JP3953662B2 - Concrete bucket flooring equipment - Google Patents
Concrete bucket flooring equipment Download PDFInfo
- Publication number
- JP3953662B2 JP3953662B2 JP28027198A JP28027198A JP3953662B2 JP 3953662 B2 JP3953662 B2 JP 3953662B2 JP 28027198 A JP28027198 A JP 28027198A JP 28027198 A JP28027198 A JP 28027198A JP 3953662 B2 JP3953662 B2 JP 3953662B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete bucket
- landing
- concrete
- bucket
- wall portion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009408 flooring Methods 0.000 title claims description 10
- 239000000463 material Substances 0.000 claims description 35
- 244000208734 Pisonia aculeata Species 0.000 claims description 4
- 238000002513 implantation Methods 0.000 claims description 3
- 230000000694 effects Effects 0.000 description 8
- 238000010276 construction Methods 0.000 description 7
- 238000012546 transfer Methods 0.000 description 7
- 238000000034 method Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 5
- 241000196324 Embryophyta Species 0.000 description 3
- 238000012937 correction Methods 0.000 description 3
- 238000005096 rolling process Methods 0.000 description 3
- 230000001276 controlling effect Effects 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000001105 regulatory effect Effects 0.000 description 2
- 239000000725 suspension Substances 0.000 description 2
- 238000013459 approach Methods 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 230000001151 other effect Effects 0.000 description 1
- 238000011144 upstream manufacturing Methods 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、例えば、ダム建設等において、ケーブルクレーンなどにより運搬されるコンクリートバケットを、生コンクリート生成供給場近くに設けられたコンクリートバケット着床場所(バンカー線)の所定位置に着床するためのコンクリートバケットの着床装置に関する。
【0002】
【従来の技術】
ダム建設現場においては、バッチャープラント(生コンクリート生成場)で生成した生コンクリートを、トランスファーカー(生コンクリート供給装置)によりコンクリートバケットに詰めて、このコンクリートバケットをコンクリート打設場所までケーブルクレーンで運搬するようにしてダム建設工事を行っている。
図9にダム建設現場の概観を示す。
図9において、1は、楕円や円あるいは四角などの形状の缶体より成るコンクリートバケット、2は、上記コンクリートバケット1に生コンクリートを詰め込むため、コンクリートバケット1が運搬されてきて着床されるコンクリートバケット着床場所であり、バンカー線と呼ばれる場所である。
20は基礎工であり、基礎工20の左岸21上に設けられた固定塔22と右岸23上に設けられた移動塔24との間にはレールケーブル25が張られている。26はこのレールケーブル25上を滑車26a,26aを介して滑走するトロリーである。トロリー26は、機械室27に設置された牽引ウインチ28で操作される牽引ケーブル29により、固定塔22と移動塔24との間を移動する。また、30は吊り下げケーブルであり、これはトロリー26の下部に設けられた滑車26b,26bを介して、機械室27に設置された巻上ウインチ31により巻き取られたり巻き戻されたりするものである。この巻上ウインチ31で操作される吊り下げケーブル30により、コンクリートバケット1がトロリー26を介して上下方向に巻上げられたり巻下げられるように吊下げられている。尚、移動塔24は固定塔22を中心として円弧を描くように川の流れの上流側と下流側とに向けて移動可能となっている。すなわち、移動塔24は、右岸23上に円弧状に敷設されたレール24Rの上をモータ24aの駆動により移動可能である。
以上のように、ケーブルを介してトロリー26でコンクリートバケット1をバンカー線2とコンクリート打設目的場所との間において移動させるとともに、バンカー線2及びコンクリート打設目的場所においてコンクリートバケット1を上下動させる上述したような構成から成るケーブルクレーンにより、ダム建設を行っている。
尚、ダムサイト32にはグランドホッパー打設方式の場合に必要なグランドホッパー33が設けられる。コンクリートの打設方式にはグランドホッパー打設方式と直打設方式とがあり、上記グランドホッパー33は直打設方式の際には不要である。
【0003】
上記バンカー線2は、詳細には、図1や図3に示すように、壁部2aと,この壁部2aの下部より延長してコンクリートバケット1が着床される床部2bを有し、上記壁部2aの上部側の平面部2cに、バッチャープラント2xと、バッチャープラント2xで作られた生コンクリートを、床部2bに着床されたコンクリートバケット1の位置まで運搬してきてコンクリートバケット1に供給口2kより供給するトランスファーカー2yとが設置されている。尚、上記平面部2c上には、壁部2aに沿って線路2Rが設けられ、この線路2R上を上記トランスファーカー2yが走行する。2dは、コンクリートバケット1の衝突衝撃を緩衝するために壁部2aに設けられた緩衝材であり、これは、横方向に平行に複数本設けられている。
【0004】
上記ケーブルクレーンやトランスファーカー2yの運行等は、運転室35に設けられたホストコンピュータ36により制御される。
