JP3905761B2 - Ventilation device in the tunnel - Google Patents
[go: Go Back, main page]

JP3905761B2 - Ventilation device in the tunnel - Google Patents

Ventilation device in the tunnel Download PDF

Info

Publication number
JP3905761B2
JP3905761B2 JP2002005126A JP2002005126A JP3905761B2 JP 3905761 B2 JP3905761 B2 JP 3905761B2 JP 2002005126 A JP2002005126 A JP 2002005126A JP 2002005126 A JP2002005126 A JP 2002005126A JP 3905761 B2 JP3905761 B2 JP 3905761B2
Authority
JP
Japan
Prior art keywords
air
outlet
tunnel
branch
face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002005126A
Other languages
Japanese (ja)
Other versions
JP2003206699A (en
Inventor
依早弥 横田
政昭 佐藤
菊池  茂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2002005126A priority Critical patent/JP3905761B2/en
Publication of JP2003206699A publication Critical patent/JP2003206699A/en
Application granted granted Critical
Publication of JP3905761B2 publication Critical patent/JP3905761B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Ventilation (AREA)
  • Duct Arrangements (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、トンネル工事における(切羽作業領域内の)粉塵濃度を低減するためのトンネル内の換気装置に関する。
【0002】
【従来の技術】
たとえば、山岳トンネルなどの掘削工事を行う際には、掘削作業に伴い大量の粉塵が生じる。このような粉塵がトンネル内に残存していると、作業者の健康を害する恐れがあるので、特に、切羽面近傍の作業領域(以下「切羽作業領域」という)における粉塵をトンネルの外部に排出するための換気装置が知られている。このような換気装置としては、一般に、いわゆる送気式の換気装置と排気式の換気装置がある。図7(a)に示すように、このうちの送気式の換気装置50は、トンネル2の上方位置において、トンネル2の坑口21から切羽作業領域22まで延在する送気風管51を有している。送気風管51の入口には、送風機52が設けられており、送気風管51内に外部の清浄な空気を導入している。送気風管51内に導入された清浄な空気は、送気風管51における吹出口53から吹き出され、切羽面23に吹き付けられる。この空気によって切羽面23の近傍に生じる粉塵を後方に吹き飛ばし、坑道24を介して坑口21から外部に排出して、トンネル2内の粉塵濃度を低減させる。
【0003】
一方、図7(b)に示すように、排気式の換気装置60は、トンネル2の内部における切羽作業領域22に設けられた短尺の短尺送気風管61を備えている。短尺送気風管61の入口には、局所送風機62が設けられており、短尺送気風管61内に空気を導入している。短尺送気風管61の吹出口63から吹き出された空気は、切羽面23に向けて吹き出される。また、排気式の換気装置60は、トンネル2の上方位置において、トンネルの切羽作業領域22から坑口21まで延在する排気風管64を備えている。排気風管64における切羽面23側の開口部である入口には、送風機65が設けられている。そして、送風機65を駆動することにより、短尺送気風管61の吹出口から吹き出された空気とともに、切羽作業領域22における粉塵を、排気風管64を介してトンネル2の外部に排出して、トンネル2内の粉塵濃度を低減させる。
【0004】
【発明が解決しようとする課題】
ところで、前記従来におけるトンネル内の換気装置は、いずれも切羽面に対して空気を直接吹き出してトンネル内の粉塵を排出するようにしている。ここで、トンネル内の切羽面近傍位置における粉塵濃度を低減させるためには、切羽面近傍位置に供給する空気の量(以下「換気量」という)を多くすることが考えられる。
【0005】
しかし、粉塵濃度を低減させるために供給される空気は、切羽面に吹き出されるため、粉塵濃度を低減することはできるものの、粉塵量が増加する傾向がみられる。ここで、上記従来の換気装置のうち、排気式の換気装置で行った換気作業時における換気量、切羽作業領域での粉塵濃度、および粉塵発生量の測定例を表1に示す。なお、切羽作業領域ではコンクリート吹付け作業を行っており、粉塵濃度は切羽面23から50mの位置で測定した。
【0006】
【表1】

