の各々の裏面側には、各々適宜間隔毎に多数のスタッド65〜68が空間A内へ立設され、当該鋼板コンクリート構造の補強及びずれ止めの役割をする。
【0032】
上記SC鋼板61、62及びスタッド65、66より構成されるSC鋼板ユニットの端部に、凹凸を有する形状の接合部69が形成され、他方、SC鋼板63、64及びスタッド67、68より構成されるSC鋼板ユニットの端部にも、上記接合部69と合致する凹凸を有する形状の接合部70が形成される。上記SC鋼板ユニット端部の接合部69、70相互を組み合わせて配置し、当該接合箇所の外側より、その反対側位置へ通しボルト形式等の鋼棒71等を用いて貫通させ固定することにより、接合部69、70相互を機械的に接合する。
【0033】
上記実施形態5と同様、SC鋼板61〜64に予め設けた孔を、予め大きく形成しておくことにより、取り付け時に於ける部材や施工上の誤差のクリアランス分となり、当該誤差を容易に吸収して取り付けることができる。更に、空間A内側に特別の手段を施すことなく、当該継手部の外側より鋼棒71等を貫通固定するのみで、SC鋼板ユニット相互の取り付けを容易に行なうことが可能となる。
【0034】
また、鋼棒71等を含めた接合部を工場等で予めコンクリートで固定してから施工現場に搬入することにより、SC鋼板ユニットの形状維持が容易となる他、空間A内のコンクリートの打設に先行してボルト接合することが可能となる。また、SC鋼板ユニットの正面及び裏面側のSC鋼板61、62を連続させて形成することにより、空間Aを閉鎖空間Aとすることができ、内側に打設されたコンクリートが外部へ漏れるのを防止する事ができる。
【0035】
上記図13は、SC鋼板ユニットの水平方向の継手構造を示しているが、図14は、鉛直方向の継手構造を示している。上記鉛直方向の継手構造も水平方向の継手構造と同様、SC鋼板61’〜64’よりなるSC鋼板ユニットを、接合部69’、70’及び連結鋼棒71’等による継手部材により連結している。
図15、16に示す継手部は、当該接合部の構造を一方が欠けた相欠き構造としたものを示している。
【0036】
【実施形態7】
図17は、本発明の鋼板コンクリート構造の継手構造の他の実施例である。
図17に示す通り、SC鋼板81、82は、所定空間Aを有して対向して配設される。該SC鋼板81、82の一端部に隣接して他のSC鋼板83、84を配設する。該SC鋼板83、84も、上記同様に所定空間Aを有して対向して配設される。上記SC鋼板81〜84の各々の裏面側には、各々適宜間隔毎に多数のスタッド85〜88が空間A内へ立設され、当該鋼板コンクリート構造の補強及びずれ止めの役割をする。
【0037】
上記図17(a)は、SC鋼板81、82及びスタッド85、86より構成されるSC鋼板ユニットの端部に、半円又は矩形の形状となるような形状の接合部89が一体的に形成され、他方、鋼板83、84及びスタッド87、88より構成されるSC鋼板ユニットの端部は、上記接合部89が挿入されるように開放部90が形成される。
上記接合部89と、開放部90とは、SC鋼板ユニットに於いて交互に形成され、例えば、図17(a)では、上記の通り、左側のSC鋼板ユニットの端部に接合部89が形成され、右側のSC鋼板ユニットの端部には開放部90が形成されているが、図17(b)では、その接合部89及び開放部90の位置が逆となっている。
【0038】
図18で示すように、上記接合部89は、鉛直方向に適宜間隔で左右のSC鋼板ユニットに於いて交互に断続的に突出形成されている。接合部89は、SC鋼板81、82、或いはSC鋼板83、84の端部に、予め工場等に於いて溶接等により一体化しておく。また、上記半円又は矩形形状となる突起部には、表面より適宜数のスタッド91を立設している。
【0039】
図18には、上記接合部89及び開放部90を、施工現場に於いて相互に噛み合わせて設置し、その噛み合わせの後、鉄筋篭92等の補強材を当該箇所に挿入する図が示されている。図19、20は、SC鋼板ユニット相互を連結した状態の断面図及び正面図を示している。組み合わせ連結した後、空間Aにコンクリートを打設する。
【0040】
SC鋼板接合部に発生する引張り力は、半円又は矩形形状となる突起部の端部鋼板で囲まれたコンクリートの支圧力となって各部材に容易に伝達される。SC鋼板接合部に発生する圧縮力は、その大半がコンクリートの圧縮力として十分伝達可能である。また、双方の端部鋼板の支圧力により作用するせん断力は、必要に応じて、一般の鉄筋コンクリート構造の柱と同様の配筋をすることにより伝達可能となる。
【0041】
【発明の効果】
本発明は、SC鋼板ユニット又は表面鋼板相互を施工現場にて溶接接合する必要がないので、以下の効果を有し、大幅な施工性と経済性の向上を実現でき、様々な鋼板コンクリート溝造(SC構造)に適用することが可能となった。その具体的効果として下記のようなものがある。
【0042】
(1)膨大な量(溶接長さ)の現場溶接が不要となり、施工現場での工数が大幅に低減した。
(2)従来技術では膨大な溶接量となるユニット相互の表面鋼板の継手が機械的な継手となり、施工性が大幅に改善された。
(3)SC鋼板ユニット相互の取り付けに必要な溶接は、全て工場溶接によることが可能となったので、信頼性が向上した。また、現場溶接状況確認のための特別な溶接管理が不要となり、溶接管理のための施工現場の工数が大幅に削減された。
【0043】
(4)SC鋼板ユニット相互の間隔、目違い等の据え付け精度による誤差及び部材の製作上の誤差等の誤差吸収が容易となり施工性が飛躍的に向上した。
(5)気候によって施工可能日が限定されず、特別の養生が必要でなくなった。
【0044】
【図面の簡単な説明】
【図1】SC鋼板ユニット相互を連結し、該SC鋼板ユニットの据え付け後にコンクリートを打設してなる鋼板コンクリート構造の水平方向の継手構造の断面図及び正面図。
【図2】鋼板コンクリート構造の鉛直方向の継手構造の断面図及び正面図。
【図3】SC鋼板ユニット相互を連結し、該SC鋼板ユニットの据え付け後にコンクリートを打設してなる他の実施例の鋼板コンクリート構造の水平方向の継手構造の断面図及び正面図。
【図4】鋼板コンクリート構造の継手構造の拡大断面図。
【図5】鋼板コンクリート構造の鉛直方向の他の実施例の継手構造の断面図及び正面図。
【図6】SC鋼板ユニット相互を連結し、該SC鋼板ユニットの据え付け後にコンクリートを打設してなる他の実施例の鋼板コンクリート構造の水平方向の継手構造の断面図及び正面図。
【図7】鋼板コンクリート構造の鉛直方向の他の実施例の継手構造の断面図及び正面図。
【図8】鋼板コンクリート構造の水平方向の継手構造の拡大断面図。
【図9】鋼板コンクリート構造の鉛直方向の継手構造の拡大断面図。
【図10】SC鋼板ユニット相互を連結し、該SC鋼板ユニットの据え付け後にコンクリートを打設してなる他の実施例の鋼板コンクリート構造の水平方向の継手構造の断面図及び正面図。