ホストコンピュータ36は、移動塔24のエンコーダ24bから出力された走行位置に関する電気的な情報、光波距離計24cから出力された移動塔24の走行位置原点補正に関する電気的な情報、ロードセル24dから出力されたコンクリートバケット1の荷重に関する電気的な情報、牽引ウインチ28を駆動するモータ28aに連結されたエンコーダ28bから出力されたトロリー26の移動位置に関する電気的な情報、巻上ウインチ31を駆動するモータ31aに連結されたエンコーダ31bから出力されたコンクリートバケット1の巻上下に関する電気的な情報、光波距離計22aから出力されたトロリー26の移動位置補正に関する電気的な情報、光波距離計2mから出力されたコンクリートバケット1の着缶位置原点補正に関する電気的な情報、エリアセンサー2nから出力されたコンクリートバケット1の着缶位置検出に関する電気的な情報、振動ジャイロ1aから出力されたコンクリートバケット1の振れ角に関する電気的な情報、エリアセンサー33aから出力されたコンクリートバケット1の位置に関する電気的な情報、トランスファーカー2yから出力されたそれ自身の位置に関する情報等を受信する。ホストコンピュータ36は、これら受信した情報を予め記憶した運転設定情報に照合して演算した制御情報に基づき、移動塔24、各ウインチ、トランスファーカー2y等の各機器を自動運転制御するものである。
【0005】
ところで、生コンクリートをコンクリートバケット1に詰め込む際、ケーブルクレーンで運搬されてくるコンクリートバケット1を、コンクリートバケット着床場所であるバンカー線2における所定位置に着床させる必要があるが、従来、バンカー線2にコンクリートバケット1を着床させるための装置として、図10,11,12に示すような装置があった。
【0006】
図10は、固定斜板を用いた着床装置である。これは、バンカー線2の床部2bに支柱40を設け、この支柱40の上端に、壁部2a方向に床部2b側に傾斜する固定斜板41を設けたものである。この着床装置によれば、ケーブルクレーンにより運搬されてきたコンクリートバケット1の底側縁部1eを、固定斜板41の傾斜面41fに当接させながら滑らせて床部2bに着床させるものである。
【0007】
図11は、回動支点を介して回動可能となった斜板を用いた着床装置である。これは、斜板50の背面中央側を、回動支点を構成するヒンジ手段51で回動可能なように支持したものである。52は固定台である。この着床装置によれば、図10のものと同じように、コンクリートバケット1の底側縁部1eを斜板50の傾斜面50fに当接させながら滑らせて床部2bに着床させるものであるが、この時、コンクリートバケット1の自重により斜板50が直立する方向に回動して(50Aに示す状態から50Bに示す状態になる)、コンクリートバケット1を床部2bに着床させるものである。尚、この装置は、コンクリートバケット1を床部2bに着床させた後に斜板51を50Aに示す状態に復元させるためのスプリング53を備えている。
【0008】
図12は、コンクリートバケット1を乗せる台車60をジャッキ61で強制的に移動させるようにしたものである。つまり、台車60を、60Aに示す状態と60Bに示す状態とに移動させるものである。
【0009】
【発明が解決しようとする課題】
しかしながら、図10,11,12に示すような従来のコンクリートバケットの着床装置では、以下のような課題があった。
図10の装置では、コンクリートバケット1が固定斜板41の傾斜面41f上を滑るとき、引っかかって傾いたりして、スムーズに着床できないことが頻繁に起こるという課題があった。
図11の装置では、コンクリートバケット1を一旦床部2bに着床させた後は、スプリング53の力ではコンクリートバケット1を壁部方向に移動させることができない(床部2bより少し浮かした状態でないと移動させることができない)。従って、コンクリートバケット1が壁部2aに着くよう床部2bに着床させるためには、壁部2aと装置との間の距離を大きく取れない。よって、着床時におけるコンクリートバケット1の水平方向の移動代H(図11参照)を大きく取れないことになる。つまり、図10や図12の装置に比べて、上記コンクリートバケット1の水平方向の移動代Hが少なくなり、着床させるときのコンクリートバケットの横揺れに対応できず、ケーブルクレーンの運転に支障を来すという課題があった。
また、図12の装置では、着床時、離床時に、動力源を制御してジャッキを操作しなくてはならないので、制御が複雑となる等の課題があった。
さらに、図10の装置では固定斜板41を、図11の装置では斜板50やスプリング53を、図12の装置では台車60やジャッキ61を、バンカー線2の全線に渡って設けなくてはならず、設備コストがかかるという課題があった。
【0010】
そこで、本発明は、上述したような課題をすべて克服できるコンクリートバケットの着床装置を得ることを目的とするものである。
すなわち、水平方向の移動代を十分に取れて、コンクリートバケットの横揺れに対応できるとともに、コンクリートバケットの大きさに自由に対応できて、コンクリートバケットをスムーズに着床させることができ、さらに、一組の装置を移動することで設備費用も安価となり、着床、離床動作に動力源や複雑な制御も必要とならない簡単な構成で、かつ、設備コストも抑えることができる着床装置を提供しようとするものである。
【0011】
【課題を解決するための手段】
本発明の請求項1に係る発明によるコンクリートバケットの着床装置は、回動支点を介してコンクリートバケット着床場所の壁部側に近づく方向でコンクリートバケット着床場所の床部側に倒れ込むように回動する所定長さのアームの先端側に、コンクリートバケットを1つ受けることが可能な大きさで、コンクリートバケットの重量を受ける前の初期状態において、上記床部に近い一端側から上記壁部より離れるよう上方向に傾斜する傾斜面を形成する状態に設定され、かつ、コンクリートバケットの重量を受けた状態において、上記アームの回動により、コンクリートバケットをガイドしながら上記壁部に対向する状態に設定されて当該コンクリートバケットを上記壁部に近い床部側に着床させるための受け材を取り付けて成り、かつ、上記受け材が上記コンクリートバケットの重量を受けている状態において上記受け材の位置を上記初期状態の方向に引き戻すように作動するとともに、コンクリートバケットが上記コンクリートバケット着床場所より離れた場合に、上記受け材の位置を上記初期状態に戻す引き戻し手段を具備する着床作動手段と、この着床作動手段を、コンクリートバケット着床場所における上記床部上において上記壁部に沿って移動させる第1移動手段とを備えて成るものである。
請求項2に係る発明は、上記第1移動手段は、上記着床作動手段を搭載し、駆動源により上記壁部に沿って上記床部上を移動する移動台車で構成した。
請求項3に係る発明は、上記着床作動手段を上記壁部に対して近接する方向又は離反する方向に移動させる第2移動手段を備えるものとした。
請求項4に係る発明は、上記受け材は、上記一端側に、上記コンクリートバケットの底面に当接する支持部材を有するL字状のパネルより成るものとした。
請求項5に係る発明は、上記初期状態の受け材の他端と延長して、受け材の傾斜面と延長する固定傾斜面を備えるものとした。
請求項6に係る発明は、上記受け材の位置が上記初期状態に戻されたときこの初期状態の位置より上記壁部とは反対側に移動しないように規制する規制手段を備えているものとした。
【0012】
【発明の実施の形態】
実施の形態1.