Figure 0003905761
【0007】
表1からわかるように、換気量を500m3/minから1000m3/minと2倍にしたとき、粉塵濃度は確かに低下したが、粉塵発生量は逆におよそ40%増加していた。このように、換気量を増加させると、粉塵濃度の低減を図ることはできるものの、粉塵量が増大してしまうので、結果的には換気効率が悪くなるという問題があった。
【0008】
そこで、本発明の課題は、トンネルの切羽作業領域における粉塵濃度を低減させるために切羽作業領域の換気を図る際に、粉塵の発生量を極力少なくし、効率よく換気を行うことができるようにすることにある。
【0009】
【課題を解決するための手段】
上記課題を解決した本発明は、トンネルの内部を換気するトンネル内の換気装置において、トンネルの切羽面に向けて空気を吹き出す吹出口が形成された送気風管を備え、送気風管には、内部を通風する空気を分流させる分岐路が形成されているとともに、分流された空気を、トンネル内のうちの切羽作業領域内における切羽面を避けた位置に吹き出す分岐吹出口が形成されており、吹出口および分岐吹出口から排出された空気が、分岐吹出口よりも坑口側に向けて流れており、坑口側に向けて流れる排気空気の風量は、吹出口から排出される吹出空気の風量と、分岐吹出口から排出される分岐吹出空気の風量の和とされていることを特徴とするものである。
【0010】
切羽面に直接空気を吹き付けると、その空気により粉塵の発生量が増加してしまう。この点、本発明に係る換気装置では、切羽作業領域内における切羽面を避けた領域に空気を供給して切羽作業領域の換気を行っている。このため、切羽作業領域に供給する空気の量を減らすことなく切羽面に対して吹き出す空気の量を低減させることができるので、粉塵発生量の増加を防止しながら、粉塵濃度の低減を図ることができる。
【0011】
また、上記課題を解決した本発明は、トンネルの内部を換気するトンネル内の換気装置において、トンネルの内部に設けられ、トンネルにおける切羽面に向けて空気を吹き出す吹出口が形成された短尺送気風管と、短尺送気風管における吹出口から吹き出された空気をトンネルの坑口側に送気する通風路を形成する排気風管を備え、短尺送気風管には、内部を通風する空気を分流させる分岐路が形成されているとともに、分流された空気を、トンネル内のうちの切羽作業領域内における切羽面を避けた位置に吹き出す分岐吹出口が形成されており、吹出口および分岐吹出口から排出された空気が、分岐吹出口よりも坑口側に向けて流れており、坑口側に向けて流れる排気空気の風量は、吹出口から排出される吹出空気の風量と、分岐吹出口から排出される分岐吹出空気の風量の和とされていることを特徴とするものである。
【0012】
このように、本発明に係る換気装置は、いわゆる排気式の換気装置にも利用することができる。
【0013】
ここで、前記短尺送気風管に導入される空気に含まれる粉塵を除去する集塵機が設けられているのが好適である。このような集塵機を設けておくことにより、短尺送気風管から排出される空気を清浄なものとすることができる。
【0014】
また、前記分岐吹出口は、前記切羽面に沿った方向に空気を吹き出すようにするのが好ましい。
【0015】
このように、分岐吹出口から切羽面に沿った方向に空気が吹き出されるようにすることにより、切羽作業領域における空気の流れを整然とさせることができるので、効率よい換気に寄与することができる。
【0016】
さらには、このとき、前記分岐吹出口は、前記吹出口から10m以内の位置に形成されているのが好ましい。分岐吹出口が吹出口から遠くに形成されていると、吹出口から吹き出され、粉塵を含む空気をトンネルの外に排出する際の空気の流れが円滑になりにくくなるからである。
【0017】
また、前記吹出口と前記分岐吹出口の分岐路に、風量調整機構が設けられている態様とするのが望ましい。このような風量調整機構を設けておくことにより、換気装置の使用状況に応じて、吹出口と分岐吹出口のそれぞれから排出される空気の割合を調整して、切羽作業領域の換気をさらに効率よく行うことができる。
【0018】
さらに、前記吹出口から前記切羽面までの距離および切羽作業の種類に基づいて、前記風量調整機構における開度を調整する制御装置が設けられているのが望ましい。かかる制御装置を設けることにより、さらに効率的に切羽作業領域の換気を行うことができる。
【0019】
【発明の実施の形態】
以下、図面を参照して、本発明の好適な実施形態について詳細に説明する。なお、同一要素には同一符号を用いるものとし、重複する説明は省略する。
【0020】
図1は、本発明の第1の実施形態に係るトンネル内の換気装置が設けられたトンネルの側断面図である。図1に示すように、本実施形態に係るトンネル内の換気装置1は、トンネル2内に設けられた、いわゆる送気式のものであり、送気風管11を有している。送気風管11は、トンネル2の坑口21から切羽作業領域22まで延在しており、清浄な空気を切羽作業領域22に対して送気する通風路を形成している。この切羽作業領域22の長さLは、切羽面23の近傍において作業が行われる領域であり、作業の種類により若干相違するが、たとえば切羽面23から30m〜100mの範囲に設定される。また、送気風管11は、坑道24の上部において、坑道24の長手方向に沿って設けられている。
【0021】
送気風管11の一端側には、入口11Aが形成され、他端側には、吹出口11Bが形成されている。入口11Aには、トンネル2の外部に設けられた送風機12が接続されている。送風機12は、トンネル2の外部における清浄な空気を送気風管11に供給している。また、吹出口11Bには、その開口面積を大きく維持するための図示しない保形部材が設けられている。吹出口11Bは、トンネル2の切羽面23に向けて開口しており、吹出口11Bからは、切羽面23に対して直接空気が吹き出される。
【0022】
また、切羽作業領域22の範囲内における送気風管11の途中位置には分岐管13が取り付けられている。分岐管13の先端には、切羽作業領域22内であって、切羽面23を避けた方向に空気を吹き出す分岐吹出口13Aが形成されている。この分岐吹出口13Aは、切羽面23に沿った方向を向いて形成されており、分岐吹出口13Aから吹き出される空気は、切羽面23に沿った方向、換言すれば切羽面23に平行する方向に流動する。吹出口11Bから分岐管13(分岐吹出口13A)までの距離は、10m以内、たとえば5m、3mなどとするのが望ましいが、10mを超える位置に設けることもできる。また、図2に示すように、送気風管11は、トンネル2の切羽面23側から見て、中央の最上部よりやや側方に寄せたわずかに低い位置に水平に設けられており、分岐管13は斜め下方を向いて取り付けられている。この分岐管13が向いている位置は、送気風管11が寄せられている位置の反対側を向いているので、分岐管13から吹き出された空気は、トンネル2における断面方向の全域に行き渡りやすくなっている。
【0023】
さらに、送気風管11における分岐管13が取り付けられている位置には、送気風管11内を通風する空気を分流させる分岐路14が形成されている。分岐路14は三つ又であり、そのうちの1つの流路が入口11Aに連通し、他の流路が吹出口11Bに連通し、さらに他の流路が分岐吹出口13Aに連通している。
【0024】
ここで、送気風管11は、たとえば折り畳み可能な蛇腹式のビニール管からなり、トンネル2を掘り進めているときに、その長さを長くすることができる。この蛇腹式の折り畳み部を分岐路14よりも坑口21側に設定しておくことにより、送気風管11を延長させた場合にも、吹出口11Bと分岐吹出口13Aの位置関係を一定に保つことができる。なお、分岐管13としてもビニール管が用いられている。
【0025】
また、図3に示すように、分岐路14には風量調整機構である風量調整ダンパ15が設けられている。風量調整ダンパ15は、分岐路14における吹出口11B側の開口面積と、分岐吹出口13A側の開口面積の比率を調整するものである。これらの開口面積の比率を調整することによって、吹出口11B側に流入する空気の量と、分岐吹出口13A側に流入する空気の量を調整している。
【0026】
風量調整ダンパ15は、分岐路14の開口面積を実際に調整するダンパ本体15Aと、ダンパ本体15Aを回動させるダンパモータ15Bを備えている。また、ダンパモータ15Bは、制御装置16に接続されている。この制御装置16には、距離センサ17および切羽作業種別センサ18が設けられている。距離センサ17としては、超音波式距離センサ、レーザ式距離センサ、など、適宜公知の距離センサを用いることができ、吹出口11Bから切羽面23までの距離を測定している。また、切羽作業種別センサ18では、切羽作業領域22で行われる作業を判断している。制御装置16では、吹出口11Bから切羽面23までの距離および切羽作業領域22で行われている作業の種別により、風量調整ダンパ15におけるダンパ本体15Aの開度を算出し、その開度となるようにダンパモータ15Bを制御している。切羽作業種別センサ18は、その作業が行われる際に使用されるツールを検出して作業を判別するものなどを用いることができるが、これに代えて、作業員が現在の作業を入力する形式のものを用いてもよい。
【0027】
また、このような制御装置や自動的な風量調整ダンパを用いることなく、たとえば手動で開度を調整可能な風量調整ダンパを用いることもできる。
【0028】
以上の構成を有する換気装置の作用について説明する。
【0029】
トンネル2における切羽作業領域22においては、たとえば発破作業、ずり出し作業、コンクリート吹付け(以下「吹付け」という)作業などの切羽作業が行われる。この切羽作業を行う際に生じる粉塵を除去してトンネル2内、特に、切羽作業領域22における粉塵濃度の低減を図るものである。トンネル2内の換気を行うには、送風機12を駆動して、送気風管11内に外気などの清浄な空気を供給する。送気風管11内に供給された清浄な空気は、送気風管11内を通って分岐路14に到達する。分岐路14においては、風量調整ダンパ15におけるダンパ本体15Aの開度により、供給された清浄な空気は、吹出口11B側および分岐吹出口13A側に分岐させる。
【0030】
吹出口11B側に吹き出された空気は、切羽面23に対して直接吹き出される。切羽面23に対して吹き出された吹出空気は、切羽作業によって発生する粉塵を吸収し、切羽面23に跳ね返されてトンネル2の坑口21側に流れる。一方、分岐吹出口13A側に吹き出された空気は、切羽作業領域22内であって、切羽面23よりも坑口21側の位置に排出される。分岐吹出口13Aから排出された分岐吹出空気は、切羽面23側から流れてくる吹出空気に合流して排出空気となり、坑口21に向けて、坑道24内を流れる。この排気空気の風量Qは、吹出空気の風量Q1と分岐吹出空気の風量Q2の和である。
【0031】
このとき、吹出口11Bから吹き出される吹出空気の気流が強いと、切羽面23における粉塵発生の原因となってしまう。ところが、換気装置1では、切羽作業領域22に吹き出す空気を吹出口11Bと分岐吹出口13Aに分割している。このため、切羽作業領域22に対して、換気のために供給する空気のうちの一部を、分岐吹出口13Aから分岐吹出空気として吹き出すことにより、吹出口11Bから吹き出す吹出空気の風量Q1を低減させることができ、気流を弱めることができる。その結果、切羽作業領域22の全体に供給する空気の風量(排気空気の風量と同等)Qを確保しながらも、切羽面23に吹き出す吹出空気の風量Q1を低減させ、その気流を弱めることができるので、粉塵の発生を防止することができる。したがって、発生させる粉塵の量を増大させることなく、切羽作業領域22における粉塵濃度を低減させることができ、その結果、効率よい換気を行うことができる。
【0032】
また、切羽作業領域22で行われる作業によっては、発生する粉塵の量が異なる。たとえば、発破作業で生じる粉塵は比較的少なく、ずり出し作業、吹付け作業などの作業で生じる粉塵は比較的多い。したがって、発破作業を行う際には、切羽面23に向けて吹き出す吹出空気の風量Q1を少なくし、分岐吹出空気の風量Q2の割合を増加させるのが好適である。また、ずり出し作業および吹付け作業を行う際には、吹出空気の風量Q1を多めにし、分岐吹出空気の風量Q2を減少させるのが好適である。
【0033】
このため、本実施形態に係る換気装置1では、分岐路14に設けた風量調整ダンパ15で吹出口11B側および分岐吹出口13A側に供給する空気の量を調整している。そして、たとえば粉塵の発生量が少ない発破作業を行う際には、吹出口11B側の開度を小さくし、分岐吹出口13A側の開度を大きくして吹出口11B側から排出される吹出空気の風量Q1を少なくし、分岐吹出口13Aから吹き出される分岐吹出空気の風量Q2を増加させる。また、粉塵の発生量が多いずり出し作業、吹付け作業を行う際には、吹出口11B側の開度を大きくし、分岐吹出口13A側の開度を小さくする。このようにして、大量に発生する粉塵を迅速に排出することができる。
【0034】
また、トンネル2の掘削作業が進むと、切羽面23と吹出口11Bとの距離が変わる。このような場合にも、吹出空気の風量Q1を調整するのが好適である。たとえば、トンネル2の掘削が進み、切羽面23と吹出口11Bとの距離が長くなった場合には、吹出口11Bから吹き出される吹出空気の風量Q1を多くし、分岐吹出空気の風量Q2を少なくする。また、送気風管11を伸ばし、切羽面23と吹出口11Bとの距離が短くなった場合には、吹出口11Bから吹き出される吹出空気の風量Q1を少なくし、分岐吹出空気の風量Q2を多くする。このように吹出空気の風量Q1と分岐吹出空気の風量Q2を調整することにより、切羽作業領域22を効率よく換気することができる。
【0035】
このような、吹出口11Bから切羽面23までの距離および切羽作業種別による吹出口11Bと分岐吹出口13Aとの空気の調整割合は、制御装置16を用いて行われる。制御装置16では、距離センサ17より出力される距離情報および切羽作業種別センサ18より出力される切羽作業種別情報に基づいて、風量調整ダンパ15におけるダンパ本体15Aの開度を算出する。そして、ダンパ本体15Aの開度が、算出されたダンパ本体15Aの開度となるように、ダンパモータ15Bを、たとえばフィードバック制御する。こうして、ダンパ本体15Aの開度を制御装置16によって調整することにより、吹出口11Bおよび分岐吹出口13Aに供給される空気の量を調整し、もって効率よい換気作業を行うことができる。
【0036】
また、図4に示すように、切羽作業領域22における下方位置であって、分岐吹出口13Aよりも坑口21寄りの位置に、集塵機19を設けることもできる。この集塵機19における坑口21側には、局所送風機20が設けられており、局所送風機20における坑口21側には、排気管20Aが設けられている。トンネル2内においては、切羽作業領域22における発破などの切羽作業のほか、坑道24における坑道作業領域25においても、作業員が土砂の搬送などの作業を行っている。このような坑道作業領域25に粉塵が混入された空気が流れると、坑道作業領域25の粉塵濃度が増加する。そこで、局所送風機20を作動させて、切羽作業領域22で発生した粉塵を含む空気を集塵機19で集塵する。この集塵機19により、切羽面23に跳ね返されて坑口21側に流れる排出空気に含まれる多量の粉塵は、集塵機19によって除去される。集塵機19によって粉塵を除去された空気は、排気管20Aから排出され、坑道作業領域25を通って坑口21の方向に流れる。したがって、坑道作業領域25を通過する空気からは粉塵が除去されているので、坑道作業領域25の粉塵濃度を増加させないようにすることができる。なお、集塵機19としては、粉塵を含む空気から粉塵を除去する機能を有する、たとえばバグフィルタを備えた乾式のもの、湿式のもの、あるいは電気式のものなど、適宜公知のものを用いることができる。
【0037】
次に、本発明の第2の実施形態について説明する。
【0038】
図5は、本実施形態に係るトンネル内の換気装置が設けられたトンネルの側断面図である。図5に示すように、本実施形態に係るトンネル内の換気装置3は、トンネル2内に設けられた、いわゆる排気式のものであり、長さが3〜10m程度の短尺であるたとえばビニール管からなる短尺送気風管31がトンネル2における切羽作業領域22に設けられている。短尺送気風管31における坑口21側には局所送風機32が取り付けられている。短尺送気風管31の切羽面23側の開口部は、空気を吹き出す吹出口31Aとなっており、吹出口31Aからは、切羽面23に対して直接空気が吹き出される。
【0039】
また、短尺送気風管31の途中位置には、短尺送気風管31の内部を通風する空気を分流させる三つ又の分岐路33が形成されている。この分岐路33の1つの流路が局所送風機32に連通し、他の流路が吹出口31Aに連通し、さらに他の流路がたとえばビニール管からなる分岐路33の先端に形成された分岐吹出口34Aに連通している。分岐管34における分岐吹出口34Aは、切羽作業領域22内における切羽面23を避けた位置に空気を吹き出すように、切羽面23に沿った方向を向いて形成されている。分岐吹出口34Aから吹き出される空気は、切羽面23に沿った方向に流動する。また、図示はしないが、分岐管34は、切羽面23側から見て斜め上方を向いて取り付けられている。このため、分岐吹出口34Aから吹き出される空気は、トンネル2の断面方向に円滑に行き渡りやすくなっている。
【0040】
さらに、トンネル2における上方位置には、短尺送気風管31における吹出口31Aから吹き出された空気をトンネル2の坑口21側に送気する通風路を形成する排気風管35が設けられている。排気風管35は、たとえばビニール管からなり、排気風管35の入口35A側には、送風機36が設けられている。送風機36は、切羽作業領域22内における多量の粉塵を含んだ空気を排気風管35の内部に導入する。排気風管35の内部に導入された多量の粉塵を含んだ空気は、排気風管35を通って、排出口35Bからトンネル2の外部に排出される。