【図11】(a)鋼板コンクリート構造の水平方向の継手構造の拡大断面図。
(b)鋼板コンクリート構造の水平方向の継手構造の他の実施例の拡大断面図。
【図12】鋼板コンクリート構造の鉛直方向の他の実施例の継手構造の断面図及び正面図。
【図13】鋼板コンクリート構造の水平方向の継手構造の断面図。
【図14】鋼板コンクリート構造の鉛直方向の他の実施例の継手構造の断面図及び正面図。
【図15】鋼板コンクリート構造の水平方向の継手構造の断面図。
【図16】鋼板コンクリート構造の鉛直方向の他の実施例の継手構造の断面図及び正面図。
【図17】(a)図18のaーaの断面図。
(b)図18のbーbの断面図。
【図18】鋼板コンクリート構造の他の実施例の水平方向の継手構造の断面図。
【図19】鋼板コンクリート構造の水平方向の他の実施例の継手構造の断面図。
【図20】鋼板コンクリート構造の水平方向の他の実施例の継手構造の正面図。
【図21】鋼板コンクリート構造の水平方向の従来例の継手構造の断面図及び正面図。
【図22】鋼板コンクリート構造の鉛直方向の従来例の継手構造の断面図及び正面図。
【符号の説明】
1、2、3、4、13、14、15、16、21、22、23、24、31、32、33、34、41、42、43、44、61、62、63、64、81、82、83、84・・SC鋼板
5、6、7、8、39、45、46、47、48、51、52、65、66、67、68、85、86・・スタッド
9、10、17、18、25、26、35、36・・連結鋼板
12・・ずれ止め鋼板
19、28、38・・鋼板
20、29・・定着ボルト、定着部を有する鋼棒等
11、27、37・・鋼棒或いは鋼板
49、50・・連結金物
53、54、55、56・・孔
69、70・・接合部
71・・鋼棒
89・・接合部
90・・開放部[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a surface steel plate disposed with a predetermined space on a member of a building or a structure such as a power generation facility, a general industrial facility, an office building, and an apartment house, concrete filled in the space, and In a steel plate concrete structure (SC structure), which is a composite structure composed of a stiffening and misalignment prevention mechanism such as a stud for making both of them into a body, an SC steel plate unit comprising the surface steel plate or the surface steel plate and its constituent materials The present invention relates to joint structures such as horizontal joints and vertical joints.
[0002]
[Prior art]
Conventionally, a steel plate concrete structure (SC structure) is a structural type having superior proof stress and deformation performance compared to a conventional reinforced concrete structure by integrating a surface steel plate and concrete. In addition, the SC structure can be used as a structural material that also serves as a temporary formwork when casting concrete, so that the steel bars and styling required in the reinforced concrete structure are not required, resulting in a significant increase in man-hours. It was possible to reduce the construction period and shorten the construction period.
[0003]
In addition, the construction of each member of the SC structure is generally carried out after manufacturing an SC steel plate unit made of a surface steel plate and a temporary steel material for maintaining its shape at a factory or a nearby processing plant, It was installed and assembled into a predetermined shape, and the SC steel plate units were joined together by field welding.
Further, the SC steel plates are directly assembled at the construction site and attached by welding the SC steel plates to each other. In any case, after assembling and joining by welding means, the concrete type is filled with concrete, and when the concrete is hardened, it has a structural type that expresses the required strength as a composite integrated structure consisting of surface steel plate and concrete Met.