以下、本発明の実施の形態1を図1ないし図6に基づき説明する。尚、図9や図3ですでに説明した構成要素については同一符号を付して説明を省略する。
各図において、3は本発明によるコンクリートバケットの着床装置である。
この着床装置3は、駆動源によりバンカー線2の壁部2aに沿って床部2b上を移動する第1移動手段としての移動台車3B上に、着床作動手段3Aを搭載して成るものである。即ち、本実施の形態1による着床装置3は、上記着床作動手段3Aを搭載し、バンカー線2の壁部2aに沿って床部2b上を移動する移動台車3Bを備えているので、着床作動手段3Aをバンカー線2の所定の位置に自由に移動可能である。
上記着床作動手段3Aは、バンカー線2に運搬されてくるコンクリートバケット1を1つ受けることが可能な大きさの受け材4を、土台7上に設けられた回動支点を構成するヒンジ手段5を介して壁部2a側に近づく方向で床部2b側に倒れ込むように回動する所定長さの2本のアーム6,6の先端6t,6t側に取り付けて成り、かつ、引き戻し手段としてのスプリング10を具備している。
尚、着床装置3の背面側には歩廊12が設けられる。12aは歩廊12の手すり、13は上記床部2b,着床装置3,歩廊12を支える床下構造体である。
【0013】
上記移動台車3Bは、例えばダム建設現場で使用する可能性のある最も大きなコンクリートバケット1を1つ着床できる面積を持った矩形板3aの下面3bの四隅に、バンカー線2の壁部2aに沿って床部2b上に設けられた2本のレール3c,3c上を滑走する車輪3dが設けられている。この移動台車3Bは、図5(a)に示すように、電動機3eから伝達ベルト3e1を介して車軸3d1に伝達される回転駆動力により走行する。
また、移動台車3Bの位置制御は、ケーブルクレーンと連動させたセンサ等で、移動台車3Bとコンクリートバケット1との距離を測定し、この測定情報をホストコンピュータ36が入力して、ホストコンピュータ36は、移動台車3Bとコンクリートバケット1との距離が所定の距離になるまで移動台車3Bを駆動し、所定の距離になれば移動台車3Bを停止する。
【0014】
また、上記コンクリートバケット1の形状や大きさは様々であるので、このような様々な形状や大きさのコンクリートバケット1に対応してこれら各種のコンクリートバケット1をバンカー線2の壁部2aにうまく近づけるようにするためには、コンクリートバケット1の形状や大きさに対応して、受け材4の位置を、上記壁部2aに対して近接する方向又は離反する方向に移動させることができれば望ましい。そこで、本実施の形態1では、上記着床作動手段3Aを、上記バンカー線2の壁部2aに対して近接する方向又は離反する方向に移動させる第2移動手段を設けるようにした。
この第2移動手段は、着床作動手段3Aをバンカー線2の壁部2aに対して近接する方向又は離反する方向に移動させる例えば電動ジャッキ3Cにより実現される。具体的には、図3,5,6に示すように、土台7,7に対応して移動台車3Bに壁部2a方向に延長するスライド溝3h,3hを設け、土台7,7の下部に、各スライド溝3h,3hを介してスライドするスライド部3i,3iを設け、このスライド部3i,3iを電動ジャッキ3C,3Cで上記壁部2aに対して近接する方向又は離反する方向に移動させる。尚、上記スライド溝3hの内側面にはガイドレール3j,3jが設けられ、このガイドレール3j,3jを介してスライド部3iがスライドしやすいようになっている。また、電動ジャッキ3Cの一端3C1側は、スライド溝3hにおけるバンカー線2の壁部2a側の一端面3kに取り付けられ、電動ジャッキ3Cの他端3C2側は、スライド溝3hの他端面3mに取り付けられている。
【0015】
尚、上記第1移動手段としての移動台車3Bの電動機3e、および第2移動手段としての電動ジャッキ3Cの駆動電力は、電線リール3fを介して外部電源から供給される。
【0016】
上記スプリング10は、その一端が固定具10aにより上記受け材4の背面側に固定され、他端が上記支柱8の背面側に設けられたスプリング反力受け11に固定具10bにより固定されている。
【0017】
上記受け材4は、コンクリートバケット1の重量を受ける前の初期状態4Aにおいて、上記床部2bに近い一端4a側から上記壁部2aより離れるよう上方向に傾斜する傾斜面4fを形成する状態に設定され、かつ、上記コンクリートバケット1の重量を受けた状態において、上記アーム6,6の回動により、上記コンクリートバケット1をガイドしながら上記壁部2aに対向する状態に設定されて当該コンクリートバケット1を移動台車3B上に着床させるものである。
また、引き戻し手段としての上記スプリング10は、上記受け材4が上記コンクリートバケット1の重量を受けている状態において上記受け材4の位置を上記初期状態4Aの方向に引き戻すように作動するとともに、コンクリートバケット1がバンカー線2より離れた場合に、上記受け材4の位置を上記初期状態4Aに戻すよう機能する。
【0018】
尚、上記受け材4は、上記一端4a側に、上記コンクリートバケット1の底面1zに当接する支持部材4xを有するL字状のパネルから成る。この支持部材4xは、上記コンクリートバケット1をガイドする過程において、その先端4t側がコンクリートバケット1の底面1zに当接しながら、受け材4が上記壁部2aに対してほぼ平行に対向する状態になった時にはその内面4uがコンクリートバケット1の底面1zに当接し、コンクリートバケット1の上部1t側が壁部2a側に若干傾くような状態にコンクリートバケット1を移動台車3B上に着床させるものである。この支持部材4xは、一例としては、図2に示すように、中空部4rを有する枠材4sで構成されているが、平板で構成してもかまわないことは言うまでもない。
【0019】