【0041】
かかる本実施形態の換気装置3においても、第1の実施形態に係る換気装置1と同様の作業効果を奏することができる。
【0042】
切羽作業領域22内における発破、ずり出し、および吹付けなどの切羽作業が行われると、切羽作業領域22には多量の粉塵が発生する。換気装置3では、局所送風機32および送風機36を作動させる。局所送風機32を作動させると、トンネル2における切羽作業領域22の坑口21側から空気を短尺送気風管31に導入し、短尺送気風管31および分岐管34を経て切羽作業領域22に送気する。このとき、切羽作業領域22には、短尺送気風管31および分岐管34を経た空気がすべて導入されるが、切羽面23に対して直接吹き出されるのは、短尺送気風管31の吹出口31Aから吹き出された空気のみである。このため、吹出口31Aから切羽面23に吹き出される吹出空気の量を低減させ、その気流を弱めることにより、粉塵の発生量を抑制することができる。その一方で、切羽作業領域22に供給される空気の量を減らさないようにすることができるので、粉塵濃度は効果的に低減させることができ、その結果、効率よい換気を行うことができる。
【0043】
ここで、本実施形態に係る換気装置3における分岐路33にも、第1の実施形態と同様の風量調整ダンパや制御装置等を設けることもできる。このような風量調整ダンパ等を設け、切羽作業の種類等に応じて、風量調整を行うことにより、さらに効率的な換気を行うことができる。
【0044】
また、本実施形態に係る換気装置3では、図6に示すように、短尺送気風管31と局所送風機32の間に、短尺送気風管31に導入される空気に含まれる粉塵を除去する集塵機37を設けることもできる。このような集塵機37を設けることにより、坑道作業領域25で発生した粉塵を短尺送気風管31に導入する前に、集塵機37によって除去することができる。したがって、切羽作業領域22に供給される空気には、清浄な空気を供給することができるので、切羽作業領域22における換気をさらに効率的に行うことができる。
【0045】
以上、本発明の好適な実施形態について説明したが、本発明は上記の各実施形態に限定されるものではない。たとえば、上記の各実施形態では分岐管を1つずつ設けていたが、これを2つあるいは3つ以上設けることもできる。このとき、たとえば切羽作業の種類や吹出口から切羽面までの距離に応じて、複数の分岐管の一部のみから空気を吹き出すような調整をすることもできる。
【0046】
また、吹出口は切羽面に沿った方向に空気を吹き出しているが、ある程度前後方向に斜めに吹き出す態様とすることもできる。また、各種風管はビニール管を用いているが、樹脂製のパイプ管や鋼管などを用いることもできる。さらに、風量調整機構としては、ダンパ以外の空気流路切換手段を用いることができる。
【0047】
【発明の効果】
以上のとおり、本発明によれば、トンネルの切羽作業領域における粉塵濃度を低減させるために切羽作業領域の換気を図る際に、粉塵の発生量を極力少なくし、効率よく換気を行うことができるようにすることができる。
【図面の簡単な説明】
【図1】第1の実施形態に係る換気装置が設けられたトンネルの側断面図である。
【図2】図1のII-II線断面図である。
【図3】風量調整ダンパの制御部の構成図である。
【図4】図1の変形例に係る換気装置が設けられたトンネルの側断面図である。
【図5】第2の実施形態に係る換気装置が設けられたトンネルの側断面図である。
【図6】図5の変形例に係る換気装置が設けられたトンネルの側断面図である。
【図7】(a)は、従来の送気式の換気装置が設けられたトンネルの側断面図、(b)は従来の排気式の換気装置が設けられたトンネルの側断面図である。
【符号の説明】
1,3…換気装置
2…トンネル
11…送気風管
11B…吹出口
12…送風機
13…分岐管
13A…分岐吹出口
14…分岐路
15…風量調整ダンパ
16…制御装置
17…距離センサ
18…切羽作業種別センサ
19…集塵機
22…切羽作業領域
23…切羽面
31…短尺送気風管
31A…吹出口
32…局所送風機
33…分岐路
34A…分岐吹出口
34…分岐管
35…排気風管[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a ventilation device in a tunnel for reducing dust concentration (in a face work area) in tunnel construction.
[0002]
[Prior art]
For example, when excavating a mountain tunnel or the like, a large amount of dust is generated along with the excavation work. If such dust remains in the tunnel, it may harm the worker's health. In particular, dust in the work area near the face (hereinafter referred to as “face work area”) is discharged outside the tunnel. Ventilators for doing this are known. As such a ventilator, there are generally a so-called air supply type ventilator and an exhaust type ventilator. As shown in FIG. 7 (a), the air-feeding type ventilator 50 has an air-feeding wind pipe 51 extending from the well entrance 21 of the tunnel 2 to the face working area 22 at a position above the tunnel 2. is doing. A blower 52 is provided at the inlet of the air supply duct 51, and external clean air is introduced into the air supply duct 51. The clean air introduced into the air supply pipe 51 is blown out from the outlet 53 in the air supply pipe 51 and blown to the face surface 23. The dust generated in the vicinity of the face surface 23 by this air is blown backward, and is discharged to the outside from the well opening 21 through the tunnel 24 to reduce the dust concentration in the tunnel 2.
[0003]
On the other hand, as shown in FIG. 7B, the exhaust type ventilation device 60 includes a short short air supply air pipe 61 provided in the face work area 22 inside the tunnel 2. A local blower 62 is provided at the inlet of the short air supply tube 61, and air is introduced into the short air supply tube 61. The air blown out from the air outlet 63 of the short air supply tube 61 is blown out toward the face surface 23. The exhaust type ventilation device 60 includes an exhaust wind pipe 64 extending from the tunnel face work area 22 to the wellhead 21 at a position above the tunnel 2. A blower 65 is provided at an inlet which is an opening on the face surface 23 side of the exhaust wind pipe 64. Then, by driving the blower 65, together with the air blown from the outlet of the short air supply duct 61, the dust in the face work area 22 is discharged to the outside of the tunnel 2 through the exhaust duct 64, The dust concentration in the tunnel 2 is reduced.
[0004]
[Problems to be solved by the invention]
By the way, all of the conventional ventilation devices in the tunnel are configured to discharge the dust in the tunnel by blowing air directly to the face. Here, in order to reduce the dust concentration in the vicinity of the face surface in the tunnel, it is conceivable to increase the amount of air (hereinafter referred to as “ventilation amount”) supplied to the position in the vicinity of the face surface.
[0005]
However, since the air supplied to reduce the dust concentration is blown to the face, the dust concentration can be reduced, but the amount of dust tends to increase. Here, Table 1 shows a measurement example of the ventilation amount, the dust concentration in the face work area, and the dust generation amount during the ventilation work performed by the exhaust type ventilation apparatus among the conventional ventilation apparatuses. In addition, concrete spraying work was performed in the face working area, and the dust concentration was measured at a position 50 m from the face face 23.
[0006]
[Table 1]
Figure 0003905761
[0007]
As can be seen from Table 1, the ventilation volume is 500m. Three / Min to 1000m Three When it was doubled with / min, the dust concentration certainly decreased, but the amount of generated dust increased by about 40%. As described above, when the ventilation amount is increased, the dust concentration can be reduced, but the dust amount is increased. As a result, there is a problem that the ventilation efficiency is deteriorated.
[0008]
Therefore, the object of the present invention is to reduce the generation amount of dust as much as possible when ventilating the face working area in order to reduce the dust concentration in the face working area of the tunnel so that the ventilation can be performed efficiently. There is to do.
[0009]
[Means for Solving the Problems]
The present invention that has solved the above-mentioned problems is a ventilation device in a tunnel for ventilating the inside of a tunnel, and includes an air supply pipe formed with an air outlet that blows air toward the face of the tunnel. Is formed with a branch path that divides the air flowing inside, The diverted air is placed at a position that avoids the face in the face work area of the tunnel. A branch outlet is formed. The air exhausted from the outlet and the branch outlet is flowing toward the wellhead side from the branch outlet, and the air volume of the exhaust air flowing toward the wellhead side is the airflow of the outlet air discharged from the outlet It is the sum of the air volume and the air volume of the branch outlet air discharged from the branch outlet. It is characterized by this.
[0010]
When air is blown directly on the face, the amount of dust generated increases due to the air. In this regard, in the ventilator according to the present invention, air is supplied to an area in the face work area where the face face is avoided to ventilate the face work area. For this reason, since it is possible to reduce the amount of air blown to the face surface without reducing the amount of air supplied to the face working area, it is possible to reduce the dust concentration while preventing an increase in the amount of dust generated. Can do.
[0011]