[0004]
In addition to joining by the above-mentioned field welding, joining means by SC steel plate unit or SC steel plate by bolt joining or the like can be considered, but it is not practical in the following points, and has a problem in practical use.
(1) An enormous amount of bolting needs to be performed, which increases the number of man-hours at the construction site.
(2) When the wall thickness is thin, it is difficult to work from the inside and bolting cannot be performed.
(3) The head of the bolt is exposed to the outside of the surface steel plate, so that it is conspicuous in appearance, and the effective volume of the space to be configured is reduced.
[0005]
[Problems to be solved by the invention]
As described above, the steel plate concrete structure (SC structure) generally has extremely excellent performance in terms of structure, but on the construction surface, it is necessary to weld and join the SC steel plate units at the construction site. It had the following problems to be solved.
[0006]
21 and 22 show examples of general joining by field welding of conventional SC steel plate units.
(1) In order to join the SC steel plate units to each other, it is necessary to perform on-site welding (Y portion in FIGS. 21 and 22) with a huge amount (welding length), and the number of man-hours at the construction site increases. .
(2) Enormous amounts of surface steel plate joints between units must all be welded on site, and workability is poor.
(3) On site welding, it is impossible to secure a good construction environment similar to factory welding, and it is difficult to ensure reliability, and welding management throughout the entire process for checking the welding status is essential. Become. In addition, man-hours for welding management are added.
[0007]
(4) Butt welding is required to reliably convey the strength of the surface steel plates to be joined to each other, but the accuracy of the weld joint spacing, misinterpretation, etc. is determined by the unit installation accuracy. Securing accuracy is difficult.
(5) Since the units are welded together, it is necessary to absorb errors due to the installation accuracy of each unit in construction, but there is a limit to the error absorption width in field welding. In particular, when the surface steel plates around the entire unit are joined by field welding, the absorption becomes difficult.
(6) The reliability and construction accuracy of on-site welding depend on the construction environment, and the workable days are limited by the climate, or appropriate curing is required.
[0008]
[Means for Solving the Problems]
The present invention eliminates the on-site welding required in the construction procedure in the prior art while securing the excellent properties of the steel plate concrete structure (SC structure), and is composed of a surface steel plate or a surface steel plate and its constituent materials. It provides a joint structure between steel plate units. In addition, the leak from the joint part of the concrete with which it fills inside can be prevented reliably by providing the said joint part with a seal | sticker, and the function as a formwork can be achieved.
[0009]
In the present invention, as a joint structure that achieves the above object, as shown in FIGS. 1 to 9, an H type or an I type made of a steel rod or the like such as a steel plate or a reinforcing bar at a position straddling the SC steel plate units to be joined. A joint structure of a steel plate concrete structure is provided in which the joint members are arranged so that stress generated on the surface steel plate of the SC steel plate unit is transmitted by the concrete cast after the SC steel plate unit is installed.
[0010]
Further, as shown in FIGS. 10 to 12, an H-type or I-type joint member made of a steel plate with a stud or the like is arranged at a position straddling the SC steel plate unit, covers the joint portion, and installs the SC steel plate unit. There is provided a joint structure of a steel plate concrete structure configured to transmit stress generated in a surface steel plate of an SC steel plate unit by concrete to be placed later.
[0011]
Further, as shown in FIGS. 13 to 16, the SC steel plate units are joined to each other by a stepped portion or an uneven portion formed at the end thereof, and the SC steel plate units are mechanically connected to each other by a connecting tool such as a bolt from the outside of the joined portion. And a joint structure of a steel plate concrete structure configured to transmit stress generated on the surface steel plate of the SC steel plate unit by the concrete cast in the space of the SC steel plate unit after installation of the SC steel plate unit.
[0012]
Also, as shown in FIG. 17 to FIG. 20, the SC steel plate unit having the concavo-convex shape so that the end portions are engaged with each other is arranged by combining the concavo-convex portions of the SC steel plate unit with each other, Provided is a steel plate concrete joint structure configured to transmit stress generated in a surface steel plate of an SC steel plate unit by concrete placed in a space.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
1 and 2 show an embodiment of a joint structure of a steel plate concrete structure according to the present invention. The surface steel plates (hereinafter referred to as SC steel plates in the examples) 1 and 2 are disposed to face each other with a predetermined space A. Other
[0014]
An SC steel plate unit is formed by each of the
[0015]
An H-shaped or I-shaped joint member is formed by the connecting
[0016]
FIG. 1 shows the joint structure in the horizontal direction of the SC steel plate unit, while FIG. 2 shows the joint structure in the vertical direction. Similarly to the horizontal joint structure, the vertical joint structure includes SC steel plate units made of
[0017]
FIG. 3 shows another example of the joint structure of the steel plate concrete structure according to the present invention. As in the first embodiment, the
The
[0018]
As shown in the enlarged cross-sectional view of FIG. 4, the
A joint member is formed by the connecting
[0019]
FIG. 3 shows the horizontal joint structure of the SC steel plate unit, while FIG. 5 shows the vertical joint structure. Similarly to the horizontal joint structure, the vertical joint structure is composed of SC steel plate units made of
[0020]
FIG. 6 shows another example of the joint structure of the steel plate concrete structure according to the present invention. Similarly to the first and second embodiments, the
The
[0021]
As shown in FIG. 6, a
A joint member is formed by the connecting
[0022]
FIG. 6 shows the horizontal joint structure of the SC steel plate unit, while FIG. 7 shows the vertical joint structure. The vertical joint structure is similar to the horizontal joint structure in that the SC steel plate unit composed of SC steel plates 21 'to 24' is connected to steel plates 25 'and 26', steel bars or steel plates 27 ', cylindrical protrusions 29', and the like. It is connected by a joint member.