また、上記ヒンジ手段5は、上記土台7上に設けられた軸受けブラケット5aに取り付けられた軸5bに、上記アーム6,6を回動自在に取り付けて成るものである。尚、受け材4を支えるアームは何本でもかまわない。要は、アームを介して回動支点から離れて受け材4を支持するようにすればよい。
【0020】
また、上記移動台車3上に設置された土台7と一体となった支柱8が立設されており、この支柱8の上部には、上記初期状態4Aの受け材4の他端4bと延長して、受け材4の傾斜面4fと延長する固定傾斜面9fを構成する固定傾斜板9が設けられている。
また、図4(b)に示すように、上記支柱8の上部に設けられた固定傾斜板9の下端側の端面9tは、垂直面となっており、上記受け材4の他端4b側の端面4tは、上記初期状態4Aにおいて上記固定傾斜板9の下端側の端面9tと当接するように面処理されている。よって、上記固定傾斜板9の下端側の端面9tである垂直面は、上記スプリング10により、上記受け材4の位置が上記初期状態4Aに戻されたときこの初期状態4Aの位置より上記壁部2a側とは反対側(歩廊12側)に移動しないように規制する規制手段として機能するものである。
【0021】
次に、本実施の形態1の作用を説明する。
コンクリートバケット1がケーブルクレーンでバンカー線2に運搬されてくると、センサの情報によりホストコンピュータ36が移動台車3Bを駆動して着床装置3をコンクリートバケット1が降下してくる位置まで移動する。次に、ケーブルクレーンで吊られた状態で、図4(a)に示すように、コンクリートバケット1の底側縁部1eを、初期状態4Aの受け材4の傾斜面4fに当接させながら下降させると、コンクリートバケット1の底部1zが支持部材4xの先端4tに当接しながら、アーム6,6の回動により、受け材4が矢印のように床部2b方向に回動する。その結果、図4(b)に示すように、コンクリートバケット1は移動台車3B上に着床される。この時、支持部材4xの厚さにより、コンクリートバケット1の上部1t側が壁部2a側に若干傾くような状態に着床される。
尚、生コンクリートが詰め込まれたコンクリートバケット1がバンカー線2より離れた場合には、スプリング10により、受け材4は、初期状態4Aに復元される。
また、形状や大きさの異なるコンクリートバケット1を使用する場合は、電動ジャッキ3Cを駆動してコンクリートバケット1の形状や大きさに合わせて着床作動手段3Aの位置を調整する。例えば、図2に示すように、大きいコンクリートバケット1Bや小さいコンクリートバケット1Aを着床させることができる。従って、着床装置3は、例えばダム建設現場などで使用する可能性のある最も大きなコンクリートバケットを着床できる規模の大きさで構成すれば、小さいコンクリートバケット1Aを使用するときに、電動ジャッキ3Cにより着床作動手段3Aの位置を調整することにより対応できる。
【0022】
本実施の形態1によれば、第1移動手段としての移動台車3Bを備えているので、バンカー線2における床部2bの全長に渡って着床作動手段3A(着床装置3)を設けない、設備コストを抑えることができる構成にて、バンカー線2の所定の位置に自由にコンクリートバケット1を着床させることが可能となる。
また、電動機3eを制御することで、移動台車3Bの移動,停止を制御でき、移動台車3Bを所定の位置に移動させるに際してきめ細かい位置制御が行える。また、受け材4が回動しながらコンクリートバケット1を着床させるので、図10の従来装置に比べて、コンクリートバケット1をスムーズに着床させることができる。
また、アーム6,6を有するので、コンクリートバケット1を着床するときにコンクリートバケット1を壁部2a方向に押し込むことができ、そのため、壁部2aと着床装置3との間の距離を大きく取れ、コンクリートバケット1の着床時における水平方向の移動代を十分に取れるので、コンクリートバケット1の横揺れに対応できる。よって、図11の従来装置のように、ケーブルクレーンの運転に支障を来すようなことがない装置が得られる。
さらに、ヒンジ手段5により回動するアーム6,6の作用により受け材4でコンクリートバケット1を自動的に着床させることができ、また、離床後は、スプリング10により自動的に初期状態4A,すなわち、次に運搬されてくるコンクリートバケット1を待機する状態に復元されるので、図12の装置に比べて、着床,離床の際に、動力源や複雑な制御も必要とならない簡単な構成の着床装置が得られる。よって、従来装置の課題をすべて解消できる装置が得られる。
また、受け材4の支持部材4xの厚さにより、コンクリートバケット1の上部1t側が壁部2a側に若干傾くような状態に着床されるので、トランスファーカー2yにより生コンクリートを入れやすい状態にコンクリートバケット1を着床させることができ、また、コンクリートバケット1の底部1zを支持部材4xの先端4tで支えながら着床動作を行えるので、コンクリートバケット1の姿勢が崩れることがなく、ケーブルクレーンによる下降運転操作も容易となる。
さらに、初期状態4Aの受け材4の傾斜面4fに延長する固定傾斜面9fを有する固定傾斜板9を備えているので、コンクリートバケット1の着床時における水平方向の移動代をさらに十分に取れるので、コンクリートバケットの横揺れにさらに十分に対応できる。よって、ケーブルクレーンの運転をより容易に行えるようになる。
また、固定傾斜板9(下端側の端面9tである垂直面)は規制手段としても機能するので、受け材4を確実に初期状態4Aに設定できる。
さらに、第2移動手段としての電動ジャッキ3Cを備えているので、形状や大きさの異なるコンクリートバケット1を使用する場合に、電動ジャッキ3Cを駆動してコンクリートバケット1の形状や大きさに合わせて着床作動手段3Aの位置を調整することができ、このような様々な形状や大きさのコンクリートバケット1に対応してこれら各種のコンクリートバケット1をバンカー線2の壁部2aにうまく近づけて着床させることができる着床装置となる。
【0023】
実施の形態2.