In addition, the present invention that has solved the above problems is a short-distance air supply device that is provided inside a tunnel and has an air outlet that blows out air toward the face of the tunnel in the tunnel ventilation device that ventilates the inside of the tunnel. It has a wind pipe and an exhaust wind pipe that forms an air passage that feeds the air blown from the outlet of the short air supply pipe to the tunnel entrance, and the short air supply pipe has air that passes through the inside. A branch path that splits the water is formed, The diverted air is placed at a position that avoids the face in the face work area of the tunnel. A branch outlet is formed. The air exhausted from the outlet and the branch outlet is flowing toward the wellhead side from the branch outlet, and the air volume of the exhaust air flowing toward the wellhead side is the airflow of the outlet air discharged from the outlet It is the sum of the air volume and the air volume of the branch outlet air discharged from the branch outlet. It is characterized by this.
[0012]
Thus, the ventilator according to the present invention can also be used for a so-called exhaust type ventilator.
[0013]
Here, it is preferable that a dust collector for removing dust contained in the air introduced into the short air supply duct is provided. By providing such a dust collector, the air discharged from the short air supply duct can be made clean.
[0014]
Moreover, it is preferable that the said branch blower outlet blows off air in the direction along the said facet.
[0015]
In this way, by allowing air to blow out from the branch outlet in the direction along the face, the air flow in the face working area can be made orderly, which can contribute to efficient ventilation. .
[0016]
Furthermore, at this time, the branch outlet is preferably formed at a position within 10 m from the outlet. This is because if the branch outlet is formed far away from the outlet, the air flows when the air containing the dust is discharged from the outlet and is discharged out of the tunnel.
[0017]
Further, it is desirable that an air volume adjusting mechanism is provided in a branch path between the outlet and the branch outlet. By providing such an air volume adjustment mechanism, the ratio of the air discharged from each of the air outlets and the branch air outlets is adjusted according to the use situation of the ventilation device, thereby further improving the ventilation of the face work area. Can be done well.
[0018]
Furthermore, it is desirable that a control device for adjusting the opening degree in the air volume adjusting mechanism is provided based on the distance from the blower outlet to the face surface and the type of face work. By providing such a control device, it is possible to more efficiently ventilate the face work area.
[0019]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings. In addition, the same code | symbol shall be used for the same element and the overlapping description is abbreviate | omitted.
[0020]
FIG. 1 is a side sectional view of a tunnel provided with a ventilation device in a tunnel according to a first embodiment of the present invention. As shown in FIG. 1, a ventilation device 1 in a tunnel according to the present embodiment is a so-called air supply type provided in a tunnel 2 and has an air supply air pipe 11. The air supply pipe 11 extends from the well entrance 21 of the tunnel 2 to the face work area 22, and forms a ventilation path for supplying clean air to the face work area 22. The length L of the face work area 22 is an area where work is performed in the vicinity of the face face 23, and is slightly different depending on the type of work, but is set within a range of 30 m to 100 m from the face face 23, for example. Further, the air supply pipe 11 is provided along the longitudinal direction of the mine shaft 24 in the upper part of the mine shaft 24.
[0021]
An inlet 11A is formed on one end side of the air supply pipe 11, and an outlet 11B is formed on the other end side. A blower 12 provided outside the tunnel 2 is connected to the entrance 11A. The blower 12 supplies clean air outside the tunnel 2 to the air supply pipe 11. In addition, the air outlet 11B is provided with a shape retaining member (not shown) for maintaining a large opening area. The air outlet 11B opens toward the face surface 23 of the tunnel 2, and air is directly blown out from the air outlet 11B to the face surface 23.
[0022]
Further, a branch pipe 13 is attached to a midway position of the air supply pipe 11 within the face working area 22. A branch outlet 13 </ b> A is formed at the tip of the branch pipe 13 to blow out air in the face working area 22 and away from the face face 23. The branch outlet 13A is formed in a direction along the face 23, and the air blown from the branch outlet 13A is parallel to the face 23, in other words, along the face 23. Flow in the direction. The distance from the air outlet 11B to the branch pipe 13 (branch air outlet 13A) is preferably within 10 m, for example, 5 m, 3 m, etc., but can also be provided at a position exceeding 10 m. In addition, as shown in FIG. 2, the air supply pipe 11 is provided horizontally at a slightly lower position near the uppermost part of the center when viewed from the face face 23 side of the tunnel 2, The branch pipe 13 is attached to face obliquely downward. Since the position where the branch pipe 13 is directed faces the opposite side of the position where the air supply pipe 11 is approached, the air blown from the branch pipe 13 spreads over the entire cross-sectional direction in the tunnel 2. It has become easier.
[0023]
Furthermore, a branch path 14 is formed at a position where the branch pipe 13 is attached in the air supply pipe 11 to divide the air passing through the air supply pipe 11. The branch path 14 is trifurcated, and one of the channels is in communication with the inlet 11A, the other channel is in communication with the outlet 11B, and the other channel is in communication with the branch outlet 13A.
[0024]
Here, the air supply tube 11 is made of, for example, a foldable bellows type vinyl tube, and the length of the air supply tube 11 can be increased when the tunnel 2 is being dug. By setting the bellows type folding portion closer to the wellhead 21 than the branch path 14, the positional relationship between the air outlet 11B and the branch air outlet 13A is made constant even when the air supply pipe 11 is extended. Can keep. A vinyl pipe is also used as the branch pipe 13.
[0025]
Further, as shown in FIG. 3, the branch path 14 is provided with an air volume adjusting damper 15 that is an air volume adjusting mechanism. The air volume adjustment damper 15 adjusts the ratio of the opening area on the outlet 11B side in the branch path 14 and the opening area on the branch outlet 13A side. By adjusting the ratio of these opening areas, the amount of air flowing into the outlet 11B side and the amount of air flowing into the branch outlet 13A are adjusted.
[0026]
The air volume adjustment damper 15 includes a damper main body 15A that actually adjusts the opening area of the branch path 14, and a damper motor 15B that rotates the damper main body 15A. The damper motor 15B is connected to the control device 16. The control device 16 is provided with a distance sensor 17 and a face work type sensor 18. As the distance sensor 17, a known distance sensor such as an ultrasonic distance sensor or a laser distance sensor can be used as appropriate, and the distance from the outlet 11B to the face surface 23 is measured. The face work type sensor 18 determines work to be performed in the face work area 22. The control device 16 calculates the opening degree of the damper main body 15A in the air volume adjustment damper 15 according to the distance from the air outlet 11B to the face surface 23 and the type of work performed in the face work area 22, and becomes the opening degree. Thus, the damper motor 15B is controlled. The face work type sensor 18 can use a tool that detects a tool used when the work is performed and discriminates the work. Instead, a form in which the worker inputs the current work is used. May be used.