[0023]
FIG. 8 shows another example of the joint structure of the steel plate concrete structure according to the present invention. As in the first to third embodiments, the
An SC steel plate unit is formed by the
[0024]
On the steel bar or
[0025]
8 shows the joint structure in the horizontal direction of the SC steel plate unit, while FIG. 9 shows the joint structure in the vertical direction. The vertical joint structure is similar to the horizontal joint structure in that the SC steel plate unit made of the steel plates 31 'to 34' protrudes from the connecting steel plates 35 'and 36', the steel bar or the steel plate 37 ', and the steel plate 37'. The
[0026]
The joint metal fittings shown in FIGS. 1 to 9 serve not only to fix SC steel plates or steel bars such as reinforcing bars so as to be positioned across the SC steel plate units to be joined, but also to install SC steel plate units. It can be installed in advance to serve as a guide when installing the SC steel plate unit.
Furthermore, by arranging the positional relationship between the joint hardware and the SC steel plate as shown in the enlarged cross-sectional view of FIG. 4, an error in the production accuracy of the SC steel plate unit or a deviation in the installation of the joint hardware can be easily absorbed. Can be joined together.
With the above configuration, SC steel plate or SC steel plate unit composed of SC steel plate unit and its constituent materials, which does not require on-site welding that is always required in the construction procedure in the past while ensuring the superior performance of SC steel plate Joint becomes possible.
[0027]
In addition to the joint structure described above, the structure of the following joint member also makes it possible to join an SC steel sheet or SC steel sheet that does not require on-site welding and an SC steel sheet unit made of the constituent material.
FIG. 10 shows another embodiment of the joint structure of the steel plate concrete structure of the present invention. The
[0028]
SC steel plate units are formed by the
[0029]
Since the
[0030]
FIG. 10 shows the joint structure in the horizontal direction of the SC steel plate unit, while FIG. 12 shows the joint structure in the vertical direction. The vertical joint structure is similar to the horizontal joint structure in that the SC steel plate units made of
Moreover, as shown in FIG.11 (b), the
In FIG.11 (b), the stud and hole which were formed in the edge part are connected so that the positional relationship may be reversed in the
[0031]
FIG. 13 shows another embodiment of the joint structure of the steel plate concrete structure of the present invention.
As shown in FIG. 13, the
[0032]
An end portion of the SC steel plate unit composed of the
[0033]
Similar to the fifth embodiment, by forming a large hole in advance in the
[0034]
In addition, it is easy to maintain the shape of the SC steel plate unit by fixing the joint including the
[0035]
13 shows the joint structure in the horizontal direction of the SC steel plate unit, while FIG. 14 shows the joint structure in the vertical direction. Similarly to the horizontal joint structure, the vertical joint structure is formed by connecting SC steel plate units made of
The joint part shown in FIGS. 15 and 16 shows a structure in which the structure of the joint part is a phased structure in which one side is missing.
[0036]
FIG. 17 shows another embodiment of the joint structure of the steel plate concrete structure of the present invention.
As shown in FIG. 17, the
[0037]
In FIG. 17A, a joint 89 having a semicircular or rectangular shape is integrally formed at the end of an SC steel plate unit composed of
The joining
[0038]
As shown in FIG. 18, the
[0039]
FIG. 18 shows a view in which the
[0040]
The tensile force generated at the SC steel plate joined portion is easily transmitted to each member as a support pressure of the concrete surrounded by the end steel plates of the projecting portions that are semicircular or rectangular. Most of the compressive force generated at the SC steel plate joint can be sufficiently transmitted as the compressive force of concrete. Moreover, the shear force which acts by the supporting pressure of both end steel plates can be transmitted by arranging the same reinforcing bars as those of a general reinforced concrete structure as necessary.
[0041]
【The invention's effect】
Since the present invention does not require the SC steel plate unit or the surface steel plates to be welded to each other at the construction site, it has the following effects, can realize a significant improvement in workability and economy, and various steel plate concrete groove structures. It became possible to apply to (SC structure). The specific effects are as follows.
[0042]
(1) A huge amount (welding length) of on-site welding is no longer required, and the number of man-hours at the construction site is greatly reduced.
(2) In the prior art, the joints between the surface steel plates of the units, which require a huge amount of welding, became mechanical joints, and the workability was greatly improved.
(3) Since all the welding necessary for the attachment of the SC steel plate units can be performed by factory welding, the reliability is improved. In addition, special welding management for confirming the on-site welding status is no longer necessary, and the number of construction sites for welding management is greatly reduced.
[0043]
(4) It is easy to absorb errors such as errors due to installation accuracy such as distance between SC steel plate units, misalignment, etc., and errors in production of members, and the workability is dramatically improved.
(5) The workable days are not limited by the climate, and no special curing is required.
[0044]
[Brief description of the drawings]
FIG. 1 is a cross-sectional view and a front view of a horizontal joint structure of a steel plate concrete structure in which SC steel plate units are connected to each other and concrete is placed after the SC steel plate unit is installed.
FIG. 2 is a cross-sectional view and a front view of a joint structure in a vertical direction of a steel plate concrete structure.