上記実施の形態1のように、移動台車3Bを電動機3eで直接駆動するのではなく、移動台車3Bをエンドレスウインチなどで牽引するようにしてもよい。
【0024】
実施の形態3.
また、第2の移動手段としては、図7に示すように、バンカー線2の全長に渡って延長する土台7の両端7e側に位置する付近の移動台車3Bの上面に、上記壁部2a側に対して直角方向に一直線に複数の位置決めボルト穴14を設け、上記土台7の両端7eには、このボルト穴14に螺着されて土台7の位置を固定するボルト15を設けるようにして第2移動手段を構成してもよい。15aはボルト15をガイドする雌ネジ部材である。
このようにしても、所望のボルト穴14の位置に着床作動手段3Aを固定することにより、コンクリートバケット1の形状や大きさに合わせて着床作動手段3Aの位置を調整することができる。よって、実施の形態1と同様に、様々な形状や大きさのコンクリートバケット1に対応してこれら各種のコンクリートバケット1をバンカー線2の壁部2aにうまく近づけて着床させることができる。
【0025】
実施の形態4.
上記各実施の形態においては、支持部材4xを有するL字状のパネルから成る受け材4を具備する着床装置を説明したが、図8に示すように、支持部材を持たない受け材4Zを用いて着床装置3を構成してもよい。この場合、支持部材を有する場合の効果は得られないが、所期の目的は十分に達成できる。すなわち、実施の形態1で得られる効果のうち、支持部材を有する場合の効果は得られないが、他の効果は得られる。
【0026】
尚、第1移動手段は、上述したように電動機3eやエンドレスウインチなどで移動する移動台車3Bに限られない。例えば、着床作動手段3Aの土台7の下にストッパ付きの車輪を設け、かつ、この車輪が滑走するレールをバンカー線2の床部2bに設けるようにして構成してもよい。また、この床部2bに設けるレールを2組以上設けることにより、壁部2aに対する着床作動手段3Aの位置を調整できるような第2移動手段を構成してもよい。すなわち、着床作動手段3Aを手動で移動させる態様の第1,第2移動手段であってもよい。以上の場合、コンクリートバケット1は、床部2b上に着床されることになる。
【0027】
【発明の効果】
以上のように、請求項1の発明によれば、コンクリートバケットを1つ受けることが可能で、このコンクリートバケットをコンクリートバケット着床場所の床部側に着床させることができる着床作動手段をコンクリートバケット着床場所における床部上において壁部に沿って移動させる第1移動手段を備えているので、コンクリートバケット着床場所における床部の全長に渡って着床作動手段(着床装置)を設けなくてもよく、設備コストを抑えることができる構成にて、コンクリートバケット着床場所の所定の位置に自由にコンクリートバケットを着床させることが可能となるコンクリートバケットの着床装置が得られる。
また、着床作動手段は、回動支点を介してコンクリート着床場所の壁部側に近づく方向で床部側に倒れ込むように回動する所定長さのアームの先端側に、コンクリートバケットの重量を受ける前の初期状態において、上記床部に近い一端側から上記壁部より離れるよう上方向に傾斜する傾斜面を形成する状態に設定され、かつ、コンクリートバケットの重量を受けた状態において、上記アームの回動により、コンクリートバケットをガイドしながら上記壁部に対向する状態に設定されて当該コンクリートバケットを上記壁部に近い床部側に着床させるための受け材を取り付けて成るものなので、水平方向の移動代を十分に取れて、コンクリートバケットの横揺れに対応でき、コンクリートバケットをスムーズに着床させることができ、着床時,離床時に動力源や複雑な制御も必要とならない簡単な構成のコンクリートバケットの着床装置となる。
請求項2の発明によれば、上記着床作動手段を搭載し、駆動源により上記壁部に沿って上記床部上を移動する移動台車で上記請求項1の第1移動手段を構成したので、電動機やエンドレスウインチなどを制御することにより、移動台車の移動,停止を制御でき、移動台車を所定の位置に移動させるに際してきめ細かい位置制御が行えるコンクリートバケットの着床装置が得られる。
請求項3に係る発明によれば、上記請求項1または請求項2において、上記着床作動手段を上記壁部に対して近接する方向又は離反する方向に移動させる第2移動手段を備えているので、電動ジャッキなどの第2移動手段を駆動してコンクリートバケットの形状や大きさに合わせて着床作動手段の位置を調整することができ、このような様々な形状や大きさのコンクリートバケットに対応してこれら各種のコンクリートバケットをコンクリート着床場所の壁部にうまく近づけて着床させることができるコンクリートバケットの着床装置が得られる。
請求項4に係る発明によれば、請求項1または請求項2または請求項3において、上記受け材は、上記一端側に、上記コンクリートバケットの底面に当接する支持部材を有するL字状のパネルより形成したので、上記効果に加えてさらに次のような効果が得られる。すなわち、生コンクリートを入れやすい状態にコンクリートバケットを着床させることができ、また、コンクリートバケットの姿勢が崩れることがなく、ケーブルクレーンによる下降運転操作も容易となるコンクリートバケットの着床装置が得られる。
請求項5に係る発明によれば、請求項1または請求項2または請求項3または請求項4において、上記初期状態の受け材の他端と延長して、受け材の傾斜面と延長する傾斜面を備えるので、上記効果に加えて、さらに、ケーブルクレーンの運転を容易にできるコンクリートバケットの着床装置が得られる。
請求項6に係る発明によれば、請求項1または請求項2または請求項3または請求項4または請求項5において、上記受け材の位置が上記初期状態に戻されたときこの初期状態の位置に位置されるよう規制する規制手段を備えているので、上記効果に加えて、さらに、受け材を確実に初期状態に設定できるコンクリートバケットの着床装置が得られる。
【図面の簡単な説明】
【図1】 本発明の実施の形態1による着床装置を示す側面図である。
【図2】 同実施の形態1による着床装置を示す平面図である。
【図3】 同実施の形態1による着床装置の概略を示す斜視図である。
【図4】 同実施の形態1による着床装置の動作説明図である。
【図5】 同実施の形態1による着床装置における第1,第2移動手段の詳細説明図である。
【図6】 同実施の形態1による着床装置の第2移動手段を説明するための部分説明図である。
【図7】 本発明の実施の形態3による着床装置における他の第2移動手段を説明するための側面図である。
【図8】 本発明の実施の形態4による着床装置を示す側面図である。
【図9】 ダム建設現場の概観を示す図である。
【図10】 従来の着床装置の一例を示す図である。
【図11】 従来の着床装置の一例を示す図である。
【図12】 従来の着床装置の一例を示す図である。
【符号の説明】
1 コンクリートバケット、2 バンカー線(コンクリートバケット着床場所)、2a 壁部、2b 床部、3 着床装置、3A 着床作動手段、3B 移動台車(第1移動手段)、4 受け材、4x 支持部材、5 ヒンジ手段(回動支点)、6 アーム、9 固定傾斜板、9f 固定傾斜面、10 スプリング(引き戻し手段)、3C 電動ジャッキ(第2移動手段)。[0001]
BACKGROUND OF THE INVENTION
The present invention is, for example, for landing a concrete bucket transported by a cable crane or the like at a predetermined position of a concrete bucket landing place (bunker line) provided near a ready-mixed concrete production supply site in dam construction or the like. The present invention relates to a flooring device for a concrete bucket.