[0027]
Further, for example, an air volume adjusting damper capable of manually adjusting the opening degree can be used without using such a control device or an automatic air volume adjusting damper.
[0028]
The operation of the ventilator having the above configuration will be described.
[0029]
In the face work area 22 in the tunnel 2, face work such as blasting work, sliding work, concrete spraying (hereinafter referred to as “blowing”) work is performed. The dust generated during the face work is removed to reduce the dust concentration in the tunnel 2, particularly in the face work area 22. To ventilate the tunnel 2, the blower 12 is driven to supply clean air such as outside air into the air supply pipe 11. The clean air supplied into the air supply duct 11 passes through the air supply duct 11 and reaches the branch path 14. In the branch path 14, the supplied clean air is branched to the outlet 11 </ b> B side and the branch outlet 13 </ b> A side by the opening of the damper main body 15 </ b> A in the air volume adjusting damper 15.
[0030]
The air blown to the blower outlet 11 </ b> B side is blown directly to the face surface 23. The blown air blown out to the face surface 23 absorbs dust generated by the face work, is bounced back to the face surface 23 and flows toward the wellhead 21 side of the tunnel 2. On the other hand, the air blown to the branch outlet 13 </ b> A is discharged into the face working area 22 and to the position closer to the wellhead 21 than the face face 23. The branch blown air discharged from the branch blower outlet 13 </ b> A merges with the blown air flowing from the face surface 23 side to become discharged air, and flows in the tunnel 24 toward the wellhead 21. The air volume Q of the exhaust air is the sum of the air volume Q1 of the blown air and the air volume Q2 of the branch blown air.
[0031]
At this time, if the airflow of the blown air blown out from the blowout port 11B is strong, it will cause dust generation on the face surface 23. However, in the ventilator 1, the air blown to the face work area 22 is divided into the blower outlet 11B and the branch blower outlet 13A. Therefore, a part of the air supplied for ventilation to the face work area 22 is blown out from the branch outlet 13A as branch outlet air, thereby reducing the air volume Q1 of the outlet air blown out from the outlet 11B. The airflow can be weakened. As a result, the air volume Q1 of the blown air blown to the face surface 23 can be reduced and the airflow can be weakened while securing the air volume Q (equivalent to the exhaust air volume) Q supplied to the entire face working area 22. As a result, generation of dust can be prevented. Therefore, the dust concentration in the face work area 22 can be reduced without increasing the amount of dust to be generated, and as a result, efficient ventilation can be performed.
[0032]
Further, the amount of dust generated varies depending on the work performed in the face work area 22. For example, the dust generated in the blasting operation is relatively small, and the dust generated in the operations such as the sliding operation and the spraying operation is relatively large. Therefore, when performing the blasting operation, it is preferable to reduce the air volume Q1 of the blown air blown toward the face surface 23 and increase the ratio of the air volume Q2 of the branched blown air. Further, when carrying out the sliding work and the blowing work, it is preferable to increase the air volume Q1 of the blown air and reduce the air volume Q2 of the branched blown air.
[0033]
For this reason, in the ventilating apparatus 1 according to the present embodiment, the amount of air supplied to the outlet 11B side and the branch outlet 13A side is adjusted by the air volume adjustment damper 15 provided in the branch path 14. For example, when performing a blasting operation that generates a small amount of dust, the air blown out from the air outlet 11B side by reducing the opening on the air outlet 11B side and increasing the opening on the branch air outlet 13A side. The air volume Q1 of the branch blown air blown out from the branch outlet 13A is increased. In addition, when performing a projecting operation and a spraying operation in which a large amount of dust is generated, the opening degree on the outlet 11B side is increased and the opening degree on the branch outlet 13A side is decreased. In this way, a large amount of dust can be quickly discharged.
[0034]
Further, as the excavation work of the tunnel 2 proceeds, the distance between the face plane 23 and the outlet 11B changes. Even in such a case, it is preferable to adjust the air volume Q1 of the blown air. For example, when the excavation of the tunnel 2 progresses and the distance between the face surface 23 and the outlet 11B becomes longer, the air volume Q1 of the blown air blown from the outlet 11B is increased, and the air volume Q2 of the branched air is increased. Reduce. Further, when the air supply pipe 11 is extended and the distance between the face plane 23 and the outlet 11B is shortened, the air volume Q1 of the blown air blown from the outlet 11B is reduced, and the air volume Q2 of the branched blown air is reduced. To increase. Thus, the face working area 22 can be efficiently ventilated by adjusting the air volume Q1 of the blown air and the air volume Q2 of the branched blown air.
[0035]
Such a distance from the air outlet 11B to the face surface 23 and the adjustment ratio of air between the air outlet 11B and the branch air outlet 13A according to the face operation type are performed using the control device 16. The control device 16 calculates the opening degree of the damper main body 15 </ b> A in the air volume adjustment damper 15 based on the distance information output from the distance sensor 17 and the face work type information output from the face work type sensor 18. Then, the damper motor 15B is feedback-controlled, for example, so that the opening degree of the damper main body 15A becomes the calculated opening degree of the damper main body 15A. Thus, by adjusting the opening degree of the damper main body 15A by the control device 16, the amount of air supplied to the air outlet 11B and the branch air outlet 13A can be adjusted, so that an efficient ventilation work can be performed.
[0036]
Moreover, as shown in FIG. 4, the dust collector 19 can also be provided in the lower position in the face work area | region 22, and the position near the wellhead 21 rather than the branch outlet 13A. A local blower 20 is provided on the wellhead 21 side of the dust collector 19, and an exhaust pipe 20 </ b> A is provided on the wellhead 21 side of the local blower 20. In the tunnel 2, in addition to face work such as blasting in the face work area 22, workers also carry out work such as transporting earth and sand in the tunnel work area 25 in the tunnel 24. When air mixed with dust flows into such a mine work area 25, the dust concentration in the mine work area 25 increases. Then, the local air blower 20 is operated, and the air containing the dust generated in the face work area 22 is collected by the dust collector 19. The dust collector 19 removes a large amount of dust contained in the exhausted air that bounces back to the face surface 23 and flows toward the wellhead 21 by the dust collector 19. The air from which the dust is removed by the dust collector 19 is discharged from the exhaust pipe 20 </ b> A and flows in the direction of the wellhead 21 through the tunnel work area 25. Therefore, since dust is removed from the air passing through the mine work area 25, the dust concentration in the mine work area 25 can be prevented from increasing. As the dust collector 19, a publicly known one having a function of removing dust from air containing dust, for example, a dry type equipped with a bag filter, a wet type, or an electric type can be used. .