FIG. 3 is a cross-sectional view and a front view of a horizontal joint structure of a steel plate concrete structure of another embodiment in which SC steel plate units are connected to each other and concrete is placed after the SC steel plate unit is installed.
FIG. 4 is an enlarged sectional view of a joint structure of a steel plate concrete structure.
FIG. 5 is a cross-sectional view and a front view of a joint structure according to another embodiment in the vertical direction of a steel plate concrete structure.
FIG. 6 is a cross-sectional view and a front view of a horizontal joint structure of a steel plate concrete structure of another embodiment in which SC steel plate units are connected to each other and concrete is placed after the SC steel plate unit is installed.
FIG. 7 is a cross-sectional view and a front view of a joint structure according to another embodiment of the vertical direction of the steel plate concrete structure.
FIG. 8 is an enlarged sectional view of a horizontal joint structure of a steel plate concrete structure.
FIG. 9 is an enlarged cross-sectional view of a vertical joint structure of a steel plate concrete structure.
FIG. 10 is a sectional view and a front view of a horizontal joint structure of a steel plate concrete structure of another embodiment in which SC steel plate units are connected to each other and concrete is placed after the SC steel plate unit is installed.
FIG. 11A is an enlarged cross-sectional view of a horizontal joint structure of a steel plate concrete structure.
(B) The expanded sectional view of the other Example of the joint structure of the horizontal direction of a steel plate concrete structure.
FIG. 12 is a cross-sectional view and a front view of a joint structure according to another embodiment of the vertical direction of the steel plate concrete structure.
FIG. 13 is a cross-sectional view of a horizontal joint structure of a steel plate concrete structure.
FIG. 14 is a cross-sectional view and a front view of a joint structure of another embodiment in the vertical direction of a steel plate concrete structure.
FIG. 15 is a cross-sectional view of a horizontal joint structure of a steel plate concrete structure.
FIG. 16 is a cross-sectional view and a front view of a joint structure according to another embodiment of the steel plate concrete structure in the vertical direction.
FIG. 17A is a cross-sectional view taken along the line aa in FIG.
(B) Sectional view of bb in FIG.
FIG. 18 is a cross-sectional view of a joint structure in the horizontal direction according to another embodiment of the steel plate concrete structure.
FIG. 19 is a cross-sectional view of a joint structure according to another embodiment in the horizontal direction of a steel plate concrete structure.
FIG. 20 is a front view of a joint structure according to another embodiment of the horizontal direction of the steel plate concrete structure.
FIG. 21 is a cross-sectional view and a front view of a joint structure of a conventional example of a steel plate concrete structure in the horizontal direction.
FIG. 22 is a cross-sectional view and a front view of a conventional joint structure in the vertical direction of a steel plate concrete structure.
[Explanation of symbols]
1, 2, 3, 4, 13, 14, 15, 16, 21, 22, 23, 24, 31, 32, 33, 34, 41, 42, 43, 44, 61, 62, 63, 64, 81, 82, 83, 84 ·· SC steel plate
5, 6, 7, 8, 39, 45, 46, 47, 48, 51, 52, 65, 66, 67, 68, 85, 86
9, 10, 17, 18, 25, 26, 35, 36 .. Connecting steel plate
12. ・ Steel prevention steel plate
19, 28, 38 ... Steel plate
20, 29 .. Fixing bolt, steel bar with fixing part, etc.
11, 27, 37 ... Steel bars or steel plates
49, 50 ... Consolidated hardware
53, 54, 55, 56 .. hole
69, 70 .. Joint
71 ... Steel bars
89..Joint part
90 .. Opening part
Claims (8)
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2001239551A JP3899866B2 (en) | 2001-08-07 | 2001-08-07 | Joint structure of steel plate concrete structure |
| US10/205,541 US20030029111A1 (en) | 2001-08-07 | 2002-07-25 | Joint structure of steel plate concrete structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2001239551A JP3899866B2 (en) | 2001-08-07 | 2001-08-07 | Joint structure of steel plate concrete structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2003049489A JP2003049489A (en) | 2003-02-21 |
| JP3899866B2 true JP3899866B2 (en) | 2007-03-28 |
Family
ID=19070284
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2001239551A Expired - Lifetime JP3899866B2 (en) | 2001-08-07 | 2001-08-07 | Joint structure of steel plate concrete structure |
Country Status (2)
| Country | Link |
|---|---|
| US (1) | US20030029111A1 (en) |
| JP (1) | JP3899866B2 (en) |
Families Citing this family (41)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| EP2205617A4 (en) * | 2007-11-06 | 2013-10-16 | Siemens Healthcare Diagnostics | SPECIFIC OLIGONUCLEOTIDE SEQUENCES OF HEPATITIS B VIRUS (HBV) |