[0002]
[Prior art]
At the dam construction site, the ready-mixed concrete produced in the batcher plant (prepared concrete production site) is packed into a concrete bucket by a transfer car (prepared concrete supply device), and this concrete bucket is transported to the concrete placement site by a cable crane. The dam construction work is done in the same way.
Fig. 9 shows an overview of the dam construction site.
In FIG. 9, 1 is a concrete bucket made of a can having a shape such as an ellipse, a circle, or a square, and 2 is concrete in which the
As described above, the
The
[0003]
In detail, the
[0004]
The operation of the cable crane and
The
[0005]
By the way, when the ready-mixed concrete is packed in the
[0006]
FIG. 10 shows a landing apparatus using a fixed swash plate. This is a structure in which a
[0007]
FIG. 11 shows a landing apparatus using a swash plate which can be rotated via a rotation fulcrum. This is such that the rear center side of the
[0008]
In FIG. 12, the
[0009]
[Problems to be solved by the invention]
However, the conventional concrete bucket landing devices as shown in FIGS. 10, 11 and 12 have the following problems.
In the apparatus of FIG. 10, when the
In the apparatus of FIG. 11, once the
Further, the apparatus of FIG. 12 has problems such as complicated control because the power source must be controlled to operate the jack when landing or leaving the floor.
Further, the
[0010]
Then, this invention aims at obtaining the flooring apparatus of the concrete bucket which can overcome all the above subjects.
In other words, the horizontal movement allowance can be taken sufficiently to cope with the rolling of the concrete bucket, the size of the concrete bucket can be freely accommodated, and the concrete bucket can be smoothly landed. By moving a set of equipment, the equipment cost will be reduced, and a grounding device with a simple configuration that does not require a power source or complicated control for landing and leaving operations, and that can suppress the equipment cost will be provided. It is what.
[0011]
[Means for Solving the Problems]
The concrete bucket landing device according to the first aspect of the present invention falls down to the floor side of the concrete bucket landing place in a direction approaching the wall side of the concrete bucket landing place via the rotation fulcrum. In the initial state before receiving the weight of the concrete bucket, the wall portion from the one end side close to the floor portion is large enough to receive one concrete bucket on the tip side of the arm having a predetermined length to rotate. In a state where an inclined surface that is inclined upward is formed so as to be further away, and in the state where the weight of the concrete bucket is received, the wall is opposed to the wall portion while guiding the concrete bucket by the rotation of the arm. Is set to attach a receiving material for landing the concrete bucket on the floor side close to the wall portion, and When the recording material receives the weight of the concrete bucket and operates to pull back the position of the receiving material in the direction of the initial state, and when the concrete bucket is away from the concrete bucket landing place, Landing actuating means comprising pull-back means for returning the position of the receiving material to the initial state, and first movement for moving the landing actuating means along the wall part on the floor part at the concrete bucket landing place Means.