[0037]
Next, a second embodiment of the present invention will be described.
[0038]
FIG. 5 is a side sectional view of a tunnel provided with a ventilation device in the tunnel according to the present embodiment. As shown in FIG. 5, the ventilation device 3 in the tunnel according to the present embodiment is a so-called exhaust type provided in the tunnel 2 and has a short length of about 3 to 10 m, for example, a vinyl tube. A short air supply pipe 31 is provided in the face work area 22 in the tunnel 2. A local blower 32 is attached to the side of the wellhead 21 in the short air supply duct 31. The opening on the face surface 23 side of the short air supply duct 31 is an air outlet 31A for blowing out air, and air is directly blown out to the face surface 23 from the air outlet 31A.
[0039]
In addition, a trifurcated branch path 33 that divides the air flowing through the inside of the short air supply tube 31 is formed in the middle of the short air supply tube 31. One branch of this branch path 33 communicates with the local blower 32, the other channel communicates with the outlet 31A, and another branch is formed at the tip of the branch path 33 made of, for example, a vinyl pipe. It communicates with the air outlet 34A. The branch outlet 34 </ b> A in the branch pipe 34 is formed facing the direction along the face surface 23 so as to blow air to a position in the face work area 22 that avoids the face face 23. The air blown out from the branch outlet 34A flows in a direction along the face surface 23. Although not shown, the branch pipe 34 is attached so as to face obliquely upward as viewed from the face surface 23 side. For this reason, the air blown out from the branch outlet 34 </ b> A is easily spread smoothly in the cross-sectional direction of the tunnel 2.
[0040]
Further, an exhaust air pipe 35 is provided at an upper position in the tunnel 2 to form an air passage for sending air blown from the air outlet 31 </ b> A in the short air supply pipe 31 to the tunnel 21 side of the tunnel 2. . The exhaust air pipe 35 is made of, for example, a vinyl pipe, and a blower 36 is provided on the inlet 35 </ b> A side of the exhaust air pipe 35. The blower 36 introduces air containing a large amount of dust in the face working area 22 into the exhaust wind pipe 35. The air containing a large amount of dust introduced into the exhaust wind pipe 35 passes through the exhaust wind pipe 35 and is discharged to the outside of the tunnel 2 from the discharge port 35B.
[0041]
Also in the ventilator 3 of this embodiment, the same working effects as the ventilator 1 according to the first embodiment can be obtained.
[0042]
When face work such as blasting, sliding out, and spraying in the face work area 22 is performed, a large amount of dust is generated in the face work area 22. In the ventilation device 3, the local blower 32 and the blower 36 are operated. When the local blower 32 is operated, air is introduced into the short air supply pipe 31 from the wellhead 21 side of the face work area 22 in the tunnel 2, and is sent to the face work area 22 via the short air supply pipe 31 and the branch pipe 34. I care. At this time, all the air that has passed through the short air supply pipe 31 and the branch pipe 34 is introduced into the face working area 22, but the air blown directly to the face face 23 is that of the short air supply air pipe 31. It is only the air blown out from the blower outlet 31A. For this reason, the generation amount of dust can be suppressed by reducing the amount of blown air blown from the blower outlet 31A to the face surface 23 and weakening the air flow. On the other hand, since the amount of air supplied to the face work area 22 can be prevented from being reduced, the dust concentration can be effectively reduced, and as a result, efficient ventilation can be performed.
[0043]
Here, the air flow adjusting damper, the control device, and the like similar to those in the first embodiment can be provided also in the branch path 33 in the ventilation device 3 according to the present embodiment. By providing such an air volume adjustment damper or the like and adjusting the air volume according to the type of face work, etc., more efficient ventilation can be performed.
[0044]
Moreover, in the ventilation apparatus 3 which concerns on this embodiment, as shown in FIG. 6, the dust contained in the air introduce | transduced into the short air supply duct 31 is removed between the short air supply duct 31 and the local air blower 32. A dust collector 37 can also be provided. By providing such a dust collector 37, dust generated in the mine work area 25 can be removed by the dust collector 37 before being introduced into the short air supply duct 31. Therefore, since clean air can be supplied to the air supplied to the face working area 22, ventilation in the face working area 22 can be performed more efficiently.
[0045]
As mentioned above, although preferred embodiment of this invention was described, this invention is not limited to each said embodiment. For example, in the above embodiments, one branch pipe is provided, but two or three or more branch pipes may be provided. At this time, for example, depending on the type of the face work or the distance from the outlet to the face surface, it is possible to make an adjustment such that air is blown from only a part of the plurality of branch pipes.
[0046]
Moreover, although the blower outlet blows out air in the direction along the face, it can be configured to blow out obliquely to some extent in the front-rear direction. Various wind pipes use vinyl pipes, but resin pipe pipes or steel pipes can also be used. Furthermore, as the air volume adjusting mechanism, air flow path switching means other than the damper can be used.
[0047]
【The invention's effect】
As described above, according to the present invention, when ventilating the face working area in order to reduce the dust concentration in the face working area of the tunnel, the amount of generated dust can be reduced as much as possible, and ventilation can be performed efficiently. Can be.
[Brief description of the drawings]
FIG. 1 is a side sectional view of a tunnel provided with a ventilation device according to a first embodiment.
2 is a cross-sectional view taken along line II-II in FIG.
FIG. 3 is a configuration diagram of a control unit of an air volume adjustment damper.
4 is a side sectional view of a tunnel provided with a ventilation device according to a modification of FIG. 1;
FIG. 5 is a side sectional view of a tunnel provided with a ventilation device according to a second embodiment.
6 is a side sectional view of a tunnel provided with a ventilation device according to a modification of FIG. 5;
7A is a side sectional view of a tunnel provided with a conventional air supply type ventilation device, and FIG. 7B is a side sectional view of a tunnel provided with a conventional exhaust type ventilation device.
[Explanation of symbols]
1,3 ... Ventilator
2 ... Tunnel
11 ... Air pipe
11B ... Air outlet
12 ... Blower
13 ... Branch pipe
13A ... Branch outlet
14 ... Branch
15 ... Air volume adjustment damper
16 ... Control device
17 ... Distance sensor
18 ... Working face type sensor
19 ... Dust collector
22 ... Working face work area
23. Face face
31 ... Short air supply tube
31A ... Air outlet
32 ... Local blower
33 ... Branch
34A ... Branch outlet
34 ... Branch pipe
35 ... Exhaust wind pipe