| JP5166134B2 (en) * | 2008-06-24 | 2013-03-21 | ショーボンド建設株式会社 | Installation structure of ultra-high-strength fiber reinforced concrete plates in concrete structures |
| JPWO2010098401A1 (en) * | 2009-02-26 | 2012-09-06 | 独立行政法人国立高等専門学校機構 | Concrete stress distribution structure, concrete stress distribution system and concrete structure construction method |
| EP2236686A1 (en) * | 2009-04-03 | 2010-10-06 | F.J. Aschwanden AG | Reinforcing element for absorbing forces in concrete slabs in the area of supporting elements |
| JP5737548B2 (en) * | 2009-09-28 | 2015-06-17 | 清水建設株式会社 | Steel plate concrete structure |
| KR101011070B1 (en) * | 2010-09-14 | 2011-01-25 | 한국수력원자력 주식회사 | Joining method between steel plate concrete structure and heterogeneous structure |
| JP2013104172A (en) * | 2011-11-10 | 2013-05-30 | Shimizu Corp | Steel plate concrete structure |
| KR101426249B1 (en) * | 2012-09-10 | 2014-08-05 | 한국수력원자력 주식회사 | Mechanical connection unit for the rc-sc connection |
| CN103590509B (en) * | 2013-11-27 | 2016-03-02 | 四川华构住宅工业有限公司 | Based on the wall wall connecting joint structure of assembled architecture |
| CN103850366A (en) * | 2014-01-15 | 2014-06-11 | 浙江杭萧钢构股份有限公司 | C-shaped steel pipe bundle composite structure |
| CN103850348A (en) * | 2014-01-15 | 2014-06-11 | 浙江杭萧钢构股份有限公司 | Industrial steel tube bindle composite structure building system |
| CN103850349A (en) * | 2014-01-15 | 2014-06-11 | 浙江杭萧钢构股份有限公司 | Frame-steel pipe bundle combined structure system for industrial residential building |
| CN103806529A (en) * | 2014-01-15 | 2014-05-21 | 浙江杭萧钢构股份有限公司 | T-shaped steel pipe bunch combined structure |
| CN103850367A (en) * | 2014-01-15 | 2014-06-11 | 浙江杭萧钢构股份有限公司 | L-shaped steel pipe bundle composite structure |
| CN103850347A (en) * | 2014-01-15 | 2014-06-11 | 浙江杭萧钢构股份有限公司 | Steel pipe bundle combined structure system for industrial residential building |
| CN103850391A (en) * | 2014-01-15 | 2014-06-11 | 浙江杭萧钢构股份有限公司 | Linear steel tube bundle composite structure |
| CN103912074B (en) * | 2014-01-26 | 2016-06-08 | 杭萧钢构股份有限公司 | A kind of framework-steel pipe bundle and steel plate concrete shear wall combined structure system |
| CN103967126A (en) * | 2014-03-31 | 2014-08-06 | 浙江杭萧钢构股份有限公司 | Steel tube bundle composite structure composed of H-shaped steel and C-shaped steel webs |
| CN104047379A (en) * | 2014-05-05 | 2014-09-17 | 浙江杭萧钢构股份有限公司 | Steel tube bundle composite structure shear wall field splice node |
| CN104404985B (en) * | 2014-10-08 | 2016-10-05 | 中国十七冶集团有限公司 | The construction method of basement bottom plate rear pouring tape waterproof construction |
| KR101520002B1 (en) * | 2015-01-05 | 2015-05-14 | (주)세종알앤디 | Precast Concrete Member With Assembly Plate And Fixing Channel |
| JP2016205100A (en) * | 2015-04-28 | 2016-12-08 | 清水建設株式会社 | Steel plate concrete structure |
| CN105522500B (en) * | 2016-01-28 | 2017-03-29 | 中交第二航务工程局有限公司 | Steel beam column non-detachable mold massing polish positioner |
| CN106049756A (en) * | 2016-05-20 | 2016-10-26 | 西安建筑科技大学 | Multi-cavity concrete filled steel tube composite column adopting rectangular steel tubes and manufacturing method |
| CN106013607A (en) * | 2016-05-20 | 2016-10-12 | 西安建筑科技大学 | Multi-cavity concrete-filled steel pipe combination column with stiffening ribs and manufacturing method |
| CN105822020A (en) * | 2016-05-20 | 2016-08-03 | 西安建筑科技大学 | Multi-cavity concrete filled steel tube combined column with C-type steel and manufacturing method |
| CN105839853A (en) * | 2016-05-20 | 2016-08-10 | 西安建筑科技大学 | Multi-cavity steel pipe concrete composite column with rectangular steel pipe end column and method |
| CN106013499A (en) * | 2016-06-08 | 2016-10-12 | 浙江新华建设有限公司 | High-strength building wall body structure |
| CN106193376A (en) * | 2016-08-18 | 2016-12-07 | 安徽富煌建筑设计研究有限公司 | Steel frame combined steel plate shearing force wall structural system in steel house |
| CN106121044A (en) * | 2016-08-18 | 2016-11-16 | 安徽富煌建筑设计研究有限公司 | Steel frame and reinforced concrete shear wall structure system in steel house |
| FR3060622B1 (en) * | 2016-12-21 | 2020-10-02 | Electricite De France | PERMANENT CONCRETE FORMWORK AND PROCESS FOR MANUFACTURING A METAL-CONCRETE COMPOSITE STRUCTURE USING SUCH FORMWORK |
| CN107060142A (en) * | 2017-05-04 | 2017-08-18 | 浙江绿筑集成科技有限公司 | A kind of compound shear wall being made up of H profile steel and T-steel and preparation method |
| CN107700473B (en) * | 2017-08-24 | 2023-03-21 | 中铁第六勘察设计院集团有限公司 | I-steel joint welded with stud |
| JP7210237B2 (en) * | 2018-11-15 | 2023-01-23 | ジオスター株式会社 | Concrete member connection structure and precast concrete member connection method |
| CN109629669A (en) * | 2019-01-14 | 2019-04-16 | 重庆大学 | A kind of dual peacetime assembled dismountable steel structure system |