According to a second aspect of the present invention, the first moving means includes a moving carriage that is mounted with the landing operation means and moves on the floor portion along the wall portion by a driving source.
The invention according to
According to a fourth aspect of the present invention, the receiving material comprises an L-shaped panel having a support member that contacts the bottom surface of the concrete bucket on the one end side.
The invention according to
The invention according to claim 6 is provided with a regulating means for regulating the position of the receiving member so as not to move to the side opposite to the wall portion from the position of the initial state when the position of the receiving material is returned to the initial state. did.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
In each figure, 3 is a concrete bucket landing apparatus according to the present invention.
This
The landing actuating means 3A is a hinge means that constitutes a pivot fulcrum provided on a
A
[0013]
The
In addition, the position control of the
[0014]
Also, since the
The second moving means is realized by, for example, an
[0015]
The driving power for the
[0016]
One end of the
[0017]
In the
Further, the
[0018]
In addition, the said receiving material 4 consists of an L-shaped panel which has the supporting
[0019]
The hinge means 5 is formed by rotatably attaching the arms 6 and 6 to a shaft 5b attached to a
[0020]
Further, a support column 8 integrated with the
As shown in FIG. 4B, an
[0021]
Next, the operation of the first embodiment will be described.
When the
When the
Moreover, when using the
[0022]
According to the first embodiment, since the moving
Further, by controlling the
Moreover, since the arm 6, 6 is provided, the
Furthermore, the
Further, since the upper 1t side of the
Furthermore, since the fixed inclined plate 9 having the fixed inclined surface 9f extending to the inclined surface 4f of the receiving member 4 in the
Further, since the fixed inclined plate 9 (vertical surface that is the
Furthermore, since the
[0023]
Instead of directly driving the
[0024]
Further, as the second moving means, as shown in FIG. 7, the
Even in this case, the position of the landing operation means 3A can be adjusted according to the shape and size of the
[0025]
Embodiment 4 FIG.
In each of the above-described embodiments, the landing apparatus including the receiving material 4 including the L-shaped panel having the
[0026]
The first moving means is not limited to the moving
[0027]
【The invention's effect】
As described above, according to the invention of
Further, the landing actuating means has a weight of the concrete bucket on the front end side of the arm of a predetermined length that rotates so as to fall down to the floor side in a direction approaching the wall side of the concrete landing place through the rotation fulcrum. In an initial state before receiving, in a state where an inclined surface that is inclined upward is formed so as to be separated from the wall portion from one end side close to the floor portion, and in a state where the weight of the concrete bucket is received, By turning the arm, it is set in a state facing the wall while guiding the concrete bucket, and a receiving material for attaching the concrete bucket to the floor side close to the wall is attached. A sufficient amount of horizontal movement allowance can be taken, the rolling of the concrete bucket can be handled, the concrete bucket can be smoothly landed, and when landing The implantation device of the concrete bucket of a power source or complicated control also simple not required structure during lifting.
According to the second aspect of the present invention, the first moving means according to the first aspect is configured by a moving carriage that is mounted with the landing operation means and moves on the floor portion along the wall portion by a drive source. By controlling the electric motor, the endless winch, etc., it is possible to control the movement and stop of the moving carriage, and to obtain a concrete bucket flooring device that can perform fine position control when moving the moving carriage to a predetermined position.
According to a third aspect of the present invention, in the first or second aspect of the invention, the second moving means for moving the landing operation means in a direction approaching or separating from the wall portion is provided. Therefore, the second moving means such as an electric jack can be driven to adjust the position of the landing operation means in accordance with the shape and size of the concrete bucket. Correspondingly, it is possible to obtain a concrete bucket landing device capable of placing these various concrete buckets close to the wall of the concrete landing place.
According to a fourth aspect of the present invention, in the first, second, or third aspect, the receiving member has an L-shaped panel having a support member that contacts the bottom surface of the concrete bucket on the one end side. In addition to the above effects, the following effects can be obtained. In other words, the concrete bucket can be placed in a state in which ready-mixed concrete can be easily put in, and the concrete bucket can be placed without causing the concrete bucket to be collapsed. .
According to a fifth aspect of the present invention, in the first, second, third, or fourth aspect, the slope extends from the other end of the receiving member in the initial state and extends from the inclined surface of the receiving member. Since the surface is provided, in addition to the above effect, a concrete bucket landing device that can facilitate the operation of the cable crane can be obtained.
According to the invention of claim 6, when the position of the receiving material is returned to the initial state in
[Brief description of the drawings]
FIG. 1 is a side view showing a landing apparatus according to
FIG. 2 is a plan view showing the landing apparatus according to the first embodiment.
FIG. 3 is a perspective view showing an outline of a landing apparatus according to the first embodiment.
FIG. 4 is an operation explanatory diagram of the landing apparatus according to the first embodiment.
5 is a detailed explanatory diagram of first and second moving means in the landing apparatus according to
FIG. 6 is a partial explanatory view for explaining a second moving means of the landing apparatus according to the first embodiment.
FIG. 7 is a side view for explaining another second moving means in the landing apparatus according to the third embodiment of the present invention.
FIG. 8 is a side view showing a landing apparatus according to Embodiment 4 of the present invention.