Claims (7)

トンネルの内部を換気するトンネル内の換気装置において、
前記トンネルの切羽面に向けて空気を吹き出す吹出口が形成された送気風管を備え、
前記送気風管には、内部を通風する空気を分流させる分岐路が形成されているとともに、分流された空気を、前記トンネル内のうちの切羽作業領域内における前記切羽面を避けた位置に吹き出す分岐吹出口が形成されており、
前記吹出口および前記分岐吹出口から排出された空気が、前記分岐吹出口よりも坑口側に向けて流れており、坑口側に向けて流れる排気空気の風量は、前記吹出口から排出される吹出空気の風量と、前記分岐吹出口から排出される分岐吹出空気の風量の和とされていることを特徴とするトンネル内の換気装置。
In the ventilation device in the tunnel that ventilates the inside of the tunnel,
An air supply pipe formed with an outlet for blowing out air toward the face of the tunnel;
The air supply pipe is formed with a branch path for diverting the air flowing through the inside, and the diverted air is placed at a position avoiding the face surface in the face work area in the tunnel. A branch outlet that blows out is formed ,
The air discharged from the outlet and the branch outlet is flowing toward the wellhead side of the branch outlet, and the air volume of the exhaust air flowing toward the wellhead is the outlet discharged from the outlet A ventilation device in a tunnel, characterized by being the sum of an air volume and an air volume of branch blown air discharged from the branch outlet .
トンネルの内部を換気するトンネル内の換気装置において、
前記トンネルの内部に設けられ、前記トンネルにおける切羽面に向けて空気を吹き出す吹出口が形成された短尺送気風管と、
前記短尺送気風管における吹出口から吹き出された空気をトンネルの坑口側に送気する通風路を形成する排気風管を備え、
前記短尺送気風管には、内部を通風する空気を分流させる分岐路が形成されているとともに、分流された空気を、前記トンネル内のうちの切羽作業領域内における前記切羽面を避けた位置に吹き出す分岐吹出口が形成されており、
前記吹出口および前記分岐吹出口から排出された空気が、前記分岐吹出口よりも坑口側に向けて流れており、坑口側に向けて流れる排気空気の風量は、前記吹出口から排出される吹出空気の風量と、前記分岐吹出口から排出される分岐吹出空気の風量の和とされていることを特徴とするトンネル内の換気装置。
In the ventilation device in the tunnel that ventilates the inside of the tunnel,
A short air supply tube provided inside the tunnel, in which a blowout port for blowing out air toward the facet in the tunnel is formed;
An exhaust air pipe that forms an air passage that feeds air blown from the air outlet in the short air supply pipe to the tunnel entrance side;
The short air supply pipe is formed with a branch path for diverting the air flowing through the inside, and the diverted air is located at a position away from the face surface in the face work area in the tunnel. A branch outlet that blows out is formed ,
The air discharged from the outlet and the branch outlet is flowing toward the wellhead side of the branch outlet, and the air volume of the exhaust air flowing toward the wellhead is the outlet discharged from the outlet A ventilation device in a tunnel, characterized by being the sum of an air volume and an air volume of branch blown air discharged from the branch outlet .
前記短尺送気風管に導入される空気に含まれる粉塵を除去する集塵機が設けられている請求項2に記載のトンネル内の換気装置。  The ventilation apparatus in a tunnel according to claim 2, further comprising a dust collector for removing dust contained in the air introduced into the short air supply duct. 前記分岐吹出口は、前記切羽面に沿った方向に空気を吹き出す請求項1〜請求項3のうちのいずれか1項に記載のトンネル内の換気装置。  The ventilator in a tunnel according to any one of claims 1 to 3, wherein the branch outlet blows air in a direction along the face surface. 前記分岐吹出口は、前記吹出口から10m以内の位置に形成されている請求項1〜請求項4のうちのいずれか1項に記載のトンネル内の換気装置。  The ventilator in a tunnel according to any one of claims 1 to 4, wherein the branch outlet is formed at a position within 10 m from the outlet. 前記吹出口と前記分岐吹出口の分岐路に、風量調整機構が設けられている請求項1〜請求項5のうちのいずれか1項に記載のトンネル内の換気装置。  The ventilation apparatus in a tunnel according to any one of claims 1 to 5, wherein an air volume adjusting mechanism is provided in a branch path between the outlet and the branch outlet. 前記吹出口から前記切羽面までの距離および切羽作業の種類に基づいて、前記風量調整機構における開度を調整する制御装置が設けられている請求項6に記載のトンネル内の換気装置。  The ventilation device in a tunnel according to claim 6, wherein a control device is provided for adjusting an opening degree in the air volume adjusting mechanism based on a distance from the blower outlet to the face surface and a kind of face work.
JP2002005126A 2002-01-11 2002-01-11 Ventilation device in the tunnel Expired - Lifetime JP3905761B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002005126A JP3905761B2 (en) 2002-01-11 2002-01-11 Ventilation device in the tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002005126A JP3905761B2 (en) 2002-01-11 2002-01-11 Ventilation device in the tunnel