| US11352786B2 (en) * | 2019-08-19 | 2022-06-07 | WSP USA, Inc. | Constructing buildings with modular wall structure |
| US20220145619A1 (en) * | 2020-11-06 | 2022-05-12 | Nelson Stud Welding, Inc. | Concrete wall frame assembly and method of manufacturing same |
| JP7680223B2 (en) * | 2021-02-26 | 2025-05-20 | 鹿島建設株式会社 | Steel plate concrete structure |
| CN113931340B (en) * | 2021-10-09 | 2022-07-05 | 湖南大学设计研究院有限公司 | Assembled semi-embedded external wall panel and building |
| CN114541616B (en) * | 2022-03-29 | 2024-04-02 | 郴州远大住宅工业有限公司 | Prefabricated wallboard connecting node and construction method thereof |
| JP2025529813A (en) * | 2022-08-19 | 2025-09-09 | ニュースケール パワー エルエルシー | Steel composite wall panel structure for use in nuclear reactor buildings and the like, and related systems and methods |
Family Cites Families (52)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US523425A (en) * | 1894-07-24 | cornell | ||
| US2731824A (en) * | 1956-01-24 | hadley | ||
| US667871A (en) * | 1900-10-17 | 1901-02-12 | Julian O Ellinger | Fireproof building structure. |
| US729299A (en) * | 1903-01-05 | 1903-05-26 | Clarence M Ellinger | Fireproof building structure. |
| US930611A (en) * | 1906-10-09 | 1909-08-10 | John C Pelton | Construction member. |
| US1135721A (en) * | 1908-02-03 | 1915-04-13 | Roy Henry Robinson | Method of constructing building-frames and analogous frames. |
| US1142805A (en) * | 1910-06-25 | 1915-06-15 | Universal Electric Welding Co | Form for concrete construction. |
| US1101983A (en) * | 1911-02-10 | 1914-06-30 | George H Barbour | Composite structure. |
| US1024312A (en) * | 1911-11-22 | 1912-04-23 | William J Connell | Concrete-structure stiffener. |
| US1250588A (en) * | 1915-09-30 | 1917-12-18 | Trussed Concrete Steel Co | Floor construction. |
| US1190725A (en) * | 1915-10-04 | 1916-07-11 | Minor E Chamberlain | Metallic lath. |
| US1328926A (en) * | 1916-06-10 | 1920-01-27 | Universal Electric Welding Com | Fencepost |
| US1653055A (en) * | 1926-01-30 | 1927-12-20 | Macomber Steel Company | Skeleton metal element for reenforced-concrete columns |
| US1688016A (en) * | 1927-06-23 | 1928-10-16 | Benjamin J Klaasen | Hollow metal joist |
| GB348855A (en) * | 1930-04-04 | 1931-05-21 | Bruno Bauer | Reinforcement for concrete columns |
| US1914065A (en) * | 1930-11-11 | 1933-06-13 | Bauer Bruno | Structure of concrete and iron columns |
| US1995477A (en) * | 1931-01-16 | 1935-03-26 | Ferrocon Corp | Composite building member |
| US2074320A (en) * | 1933-03-20 | 1937-03-23 | Bauer Bruno | Combination wrapping |
| US2987855A (en) * | 1958-07-18 | 1961-06-13 | Gregory Ind Inc | Composite tall-beam |
| US3246437A (en) * | 1962-10-17 | 1966-04-19 | Universal Moulded Fiber Glass | Joint for interconnecting panels |
| US3261135A (en) * | 1963-05-16 | 1966-07-19 | Martin C Knabe | Precast concrete beam and column joint construction |
| US3340664A (en) * | 1964-04-23 | 1967-09-12 | Gateway Erectors Inc | Concrete structure with butt spliced compression and tension reinforcement |
| DE1484979A1 (en) * | 1964-12-18 | 1969-05-14 | Salzgitter Ind | Reinforced concrete reinforcement for highly stressed structures |
| US3374592A (en) * | 1964-12-24 | 1968-03-26 | David B. Cheskin | Precast column with shear-head sections |
| GB1253033A (en) * | 1968-01-23 | 1971-11-10 | ||
| US3512819A (en) * | 1968-09-13 | 1970-05-19 | Foamcor Inc | Connector structure for modular panels and the like |
| US3606418A (en) * | 1969-03-10 | 1971-09-20 | Armco Steel Corp | Structural member |
| US3834095A (en) * | 1970-12-11 | 1974-09-10 | S Ohlson | Building construction and method |
| US3726551A (en) * | 1971-06-30 | 1973-04-10 | N Levenberg | Tubular rigid angled joint |
| US3998028A (en) * | 1973-07-30 | 1976-12-21 | John Pelletier | Furring and fireproofing protection clip assembly |
| US4014089A (en) * | 1975-02-21 | 1977-03-29 | Kajima Corporation | Method of connecting beams and columns of steel frame construction |
| US4409764A (en) * | 1976-08-02 | 1983-10-18 | Ennis H. Proctor | System and method for reinforced concrete construction |
| US4211045A (en) * | 1977-01-20 | 1980-07-08 | Kajima Kensetsu Kabushiki Kaisha | Building structure |
| US4125973A (en) * | 1977-03-28 | 1978-11-21 | Realsources, Inc. | Form assembly for building framework |
| LU77749A1 (en) * | 1977-07-12 | 1979-03-26 | Arbed | COMPOSITE BEAM |
| LU84966A1 (en) * | 1983-08-12 | 1985-04-24 | Arbed | COMPOSITE PROFILES |
| US5012622A (en) * | 1985-03-05 | 1991-05-07 | Shimizu Construction Co., Ltd. | Structural filler filled steel tube column |
| LU86063A1 (en) * | 1985-08-30 | 1987-03-06 | Arbed | COMPOSITE BEAM |
| US4901498A (en) * | 1985-09-23 | 1990-02-20 | Sohio Petroleum Company | T-headed stirrup for reinforced concrete structures |
| US5014478A (en) * | 1989-09-22 | 1991-05-14 | Insulated Panel Systems, Inc. | Panels and panel interlocking means |