FIG. 9 is a view showing an overview of a dam construction site.
FIG. 10 is a diagram showing an example of a conventional landing apparatus.
FIG. 11 is a diagram illustrating an example of a conventional landing apparatus.
FIG. 12 is a diagram showing an example of a conventional landing apparatus.
[Explanation of symbols]
DESCRIPTION OF
Claims (6)
回動支点を介して上記壁部側に近づく方向で上記床部側に倒れ込むように回動する所定長さのアームの先端側に、上記コンクリートバケットを1つ受けることが可能な大きさで、上記コンクリートバケットの重量を受ける前の初期状態において、上記床部に近い一端側から上記壁部より離れるよう上方向に傾斜する傾斜面を形成する状態に設定され、かつ、上記コンクリートバケットの重量を受けた状態において、上記アームの回動により、上記コンクリートバケットをガイドしながら上記壁部に対向する状態に設定されて当該コンクリートバケットを上記壁部に近い床部側に着床させるための受け材を取り付けて成り、かつ、上記受け材が上記コンクリートバケットの重量を受けている状態において上記受け材の位置を上記初期状態の方向に引き戻すように作動するとともに、コンクリートバケットが上記コンクリートバケット着床場所より離れた場合に、上記受け材の位置を上記初期状態に戻す引き戻し手段を具備する着床作動手段と、
上記着床作動手段を上記コンクリートバケット着床場所における上記床部上において上記壁部に沿って移動させる第1移動手段とを備えて成ることを特徴とするコンクリートバケットの着床装置。To place a concrete bucket at a predetermined position in a concrete bucket landing place having a wall portion and a floor portion extending from the lower portion of the wall portion, and the ready-mixed concrete supply device being disposed on the upper side of the wall portion. Equipment,
With a size capable of receiving one of the concrete buckets on the tip side of the arm of a predetermined length that pivots so as to fall into the floor side in a direction approaching the wall side through a pivot point, In an initial state before receiving the weight of the concrete bucket, it is set to a state in which an inclined surface that is inclined upward from the one end side close to the floor portion is separated from the wall portion, and the weight of the concrete bucket is In the received state, a receiving material for setting the concrete bucket to be opposed to the wall portion while guiding the concrete bucket by the rotation of the arm and for landing the concrete bucket on the floor side close to the wall portion. And in the state where the receiving material receives the weight of the concrete bucket, the position of the receiving material is the direction of the initial state. Together they operate to pull back, when the concrete bucket is separated from the concrete bucket implantation site, and implantation actuating means comprise means pullback return the position of the receiving member in the initial state,
A concrete bucket landing device comprising: first moving means for moving the landing actuation means along the wall portion on the floor portion at the concrete bucket landing location.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP28027198A JP3953662B2 (en) | 1998-10-01 | 1998-10-01 | Concrete bucket flooring equipment |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP28027198A JP3953662B2 (en) | 1998-10-01 | 1998-10-01 | Concrete bucket flooring equipment |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2000110148A JP2000110148A (en) | 2000-04-18 |
| JP3953662B2 true JP3953662B2 (en) | 2007-08-08 |
Family
ID=17622675
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP28027198A Expired - Fee Related JP3953662B2 (en) | 1998-10-01 | 1998-10-01 | Concrete bucket flooring equipment |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3953662B2 (en) |
-
1998
- 1998-10-01 JP JP28027198A patent/JP3953662B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2000110148A (en) | 2000-04-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102849624B (en) | The method of operation crane and crane | |
| CN201411635Y (en) | Construction trolley of safety barrier template | |
| KR101201878B1 (en) | Lift for Transferring Heavy Structure | |
| CN217518209U (en) | Novel tower crane type vibrating equipment | |
| KR101872923B1 (en) | Drone type aerial work platform | |
| CN109264623B (en) | Operation method of intelligent Internet communication optical cable maintenance lifting device | |
| JP4796391B2 (en) | Wind power generator installation mechanism and installation method | |
| JP4104249B2 (en) | Steel tower mobile robot | |
| JP3953662B2 (en) | Concrete bucket flooring equipment | |
| CN113502848B (en) | Translation installation method for prefabricated plate under assembled station cover plate | |
| CN113845024B (en) | Hydraulic lifting portal frame for subway construction | |
| CN119176479B (en) | Hoisting structure of high and large formwork support | |
| CN115580092A (en) | Magnetic levitation long stator coil automatic laying device and method | |
| JP3737289B2 (en) | Concrete bucket flooring equipment | |
| CN217999008U (en) | Two-way hollow precast shear force wallboard erection equipment of concrete | |
| CN113548583B (en) | Main drive hoisting tool of escalator and operation method | |
| KR100500728B1 (en) | Automatic conveyor system for monorail | |
| JP6738779B2 (en) | Pile driver and method of changing the posture of the pile driver | |
| CN223793589U (en) | Auxiliary device for concrete pipe pile construction | |
| CN221565611U (en) | Stable lifting device for coal mine electromechanical transportation | |
| CN219823019U (en) | Coal leveling device | |
| CN224117342U (en) | A transport device for airline ticket vending machines | |
| CN117090242B (en) | A method for assembling a composite assembled underground station | |
| JPH11311027A (en) | Support device for erecting long member | |
| CN121740494B (en) | Crane wind-proof and anti-skid capability test detection platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050920 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070418 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070424 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070425 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100511 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110511 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110511 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120511 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120511 Year of fee payment: 5 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120511 Year of fee payment: 5 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120511 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130511 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130511 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140511 Year of fee payment: 7 |
|
| LAPS | Cancellation because of no payment of annual fees |