Publications (2)

Publication Number Publication Date
JP2003206699A JP2003206699A (en) 2003-07-25
JP3905761B2 true JP3905761B2 (en) 2007-04-18

Family

ID=27644257

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002005126A Expired - Lifetime JP3905761B2 (en) 2002-01-11 2002-01-11 Ventilation device in the tunnel

Country Status (1)

Country Link
JP (1) JP3905761B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100858878B1 (en) * 2008-04-02 2008-09-17 에스텍이앤지(주) Dust collection ventilation device for tunnel construction
JP5006834B2 (en) * 2008-05-02 2012-08-22 株式会社三井三池製作所 Tunnel ventilation method and tunnel ventilation device
KR101188220B1 (en) * 2009-10-15 2012-10-08 (주)비엔텍아이엔씨 Ventilation system for tunnel's construction and control method for the same
ES2612403B1 (en) * 2015-10-14 2018-02-20 Obras Subterraneas, S.A. MEANS AND PROCEDURE FOR CONTROL OF THE WORK ATMOSPHERE IN TUNNELS
JP6152197B1 (en) * 2016-05-31 2017-06-21 株式会社流機エンジニアリング Ventilation device in the tunnel
CN108150214B (en) * 2018-01-18 2023-09-05 山东大学 A system and method for automatically reducing fog, dust and temperature during tunnel construction
CN112796818A (en) * 2021-01-27 2021-05-14 中钢集团马鞍山矿山研究总院股份有限公司 Local ventilation and refrigeration combined high-temperature excavation roadway heat extraction and cooling system

Also Published As

Publication number Publication date
JP2003206699A (en) 2003-07-25

Similar Documents

Publication Publication Date Title
JP3905761B2 (en) Ventilation device in the tunnel
CN106140769B (en) fume hood
JP6401067B2 (en) Tunnel ventilation method and tunnel ventilation system
JP2017521226A (en) Fume hood
JP5006834B2 (en) Tunnel ventilation method and tunnel ventilation device
JP6495578B2 (en) Tunnel ventilation method
US20120104831A1 (en) Heading Machine
JP4319619B2 (en) Ventilation device in the tunnel
JP4644049B2 (en) Ventilation method and ventilation device
EP0726363A1 (en) Improvements relating to a debris collecting apparatus
JP6333590B2 (en) Blower dust collector
JP4454163B2 (en) Ventilation method in tunnel during construction
CN112647998A (en) Tunneling roadway ventilation method and coal mine roadway system
JP3996934B2 (en) Tea leaf picking machine
JP4217958B2 (en) Ventilation method in tunnel tunnel
JP2002349200A (en) Ventilation method for tunnel work and ventilation device for tunnel work
KR101188220B1 (en) Ventilation system for tunnel&#39;s construction and control method for the same
JP2003206700A (en) Ventilation equipment in tunnel
GB2256668A (en) Ventilation system for a mining machine
DE60314356D1 (en) planer
DK1428616T3 (en) Planer
JP4742008B2 (en) Tunnel ventilation equipment
JP3009526B2 (en) Method and apparatus for ventilating tunnel during excavation
JP4521371B2 (en) Method for collecting contaminated air in tunnel and ventilation equipment in tunnel using the same
RU23180U1 (en) DEVICE FOR FIGHTING DUST ON A DRIVING COMBINE

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040914

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060905

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061031

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070109

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070112

R150 Certificate of patent or registration of utility model

Ref document number: 3905761

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100119

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130119

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160119

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250