| US5152112A (en) * | 1990-07-26 | 1992-10-06 | Iota Construction Ltd. | Composite girder construction and method of making same |
| US5050358A (en) * | 1990-08-01 | 1991-09-24 | Vladislavic Neven I | Structural members and building frames |
| US5259160A (en) * | 1990-09-24 | 1993-11-09 | Metalmeccania Carannante Spa | Knot for the connection of pillars and girders in spatial frames in metallic carpentry |
| US5392580A (en) * | 1992-05-06 | 1995-02-28 | Baumann; Hanns U. | Modular reinforcement cages for ductile concrete frame members and method of fabricating and erecting the same |
| DE4412598A1 (en) * | 1994-04-13 | 1995-10-19 | Zellner Wilhelm | Dowel bar for shear reinforcement |
| KR100189216B1 (en) * | 1996-11-14 | 1999-06-01 | 소광민 | Sectional steel house and the executing method thereof |
| JP3080911B2 (en) * | 1997-09-29 | 2000-08-28 | ゼンテリア株式会社 | Joint method of column and beam in building structure with heavy steel structure |
| US6295770B1 (en) * | 1999-12-29 | 2001-10-02 | Chyi Sheu | Steel frame building structure |
| DE10002383A1 (en) * | 2000-01-20 | 2001-07-26 | Oliver Matthaei | Transverse stressed steel or stressed concrete part has reinforcement layers on surfaces and a flat surface component placed at right angles to surface and over entire structural thickness between reinforcement layers |
| IT1316774B1 (en) * | 2000-02-18 | 2003-05-12 | Sergio Zambelli | REINFORCEMENT FOR PREFABRICATED CONCRETE PANELS, ADHESION, CONIL CONCRETE, IMPROVED |
| US6625943B1 (en) * | 2001-02-27 | 2003-09-30 | Peter S. Renner | Building interior construction system and method |
| US6829872B2 (en) * | 2002-03-19 | 2004-12-14 | William J. Wahlsteen | Process and device for connecting I-beams |
-
2001
- 2001-08-07 JP JP2001239551A patent/JP3899866B2/en not_active Expired - Lifetime
-
2002
- 2002-07-25 US US10/205,541 patent/US20030029111A1/en not_active Abandoned
Also Published As
| Publication number | Publication date |
|---|---|
| JP2003049489A (en) | 2003-02-21 |
| US20030029111A1 (en) | 2003-02-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3899866B2 (en) | Joint structure of steel plate concrete structure | |
| JP5635734B2 (en) | Beam-column joints and reinforcement hardware for beam-column joints | |
| WO2020209150A1 (en) | Clt structure | |
| JP4095534B2 (en) | Joint structure of column and beam in ramen structure and its construction method | |
| KR102027704B1 (en) | Prefabricated Steel Column Using Honeycomb Steel Plate And Manufacturing Method Thereof | |
| JP5275545B2 (en) | Seismic wall and its construction method | |
| JP6259381B2 (en) | Reinforcement structure of reinforced concrete structure and its construction method | |
| JP2000234443A (en) | Reinforcement structure for existing structures | |
| JPS5944443A (en) | Reinforced enclosure | |
| KR20220014074A (en) | Prefabricated module for composite hollow wall and composite hollow wall using the same | |
| JP5613466B2 (en) | Concrete wall mounting structure | |
| JP2003313951A (en) | Column and beam joint structure in composite structure building | |
| JP7780324B2 (en) | Earthquake-resistant reinforcement method | |
| JP4285427B2 (en) | Seismic reinforcement structure for buildings | |
| JP6139239B2 (en) | Structural members using existing steel | |
| JPH10219700A (en) | Joint structure of column base and steel underground beam | |
| KR20080057033A (en) | Double steel wall panel and manufacturing method thereof | |
| JP6460810B2 (en) | Joint structure of steel column and reinforced concrete beam | |
| JP2015510062A (en) | Turnbuckle to connect structural elements | |
| JP2011184900A (en) | Earthquake-resisting wall structure of building | |
| JP3651032B2 (en) | Basement structure | |
| JP3160730B2 (en) | Connecting columns and beams | |
| JPS6023371Y2 (en) | composite precast concrete beam | |
| JP7313770B2 (en) | Beam reinforcement structure, structure for beam reinforcement, steel frame structure, and beam reinforcement method | |
| JPH0833016B2 (en) | Concrete assembling basement skeleton structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050112 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060905 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20061102 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061212 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061218 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 3899866 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100112 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130112 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160112 Year of fee payment: 9 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
| R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
| R371 | Transfer withdrawn |
Free format text: JAPANESE INTERMEDIATE CODE: R371 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| EXPY | Cancellation because of completion of term |